25 July 2018
Agenda
▪ Introductions
▪ Objectives of the day
▪ Problem statement
▪ Overview of the PRIDe in Gas Model
▪ Summary of approach
▪ Timelines
▪ Conclusions and next steps
Gemserv 2
Objectives for the day
▪ Share information on the PRIDe in Gas Model
▪ Discuss and Define the use of each PRIDe technique
▪ Perform analysis on each PRIDe technique▪ What we like
▪ What we don’t like (what can be changed)
▪ Gain agreement on the overall use of the PRIDe in Gas Model
▪ Gain agreement on timelines for implementation
▪ Gain PAC commitment/prioritisation for next steps
Gemserv 3
Problem statement
▪ Currently have limited tools to manage performance related risks in the market
▪ Current controls are not scalable to effectively resolve a wide range of risks▪ Significant risks
▪ Non significant risks
▪ Ability to escalate risks is not defined
Gemserv 4
PRIDe in Gas Model
Gemserv 5
PRIDe in Gas Model
▪ Complementary set of Preventive, Detective, Incentive and Remedial assurance techniques. Used flexibly to address Settlement risks
▪ The use of any techniques under this model is the decision and discretion of the PAC based on the information it receives through the PARR and the PAFA
▪ A risk that presents a significant impact to Settlement would necessitate the use of a stronger control
▪ Whereas a risk that presents a smaller impact to Settlement would necessitate the use of a weaker control
Gemserv 6
Prevent
Gemserv 8
▪ Used as a first course of action to consider when presented with a risk to Settlement
▪ Technique is always used for managing risks
▪ It contains the use of the PARR and production of performance reports on a monthly basis
Gemserv 9
Prevent
PAFA
Mar
ket
Pa
rtic
ipa
nts
(S
hip
pers
an
d T
ran
spo
rte
rs)
PAC
CD
SP Start CDSP extracts data
PAFA produces and analyses PARR
reports
Are there any outliers?
Can further analysis be done
with current data?
Yes
NoRequest additional data from the CDSP for further analysis
Report on industry performance along
with any PAFA recommendations
No
Data sent to PAFACDSP extracts data
for further investigation
PAFA analyses additional data
Yes
Report on additional areas for analysis along with
any PAFA recommendations
PAC provide comments and
decision on recommendations
PAC provide comments and
decision on recommendations
PAC agree on timescale of next
steps
PAFA to use another technique to
manage industry issue
PAFA to educate Market Participants
on where performance is below industry
standards
PAFA to continue to monitor reports for both Shipper and
industry performance
PAFA investigates further into
performance issue
Market Participants receive report
Publish report to PAC and Industry
Publish report to PAC and Industry
Market Participant and PAFA arrange
an education workshop
Incentivise Technique
Detect Technique
Remedy Technique
Prevent
Control strength Control
Low Continue to monitor PARR reports as standing monitoring
Continue to monitor PARR reports for a fixed timescale before escalation decision
Provide education to the industry
Provide engagement to acknowledge performance
Medium Consider if further analysis is required on an adhoc basis
Consider if further analysis is required on a frequent basis
Determine if current risks are being mitigated
Determine if escalation for other techniques is required
Gemserv 10
Detect
▪ Used to further investigate and audit areas of interest
▪ Drill down into data to find determine materiality of issues
▪ Determine root cause if not already known via data analysis or engagement with parties
▪ Monitoring of issue via ad-hoc developed anonymised reports
▪ Option for issues not captured in the PARR reports to be presented and discussed
Gemserv 11
Detect
Gemserv 12
Control strength Control
Low Use Prevent technique to continue monitoring for a fixed timescale before escalation decision
Use Prevent technique to continue monitoring standing monitoring
Medium Define and create adhoc reports as standing monitoring
Define requirements for CDSP data extract
Request data analysis from PAFA
Recommend further area of investigation
Determine if escalation for other techniques is required
Determine the conditions to appeal any escalation decision for incentive and remedy techniques
Determine if current risks are being mitigated
Determine if newly identified risks/issues are being mitigated
Gemserv 13
Detect
PAFA
Mar
ket
Part
icip
ants
(S
hip
pe
rs a
nd
Tr
ansp
ort
ers)
PAC
CD
SP
Start
CDSP extracts data
PAFA analyses data
PAC discuss current industry issues and
areas of interest
Define areas to audit and
investigate
PAC decide what areas of the industry to
investigate and what data is
required
PAFA recommend areas to investigate based on industry performance and
industry issues
PAFA produces report with
recommendation on next steps
PAC provide comments and
decision on recommendations
PAC informs the industry of
investigation
Market Participants informed of investigation
PreventiveTechnique
Remedy Technique
Incentivise Technique
Incentivise
▪ Used for persistent performance issues and encouraging positive behaviours
▪ PAC receives non anonymised report data with names of all parties contributing to issues captured in PARR reports
▪ PAC receives non anonymised report data with names of all parties contributing to persisting issues not captured in PARR reports
Gemserv 14
Incentivise
Gemserv 15
Control strength Control
Medium Determine the conditions for entering and exiting liquidated damages
Determine the conditions for peer comparison reporting
Determine the conditions to appeal any decision for liquidated damages
Determine the conditions to appeal any decision for peer comparison reporting
High Determine if the significance of poor performance necessitates the use of liquidated damages
Determine if the significance of poor performance necessitates the use of peer comparison tables
Determine if performance is improving
Determine if current risks are being mitigated
Determine if escalation for other techniques is required
Incentivise
▪ Can you incentivise via name and shame?
▪ Does the lability represent the risk incurred?▪ How would this be quantified?
▪ Who pays who?▪ How would cash flow be managed and redistributed?
▪ What happens if a Party doesn’t pay?▪ Escalation actions?
▪ What if the fine is less than the cost of the benefit?▪ Fit for purpose?
▪ Mechanism for model adjustment?
Gemserv 16
Gemserv 17
Incentivise
PAFA
Mar
ket
Part
icip
ants
(S
hip
pers
an
d Tr
ansp
ort
ers)
PA
CC
DSP Start
PAFA produces Anonymised and
UnAnonymised Peer comparison reports
Publish report to PAC and Industry respectively via
Huddle
Receive UnAnonymised
report for consideration
Receive Anonymised report
PAFA presents analyses of report
along with recommendations
for next steps
CDSP extracts data
Provide comments and decision on
PAFA recommendations
PAC agree on timescale of next
steps
Provide queries to the PAFA based on
findings
PAFA investigates and provides support and education
Market Participant and PAFA arrange
an education workshop
PAFA recommends uses liquidated
damages based on Market Participant
performance
Prevent Technique
PAC discuss and decide on using
liquidated damages for the agreed
period
PAC informs Market Participants on
liquidated damages to be received
Market Participant receives liquidated
damages
PAC decides if another technique needs to be used
Remedy Technique
Remedy
▪ Used as a last resort once other techniques have been exhausted
▪ Used to monitor party resolution plans based on PAC exit conditions
▪ PAFA to provide updates on resolution plan progress at agreed frequency to PAC
▪ PAC discussion on next steps based on lack of improvement
Gemserv 18
Remedy
Gemserv 19
Control strength Control
Medium Determine the conditions to appeal any decision for escalation to UNCC
Determine the conditions to appeal any decision for expulsion from UNC
High Define and create resolution plan to improve market participant performance
Request the PAFA to monitor resolution plan and provide updates
Determine if escalation to UNCC is required
Determine if recommendation for expulsion from UNC is required
Gemserv 20
Remedy
PAFA
Mar
ket
Part
icip
ants
(S
hip
pers
an
d Tr
ansp
ort
ers)
PAC
CD
SP
Incentivise Technique
PAFA informs the Market Participant
of PAC decision
Market Participant proposes a
resolution plan for PAC approval and sends to the PAFA
PAFA reviews resolution plan and provides comments
and provides comments
PAFA reviews resolution plan
PAFA presents resolution plan to
the PAC
PAC monitors the Market Participant via PAFA reporting
until resolution
PAFA provides monthly updates to
the PAC
Detect Technique
Prevent Technique
PAFA arranges industry workgroup to assess industry performance issue
PAFA actions PAC s decision
PAFA produces a report of workgroup
conclusions and recommendations
PAC decides on next steps
Appeals process
▪ A Market Participant can appeal the PAC’s decision to activate a PRIDe technique if they believe:
▪ The due process has not been followed
▪ The use of evidence and circumstances has either been over or under emphasised
▪ The evidence used has been misinterpreted
▪ Appeal can be via email to the PAFA or PAC describing the query within 10 Working Days of a decision being made
▪ The appeal will be considered by the PAC at their next available meeting
Gemserv 21
Summary approach
Planning
• Initial PRIDeworkshop
• PRIDe project plan agreed
Development
• Technique definition workshop
• Revision of PRIDemodel
• UNC impact assessment and implementation approach workshop
• Modification drafting workshop
Implementation
• Implementation date
• Trial run using industry data
Go live
• Go live
Gemserv 22
July Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun July
Timeline
Gemserv 23
July Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun July
Planning
Development
Implementation
Go Live
Initial workshop
Project plan agreed
Technique definition workshop
Revision of PRIDemodel
UNC impact assessment and implementation approach workshop
Modification drafting workshop
Modification raised
Implementation date
Trial run start
Trial run finish
Go Live
Indicative timeline
Timeline
Event Date
Initial PRIDe workshop 25 July 2018
Project plan agreed August/September 2018
PRIDe technique definition workshop w/c 17 September 2018
Revision of PRIDe model 9 October 2018
UNC impact assessment and implementation approach workshop w/c 15 October 2018
Modification drafting workshop w/c 22 October 2018z
Modification raised w/c 12 November 2018
Modification process w/c 12 November 2018 – 18 February 2019
Implementation date 4 March 2019
Trial run using industry data 4 March 2019 – 6 May 2019
Go live 6 May 2019
Gemserv 24
Indicative timeline
Conclusions and next steps
Gemserv 25