process calculations
DESCRIPTION
Process calculations for Sewage Pumping StationTRANSCRIPT
![Page 1: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/1.jpg)
DESIGN PARAMETERS:
Average Flow (Qav) = 1.00 MLD = 41.7 m3/hr = 0.012 m
3/sec
Peak Flow (Qpk) = 3.00 MLD = 125 m3/hr = 0.035 m
3/sec
Peak Flow Factor = (Qpk / Qav) = 3.00
INLET CHAMBER :
Unit to be designed for Peak Flow = 3.00 MLD = 125.0 m3/hr = 0.035 m3/sec
and to be checked for Average Flow = 1.00 MLD = 41.7 m3/hr = 0.012 m
3/sec
Capacity of Stilling Chamber = 30 sec on peak flow
Volume required = 0.035 x 30
= 1.04 m3
Providing SWD = 0.60 m
Length Provided = 1.60 m
Width Provided = 1.20 m
Providing Freeboard = 0.50 m
Volume Provided = 1.15 m3
OK
Provide Stilling Chamber of 1200 wide x 1600 Long x 600 SWD
COARSE SCREEN CHANNELS :
No. of units to be provided = 2 Nos. (1 Mechanical W + 1 Mechanical S)
Mechanical Screen Channel
Unit to be designed for Pk. Flow = 3.00 MLD = 125.0 m3/hr = 0.035 m3/sec
and to be checked for Avg. Flow = 1.00 MLD = 41.6667 m3/hr = 0.012 m
3/sec
PROCESS DESIGN CALCULATIONS FOR 1.0 MLD CAPACITY SEWAGE PUMPING STATION (SPS)
![Page 2: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/2.jpg)
AT PALI, RAJASTHAN
PROCESS DESIGN CALCULATIONS FOR 1.0 MLD CAPACITY SEWAGE PUMPING STATION (SPS)
As there will be one stream,
Design Flow at Peak Condn = 0.035 m3/sec = 0.035 m
3/sec
1
Design Flow at Avg. Condn = 0.012 m3/sec = 0.012 m
3/sec
1
Velocity thru Screen Channel for :
Q pk = 1.0 m/s
Q avg = 0.5 m/s
Area of screen channel reqd. for Qpk = 0.035 m3/sec = 0.035 m2
1 m/s
Area of screen channel reqd. for Qavg = 0.012 m3/sec = 0.02315 m2
0.5 m/s
Considering 50 mm opening and 10 mm thickness of bars,
Gross area required = 0.035 x 60 = 0.042 m2
50
Assuming width of channel as = 600 mm
Width of side frame on each side = 0 mm
Total width of channel = 600 mm
Liquid depth in screen = 69 mm Say 100 mm
Height of dead plate = 500 mm
Total depth of screen = 600 mm Say 600 mm
Angle of inclination with horizontol = 45 Deg
Provide length of Screen Chamber as = 6.00 m
Provide free board as = 300 mm on upstream side
![Page 3: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/3.jpg)
AT PALI, RAJASTHAN
PROCESS DESIGN CALCULATIONS FOR 1.0 MLD CAPACITY SEWAGE PUMPING STATION (SPS)
Provide Screen Channel of 600 wide x 600 SWD x 6000 Long
Check for Headloss in screen
Headloss thru screen under clean conditions
HL = 0.0729(V12 ‐ V22)
Net area available thru screen = 0.6 x 0.1 x 50
x 60
= 0.050 m2
Velocity thru screen at peak flow (V1) = 0.035 m/s
0.050
= 0.694 m/s
Approach velocity at peak flow (V2) = 0.035
0.6 x 0.6
= 0.096 m/s
Headloss (HL) = 0.034 m = 34.48 mm
Headloss thru screen under half clogged
conditions
HL = 0.0729(V12 ‐ V22)
Velocity thru screen at peak flow (V1) = 1.389 m/s
Approach velocity at peak flow (V2) = 0.035
0.60 x 0.6
= 0.096 m/s
Headloss (HL) = 0.140 m = 140 mm
COLLECTING TANK
![Page 4: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/4.jpg)
AT PALI, RAJASTHAN
PROCESS DESIGN CALCULATIONS FOR 1.0 MLD CAPACITY SEWAGE PUMPING STATION (SPS)
Unit to be designed for Peak Flow = 3.00 MLD = 125.0 m3/hr = 0.035 m
3/sec
Capacity of Collecting Tank = 20 minutes on peak flow
Volume required = 0.035 x 20 x 60
= 41.67 m3
Providing SWD = 2.00 m
Diameter required = 5.15 m
Diameter Provided = 5.20 m
Volume Provided = 42.47 m3
OK
Provide Collecting Tank of size 5200 dia x 2000 SWD
Pumping Machinery in Collecting Tank
Type of pumps = Non clog sewage submersible
Total Flow = 125 m3/hr = 0.035 m3/sec
Dia of pumping main (as per tender) = 250 mm
Length of pipe from SPS to manhole = 500 m
Frictional Losses = 2.0 m
Static Head = 9.0 m
Other Miscellaneous Losses @ 20% = 2.2 m
Terminal head required = 1.0 m
Total Head required = 14.2 m Say 16 m
Number of pumps, for discharge 0.86 MLD = 2 Discharge per pump = 9.95 LPS
![Page 5: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/5.jpg)
AT PALI, RAJASTHAN
PROCESS DESIGN CALCULATIONS FOR 1.0 MLD CAPACITY SEWAGE PUMPING STATION (SPS)
HP required by Pump = 9.95 x 16 / 0.7 / 75
= 3.03 HP Say 3.3 HP
Number of pumps, for discharge 0.43 MLD = 2 Discharge per pump = 4.98 LPS
HP required by Pump = 4.98 x / 0.7 / 75
= 1.52 HP Say 1.7 HP
![Page 6: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/6.jpg)
DESIGN PARAMETERS:
Average Flow (Qav) = 15.00 MLD = 625.0 m3/hr = 0.174 m3/sec
Peak Flow Factor = (Qpk / Qav) = 2.25
Peak Flow (Qpk) = 33.75 MLD = 1406.25 m3/hr = 0.391 m3/sec
QUALITY OF INLET WASTE :
Biological Oxygen Demand (BOD5) = 300 mg/l
Chemical Oxygen Demand (COD) = 650 mg/l
Total Suspended Solids (TSS) = 600 mg/l
Fecal Coli form = 1 x 104 MPN / 100 ml
Total Kjeldahl Nitrogen ( TKN as N) = 55 mg/l
Total Phosphorous (TP) = 6 mg/l
OUTLET STANDARDS REQD. :
Biological Oxygen Demand (BOD5) = < 10 mg/l
Chemical Oxygen Demand (COD) = < 100 mg/l
Total Suspended Solids (TSS) = < 10 mg/l
Fecal Coliform = < 230 MPN / 100 ml
Total Nitrogen (as N) = < 10 mg/l
Total Phosphorous (TP) = < 1 mg/l
INLET CHAMBER :
Unit to be designed for Peak Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
and to be checked for Average Flow = 15.00 MLD = 625.0 m3/hr = 0.174 m3/sec
Capacity of Stilling Chamber = 30 sec on peak flow
Volume required = 0.391 x 30
= 11.72 m3
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
![Page 7: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/7.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Providing SWD = 1.00 m
Length Provided = 4.00 m
Width Provided = 3.00 m
Providing Freeboard = 0.50 m
Volume Provided = 12.00 m3
OK
Provide Stilling Chamber of 3000 wide x 4000 Long x 1000 SWD
COARSE SCREEN CHANNELS :
No. of units to be provided = 2 Nos. (1 mechanical W + 1 Mechnaical S)
Mechnical Screen Channel
Unit to be designed for Pk. Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
and to be checked for Avg. Flow = 15.00 MLD = 625 m3/hr = 0.174 m3/sec
As there will be one stream,
Design Flow at Peak Condn = 0.391 m3/sec = 0.391 m3/sec
1
Design Flow at Avg. Condn = 0.174 m3/sec = 0.174 m3/sec
1
Velocity thru Screen Channel for :
Q pk = 1.0 m/s
Q avg = 0.5 m/s
Area of screen channel reqd. for Qpk = 0.391 m3/sec = 0.391 m2
1 m/s
Area of screen channel reqd. for Qavg = 0.174 m3/sec = 0.34722 m2
0.5 m/s
Considering 50 mm opening and 10 mm thickness of bars,
Gross area required = 0.391 x 60 = 0.469 m2
50
Assuming width of channel as = 1000 mm
![Page 8: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/8.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Width of side frame on each side = 0 mm
Total width of channel = 1000 mm
Liquid depth in screen = 469 mm Say 470 mm
Height of dead plate = 500 mm
Total depth of screen = 970 mm Say 1000 mm
Angle of inclination with horizontol = 45 Deg
Provide length of Screen Chamber as = 7.00 m
Provide free board as = 500 mm on upstream side
Provide Screen Channel of 1000 wide x 1000 SWD x 7000 Long
Check for Headloss in screen
Headloss thru screen under clean conditions
HL = 0.0729(V12 ‐ V22)
Net area available thru screen = 1 x 0.47 x 50
x 60
= 0.392 m2
Velocity thru screen at peak flow (V1) = 0.391 m/s
0.392
= 0.997 m/s
Approach velocity at peak flow (V2) = 0.391
1 x 1
= 0.391 m/s
Headloss (HL) = 0.061 m = 61.39 mm
Headloss thru screen under half clogged
conditions
HL = 0.0729(V12 ‐ V22)
![Page 9: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/9.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Velocity thru screen at peak flow (V1) = 1.995 m/s
Approach velocity at peak flow (V2) = 0.391
1.00 x 1
= 0.391 m/s
Headloss (HL) = 0.279 m = 279 mm
COLLECTING TANK
Unit to be designed for Peak Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
Capacity of Collecting Tank = 20 minutes on peak flow
Volume required = 0.391 x 20 x 60
= 468.75 m3
Providing SWD = 2.50 m
Diameter required = 15.45 m
Diameter Provided = 16.00 m
Volume Provided = 502.65 m3
OK
Provide Collecting Tank of size 16000 dia x 2500 SWD
Pumping Machinery in Collecting Tank
Type of pumps = Non clog sewage submersible
Total Flow = 1406.25 m3/hr
Number of working pumps = 2
Number of standby pumps = 2
Discharge per pump = 703.125 m3/hr
= 11719 LPM = 195.3 LPS
Static Head = 11.5 m
![Page 10: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/10.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Misc Losses @ 20% = 2.3 m
Required Head of Pump = 13.8 m
Take Head of pump = 15.0 m
Number of pumps, for discharge 15 MLD = 2 Discharge per pump = 173.61 LPS
BHP required by Pump = 173.61 x 15 / 0.7 / 75
= 49.6 BHP Say 54.6 BHP
Number of pumps, for discharge 7.5 MLD = 2 Discharge per pump = 86.81 LPS
BHP required by Pump = 86.81 x 15 / 0.7 / 75
= 24.8 BHP Say 27.3 BHP
STILLING CHAMBER :
Unit to be designed for Peak Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
and to be checked for Average Flow = 15.00 MLD = 625.0 m3/hr = 0.174 m3/sec
Capacity of Stilling Chamber = 30 sec on peak flow
Volume required = 0.391 x 30
= 11.72 m3
Providing SWD = 2.00 m
Length Provided = 3.00 m
Width Provided = 2.00 m
Providing Freeboard = 0.50 m
Volume Provided = 12.00 m3
OK
Provide Stilling Chamber of 2000 wide x 3000 Long x 2000 SWD
FINE SCREEN CHANNELS :
No. of units to be provided = 2 Nos. (1 Mechanical W + 1 Mechanical S)
Mechanical Screen Channel
Unit to be designed for Pk. Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
![Page 11: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/11.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
and to be checked for Avg. Flow = 15.00 MLD = 625 m3/hr = 0.174 m3/sec
As there will be one stream,
Design Flow at Peak Condn = 0.391 m3/sec = 0.391 m3/sec
1
Design Flow at Avg. Condn = 0.174 m3/sec = 0.174 m3/sec
1
Velocity thru Screen Channel for :
Q pk = 1.0 m/s
Q avg = 0.3 m/s
Area of screen channel reqd. for Qpk = 0.391 m3/sec = 0.391 m2
1 m/s
Area of screen channel reqd. for Qavg = 0.174 m3/sec = 0.5787 m2
0.3 m/s
Considering 6 mm opening and 3 mm thickness of bars,
Gross area required = 0.579 x 9 = 0.868 m2
6
Assuming width of channel as = 1100 mm
Width of side frame on each side = 150 mm
Total width of channel = 1400 mm
Liquid depth in screen = 789 mm = 800 mm
Height of dead plate = 50 mm
Total depth of screen = 850 mm = 850 mm
Angle of inclination with horizontol = 40 Deg
Provide length of Screen Chamber as = 7.00 m
Provide free board as = 300 mm on upstream side
Provide Screen Channel of 1400 wide x 850 SWD x 7000 Long
Check for Headloss in screen
![Page 12: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/12.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Headloss thru screen under clean conditions
HL = 0.0729(V12 ‐ V22)
Net area available thru screen = 1.1 x 0.8 x 6
x 9
= 0.587 m2
Velocity thru screen at peak flow (V1) = 0.391 m/s
0.587
= 0.666 m/s
Approach velocity at peak flow (V2) = 0.391
1.4 x 0.85
= 0.328 m/s
Headloss (HL) = 0.024 m = 24.46 mm
Headloss thru screen under half clogged
conditions
HL = 0.0729(V12 ‐ V22)
Velocity thru screen at peak flow (V1) = 1.332 m/s
Approach velocity at peak flow (V2) = 0.391
1.40 x 0.85
= 0.328 m/s
Headloss (HL) = 0.121 m = 121 mm
GRIT REMOVAL UNIT :
No. of units to be provided = 2 Nos. (1 Mechanical W + 1 Mechanical S)
Mechanical Grit Chamber
Unit to be designed for Pk. Flow = 33.75 MLD = 1406.3 m3/hr = 0.391 m3/sec
Surface Overflow Rate = 959 m3/day/m2
![Page 13: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/13.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Plan Area required = 35.19 m2
Length required = 6 m Say 6 m
Width provided = 6 m
Area Provided = 36 m2 OK
HRT at peak Flow = 1 min
Volume Required = 23.44 m3
SWD Required = 0.65111 m
Say 0.7 m
Velocity thru Grit Channel = 0.09 m/sec
Provide Mechanical Grit Chambers of 6000 wide x 6000 Long x 700 SWD
SBR REACTORS :
Calculations for SBR Reactors shall be provided by the technology provider.
CHLORINE CONTACT TANK :
Volume of sewage treated = 15.00 MLD = 625.0 m3/hr
Design retention time in CCT = 30 min
Volume of Chlorination tank = 625 x 30
60
= 312.50 m3
Providing SWD = 3.0 m
Dia Provided = 11.6 m
Volume provided = 317.05 m3 OK
Providing Freeboard = 0.5 m
Provide Chlorine Contact Tank of size 11600 dia x 3000 SWD
CHLORINATOR:
![Page 14: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/14.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Treated sewage flow rate = 625 m3/hr
Design chlorine dosage (for chlorinator
capacity only)= 5 ppm
Number of chlorinators = 1 nos. Working + 1 nos standby
Chlorine dosage rate = 625 x 5
1 x 1000
= 3.13 Kg/hr
Chlorinator capacity offered = 3.5 Kg/hr
Number of Standby chlorinators = 1 nos.
Total number of chlorinators = 2 nos.
Consumption of chlorine gas = 75 kg/day = 2250 kg/month
No. of Chlorine Tonners provided = 3 Nos
COMMON TREATED EFFLUENT CHAMBER :
Treated sewage flow rate = 625.0 m3/hr
Design retention time in effuent chamber = 30 min
Volume of treated effuent chamber = 625 x 30 = 312.50 m3
60
Providing SWD = 3.0 m
Dia Provided = 11.6 m
Volume provided = 317.05 m3 OK
Providing Freeboard = 0.5 m
Provide Effuent Treated Chamber of size 11600 dia x 3000 SWD
Pumping Machinery in Effuent Chamber
Type of pumps = Centrifugal Pump
Decant Flow = 1250.0 m3/hr
![Page 15: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/15.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Number of working pumps = 2
Number of standby pumps = 1
Discharge per pump = 625 m3/hr
= 10417 LPM = 173.6 LPS
Static Head = 27.2 m
Misc Losses @ 20% = 5.44
Required Head of Pump = 32.64
Provide Head of pump = 33.0 m
HP required for the pump = 173.6 x 33 x 0.746
75 x 0.7
= 87.7 BHP Say 96.5 HP
SLUDGE CALCULATIONS :
Total Sludge as per CTECH calculations = 4763 kg/day
Sludge Consistency = 0.80%
Density of Sludge = 1050 kg/m3
Volume of Sludge = 4763 x 100 / 0.8 / 1050
= 567.0 m3/day
SLUDGE SUMP (SLUDGE HOLDING TANK) :
Hydraulic Retention Time of Tank = 6 hours
Quantity of sludge produced in a day = 567.0 m3/day
Volume required = 567.0 x 6 / 24.0
= 141.80 m3
Providing SWD = 2.50 m
Provide Dia = 8.50 m
![Page 16: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/16.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Volume Provided = 141.86 m3
OK
Providing Freeboard = 0.5 m
Provide Sludge Holding Tank of Size 8500 Dia x 2500 SWD
SLUDGE SUMP AIR BLOWER:
Volume of Sludge Sump = 141.80 m3
Design air agitation = 1.20 Nm3/hr/m3
No. of working blowers = 1 No
No. of standby blowers = 1 No
Required capacity of blowers = 141.8 x 1.2 / 1.0
170.2 Nm3/hr
Capacity of Blowers offered = 180 Nm3/hr
HP of air blower required = 5.2 HP
CENTRIFUGE & CENTRIFUGE FEED PUMPS:
Sludge produced per day = 567.0 m3/day
Max Number of hours of operation = 12 hours per day
Sludge flowrate = 47.25 m3/hrs
No. of working centrifuge considered = 1 no.
No. of standby centrifuge considered = 1 no.
Capacity of centrifuge required = 47.25
1
= 47.25 m3/hrs
Capacity of centrifuge offered = 50 m3/hrs
HP of centrifuge drive = 15 HP
![Page 17: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/17.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Actual Working hours of centrifuge = 11.34 hrs/day
< 12 hrs/day OK
Capacity of centrifuge feed pumps offered = 50 m3/hrs = 13.89 LPS
No. of working pumps = 1 no.
No. of standby pumps = 1 no.
Static Head = 20 m
HP required for the pump = 13.89 x 20 x 0.746
75 x 0.4
= 6.9 BHP Say 7.6 HP
POLYELECTROLYTE DOSING SYSTEM:
Quantity of sludge to be dewatered in a day = 4763 Kg/day
Considering Polymer dose = 2 Kg/Ton of dry sludge
Quantity of poly required = 4763 x 2
1000
Quantity of poly required = 9.526 Kg/day
Considering strength of poly solution = 0.10%
Volume of polyelectrolyte solution = 9.526
0.10% x 1000
Volume of polyelectrolyte solution = 9.526 m3
Considering nos. of tanks = 2 nos
Volume of each dosing tank = 4.76 m3
Considering SWD of tank = 1.5 m
Length / Width provided = 1.8 m
Providing Freeboard = 0.3 m
Provide Polymer dosing tanks of = 1800 wide x 1800 Long x 1500 SWD
![Page 18: Process Calculations](https://reader035.vdocuments.net/reader035/viewer/2022080222/563db949550346aa9a9bd9ac/html5/thumbnails/18.jpg)
PROCESS DESIGN CALCULATIONS FOR 15.0 MLD CAPACITY SEWAGE TREATMENT PLANT (STP)
BASED ON SEQUENTIAL BATCH REACTOR (SBR) TECHNOLOGY AT PALI, RAJASTHAN
Working hours of centrifuge = 11.34 hrs
Reqd capacity of Poly dosing pumps = 9.526 x 1000
11.34 x 1
= 840.01 Lph
Capacity of poly dosing pumps offered = 850 LPH
No. of working pumps for each tank = 1 no.