problems in overall differential protection of generator and gt
TRANSCRIPT
-
7/27/2019 Problems in Overall Differential Protection of Generator and GT
1/4
PROJECT : CPCL, MANALI, 1 X 20 MW GTG, UNIT 3
PROBLEM : PROBLEMS IN OVERALL DIFFERENTIAL PROTECTIONOF GENERATOR AND GENERATOR TRANSFORMER
While commissioning Generator Transformer ( GT ) of gas turbine,it was observed that the overall differential protection of the
Generator was repeatedly acting inspite of all healthy connections.
The electrical system of CPCL is provided with a Generator of 28.5MVA/ 11 kV/ 1478 A rating and a Generator Transformer of 33 MVA/
11 kV/ 7.07 kV DYn11 group. The Current Transformers (3 nos.) on
the Generator neutral side is rated for 2000/ 1 A and currenttransformer on the 7 kV side of the transformer is 3000/1 (3 no.s).
The relay supplied for overall differential protection is DUOBIAS of
EASUN REYROLLE.
Normally in the older relays, all the CT connections are given as per
book theory (star on delta side of transformer and delta on star side
of transformer) and interposing CTs are used to count for the ratiomismatches with the transformer current ratio. The generator does not
contribute to any change in this configuration. In the later designs ofnumerical relays, the same function of interposing CTs and connections
of the interposing CTs can be specified by simple software variables.This has eased the system of protection by eliminating the use of
interposing CTs, standard CT connections irrespective of star or delta
side of Generator Transformer and use of the same relay for multipleprotections as in the case at CPCL. The same DUOBIAS relay was used
for transformer star side Restricted Earth Fault Protection also. At
CPCL both the Generator side CTs and the transformer bushing CTs
-
7/27/2019 Problems in Overall Differential Protection of Generator and GT
2/4
were connected in star and connected to the relay in a 4 wire
configuration. As per the old theory, the CTs on the star side of the
transformer should be delta and because of the use of the numericalrelay star connection was given, the vector group configuration of the
internal interposing CTs as yd1 ( equivalent of DYn11 when seen fromthe transformer star side) is to be given. The delta side of thetransformer however was having only a star CT configuration and hence
a yy0 interposing CT configuration in the relay was sufficient. Suitable
multipliers were also incorporated (1.08 for HT side CTs and 1.10 for
LT side CTs)
Once the relay configurations were set, wiring configurations were
checked and found to be alright as per the schematic andinterconnection diagram. Again, it was checked for differential stability
and the system stability could not be established. System was
analysed again by raising the current slightly under short circuitconnection. It was observed at a particular point of primary current,
the winding current on the HT side read 0.07 A and the winding
Current on LT side also read 0.07 A. An operating current of 0.12 A
was observed through the relay, whereas the current of 0.14 A wasexpected or 0 A in case of polarity problem. As the measured value of
0.12 A is close to 0.14 A, the polarity was reversed. So CT polarities
at the transformer end were reversed as that of Generator CTspolarity. It was observed that the HT side winding, LT side winding,
relay operating currents all read 0.07 A. It was inferred from this
that it can occur only if the phase is shifted by 120 deg. 120 deg.phase shift gives a resultant of 0.07 A and if polarity is reversed,
the angle becomes 60 degrees and it gives a resultant of 0.12 A.Hence phase CTs of R,Y, B on any one side were suspected to have got
shifted by 120 degrees.
-
7/27/2019 Problems in Overall Differential Protection of Generator and GT
3/4
To confirm the same, the vector group configuration of the interposing
CT was changed to yd4 corresponding to 120 degrees and it was found
that relay current became zero. The Generator side Neutral CTs werechecked and it was found to be in order by physical verification and
continuity. The transformer was inspected for any markings of phasedetails. There was no printed Phase details near the CT termination andalso the CTs were totally immersed in oil and hence oil is to be
drained to verify the CTs physically. Assembly drawing from BHEL-
Jhansi was not available.
The vector group of the transformer is confirmed, as the machine hasbeen synchronized many a times already. Core balance test connection
was made with the transformer windings on the LT side shorted and a
small voltage of 6 V was given with a single phase 230 V variac. Based
on the % impedance already known, this current should be around 6 A.Also it was observed that the same current was only flowing in the
single phase winding of the transformer where the voltage was given.
The other two windings acts like a potential divider and hence shouldshow a drop of 3 V across each winding. So the winding with 6 V will
draw a current of 6 A on the same winding whereas the other two
windings were drawing just 3 A, correspondingly the secondary sideinline winding also drew higher current than the other two. The vector
grouping for a Dyn11 configuration is as shown below:
Applied Voltage = 6 V across RY
The other two voltages VYB = 3 V, VBR= 3 V Hence currents in thesetwo windings should also be lesser than the winding RY, so corresponding
secondary current would also be less than the one corresponding to RY.
Now for vector group Dyn11
Primary RY corresponds to secondary nrPrimary YB corresponds to secondary ny
Primary BR corresponds to secondary nb
-
7/27/2019 Problems in Overall Differential Protection of Generator and GT
4/4
Hence with higher voltage across RY should give a higher current across
RY and hence nr under short circuit condition. Practically it was
observed that the current in one phase of the secondary of thesecondary side CT showed 5 mA whereas the other two showed 2.5 mA,
hence it was concluded that this CT corresponds to r phase of thesecondary of the transformer. Similarly the other two phases were also
found out by giving a small voltage in the other two phases one by one
and the CTs for each phase were identified. It was observed that theCTs did not match with the markings.
The CTs were correctly marked, the machine was again rolled and
checked. The values indicated change in polarity of one of the CTs. Sopolarities were then interchanged one by one and checked for stability.
b phase CT polarity was found reversed and corrected. Operating
currents in both the primary side and secondary windings were found to
be 0.07 A and the relay currents were found to be zero and hencestability of the system was proved.
,