procurement arrangements applicable to ppp contracts financed under world bank projects summary of...
DESCRIPTION
Procurement arrangements applicable to PPP contracts financed under World Bank projects Summary of guidance note. OPCPR Mar. 2010. Information Note - PPP. Information Note - Contents. Implementation of a PPP project. PPP involves a series of contracts. Guidance Notes - Objectives. - PowerPoint PPT PresentationTRANSCRIPT
1
Procurement arrangements applicable
toPPP contracts
financed under World Bank projects
Summary of guidance noteOPCPR Mar. 2010
2
Information Note - PPP
Provide background information PPP
Aspects that influence procurement and corresponding contracts involved
Discuss best practices
3
Information Note - Contents
Concept and Use of PPPs
• Management & Lease Contracts
• Concessions• Greenfield projects• Divestitures
PPP vs. Construction Contracts
• Distribution of risks• Duration• Source of Financing• Market risk• Termination
Roles and responsibilities
• Government• Private Partners• Financial Institutions
(Lenders)• Multilateral
Agencies
Procurement concepts and examples of globally used procurement
methods
4
Implementation of a PPP project
Entrepreneur
• Selected by the government• Becomes responsible for project implementation
SPV
• Local Project company (concessionaire)• Secures financing• Selects and hire a construction contractor, usually under a Engineering Procurement and Construction (EPC) turn-key contract• Finalizes the contract with the operator (and maintenance) sub-contractor• Secures the supply for inputs for operation of the facility
5
PPP involves a series of contractsShareholders Agreement
Project Implementation Agreement
Concession Contract
Loan Agreements
Insurance agreements
Construction Contract
Operation and Maintenance Contract
Supply of Inputs Contract
Sales Contract
6
Guidance Notes - Objectives
Provide guidance to task teams on PPP procurement policy
• Role of WBG & Procurement• Preparing & supervising PPP projects• Clarify application of Procurement GL
• Provisions• Acceptable practices
7
How is WBG associated with PPPs• IFC and IBRD provide
advisory services to clients
• IFC also participates by lending directly to the private sector investors
• IBRD and IDA finance Output–Based Aid (OBA) subsidies, investments that are sovereign-guaranteed and consultants hired as transaction advisors
• MIGA provides guarantees to government agencies
EquityAssets
(Equipment/ Land)
VGF/ Subsidies
Loans to Financial
Intermediary
Role of WBG in PPPs
Advisory Services
Investment lending
Non-sovereign
guaranteed lending
Sovereign guaranteed
lending
Through hired
consultantsDirect
Guarantees
GuaranteesIFC WB
8
PPP project preparation
•Multiple stakeholders•Risk management•Contractual arrangements•Not necessarily the same as conventional procurement contracts
PPP structures are complicated
•Early dialogue with borrowers•Information about Bank policies & procedures•Building borrower capacities•Performance indicators
Upstream involvement
•Early involvement benefits the team•Helps consider various procurement options•Discussions in isolation are less productive
Procurement in support role
Relevant provisions in GL
9
BOO/BOT/BOOT, Concessions and Similar Private Sector Arrangements• GL 3.13
Existing Incumbent Concessionaire• OM dt.
November 7, 2005
Guarantees• GL 1.5 and 3.16
(OP14.25)Divestitures• GL 3.13 (?)
Financial Intermediary Loans
Bank Procurement
GL
10
Procurement Approach to
PPPs
Applying Section I
Bidding Documents
•Bank SBDs not available•Borrower documents should contain minimum components specified
Bidding Process
•ICB is preferred•LIB when limited qualified bidders•NCB only exceptional cases
Advertisement & Promotion
•Recommended to have a pre-bid conference to disseminate information to potential bidders•Innovative means like road shows, data room•First version of bid documents for comments
Bidder prequalification•Ensures quality bidders•Indicates market perception of risk•Based on quantifiable and objective criteria•Due diligence to verify past performance of bidders•GL do not permit limiting number of bidders during pre-qualification
11
Applying Section I (contd.)
Bid submission and Opening
•Allow sufficient time for bid preparation•One, two or three stage•Clarifications may be required for evaluation of technical proposals
Bid Evaluation
•As per the content and criteria clearly specified in the Bid Documents
Negotiation of Final Contract
•Contract awarded to Most Economically Advantageous Offer•Can be preceded by discussions of final details of contract terms, financing plan
Complaints and Appeals
•Clear and effective mechanism needs to be defined•Frivolous complaints can be discouraged but should not prevent bidders from submitting their feedback
12
Thinking points
13
Timing of Bank involvement
Discussions with the borrower
Role & composition of the task team
Procurement in a support role
Our capacity
14
Resources
OPCPR
• Finalize and disseminate the Information and Guidance Notes• We will need support from Sectors
Global Expert Team (GET)
• Working together
15
Thank You!
16
Backup slides
Management & Lease contracts• Ownership of the assets continues with the public
sector• Bank may be requested to finance a Management
contract or the expansions and/or rehabilitation of the facilities
• Under Bank GL similar to procurement of services and/or works
• Should follow the Consultants Guidelines for Management contract and Section II of Bank procurement guidelines for expansion or rehabilitation
Concessions
• Ownership of the assets is mixed for a period and is transferred to the public sector at the end of the contract, and investments are required and were part of the award of the concession
• Bank may be requested to finance (or co-finance) e.g a BOT type contract, as part of the award of the concession (Bank GL para 3.13)
Greenfield Projects
• Ownership of the new assets rests with the private sector and is transferred to the public sector at the end of the contract
• Selection of the private partner is part of the award of the Greenfield project
• Bank may be requested to finance (or co-finance) a BOT type contract, as part of the award of the concession(Bank GL para 3.13)
Divestitures• Private entity buys an equity stake in a state-owned asset or enterprise
through an asset sale• Bank may be requested to finance government investments or new
installations and expansions under responsibility of the private concessionaire
• Bank GL para 3.13 – applicable if investments (either by the government or by the concessionaire) are part of the procurement process for divestiture
• If investments are made some time after divestiture took place and an incumbent concessionaire is already in place, there are two possibilities:– Large investments on new facilities (like a ‘Greenfield’ project) - procurement
of services and/or works– Expansion of existing network or system made by the incumbent
concessionaire (not a ‘Greenfield’ project) – para 3.13 of GL
Concessions
Concessionaire or Entrepreneur can procure goods, works and services required by the facility using its own procurement practices
• subject to eligibility conditions defined under para 1.8 GL• Concessionaire or Entrepreneur selected based on ICB acceptable to the Bank (para 3.13a)
ICB procedures followed by the Borrower to select the Concessionaire or Entrepreneur
• do not need to be carried out in accordance with Section II of the Procurement Guidelines • basic principles established in Section I of the Guidelines are observed• Competitive bidding procedures with clear rules and provisions for all relevant information to bidders
GuaranteesOP14.25 (Guarantees)
• Compliance with paragraphs 1.5 and 3.16 of the Procurement Guidelines
Such arrangements are not subject to OP 11.00 (Procurement)
• When the project does not finance new investments
Key features:
• Due regard to economy and efficiency• Bank to be satisfied that procedures used to fulfill the borrower’s obligations to cause the project to be carried out diligently and efficiently and that the goods and works are procured with satisfactory quality,
delivery time and price
Should review borrower systems procurement, organization & control
Existing Incumbent Concessionaire
Concessionaire (privately or publicly owned) already exists
• Government may seeks Bank financing for expansion of existing systems (not Greenfield projects)
OM dt. November 7, 2005
• Small amounts involved in downstream procurement, makes use of Bank’s ICB procedures
Guidance
• Eligibility of incumbent concessionaire defined by Para 1.8 (c) of the Guidelines• Up-front assessment of the procurement capacity and procurement procedures• Bank may accept if procedures result in fair competition to bidders, economy (lowest cost), efficiency (satisfactory quality), transparency.• Post review by Bank
Divestitures
Investments (either by the government or by the Concessionaire) are part of the procurement process for divesture
• Para 3.13
Investments made after the divesture took place and incumbent Concessionaire is already in place
• Large investments on new facilities (like a ‘Greenfield’ project) – are similar to conventional procurements of services and/or works under Bank Guidelines, and should follow Section II of Bank Procurement Guidelines; or
• Expansion of existing network or system made by the incumbent Concessionaire – para 3.13
Background
Oct 2007: Heads of Procurement of the Multilateral Development Banks created a Working Group, co-chaired by WB & IDB
Feb 2008: PPP monitoring group formed with staff from Procurement, Infrastructure, GPOBA and PPIAF
Dec 2008: Internal survey on issues related to Procurement & where Bank can help
25