probabilistic activity time

21
Probabilistic Activity Times Probabilistic Time Estimates Carrine Kezia Aulia :: 102183022

Upload: carrine-aulia

Post on 17-Jun-2015

255 views

Category:

Leadership & Management


0 download

DESCRIPTION

-

TRANSCRIPT

Page 1: Probabilistic Activity Time

Probabilistic Activity TimesProbabilistic Time Estimates

Carrine Kezia Aulia :: 102183022

Page 2: Probabilistic Activity Time

• Single time estimates

• Didn’t allow for any variation

• AT treated as if they are known for certain

COMPARISON CPM AND PERTREVIEW

• Multiple time estimates

• Allow for any variation

• AT treated as probabilistic

PERT uses probabilistic activity times

CPM PERT

Page 3: Probabilistic Activity Time

Approach to estimating activity times

WHAT IS PROBABILISTIC ACTIVITY TIMES?What’s it all about?

• Completion time estimates can be estimated using the

Three Time Estimate Three Time Estimate approachapproach

• In this approach, three time estimates are required for each activity

Page 4: Probabilistic Activity Time

MOST LIKELY TIME (m)

THREE TIME ESTIMATES

OPTIMISTIC TIME (a)

PESSIMISTIC TIME (b)

123

most frequently occur if the activity were repeated many times

the shortest possible time to complete the activity if everything went right

the longest possible time to complete the activity if everything went wrong

Page 5: Probabilistic Activity Time

with THREE TIME estimates, the activity completion timecan be approximated by a BETA DISTRIBUTION

BETA DISTRIBUTION

BETA DISTRIBUTIONS CAN COME IN A VARIETY OF SHAPES :

Page 6: Probabilistic Activity Time

FORMULAMEAN AND VARIANCE

a + 4m + b

6

b - a

6

2

mean (expected time)

variance σ2

t

MOST LIKELY TIME (m)

OPTIMISTIC TIME (a)

PESSIMISTIC TIME (b)

Page 7: Probabilistic Activity Time

EXAMPLEA PROJECT NETWORK WITH PROBABILISTIC TIME ESTIMATE

Page 8: Probabilistic Activity Time

EXAMPLEACTIVITY TIME ESTIMATES

a + 4m + b

6

b - a

6

2

t σ2

Page 9: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

Page 10: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

0

8

8 8

5

13

0

6

6

3

0 3

3

6 9

4

3 7

2

3 5

7

9 16

4

9 13

4

13 17

9

16 25

2516

2521

2116

169

1612

1614

95

52

9660

91

EXPECTED TIME : 25CRITICAL PATH :2-5-8-11

Page 11: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

25WEEKS

6,89WEEKS

Page 12: Probabilistic Activity Time

EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK

ADD ALL THE σ2 OFF THE CRITICAL PATH

SD

what does this formula means?what does these numbers mean?

Page 13: Probabilistic Activity Time

EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK

25WEEKS

6,89WEEKS

2,62WEEKS

EXPECTED TIME

μ

σ2 σ

Page 14: Probabilistic Activity Time

EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK

25WEEKS

EXPECTED TIME

μ

30WEEKS

PROPOSED PROJECT TIME

X WHAT IS THE PROBABILITY THAT

THE SYSTEM WILL BE READY BY THAT

TIME?

WHAT IS THE PROBABILITY THAT

THE SYSTEM WILL BE READY BY THAT

TIME?

Page 15: Probabilistic Activity Time

EXAMPLEPROBABILISTIC ANALYSIS OF THE PROJECT NETWORK

Z =X – μ

σ

30WEEKS

25WEEKS

2.62

-= 1.911.91

Page 16: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

z = 1.91

Page 17: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

Page 18: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

0.9719probability of completing

the project in 30 days

0.9719probability of completing

the project in 30 days

Page 19: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

www.measuringusability.com

Page 20: Probabilistic Activity Time

EXAMPLEACTIVITY EARLIEST AND LATEST TIMES AND SLACK

z = 1.91

97.19 %

Page 21: Probabilistic Activity Time