PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development Partners)

Procurement of INFRASTRUCTURE

PROJECTS

(CALAYAN PORT DEVELOPMENT PROJECT)

Government of the Republic of the Philippines

Fourth Edition December 2010

Page 2: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

2

TABLE OF CONTENTS

SECTION I. INVITATION TO BID ........................................................................................3

SECTION II. INSTRUCTIONS TO BIDDERS .......................................................................6

SECTION III. BID DATA SHEET ......................................................................................33

SECTION IV. GENERAL CONDITIONS OF CONTRACT ...............................................38

SECTION V. SPECIAL CONDITIONS OF CONTRACT ...................................................71

SECTION VI. SPECIFICATIONS ........................................................................................74

SECTION VII. DRAWINGS ..............................................................................................147

SECTION VIII. BILL OF QUANTITIES ..........................................................................148

SECTION IX. BIDDING FORMS ......................................................................................150

Page 3: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

3

Section I. Invitation to Bid

Page 4: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

4

INVITATION TO BID FOR CALAYAN PORT DEVELOPMENT PROJECT

The Department of Transportation and Communications (DOTC), through its Bids and Awards Committee (BAC), invites contractors registered with and classified by the Philippine Contractors Accreditation Board (PCAB) to join in the procurement of the herein project:

Name of Project Brief Description Location Source of Fund ABC/Duration PCAB Registration Minimum Equipment Requirement (OWNED/LEASED)

: : : : : : :

Calayan Port Development Project

Construction of Rock Causeway and R.C. Pier Brgy. Magsidel, Calayan, Cagayan CY 2013 Php 54,120,905.82 / 240 Calendar Days Medium A for Port, Harbor or Offshore Engineering

1 – Payloader (80 HP.) (1.50m3)

1 – Dumptruck (8 m3)

1 – Crawler Crane (20tons)

2 – One Bagger Concrete Mixer

2 – Concrete Vibrator

1 – Water Tank Truck (1,000 Gal.)

1 – Road Grader (125 HP.)

1 – Vibratory Compactor

(10 T. Min.)

1 – Truck Mounted Feeder Crane

1 – Barge w/ Tugboat

1 – Diesel Hammer

(K40, wt. = 4tons)

1 – Drop Hammer

2 – Welding Machine

1 – Oxyacetylene

1 – 40 Kva Generator Set

1 - Service Vehicle

(Pick-up at least 2008 Model)

The schedule of procurement activities are shown below: Issuance of Bid Tender Documents 12 September 2014 – 07 October 2014 Pre-Bidding Conference 23 September 2014, 1:30 am, at Unit 167, 16th Floor,

The Columbia Tower, Ortigas Ave., Mandaluyong City

Submission and Receipt of Bids The deadline for submission and receipt of bids is 07 October 2014, until 1:30 pm, only at Unit 153, 15th Floor, The Columbia Tower, Ortigas Ave., Mandaluyong City. Bids may be submitted before 07 October 2014, deadline at Unit 153, 15th Floor, The Columbia Tower,

Republic of the Philippines DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS

Page 5: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development
Page 6: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

6

Section II. Instructions to Bidders

Page 7: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

7

TABLE OF CONTENTS

A. GENERAL ........................................................................................................ 9

1. Scope of Bid ..............................................................................................................9

2. Source of Funds ........................................................................................................9

3. Corrupt, Fraudulent, Collusive, and Coercive Practices ...........................................9

4. Conflict of Interest ..................................................................................................11

5. Eligible Bidders .......................................................................................................12

6. Bidder’s Responsibilities ........................................................................................13

7. Origin of GOODS and Services ..............................................................................15

8. Subcontracts ............................................................................................................15

B. CONTENTS OF BIDDING DOCUMENTS .......................................................... 15

9. Pre-Bid Conference .................................................................................................15

10. Clarification and Amendment of Bidding Documents............................................16

C. PREPARATION OF BIDS ................................................................................. 16

11. Language of Bids ....................................................................................................16

12. Documents Comprising the Bid: Eligibility and Technical Components ...............16

13. Documents Comprising the Bid: Financial Component .........................................19

14. Alternative Bids ......................................................................................................19

15. Bid Prices ................................................................................................................20

16. Bid Currencies .........................................................................................................21

17. Bid Validity ...........................................................................................................211

18. Bid Security .............................................................................................................21

19. Format and Signing of Bids ....................................................................................23

20. Sealing and Marking of Bids...................................................................................24

D. SUBMISSION AND OPENING OF BIDS............................................................ 24

21. Deadline for Submission of Bids ............................................................................24

22. Late Bids .................................................................................................................25

23. Modification and Withdrawal of Bids ....................................................................25

24. Opening and Preliminary Examination of Bids ......................................................25

E. EVALUATION AND COMPARISON OF BIDS ................................................... 27

25. Process to be Confidential .......................................................................................27

26. Clarification of Bids ................................................................................................27

27. Detailed Evaluation and Comparison of Bids .........................................................27

28. Post Qualification ....................................................................................................28

Page 8: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

8

29. Reservation Clause ..................................................................................................29

F. AWARD OF CONTRACT ................................................................................. 30

30. Contract Award .......................................................................................................30

31. Signing of the Contract ...........................................................................................31

32. Performance Security ..............................................................................................31

33. Notice to Proceed ....................................................................................................32

Page 9: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

9

A. General

1. Scope of Bid

1.1. The Procuring Entity as defined in the Bid Data Sheet (BDS), invites bids for the construction of Works, as described in Section VI. Specifications. The name and identification number of the Contract is provided in the BDS.

1.2. The successful bidder will be expected to complete the Works by the intended completion date specified in SCC Clause 1.16.

2. Source of Funds

The Procuring Entity has a budget or has applied for or received funds from the Funding Source named in the BDS, and in the amount indicated in the BDS. It intends to apply part of the funds received for the Project, as defined in the BDS, to cover eligible payments under the Contract for the Works.

3. Corrupt, Fraudulent, Collusive, and Coercive Practices

3.1. Unless otherwise specified in the BDS, the Procuring Entity, as well as bidders and contractors, shall observe the highest standard of ethics during the procurement and execution of the contract. In pursuance of this policy, the Funding Source:

(a) defines, for purposes of this provision, the terms set forth below as follows:

(i) "corrupt practice" means behavior on the part of officials in the public or private sectors by which they improperly and unlawfully enrich themselves, others, or induce others to do so, by misusing the position in which they are placed, and includes the offering, giving, receiving, or soliciting of anything of value to influence the action of any such official in the procurement process or in contract execution; entering, on behalf of the Procuring Entity, into any contract or transaction manifestly and grossly disadvantageous to the same, whether or not the public officer profited or will profit thereby, and similar acts as provided in Republic Act 3019;

(ii) "fraudulent practice" means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to the detriment of the Procuring Entity, and includes collusive practices among Bidders (prior to or after Bid submission) designed to establish bid prices at artificial, non-competitive levels and to deprive the Procuring Entity of the benefits of free and open competition;

(iii) “collusive practices” means a scheme or arrangement between two or more bidders, with or without the knowledge of the

Page 10: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

10

Procuring Entity, designed to establish bid prices at artificial, non-competitive levels; and

(iv) “coercive practices” means harming or threatening to harm, directly or indirectly, persons, or their property to influence their participation in a procurement process, or affect the execution of a contract;

(v) “obstructive practice” is

(aa) deliberately destroying, falsifying, altering or concealing of evidence material to an administrative proceedings or investigation or making false statements to investigators in order to materially impede an administrative proceedings or investigation of the Procuring Entity or any foreign government/foreign or international financing institution into allegations of a corrupt, fraudulent, coercive or collusive practice; and/or threatening, harassing or intimidating any party to prevent it from disclosing its knowledge of matters relevant to the administrative proceedings or investigation or from pursuing such proceedings or investigation; or

(bb) acts intended to materially impede the exercise of the inspection and audit rights of the Procuring Entity or any foreign government/foreign or international financing institution herein.

(b) will reject a proposal for award if it determines that the bidder recommended for award has engaged in corrupt or fraudulent practices in competing for the Contract; and

(c) will declare a firm ineligible, either indefinitely or for a stated period of time, to be awarded Contract funded by the Funding Source if it at any time determines that the firm has engaged in corrupt or fraudulent practices in competing or, or in executing, a Contract funded by the Funding Source.

3.2. Further, the Procuring Entity will seek to impose the maximum civil, administrative, and/or criminal penalties available under the applicable laws on individuals and organizations deemed to be involved in any of the practices mentioned in Instructions to Bidders (ITB) Clause 3.1(a).

3.3. Furthermore, the Funding Source and the Procuring Entity reserve the right to inspect and audit records and accounts of a contractor in the bidding for and performance of a contract themselves or through independent auditors as reflected in the GCC Clause 34.

Page 11: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

11

4. Conflict of Interest

4.1. All bidders found to have conflicting interests shall be disqualified to participate in the procurement at hand, without prejudice to the imposition of appropriate administrative, civil, and criminal sanctions. A Bidder may be considered to have conflicting interests with another Bidder in any of the events described in paragraphs (a) through (c) and a general conflict of interest in any of the circumstances set out in paragraphs (d) through (g) below:

(a) A Bidder has controlling shareholders in common with another Bidder;

(b) A Bidder receives or has received any direct or indirect subsidy from any other Bidder;

(c) A Bidder has the same legal representative as that of another Bidder for purposes of this Bid;

(d) A Bidder has a relationship, directly or through third parties, that puts them in a position to have access to information about or influence on the bid of another Bidder or influence the decisions of the Procuring Entity regarding this bidding process. This will include a firm or an organization who lends, or temporarily seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project if the personnel would be involved in any capacity on the same project;

(e) A Bidder submits more than one bid in this bidding process. However, this does not limit the participation of subcontractors in more than one bid;

(f) A Bidder who participated as a consultant in the preparation of the design or technical specifications of the goods and related services that are the subject of the bid; or

(g) A Bidder who lends, or temporary seconds, its personnel to firms or organizations which are engaged in consulting services for the preparation related to procurement for or implementation of the project, if the personnel would be involved in any capacity on the same project.

4.2. In accordance with Section 47 of the IRR of RA 9184, all Bidding Documents shall be accompanied by a sworn affidavit of the Bidder that it is not related to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), members of the Technical Working Group (TWG), members of the BAC Secretariat, the head of the Project Management Office (PMO) or the end-user unit, and the project consultants, by consanguinity or affinity up to the third civil degree. On the part of the bidder, this Clause shall apply to the following persons:

(a) If the Bidder is an individual or a sole proprietorship, to the Bidder himself;

Page 12: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

12

(b) If the Bidder is a partnership, to all its officers and members;

(c) If the Bidder is a corporation, to all its officers, directors, and controlling stockholders; and

(d) If the Bidder is a joint venture (JV), the provisions of items (a), (b), or (c) of this Clause shall correspondingly apply to each of the members of the said JV, as may be appropriate.

Relationship of the nature described above or failure to comply with this Clause will result in the automatic disqualification of a Bidder.

5. Eligible Bidders

5.1. Unless otherwise indicated in the BDS, the following persons shall be eligible to participate in this Bidding:

(a) Duly licensed Filipino citizens/sole proprietorships;

(b) Partnerships duly organized under the laws of the Philippines and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines;

(c) Corporations duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the outstanding capital stock belongs to citizens of the Philippines;

(d) Cooperatives duly organized under the laws of the Philippines, and of which at least seventy five percent (75%) of the interest belongs to citizens of the Philippines; and

(e) Persons/entities forming themselves into a JV, i.e., a group of two (2) or more persons/entities that intend to be jointly and severally responsible or liable for a particular contract: Provided, however, that, in accordance with Letter of Instructions No. 630, Filipino ownership or interest of the joint venture concerned shall be at least seventy five percent (75%): Provided, further, that joint ventures in which Filipino ownership or interest is less than seventy five percent (75%) may be eligible where the structures to be built require the application of techniques and/or technologies which are not adequately possessed by a person/entity meeting the seventy five percent (75%) Filipino ownership requirement: Provided, finally, that in the latter case, Filipino ownership or interest shall not be less than twenty five percent (25%). For this purpose Filipino ownership or interest shall be based on the contributions of each of the members of the joint venture as specified in their JVA.

5.2. The Procuring Entity may also invite foreign bidders when provided for under any Treaty or International or Executive Agreement as specified in the BDS.

5.3. Government Corporate Entities may be eligible to participate only if they can establish that they (a) are legally and financially autonomous, (b) operate

Page 13: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

13

under commercial law, and (c) are not dependent agencies of the GOP or the Procuring Entity.

5.4. (a) Unless otherwise provided in the BDS, the Bidder must have completed, within ten (10) years from the submission of bids, a single contract that is similar to this Project, equivalent to at least fifty percent (50%) of the ABC adjusted to current prices using the National Statistics Office consumer price index.

(b) For Foreign-funded Procurement, the Procuring Entity and the foreign government/foreign or international financing institution may agree on another track record requirement, as specified in the BDS.

For this purpose, contracts similar to the Project shall be those described in the BDS, and completed within the period stated in the Invitation to Bid and ITB Clause 12.1(a)(iii).

5.5. The Bidder must submit a computation of its Net Financial Contracting Capacity (NFCC), which must be at least equal to the ABC to the bid, calculated as follows:

NFCC = [(Current assets minus current liabilities) (K)] minus the value of all outstanding or uncompleted portions of the projects under ongoing contracts, including awarded contracts yet to be started coinciding with the contract for this Project.

Where:

K = 10 for a contract duration of one year or less, 15 for a contract duration of more than one year up to two years, and 20 for a contract duration of more than two years.

The values of the bidder’s current assets and current liabilities shall be based on the data submitted to the BIR, through its Electronic Filing and Payment System (EFPS).

6. Bidder’s Responsibilities

6.1. The Bidder or its duly authorized representative shall submit a sworn statement in the form prescribed in Section IX. Bidding Forms as required in ITB Clause 12.1(b)(iii).

6.2. The Bidder is responsible for the following:

(a) Having taken steps to carefully examine all of the Bidding Documents;

(b) Having acknowledged all conditions, local or otherwise, affecting the implementation of the contract;

(c) Having made an estimate of the facilities available and needed for the contract to be bid, if any;

Page 14: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

14

(d) Having complied with its responsibility to inquire or secure Supplemental/Bid Bulletin/s as provided under ITB Clause 10.3.

(e) Ensuring that it is not “blacklisted” or barred from bidding by the GOP or any of its agencies, offices, corporations, or LGUs, including foreign government/foreign or international financing institution whose blacklisting rules have been recognized by the GPPB;

(f) Ensuring that each of the documents submitted in satisfaction of the bidding requirements is an authentic copy of the original, complete, and all statements and information provided therein are true and correct;

(g) Authorizing the Head of the Procuring Entity or its duly authorized representative/s to verify all the documents submitted;

(h) Ensuring that the signatory is the duly authorized representative of the Bidder, and granted full power and authority to do, execute and perform any and all acts necessary and/or to represent the Bidder in the bidding, with the duly notarized Secretary’s Certificate attesting to such fact, if the Bidder is a corporation, partnership, cooperative, or joint venture;

(i) Complying with the disclosure provision under Section 47 of the Act in relation to other provisions of Republic Act 3019; and

(j) Complying with existing labor laws and standards, if applicable.

Failure to observe any of the above responsibilities shall be at the risk of the Bidder concerned.

6.3. The Bidder, by the act of submitting its bid, shall be deemed to have inspected the site, determined the general characteristics of the contract works and the conditions for this Project and examine all instructions, forms, terms, and project requirements in the Bidding Documents.

6.4. It shall be the sole responsibility of the prospective bidder to determine and to satisfy itself by such means as it considers necessary or desirable as to all matters pertaining to this Project, including: (a) the location and the nature of the contract, project, or work; (b) climatic conditions; (c) transportation facilities; (c) nature and condition of the terrain, geological conditions at the site communication facilities, requirements, location and availability of construction aggregates and other materials, labor, water, electric power and access roads; and (d) other factors that may affect the cost, duration and execution or implementation of the contract, project, or work.

6.5. The Procuring Entity shall not assume any responsibility regarding erroneous interpretations or conclusions by the prospective or eligible bidder out of the data furnished by the procuring entity.

Page 15: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

15

6.6. Before submitting their bids, the Bidders are deemed to have become familiar with all existing laws, decrees, ordinances, acts and regulations of the Philippines which may affect the contract in any way.

6.7. The Bidder shall bear all costs associated with the preparation and submission of his bid, and the Procuring Entity will in no case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding process.

6.8. Bidders should note that the Procuring Entity will only accept bids only from those that have paid the nonrefundable fee for the Bidding Documents at the office indicated in the Invitation to Bid.

7. Origin of GOODS and Services

There is no restriction on the origin of Goods, or Contracting of Works or Services other than those prohibited by a decision of the United Nations Security Council taken under Chapter VII of the Charter of the United Nations.

8. Subcontracts

8.1. Unless otherwise specified in the BDS, the Bidder may subcontract portions of the Works to an extent as may be approved by the Procuring Entity and stated in the BDS. However, subcontracting of any portion shall not relieve the Bidder from any liability or obligation that may arise from the contract for this Project.

8.2. Subcontractors must submit the documentary requirements under ITB Clause 12 and comply with the eligibility criteria specified in the BDS. In the event that any subcontractor is found by the Procuring Entity to be ineligible, the subcontracting of such portion of the Works shall be disallowed.

8.3. The Bidder may identify the subcontractor to whom a portion of the Works will be subcontracted at any stage of the bidding process or during contract implementation. If the Bidder opts to disclose the name of the subcontractor during bid submission, the Bidder shall include the required documents as part of the technical component of its bid.

B. Contents of Bidding Documents

9. Pre-Bid Conference

9.1. (a) If so specified in the BDS, a pre-bid conference shall be held at the venue and on the date indicated therein, to clarify and address the Bidders’ questions on the technical and financial components of this Project.

(b) The pre-bid conference shall be held at least twelve (12) calendar days before the deadline for the submission of and receipt of bids. If the Procuring Entity determines that, by reason of the method, nature, or complexity of the contract to be bid, or when international participation will be more advantageous to the GOP, a longer period for the preparation of bids is necessary, the pre-bid conference shall be held at least thirty (30) calendar days before the deadline for the submission and receipt of bids, as specified in

Page 16: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

16

the BDS.

9.2. Bidders are encouraged to attend the pre-bid conference to ensure that they fully understand the Procuring Entity’s requirements. Non-attendance of the Bidder will in no way prejudice its bid; however, the Bidder is expected to know the changes and/or amendments to the Bidding Documents as recorded in the minutes of the pre-bid conference and the Supplemental/Bid Bulletin.

9.3. Any statement made at the pre-bid conference shall not modify the terms of the bidding documents unless such statement is specifically identified in writing as an amendment thereto and issued as a Supplemental/Bid Bulletin.

10. Clarification and Amendment of Bidding Documents

10.1. Bidders who have purchased the Bidding Documents may request for clarification(s) on any part of the Bidding Documents or for an interpretation. Such a request must be in writing and submitted to the Procuring Entity at the address indicated in the BDS at least ten (10) calendar days before the deadline set for the submission and receipt of Bids.

10.2. Supplemental/Bid Bulletins may be issued upon the Procuring Entity’s initiative for purposes of clarifying or modifying any provision of the Bidding Documents not later than seven (7) calendar days before the deadline for the submission and receipt of Bids. Any modification to the Bidding Documents shall be identified as an amendment.

10.3. Any Supplemental/Bid Bulletin issued by the BAC shall also be posted on the Philippine Government Electronic Procurement System (PhilGEPS) and the website of the Procuring Entity concerned, if available. Unless, otherwise provided in the BDS, it shall be the responsibility of all Bidders who secure the Bidding Documents to inquire and secure Supplemental/Bid Bulletins that may be issued by the BAC. However, bidders who have submitted bids before the issuance of the Supplemental/Bid Bulletin must be informed and allowed to modify or withdraw their bids in accordance with ITB Clause 23.

C. Preparation of Bids

11. Language of Bids

The Bid, as well as all correspondence and documents relating to the Bid exchanged by the Bidder and the Procuring Entity, shall be written in English. Supporting documents and printed literature furnished by the Bidder may be in another language provided they are accompanied by an accurate translation in English certified by the appropriate embassy or consulate in the Philippines, in which case the English translation shall govern, for purposes of interpretation of the Bid.

12. Documents Comprising the Bid: Eligibility and Technical Components

12.1. Unless otherwise indicated in the BDS, the first envelope shall contain the following eligibility and technical documents:

Page 17: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

17

(a) Eligibility Documents –

Class "A" Documents:

(i) Registration certificate from the Securities and Exchange Commission (SEC), Department of Trade and Industry (DTI) for sole proprietorship, or Cooperative Development Authority (CDA) for cooperatives, or any proof of such registration as stated in the BDS;

(ii) Mayor’s permit issued by the city or municipality where the principal place of business of the prospective bidder is located;

(iii) Statement of all its ongoing and completed government and private contracts within ten (10) years from the submission of bids, including contracts awarded but not yet started, if any. The statement shall include, for each contract, the following:

(iii.1) name of the contract;

(iii.2) date of the contract;

(iii.3) contract duration;

(iii.4) owner’s name and address;

(iii.5) nature of work;

(iii.6) contractor’s role (whether sole contractor, subcontractor, or partner in a JV) and percentage of participation;

(iii.7) total contract value at award;

(iii.8) date of completion or estimated completion time;

(iii.9) total contract value at completion, if applicable;

(iii.10) percentages of planned and actual accomplishments, if applicable;

(iii.11) value of outstanding works, if applicable;

(iii.12) the statement shall be supported by the notices of award and/or notices to proceed issued by the owners; and

(iii.13) the statement shall be supported by the Constructors Performance Evaluation System (CPES) rating sheets, and/or certificates of completion and owner’s acceptance, if applicable;

Page 18: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

18

(iv) Unless otherwise provided in the BDS, valid Philippine Contractors Accreditation Board (PCAB) license and registration for the type and cost of the contract for this Project;

(v) Audited financial statements, showing, among others, the prospective total and current assets and liabilities, stamped “received” by the BIR or its duly accredited and authorized institutions, for the preceding calendar year which should not be earlier than two (2) years from the date of bid submission;

(vi) NFCC computation in accordance with ITB Clause 5.5; and

(vii) Tax clearance per Executive Order 398, Series of 2005, as finally reviewed and approved by the BIR.

Class "B" Document:

(viii) If applicable, valid Joint Venture Agreement (JVA) or, in lieu thereof, duly notarized statements from all the potential joint venture partners stating that they will enter into and abide by the provisions of the JVA in the instance that the bid is successful shall be included in the bid.

(b) Technical Documents –

(i) Bid security as prescribed in ITB Clause 18. If the Bidder opts to submit the bid security in the form of:

(i.1) a bank draft/guarantee or an irrevocable letter of credit issued by a foreign bank, it shall be accompanied by a confirmation from a Universal or Commercial Bank; or

(i.2) a surety bond accompanied by a certification coming from an authorized Insurance Commission that a surety or insurance company is authorized to issue such instrument;

(ii) Project Requirements, which shall include the following:

(ii.1) Organizational chart for the contract to be bid;

(ii.2) List of contractor’s personnel (viz, project Manager, Project Engineers, Materials Engineers, and Foremen), to be assigned to the contract to be bid, with their complete qualification and experience data; and

(ii.3) List of contractor’s equipment units, which are owned, leased, and/or under purchase agreements, supported by certification of availability of equipment from the equipment lessor/vendor for the duration of the project; and

Page 19: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

19

(iii) Sworn statement in accordance with Section 25.2(b)(iv) of the IRR of RA 9184 and using the form prescribed in Section IX. Bidding Forms.

13. Documents Comprising the Bid: Financial Component

13.1. Unless otherwise stated in the BDS, the financial component of the bid shall contain the following:

(a) Financial Bid Form in accordance with the form prescribed in Section IX. Bidding Forms and

(b) Any other document related to the financial component of the bid as stated in the BDS.

13.2. (a) Unless indicated in the BDS, all Bids that exceed the ABC shall not be accepted.

(b) Unless otherwise indicated in the BDS, for foreign-funded procurement, a ceiling may be applied to bid prices provided the following conditions are met:

(i) Bidding Documents are obtainable free of charge on a freely accessible website. If payment of Bidding Documents is required by the procuring entity, payment could be made upon the submission of bids.

(ii) The procuring entity has procedures in place to ensure that the ABC is based on recent estimates made by the engineer or the responsible unit of the procuring entity and that the estimates are based on adequate detailed engineering (in the case of works) and reflect the quality, supervision and risk and inflationary factors, as well as prevailing market prices, associated with the types of works or goods to be procured.

(iii) The procuring entity has trained cost estimators on estimating prices and analyzing bid variances. In the case of infrastructure projects, the procuring entity must also have trained quantity surveyors.

(iv) The procuring entity has established a system to monitor and report bid prices relative to ABC and engineer’s/procuring entity’s estimate.

(v) The procuring entity has established a monitoring and evaluation system for contract implementation to provide a feedback on actual total costs of goods and works.

Page 20: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

20

14. Alternative Bids

14.1. Alternative Bids shall be rejected. For this purpose, alternative bid is an offer made by a Bidder in addition or as a substitute to its original bid which may be included as part of its original bid or submitted separately therewith for purposes of bidding. A bid with options is considered an alternative bid regardless of whether said bid proposal is contained in a single envelope or submitted in two (2) or more separate bid envelopes.

14.2. Bidders shall submit offers that comply with the requirements of the Bidding Documents, including the basic technical design as indicated in the drawings and specifications. Unless there is a value engineering clause in the BDS, alternative bids shall not be accepted.

14.3. Each Bidder shall submit only one Bid, either individually or as a partner in a JV. A Bidder who submits or participates in more than one bid (other than as a subcontractor if a subcontractor is permitted to participate in more than one bid) will cause all the proposals with the Bidder’s participation to be disqualified. This shall be without prejudice to any applicable criminal, civil and administrative penalties that may be imposed upon the persons and entities concerned.

15. Bid Prices

15.1. The contract shall be for the whole Works, as described in ITB Clause 1.1, based on the priced Bill of Quantities submitted by the Bidder.

15.2. The Bidder shall fill in rates and prices for all items of the Works described in the Bill of Quantities. Bids not addressing or providing all of the required items in the Bidding Documents including, where applicable, bill of quantities, shall be considered non-responsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Government.

15.3. All duties, taxes, and other levies payable by the Contractor under the Contract, or for any other cause, prior to the deadline for submission of bids, shall be included in the rates, prices, and total bid price submitted by the Bidder.

15.4. All bid prices for the given scope of work in the contract as awarded shall be considered as fixed prices, and therefore not subject to price escalation during contract implementation, except under extraordinary circumstances as specified in GCC Clause 47. Price escalation may be allowed in extraordinary circumstances as may be determined by the National Economic and Development Authority in accordance with the Civil Code of the Philippines, and upon the recommendation of the Procuring Entity. Furthermore, in cases where the cost of the awarded contract is affected by any applicable new laws, ordinances, regulations, or other acts of the GOP, promulgated after the date of bid opening, a contract price adjustment shall be made or appropriate relief shall be applied on a no loss-no gain basis.

Page 21: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

21

16. Bid Currencies

16.1. All bid prices shall be quoted in Philippine Pesos unless otherwise provided in the BDS. However, for purposes of bid evaluation, bids denominated in foreign currencies shall be converted to Philippine currency based on the exchange rate prevailing on the day of the Bid opening.

16.2. If so allowed in accordance with ITB Clause 16.1, the Procuring Entity for purposes of bid evaluation and comparing the bid prices will convert the amounts in various currencies in which the bid price is expressed to Philippine Pesos at the exchange rate as published in the BSP reference rate bulletin on the day of the bid opening.

16.3. Unless otherwise specified in the BDS, payment of the contract price shall be made in Philippine Pesos.

17. Bid Validity

17.1. Bids shall remain valid for the period specified in the BDS which shall not exceed one hundred twenty (120) calendar days from the date of the opening of bids.

17.2. In exceptional circumstances, prior to the expiration of the bid validity period, the Procuring Entity may request Bidders to extend the period of validity of their bids. The request and the responses shall be made in writing. The bid security described in ITB Clause 18 should also be extended corresponding to the extension of the bid validity period at the least. A Bidder may refuse the request without forfeiting its bid security, but his bid shall no longer be considered for further evaluation and award. A Bidder granting the request shall not be required or permitted to modify its bid.

18. Bid Security

18.1. The bid security in the amount stated in the BDS shall be equal to the percentage of the ABC in accordance with the following schedule:

Form of Bid Security Amount of Bid Security (Equal to Percentage of the ABC)

(a) Cash or cashier’s/manager’s check issued by a Universal or Commercial Bank.

Two percent (2%)

(b) Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

(c) Surety bond callable upon demand issued by a surety or Five percent (5%)

Page 22: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

22

insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or

(d) Any combination of the foregoing.

Proportionate to share of form with respect to total amount of

security

For biddings conducted by local government units, the Bidder may also submit bid securities in the form of cashier’s/manager’s check, bank draft/guarantee, or irrevocable letter of credit from other banks certified by the BSP as authorized to issue such financial statement.

18.2. The bid security should be valid for the period specified in the BDS. Any bid not accompanied by an acceptable bid security shall be rejected by the Procuring Entity as non-responsive.

18.3. No bid securities shall be returned to bidders after the opening of bids and before contract signing, except to those that failed or declared as post-disqualified, upon submission of a written waiver of their right to file a motion for reconsideration and/or protest. Without prejudice on its forfeiture, Bid Securities shall be returned only after the bidder with the Lowest Calculated Responsive Bid has signed the contract and furnished the Performance Security, but in no case later than the expiration of the Bid Security validity period indicated in ITB Clause 18.2.

18.4. Upon signing and execution of the contract, pursuant to ITB Clause 31, and the posting of the performance security, pursuant to ITB Clause 32, the successful Bidder’s Bid security will be discharged, but in no case later than the Bid security validity period as indicated in ITB Clause 18.2.

18.5. The bid security may be forfeited:

(a) if a Bidder:

(i) withdraws its bid during the period of bid validity specified in ITB Clause 17;

(ii) does not accept the correction of errors pursuant to ITB Clause 27.3(b);

(iii) fails to submit the requirements within the prescribed period, or a finding against their veracity, as stated in ITB Clause 28.2;

(iv) submission of eligibility requirements containing false information or falsified documents;

(v) submission of bids that contain false information or falsified documents, or the concealment of such information in the bids in order to influence the outcome of eligibility screening or any other stage of the public bidding;

Page 23: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

23

(vi) allowing the use of one’s name, or using the name of another for purposes of public bidding;

(vii) withdrawal of a bid, or refusal to accept an award, or enter into contract with the Government without justifiable cause, after the Bidder had been adjudged as having submitted the Lowest Calculated and Responsive Bid;

(viii) refusal or failure to post the required performance security within the prescribed time;

(ix) refusal to clarify or validate in writing its bid during post-qualification within a period of seven (7) calendar days from receipt of the request for clarification;

(x) any documented attempt by a bidder to unduly influence the outcome of the bidding in his favor;

(xi) failure of the potential joint venture partners to enter into the joint venture after the bid is declared successful; or

(xii) all other acts that tend to defeat the purpose of the competitive bidding, such as habitually withdrawing from bidding, submitting late Bids or patently insufficient bid, for at least three (3) times within a year, except for valid reasons.

(b) if the successful Bidder:

(i) fails to sign the contract in accordance with ITB Clause 31;

(ii) fails to furnish performance security in accordance with ITB Clause 32.

19. Format and Signing of Bids

19.1. Bidders shall submit their bids through their duly authorized representative using the appropriate forms provided in Section IX. Bidding Forms on or before the deadline specified in the ITB Clause 21 in two (2) separate sealed bid envelopes, and which shall be submitted simultaneously. The first shall contain the technical component of the bid, including the eligibility requirements under ITB Clause 12.1, and the second shall contain the financial component of the bid.

19.2. Forms as mentioned in ITB Clause 19.1 must be completed without any alterations to their format, and no substitute form shall be accepted. All blank spaces shall be filled in with the information requested.

19.3. The Bidder shall prepare an original of the first and second envelopes as described in ITB Clauses 12 and 13. In addition, the Bidder shall submit copies of the first and second envelopes. In the event of any discrepancy between the original and the copies, the original shall prevail.

Page 24: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

24

19.4. The bid, except for unamended printed literature, shall be signed, and each and every page thereof shall be initialed, by the duly authorized representative/s of the Bidder.

19.5. Any interlineations, erasures, or overwriting shall be valid only if they are signed or initialed by the duly authorized representative/s of the Bidder.

20. Sealing and Marking of Bids

20.1. Bidders shall enclose their original eligibility and technical documents described in ITB Clause 12, in one sealed envelope marked “ORIGINAL - TECHNICAL COMPONENT”, and the original of their financial component in another sealed envelope marked “ORIGINAL - FINANCIAL COMPONENT”, sealing them all in an outer envelope marked “ORIGINAL BID”.

20.2. Each copy of the first and second envelopes shall be similarly sealed duly marking the inner envelopes as “COPY NO. ___ - TECHNICAL COMPONENT” and “COPY NO. ___ – FINANCIAL COMPONENT” and the outer envelope as “COPY NO. ___”, respectively. These envelopes containing the original and the copies shall then be enclosed in one single envelope.

20.3. The original and the number of copies of the Bid as indicated in the BDS shall be typed or written in indelible ink and shall be signed by the bidder or its duly authorized representative/s.

20.4. All envelopes shall:

(a) contain the name of the contract to be bid in capital letters;

(b) bear the name and address of the Bidder in capital letters;

(c) be addressed to the Procuring Entity’s BAC identified in ITB Clause 10.1;

(d) bear the specific identification of this bidding process indicated in the Invitation to Bid; and

(e) bear a warning “DO NOT OPEN BEFORE…” the date and time for the opening of bids, in accordance with ITB Clause 21.

20.5. If bids are not sealed and marked as required, the Procuring Entity will assume no responsibility for the misplacement or premature opening of the bid.

D. Submission and Opening of Bids

21. Deadline for Submission of Bids

Page 25: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

25

Bids must be received by the Procuring Entity’s BAC at the address and on or before the date and time indicated in the BDS.

22. Late Bids

Any bid submitted after the deadline for submission and receipt of bids prescribed by the Procuring Entity, pursuant to ITB Clause 21, shall be declared “Late” and shall not be accepted by the Procuring Entity.

23. Modification and Withdrawal of Bids

23.1. The Bidder may modify its bid after it has been submitted; provided that the modification is received by the Procuring Entity prior to the deadline prescribed for submission and receipt of bids. The Bidder shall not be allowed to retrieve its original bid, but shall be allowed to submit another bid equally sealed, properly identified, linked to its original bid marked as “TECHNICAL MODIFICATION” or “FINANCIAL MODIFICATION” and stamped “received” by the BAC. Bid modifications received after the applicable deadline shall not be considered and shall be returned to the Bidder unopened.

23.2. A Bidder may, through a letter of withdrawal, withdraw its bid after it has been submitted, for valid and justifiable reason; provided that the letter of withdrawal is received by the Procuring Entity prior to the deadline prescribed for submission and receipt of bids.

23.3. Bids requested to be withdrawn in accordance with ITB Clause 23.1 shall be returned unopened to the Bidders. A Bidder may also express its intention not to participate in the bidding through a letter which should reach and be stamped by the BAC before the deadline for submission and receipt of bids. A Bidder that withdraws its bid shall not be permitted to submit another bid, directly or indirectly, for the same contract.

23.4. No bid may be modified after the deadline for submission of bids. No bid may be withdrawn in the interval between the deadline for submission of bids and the expiration of the period of bid validity specified by the Bidder on the Financial Bid Form. Withdrawal of a bid during this interval shall result in the forfeiture of the Bidder’s bid security, pursuant to ITB Clause 18.5, and the imposition of administrative, civil, and criminal sanctions as prescribed by RA 9184 and its IRR.

24. Opening and Preliminary Examination of Bids

24.1. The BAC shall open the first bid envelopes of Bidders in public as specified in the BDS to determine each Bidder’s compliance with the documents prescribed in ITB Clause 12. For this purpose, the BAC shall check the submitted documents of each bidder against a checklist of required documents to ascertain if they are all present, using a non-discretionary “pass/fail” criterion. If a bidder submits the required document, it shall be rated “passed” for that particular requirement. In this regard, bids that fail to include any

Page 26: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

26

requirement or are incomplete or patently insufficient shall be considered as “failed”. Otherwise, the BAC shall rate the said first bid envelope as “passed”.

24.2. Unless otherwise specified in the BDS, immediately after determining compliance with the requirements in the first envelope, the BAC shall forthwith open the second bid envelope of each remaining eligible bidder whose first bid envelope was rated “passed”. The second envelope of each complying bidder shall be opened within the same day. In case one or more of the requirements in the second envelope of a particular bid is missing, incomplete or patently insufficient, and/or if the submitted total bid price exceeds the ABC unless otherwise provided in ITB Clause 13.1(b), the BAC shall rate the bid concerned as “failed”. Only bids that are determined to contain all the bid requirements for both components shall be rated “passed” and shall immediately be considered for evaluation and comparison.

24.3. Letters of withdrawal shall be read out and recorded during bid opening, and the envelope containing the corresponding withdrawn bid shall be returned to the Bidder unopened. If the withdrawing Bidder’s representative is in attendance, the original bid and all copies thereof shall be returned to the representative during the bid opening. If the representative is not in attendance, the Bid shall be returned unopened by registered mail. The Bidder may withdraw its bid prior to the deadline for the submission and receipt of bids, provided that the corresponding letter of withdrawal contains a valid authorization requesting for such withdrawal, subject to appropriate administrative sanctions.

24.4. If a Bidder has previously secured a certification from the Procuring Entity to the effect that it has previously submitted the above-enumerated Class “A” Documents, the said certification may be submitted in lieu of the requirements enumerated in ITB Clause 12.1(a), items (i) to (vi).

24.5. In the case of an eligible foreign Bidder as described in ITB Clause 5, the Class “A” Documents enumerated in ITB Clause 12.1(a) may be substituted with the appropriate equivalent documents, if any, issued by the country of the foreign Bidder concerned.

24.6. Each partner of a joint venture agreement shall likewise submit the documents required in ITB Clauses 12.1(a)(i) and 12.1(a)(ii). Submission of documents required under ITB Clauses 12.1(a)(iii) to 12.1(a)(vi) by any of the joint venture partners constitutes compliance.

24.7. A Bidder determined as “failed” has three (3) calendar days upon written notice or, if present at the time of bid opening, upon verbal notification within which to file a request for reconsideration with the BAC: Provided, however, that the request for reconsideration shall not be granted if it is established that the finding of failure is due to the fault of the Bidder concerned: Provided, further, that the BAC shall decide on the request for reconsideration within seven (7) calendar days from receipt thereof. If a failed Bidder signifies his intent to file a request for reconsideration, the BAC shall keep the bid envelopes of the said failed Bidder unopened and/or duly sealed until such time that the request for reconsideration or protest has been resolved.

Page 27: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

27

E. Evaluation and Comparison of Bids

25. Process to be Confidential

25.1. Members of the BAC, including its staff and personnel, as well as its Secretariat and TWG, are prohibited from making or accepting any kind of communication with any bidder regarding the evaluation of their bids until the issuance of the Notice of Award, unless n the case of ITB Clause 26.

25.2. Any effort by a bidder to influence the Procuring Entity in the Procuring Entity’s decision in respect of Bid evaluation, Bid comparison or contract award will result in the rejection of the Bidder’s Bid.

26. Clarification of Bids

To assist in the evaluation, comparison and post-qualification of the bids, the Procuring Entity may ask in writing any Bidder for a clarification of its bid. All responses to requests for clarification shall be in writing. Any clarification submitted by a Bidder in respect to its bid and that is not in response to a request by the Procuring Entity shall not be considered

27. Detailed Evaluation and Comparison of Bids

27.1. The Procuring Entity will undertake the detailed evaluation and comparison of Bids which have passed the opening and preliminary examination of Bids, pursuant to ITB Clause 24, in order to determine the Lowest Calculated Bid.

27.2. In evaluating the Bids to get the Lowest Calculated Bid, the Procuring Entity shall undertake the following:

(a) The detailed evaluation of the financial component of the bids, to establish the correct calculated prices of the bids; and

(b) The ranking of the total bid prices as so calculated from the lowest to highest. The bid with the lowest price shall be identified as the Lowest Calculated Bid.

27.3. The Procuring Entity's BAC shall immediately conduct a detailed evaluation of all bids rated “passed,” using non-discretionary “pass/fail” criterion. The BAC shall consider the following in the evaluation of bids:

(a) Completeness of the bid. Unless the ITB specifically allows partial bids, bids not addressing or providing all of the required items in the Schedule of Requirements including, where applicable, bill of quantities, shall be considered non-responsive and, thus, automatically disqualified. In this regard, where a required item is provided, but no price is indicated, the same shall be considered as non-responsive, but specifying a "0" (zero) for the said item would mean that it is being offered for free to the Procuring Entity; and

(b) Arithmetical corrections. Consider computational errors and omissions to enable proper comparison of all eligible bids. It may also consider

Page 28: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

28

bid modifications if expressly allowed in the BDS. Any adjustment shall be calculated in monetary terms to determine the calculated prices.

27.4. Based on the detailed evaluation of bids, those that comply with the above-mentioned requirements shall be ranked in the ascending order of their total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, to identify the Lowest Calculated Bid. Total calculated bid prices, as evaluated and corrected for computational errors, discounts and other modifications, which exceed the ABC shall not be considered, unless otherwise indicated in the BDS.

27.5. The Procuring Entity’s evaluation of bids shall only be based on the bid price quoted in the Financial Bid Form

27.6. Bids shall be evaluated on an equal footing to ensure fair competition. For this purpose, all bidders shall be required to include in their bids the cost of all taxes, such as, but not limited to, value added tax (VAT), income tax, local taxes, and other fiscal levies and duties which shall be itemized in the bid form and reflected in the detailed estimates. Such bids, including said taxes, shall be the basis for bid evaluation and comparison.

28. Post Qualification

28.1. The Procuring Entity shall determine to its satisfaction whether the Bidder that is evaluated as having submitted the Lowest Calculated Bid (LCB) complies with and is responsive to all the requirements and conditions specified in ITB Clauses 5, 12, and 13.

28.2. Within a non-extendible period of three (3) calendar days from receipt by the Bidder of the notice from the BAC that it submitted the LCB, the Bidder shall submit the following documentary requirements:

(a) Latest income and business tax returns in the form specified in the BDS;

(b) Certificate of PhilGEPS Registration; and

(c) Other appropriate licenses and permits required by law and stated in the BDS.

Failure of the Bidder declared as LCB to duly submit the requirements under this Clause or a finding against the veracity of such, shall be ground for forfeiture of the bid security and disqualification of the Bidder for award.

28.3. The determination shall be based upon an examination of the documentary evidence of the Bidder’s qualifications submitted pursuant to ITB Clauses 12 and 13, as well as other information as the Procuring Entity deems necessary and appropriate, using a non-discretionary “pass/fail” criterion.

28.4. If the BAC determines that the Bidder with the Lowest Calculated Bid passes all the criteria for post-qualification, it shall declare the said bid as the Lowest

Page 29: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

29

Calculated Responsive Bid, and recommend to the Head of the Procuring Entity the award of contract to the said Bidder at its submitted price or its calculated bid price, whichever is lower, subject to ITB Clause 30.3.

28.5. A negative determination shall result in rejection of the Bidder’s Bid, in which event the Procuring Entity shall proceed to the next Lowest Calculated Bid to make a similar determination of that Bidder’s capabilities to perform satisfactorily. If the second Bidder, however, fails the post qualification, the procedure for post qualification shall be repeated for the Bidder with the next Lowest Calculated Bid, and so on until the Lowest Calculated and Responsive Bid is determined for contract award.

28.6. Within a period not exceeding seven (7) calendar days from the date of receipt of the recommendation of the BAC, the Head of the Procuring Entity shall approve or disapprove the said recommendation. In the case of government owned and government-owned and/or -controlled corporations (GOCCs) and government financial institutions (GFIs), the period provided herein shall be fifteen (15) calendar days.

29. Reservation Clause

29.1. Notwithstanding the eligibility or post-qualification of a bidder, the Procuring Entity concerned reserves the right to review its qualifications at any stage of the procurement process if it has reasonable grounds to believe that a misrepresentation has been made by the said bidder, or that there has been a change in the Bidder’s capability to undertake the project from the time it submitted its eligibility requirements. Should such review uncover any misrepresentation made in the eligibility and bidding requirements, statements or documents, or any changes in the situation of the Bidder which will affect its capability to undertake the project so that it fails the preset eligibility or bid evaluation criteria, the Procuring Entity shall consider the said Bidder as ineligible and shall disqualify it from submitting a bid or from obtaining an award or contract.

29.2. Based on the following grounds, the Procuring Entity reserves the right to reject any and all Bids, declare a Failure of Bidding at any time prior to the contract award, or not to award the contract, without thereby incurring any liability, and make no assurance that a contract shall be entered into as a result of the bidding:

(a) if there is prima facie evidence of collusion between appropriate public officers or employees of the Procuring Entity, or between the BAC and any of the bidders, or if the collusion is between or among the bidders themselves, or between a bidder and a third party, including any act which restricts, suppresses or nullifies or tends to restrict, suppress or nullify competition;

(b) if the Procuring Entity’s BAC is found to have failed in following the prescribed bidding procedures; or

Page 30: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

30

(c) for any justifiable and reasonable ground where the award of the contract will not redound to the benefit of the Government as follows:

(i) If the physical and economic conditions have significantly changed so as to render the project no longer economically, financially or technically feasible as determined by the head of the procuring entity;

(ii) If the project is no longer necessary as determined by the head of the procuring entity; and

(iii) If the source of funds for the project has been withheld or reduced through no fault of the Procuring Entity.

29.3. In addition, the Procuring Entity may likewise declare a failure of bidding when:

(a) No bids are received;

(b) All prospective bidders are declared ineligible;

(c) All bids fail to comply with all the bid requirements or fail post-qualification; or

(d) The bidder with the Lowest Calculated Responsive Bid refuses, without justifiable cause to accept the award of contract, and no award is made.

F. Award of Contract

30. Contract Award

30.1. Subject to ITB Clause 28, the Procuring Entity shall award the contract to the Bidder whose Bid has been determined to be the Lowest Calculated and Responsive Bid (LCRB).

30.2. Prior to the expiration of the period of Bid validity, the Procuring Entity shall notify the successful Bidder in writing that its Bid has been accepted, through a Notice of Award received personally or sent by registered mail or electronically, receipt of which must be confirmed in writing within two (2) days by the LCRB and submitted personally or sent by registered mail or electronically to the Procuring Entity.

30.3. Notwithstanding the issuance of the Notice of Award, award of contract shall be subject to the following conditions:

(a) Submission of the following documents within the prescribed period from receipt by the Bidder of the notice that it has the Lowest Calculated and Responsive Bid:

(i) Valid JVA, if applicable, within ten (10) calendar days;

Page 31: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

31

(ii) Valid PCAB license and registration for the type and cost of the contract to be bid for foreign bidders, within thirty (30) calendar days, if allowed under a Treaty or International or Executive Agreement mentioned in ITB Clause 12.1(a)(iv);

(b) Posting of the performance security in accordance with ITB Clause 32;

(c) Signing of the contract as provided in ITB Clause 31; and

(d) Approval by higher authority, if required.

31. Signing of the Contract

31.1. At the same time as the Procuring Entity notifies the successful Bidder that its Bid has been accepted, the Procuring Entity shall send the Contract Form to the Bidder, which Contract has been provided in the Bidding Documents, incorporating therein all agreements between the parties.

31.2. Within ten (10) calendar days from receipt of the Notice of Award, the successful Bidder shall post the required performance security, sign and date the contract and return it to the Procuring Entity.

31.3. The Procuring Entity shall enter into contract with the successful Bidder within the same ten (10) calendar day period provided that all the documentary requirements are complied with.

31.4. The following documents shall form part of the contract:

(a) Contract Agreement;

(b) Bidding Documents;

(c) Winning bidder’s bid, including the Technical and Financial Proposals, and all other documents/statements submitted;

(d) Performance Security;

(e) Credit line in accordance with ITB Clause 5.5, if applicable;

(f) Notice of Award of Contract; and

(g) Other contract documents that may be required by existing laws and/or specified in the BDS.

32. Performance Security

32.1. To guarantee the faithful performance by the winning Bidder of its obligations under the contract, it shall post a performance security within a maximum period of ten (10) calendar days from the receipt of the Notice of Award from the Procuring Entity and in no case later than the signing of the contract.

Page 32: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

32

32.2. The performance security shall be denominated in Philippine Pesos and posted in favor of the Procuring Entity in an amount equal to the percentage of the total contract price as stated in the BDS in accordance with the following schedule:

Form of Performance Security Amount of Performance Security (Equal to Percentage of the Total

Contract Price) (a) Cash or cashier’s/manager’s

check issued by a Universal or Commercial Bank.

Ten percent (10%)

(b) Bank draft/guarantee or irrevocable letter of credit issued by a Universal or Commercial Bank: Provided, however, that it shall be confirmed or authenticated by a Universal or Commercial Bank, if issued by a foreign bank.

(c) Surety bond callable upon demand issued by a surety or insurance company duly certified by the Insurance Commission as authorized to issue such security; and/or

Thirty percent (30%)

(d) Any combination of the foregoing.

Proportionate to share of form with respect to total amount of security

32.3. Failure of the successful Bidder to comply with the above-mentioned requirement shall constitute sufficient ground for the annulment of the award and forfeiture of the bid security, in which event the Procuring Entity shall initiate and complete the post qualification of the second Lowest Calculated Bid. The procedure shall be repeated until the Lowest Calculated and Responsive Bid is identified and selected for contract award. However if no Bidder passed post-qualification, the BAC shall declare the bidding a failure and conduct a re-bidding with re-advertisement.

33. Notice to Proceed

33.1. Within three (3) calendar days from the date of approval of the Contract by the appropriate government approving authority, the Procuring Entity shall issue its Notice to Proceed to the Bidder.

33.2. The contract effectivity date shall be provided in the Notice to Proceed by the Procuring Entity, which date shall not be later than seven (7) calendar days from the issuance of the Notice to Proceed.

Page 33: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

33

Section III. Bid Data Sheet

Page 34: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

34

Bid Data Sheet

ITB Clause

1.1 The PROCURING ENTITY is Department of Transportation and Communications (DOTC).

The name of the Contract is Calayan Port Development Project (Construction of Rock Causeway and R.C. Pier).

2

The Funding Source is:

The Government of the Philippines (GOP) through DOTC C.Y. 2013.

The name of the Project is Calayan Port Development Project (Construction of Rock Causeway and R.C. Pier).

3.1 No further instructions.

5.1 No further instructions.

5.2 Bidding is restricted to eligible bidders as defined in ITB Clause 5.1.

5.4.(a) The bidders must have an experience of having completed at least one (1) contract that is similar to the contract to be bid, and whose value, adjusted to current prices using the NSO consumer price indices, must be at least fifty percent (50%) of the Approved Budget for the contract.

For this purpose, similar contracts shall refer to Port and Harbor Projects.

8.1 Subcontracting is not allowed.

8.2 Not applicable.

9.1 The DOTC will hold a pre-bid conference for this Project on 23 September 2014, 1:30 pm, at 16th Floor, DOTC Multi-Purpose Room, The Columbia Tower, Ortigas Avenue, Mandaluyong City.

10.1 The Procuring Entity’s address is:

Department of Transportation and Communications Secondary Bids and Awards Committee Office (BAC) The Columbia Tower, Ortigas Avenue, Mandaluyong City Telefax: 654-7725

10.3 No further instructions.

12.1 No further instructions.

Page 35: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

35

12.1(a)(i) No other acceptable proof of registration is recognized.

12.1(a)(ii) No further instructions.

12.1(a)(iii) Bidders must also submit the following:

1. Duly signed Statement of all Ongoing Government & Private Construction Contracts including contracts awarded but not yet started (SF-INFR-15).

2. Duly signed Statement of all Completed Government & Private Construction Contracts which are similar in nature (SF-INFR-16).

12.1(a)(iv) Valid PCAB license and registration for the type and cost of the contract for this project. For joint venture bidders, a Joint License issued by the PCAB pursuant to Section 38 of RA 4566, and not the PCAB license and registration individually issued to each joint venture partner must be submitted. Failure of the joint venture bidder to submit a Joint License may be a ground for its disqualification despite the submission of the individual licenses of each joint venture partner.

The PCAB Registration for this project is Medium A for Port, Harbor or Offshore Engineering.

12.1(b)(ii)(ii.2) List of Contractors Personnel to be assigned to the contract to be bid with their respective curriculum vitae showing, among others, their educational attainment, professional qualification and experiences (SF-INFR-48), as follows:

1. Project Manager 2. Civil Engineer (licensed) 3. Materials Engineer (duly accredited by DPWH) 4. Safety Officer (with certificate of training in occupational safety and health) Duly signed Statement of Availability of Key Personnel and Equipment (SF-INFR-18).

12.1(b)(ii)(ii.3) List of Contractor’s Equipment OWNED/LEASED (pls. see Invitation to Bid), assigned to the Proposed Contract (SF-INFR-49).

13.1 Checklist of Financial Components:

1. Bid Prices in the bill of quantities in the prescribed form. 2. Detailed estimates including summary sheet indicating the unit prices of construction materials, labor rates and equipment OWNED/LEASED (Pls. see Invitation to Bid) used in coming up with the bid, and 3. Cash flow by quarter and payment schedules.

Page 36: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

36

13.1(b) The ABC is Fifty-Four Million One Hundred Twenty Thousand Nine Hundred Five and 82/100 Pesos (P 54,120,905.82). Any bid with a financial component exceeding this amount shall not be accepted.

14.2 No further instructions.

14.2 No further instructions.

16.1 The bid prices shall be quoted in Philippine Pesos.

17.1 Bids will be valid until One Hundred Twenty (120) calendar days from the date of the opening of bids.

18.1 The bid security shall be in the following amount:

1. The amount of One Million Eighty-Two Thousand Four Hundred Eighteen and 12/100 Pesos (P 1,082,418.12) or two percent (2%) of the ABC, if bid security is in cash, cashier’s/manager’s check, bank draft/guarantee or irrevocable letter of credit;

2. The amount of Two Million Seven Hundred Six Thousand Forty-Five and 29/100 Pesos (P 2,706,045.29) or five percent (5%) of the ABC, if bid security is in Surety Bond;

3. Any combination of the foregoing proportionate to the share of form with respect to total amount of security; or

4. Bid Securing Declaration.

In lieu of a bid security mentioned above, the bidder may submit a Bid Securing Declaration that is an undertaking which states, among others, that the bidder shall enter in to contract with the procuring entity and furnish the required performance security within ten (10) calendar days, or less, as indicated in the Bidding Documents, from receipt of the Notice of Award, and committing to pay the corresponding fine and be suspended for a period of time from being qualified to participate in any government procurement activity in the event it violates any of the conditions stated therein as required in the guidelines issued by the GPPB.

In no case shall bid security or Bid Securing Declaration be returned later than the expiration of the bid validity period indicated in the Bidding Documents, unless it has been extended in accordance with Section 28.2 of the IRR.

The Bid Securing Declaration Form is in Section IX. Bidding Form.

18.2 The bid security shall be valid until One Hundred Twenty (120) calendar days from the date of the opening of bids.

20.3 Each Bidder shall submit One (1) original and Two (2) copies of the first and second components of its bid.

Page 37: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

37

21 The address for submission of bids is :

Department of Transportation and Communications Bids and Awards Committee Office

15th Floor, Unit 153, The Columbia Tower, Ortigas Avenue, Mandaluyong City Tel No: 654-7725;727-7960 local 235

Fax No: 654-7725

The deadline for submission of bids is 07 October 2014, 1:30 pm. 24.1 The place of bid opening is at DOTC, Unit 167, The Columbia Tower,

Ortigas Avenue, Mandaluyong City.

The date and time of bid opening is 07 October 2014, 1:30 pm.

24.2 No further instructions.

27.3(b) Bid modification is not allowed.

27.4 No further instructions.

28.2(a) Only tax returns filed and taxes paid through the BIR Electronic Filing and Payment System (EFPS) shall be accepted.

NOTE: The latest income and business tax returns are those within the last six months preceding the date of bid submission.

28.2(c) Additional document:

Valid Certificate of Registration indicating the Tax Identification Number and photocopy of TIN Card.

31.4(g) Construction schedule and S-curve, manpower schedule, construction methods, equipment utilization schedule, construction safety and health program duly approved by the Department of Labor and Employment, and PERT/CPM.

32.2 The performance security shall be in the following amount:

1. The amount of (10% of the total contract amount), if performance security is in cash, cashier’s/manager’s check, bank draft/guarantee or irrevocable letter of credit;

2. The amount of (30% of the total contract amount), if performance security is in Surety Bond; or

3. Any combination of the foregoing proportionate to the share of form with respect to total amount of security.

Page 38: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

38

Section IV. General Conditions of Contract

Page 39: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

39

TABLE OF CONTENTS

1. DEFINITIONS ................................................................................................. 41

2. INTERPRETATION ......................................................................................... 43

3. GOVERNING LANGUAGE AND LAW .............................................................. 43

4. COMMUNICATIONS ....................................................................................... 43

5. POSSESSION OF SITE ..................................................................................... 44

6. THE CONTRACTOR’S OBLIGATIONS ............................................................ 44

7. PERFORMANCE SECURITY ............................................................................ 45

8. SUBCONTRACTING ........................................................................................ 46

9. LIQUIDATED DAMAGES ................................................................................ 46

10. SITE INVESTIGATION REPORTS .................................................................... 47

11. THE PROCURING ENTITY, LICENSES AND PERMITS .................................... 47

12. CONTRACTOR’S RISK AND WARRANTY SECURITY ..................................... 47

13. LIABILITY OF THE CONTRACTOR ................................................................ 49

14. PROCURING ENTITY’S RISK ......................................................................... 49

15. INSURANCE ................................................................................................... 50

16. TERMINATION FOR DEFAULT OF CONTRACTOR ......................................... 51

17. TERMINATION FOR DEFAULT OF PROCURING ENTITY ............................... 52

18. TERMINATION FOR OTHER CAUSES ............................................................ 52

19. PROCEDURES FOR TERMINATION OF CONTRACTS ...................................... 53

20. FORCE MAJEURE, RELEASE FROM PERFORMANCE ................................... 56

21. RESOLUTION OF DISPUTES ........................................................................... 57

22. SUSPENSION OF LOAN, CREDIT, GRANT, OR APPROPRIATION ................... 57

23. PROCURING ENTITY’S REPRESENTATIVE’S DECISIONS .............................. 57

24. APPROVAL OF DRAWINGS AND TEMPORARY WORKS BY THE PROCURING ENTITY’S REPRESENTATIVE .................................................... 58

25. ACCELERATION AND DELAYS ORDERED BY THE PROCURING ENTITY’S REPRESENTATIVE ........................................................................ 58

26. EXTENSION OF THE INTENDED COMPLETION DATE ................................... 58

27. RIGHT TO VARY ............................................................................................ 58

28. CONTRACTORS RIGHT TO CLAIM ................................................................ 59

Page 40: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

40

29. DAYWORKS ................................................................................................... 59

30. EARLY WARNING ......................................................................................... 59

31. PROGRAM OF WORK .................................................................................... 60

32. MANAGEMENT CONFERENCES ..................................................................... 60

33. BILL OF QUANTITIES .................................................................................... 60

34. INSTRUCTIONS, INSPECTIONS AND AUDITS .................................................. 61

35. IDENTIFYING DEFECTS ................................................................................. 61

36. COST OF REPAIRS ......................................................................................... 61

37. CORRECTION OF DEFECTS ........................................................................... 61

38. UNCORRECTED DEFECTS ............................................................................. 62

39. ADVANCE PAYMENT ..................................................................................... 62

40. PROGRESS PAYMENTS .................................................................................. 63

41. PAYMENT CERTIFICATES ............................................................................. 63

42. RETENTION ................................................................................................... 64

43. VARIATION ORDERS ..................................................................................... 64

44. CONTRACT COMPLETION ............................................................................. 66

45. SUSPENSION OF WORK ................................................................................. 66

46. PAYMENT ON TERMINATION ........................................................................ 67

47. EXTENSION OF CONTRACT TIME ................................................................. 68

48. PRICE ADJUSTMENT ..................................................................................... 69

49. COMPLETION ................................................................................................ 69

50. TAKING OVER ............................................................................................... 69

51. OPERATING AND MAINTENANCE MANUALS ................................................ 69

Page 41: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

41

1. Definitions

For purposes of this Clause, boldface type is used to identify defined terms.

1.1. The Arbiter is the person appointed jointly by the Procuring Entity and the Contractor to resolve disputes in the first instance, as provided for in GCC Clause 20.

1.2. Bill of Quantities refers to a list of the specific items of the Work and their corresponding unit prices, lump sums, and/or provisional sums.

1.3. The Completion Date is the date of completion of the Works as certified by the Procuring Entity’s Representative, in accordance with GCC Clause 49.

1.4. The Contract is the contract between the Procuring Entity and the Contractor to execute, complete, and maintain the Works.

1.5. The Contract Price is the price stated in the Letter of Acceptance and thereafter to be paid by the Procuring Entity to the Contractor for the execution of the Works in accordance with this Contract.

1.6. Contract Time Extension is the allowable period for the Contractor to complete the Works in addition to the original Completion Date stated in this Contract.

1.7. The Contractor is the juridical entity whose proposal has been accepted by the Procuring Entity and to whom the Contract to execute the Work was awarded.

1.8. The Contractor’s Bid is the signed offer or proposal submitted by the Contractor to the Procuring Entity in response to the Bidding Documents.

1.9. Days are calendar days; months are calendar months.

1.10. Dayworks are varied work inputs subject to payment on a time basis for the Contractor’s employees and Equipment, in addition to payments for associated Materials and Plant.

1.11. A Defect is any part of the Works not completed in accordance with the Contract.

1.12. The Defects Liability Certificate is the certificate issued by Procuring Entity’s Representative upon correction of defects by the Contractor.

1.13. The Defects Liability Period is the one year period between contract completion and final acceptance within which the Contractor assumes the responsibility to undertake the repair of any damage to the Works at his own expense.

Page 42: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

42

1.14. Drawings are graphical presentations of the Works. They include all supplementary details, shop drawings, calculations, and other information provided or approved for the execution of this Contract.

1.15. Equipment refers to all facilities, supplies, appliances, materials or things required for the execution and completion of the Work provided by the Contractor and which shall not form or are not intended to form part of the Permanent Works.

1.16. The Intended Completion Date refers to the date specified in the SCC when the Contractor is expected to have completed the Works. The Intended Completion Date may be revised only by the Procuring Entity’s Representative by issuing an extension of time or an acceleration order.

1.17. Materials are all supplies, including consumables, used by the Contractor for incorporation in the Works.

1.18. The Notice to Proceed is a written notice issued by the Procuring Entity or the Procuring Entity’s Representative to the Contractor requiring the latter to begin the commencement of the work not later than a specified or determinable date.

1.19. Permanent Works all permanent structures and all other project features and facilities required to be constructed and completed in accordance with this Contract which shall be delivered to the Procuring Entity and which shall remain at the Site after the removal of all Temporary Works.

1.20. Plant refers to the machinery, apparatus, and the like intended to form an integral part of the Permanent Works.

1.21. The Procuring Entity is the party who employs the Contractor to carry out the Works stated in the SCC.

1.22. The Procuring Entity’s Representative refers to the Head of the Procuring Entity or his duly authorized representative, identified in the SCC, who shall be responsible for supervising the execution of the Works and administering this Contract.

1.23. The Site is the place provided by the Procuring Entity where the Works shall be executed and any other place or places which may be designated in the SCC, or notified to the Contractor by the Procuring Entity’s Representative as forming part of the Site.

1.24. Site Investigation Reports are those that were included in the Bidding Documents and are factual and interpretative reports about the surface and subsurface conditions at the Site.

1.25. Slippage is a delay in work execution occurring when actual accomplishment falls below the target as measured by the difference between the scheduled and actual accomplishment of the Work by the Contractor as established from the work schedule. This is actually described as a percentage of the whole Works.

Page 43: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

43

1.26. Specifications means the description of Works to be done and the qualities of materials to be used, the equipment to be installed and the mode of construction.

1.27. The Start Date, as specified in the SCC, is the date when the Contractor is obliged to commence execution of the Works. It does not necessarily coincide with any of the Site Possession Dates.

1.28. A Subcontractor is any person or organization to whom a part of the Works has been subcontracted by the Contractor, as allowed by the Procuring Entity, but not any assignee of such person.

1.29. Temporary Works are works designed, constructed, installed, and removed by the Contractor that are needed for construction or installation of the Permanent Works.

1.30. Work(s) refer to the Permanent Works and Temporary Works to be executed by the Contractor in accordance with this Contract, including (i) the furnishing of all labor, materials, equipment and others incidental, necessary or convenient to the complete execution of the Works; (ii) the passing of any tests before acceptance by the Procuring Entity’s Representative; (iii) and the carrying out of all duties and obligations of the Contractor imposed by this Contract as described in the SCC.

2. Interpretation

2.1. In interpreting the Conditions of Contract, singular also means plural, male also means female or neuter, and the other way around. Headings have no significance. Words have their normal meaning under the language of this Contract unless specifically defined. The Procuring Entity’s Representative will provide instructions clarifying queries about the Conditions of Contract.

2.2. If sectional completion is specified in the SCC, references in the Conditions of Contract to the Works, the Completion Date, and the Intended Completion Date apply to any Section of the Works (other than references to the Completion Date and Intended Completion Date for the whole of the Works).

3. Governing Language and Law

3.1. This Contract has been executed in the English language, which shall be the binding and controlling language for all matters relating to the meaning or interpretation of this Contract. All correspondence and other documents pertaining to this Contract which are exchanged by the parties shall be written in English.

3.2. This Contract shall be interpreted in accordance with the laws of the Republic of the Philippines.

4. Communications

Page 44: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

44

Communications between parties that are referred to in the Conditions shall be effective only when in writing. A notice shall be effective only when it is received by the concerned party.

5. Possession of Site

5.1. On the date specified in the SCC, the Procuring Entity shall grant the Contractor possession of so much of the Site as may be required to enable it to proceed with the execution of the Works. If the Contractor suffers delay or incurs cost from failure on the part of the Procuring Entity to give possession in accordance with the terms of this clause, the Procuring Entity’s Representative shall give the Contractor a Contract Time Extension and certify such sum as fair to cover the cost incurred, which sum shall be paid by Procuring Entity.

5.2. If possession of a portion is not given by the date stated in the SCC Clause 5.1, the Procuring Entity will be deemed to have delayed the start of the relevant activities. The resulting adjustments in contact time to address such delay shall be in accordance with GCC Clause 46.

5.3. The Contractor shall bear all costs and charges for special or temporary right-of-way required by it in connection with access to the Site. The Contractor shall also provide at his own cost any additional facilities outside the Site required by it for purposes of the Works.

5.4. The Contractor shall allow the Procuring Entity’s Representative and any person authorized by the Procuring Entity’s Representative access to the Site and to any place where work in connection with this Contract is being carried out or is intended to be carried out.

6. The Contractor’s Obligations

6.1. The Contractor shall carry out the Works properly and in accordance with this Contract. The Contractor shall provide all supervision, labor, Materials, Plant and Contractor's Equipment, which may be required. All Materials and Plant on Site shall be deemed to be the property of the Procuring Entity.

6.2. The Contractor shall commence execution of the Works on the Start Date and shall carry out the Works in accordance with the Program of Work submitted by the Contractor, as updated with the approval of the Procuring Entity’s Representative, and complete them by the Intended Completion Date.

6.3. The Contractor shall be responsible for the safety of all activities on the Site.

6.4. The Contractor shall carry out all instructions of the Procuring Entity’s Representative that comply with the applicable laws where the Site is located.

6.5. The Contractor shall employ the key personnel named in the Schedule of Key Personnel, as referred to in the SCC, to carry out the supervision of the Works. The Procuring Entity will approve any proposed replacement of key

Page 45: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

45

personnel only if their relevant qualifications and abilities are equal to or better than those of the personnel listed in the Schedule.

6.6. If the Procuring Entity’s Representative asks the Contractor to remove a member of the Contractor’s staff or work force, for justifiable cause, the Contractor shall ensure that the person leaves the Site within seven (7) days and has no further connection with the Work in this Contract.

6.7. During Contract implementation, the Contractor and his subcontractors shall abide at all times by all labor laws, including child labor related enactments, and other relevant rules.

6.8. The Contractor shall submit to the Procuring Entity for consent the name and particulars of the person authorized to receive instructions on behalf of the Contractor.

6.9. The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities, and the Procuring Entity between the dates given in the schedule of other contractors particularly when they shall require access to the Site. The Contractor shall also provide facilities and services for them during this period. The Procuring Entity may modify the schedule of other contractors, and shall notify the Contractor of any such modification thereto.

6.10. Should anything of historical or other interest or of significant value be unexpectedly discovered on the Site, it shall be the property of the Procuring Entity. The Contractor shall notify the Procuring Entity’s Representative of such discoveries and carry out the Procuring Entity’s Representative’s instructions in dealing with them.

7. Performance Security

7.1. Within ten (10) calendar days from receipt of the Notice of Award from the Procuring Entity but in no case later than the signing of the contract by both parties, the Contractor shall furnish the performance security in any the forms prescribed in ITB Clause 32.2.

7.2. The performance security posted in favor of the Procuring Entity shall be forfeited in the event it is established that the Contractor is in default in any of its obligations under the Contract.

7.3. The performance security shall remain valid until issuance by the Procuring Entity of the Certificate of Final Acceptance.

7.4. The performance security may be released by the Procuring Entity and returned to the Contractor after the issuance of the Certificate of Final Acceptance subject to the following conditions:

(a) There are no pending claims against the Contractor or the surety company filed by the Procuring Entity;

(b) The Contractor has no pending claims for labor and materials filed against it; and

Page 46: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

46

(c) Other terms specified in the SCC.

7.5. The Contractor shall post an additional performance security following the amount and form specified in ITB Clause 32.2 to cover any cumulative increase of more than ten percent (10%) over the original value of the contract as a result of amendments to order or change orders, extra work orders and supplemental agreements, as the case may be. The Contractor shall cause the extension of the validity of the performance security to cover approved contract time extensions.

7.6. In case of a reduction in the contract value or for partially completed Works under the contract which are usable and accepted by the Procuring Entity the use of which, in the judgment of the implementing agency or the Procuring Entity, will not affect the structural integrity of the entire project, the Procuring Entity shall allow a proportional reduction in the original performance security, provided that any such reduction is more than ten percent (10%) and that the aggregate of such reductions is not more than fifty percent (50%) of the original performance security.

7.7. Unless otherwise indicated in the SCC, the Contractor, by entering into the Contract with the Procuring Entity, acknowledges the right of the Procuring Entity to institute action pursuant to Act 3688 against any subcontractor be they an individual, firm, partnership, corporation, or association supplying the Contractor with labor, materials and/or equipment for the performance of this Contract.

8. Subcontracting

8.1. Unless otherwise indicated in the SCC, the Contractor cannot subcontract Works more than the percentage specified in ITB Clause 8.1.

8.2. Subcontracting of any portion of the Works does not relieve the Contractor of any liability or obligation under this Contract. The Contractor will be responsible for the acts, defaults, and negligence of any subcontractor, its agents, servants or workmen as fully as if these were the Contractor’s own acts, defaults, or negligence, or those of its agents, servants or workmen.

8.3. Subcontractors disclosed and identified during the bidding may be changed during the implementation of this Contract, subject to compliance with the required qualifications and the approval of the Procuring Entity.

9. Liquidated Damages

9.1. The Contractor shall pay liquidated damages to the Procuring Entity for each day that the Completion Date is later than the Intended Completion Date. The applicable liquidated damages is at least one-tenth (1/10) of a percent of the cost of the unperformed portion for every day of delay. The total amount of liquidated damages shall not exceed ten percent (10%) of the amount of the contract. The Procuring Entity may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor. Once the cumulative amount of liquidated damages reaches ten

Page 47: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

47

percent (10%) of the amount of this Contract, the Procuring Entity shall rescind this Contract, without prejudice to other courses of action and remedies open to it.

9.2. If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer of the Procuring Entity shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. The Contractor shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in GCC Clause 40.3.

10. Site Investigation Reports

The Contractor, in preparing the Bid, shall rely on any Site Investigation Reports referred to in the SCC supplemented by any information obtained by the Contractor.

11. The Procuring Entity, Licenses and Permits

The Procuring Entity shall, if requested by the Contractor, assist him in applying for permits, licenses or approvals, which are required for the Works.

12. Contractor’s Risk and Warranty Security

12.1. The Contractor shall assume full responsibility for the Works from the time project construction commenced up to final acceptance by the Procuring Entity and shall be held responsible for any damage or destruction of the Works except those occasioned by force majeure. The Contractor shall be fully responsible for the safety, protection, security, and convenience of his personnel, third parties, and the public at large, as well as the Works, Equipment, installation, and the like to be affected by his construction work.

12.2. The defects liability period for infrastructure projects shall be one year from contract completion up to final acceptance by the Procuring Entity. During this period, the Contractor shall undertake the repair works, at his own expense, of any damage to the Works on account of the use of materials of inferior quality within ninety (90) days from the time the Head of the Procuring Entity has issued an order to undertake repair. In case of failure or refusal to comply with this mandate, the Procuring Entity shall undertake such repair works and shall be entitled to full reimbursement of expenses incurred therein upon demand.

12.3. Unless otherwise indicated in the SCC, in case the Contractor fails to comply with the preceding paragraph, the Procuring Entity shall forfeit its performance security, subject its property(ies) to attachment or garnishment proceedings, and perpetually disqualify it from participating in any public bidding. All payables of the GOP in his favor shall be offset to recover the costs.

12.4. After final acceptance of the Works by the Procuring Entity, the Contractor shall be held responsible for “Structural Defects”, i.e., major faults/flaws/deficiencies in one or more key structural elements of the project

Page 48: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

48

which may lead to structural failure of the completed elements or structure, or “Structural Failures”, i.e., where one or more key structural elements in an infrastructure facility fails or collapses, thereby rendering the facility or part thereof incapable of withstanding the design loads, and/or endangering the safety of the users or the general public:

(a) Contractor – Where Structural Defects/Failures arise due to faults attributable to improper construction, use of inferior quality/substandard materials, and any violation of the contract plans and specifications, the contractor shall be held liable;

(b) Consultants – Where Structural Defects/Failures arise due to faulty and/or inadequate design and specifications as well as construction supervision, then the consultant who prepared the design or undertook construction supervision for the project shall be held liable;

(c) Procuring Entity’s Representatives/Project Manager/Construction Managers and Supervisors – The project owner’s representative(s), project manager, construction manager, and supervisor(s) shall be held liable in cases where the Structural Defects/Failures are due to his/their willful intervention in altering the designs and other specifications; negligence or omission in not approving or acting on proposed changes to noted defects or deficiencies in the design and/or specifications; and the use of substandard construction materials in the project;

(d) Third Parties - Third Parties shall be held liable in cases where Structural Defects/Failures are caused by work undertaken by them such as leaking pipes, diggings or excavations, underground cables and electrical wires, underground tunnel, mining shaft and the like, in which case the applicable warranty to such structure should be levied to third parties for their construction or restoration works.

(e) Users - In cases where Structural Defects/Failures are due to abuse/misuse by the end user of the constructed facility and/or non–compliance by a user with the technical design limits and/or intended purpose of the same, then the user concerned shall be held liable.

12.5. The warranty against Structural Defects/Failures, except those occasioned on force majeure, shall cover the period specified in the SCC reckoned from the date of issuance of the Certificate of Final Acceptance by the Procuring Entity.

12.6. The Contractor shall be required to put up a warranty security in the form of cash, bank guarantee, letter of credit, GSIS or surety bond callable on demand, in accordance with the following schedule:

Form of Warranty Minimum Amount in

Percentage (%) of Total Contract Price

(a) Cash or letter of credit issued by Universal or Commercial bank: provided, however, that the letter of

Five Percent (5%)

Page 49: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

49

credit shall be confirmed or authenticated by a Universal or Commercial bank, if issued by a foreign bank

(b) Bank guarantee confirmed by Universal or Commercial bank: provided, however, that the letter of credit shall be confirmed or authenticated by a Universal or Commercial bank, if issued by a foreign bank

Ten Percent (10%)

(c) Surety bond callable upon demand issued by GSIS or any surety or insurance company duly certified by the Insurance Commission

Thirty Percent (30%)

12.7. The warranty security shall be stated in Philippine Pesos and shall remain effective for one year from the date of issuance of the Certificate of Final Acceptance by the Procuring Entity, and returned only after the lapse of said one year period.

12.8. In case of structural defects/failure occurring during the applicable warranty period provided in GCC Clause 12.5, the Procuring Entity shall undertake the necessary restoration or reconstruction works and shall be entitled to full reimbursement by the parties found to be liable for expenses incurred therein upon demand, without prejudice to the filing of appropriate administrative, civil, and/or criminal charges against the responsible persons as well as the forfeiture of the warranty security posted in favor of the Procuring Entity.

13. Liability of the Contractor

Subject to additional provisions, if any, set forth in the SCC, the Contractor’s liability under this Contract shall be as provided by the laws of the Republic of the Philippines.

14. Procuring Entity’s Risk

14.1. From the Start Date until the Certificate of Final Acceptance has been issued, the following are risks of the Procuring Entity:

(a) The risk of personal injury, death, or loss of or damage to property (excluding the Works, Plant, Materials, and Equipment), which are due to:

(i) any type of use or occupation of the Site authorized by the Procuring Entity after the official acceptance of the works; or

(ii) negligence, breach of statutory duty, or interference with any legal right by the Procuring Entity or by any person employed by or contracted to him except the Contractor.

Page 50: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

50

(b) The risk of damage to the Works, Plant, Materials, and Equipment to the extent that it is due to a fault of the Procuring Entity or in the Procuring Entity’s design, or due to war or radioactive contamination directly affecting the country where the Works are to be executed.

15. Insurance

15.1. The Contractor shall, under his name and at his own expense, obtain and maintain, for the duration of this Contract, the following insurance coverage:

(a) Contractor’s All Risk Insurance;

(b) Transportation to the project Site of Equipment, Machinery, and Supplies owned by the Contractor;

(c) Personal injury or death of Contractor’s employees; and

(d) Comprehensive insurance for third party liability to Contractor’s direct or indirect act or omission causing damage to third persons.

15.2. The Contractor shall provide evidence to the Procuring Entity’s Representative that the insurances required under this Contract have been effected and shall, within a reasonable time, provide copies of the insurance policies to the Procuring Entity’s Representative. Such evidence and such policies shall be provided to the Procuring Entity’s through the Procuring Entity’s Representative.

15.3. The Contractor shall notify the insurers of changes in the nature, extent, or program for the execution of the Works and ensure the adequacy of the insurances at all times in accordance with the terms of this Contract and shall produce to the Procuring Entity’s Representative the insurance policies in force including the receipts for payment of the current premiums.

The above insurance policies shall be obtained from any reputable insurance company approved by the Procuring Entity’s Representative.

15.4. If the Contractor fails to obtain and keep in force the insurances referred to herein or any other insurance which he may be required to obtain under the terms of this Contract, the Procuring Entity may obtain and keep in force any such insurances and pay such premiums as may be necessary for the purpose. From time to time, the Procuring Entity may deduct the amount it shall pay for said premiums including twenty five percent (25%) therein from any monies due, or which may become due, to the Contractor, without prejudice to the Procuring Entity exercising its right to impose other sanctions against the Contractor pursuant to the provisions of this Contract.

15.5. In the event the Contractor fails to observe the above safeguards, the Procuring Entity may, at the Contractor’s expense, take whatever measure is

Page 51: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

51

deemed necessary for its protection and that of the Contractor’s personnel and third parties, and/or order the interruption of dangerous Works. In addition, the Procuring Entity may refuse to make the payments under GCC Clause 39 until the Contractor complies with this Clause.

15.6. The Contractor shall immediately replace the insurance policy obtained as required in this Contract, without need of the Procuring Entity’s demand, with a new policy issued by a new insurance company acceptable to the Procuring Entity for any of the following grounds:

(a) The issuer of the insurance policy to be replaced has:

(i) become bankrupt;

(ii) been placed under receivership or under a management committee;

(iii) been sued for suspension of payment; or

(iv) been suspended by the Insurance Commission and its license to engage in business or its authority to issue insurance policies cancelled; or

(v) Where reasonable grounds exist that the insurer may not be able, fully and promptly, to fulfill its obligation under the insurance policy.

16. Termination for Default of Contractor

16.1. The Procuring Entity shall terminate this Contract for default when any of the following conditions attend its implementation:

16.2. Due to the Contractor’s fault and while the project is on-going, it has incurred negative slippage of fifteen percent (15%) or more in accordance with Presidential Decree 1870, regardless of whether or not previous warnings and notices have been issued for the Contractor to improve his performance;

16.3. Due to its own fault and after this Contract time has expired, the Contractor incurs delay in the completion of the Work after this Contract has expired; or

16.4. The Contractor:

(a) abandons the contract Works, refuses or fails to comply with a valid instruction of the Procuring Entity or fails to proceed expeditiously and without delay despite a written notice by the Procuring Entity;

(b) does not actually have on the project Site the minimum essential equipment listed on the Bid necessary to prosecute the Works in accordance with the approved Program of Work and equipment deployment schedule as required for the project;

Page 52: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

52

(c) does not execute the Works in accordance with this Contract or persistently or flagrantly neglects to carry out its obligations under this Contract;

(d) neglects or refuses to remove materials or to perform a new Work that has been rejected as defective or unsuitable; or

(e) sub-lets any part of this Contract without approval by the Procuring Entity.

16.5. All materials on the Site, Plant, Equipment, and Works shall be deemed to be the property of the Procuring Entity if this Contract is rescinded because of the Contractor’s default.

17. Termination for Default of Procuring Entity

The Contractor may terminate this Contract with the Procuring Entity if the works are completely stopped for a continuous period of at least sixty (60) calendar days through no fault of its own, due to any of the following reasons:

(a) Failure of the Procuring Entity to deliver, within a reasonable time, supplies, materials, right-of-way, or other items it is obligated to furnish under the terms of this Contract; or

(b) The prosecution of the Work is disrupted by the adverse peace and order situation, as certified by the Armed Forces of the Philippines Provincial Commander and approved by the Secretary of National Defense.

18. Termination for Other Causes

18.1. The Procuring Entity may terminate this Contract, in whole or in part, at any time for its convenience. The Head of the Procuring Entity may terminate this Contract for the convenience of the Procuring Entity if he has determined the existence of conditions that make Project Implementation economically, financially or technically impractical and/or unnecessary, such as, but not limited to, fortuitous event(s) or changes in law and National Government policies.

18.2. The Procuring Entity or the Contractor may terminate this Contract if the other party causes a fundamental breach of this Contract.

18.3. Fundamental breaches of Contract shall include, but shall not be limited to, the following:

(a) The Contractor stops work for twenty eight (28) days when no stoppage of work is shown on the current Program of Work and the stoppage has not been authorized by the Procuring Entity’s Representative;

(b) The Procuring Entity’s Representative instructs the Contractor to delay the progress of the Works, and the instruction is not withdrawn within twenty eight (28) days;

Page 53: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

53

(c) The Procuring Entity shall terminate this Contract if the Contractor is declared bankrupt or insolvent as determined with finality by a court of competent jurisdiction. In this event, termination will be without compensation to the Contractor, provided that such termination will not prejudice or affect any right of action or remedy which has accrued or will accrue thereafter to the Procuring Entity and/or the Contractor. In the case of the Contractor's insolvency, any Contractor's Equipment which the Procuring Entity instructs in the notice is to be used until the completion of the Works;

(d) A payment certified by the Procuring Entity’s Representative is not paid by the Procuring Entity to the Contractor within eighty four (84) days from the date of the Procuring Entity’s Representative’s certificate;

(e) The Procuring Entity’s Representative gives Notice that failure to correct a particular Defect is a fundamental breach of Contract and the Contractor fails to correct it within a reasonable period of time determined by the Procuring Entity’s Representative;

(f) The Contractor does not maintain a Security, which is required;

(g) The Contractor has delayed the completion of the Works by the number of days for which the maximum amount of liquidated damages can be paid, as defined in the GCC Clause 7.5; and

(h) In case it is determined prima facie by the Procuring Entity that the Contractor has engaged, before or during the implementation of the contract, in unlawful deeds and behaviors relative to contract acquisition and implementation, such as, but not limited to, the following:

(i) corrupt, fraudulent, collusive, coercive, and obstructive practices as defined in ITB Clause 3.1(a), unless otherwise specified in the SCC;

(ii) drawing up or using forged documents;

(iii) using adulterated materials, means or methods, or engaging in production contrary to rules of science or the trade; and

(iv) any other act analogous to the foregoing.

18.4. The Funding Source or the Procuring Entity, as appropriate, will seek to impose the maximum civil, administrative and/or criminal penalties available under the applicable law on individuals and organizations deemed to be involved with corrupt, fraudulent, or coercive practices.

18.5. When persons from either party to this Contract gives notice of a fundamental breach to the Procuring Entity’s Representative in order to terminate the existing contract for a cause other than those listed under GCC Clause 18.3,

Page 54: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

54

the Procuring Entity’s Representative shall decide whether the breach is fundamental or not.

18.6. If this Contract is terminated, the Contractor shall stop work immediately, make the Site safe and secure, and leave the Site as soon as reasonably possible.

19. Procedures for Termination of Contracts

19.1. The following provisions shall govern the procedures for the termination of this Contract:

(a) Upon receipt of a written report of acts or causes which may constitute ground(s) for termination as aforementioned, or upon its own initiative, the Procuring Entity shall, within a period of seven (7) calendar days, verify the existence of such ground(s) and cause the execution of a Verified Report, with all relevant evidence attached;

(b) Upon recommendation by the Procuring Entity, the Head of the Procuring Entity shall terminate this Contract only by a written notice to the Contractor conveying the termination of this Contract. The notice shall state:

(i) that this Contract is being terminated for any of the ground(s) afore-mentioned, and a statement of the acts that constitute the ground(s) constituting the same;

(ii) the extent of termination, whether in whole or in part;

(iii) an instruction to the Contractor to show cause as to why this Contract should not be terminated; and

(iv) special instructions of the Procuring Entity, if any.

The Notice to Terminate shall be accompanied by a copy of the Verified Report;

(c) Within a period of seven (7) calendar days from receipt of the Notice of Termination, the Contractor shall submit to the Head of the Procuring Entity a verified position paper stating why the contract should not be terminated. If the Contractor fails to show cause after the lapse of the seven (7) day period, either by inaction or by default, the Head of the Procuring Entity shall issue an order terminating the contract;

(d) The Procuring Entity may, at anytime before receipt of the Bidder’s verified position paper described in item (c) above withdraw the Notice to Terminate if it is determined that certain items or works subject of the notice had been completed, delivered, or performed before the Contractor’s receipt of the notice;

Page 55: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

55

(e) Within a non-extendible period of ten (10) calendar days from receipt of the verified position paper, the Head of the Procuring Entity shall decide whether or not to terminate this Contract. It shall serve a written notice to the Contractor of its decision and, unless otherwise provided in the said notice, this Contract is deemed terminated from receipt of the Contractor of the notice of decision. The termination shall only be based on the ground(s) stated in the Notice to Terminate; and

(f) The Head of the Procuring Entity may create a Contract Termination Review Committee (CTRC) to assist him in the discharge of this function. All decisions recommended by the CTRC shall be subject to the approval of the Head of the Procuring Entity.

19.2. Pursuant to Section 69(f) of RA 9184 and without prejudice to the imposition of additional administrative sanctions as the internal rules of the agency may provide and/or further criminal prosecution as provided by applicable laws, the procuring entity shall impose on contractors after the termination of the contract the penalty of suspension for one (1) year for the first offense, suspension for two (2) years for the second offense from participating in the public bidding process, for violations committed during the contract implementation stage, which include but not limited to the following:

(a) Failure of the contractor, due solely to his fault or negligence, to mobilize and start work or performance within the specified period in the Notice to Proceed (“NTP”);

(b) Failure by the contractor to fully and faithfully comply with its contractual obligations without valid cause, or failure by the contractor to comply with any written lawful instruction of the procuring entity or its representative(s) pursuant to the implementation of the contract. For the procurement of infrastructure projects or consultancy contracts, lawful instructions include but are not limited to the following:

(i) Employment of competent technical personnel, competent engineers and/or work supervisors;

(ii) Provision of warning signs and barricades in accordance with approved plans and specifications and contract provisions;

(iii) Stockpiling in proper places of all materials and removal from the project site of waste and excess materials, including broken pavement and excavated debris in accordance with approved plans and specifications and contract provisions;

(iv) Deployment of committed equipment, facilities, support staff and manpower; and

(v) Renewal of the effectivity dates of the performance security after its expiration during the course of contract implementation.

Page 56: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

56

(c) Assignment and subcontracting of the contract or any part thereof or substitution of key personnel named in the proposal without prior written approval by the procuring entity.

(d) Poor performance by the contractor or unsatisfactory quality and/or progress of work arising from his fault or negligence as reflected in the Constructor's Performance Evaluation System (“CPES”) rating sheet. In the absence of the CPES rating sheet, the existing performance monitoring system of the procuring entity shall be applied. Any of the following acts by the Contractor shall be construed as poor performance:

(i) Negative slippage of 15% and above within the critical path of the project due entirely to the fault or negligence of the contractor; and

(ii) Quality of materials and workmanship not complying with the approved specifications arising from the contractor's fault or negligence.

(e) Willful or deliberate abandonment or non-performance of the project or contract by the contractor resulting to substantial breach thereof without lawful and/or just cause.

In addition to the penalty of suspension, the performance security posted by the contractor shall also be forfeited.

20. Force Majeure, Release From Performance

20.1. For purposes of this Contract the terms “force majeure” and “fortuitous event” may be used interchangeably. In this regard, a fortuitous event or force majeure shall be interpreted to mean an event which the Contractor could not have foreseen, or which though foreseen, was inevitable. It shall not include ordinary unfavorable weather conditions; and any other cause the effects of which could have been avoided with the exercise of reasonable diligence by the Contractor.

20.2. If this Contract is discontinued by an outbreak of war or by any other event entirely outside the control of either the Procuring Entity or the Contractor, the Procuring Entity’s Representative shall certify that this Contract has been discontinued. The Contractor shall make the Site safe and stop work as quickly as possible after receiving this certificate and shall be paid for all works carried out before receiving it and for any Work carried out afterwards to which a commitment was made.

20.3. If the event continues for a period of eighty four (84) days, either party may then give notice of termination, which shall take effect twenty eight (28) days after the giving of the notice.

Page 57: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

57

20.4. After termination, the Contractor shall be entitled to payment of the unpaid balance of the value of the Works executed and of the materials and Plant reasonably delivered to the Site, adjusted by the following:

(a) any sum to which the Contractor is entitled under GCC Clause 27;

(b) the cost of his suspension and demobilization;

(c) any sum to which the Procuring Entity is entitled.

20.5. The net balance due shall be paid or repaid within a reasonable time period from the time of the notice of termination.

21. Resolution of Disputes

21.1. If any dispute or difference of any kind whatsoever shall arise between the parties in connection with the implementation of the contract covered by the Act and this IRR, the parties shall make every effort to resolve amicably such dispute or difference by mutual consultation.

21.2. If the Contractor believes that a decision taken by the PROCURING ENTITY’s Representative was either outside the authority given to the PROCURING ENTITY’s Representative by this Contract or that the decision was wrongly taken, the decision shall be referred to the Arbiter indicated in the SCC within fourteen (14) days of the notification of the PROCURING ENTITY’s Representative’s decision.

21.3. Any and all disputes arising from the implementation of this Contract covered by the R.A. 9184 and its IRR shall be submitted to arbitration in the Philippines according to the provisions of Republic Act No. 876, otherwise known as the “ Arbitration Law” and Republic Act 9285, otherwise known as the “Alternative Dispute Resolution Act of 2004”: Provided, however, That, disputes that are within the competence of the Construction Industry Arbitration Commission to resolve shall be referred thereto. The process of arbitration shall be incorporated as a provision in this Contract that will be executed pursuant to the provisions of the Act and its IRR: Provided, further, that, by mutual agreement, the parties may agree in writing to resort to other alternative modes of dispute resolution.

22. Suspension of Loan, Credit, Grant, or Appropriation

In the event that the Funding Source suspends the Loan, Credit, Grant, or Appropriation to the Procuring Entity, from which part of the payments to the Contractor are being made:

(a) The Procuring Entity is obligated to notify the Contractor of such suspension within seven (7) days of having received the suspension notice.

Page 58: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

58

(b) If the Contractor has not received sums due it for work already done within forty five (45) days from the time the Contractor’s claim for payment has been certified by the Procuring Entity’s Representative, the Contractor may immediately issue a suspension of work notice in accordance with GCC Clause 45.2.

23. Procuring Entity’s Representative’s Decisions

23.1. Except where otherwise specifically stated, the Procuring Entity’s Representative will decide contractual matters between the Procuring Entity and the Contractor in the role representing the Procuring Entity.

23.2. The Procuring Entity’s Representative may delegate any of his duties and responsibilities to other people, except to the Arbiter, after notifying the Contractor, and may cancel any delegation after notifying the Contractor.

24. Approval of Drawings and Temporary Works by the Procuring Entity’s Representative

24.1. All Drawings prepared by the Contractor for the execution of the Temporary Works, are subject to prior approval by the Procuring Entity’s Representative before its use.

24.2. The Contractor shall be responsible for design of Temporary Works.

24.3. The Procuring Entity’s Representative’s approval shall not alter the Contractor’s responsibility for design of the Temporary Works.

24.4. The Contractor shall obtain approval of third parties to the design of the Temporary Works, when required by the Procuring Entity.

25. Acceleration and Delays Ordered by the Procuring Entity’s Representative

25.1. When the Procuring Entity wants the Contractor to finish before the Intended Completion Date, the Procuring Entity’s Representative will obtain priced proposals for achieving the necessary acceleration from the Contractor. If the Procuring Entity accepts these proposals, the Intended Completion Date will be adjusted accordingly and confirmed by both the Procuring Entity and the Contractor.

25.2. If the Contractor’s Financial Proposals for an acceleration are accepted by the Procuring Entity, they are incorporated in the Contract Price and treated as a Variation.

26. Extension of the Intended Completion Date

26.1. The Procuring Entity’s Representative shall extend the Intended Completion Date if a Variation is issued which makes it impossible for the Intended Completion Date to be achieved by the Contractor without taking steps to accelerate the remaining work, which would cause the Contractor to incur additional costs. No payment shall be made for any event which may warrant the extension of the Intended Completion Date.

Page 59: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

59

26.2. The Procuring Entity’s Representative shall decide whether and by how much to extend the Intended Completion Date within twenty one (21) days of the Contractor asking the Procuring Entity’s Representative for a decision thereto after fully submitting all supporting information. If the Contractor has failed to give early warning of a delay or has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing the new Intended Completion Date.

27. Right to Vary

27.1. The Procuring Entity’s Representative with the prior approval of the Procuring Entity may instruct Variations, up to a maximum cumulative amount of ten percent (10%) of the original contract cost.

27.2. Variations shall be valued as follows:

(a) At a lump sum price agreed between the parties;

(b) where appropriate, at rates in this Contract;

(c) in the absence of appropriate rates, the rates in this Contract shall be used as the basis for valuation; or failing which

(d) at appropriate new rates, equal to or lower than current industry rates and to be agreed upon by both parties and approved by the Head of the Procuring Entity.

28. Contractor's Right to Claim

If the Contractor incurs cost as a result of any of the events under GCC Clause 12, the Contractor shall be entitled to the amount of such cost. If as a result of any of the said events, it is necessary to change the Works, this shall be dealt with as a Variation.

29. Dayworks

29.1. Subject to GCC Clause 43 on Variation Order, and if applicable as indicated in the SCC, the Dayworks rates in the Contractor’s Bid shall be used for small additional amounts of work only when the Procuring Entity’s Representative has given written instructions in advance for additional work to be paid for in that way.

29.2. All work to be paid for as Dayworks shall be recorded by the Contractor on forms approved by the Procuring Entity’s Representative. Each completed form shall be verified and signed by the Procuring Entity’s Representative within two days of the work being done.

29.3. The Contractor shall be paid for Dayworks subject to obtaining signed Dayworks forms.

30. Early Warning

Page 60: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

60

30.1. The Contractor shall warn the Procuring Entity’s Representative at the earliest opportunity of specific likely future events or circumstances that may adversely affect the quality of the work, increase the Contract Price, or delay the execution of the Works. The Procuring Entity’s Representative may require the Contractor to provide an estimate of the expected effect of the future event or circumstance on the Contract Price and Completion Date. The estimate shall be provided by the Contractor as soon as reasonably possible.

30.2. The Contractor shall cooperate with the Procuring Entity’s Representative in making and considering proposals for how the effect of such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying out any resulting instruction of the Procuring Entity’s Representative.

31. Program of Work

31.1. Within the time stated in the SCC, the Contractor shall submit to the Procuring Entity’s Representative for approval a Program of Work showing the general methods, arrangements, order, and timing for all the activities in the Works.

31.2. An update of the Program of Work shall show the actual progress achieved on each activity and the effect of the progress achieved on the timing of the remaining work, including any changes to the sequence of the activities.

31.3. The Contractor shall submit to the Procuring Entity’s Representative for approval an updated Program of Work at intervals no longer than the period stated in the SCC. If the Contractor does not submit an updated Program of Work within this period, the PROCURING ENTITY’s Representative may withhold the amount stated in the SCC from the next payment certificate and continue to withhold this amount until the next payment after the date on which the overdue Program of Work has been submitted.

31.4. The Procuring Entity’s Representative’s approval of the Program of Work shall not alter the Contractor’s obligations. The Contractor may revise the Program of Work and submit it to the Procuring Entity’s Representative again at any time. A revised Program of Work shall show the effect of any approved Variations.

31.5. When the Program of Work is updated, the Contractor shall provide the Procuring Entity’s Representative with an updated cash flow forecast. The cash flow forecast shall include different currencies, as defined in the Contract, converted as necessary using the Contract exchange rates.

31.6. All Variations shall be included in updated Program of Work produced by the Contractor.

Page 61: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

61

32. Management Conferences

32.1. Either the Procuring Entity’s Representative or the Contractor may require the other to attend a Management Conference. The Management Conference shall review the plans for remaining work and deal with matters raised in accordance with the early warning procedure.

32.2. The Procuring Entity’s Representative shall record the business of Management Conferences and provide copies of the record to those attending the Conference and to the Procuring Entity. The responsibility of the parties for actions to be taken shall be decided by the PROCURING ENTITY’s Representative either at the Management Conference or after the Management Conference and stated in writing to all who attended the Conference.

33. Bill of Quantities

33.1. The Bill of Quantities shall contain items of work for the construction, installation, testing, and commissioning of work to be done by the Contractor.

33.2. The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of the work done at the rate in the Bill of Quantities for each item.

33.3. If the final quantity of any work done differs from the quantity in the Bill of Quantities for the particular item and is not more than twenty five percent (25%) of the original quantity, provided the aggregate changes for all items do not exceed ten percent (10%) of the Contract price, the Procuring Entity’s Representative shall make the necessary adjustments to allow for the changes subject to applicable laws, rules, and regulations.

33.4. If requested by the Procuring Entity’s Representative, the Contractor shall provide the Procuring Entity’s Representative with a detailed cost breakdown of any rate in the Bill of Quantities.

34. Instructions, Inspections and Audits

34.1. The Procuring Entity’s personnel shall at all reasonable times during construction of the Work be entitled to examine, inspect, measure and test the materials and workmanship, and to check the progress of the construction.

34.2. If the Procuring Entity’s Representative instructs the Contractor to carry out a test not specified in the Specification to check whether any work has a defect and the test shows that it does, the Contractor shall pay for the test and any samples. If there is no defect, the test shall be a Compensation Event.

34.3. The Contractor shall permit the Funding Source named in the SCC to inspect the Contractor’s accounts and records relating to the performance of the Contractor and to have them audited by auditors appointed by the Funding Source, if so required by the Funding Source.

35. Identifying Defects

Page 62: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

62

The Procuring Entity’s Representative shall check the Contractor’s work and notify the Contractor of any defects that are found. Such checking shall not affect the Contractor’s responsibilities. The Procuring Entity’s Representative may instruct the Contractor to search uncover defects and test any work that the Procuring Entity’s Representative considers below standards and defective.

36. Cost of Repairs

Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and the end of the Defects Liability Periods shall be remedied by the Contractor at the Contractor’s cost if the loss or damage arises from the Contractor’s acts or omissions.

37. Correction of Defects

37.1. The Procuring Entity’s Representative shall give notice to the Contractor of any defects before the end of the Defects Liability Period, which is One (1) year from project completion up to final acceptance by the Procuring Entity’s.

37.2. Every time notice of a defect is given, the Contractor shall correct the notified defect within the length of time specified in the Procuring Entity’s Representative’s notice.

37.3. The Contractor shall correct the defects which he notices himself before the end of the Defects Liability Period.

37.4. The Procuring Entity shall certify that all defects have been corrected. If the Procuring Entity considers that correction of a defect is not essential, he can request the Contractor to submit a quotation for the corresponding reduction in the Contract Price. If the Procuring Entity accepts the quotation, the corresponding change in the SCC is a Variation.

38. Uncorrected Defects

38.1. The Procuring Entity shall give the Contractor at least fourteen (14) days notice of his intention to use a third party to correct a Defect. If the Contractor does not correct the Defect himself within the period, the Procuring Entity may have the Defect corrected by the third party. The cost of the correction will be deducted from the Contract Price.

38.2. The use of a third party to correct defects that are uncorrected by the Contractor will in no way relieve the Contractor of its liabilities and warranties under the Contract.

39. Advance Payment

39.1. The Procuring Entity shall, upon a written request of the contractor which shall be submitted as a contract document, make an advance payment to the contractor in an amount not exceeding fifteen percent (15%) of the total contract price, to be made in lump sum or, at the most two, installments according to a schedule specified in the SCC.

Page 63: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

63

39.2. The advance payment shall be made only upon the submission to and acceptance by the Procuring Entity of an irrevocable standby letter of credit of equivalent value from a commercial bank, a bank guarantee or a surety bond callable upon demand, issued by a surety or insurance company duly licensed by the Insurance Commission and confirmed by the Procuring Entity.

39.3. The advance payment shall be repaid by the Contractor by an amount equal to the percentage of the total contract price used for the advance payment.

39.4. The contractor may reduce his standby letter of credit or guarantee instrument by the amounts refunded by the Monthly Certificates in the advance payment.

39.5. The Procuring Entity will provide an Advance Payment on the Contract Price as stipulated in the Conditions of Contract, subject to the maximum amount stated in SCC Clause 39.1.

40. Progress Payments

40.1. The Contractor may submit a request for payment for Work accomplished. Such request for payment shall be verified and certified by the Procuring Entity’s Representative/Project Engineer. Except as otherwise stipulated in the SCC, materials and equipment delivered on the site but not completely put in place shall not be included for payment.

40.2. The Procuring Entity shall deduct the following from the certified gross amounts to be paid to the contractor as progress payment:

(a) Cumulative value of the work previously certified and paid for.

(b) Portion of the advance payment to be recouped for the month.

(c) Retention money in accordance with the condition of contract.

(d) Amount to cover third party liabilities.

(e) Amount to cover uncorrected discovered defects in the works.

40.3. Payments shall be adjusted by deducting therefrom the amounts for advance payments and retention. The Procuring Entity shall pay the Contractor the amounts certified by the Procuring Entity’s Representative within twenty eight (28) days from the date each certificate was issued. No payment of interest for delayed payments and adjustments shall be made by the Procuring Entity.

40.4. The first progress payment may be paid by the Procuring Entity to the Contractor provided that at least twenty percent (20%) of the work has been accomplished as certified by the Procuring Entity’s Representative.

Page 64: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

64

40.5. Items of the Works for which a price of “0” (zero) has been entered will not be paid for by the Procuring Entity and shall be deemed covered by other rates and prices in the Contract.

41. Payment Certificates

41.1. The Contractor shall submit to the Procuring Entity’s Representative monthly statements of the estimated value of the work executed less the cumulative amount certified previously.

41.2. The Procuring Entity’s Representative shall check the Contractor’s monthly statement and certify the amount to be paid to the Contractor.

41.3. The value of Work executed shall:

(a) be determined by the Procuring Entity’s Representative;

(b) comprise the value of the quantities of the items in the Bill of Quantities completed; and

(c) include the valuations of approved variations.

41.4. The Procuring Entity’s Representative may exclude any item certified in a previous certificate or reduce the proportion of any item previously certified in any certificate in the light of later information.

42. Retention

42.1. The Procuring Entity shall retain from each payment due to the Contractor an amount equal to a percentage thereof using the rate as specified in ITB Sub-Clause 42.2.

42.2. Progress payments are subject to retention of ten percent (10%), referred to as the “retention money.” Such retention shall be based on the total amount due to the Contractor prior to any deduction and shall be retained from every progress payment until fifty percent (50%) of the value of Works, as determined by the Procuring Entity, are completed. If, after fifty percent (50%) completion, the Work is satisfactorily done and on schedule, no additional retention shall be made; otherwise, the ten percent (10%) retention shall again be imposed using the rate specified therefor.

42.3. The total “retention money” shall be due for release upon final acceptance of the Works. The Contractor may, however, request the substitution of the retention money for each progress billing with irrevocable standby letters of credit from a commercial bank, bank guarantees or surety bonds callable on demand, of amounts equivalent to the retention money substituted for and acceptable to the Procuring Entity, provided that the project is on schedule and is satisfactorily undertaken. Otherwise, the ten (10%) percent retention shall be made. Said irrevocable standby letters of credit, bank guarantees and/or surety bonds, to be posted in favor of the Government shall be valid for a duration to be determined by the concerned implementing office/agency or Procuring Entity and will answer for the purpose for which the ten (10%)

Page 65: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

65

percent retention is intended, i.e., to cover uncorrected discovered defects and third party liabilities.

42.4. On completion of the whole Works, the Contractor may substitute retention money with an “on demand” Bank guarantee in a form acceptable to the Procuring Entity.

43. Variation Orders

43.1. Variation Orders may be issued by the Procuring Entity to cover any increase/decrease in quantities, including the introduction of new work items that are not included in the original contract or reclassification of work items that are either due to change of plans, design or alignment to suit actual field conditions resulting in disparity between the preconstruction plans used for purposes of bidding and the “as staked plans” or construction drawings prepared after a joint survey by the Contractor and the Procuring Entity after award of the contract, provided that the cumulative amount of the Variation Order does not exceed ten percent (10%) of the original project cost. The addition/deletion of Works should be within the general scope of the project as bid and awarded. The scope of works shall not be reduced so as to accommodate a positive Variation Order. A Variation Order may either be in the form of a Change Order or Extra Work Order.

43.2. A Change Order may be issued by the Procuring Entity to cover any increase/decrease in quantities of original Work items in the contract.

43.3. An Extra Work Order may be issued by the Procuring Entity to cover the introduction of new work necessary for the completion, improvement or protection of the project which were not included as items of Work in the original contract, such as, where there are subsurface or latent physical conditions at the site differing materially from those indicated in the contract, or where there are duly unknown physical conditions at the site of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in the Work or character provided for in the contract.

43.4. Any cumulative Variation Order beyond ten percent (10%) shall be subject of another contract to be bid out if the works are separable from the original contract. In exceptional cases where it is urgently necessary to complete the original scope of work, the Head of the Procuring Entity may authorize a positive Variation Order go beyond ten percent (10%) but not more than twenty percent (20%) of the original contract price, subject to the guidelines to be determined by the GPPB: Provided, however, That appropriate sanctions shall be imposed on the designer, consultant or official responsible for the original detailed engineering design which failed to consider the Variation Order beyond ten percent (10%).

43.5. In claiming for any Variation Order, the Contractor shall, within seven (7) calendar days after such work has been commenced or after the circumstances leading to such condition(s) leading to the extra cost, and within twenty-eight (28) calendar days deliver a written communication giving full and detailed particulars of any extra cost in order that it may be investigated at that time.

Page 66: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

66

Failure to provide either of such notices in the time stipulated shall constitute a waiver by the contractor for any claim. The preparation and submission of Variation Orders are as follows:

(a) If the Procuring Entity’s representative/Project Engineer believes that a Change Order or Extra Work Order should be issued, he shall prepare the proposed Order accompanied with the notices submitted by the Contractor, the plans therefore, his computations as to the quantities of the additional works involved per item indicating the specific stations where such works are needed, the date of his inspections and investigations thereon, and the log book thereof, and a detailed estimate of the unit cost of such items of work, together with his justifications for the need of such Change Order or Extra Work Order, and shall submit the same to the Head of the Procuring Entity for approval.

(b) The Head of the Procuring Entity or his duly authorized representative, upon receipt of the proposed Change Order or Extra Work Order shall immediately instruct the technical staff of the Procuring Entity’s to conduct an on-the-spot investigation to verify the need for the Work to be prosecuted. A report of such verification shall be submitted directly to the Head of the Procuring Entity or his duly authorized representative.

(c) The, Head of the Procuring Entity or his duly authorized representative, after being satisfied that such Change Order or Extra Work Order is justified and necessary, shall review the estimated quantities and prices and forward the proposal with the supporting documentation to the Head of Procuring Entity for consideration.

(d) If, after review of the plans, quantities and estimated unit cost of the items of work involved, the proper office of the procuring entity empowered to review and evaluate Change Orders or Extra Work Orders recommends approval thereof, Head of the Procuring Entity or his duly authorized representative, believing the Change Order or Extra Work Order to be in order, shall approve the same.

(e) The timeframe for the processing of Variation Orders from the preparation up to the approval by the Head of the Procuring Entity concerned shall not exceed thirty (30) calendar days.

44. Contract Completion

Once the project reaches an accomplishment of ninety five (95%) of the total contract amount, the Procuring Entity may create an inspectorate team to make preliminary inspection and submit a punch-list to the Contractor in preparation for the final turnover of the project. Said punch-list will contain, among others, the remaining Works, Work deficiencies for necessary corrections, and the specific duration/time to fully complete the project considering the approved remaining contract time. This, however, shall not preclude the claim of the Procuring Entity for liquidated damages.

Page 67: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

67

45. Suspension of Work

45.1. The Procuring Entity shall have the authority to suspend the work wholly or partly by written order for such period as may be deemed necessary, due to force majeure or any fortuitous events or for failure on the part of the Contractor to correct bad conditions which are unsafe for workers or for the general public, to carry out valid orders given by the Procuring Entity or to perform any provisions of the contract, or due to adjustment of plans to suit field conditions as found necessary during construction. The Contractor shall immediately comply with such order to suspend the work wholly or partly.

45.2. The Contractor or its duly authorized representative shall have the right to suspend work operation on any or all projects/activities along the critical path of activities after fifteen (15) calendar days from date of receipt of written notice from the Contractor to the district engineer/regional director/consultant or equivalent official, as the case may be, due to the following:

(a) There exist right-of-way problems which prohibit the Contractor from performing work in accordance with the approved construction schedule.

(b) Requisite construction plans which must be owner-furnished are not issued to the contractor precluding any work called for by such plans.

(c) Peace and order conditions make it extremely dangerous, if not possible, to work. However, this condition must be certified in writing by the Philippine National Police (PNP) station which has responsibility over the affected area and confirmed by the Department of Interior and Local Government (DILG) Regional Director.

(d) There is failure on the part of the Procuring Entity to deliver government-furnished materials and equipment as stipulated in the contract.

(e) Delay in the payment of Contractor’s claim for progress billing beyond forty-five (45) calendar days from the time the Contractor’s claim has been certified to by the procuring entity’s authorized representative that the documents are complete unless there are justifiable reasons thereof which shall be communicated in writing to the Contractor.

45.3. In case of total suspension, or suspension of activities along the critical path, which is not due to any fault of the Contractor, the elapsed time between the effective order of suspending operation and the order to resume work shall be allowed the Contractor by adjusting the contract time accordingly.

46. Payment on Termination

46.1. If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the Procuring Entity’s Representative shall issue a certificate for the value of the work done and Materials ordered less advance payments received up to the date of the issue of the certificate and less the percentage to

Page 68: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

68

apply to the value of the work not completed, as indicated in the SCC. Additional Liquidated Damages shall not apply. If the total amount due to the Procuring Entity exceeds any payment due to the Contractor, the difference shall be a debt payable to the Procuring Entity.

46.2. If the Contract is terminated for the Procuring Entity’s convenience or because of a fundamental breach of Contract by the Procuring Entity, the Procuring Entity’s Representative shall issue a certificate for the value of the work done, Materials ordered, the reasonable cost of removal of Equipment, repatriation of the Contractor’s personnel employed solely on the Works, and the Contractor’s costs of protecting and securing the Works, and less advance payments received up to the date of the certificate.

46.3. The net balance due shall be paid or repaid within twenty eight (28) days from the notice of termination.

46.4. If the Contractor has terminated the Contract under GCC Clauses 17 or 16.5, the Procuring Entity shall promptly return the Performance Security to the Contractor.

47. Extension of Contract Time

47.1. Should the amount of additional work of any kind or other special circumstances of any kind whatsoever occur such as to fairly entitle the contractor to an extension of contract time, the Procuring Entity shall determine the amount of such extension; provided that the Procuring Entity is not bound to take into account any claim for an extension of time unless the Contractor has, prior to the expiration of the contract time and within thirty (30) calendar days after such work has been commenced or after the circumstances leading to such claim have arisen, delivered to the Procuring Entity notices in order that it could have investigated them at that time. Failure to provide such notice shall constitute a waiver by the Contractor of any claim. Upon receipt of full and detailed particulars, the Procuring Entity shall examine the facts and extent of the delay and shall extend the contract time completing the contract work when, in the Procuring Entity’s opinion, the findings of facts justify an extension.

47.2. No extension of contract time shall be granted the Contractor due to (a) ordinary unfavorable weather conditions and (b) inexcusable failure or negligence of Contractor to provide the required equipment, supplies or materials.

47.3. Extension of contract time may be granted only when the affected activities fall within the critical path of the PERT/CPM network.

47.4. No extension of contract time shall be granted when the reason given to support the request for extension was already considered in the determination of the original contract time during the conduct of detailed engineering and in

Page 69: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

69

the preparation of the contract documents as agreed upon by the parties before contract perfection.

47.5. Extension of contract time shall be granted for rainy/unworkable days considered unfavorable for the prosecution of the works at the site, based on the actual conditions obtained at the site, in excess of the number of rainy/unworkable days pre-determined by the Procuring Entity in relation to the original contract time during the conduct of detailed engineering and in the preparation of the contract documents as agreed upon by the parties before contract perfection, and/or for equivalent period of delay due to major calamities such as exceptionally destructive typhoons, floods and earthquakes, and epidemics, and for causes such as non-delivery on time of materials, working drawings, or written information to be furnished by the Procuring Entity, non-acquisition of permit to enter private properties within the right-of-way resulting in complete paralyzation of construction activities, and other meritorious causes as determined by the Procuring Entity’s Representative and approved by the Head of the Procuring Entity. Shortage of construction materials, general labor strikes, and peace and order problems that disrupt construction operations through no fault of the Contractor may be considered as additional grounds for extension of contract time provided they are publicly felt and certified by appropriate government agencies such as DTI, DOLE, DILG, and DND, among others. The written consent of bondsmen must be attached to any request of the Contractor for extension of contract time and submitted to the Procuring Entity for consideration and the validity of the Performance Security shall be correspondingly extended.

48. Price Adjustment

Except for extraordinary circumstances as determined by NEDA and approved by the GPPB, no price adjustment shall be allowed. Nevertheless, in cases where the cost of the awarded contract is affected by any applicable new laws, ordinances, regulations, or other acts of the GOP, promulgated after the date of bid opening, a contract price adjustment shall be made or appropriate relief shall be applied on a no loss-no gain basis.

49. Completion

The Contractor shall request the Procuring Entity’s Representative to issue a certificate of Completion of the Works, and the Procuring Entity’s Representative will do so upon deciding that the work is completed.

50. Taking Over

The Procuring Entity shall take over the Site and the Works within seven (7) days from the date the Procuring Entity’s Representative issues a certificate of Completion.

51. Operating and Maintenance Manuals

51.1. If “as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall supply them by the dates stated in the SCC.

Page 70: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

70

If the Contractor does not supply the Drawings and/or manuals by the dates stated in the SCC, or they do not receive the Procuring Entity’s Representative’s approval, the Procuring Entity’s Representative shall withhold the amount stated in the SCC from payments due to the Contractor.

Page 71: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

71

Section V. Special Conditions of Contract

Page 72: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

72

Special Conditions of Contract

GCC Clause

1.16 The Intended Completion Date is Two Hundred Forty (240) calendar days.

1.21 The Procuring Entity is the Department of Transportation and Communications (DOTC).

1.22 The Procuring Entity’s Representative is the DOTC Project Manager concerned.

1.23 The Site is located at Brgy. Magsidel, Calayan, Cagayan.

1.27 The Start Date is the 7th calendar day after the date of the receipt of the Notice to Proceed.

1.30 The Works consist of Construction of Rock Causeway and R.C. Pier.

2.2 No further instructions.

5.1 The DOTC shall give possession of all parts of the Site to the Contractor beginning on the date of effectivity of contract until the date of its termination and/or project completion.

6.5 The Contractor shall employ the following Key Personnel:

Project Manager Civil Engineer (licensed) 1 Materials Engineer (accredited by DPWH) 1 Safety Officer

7.4(c) No further instructions.

7.7 No further instructions.

8.1 No further instructions.

10 The site investigation reports are: Not Applicable.

12.3 No further instructions.

12.5 In case of permanent structures, such as buildings of types 4 and 5 as classified under the National Building Code of the Philippines and other structures made of steel, iron, or concrete which comply with relevant structural codes (e.g., DPWH Standard Specifications), such as, but not limited to, steel/concrete bridges, flyovers, aircraft movement areas, ports, dams, tunnels, filtration and treatment plants, sewerage systems, power plants, transmission and communication towers, railway system, and other similar permanent structures: Fifteen (15) years.

Page 73: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

73

In case of semi-permanent structures, such as buildings of types 1, 2, and 3 as classified under the National Building Code of the Philippines, concrete/asphalt roads, concrete river control, drainage, irrigation lined canals, river landing, deep wells, rock causeway, pedestrian overpass, and other similar semi-permanent structures: Five (5) years.

In case of other structures, such as Bailey and wooden bridges, shallow wells, spring developments, and other similar structures: Two (2) years.

12 If the Contractor is a joint venture, “All partners to the joint venture shall be jointly and severally liable to the Procuring Entity.”

15 Contractor’s All Risk Insurance (CARI)

Shall be submitted by the contractor as part of the requirements for contract facilitation.

18.3(h)(i) No further instructions.

21.2 The Arbiter is: Construction Industry Arbitration Commission

5th Floor, Executive Building Corner Buendia, Makati City

29.1 Dayworks are applicable at the rate shown in the Contractor’s original Bid.

31.1 The Contractor shall submit the Program of Work to the Procuring Entity’s Representative (DOTC Project Manager concerned) within 10

days of delivery of the Letter of Acceptance.

31.3 The period between Program of Work updates is 7 to 15 days.

The amount to be withheld for late submission of an updated Program of Work is 5% of the contract amount.

34.3 The Funding Source is the Government of the Philippines.

39.1 The amount of the advance payment is 15% of the contract amount.

40.1 No further instructions.

51.1 The date by which operating and maintenance manuals are required is [N/A].

The date by which “as built” drawings are required is 15 days after project completion.

51.2 The amount to be withheld for failing to produce “as built” drawings and/or operating and maintenance manuals by the date required is 5% of the contract amount.

Page 74: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

74

Section VI. Specifications

Page 75: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

75

Name of Project : CALAYAN PORT DEVELOPMENT PROJECT Location : Brgy. Magsidel, Calayan, Cagayan Duration : TWO HUNDRED FORTY (240) CALENDAR DAYS Source of Fund : CY 2013

SCOPE OF WORK

The project covers the Construction of Rock Causeway and R.C. Pier which shall be done in accordance with the approved plans, specifications and provisions of contract under the following scope of works, to wit; ITEM 701a. Corestones (10-50kg./pc). This item covers the supply of materials, labor and

equipment necessary for the completion of Corestones for the construction of rock causeway and shall be done in accordance with the approved plans and design grade. (Pls. refer to plans)

ITEM 701b. Secondary Rocks (80-100 kg./pc). This item covers the supply of materials, labor and

equipment necessary for the completion of Secondary Rocks for the construction of rock causeway and shall be done in accordance with the approved plans and design grade. (Pls. refer to plans)

ITEM 701c. Armor Rocks (1.0 -1.5 ton/pc). This item covers the supply of materials, labor and

equipment necessary for the completion of Armor Rocks for the construction of rock causeway and shall be done in accordance with the approved plans and design grade. (Pls. refer to plans)

ITEM 405a. Concrete Works (3000psi). This item covers the supply of materials, labor and

equipment necessary for the construction of wave deflector, concrete curb, concrete blocks and concrete stair landing with a minimum concrete strength of 3000psi. All works shall be done in accordance with the approved plans and specifications. (Pls. refer to plans)

ITEM 405b. Reinforcing Steel Bars. This item covers the supply of materials, labor and

equipment necessary for the fabrication and installation of steel bars for item 405a. (Concrete Works). All works shall be done in accordance with the approved plans and specifications. (Pls. refer to plans)

ITEM 405c. Mooring Ring. This item covers the supply of materials, labor and equipment

necessary in the fabrication and installation of 7-sets, 16mm. Ø stainless steel mooring ring. (Refer to plans)

ITEM 201 Aggregate Base Course (0.25m. thick.). This item covers the laying of 0.25 m. thick

aggregate base course and should be spread and compacted prior to the pouring of Portland Cement Concrete Pavement and shall be done in accordance with the approved plans and specifications. (Pls. refer to plans)

ITEM 307 Portland Cement Concrete Pavement (0.25 m. thick). This item covers the supply of

materials, labor and equipment necessary in laying 0.25 m. thick concrete pavement along the rock causeway. The design strength of the concrete pavement shall be

Page 76: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

76

3500 psi. Supply, fabrication and installation of reinforcing bars, formworks, curing compound and asphalt sealant are included under this item. (Pls. refer to plans)

ITEM I Pre-Stressed Concrete Square Piles. This covers the supply of materials, labor and equipment Necessary for the construction of 49 pieces - 24.0 m. long reinforced concrete square piles for the Proposed R.C. Pier. The required compressive strength shall be 5000 psi/35Mpa. Provision of reinforcing steel bars and formworks shall be included under this item. (Pls. refer to plans) II(a) Vertical Pile Driving. This item covers the supply of materials, labor and equipment necessary for driving 21 pieces - 24.0 m. long reinforced concrete square piles and shall be driven down to desired elevation. (Pls. refer to plans) II(b) Batter Pile Driving. This item covers the supply of materials, labor and equipment necessary for driving 26 pieces – 24.0 m. long reinforced concrete square piles and shall be driven down to desired elevation. (Pls. refer to plans) III Test Pile Driving. This item covers the supply of materials and equipment necessary for driving 2 pieces – 24.0 m. long reinforced concrete square piles and shall be driven down to desired elevation. (Pls. refer to plans) IV Concrete Works (5000 psi). This item covers the supply of materials, labor and equipment necessary for the construction of concrete slab, beams, pile caps and concrete curb with a concrete strength of 5000 psi/35 MPa. All works shall be done in accordance with the approved plans and specifications. Provision of formworks shall be included under this item. (Pls. refer to plans) V Reinforcing Steel Bars. This item covers the supply of materials, labor and

equipment necessary for the fabrication and installation of steel bars for item IV (Concrete Works). All works shall be done in accordance with the approved plans and specifications. (Pls. refer to plans)

VI Mooring Bollard. This item covers the supply of materials, labor and equipment necessary in the installation of 3 – mooring bollard with complete accessories. All works shall be done in accordance with the approved plans and specifications. (Pls. refer to plans) VII Rubber Fender. This item covers the supply of materials, labor and equipment

necessary in the installation of 5 – pieces rubber fender with complete accessories. All works shall be done in accordance with the approved plans and specifications. (Pls. refer to plans)

SPL-1 Temporary Facilities The contractor shall supply the following provisions within ten (10) days upon receipt of the Notice to Proceed (NTP) A. STAFF HOUSE This covers the rental of a fully furnished staff house for the exclusive use of the

Project Engineer. Payment of water and electric bill shall be the responsibility of the contractor for the entire duration of the project.

Page 77: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

77

B. SERVICE VEHICLE This covers the provision of service vehicle of at least 2009 model, in good running

condition and updated registration on a rental basis including driver and twelve (12) liters of fuel per day for the exclusive use of the DOTC Engineer supervising the project for one hundred fifty (150) Calendar Days.

The contractor shall be responsible for all laboratory, material testing and survey instruments necessary in the project implementation. Expenses for the said testing shall be incorporated in the contractor’s overhead cost and shall not be considered as pay item.

Page 78: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

78

ITEM 701 - ROCK WORKS

701.1 - SCOPE OF WORK This specification covers rockworks and the construction of the rock causeway. The works to be carried out shall be, but not limited to the following: 1. Supply and laying of the core stones bedding. 2. Supply and laying of the Armor Stones (1st layer). 3. Supply and laying of the Armor Stones (2nd layer). 4. Placement of concrete curb 5. Construction of concrete pavement. 701.2 - SETTING OUT WORKS 1. Topographic/Hydrographic Survey: Prior to commencement of the work, the Contractor shall conduct a topographic/hydrographic survey in conjunction with the "Engineer's" instructions. This Survey shall form the basis for quantity measurement. 2. The Contractor shall set out works and be solely responsible for accuracy of such setting out. 701.3 - MATERIALS

1. Concrete for curb shall be in accordance with the provisions of Item 405, Concrete Works, using fc" = 21 Mpa. 2. Concrete works for pavement shall be in accordance with Item 501 - Portland Cement Concrete Pavement. 3. All rocks to be used shall be angular, hard, durable with the long dimension not more than three times the short. It shall not likely to disintegrate in sea water and if subjected to five (5) cycles of the sodium sulfate soundness test, the weighted loss shall not exceed 12 mass percent. 4. All rocks shall have a minimum weight of 1000 kgs. per cubic meter (specific gravity 2.6) of solid materials when measured dry.

Page 79: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

79

5. Rocks with specific gravity higher than the above specified is preferable and will readily be accepted. But no adjustment (increase) in the contract price will be made on this account. 6. Rocks that are sub-angular may be subject to the approval of the Engineer. Rounded or well rounded pieces will not be accepted. 7. Rocks of the primary cover layer should be sound, durable and hard. It should be free from laminations, weak cleavages, and undesirable weathering, and should be of such character that it will not disintegrate from the action of the air, sea-water, or in handling and placing. All stone should be angular quarry stone. 8. The greatest dimensions of individual rock unit should not be greater than three times the least dimension. 9. All rocks should conform to the following test designations : Apparent specific gravity, ASTM C-127 and abrasion, ASTM C-131. 10. The weight of the individual pieces of rocks may exceed the minimum in the table below by thirty three (33%) percent but not less than the weight specified hereunder.

1) Armor Stones Ist layer .................... 1 ton/pc. 2nd layer .................... 50 to 100 kg/pc 2) Core Stones .................. 1 to 30 kg/pc. Corestone bedding shall be reasonably well graded in weight between the minimum and

maximum sizes. 701.4 - CONSTRUCTION METHOD

1. Construction method of concrete pavement shall be in accordance with the provisions of Item 501- Portland Cement Concrete Pavement. 2. The core stone shall be placed at convenient height and width for each delivery of materials. 3. The armor stone shall cover the sides, berm and top of the causeway for core stone protection. 4. The armor stone filler shall not be less than one half (1/2) of the weight and size of the armor stone. 5. The armor stone shall be placed with the longitudinal section perpendicular to the slope and longitudinal section of the causeway. 6. No cutting, spalling or coursing of the stones shall be allowed, but it is expected that the work shall be done in a workmanlike and skilled manner, which implies careful selection of stones.

Page 80: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

80

7. The armor stone filler rock shall be wedded firmly in between the facing of armor rocks so that the latter shall be in the stable position. 8. Armor stones shall be placed individually by crane equipped with suitable bucket or by other means acceptable to the Engineer. 9. The rock mole/rock causeway can be constructed by any method acceptable to the Engineer. Prior to the start of work, the Contractor shall submit to the Engineer for approval his method and sequence of construction. The Engineer's approval of the method and sequence of construction shall not release the Contractor from responsibility to achieve the satisfactory implementation of the work. 10. Permissible Tolerance a) Core Stones Alignment : plus or minus 0.30 m Elevation : plus or minus 0.30 m b) Armor Stones Alignment : plus or minus 0.30 m Elevation : plus or minus 0.20 m

Page 81: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

81

ITEM 201 – AGGREGATE BASE COURSE

201.1 DESCRIPTION This item shall consist of base course composed of crushed, partially crushed or uncrushed coarse aggregate bonded with either soil or fine aggregate. Or both spreading and compacting crushed aggregate base material of crushed gravel, crushed stone or crushed rock constructed on a prepared sub-grade or sub-base in one or more layers in accordance with the specifications. And shall conform to the dimensions and typical cross section shown on the plans and with the lines and grades established by the Engineer. Crushed aggregate base materials shall be Class A, Class B, or Class C as shown on the plans. When crushed aggregate base course is required to be placed on a sub-grade consisting of an existing cement concrete pavement prepared in accordance with Item 106 “Sub-grade Preparation” and where the surface levels of the resulting sub-grade level are outside the permitted tolerances in Table 106-A of Item 106 leveling course of crushed aggregate base material shall be laid as shown on the plans. 201.2 MATERIAL REQUIREMENTS Material for crushed aggregate base course shall consist of crushed or partly crushed hard durable gravel stone or rock fragments. It shall be clean and free from organic matters, lumps of clay and other deleterious substances. The material shall be of such a nature that it can be compacted readily under watering and rolling to form a firm, stable base. The aggregates shall consist of both fine and coarse fragments of crushed stones, crushed slab or crushed gravel mixed or blended with sand, screening, or other materials conforming to the grading requirements of Table 201-A. The crushed stone shall consist of hard, durable particles or fragments of stone and shall be free from excess flat, elongated, soft or disintegrated pieces, dirt or other objectionable matter. The material shall comply with the following grading and quality requirements; a. The aggregate when graded shall produce a smooth, evenly distributed curve within the limits

for Class A, Class B, or Class C given in Table 201-A.

TABLE 201-A – AGGREGATE BASE COURSE GRADING

US STANDARD SIEVE PERCENT PASSING BY WEIGHT

mm Alternate Class A Class B Class C

50.00 2” 100 100 -

37.50 1 ½” 80 – 100 80 – 100 -

25.00 1” 60 – 100 60 –100 100

19.00 ¾” 50 – 85 55 – 85 75 – 100

4.75 No. 04 25 - 45 35 – 60 40 – 60

2.00 No. 10 15 – 35 25 – 50 25 – 45

0.425 No. 40 8 – 22 15 – 30 12 – 25

0.075 No. 200 2 – 9 8 –15 5 – 12

Page 82: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

82

b. The course aggregate material retained on a 4.75mm (No. 4) sieve shall consist of material of

which not less than 50% by weight shall be crushed particles, having a minimum of one fractured face.

c. The course aggregate retained on a 4.75mm (No.4) sieve shall have a percentage of wear by the

Los Angeles Abrasion Test AASHTO T96 of not more than 40% for crushed and 50% for uncrushed.

d. The material shall have a loss of less than 12% when subject to five cycles of sodium sulfate

soundness test according to AASHTO T104. e. The sand equivalent determined according to AASHTO T176 should not be less than 50. f. The material passing the 19mm (3/4”) sieve shall have a minimum soak CBR value of 80% tested

according to AASHTO T 193. The CBR value shall be obtained at the maximum dry density determined according to AASHTO T 180.

The portion of material passing the 0.425mm (No. 40) sieve shall have a liquid limit of not more than 25 and a plasticity Index of not more than 6 as determined by AASHTO T89 and 90 respectively. The crushed slab shall be air-cooled, blast furnace slag and shall consist of angular fragment reasonably clean and free of thin, elongated or soft pieces, dirt or other objectionable matter. It shall weigh not less than 1120 kilogram per cubic meter as determined by AASHTO T19. The method used in the production of crushed gravel shall be such that the fractured particles occurring in the finished product shall be as nearly constant and uniform as practicable and shall result in at least the specified percentage of material retained on a No. 4 mesh sieve having one or more fractured faces. If necessary, to meet his requirements or to eliminate and excess of fine uncrushed particles, the gravel shall be screened before crushing. All stone, rocks and boulders of inferior quality in the pit shall be wasted. All material passing the No. 4 mesh sieve produced in the crushing operation of either stone, slag or gravel shall be incorporated in the base material to the extent permitted by the gradation requirements. The final gradation decided on within the limits designated in the table shall be well graded from coarse to fine and shall not vary from the low limit on one sieve to the high on the adjacent sieves, or vice versa. The amount of the fraction of material passing the No. 200 mesh sieve shall not exceed one-half the fraction passing the No. 40 mesh sieve. The selection of any gradation shown in Table 155-A shall be such that the maximum size aggregate used in any course shall be not more than two-thirds the thickness of the layer of the course being constructed. 201.2.1 FILLER FOR BLENDING

Page 83: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

83

The filler in addition to the naturally present in the base course material, is necessary for satisfactory bonding of the material, for changing the soil constant of the material passing the No. 40 mesh sieve or for correcting the gradation to the limitations of the specified gradation, it shall be uniformly blended with the base course material at the crushing plant or at the mixing plant. The material for such purpose shall be obtain from sources approved by the Engineer and shall be of the specified gradation. The additional filler may be composed of sand but the amount of sand shall not exceed 20% by weight of the total combined base aggregate. All sand shall pass a No. 4 mesh sieve and not more than 5% by weight shall pass a No. 200 mesh sieve. 201.3 CONSTRUCTION METHODS 201.3.1 OPERATION IN PITS AND QUARRIES All works involved in cleaning and the Contractor shall perform stripping pits and quarries, including handling of unsuitable materials. All material shall be handled in a manner that shall secure a uniform and satisfactory base product. The base course material shall be obtained from approved sources. 201.3.2 EQUIPMENT All equipment necessary for the proper construction on this work shall be available at the project site, in first class working condition, and approved by the Engineer before construction is permitted to start. 201.3.3 PREPARING UNDERLYING COURSE The underlying course shall be checked and accepted by the Engineer before placing and spreading operations are started. Any ruts or soft, yielding places due to improper drainage conditions, hauling or any other cause, shall be corrected and rolled to the required density before the base course is placed thereon. Grade control between the edges of the pavement shall be accomplished by graded stakes, steel pins, or forms placed in lanes parallel to the centerline of the pavement at intervals sufficiently close at string line or check boards may be placed between the stakes, pins or forms. 201.3.4 METHODS OF PRODUCTION a. PLANT MIX. When provided in the proposal, or when selected by the contractor and approved

by the Engineer, the base material shall be uniformly blended or mixed in an approved plant. The mixing plant shall include bins for storage and batching of the aggregates, pumps and tanks for water, and batch mirror of either pugmill or drum type. All mineral aggregates shall be batch into the mixer by weight. The agitation shall be such that a thorough dispersion of moisture is obtained. The Engineer shall fix the size of the batch at time of mixing. The base course material produced by combining two or more materials from different sources shall be mixed in a mixing plant described herein. The mixture material shall be at satisfactory moisture content to obtain maximum density.

Page 84: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

84

b. TRAVEL PLANT. When the use of travelling plant is allowed, the plant shall blend and mix the materials to meet these specifications. It shall accomplish a thorough mixing in one trip. The agitation shall be such that the dispersion of the moisture is complete. The machine shall move at uniform rate of speed and this speed shall be regulated to fix the mixing time. If a window-type travel plant is employed for mixing, the aggregate shall be placed in windrows parallel to the pavement centerline.

The windrow volume shall be sufficient to cover exact areas as planned. The windrow contents shall produce a mixture of the required gradation and bonding quantities. If a travel plant is used which the type that mixes previously spread aggregates in-place, the material shall have been spread in such thickness and proportions as may be handled by the machine to develop a base course of the thickness of each layer and of the gradation required. With either type of equipment, the mixed material shall be of a satisfactory moisture content to obtain the maximum density.

c. PROPORTIONING OR BLENDING IN-PLACE. When the base materials are to be proportioned and

mixed or blended in place, the different layers shall be placed and spread with the relative proportions of the components of the mixture being designated by the Engineer. The base aggregate shall be deposited and spread evenly over the first layer. They shall be thoroughly mixed and blended by means of the approved graders, discs, harrows, rotary tiller, or a machine capable of combining these operations, supplemented by other suitable equipment if necessary. The mixing shall continue until the mixture is uniform throughout and accepted by the Engineer. Areas of segregated material shall be corrected by the addition of needed material by re-mixing. Water shall be uniformly applied, prior and at the proper moisture content. When the mixing and blending have been completed, the material shall be bladed and dragged, if necessary, until smooth surface is obtained, true to the line and grade.

d. MATERIALS OF PROPER GRADATION. When the entire base coarse materials from coarse to fine

be secured in a uniform well-graded condition and contains approximately the proper moisture, such approved material may be handled directly to the spreading equipment. The material may be obtained from gravel pits, stockpiles or produced from a crushing and screening plant with the proper blending. The material from these sources shall meet the requirements for gradation, quality and consistency. The base material shall be at satisfactory moisture content to obtain maximum density. Any minor deficiency or excess of moisture content may be corrected by surface sprinkling or by aeration. In such instances, some mixing or manipulation may be required immediately proceeding the rolling to obtain the required moisture content. The final operation shall be blading or gragging, if necessary, to obtain a smooth uniform surface to line and grade.

201.3.4 METHODS OF SPREADING a. The aggregate base material that is correctly proportioned, has been processed in a plant, shall

be placed on the prepared underlying course and compacted in layers of the thickness shown in the plans. The depositing and spreading of the material shall commence were designated and shall progress continuously without breaks. The material shall be deposited and spread in lanes on a uniform layer without segregation of size to such loose depth when compacted, the layer shall have the required thickness. The base aggregate shall be spread by spreader boxes or other approved devices having positive thickness controls that shall spread the aggregate in the required amount to avoid or minimize the need for hand manipulating. Dumping from vehicles

Page 85: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

85

in piles, which require re-handling shall not be permitted. Hauling over the uncompacted base course shall not be permitted.

b. The aggregate base material that has been processed in a traveling plant, or mixed and blended

in-place, shall be spread in a uniform layer of required depth and width and to the typical cross-section. The spreading shall be by self-powered blade grader, mechanical spreader or other approved method. In spreading, care shall be taken to prevent cutting into the underlying layer. The material shall be bladed until a smooth uniform surface is obtained, true to line and grade.

c. The base course shall be constructed in neither a layer not less than 62mm nor more than

112mm of compacted thickness. The aggregate as spread shall be on uniform grading with no pockets of fine or coarse materials. The aggregate, unless otherwise permitted by the Engineer, shall not be spread more than 1,670 square meters in advance of the rolling. Any necessary sprinkling shall be kept within these limits. No materials shall be placed in snow or on soft, muddy or frozen coarse.

When more than one layer is required, the construction procedure described herein shall apply similarly to each layer. The Engineer shall make tests to determine the maximum density and the proper moisture content of the base material and this information will be available to the Contractor. The base material shall be at a satisfactory moisture content when rolling is started and by any minor variation prior to or during rolling shall be corrected by sprinkling or by aeration if necessary. During the mixing and spreading process, sufficient caution shall be exercised to prevent the incorporation of sub-grade, sub-base, or shoulder material in the base course mixture. 201.3.5 FINISHING AND COMPACTING After spreading, the aggregate shall be thoroughly compacted by rolling. The rolling progress gradually from the side to the center of the lane under construction or from one side toward previously placed material by lapping uniformly each preceding rear wheel track by one half the width of such truck. Rolling shall continue until the aggregate is thoroughly set, the interstices of the material reduced to a minimum, and until creeping of the material ahead of the roller is no longer visible. Rolling shall continue until the base material has been compacted to not less than 100% density as determined by the compaction control tests specified to AASHTO T 180 and AASHTO T 99. Blading and rolling shall be shall be done alternately, as required or directed, to obtain a smooth, even and uniformly compacted base. The course shall not be rolled when the underlying course is soft or yielding or when the rolling causes undulation in the base course. When the rolling develops irregularities that exceed 9mm when tested with a 5m straightedge, the irregular surface shall be loosened, refilled with the same kind of material as that used in constructing the course, and rolled again as required. In area inaccessible to rollers, the base course material shall be tampered thoroughly with mechanical tampers. 201.3.6 Surface Test After the course has been completely compacted, the surface shall be tested for smoothness and accuracy of grade and crown. Any portion lacking the required smoothness or failing in accuracy of grade or crown shall be scarified, re-shaped, re-compacted and otherwise manipulated as the

Page 86: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

86

Engineer may direct until the required smoothness and accuracy are obtained. The finished surface shall not vary more than 9mm from a 5m straightedge when applied to the surface parallel with, and a right angel to the centerline. 201.3.7 THICKNESS The thickness of the base course shall be determined by depth tests or cores taken at intervals in such manner that each test shall represent no more than 250 square meters. When the base deficiency is more than 12.5mm, the Contractor shall correct such areas by scarifying, adding satisfactory base mixture, rolling, sprinkling reshaping and finishing in accordance with these specification. The Contractor shall replace at his expense, the base material where borings have been taken for test purpose. 201.3.8 TRIAL SECTION Same as Item 200.3.10, Aggregate Sub-base Course. 201.3.9 PROTECTION Work on the base course shall not be accomplished when the sub-grade is wet. Hauling the equipment may be routed over completed portions of the base course, provided no damage results and provided that such equipment is routed over the full width of the base course to avoid rutting or uneven compaction. However, the Engineer shall have full and specific authority to stop all hauling over completed or partially completed base course when, in his opinion, such hauling is causing damage. The Contractor at his own expense shall repair any damage resulting to the base course from rutting equipment over the base coarse. 201.3.10 MAINTENANCE Following the completion of the base course, the Contractor shall perform all the maintenance work necessary to keep the base course in condition satisfactory for priming, the surface shall be kept clean, and free from foreign material. The base course shall be properly drained at all times. If cleaning is necessary, or if the prime coat becomes disturbed, any work or restitution necessary shall be performed at the expense of the Contractor. Before preparation begins for the application of the surface treatment for a surface course, the base course shall be allowed too partially dry until the average moisture content of the full depth base mixture. The drying shall not continue to the extent that the surface of the base becomes dusty with consequent loss of binder. If during the curing period the surface of the base dries fast, it shall be kept moist by sprinkling until such time as the prime coat is applied as directed. 201.4 METHOD OF MEASUREMENT The quantity of aggregate base course to pay for, either crushed or uncrushed as required in the proposal, shall be the number of cubic meters of base course material placed, bonded, and accepted in the completed base course. The quantity of base course material shall be measured in final position base upon depth tests, or cores taken as directed by the Engineer. Or at the rate of 1 depth test for each 250 square meters of base course, or by means of average areas on the complete work computed from elevations to the nearest 0.003 meter. On individual depth measurements, thickness

Page 87: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

87

more than 0.0125 meter in excess of the shown on plans shall be considered as specified thickness plus 0.0125 meter in computing the quantity for payment. Base material shall not be included in any other excavation quantities. 201.5 BASIS OF PAYMENT Payment shall be made at the contract unit price per cubic meter for aggregate base course. The price shall be full compensation for furnishing all materials and for all operations, hauling and placing of these materials, and for all labor, equipment tools and incidentals necessary to complete the Item. Payment will be made under:

PAY ITEM NUMBER DESCRIPTION UNIT OF MEASUREMENT

201 (1) Uncrushed Aggregate Base Course

cu.m.

201 (2) Crushed Aggregate Base Course cu.m.

Page 88: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

88

ITEM 307 – PORTLAND CEMENT CONCRETE PAVEMENT (Plain and Reinforced)

307.1 DESCRIPTION This item shall consist of pavement composed of Portland Cement Concrete, with or without reinforcement as specified on a prepared sub-base or base course in accordance with these specifications. And shall conform to the thickness and typical cross-section as shown on the plans and with the lines and grades established by the Engineer. 307.2 MATERIALS Fine aggregate for concrete shall consist of natural sand, stone, screening or other inert materials with similar characteristics or combination thereof, having hard, strong and durable particles approved by the Engineer. It shall not contain more than three (3) mass percent of materials passing the 0.075mm (No. 200 sieve) by washing nor more than one (1) percent each sieve of clay lumps or shale. The use of beach sand will not be allowed without the approval of the Engineer. If fine aggregate is subjected to five (5) cycles of the sodium sulfate soundness test, the weighted loss shall not exceed ten (10) mass percent. The fine aggregate shall be free from injurious amounts of organic impurities. If subjected to the colorimetric test for organic impurities and a color darker than the standard is produced, it shall be rejected. However, when tested for the effect of organic impurities of strength of mortar by AASHTO T71, the fine aggregate may be used if the relative strength within 7 days and 28 days in not less than 95%. The fine aggregate shall be well graded from coarse to fine and shall conform to Table 307-1.

Table 307 – 1 GRADATION FOR FINE AGGREGATE

SIEVE DESIGNATION PERCENTAGE PASSING BY WEIGHT

mm inches

9.50 3/8 100

4.75 No. 04 95 – 100

1.18 No. 16 45 – 80

0.30 No. 50 5 – 30

0.50 No. 100 0 – 10

307.2.1 COARSE AGGREGATE It shall consist of crushed stone, gravel, gravel, blast furnace slag, or other approved inert materials of similar characteristics, or combination thereof, having hard, strong, durable pieces and free from any adherent coatings.

Page 89: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

89

It shall not contain more than one (1) percent of material passing the 0.075mm (No. 200) sieve, not more than 0.25 mass percent of clay lumps, nor more than 3.50 percent of soft fragments. If the coarse aggregate is subjected to five (5) cycles of the sodium sulfate soundness test, the weight loss shall not exceed 12 mass percent. It shall have a mass percent of wear not exceeding 40 when tested by AASHTO T96. If slag is used, its density shall not be less than 1120 kg./cu.m. (70lb./cu.ft.). The gradation of the coarse aggregate shall conform to Table 307-2. Only when one grading specific shall be used from any one course.

TABLE 307-2 GRADING REQUIREMENTS FOR COARSE AGGREGATE

SIEVE DESIGNATION MASS PERCENT PASSING

mm inches Grading A Grading B Grading C

75.00 3 100 - -

63.00 2 ½ 90 – 100 100 100

50.00 2 - 90 – 100 95 – 100

37.00 1 ½ 25 – 60 35 – 70 -

25.00 1 - 0 –15 35 – 70

19.00 ¾ 0 – 10 - -

12.50 ½ 0 – 5 0 – 5 10 – 30

4.75 No. 04 - - 0 – 5

307.2.2 CEMENT Except when specifically approved by the “Engineer”, only one brand of cement shall be used for any individual structure. In determining the approved mix, only Portland Cement shall be used. 1. Portland Cement – ASTM C 150, Type I 2. High Early Strength Portland Cement Type III may be used for pre-cast concrete with a tricalcium

aluminate limited to 8%, conforming to ASTM C150. If, for any reason, cement becomes partially set or contains lumps of caked cement, it shall be rejected. Cement salvaged from discarded or used bag shall not be used.

307.2.3 ADMIXTURES The use of any material added to the concrete mix shall be approved by the “Engineer”. The Contractor shall submit certificates indicating that the material furnished shall meet all the requirements indicated below for the admixtures for which approval are desired. In addition, the “Engineer” may require the contractor to submit complete test data from a laboratory showing that the material to be furnished meets all the requirements of the cited specifications. Subsequent test will be made on samples taken by the Engineer from the supply of the material being furnished or proposed for use on the work to determine whether the admixture is uniform in quality with that approved. Admixtures stored longer than 6 months shall not be used until proven to be satisfactory. 1. Air-entraining admixtures shall meet the requirements of AASHTO M154 or ASTM C260. Air-

entraining admixtures shall be added to the mixer in the amount necessary to produce the

Page 90: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

90

specific air content. Testing shall be conducted with cement and aggregate proposed for the project.

2. Water-reducing set controlling admixtures shall meet the requirements of AASHTO M194

Type A – Water Reducing Type D – Water Reducing and Retarding

Water reducing admixtures shall be added at the mixer separately from air entraining admixtures in accordance with the manufacturer’s printed instructions. Other admixtures if approved shall be tested for conformance to the referred specifications. Admixtures containing chloride ions or other ions producing deleterious effects shall not be used. 307.2.4 WATER The water used in concrete, mortar and grout shall be free from objectionable quantities of silt, organic matter, alkali, salts and other impurities. Water will be tested in accordance with and shall meet the suggested requirements of AASHTO T26. Water known to be potable quality may be used without testing. Where the source of water is relatively shallow, the intake shall be so enclosed as to exclude silt, mud, grass or other foreign materials. 307.2.5 STEEL REINFORCEMENT It shall conform to the requirements of AASHTO M31 or M42, except that the rails steel shall not be used for the bars that are to be bent and re-straightened during construction. Tie bars shall be deformed bars. Dowels shall be plain round bars of the size specified and shall be free from any deformation restricting slippage in the concrete. Before delivery to the site, one-half of the length of each dowel bar shall be painted with one coat of approved lead or tar paint. The sleeves of dowels shall be metal or an approved design to cover 50-75mm (2-3 inches), plus or minus 5mm (1/4 inch) of the dowel, with a closed end, and with a suitable stop to hold the end dowel. Sleeves shall be of such design that they do not collapse during construction. The nominal dimensions and unit weight of bar designation shall be in accordance with the following table:

NOMINAL DIAMETER

NOMINAL PERIMETER

NOMINAL SECTIONAL AREA

UNIT WEIGHT

mm mm sq.m. kg./m

6 18.80 28.27 0.222

10 31.40 78.54 0.616

12 37.70 113.10 0.888

16 50.30 201.10 1.579

20 62.80 314.20 2.466

25 78.50 490.90 3.854

28 88.00 615.70 4.833

32 100.50 804.20 6.313

36 113.10 1017.90 4.991

40 125.70 1256.60 9.864

Page 91: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

91

50 157.10 1963.50 15.413

307.2.5.1 Welding of reinforcement bars shall only be permitted where shown; all welding shown shall be performed in accordance with ASWD D 12.1. 307.2.5.2 Exposed reinforcement bars, dowels and plates intended for bonding with future extensions shall be protected from corrosion. 307.2.5.3 Concrete Protection for Reinforcement 1. The minimum concrete cover of reinforcement shall be as indicated on the Drawings and as

shown in table. 2. The tolerance for Concrete Cover for Reinforcing Steel other Tendons. Minimum Cover Maximum Variation

7.50 cm or more 9 mm less than 7.50 cm 6 mm

307.2.6 JOINT FILLER 307.2.6.1 Poured Joint Fillers shall be mixed with asphalt and mineral or rubber conforming to applicable requirements of AASHTO M173. 307.2.6.2 Preformed Joint Fillers shall conform to the requirements of AASHTO M33 (ASTM D 994), AASHTO M153, AASHTO M213, AASHTO M 220, as specified. At expansion joints in concrete slabs to be exposed, and at the other joints indicated to receive joint sealant, pre-molded expansion joint filler strips shall be installed at the proper level below the elevation with slightly tapered, dressed, and oiled wood strip temporarily secured to the top thereof to form a groove, when surface dry, shall be cleaned of foreign matter loose particles, and concrete protrusions, then filled approximately flush with joint sealant so as to be slightly concave after drying. Finish of concrete joints: Edges of exposed concrete slabs along expansion joints shall be nearly finished with a slightly rounded edging tools. 307.2.7 JOINT SEALER No reinforcement, corner protection angles or other fixed metal items shall be run continuous through joints containing expansion joint filler, through joints containing expansion joint filler, through crack-control joints in slabs on grade and vertical surfaces. 307.2.8 CURING MATERIALS Curing materials shall conform to one of the following specifications: a. Cotton mats for curing concrete shall conform to AASHTO M73.

Page 92: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

92

b. Waterproof paper for curing concrete shall conform to AASHTO M139. c. White polyethylene sheeting (film) for curing concrete shall conform to AASHTO M171. d. Burlap cloth made from jute or kenaf shall conform to AASHTO M182. e. Liquid membrane forming compounds for curing concrete shall conform to AASHTO M148, Type

2 (all resin base). Or Fed. Spec. TT-C-800, Type 2. 307.2.9 STORAGE OF CEMENT AND AGGREGATE 1. Cement: Immediately upon receipt at the site, the cement shall be stored separately in a dry

weatherproof properly ventilated structure, with adequate provisions for prevention or absorption of moisture. The floor shall be raised from the ground. Provisions for storage shall be ample, and the shipments of cement as received shall be separately stored in such a manner as to allow the earliest deliveries to be used first and to provide easy access for identification and inspection of each shipment. Storage building shall have a capacity for storage of a sufficient quantity of cement to allow sampling at least twelve (12) days before the cement is to be used. The cement most likely to have been exposed to moisture or stored in bags for more than 3 months shall not be used unless proven by test to be in good condition. Stored cement shall meet the test requirements at any time after storage when the “Engineer” orders retest. At the time of use, all cement shall be free flowing and free of lumps.

2. Aggregates: Stored and handled to ensure good drainage to prevent segregation and the

inclusion of foreign materials. The “Engineer” may require the coarse aggregate to be separated into two or more sizes. Different sizes of aggregate shall be stored in separate bins or in separate stockpiles sufficiently remote from each other to prevent the materials at the edges of the stockpiles from becoming intermixed.

307.3 PROPORTIONING, CONSISTENCY AND STRENGTH OF CONCRETE 307.3.1 CONCRETE MIX PROPORTIONING The Contractor shall prepare the design mix based on the absolute volume method as outlined in the American Concrete Institute (ACI) Standard 211.1, “Recommended Practice for Selecting Proportions for Normal and Heavyweight Concrete”. Prior to the start of paving operations and after approval of all material to be used in the concrete, the Engineer shall determine the proportions of materials to be used to produce the specified strength. Trial design batches and testing to meet requirements in the class of concrete specified shall be the responsibility of the Contractor. Test for slump, unit weight and air content shall be performed in the field in the presence of the PMO. Trial mix shall be designed for maximum permitted slump and air content. The temperature of concrete in each trial shall be reported. For each water cement ratio at least three samples for each test age shall be made and cured in accordance with AASHTO T22, AASHTO T97 and AASHTO T177. 307.3.1.1 Entrained-Air Content: Air-entrainment shall be produced by adding an air-entraining agent at the mixer. Air content volume shall be maintained at 5 to 7 percentage as determined by AASHTO T152 or ASTM C231. 307.3.1.2 “Engineer” shall determine from laboratory test of the materials to be used, tested by the Contractor, the cement content and proportions of aggregates and water that will produce a

Page 93: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

93

workable concrete having a slump between 40 and 75mm if not vibrated or between 10 and 40mm if vibrated, and a flexural strength of not less than 3.80 Mpa (550 psi) when tested by the third point method or 4.50 Mpa (650 psi) when tested by the midpoint method; or a compressive strength of 24.1 Mpa (3,500 psi) when tested at 28 days in accordance with AASHTO T97, T177, or AASHTO T22 respectively. 307.3.2 SELECTION OF PROPORTIONS For each portion of the structure, proportions shall be selected so that maximum permitted water-cement ratio is not exceeded and so as to produce an average strength (fc’) by the amount indicated below. When the production facility has a standard deviation record determined in accordance with ACI 214, based on 30 consecutive strength tests of similar mixture strength. The average strength used as a basis for selecting proportioning shall exceed the specified strength, fc’, by at least: 1) 30 kg/sq.m. if standard deviation is less than 20 kg/sq.cm. 2) 40 kg/sq.m. if standard deviation is 20 to 30 kg/sq.cm. 3) 50 kg/sq.m. if standard deviation is 30 to 40 kg/sq.cm. 4) 60 kg/sq.m. if standard deviation is 40 to 50 kg/sq.cm. 5) if the standard deviation exceed 50 kg/sq.cm. or if a standard deviation record is not available,

proportions shall be selected to produce an average strength of at least 70 kg/sq.cm. greater than the specified strength.

307.3.3 STRENGTH OF CONCRETE Strength of concrete shall meet the following requirements: 1) The average of any 5 consecutive strength tests at the end of 28 days shall have an average

strength equal or greater than the specified strength. 2) Not more than 15% of the samples tested at the end of 28 days shall have an average strength

less than the specified strength specimens, which are obviously defective shall not be considered in the determination of strength.

3) When it appears that the test specimens will fail to conform to the requirements for strength,

“Engineer” shall have the right to order changes in the concrete sufficient to increase the strength. When a satisfactory relationship between 7-day and 28-day strength has been established and approved, the 7-day test results may be used as an indication of the 28-day strength.

Corrective measures to remedy deficiencies in aggregate gradation shall be used only in written approval of the “Engineer” 307.3.4 CONSISTENCY (SLUMP) Test shall be made in conformance with AASHTO T119, unless otherwise specified by the “Engineer”, slump shall be within the following limits.

STRUCTURAL ELEMENT SLUMP FOR VIBRATED CONCRETE

Minimum, mm Maximum, mm

Pre-cast concrete 50 70

Page 94: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

94

Wall column and grade beam, 25cm. max. thick

50 70

Lean concrete 70 100

Pavement 10 40

307.4 CONSTRUCTION METHOD 307.4.1 QUALITY CONTROL OF CONCRETE The Contractor shall be responsible for the quality control of all materials during the handling, blending, mixing and placement operations. The contractor shall furnish the “Engineer” a Quality Control Plan with the detailed production control procedures and the type and frequency of sampling and testing to ensure that the concrete produced complies with the specification requirements. The “Engineer” shall be provided free access to recent plan production records, information copies of mix design, materials certification and sampling and testing reports. Sampling and qualified personnel shall perform all batching and mixing operations for the concrete mix and shall be present at the plant and job site to control the concrete production whenever the plant is in operation. The Contractor shall perform all sampling, testing and inspection necessary to assure quality control of the component materials and the concrete. The Contractor shall be responsible for determining the gradation of fine aggregate and for testing the concrete mixture for slump, air content, water-cement ration and temperature. He shall conduct his operations so as to produce a mix conforming to the approved mix design. The Contractor shall maintain adequate records of all inspection and test. The records shall indicate the nature and number of observations made, the number and type of deficiencies found, the quantities approved and rejected, and nature and any corrective actions taken. The “Engineer” for acceptance purposes as he deems necessary. 307.4.2 EQUIPMENT Equipment and tools necessary for handling materials and performing all parts of the work shall be approved by the “Engineer” as to design, capacity and mechanical condition. The equipment shall be at the job site sufficiently before the start of construction operations for examination and approval. A) BATCHING PLANT AND EQUIPMENT

(1) General The batching plant shall include bins, weighing hoppers, and scales for the fine aggregate and for each size of coarse aggregate. If bulk cement is used, hopper and a separate scale for cement shall be included. The weighing hoppers shall be properly scaled and vented to preclude ducting during operation. (2) Bins and Hoppers

Page 95: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

95

Bins with adequate separate compartments for fine aggregate and for each required size of coarse aggregate shall be provided in the batching plant. Each compartment shall discharged efficiently and freely in the weighing hopper. Means of control shall be provided so that as the quantity desired in the weighing hopper is approached, the material may be added slowly and shut off with precision. A port of other opening for removing an overload of any one of the several materials from the hopper shall be provided. Weighing hoppers shall be constructed to eliminate accumulations of tar materials and to discharge fully. (3) Scales

The scales for weighing aggregates and cement shall be of either the beam or the springless dial type. They shall be accurate within 0.50% throughout their range of use. When beam-type scales are used, provisions, such as “tell-tale” dial, shall be made for indicating to the operator that the required load in the weighing hopper is being approached. A device on the weighing beams shall clearly indicate critical position. Poises shall be designed to be locked in any position and to prevent unauthorized change. The weight beam and “tell-tale” device shall be in full view of the operator while charging the hopper, and he shall have convenient access to all controls. (4) Recorders

An accurate recorder shall produce a graphical or digital record of the scale reading after each of the aggregates and cementing materials have been discharged (return to zero reference). The weights or volumes of water and admixtures shall also be recorded if batched at a central batching plant. Each recorder shall be housed in a cabinet, which shall be capable of being locked. The charts or tapes shall clearly indicate the different types of mixes used by stamped letters, numerals colored ink or other suitable means. It shall be so marked that variations in batch weights of each type of mix can be readily observed. All weighing, indicating, recording and control equipment shall be sufficiently protected against exposures to dust, moisture and vibration so that there is no interference with proper operation of the equipment. The recorder weights or volumes when compared to the weights or volumes actually batched shall be within the following limits of accuracy.

Materials Percent Cement 1 Water 1 Aggregate 2 Admixture 3 (5) Water Batcher and Dispenser for Admixtures

Equipment for batching water and admixtures shall be provided at the batching plant or included with the paving mixer or truck mixers as required for the type of plant used.

Page 96: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

96

(a) Water Batchers: A suitable water measuring device shall be provide which will be capable of measuring the mixing water within the specified requirements for each batch. The mechanism for delivering water to the mixers shall be such that leakage will not occur when the valves are closed. The filling and discharge valves for the water bather shall be so interlocked that the discharge valve is fully closed.

(b) Dispensers: An accurate mechanical device for measuring and dispensing each admixture

shall be provided. Each device shall be capable of ready adjustment to permit varying of the quality and admixture to be batched. Each dispenser shall be interlocked with the batching and discharging operations of latter so that each admixture is separately batched and discharged automatically in a manner to obtain uniform distribution throughout the batch in the specific period. When use of truck mixers makes this requirement impracticable, the admixture dispenser shall be interlocked with the sand batcher. Admixture will not be combined prior to introduction of water and sand.

(6) Moisture Control The plant shall be capable of ready adjustment to compensate for the varying moisture content of the aggregate, and to change the weights of the materials being batched. An electric moisture content gadget shall be attached in the fine aggregate bin to monitor the actual moisture content. The sensing element shall be arranged so that the measurement is made near the batcher charging the gate of the sand bin or in the sand batcher.

B) MIXERS (1) General Concrete may be mixed at the construction site, at a central point, or wholly or in part in truck mixers. Each mixer shall have attached in a prominent place a manufacturer’s plate showing the capacity of the drum in terms of volume of mixed concrete and the speed of rotation of the mixing drum blades. Stationary mixers, truck mixers or paving mixers of approved design. The mixers shall have a rated capacity of at least 0.76 cu.m. of mixed concrete and shall not be charged in excess of the capacity recommended by the manufacturer. Mixers shall be capable of combining the materials into a uniform mixture and of discharging this mixture without segregation. Stationary and paving mixers if used shall be provided with an acceptable device to lock the discharge mechanism until the required mixing time has elapsed. The mixing plant shall include a device for automatically counting the total number batches of concrete mixed. The mixers shall be operated at the drum of the mixing blade speed of rotation of the mixer drum or blades, and of proper introduction of the materials into the mixer. The acceptability of truck mixer will be determined by uniform test as required by ASTM C94. When mixed at the site or in a central mixing plant, the mixing time shall not be less than 50 seconds nor more than 90 seconds, unless mixer performance test proved adequate mixing of the concrete is shorter time period. Four seconds shall be added to the specific mixing time if timing starts the instant that the skip reaches its maximum raised position. Mixing time ends when the discharged chute opens. Transfer time in multiple drum mixers is included in mixing time. Mixing time for stationary or paving mixers will be increased when such increase is necessary to secure the required uniformity and consistency of the concrete. Any concrete mixes less than the specified time shall be discarded and be disposed off by the Contractor at his own expense. Excessive over mixing requiring

Page 97: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

97

additions of water will not be satisfactory operating condition and mixer shall be kept free of hardened concrete. Mixer blades shall be replaced when worn down more than 10% of their depth. Should any mixer at any time produce unsatisfactory results, its use shall be promptly discontinued until it is repaired. (2) Mixers at Construction Sites Mixing shall be in an approved mixer capable of combining the aggregates, cement and water into a thoroughly mixed and uniform mass within the specified mixing period, and of discharging and distributing the mixture without segregation on the prepared grade. The mixer shall be equipped with an approved timing device, which will automatically lock discharge lever when the drum has been charged and release it at the end of mixing. The device shall be equipped with a bell or other suitable warning device adjusted to give clearly audible signal each time the locked is release. In case of failure of the timing device, the mixer may be used for the balance of the day while it is being prepared, provided that each batch is mixed 90 seconds. The mixer shall be equipped with a suitable non re-settable bath counter, which shall correctly indicate the number of batches mixed. (3) Central Plant Mixers Mixers for central plant mixing (plant mixer, revolving drum type mixers, single opening revolving truncated drum mixer at one end and discharging at the other end) shall have attached thereto into a prominent place by the manufacturer, a metal plate(s) on which is plainly marked the various uses for which the equipment is designed, the nominal capacity (cu.m.) of the drum or container in terms of the volume of the mixing central plant mixers shall be equipped with an acceptable timing device that will not permit the batch to be discharge until the specified mixing time has elapsed. The water system for a central mixer shall be either a calibrated measuring tank or meter and shall be cleaned at suitable intervals. They shall be examined daily for changes in condition due to accumulation of hard concrete or mortar or the wear blades. The pick-up and throwover blade shall be replaced when they have worn down 19mm or more. The Contractor shall provide the “Engineers” with a copy of the manufacturer’s design showing dimensions and arrangements of blades in reference to original height and depth. (4) Truck Mixers and Truck Agitators Truck mixers used for mixing and hauling concrete, truck and truck agitators used for hauling central-mixed concrete, shall conform to the requirements of AAHTO M157. (5) Non-Agitators Trucks Non-agitating hauling equipment shall conform to the requirements of AASHTO M157. C) FINISHING EQUIPMENT (1) Finishing Machine The finishing machine shall be equipped with at least two oscillating type transverse screeds. (2) Vibrators

Page 98: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

98

Vibrator for full width vibration of concrete paving slabs, may be either the surface pan type or internal type with either immersed tube or multiple spuds. They may be mounted on a separate carriage. They shall not come in contract with the joint, load transfer devices, sub-grade or side. D) FORMS Straight side forms shall be made of metal having thickness of not less than 5mm and shall be furnished in sections not less than 3mm length. Form shall have a depth equal to the prescribed edge thickness of the concrete, without horizontal joint, and a base with equal to the depth of the forms. Flexible or curve forms of proper radius shall be used for curves of 30m radius less. Flexible or curve form shall be of a design acceptable to the Project Engineer. Forms shall be provided with adequate devices for secure setting so that when in place they will withstand, without visible spring or settlement, the impact and vibration of the consolidating and finishing equipment. Flange braces shall extend outward on the base not less than two-thirds the heights of the forms. Forms with battered top surfaces, and bent, twisted or broken forms shall be removed from the work. Repaired forms shall not be used until inspected and approved. Built up forms shall not be used except as approved by the “Engineer”. The top face of the forms shall not vary from a true plane more than 3mm in 3 meters and the upstanding leg shall vary more than 19mm. The forms shall contain provisions for locking the ends of abutting sections together tightly for secure setting. 307.4.3 Form Setting Forms shall be set sufficiently in advance of the concrete placement. After the forms have been set to correct grade, the grade shall be thoroughly tamped, either mechanically or by hand, at both the inside and outside edges of the base of the forms. Forms shall be staked into place with not less than 3 pins for each 3-meter section. A pin shall be placed at each side of every point. Form sections shall be tightly locked and shall not deviate from true line by more than 6mm at finishing machine will not be tolerated. Forms shall be cleaned and oiled prior to the placing of concrete. The alignment and grade elevation of the forms shall be checked and corrections made by the Contractor immediately before placing the concrete. When any form has been disturbed or any other has become unstable, the form shall be reset and re-checked. 307.4.4. Preparation of Base After the sub-base or base has been placed and compacted to the required density, the areas which will support the paving machine and the grade on which the pavement is to be constructed shall be trimmed to the proper elevation by means of a properly designed machine extending the work at least 60 cm beyond the edge of the proposed concrete pavement. If loss of density results from the trimming operations, it shall be restored by additional compaction before concrete is placed. If any traffic is allowed to use the prepared sub-grade or base, the surface shall be checked and corrected immediately before placing of concrete. 307.4.5 Handling, Measuring and Batching Materials The batch plant site, layout equipment and provisions for transporting material shall assure a continuous supply of materials to the work. Stockpile shall be built up in layers of not more than one (1) meter in thickness. Each layer shall be completely in place before beginning the next, which shall not be allowed to “cone” down over the next lower layer. Aggregates from different grading shall not be stockpiled together.

Page 99: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

99

Aggregates shall be handled from stockpiles of other sources to the batching plant in such a manner as to secure the specified grading material. All aggregates produced and handled by hydraulic methods, and washed aggregates, shall be stockpiled or binning for draining at least twelve (12) hours before being batched. When mixing is done at the job site, aggregates shall be transported from the batching plant to the mixer in batch boxes, vehicle bodies, or other containers of adequate capacity and construction to properly carry the volume required. Partitions separating batches shall be adequate and effective to prevent spilling from one compartment to another while in transit or while being dumped. When bulk cement is used, the Contractor shall use a suitable method of handling the cement from weighing hopper or transporting container or into the batch itself for transportation to the mixer, such as chute, boot or other approved device, to prevent loss of cement. The device shall be arranged to provide positive assurance of the actual presence in each batch of the entire cement content specified. Bulk cement shall be transported to the mixer in light compartments capable of carrying the full amount of cement required for each batch, of if permitted between the fine and coarse aggregate. When cement is placed in contact with the aggregates, batches may be rejected unless mixed with in one and one-half (1 ½) hours of such contract. 307.4.6 Mixing Concrete Concrete may be mixed at the work site in a central mix plant or in truck mixers. The mixers shall be on an approved type and capacity. Mixing time shall be measured from the time all materials, except water, are emptied into the drum. Ready-mixed concrete shall be mixed and delivered in accordance with the requirements of AASHTO M 157, except that the minimum required revolutions at the mixing speed for transit-mixed concrete may be reduced to not less than the recommended by the mixer manufacturer shall be indicated in the manufacturer’s serial plate attached to the mixer. Mixing time shall conform to the requirements indicated under Item Mixer. The volume of concrete mix per batch shall not exceed the mixer’s nominal capacity in cubic meter, as shown on the manufacturer’s standard rating plate on the mixer, except that an overload up to 10% above the mixers nominal capacity may be permitted provided concrete test data for strength, segregation, and uniform consistency are satisfactory and provided no slippage of concrete takes place. The batch shall be charged into the drum so that the portion of the mixing water shall enter in advance of the cement and aggregates. The flow of water shall be uniform and all water shall be in the drum by the end of the first 15 seconds of the mixing period. The throat of the drum shall be kept free of such accumulations as may restricts the free flow of materials into the drum. Mixed concrete from the central mixing plant shall be transported in truck mixers, truck agitators or non-agitating trucks specified in sub-section EQUIPMENT. Mixing time as indicated in sub-section MIXER may be reduced during hot weather or under other conditions contributing to quick hardening of the concrete. Re-tempering concrete by adding water or by other means will not be permitted, except that when concrete is delivered in truck mixers, additional water may be added to the batch materials and additional mixing performed to increase the slump to meet the specified requirement, if permitted by the “Engineer”, provided all these operations are performed with in the specified slump limits at time of placement shall not be used.

Page 100: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

100

Admixtures for increasing the workability or for accelerating the setting of concrete will be permitted only when specifically approved by the “Engineer”. 307.4.7 Limitation of Mixing No concrete shall be mixed, placed, or finished with insufficient light, unless adequate and approved artificial lighting system is operated. During not weather, the “Engineer” may require steps to be taken to prevent temperature of the mixed concrete from exceeding the specified maximum requirements. Concrete not placed within 90 minutes from the time the ingredients were charged to the mixing drum or that has developed initial set shall not be used. Re-tampering of concrete, which has partially hardened, that is, re-mixing with or without additional cement, aggregate, or water shall not be permitted. 307.4.8 Placing of Concrete Concrete shall be deposited in such a manner to require minimal re-handling. Unless truck mixers, truck agitators or non-agitating hauling equipment are equipped with means to discharge concrete without segregation of the materials. The concrete shall be unloaded into an approved spreading device and mechanically spread on the grade in such a manner as to prevent segregation of the materials. Placing shall be continuous between transverse joints without the use of intermediate bulkheads. Necessary hand spreading shall be done with shovels, not rakes. Workmen shall not be allowed to walk in freshly mixed concrete with boots or shoe coated with earth on foreign substances. When concrete is to be deposited adjoining a previously constructed lane of pavement and when mechanical equipment will be operated upon the existing lane of pavement, the concrete shall be at least 10 days old and approval shall be obtained from the Engineer. If only finishing equipment is carried on the existing lane, paving in adjoining lanes may be permitted after 3 days, if approved by the “Engineer”. Concrete shall be thoroughly consolidated against and along the faces of all forms and along full length and both sides of all joint assemblies by means of vibrators inserted in the concrete. Vibrators shall not be permitted to come in contact with a join assembly, the grade, or a side form. In no case shall the vibrator be operated longer than 15 seconds in any one location. Concrete shall be deposited as near to expansion and contraction joints as possible without disturbing them but shall not be dumped from the discharge bucket or hopper unto a joint assemble. Should any concrete materials fall on or be worked into the surface of a complete slab they shall be removed immediately by approved methods. 307.4.9 Test Specimen Following the placing of concrete, it shall be stuck-off to the cross section shown on the plans and to an elevation such that when the concrete is properly consolidated and finished, the surface of the pavement shall be at elevation shown on the plans. When reinforced concrete pavement is placed in two layers, the bottom layer shall be stuck-off to such length and depth that the sheet of fabric or

Page 101: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

101

bar may be laid full-length on the concrete on its final position without further manipulation. The reinforcement shall then be placed directly upon the concrete, after which the top layer of the concrete shall be placed, struck-off and screened. Any portion of the bottom layer of the concrete which has been placed more than 30 minutes without being covered with the top layer shall be removed and replaced with freshly mixed concrete at the Contractor’s expense. When reinforced concrete is placed in one layer, the reinforcement may be positioned in advance of concrete placement or it may be placed at the depth shown on the plans in plastic concrete by mechanical or vibratory means after screeding. Reinforcing steel, at the time concrete is placed, shall be free of mud oil, or other organic matter that may be adversely affect or reduce bond. Reinforcing steel with rust, mill scale or combination of both will be considered satisfactory, provided the minimum dimensions, weight and tensile properties of a hand wire-brushed test specimen are not less than the applicable AASHTO Specification requirement. 307.4.10 Joints General. Longitudinal and transverse joints shall be constructed as indicated on the plans and in accordance with these requirements. All joints shall be constructed true to line with their faces perpendicular to the surface of the pavement. Joint shall not vary more than 6.0mm from a true to line or from their designated position. The vertical surface of the pavement adjacent to all expansion joints shall be finished to a true plane and edged to a radius of 6.0mm, or as shown on the plans. The surface across the joints shall be tested with a 3.0-meter straightedge and any irregularities in excess of 3.0mm shall be corrected before the concrete has hardened. When required, keyways shall be accurately formed with template of metal or wood. The gauge or thickness of the material in the template shall be such that the keyway, as specified is formed and is in the correct location. Transverse joints in succeeding lanes shall be placed in line with similar joint in the first lane. In case of widening of existing pavements, transverse joint shall be so prepared, finished or cut to provide a groove of sufficient width and depth to receive and effectively retain joint-sealing material. Tie bars installed principally in longitudinal joints as shown on the plans shall consist of deformed bars of 16mm diameter and 76cm long, or as designated on the plans. Tie bars shall be placed at right angles to centerline of the concrete slab and as spaced at intervals of 76cm, unless otherwise specified. They shall be held in position parallel to the pavement surface midway between the surfaces of the slab. When tie bars extend into an unpaved lane, they may be bent at right angles for longitudinal construction joints, unless threaded bolt or other assembled tie bars are specified. These bars shall not be painted, greased or enclosed in sleeves. Dowel bars or other load-transfer units of an approved type shall be placed across transverse or other joints in the manner as specified on the plans. They shall be of the dimensions and spacing as shown and held rigidly in the middle of the slab depth in the proper horizontal and vertical alignment by an approved assemble device to be left permanently in place. The dowel or load transfer and joint devices shall be rigid and placed in position. A metal, or other type, dowels expansion cap or sleeve shall be furnished for each dowel bar used with expansion joints. These caps are substantial enough to prevent collapse and shall be placed on the ends of the dowels as shown on the plans. The portion of each dowel painted with most preventive paint, as required under 307-2.5, shall be thoroughly coated with asphalt MC-70, or an

Page 102: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

102

approved lubricant, to prevent the concrete from binding to that portion of the dowel. An approved metal dowel cap or sleeve conforming to the requirements of 307-2.5 shall be furnished for each dowel bar used in expansion joints. The caps or sleeve shall fit the dowel assemblies at contraction joints; dowel bar may be placed in full thickness of pavement by a mechanical device approved by the “Engineer”. Installation. If the paving system is operated from an adjacent lane, any joint materials required shall be set by immediately after the final testing of the grade. If the paving mixer is operated from the lane being poured, the materials shall be set immediately after the mixer moves forward to permit much time for proper installation. All joint materials required shall be put in place on the completed and accepted grade. The materials and joint position shall be either set at right angles or parallel to the centerline pavement except, for fillets or irregular sections. The top of an assembled joint device shall be set at the proper distance below the proper pavement surface and elevation shall be checked. Such devices shall be set to the required position and the line shall be securely held in place by stakes or other means during the pouring and finishing of the concrete. The pre-molded joint materials shall be placed and held in several position, if adjacent units. Dowel bars shall be checked for exact position supported. Any joint installation not firmly and securely supported shall be reset. When joint in concrete pavement are sewed, the joint shall be cut at the time and in the manner approved by the “Engineer”. The equipment used shall be as described in 307.4.2. The circular cutter shall be capable of cutting a groove in a straight line; the circular cutter shall produce a slot at least 3.00m wide. When shown on the plans or required to be widened by means of a second shallower cut or by suitable and approved beveling to provide adequate space for joint sealers. Sawing of the joints shall commence as soon as the concrete has hardened sufficiently to permit cutting without chipping, spalling or tearing. Concrete shall be sawed at the required spacing consecutively in sequence of the concrete placement, unless otherwise approved by the “Engineer”. Longitudinal Joints. Longitudinal construction joints necessary for runway construction shall be formed against suitable side forms (usually made of steel) with keyways, unless otherwise indicated in the plans. Wooden forms may be used under special conditions, when approved by the “Engineer”. In these instances where the keyed construction joint is not designated, a butt type joint shall painted and greased. The edges of the joints shall be finished with a grooving tool or edging tools and space or slot shall be formed along the joint of the dimensions, as indicated to receive the joint sealing material. Provisions shall be made for the installation of the tie bars as noted on the plans. Contradiction or Weakened Plane Type. The longitudinal groove formed or sawed in the top of the slab shall be installed where indicated on the drawings. The groove shall be formed in the plastic concrete with suitable tools or materials to obtain the width and depth specified, or it shall be sawed with approved equipment in the hardened concrete to the dimensions required. When the groove is formed in plastic concrete, it shall be true to line with not more than 6.0mm variation in 3.0m; it shall be finished even and smooth with an edging tool. If an insert material is used, the installation and edge finish shall be according to the manufacturer’s instruction. The sawed shall be straight and of uniform width and depth. In either case, the groove shall be clean cut so that spalling will be avoided at intersection with transverse joints. Tie bars shall be installed across these joints, unless otherwise shown on the plans.

Page 103: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

103

Expansion. Longitudinal expansion joints shall be installed where designated on the plans. These shall be butt type without load transfer devices and shall include pre-molded expansion material. The thickness of the concrete at these joints shall be increased by at least 25% of the normal pavement thickness to the nearest inch but not less than 50mm. This increase shall be slope to normal thickness is not less than 3.0m from the joint or to the nearest joint such as groove joint. The pre-molded filler of the thickness shown on the plans shall extend for the full depth and width of the slab at the joint, except for space for sealant at the top of the slab. The filler shall be securely staked and fastened into position perpendicular to the proposed finished surface. A metal or wooden cap shall be provided to protect the edge of the filler and to permit the concrete to placed and finished. After the concrete has been placed and the struck-off, the cap shall be carefully withdrawn leaving the space over the pre-molded filler. The edges of the joint shall be finished and tooled while the concrete is still plastic. TRANSVERSE JOINT Expansion. Transverse expansion joints shall be installed at the location and spacing as shown on the plans. The joints shall be installed at right angles to the centerline perpendicular to the surface of the pavement. The joint shall be so installed and finished to ensure complete separation of the slabs. Expansion joints shall be pre-molded type conforming to these specifications and with the plans and shall be to the full width of the pavement strip. All concrete shall be cleaned from the top of the joint material before pavement is opened to traffic, this space shall be swept, clean and filled with approved joint sealing material. The filler shall be placed on the side of the installing plate nearest the mixer. A metal channel cap of at least 10-gauge material shall protect the top edge of the filler. The installing device may be designed with this cap self-contained. All device used for the installation of expansion joints shall be approved by the Engineer. They shall be easily removable without disturbing the concrete and held in proper transverse and vertical alignment. Immediately after forms are removed, any concrete bridging the joint space at the ends shall be removed for the full width and depth of the joint. When specified, expansion joints shall be equipped with dowels of dimensions and at the spacing and location indicated on the plans. The dowels shall be firmly supported in place and accurately aligned parallel to the sub-grade and the centerline of the pavement and will ensure that the dowels are not displaced during construction. Other types of load transfer devices may be used, when approved by the “Engineer”. Contraction. Transverse contraction joints, weakened plane joints, or both, shall be installed at the locations and spacing as shown on the plans. These joints will be installed by forming a groove or cleft in the top of the slab while the concrete is still plastic or by sawing a groove into the concrete surface after the concrete has hardened in the same manner as specified in 307.4.1. Dowel bar assembly shall be installed, when required, as shown on the plans. Reinforcing steel mesh or bars shall be continued through weakened-plane joints as shown for reinforced concrete pavement.

Page 104: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

104

Construction. Transverse construction joints shall be installed in accordance with the details on the plans and ordinarily are only needed when it is necessary to suspend the work for more than 30 minutes. When the installation of the joint can be planned in advance, it shall be located at a contraction or expansion joint. The joint shall not be allowed within 2.40 meters of a regular spaced transverse joint. If the pouring of the concrete has been stopped, causing a joint to fall within this limit, it shall be removed back to the previously spaced regular joint. 307.4.11 FINAL STRIKE-OFF, CONSOLIDATED AND FINISHING Sequence. The sequence of operations shall be strike-off and consolidation, floating and removal of laitance, straight edging, and final surface finish. The addition of superficial water to the surface of the concrete to assist in finishing operations generally will not be permitted. If the application of water to the surface is permitted, it shall be applied as a fog spray by means of approved spray equipment. Finishing Joints. The concrete adjacent to joints shall be compacted or firmly placed without voids or segregation against the joint material; it shall be firmly placed without voids or segregation under and around all load transfer devices, joint assembly units, and other features designed to extend into the pavement. Concrete adjacent to joints shall be mechanically vibrated as required in 307.4.7. After the concrete has been placed and vibrated adjacent to the joints as required in 307.4.7, the finishing machine shall be operated in a manner to avoid damage or misalignment of joints. If uninterrupted operations of the finishing machine, to, over, and beyond the joints causes segregation of concrete, damage to or misalignment of the joints, the finishing machine shall be stopped when the front screed is approximately 20 cm from the joint. Segregated concrete shall be removed from the front of and off the joint; the front screed shall be lifted and set directly on top of the joint and the forward motion of the finishing machine shall be resumed. When the second screed is closed enough to permit the excess mortar in front of it to flow over the joint, it shall be lifted and carried over the joint. Thereafter, the finishing machine may be run over without lifting the screeds, provided there is no segregated concrete immediately between the joint and the screed or on top of the joint. MACHINE FINISHING Non-Vibratory Method. The concrete shall be spread as soon as it is placed and it shall be struck-off and screed by an approved finishing machine. The machine shall go over each area as many times and at such intervals as necessary to give the proper compaction and to leave a surface of uniform texture. Excessive operation over a given area shall be avoided. The tops of the forms shall be kept clean by an effective device attached to the machine and the travel of the machine on the forms shall be maintained true without lift, wobbling or other vibration tending to affect the precision finish. During the first pass of the finishing machine, a uniform ridge of concrete shall be maintained ahead of the front screed for its entire length. Vibratory Method. When vibration is specified, the vibrators for full-width vibration of concrete paving slabs shall meet the requirement specified in 307.4.2 (c)(2). If uniform and satisfactory density of the concrete is not obtained by the vibratory method at joints, along forms, at structures, and throughout the pavement, the contractor will be required to furnish equipment and methods

Page 105: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

105

that will produce pavement conforming to the specifications. All provisions in sub-paragraph (1) above not in conflict with the provisions for the vibratory method shall govern. Hand Finishing. Unless otherwise specified, hand finishing methods will not be permitted, except under the following conditions; Narrow widths or areas of irregular dimensions where operation of the mechanical equipment is impractical may be finished by hand methods. Concrete, as soon as placed, shall be struck-off and screed. An approved portable screed shall be used. A second screed shall be provided for striking-off the bottom layer of concrete when reinforcement is used. The screed for the surface shall be at least 60cm longer than the maximum width of the slab to be struck-off. It shall be of approved design, sufficiently rigid to retain its shape, and shall be constructed either of metal or of suitable material, shed with metal. Consolidation shall be attained by the use of a suitable vibrator or other approved equipment. Floating. After the concrete has been struck-off and consolidated, it shall be further smoothed, trued and consolidated by means of a longitudinal float, using one of the following methods as specified or permitted: 1. Hand Method. The hand operated longitudinal float shall be not less than 350mm in length and

350mm in length and 150mm in width, properly and warping. The longitudinal float, operated from foot bridges resting on the side forms and spanning but not touching the concrete, shall be work with sawing motion, while held in a floating position parallel to the runway centerline of the pavement shall be in successive advances of not more than one half the length of the float. Any excess water or soupy material shall be wasted over the side forms on each pass.

2. Alternative Mechanical Method. As an alternative to 307.4.1. (e)(2) above, the contractor may

use any machine composed of a cutting and smoothing float(s), suspended from the guided rigid frame. Four or more visible wheels riffing on and constantly in contact with the side forms shall carry the frame.

If necessary, following one of the preceding methods of floating, long handed floats having blades not less than 1.5mm in length and 0.150mm in width may be used to smoothed and fill in open-textured area in pavement. Long handled floats shall not be used to float the entire surface of the pavement in lieu of, or supplementing, one of the preceding methods of floating. When strike-off and consolidation are done by hand and the crown of the pavement will not permit the use of the longitudinal float, the surface shall be floated transversely by means of the long-handled float. Care shall be taken not to work the crown out of the pavement by a straightedge 10 feet or more in length. Successive drags shall be lapped one-half the length of the blade. Straightedge Testing and Surface Correction. After the floating has been completed and the excess water removed, but while the concrete is still plastic. The surface of the concrete shall be tested for trueness with a 5-meter straight edge. For this purpose the contractor shall furnish and use an accurate 5-meter straight edge swung from handles 900mm longer than one half the width of the slab. The straight edge shall be held in contact with the surface in successive positions parallel to the centerline and the whole area gone over from one side of the slab to the other, as necessary.

Page 106: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

106

Advancing shall be in successive stages of not one-half the length of the straight edge. Any depressions shall be immediately filled with freshly mixed concrete, struck-off, consolidated and refinished. Special attention shall be given to assure that the surface across joints meets the requirements for the smoothness. Straight edge testing and surface corrections shall continue until the slab conforms to the required grade and cross-section. Final Finish. The surface of a runway shall be finished with either a broom finish or a belt finish. Taxiways, aprons, and other pavements may be finished with wither a broom finish, a belt finish, or a drag finish. Broom Finish. If the surface texture is to be broom finish, it shall be applied when the water sheen has practically disappeared. The broom shall be drawn from the center to the edge of the pavement with adjacent strokes slightly overlapping. The brooming operation shall be uniform in appearance and not more than 3.0mm in depth. Brooming shall be completed before the concrete is in such operation. The surface thus finished shall be free from rough and porous areas, irregularities, and depression resulting from improper handling of the broom. Broom shall be of quality, in size, and construction and shall be operated to produce a surface finish meeting the approval of the “Engineer”. Subject to the approval of the “Engineer”, the Contractor may be permitted to substitute mechanical brooming in lieu of the manual brooming as herein described. Belt Finish. If the surface texture is to be a belt finish, when straight edging is completed and water sheen has practically disappeared and just before the concrete becomes non-plastic, the surface shall be belted with 2-ply canvass belt not less than 200mm wide at least 900mm longer than the pavement width. Hand belts shall have suitable handles to permit controlled, uniform manipulation. The belt shall be operated with short stroke transverse to the centerline and a rapid advance parallel to the centerline. Drag Finish. If the surface texture is to be a drag finish, a drag shall be used; it shall consist of seamless strip of damp burlap or cotton fabric, and it shall produce a uniform surface of gritty texture dragging it longitudinally along the full width of pavement. For pavement 16 feet or more in width, the drag shall be mounted on a bridge, which travel on the form. The dimensions of the drag shall be such that a strip of burlap of fabric at least 900mm wide is not in contact with the full width, of the pavement surface while the drag is used. The drag shall be approximately 150mm wider than the upper layer. The drag shall be maintained in such a condition that the resultant surface is of uniform appearance and reasonably free from grooves over 1.50mm in depth. Drag that cannot be cleaned shall be discarded and substituted. Edging at Forms and Joints. After the final finish, but before the concrete has taken its initial set, the edges of the pavement along each side of each slab, on each side of transverse expansion joint, formed joints, transverse construction joints, and emergency construction joints shall be worked with an approved tool rounded to the radius required by the plans. A well-defined and continuous radius shall be produced and a smooth dense, mortar finish obtained. Tilting of the tool during use shall not unduly disturb the surface of the slab. At all joints any tool marks appearing on the adjacent to the joints shall be eliminated by brooming the surface. In doing this rounding of the edge shall not be disturbed. All concrete on top of the joint filler shall be completely removed. All joints shall be tested with straightedge before the concrete has set, and correction shall be made if only one side of the joint is higher than the other or if they are higher than the other or if they are higher or lower than the adjacent slabs.

Page 107: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

107

307.4.12 Surface Test. As soon as the concrete has hardened sufficiently, the pavement shall be tested with 5-meter straight edge or other specified device. Areas showing high spots of more than 6mm but not exceeding 12.5mm in 5-meter shall be when marked immediately ground with approved grinding tool to an elevation where the area or spot will not show surface deviations in excess of 6mm when tested with 5-meter straight edge. Where the departure from correct cross section exceeds 12.50mm, the pavement shall be removed and replaced by and at the expense of the contractor. All of whatever kind that may elect to use, lack of water to adequately take care of both curing and other requirements, shall be cause for immediate suspension of concreting operations. The concrete shall not be left exposed for more than ½ hour between stages of curing or during the curing period. Cotton or Burlaps Mats. The surface of the pavement shall be entirely covered with mats. The mats shall be used of such length (or width) that, a laid, they will extend at least twice the thickness of the pavement beyond the edges of the slab. The mat shall be placed and weighed to remain in intimate contact with the surface covered has been placed, unless otherwise specified, the covering shall be maintained in placed for 72 hours after the concrete has been placed. Straw Curing. When this type of curing is used, the pavement shall be cured initially with burlap or cotton mats, as specified in 307.4.13 (a) until after placing the concrete. As soon as the mats are removed, the surface and the sides of the pavement shall be thoroughly wetted and covered with at least 8 inches of straw or hay, the thickness of which is to be measured after the wetting. For the straw or hay, the thickness of which is to be measured after the after wetting. If the straw or hay covering becomes displaced during the curing period, it shall be replaced to the original depth and saturated. It shall be kept thoroughly saturated with water for 3 days and thoroughly wetted down during the morning of the fourth day, and the cover shall remain in place until the concrete has attained the required strength. When permission is given to open the pavement swept clean. The covering shall be removed and disposed of in such a manner as to leave the area in a neat and presentable condition. The straw or hay shall not be disposed of by burning or adjacent to the pavement. Impervious Membrane Method. The entire surface of the pavement shall be sprayed uniformly with white pigmented curing compound immediately after the finishing of the surface and before the set of the concrete has taken place; if pavement is cured initially with jute or cotton mats, it may applied upon removal of the mats. The curing compound shall not be applied during rainfall. Curing compound shall be applied mechanical sprayers under pressure at the rate of 14 liters to not more than 14sq.m.. The spraying equipment shall be of the fully atomizing type equipped with a tank agitator. At the time of use, the compound shall be in a thoroughly mixed condition with the pigment uniformly dispersed through the vehicle. During application, the compound shall be stirred of off-widths or shapes and concrete surfaces exposed by the removal of forms will be permitted. Curing compound shall not be applied to the inside faces of joints to be sealed. The curing compound shall be of such character that the film hardens within 30 minutes after application. Should the film become damaged from any cause within the required curing period, the damaged portion shall be repaired immediately with additional compound. Upon removal of side forms, the sides of the exposed slab shall be protected immediately to provide a curing treatment equal to that provided for the surface.

Page 108: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

108

White Polyethylene Sheeting. The top surface and sides of the pavement shall be entirely covered with polyethylene sheeting. The units shall be lapped at least 18 inches. The sheeting shall be placed and weighed to remain in intimate contact with the surface covered. The sheeting as prepared for use shall have such dimensions that each unit, as laid, will extend beyond the edges of slabs at least twice the thickness of the pavement. Unless otherwise specified, the covering shall be maintained in place for 72 hours after the concrete has been placed. Curing in Cold Weather. When the average daily temperature is below 0° Fahrenheit, curing shall consist of covering the newly laid pavement with not less than 30 cm of loose, dry hay or straw, or equivalent protective curing authorized by the “Engineer”, which shall be retained in place for 10 days. Admixture for curing temperature control may be used only when authorized by the “Engineer”. When concrete is being placed and the air temperature may be expected to drop below 35° Fahrenheit, a sufficient supply of straw, hay, grass or other suitable blanketing material shall be provided along the work. Any time the temperature may be expected to reach the point during the day or night, the material so provided shall be spread over the pavement to the sufficient depth to prevent freezing of the concrete. The period of time such protection shall be maintained must not be less than 10 days. The Contractor shall be responsible for the quality and strength of the concrete placed during cold weather, and any concrete injured by frost action shall be removed and replaced at the Contractor’s expense. 307.4.13 Removing Forms. Unless otherwise specified, the forms shall not be removed from freshly placed concrete until it has set for at least 12 hours, except where auxiliary forms are used temporarily in widened areas. Forms shall be removed carefully to avoid damage to the pavement. After the forms have been remove, the sides of the slab shall be cured as outlined in one of the methods indicated in 307.4.12. Major honeycomb areas shall be considered as defective work and shall be removed and replaced. Any area or section so removed shall not be less than 3.0 meters in length not less than the full width of the lane involved. When it is necessary to remove and replace a section of pavement, any remaining portion of the slab adjacent to the joints that is less than 3.0 meters in length shall also be removed and replaced. 307.4.14 Sealing Joints. The joints in the pavement shall be sealed in accordance with Item 907. 307.4.15 Protection of Pavement The Contractor shall protect the pavement and its appurtenances against both public traffic caused by his own employees and agents. This shall include watchmen to direct traffic and the erection and maintenance of warning signs, lights, pavement bridges, or crossovers, etc. The plans or special provisions will indicate the location and type of device or facility required to protect the work and provide adequately for traffic. Any damage to the pavement occurring prior to the final acceptance and within the guarantee period shall be replaced or the pavement replaced at the Contractor’s expense.

Page 109: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

109

307.4.16 Opening to Traffic. The “Engineer” shall decide when the pavement shall be opened to traffic. The pavement shall not be opened to traffic for at least 14 days after the concrete has been placed or until the strength has been attained for service use. Prior to opening, the pavement shall be cleaned. For the purpose of establishing an adjusted unit price for pavement, units to be considered separately are defined as 300 lineal metes of pavement in each paving lane starting from the end of the pavement bearing the smaller station number. The last unit in each lane shall be 300 meters plus the fractional part of the 300 meters remaining. When the measurement of the core from a unit is not deficient more than 5mm from the plane thickness, full payment will be made. When such measurement id deficient more than 5mm and not more than 25mm from the plan thickness, two additional cores at intervals not less than 90 meters shall be taken and used in the average thickness for that unit. An adjusted unit price as provided in 307.5.1 (b) will be paid. Other areas such as intersections, entrances, crossovers, ramps, etc., shall be considered as one unit, and the thickness of each unit will be determined separately. Small irregular unit areas may be included as part of another unit. At such points as the “Engineer” may select in each unit, one core shall be taken for each 83.5 square meters of pavement, or fraction thereof, in the unit. If the core is deficient in thickness by more than 5mm but not more than 25mm from the plan thickness, two additional cores shall be taken from the areas represented and the average of the three cores determined. If the average measurement of these three cores is not deficient by more than 5mm from the plan thickness, full payment will be made. If the thickness of the three cores is deficient by more than 5mm but not more than 25mm from the plan thickness, an adjusted unit price, as provided in 307.5.1 (b), will be paid for the area represented by these cores. In calculating the average thickness of the pavement, measurements which are in excess of the specified thickness by more than 5mm shall be considered as specified thickness plus 5mm, and measurements which are less than the specified thickness by more than 25mm shall not be included in the average. When the measurement of any core is less than the specified thickness by more than 25-mm, the actual thickness of the pavement in this area shall be determined by taking additional cores at not less than 3-meters intervals parallel to the centerline in each direction from the affected location, until each direction from the affected location, until in each direction a core has found deficient by more than 25-mm. Areas found deficient in thickness by more than 25-mm shall be evaluated by the “Engineer” and, if in his judgment the deficient areas warrant removal, they shall be removed and replaced with concrete of the thickness shown on the plans. Exploratory cores for deficient thickness will not be used in average for adjusted unit price. 307.5 METHOD OF MEASUREMENT The quantity to be paid for shall be the number of square meters of either plain or reinforced pavement as specified in place, completed and accepted, less deductions as hereinafter required for deficient thickness. 307.6 BASIS OF PAYMENT 307.6.1 General

Page 110: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

110

The accepted quantities of concrete pavement will be paid for at the contract unit price per square meter which price and payment shall be full compensation for furnishing and placing of all materials, including any dowels, steel reinforcement and joint material, provided however, that for any pavement found deficient in the thickness by more that 5-mm, but not more than 25-mm, only the reduced price stipulated below shall be paid. No additional payment over the unit contract bid price shall be made for any pavement which has an average thickness in excess of that shown on the plans. Payment will be made under:

PAYMENT NUMBER DESCRIPTION UNIT OF MEASUREMENT

307 Portland Cement Concrete Pavement

Square Meter

Price adjustments, where the average thickness of pavement is deficient in thickness by more than 5-mm but not more than 25-mm, payment will be made at an adjusted price as specified in the following table:

CONCRETE PAVEMENT DEFICIENCY

DEFICIENCY INTHICKNESS DETERMINED BY CORES (mm)

PROPORTIONAL PART OF CONTRACT PRICE ALLOWED (%)

0.00 to 5.00 100

5.01 to 7.62 80

7.63 to 10.16 72

10.16 to 12.50 68

12.51 to 19.00 57

19.01 to 25.00 50

When the thickness of pavement is deficient by more than 25-mm and in the judgment of the “Engineer”, the area of such deficiency should not be removed and replaced, there shall be no payment for the area retained. 307.6.2 ACCEPTANCE OF CONCRETE The strength of concrete shall be deemed acceptable if the average of three consecutive strength test results is equal to 650 psi for flexural strength or exceeds the specified strength required. Concrete deemed to be not acceptable using the above criteria may be rejected unless the Contractor can provide evidence, by means of core tests, that the quality of concrete represented by the failed test results is acceptable in place. These cores shall be taken in accordance with AASHTO 124 and soaked for 24 hours prior to test. Concrete in the area represented by the cores will be deemed acceptable for the average strength of the cores is equal to at least 85% and of no single core is less than 75% of the specified strength.

Page 111: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

111

ITEM – 703 PILING WORKS

703.1 SCOPE OF WORK

This section covers the technical requirements for the materials, workmanship, fabrication, installation and testing of piling works under contract.

703.1.2 General Provisions

The following publications listed below, but referred to thereafter by basic designation only, form part of this specification to the extent indicated by the references thereto:

AWS D1.1 Structural Welding Code

ASTM D114.3 Load Settlement Relationship

For technical requirements covering design, manufacture and installation of Pre-stressed Concrete Piling which is also covered under this Contract, pertinent provisions of the Pre-stressed Concrete Institute (PCI) as specified in their PCI Journal/March-April 1977 entitled “Recommendation Practice for Design, Manufacture and Installation of Pre-stressed Concrete Piling” shall be followed.

The contractor shall be deemed to have included in his unit price allowances to cover all risks that may arise during or connection with the piling works.

703.2 FABRICATION

703.2.1 Pre-Cast Reinforced Concrete Piles (RC Piles):

RC piles shall be fabricated as far as practicable in single length in accordance with Item 405 – Concrete Works. Compressive strength of concrete at 28 days shall be 27.60 MPa or 281.63 kg/sq.m cm.

Fabricated RC piles shall be free from bends and twist. Where bends shall exist, in any section along the entire length of the pile, it shall not exceed the 200 mm permissible tolerance.

703.2.2 Pre-stressed Concrete Piles (PC Piles)

Page 112: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

112

It is required that fabricators are regularly engaged in the production of pre-stressed concrete piles or other pre-stressed concrete products for a period of not less than three (3) years, and show a quality capability through certification in the PCI Plant Certification Program or through an established quality control program based on PCI Manual MNL 166-77. Manufacturing plants producing different methods such as long-line continuous production in either fixed forms or by using a slip from machine, and segmental joining by post-tensioning and/or welding.

PC Piles shall be fabricated with a minimum specified concrete strength of f`c=34.50 Mpa or 352.04 kg/ sq.cm. (Class A.A.A concrete) or as specified in the plants and drawings. The use of fibrin 23 or equal as admixture will increase the strength, water proofing and durability of concrete.

703.3 GENERAL REQUIREMENTS

Soil investigation as required by the “Engineer” shall be done prior to piling works.

703.3.1 Pile Length

Pile length shown on the Plans are for estimating purposes only and are based upon probable lengths remaining in place in the completed structure. The Contractor shall determine the final length of piles required to develop the bearing power specified in the Plans. This may be accomplished by the following methods:

1. Test piles length as directed by the “Engineer” shall be driven at such points as

designated by the “Engineer” base on result of sub-soil investigation report and plans that they may be left in place, cutoff, and become a part of the permanent structure. From their performance under driving, the “Engineer” will determine the lengths of piles required.

2. Computing the length by the Hiley Formula or other formula acceptable to the “Engineer”.

The above shall not be constructed to mean that driving may stop when such penetration as shown on the plans has been secured, but that driving shall continue in every case until the total penetration obtained and or pile has been driven to “refusal” to the satisfaction of the “Engineer” regardless of the fact that sufficient bearing capacity was determined by formula may be obtained at a lesser depth.

All piles which have passed to the required test shall be marked indicating the data shown below or any other approved manner not to be easily destroyed.

1. Dimension 2. Production Number 3. One meter length interval markings

Page 113: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

113

703.4 TESTING

The process of pile production at the manufacturer’s factory shall be inspected by the “Engineer” or his authorized representatives, whenever he considers necessary.

703.4.1 Storage and Handling

When raising or transporting piles, Contractor shall provide sling or other equipment to avoid any appreciable bending of the pile or cracking of the concrete. Piles shall be lifted only on designated points with hooks provided for each pile. Piles materially damaged in handling or driving shall be removed at site and replaced by the Contractor at his own expense, as directed by the “Engineer”.

Concrete piles shall be so handled at all times as to avoid breaking or chipping the edges.

Piles may be stored at open air but on wooden sleepers to be placed in a manner not to cause excessive bending.

Piles shall be stacked on a stable yard preferably near the loading area for driving and shall not be stacked more than 3 layers high.

703.5 PENETRATION AND SET

The pile shall be driven down either to the required levels or until the required blow counts are obtained. Internationally recognized driving formula, such as Hiley’s formula or wave equation analysis shall be utilized to compute the stress of pile while driving the bearing capacity of piles.

703.5.1 Pile Driving

Pile heads shall be protected against damage by utilizing a driving helmet and duly designated to centralized the driving impact.

The pile leaders shall be of sufficient rigidity and fixity during driving operations.

The procedure and the data for hammer to be used for driving shall be submitted to the “Engineer” prior to starting the driving operation. The “Engineer’s” approval of the pile driving equipment will not release the contractor in any way from the responsibility for the adequacy of the selected equipment.

Page 114: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

114

All driving surfaces shall be cut square prior to commencement of driving. Every effort shall be made to drive continuously without interruption.

Unless otherwise directed by the “Engineer”, all piles shall be driven to their full strength from the required pile tip up to the cut-off elevations, as indicated on the Plans. The piles which have not reached the required penetration rate per blow when the top has been driven to the cut-off elevations shall be spliced as specified and driven to a depth sufficient to develop the required penetration rate per blow.

The Contractor shall repair all damage to piles during driving. A minimum cut-off allowance, not less than 600 mm shall be provided for all corrections at in place splices and at all the pile heads for removal after completion of the driving.

The piles which have been uplifted after being driven shall be re driven to the required penetration and as to “refusal” after completing other activities in the nearby area.

Splicing of piles if any, shall be subjected to the “Engineer’s” approval. The Contractor may propose and submit splicing procedure together with plans, working drawings and pile driving methodology.

703.6 SPECIAL CONDITIONS

1. Jetting: Where satisfactory penetration is not obtained, water jets may be used subject

to the approval of the “Engineer”. The number of jets and the volume and pressure of water shall be sufficient to freely erode the materials adjacent to the pile. Before the desired penetration is reached, the jet shall be removed at least one meter short of the minimum specified penetration and the pile shall be finally set under normal driving operations.

2. Drilling: When it has been satisfactorily demonstrated to the “Engineer” that the pile

can not be driven in the regular manner or by use of water jets, undersized pilot hole may be drilled below the pile tip to facilitate the driving.

When the drilling is permitted, the pilot hole drilled shall have a diameter of not more than 75% of the cross-section of the driven pile and the drilling shall continue only through the strata of hard material obstructing the driving. The Contractor shall make every effort to provide a stable hole of uniform diameter in order to avoid losing the soil-pile friction along the length of the pilot hole. Before the desired penetration is reached, the drill has be removed at least one meter short of the minimum specified penetration and the pile shall be finally set under normal driving operation.

703.7 PILE DRIVING RECORDS

Page 115: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

115

Driving records shall be prepared for each pile on Form No. 001 attached at the end of this Section and shall be submitted to the “Engineer” daily. Driving record shall include type of hammer, pressure, number of blows per 300mm length of pile and final tip elevation.

703.7.1 Permissible Tolerance

1. Position error in plan : - 100 mm

2. Cut-off elevation : - 10 mm

Pulling the head of the pile to attain the design position shall not be permitted.

703.8 MEASUREMENT AND PAYMENT

Quantity of Cast Reinforced Concrete Piles to be paid for shall be measured by the lineal meter or a fraction thereof placed in accordance with the contract and as ordered, specified and accepted by the “Engineer”.

Driving of Reinforced Concrete Piles to be paid for shall be measured by the lineal meter or a fraction thereof placed in accordance with the Contract and accepted in completed work, excluding pile length cut from driven piles to adjust the elevation as required and shown on the Plans.

No payment for cutting of piles shall be made, as this item is deemed incidental to the cost of driving.

Page 116: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

116

ITEM 405 – CONCRETE WORKS

405.1 SCOPE OF WORK

This Section includes all cast-in-place and pre-cast concrete and related works required under these Specifications, except Portland Cement Concrete Pavement. 405.2 GENERAL PROVISIONS Concrete shall consist of mixture of Portland Cement, fine aggregate, coarse aggregate, admixtures when specified, and water mixed in the proportions specified or approved by the Engineer. The following publications of the issued, listed below, but referred to thereafter by basic designation only, form a part of this Specification to the extent indicated by the reference thereto: 1. American Concrete Institute ( ACI ), Standard:

ACI 211.1 Recommended Practice for Selecting Proportions for Structural Concrete.

ACI 214 Recommended Practice for Evaluation of Compressive Test Results of Field Concrete.

ACI 305 Recommended Practice for Hot Weather Converting

ACI 315 Manual of Standard Practice for Detailing Concrete Structure

ACI 318 Building Code Requirements for Reinforced Concrete, with Commentary

2. American Society for Testing and Materials ( ASTM ) Publications:

A 82 Cold-Drawn Steel Wire for Concrete Reinforcement

A 185 Welded Steel Wire Fabric Concrete Reinforcement

A 615 Deformed and Plain Billet-Steel Bars for Concrete Reinforcement.

A 616 Rail-Steel Deformed and Plain Bars for Concrete Reinforcement

A 617 Axle-Steel Deformed and Plain Bars for Concrete Reinforcement

C 31 Making and Curing Concrete Test Specimens in the field

C 33 Concrete Aggregate

C 39 Compressive Strength of Cylindrical Concrete Specimens

C 42 Drilled Cores and Sawed Beams of Concrete, obtaining and testing

C 94 Ready-Mixed Concrete

Page 117: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

117

C 143 Slump of Portland Cement Concrete

C 150 Portland Cement

C 171 Sheet Materials for Curing Concrete

C 172 Sampling Fresh Concrete in the ASTM Publication

C 173 Air Content of Freshly Mixed Concrete by the Volumetric Method

C 192 Making and Curing Concrete Test Specimens in the Laboratory C 231 Air Content of Freshly Mixed Concrete by the Pressure Method

C 260 Air-Entraining Admixture for Concrete C 309 Liquid Membrane-Forming Compounds for Curing Concrete

C 494 Chemical Admixture for Concrete

C 1751 Preformed Expansion Joint Fillers for Concrete Paving and Structural Construction.

(Non-extruding and Resilient Bituminous Types ) 3. American Welding Society ( AWS )

D.12.1 Welding Reinforcing Steel, Metal Inserts and Connections in Reinforced Concrete Construction.

4. Philippine Standard (PS) 681 – 04 .02, 1975

DSB 275 Steel Bars for Concrete Reinforcement 405.3 SUBMITTALS Refer to General and Special Requirements of the Contract. Test Reports and Certificates shall be furnished for approval before delivery of certified or testes materials to the Project Site. 405.4 CLASSES OF CONCRETE AND USAGE 405.4.1 STRENGTH REQUIREMENTS: Concrete of the various classes indicated and as required under other sections, and unless specified in the plan shall be proportioned and mixed for the following strength:

Class Size of Aggregate (mm)

Specified Compressive Strength 28 days f’c = kg/sq.cm.

A-A 25 420

A 40 240

B 40 210

Page 118: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

118

C 50 175

Seal 25 240

In addition to the above, the maximum permissible water-cement ratio by weight shall not be greater than 0.55 unless otherwise the Engineer. 405.4.2 USAGE Concrete of the various classes to be used shall be as follows: 1. Class A-A concrete: For pre-stressed concrete structures and members. 2. Class A concrete: For pre-cast structure, superstructures and heavily reinforced substructures

which include slabs beams, walls, girders, columns, arch ribs, box culverts, reinforce abutments, retaining walls, reinforced footings and foundation of buildings.

1. Class B concrete: Footings, pedestals, foundation of equipment, retaining wall, curb, slab on

grade, pipe bedding gravity walls, unreinforced or with only a small amount of reinforcement. 2. Class C concrete: Leveling concrete. 3. Class Seal: Concrete deposited in water 405.4.3 Additives acceptable to the Engineer shall be used for all reinforced concrete structures exposed to salt water action. 405.5 MATERIALS 405.5.1 CEMENT Except when specifically approved by the Engineer only one brand of cement shall be used for any individual structure. In determining the approved mix, only Portland Cement shall be used. 1. Portland Cement: ASTM C 150, Type I 2. High-Early Strength Portland Cement Type III may be used for pre-cast concrete. Cement Type III

shall conform to ASTM C 150 with a tricalcium aluminate limited to 8 percent. 405.5.2 ADMIXTURES Shall conform to the following: 1. Air-Entraining Admixtures: ASTM C 260 2. Admixture other than air-entraining agent shall conform to ASTM C 494. 3. Admixture containing chloride ions, or other ions producing deleterious effects, shall not be

used.

Page 119: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

119

405.5.3 AGGREGATES: 1. Coarse Aggregates: Conforming to ASTM C 33 and having nominal sizes passing 38.0 mm to

19.00 mm, 19.0 mm to 9.5 mm to No. 4 sieve. The material shall be well graded between the limits indicated and individually stocked piled. It shall be the Contractor’s responsibility to blend the materials to meet the gradation requirements for various type of concrete as specified herein.

a. Nominal sizes for combined gradation shall be as follows: Table 405.1 - Grading Requirements for Coarse Aggregate

Sieve Designation Mass Percent Passing for

Standard Alternate Class Class Class Class Class

Mm US Standard B C A A-A Seal

63 2 ½ “ 100

50 2 “ 95-100 100

37.50 1 ½ “ 95-100 100

25 1 “ 35-70 90-100 100

19.0 ¾” 35-70 90-100 100

12.5 ½ “ 10-30 25-60 90-100

9.5 3/8 “ 10-30 20-55 40-70

4.75 No. 4 0.5 0.5 0.10 0.10 0.15

The measured cement content shall be within plus ( + ) or minus ( - ) 2 mass percent of the design cement content. 2. Fine aggregate: ASTM 33 except for gradation which has been revised to meet local conditions.

Unless otherwise required by the Engineer, grading of fine aggregate shall be as follows:

ASTM Sieve By Weight Passing

9.5 mm ( 3/8”) 100

No. 4 90-100

No. 8 80-100

No. 16 50-90

No. 30 25-60

No. 50 10-30

No. 100 2-10

a. Grading of fine aggregate shall be reasonably uniform and fineness modulus thereof

shall not vary more than 0.2 from that of the representative sample on which mix proportions of concrete are based.

b. Due care shall be taken to prevent segregation. 405.5.4 WATER The water used in concrete, mortar and grout shall be free from objectionable quantities of silt, organic matter, alkali, salts and other impurities.

Page 120: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

120

405.5.5 ANCHORAGE ITEMS: a. Dowels for anchoring mechanical items to concrete shall be of manufacturer’s standard and of

types required to engage with the anchors to be provided and installed therein under other sections of these Specifications and shall be subject to the approval of the Engineer.

b. Slots shall be dovetail-type, of not lighter than 24-gauge zinc-coated steel, with filler that

prevents concrete or water from entering and that can be easily removed or punctured for installing anchors.

c. Inserts for suspended ceilings: Wire inserts for attachment of wire hangers for suspended

ceilings shall not be lighter than 7-gauge zinc-coated steel wire. When flat iron or steel hangers are to be used zinc-coated inserts of the same section shall be set in the concrete.

d. Inserts for bolt hangers shall be of malleable iron or of cast of wrought steel. Inserts for bolt

hangers shall either be threaded or slotted as required by the types of hanger to be used. Threaded inserts shall have integral lugs to prevent turning.

405.5.6 CURING MATERIALS: a. Impervious Sheet Materials: ASTM C 171, type optional except that polyethylene film, of used,

shall be white opaque. b. Burlap of commercial quality, non-staining type, consisting of 2 layers opaque. c. Inserts for suspended ceilings: Wire inserts for attachment of wire hangers for suspended

ceilings not be lighter than 7-gauge zinc-coated steel wire. When flat iron or steel hangers are to be used zinc-coated inserts to the same section shall be set in the concrete.

d. Inserts for bolt hangers shall be of malleable iron or of cast of wrought steel. Inserts for bolt

hangers shall either be treated or slotted as required by the types of hanger to be used. Threaded inserts shall have integral lugs to prevent turning.

405.5.7 FORM MATERIALS: Coatings and Ties are specified under 405.5.14, Form work of this Specification. 405.5.8 REINFORCEMENT a. Deformed Bars conforming to PS 681-04.02 ( DSB 275 ); 1975 First Revision, or conforming to Bar

Reinforcement of Item 401-Reinforcing Steel. b. Mesh Reinforcement conforming to JIS G 3551 or equivalent. 405.5.9 EXPANSION JOINT FILLER: Preformed joint filler conforming to ASTM 17521, type and class suitable for the use intended. 405.5.10 VAPOR BARRIER:

Page 121: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

121

a. Asphalt-saturated waterproof reinforced draft paper. b. Polyethylene sheeting shall not be less than 0.2 mm nominal thickness.

405.5.11 WATERSTOPS SHALL BE OF THE FOLLOWING: Copper conforming to ASTM B 370, 567 gms weight: or stainless steel conforming to ASTM A 167, type 304 L, finish 2D or equivalent, annealed 0.94 mm nominal thickness. 405.6 SAMPLES AND TESTING Testing except as otherwise specified herein, shall be performed by an approved testing agency as proposed by the Contractor and approved by the Engineer at no additional cost to the Government.

Cement: Sampled either at the mill or at the site of the work and tested by an approved independent commercial national testing laboratory at no additional cost to the Government. Certified copies of laboratory test reports shall be furnished for each lot of cement and shall include all test data, results, and certificates that the sampling and testing procedures are in conformance with the Specifications. No cement shall be used until notice has been given by the Engineer that the test results are satisfactory. Cement that has been stored, other than in bins at the mills, for more than 3 months after delivery to the Site shall be retreated before use. Cement delivered at the Site and later fond under test to be unsuitable shall not be incorporated into the permanent works.

Aggregate: Tested as prescribed in ASTM C33. Reinforcement: Certified copies of mill certificate of tests shall accompany deliveries of steel

bar reinforcement. If requested by the Engineer additional testing of the materials shall be made at the Contractor’s expense.

Concrete Tests: Provide for test purposes, one set of the test specimens taken under the

instruction of the Engineer from each 75 cu. m. or fraction thereof of each class of concrete placed or at least one set of test specimens shall be provided for each class of concrete placed in each 8-hour shift. Each shall consist of three test specimens, and shall be made from a separate batch. Samples shall be secured in conformance with ASTM C172. Test specimen shall be made, cured, and packed for shipment in accordance with ASTM C31. Cylinders will be tested by and at the expense of the Contractor in accordance with ASTM C39. Test specimens will be evaluated separately, by the Engineer for meeting strength level requirements for each with CONCRETE QUALITY of ACI 318 . The standard age of test shall be 28 days, but 7 days tests may be used, with the permission of the Engineer, provided that the relation between the 7-day and 28-day strengths on the concrete is established by tests for the materials and proportions used. When samples fail to conform to the requirements for strength, the Engineer shall have the right to order a change in the proportions of the concrete mix for the remaining portions of the work at no additional cost to the Government.

Test of Hardened Concrete in or Removed from the Structure: When the result of the

strength tests of the control specimens indicates in the concrete as placed

Page 122: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

122

does not meet the Specifications requirements or where there is other evidence that the quality of the concrete is below the specification requirements, test on core of in-place concrete shall be made in conformance with ASTM C 42.

a. Core specimens shall be obtained by the Contractor and shall be tested. Any

deficiency shall be corrected; if the Contractor elects, he may submit a proposal for approval that a load test is made. If the proposal is approved, the Contractor and the test results evaluated by the Engineer in conformance with 20 of ACI 318 shall make the load test. The cost of the load tests shall be borne by the Contractor. If any concrete shows evidence of failure during the load test or fails the load test as evaluated the deficiency shall be corrected in a manner approved by the Engineer at no additional cost to the Government.

Admixtures: All admixtures shall be tested and those that have been in storage at the

project Site for longer than 6 months shall not be used until proved by retest to be satisfactory.

a. Air-Entraining Admixtures: Tested for conformance to the referenced

specification under which it is furnished. The testing shall be conducted with cement and aggregate proposed for the project.

b. Other admixtures if approved, tested for conformance to the referenced

specifications under which it is furnished. The testing shall be conducted with cement and aggregate proposed for the Project.

405.7 STORAGE Storage accommodation for concrete materials shall be subject to approval and shall afford easy access for inspection and identification of each shipment in accordance with test reports.

Cement: Immediate upon receipt at the Site, the Cement shall be stored separately in a dry weather tight, properly ventilated structure, with of adequate provisions for prevention or absorption of moisture. Cement bags should not be stacked more than 13 bags high. The cement most likely to have been exposed to moisture or stored in bags for more than 3 months shall not be used unless proven by test to be in good condition.

Aggregate: Stored to assure good drainage, to preclude inclusion of foreign matter, and to

preserve the gradation. 405.8 FORMWORK Forms: Designed, constructed, and maintained so as to insure that, after removal, the

finished concrete members will have true surfaces, free of offset, waving or bulges, and will conform accurately to the indicated shapes, dimensions, .lines, elevation, and positions in the plan. Form surfaces that will be contact with concrete shall be thoroughly cleaned before each use.

Page 123: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

123

405.8.1 DESIGN Studs and wale shall be spaced to prevent deflection of form materials. Forms and joints shall be sufficiently tight to prevent leakage of grout and cement paste during placing of concrete. Juncture of formwork panels shall occur at vertical control joints, and construction joints. Forms placed on successive units for continuous surfaces shall be fitted in accurate alignment to assure smooth completed surface free from irregularities and signs of discontinuity. Temporary opening shall be arranged to wall and where otherwise required to facilitate cleaning and inspection. Forms shall be readily removable without impact, shock, or damage to the concrete. 405.8.2 CONCRETE SURFACES TO BE EXPOSED Form surfaces that will be in contact with concrete shall be of materials that is non reactive with concrete and that will produce concrete surfaces equivalent in smoothness and appearance to that produced by new 1.2 x 2.4 meters plywood panels approved by the Engineer. Smaller size panels shall be used only where required by opening on the above architectural lines or joints, with each area less than 1.2 meters wide formed with single panel accurately cut to the required dimensions. Cut surfaces shall be smooth and treated with form coating. Panel joints that will being contact with concrete shall be smooth and free of offset. Form materials with defects that will impair the texture and appearance of finish surfaces shall not be used. Form lining, if used, shall be installed over solid backing. Column forms shall be made with a minimum number of joints. 405.8.3 CONCRETE SURFACES TO BE UNEXPOSED Form surfaces that will be in contact with concrete shall be sound, tight lumber or other material producing equivalent finish. 405.8.4 SAMPLE CONCRETE PANELS Before constructing structural formwork, sample concrete panel for exposed or painted concrete shall be constructed and approved for smooth finish specified in paragraph FINISHES OF CONCRETE OTHER THAN FLOOR SLABS. The panel shall not be less than 1.8 meter long by 1.2 meter high. Concrete shall be of the approved design mix. Forms shall include a typical joint between form panels. Sample panels shall show tie-hole patching and smooth finish. Sample panels shall be constructed at approved locations, not as part of the structure, and shall be protected from construction operations, weather, and other damage until acceptance of the completed concrete work. The approved sample panel shall be representative of the smooth concrete finish required in the work. 405.8.5 Form Ties shall be factory-fabricated, removable or snap-off metal ties of design that it will

not allow form deflection and will not spall concrete upon removal. Solid backing shall be provided for each tie. Ties shall be fitted with devices that will leave holes in the concrete surface no less than 9 mm nor more than 2.5 mm in diameter and of depth not less than 25 mm.

The portions of the tie remaining in the concrete after removal of the exterior parts shall not project beyond the surface of the concrete and shall be at least 38 mm back from any surface of the concrete that will be exposed, painted, damp-proofed, water-proofed, or receive direct applications of plaster. Bolts and rods that are to be completely withdrawn shall be coated with a non-staining bond breaker.

Page 124: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

124

405.8.6 CHAMFERING External corners of columns, girders, beams, foundation wall projecting beyond overlaying masonry, and other external corners that will be exposed shall be chamfered, beveled or rounded, not less than 19 mm, by molding in the forms unless the drawings specifically state that chamfering is to be omitted. 405.8.7 COATINGS Forms for exposed surfaces shall be coated with form oil or form-release agent before reinforcement is placed. The coating shall be a commercial formulation of satisfactory and proven performance that will not bond with, stain, or adversely affect concrete surfaces, and will not impair subsequent treatment of concrete surfaces depending upon or adhesion nor impede the wetting of surfaces to be cured with water or curing compounds. The coating shall be used as recommended in the manufacturer’s printed or written instructions. Forms for unexposed surfaces may be wet with water in lieu of coating immediately before placing of concrete. Surplus coating on form surfaces and coating on reinforcement steel and construction joints shall be removed before placing concrete. 405.8.8 Removal of forms shall be in a manner to insure complete safety of the structure after the

following conditions have been met. Where structural as a whole is supported on shores, forms for beam and girder sides, columns, and similar vertical structural members may be removed after 24 hours, provided concrete is sufficiently hard not to be injured thereby.

Supporting forms of shoring shall not be removed until structural members have acquired sufficient strength to support safely their own weight and any construction and/or storage load to which they may be subjected, but in no case shall they be removed in less than 7 days, nor shall forms used for curing be removed before expiration of curing period except as specified in paragraph CURING. Care shall be taken to avoid spalling the concrete surface or damaging concrete edges. Wood forms shall be completely removed.

a. Control Tests: Results of suitable control tests will be used as evidence that concrete has attained sufficient strength to permit removal of supporting forms. Cylinders required for control tests shall be provided in addition to those otherwise required by the specifications. Test specimens shall be removed from molds at end of 24 hours and stored near to the structure as possible at points of sampling, shall receive insofar as practicable the same protection from the elements during curing as given in those portions of the structure which they represent, and shall not be removed from the structure for transmittal to the laboratory prior to expiration of three-fourths of the proposed period before removal of forms. Supporting forms or shoring shall not be removed until control-test specimens have attained strength of at least 15.68 Mpa. The newly unsupported portions of the structure shall not be subject to heavy construction or material loading.

b. Tie-Rods to be entirely remove from the wall shall be loosened 24 hours after concrete is

placed, and form ties, except for a sufficient number to hold forms in place, may be removed at that time. Ties wholly withdrawn from wall shall be pulled toward the face that will be concealed from view in the permanent work.

Page 125: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

125

405.9 REINFORCEMENT 405.9.1 REINFORCEMENT Fabricated to shapes and dimensions shown and shall be placed where indicated. Reinforcement shall be of loose or flaky rust and mill scale, or coating, and any other substance that would reduce or destroy the bond. Reinforcing steel reduce in section shall not be used. After any substantial delay in the work, previously placed reinforcing steel for future binding shall be inspected and cleaned. Reinforcing steel shall not be bent or straightened in a manner injurious to the steel or concrete. Bars with kinks or bends not shown on the Drawing shall not be placed. The use of heat to bend or straighten reinforcing steel shall not be permitted. Bars shall be removed as necessary to avoid interference with other reinforcing steel, conduits, or embedded items. If bars are move more than one bar diameter, the resulting arrangement of bars including additional bars necessary to meet structural requirement shall be approved before concrete is places. In slabs, beams, and girders, reinforcing steel shall not be spliced at points of maximum stress unless otherwise indicated. Unless otherwise shown on the Drawing, laps or splices shall be 40 times the reinforcing bar diameter. 405.9.2 The nominal dimensions and unit weights of bar designation shall be in accordance with the

following table:

Nominal Diameter Nominal Perimeter (mm)

Nominal Sectional Area (sq.mm)

Unit Weight (Kg/m)

6 mm 18.8 28.27 0.222

10 mm 31.4 78.54 0.616

12 mm 37.7 113.10 0.888

16 mm 50.3 201.10 1.579

20 mm 62.8 314.2 2.466

25 mm 78.5 490.9 3.854

28 mm 88.0 615.7 4.833

32 mm 100.5 804.2 6.313

36 mm 113.1 1017.9 7.991

40 mm 125.7 1256.6 9.864

50 mm 157.1 1963.5 15.413

405.9.3 Wire-mesh reinforcement shall be continuous between crack control joints in slabs on grade

and shall be continuous between expansion joints in other slabs. Laps shall be at least one full mesh plus 50 mm staggered to avoid continuous lap in either direction, and securely wired or clipped with standard clips.

405.9.4 Dowels in slabs on grade shall be installed at right angles to construction joints and

expansion joints. Dowels shall be accurately aligned parallel to the finished surface, and shall be rigidly held in place and supported during placing of the concrete. One end of dowels shall be oiled or greased.

405.9.5 Tie bard on grade shall be placed at right angles to construction joints. Tie bars shall be

accurately aligned parallel to the finished surface, and shall be rigidly held in place and supported during placing of the concrete.

Page 126: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

126

405.9.6 Supports shall be provided in conformance with ACI 315 and ACI 318 unless otherwise indicated or specified. Wire ties, when used, shall be a 16-gauge black annealed wire and shall have end pointing away from the form.

a. For slabs on grade: Reinforcement shall be supported on pre-cast structure units spaced

at intervals required by size of reinforcement used, to keep reinforcement the minimum height specified or indicated above the underside of slab or footing.

b. For slabs other than on grade: Supports for which any portion will be less than 25 mm

concrete surface that will be exposed to view or painted shall be plastic-coated steel conforming to ACI 315, stainless steel, pre-cast concrete units, or plastic. Pre-cast concrete units shall be wedge-shaped, not larger than 9 cm, and of thickness equal to that indicated for concrete protection of reinforcement. The pre-cast units shall have cast-in galvanized tie wire booked at top for anchorage and shall blend with concrete surfaces after finishing is completed.

c. Concrete shall be of the same quality as for slabs, but with coarse aggregate reduced.

Plastic supports shall be of strength and spaced so as not to be deformed weight to which it is subjected.

405.9.7 Welding of reinforcing bars shall only be permitted where shown; all welding shown shall be

performed in accordance with AWS D 12.1 405.9.8 Exposed reinforcement bars, dowels and plates lm13 intended for bonding with future

extensions shall be protected from corrosion. 405.9.9 Concrete Protection for Reinforcement

a. The minimum concrete cover of reinforcement shall be as indicated on the Drawings and as shown in the table below.

b. Tolerance for Concrete Cover of Reinforcing Steel other than Tendons.

Minimum Cover Maximum Variation

7.5 cm. Or more 9 mm

less than 7.5 cm. 6 mm

405.10 PROPORTIONS OF CONCRETE MIXES 405.10.1 Trial design batches and testing to meet requirements of the classes of concrete

specified shall be the responsibility of the Contractor. The design mix shall be of consistencies specified hereafter in Test for Slump, unit weight, and air content shall be performed in the field under the presence of the Engineer.

405.10.2 Entrained-Air Content: Air-entrainment shall be produced by adding an air-entraining agent at the mixer. Air Content in concrete by volume shall be maintained at 5 to 7 percent, as determined by ASTM C 231. 405.10.3 Concrete Proportioning: Samples of approved aggregate shall be obtained in accordance with the requirements of ASTM D 75. Samples of materials other than aggregate shall

Page 127: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

127

be representative of those proposed for the project and shall be accompanied by the manufacturer’s test reports indicating compliance with applicable specified requirements. Trial mixes having proportions, consistencies and air content suitable for the work shall be made based on ACI Standard 211.1 using at least three different water-cement ratios which will produce a range of strength encompassing those required for the work. Trial mix shall be designed for maximum permitted slump and air content. The temperature of concrete in each trial batch shall be reported. For each water-cement ratio at least three test cylinders for each test age shall be made and cured in accordance with ASTM C 39. From these test results, a curve shall be plotted showing the relationship water-cement ratio and strength. 405.10.4 Average Strength: For each portion of the structure, proportions shall be selected so that

the maximum permitted water-cement ration is no exceeded and so as to produce an average strength to exceed the specified strength fc’ by the amount indicated below. Where production facility has a standard deviation record determined in accordance with ACI 214, based on 30 consecutive strength tests of similar mixture proportions as proposed it shall be used in selecting average strength.

The average strength used as the basis for selecting proportions shall exceed the specified strength fc’ by at least:

1. 30 kg/sq. cm. If standard deviation is less than 20 kg/sq. cm. 2. 40 kg/sq. cm. If standard deviation is 20 to 30 kg/sq. cm. 3. 50 kg/sq. cm. If standard deviation is 30 to 40 kg/sq. cm. 4. 60 kg/sq. cm. If standard deviation is 40 to 50 kg/sq. cm. 5. If the standard deviation exceed 50 kg. Sq. cm. Or if a standard deviation record is not

available, proportions shall be selected to produce an average strength of at least 70 kg/sq. cm. Greater than the specified strength.

405.10.5 Corrective additions to remedy deficiencies in aggregate gradation shall be used only on

written approval of the Engineer. 405.4.17,6 Slump: Tests shall be made in conformance with ASTM C 143, and unless otherwise specified by the Engineer slump shall be within the following limits:

Structural Element Slump for Vibrated Concrete

Minimum Maximum

Pre-cast Concrete 5 cm 7 cm

Wall, column and grade beam, 25cm maximum thickness

5 cm 7 cm

All other concrete 5 cm 10 cm

Lean Concrete 10 cm 20 cm

405.11 BATCHING AND MIXING 405.11.1 The Contractor shall provide a semi-automatic or better batching plant and concrete

Page 128: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

128

mixing equipment having a sufficient capacity to satisfy concrete placement requirements. 405.11.2 B ATCHING PLANT 1. Arrangement: Separate bins or compartment shall provided for each size or classification of

aggregate and for bulk Portland cement. The compartments shall be of ample size and so constructed that the materials will be maintained separately so that the flow of each material into its batcher is stopped automatically when the designated weight has been reached.

2. Aggregates may be weighed in separate weigh batches with individual scales, or cumulatively on

one weigh batcher with one scale. Bulk cement shall be weighed on a separate scale in a separate weigh batcher. Water may be measured by weight or by volume. If measured by weight, it shall not be weighed cumulatively with another ingredient. Batching controls shall be so interlocked that the charging mechanism cannot be opened until the scales have returned to zero. These requirements can be satisfied when actuated by one or more starting mechanism.

A semi-automatic batcher control shall start the weighing operation of each material and stop automatically when the designated weight of each material has been reached and interlocked in such a manner that the discharge device cannot be actuated until the indicated material is within the applicable to tolerance. The plant shall be arranged so as to facilitate the inspection of all operations at all times. Suitable facilities shall be provided for obtaining representative samples of aggregate from each of the bin of compartments for test purposes. Delivery of materials from the batching equipment shall be within the following limits of accuracy.

Materials Percent

Cement 1

Water 1

Aggregate 2

Admixtures 3

3. Water Bather and dispenser for Admixtures: Equipment for batching water and admixtures shall

be provided at the batching plant or included with the paving mixer or truck mixers as required for the type of plant used.

a. Water Batchers: A suitable water measuring device shall be provided which will be capable

of measuring the mixing water within the specified requirements for each batch. The mechanism for delivering water to the mixers shall be such that leakage will not occur when the values are closed.

The filling and discharge valves for the water batcher shall be so interlocked that the discharge valve cannot be opened before the filling valve is fully closed.

b. Dispensers: An accurate mechanical device for measuring and dispensing each admixture

shall be provided. Each device shall be capable of ready adjustment to permit varying of the quantity of admixture to be batched. Each dispenser shall be interlocked with the batching and discharging operations of the water so that each admixture is separately batched and discharge automatically in a manner to obtain uniform distribution throughout the batch in the specified mixing period. When use of truck mixers makes this requirement

Page 129: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

129

impracticable, the admixture dispenser shall be interlocked with the sand batcher. Admixtures will not be combined prior to introduction into water or sand.

3. Moisture Control: The plant shall be capable ready adjustment to compensate for the

varying moisture contents of the aggregate, and to change the weights of the materials being batched. An electric moisture meter shall be provided for measurement of moisture content in the fine aggregate. The sensing element shall be arranged so that the measurement is made near the batcher charging gate of the sand bin or in the sand batcher.

4. Scales: Adequate facilities shall be provided for the accurate measurement and control of

each of the material entering each batch of concrete. The weighing equipment shall conform to the applicable requirements of National Bureau of Standard Handbook 44 or other international standard for scale except that the accuracy shall be within 0.2 percent of scale capacity. The Contractor shall provide standard test weights and any other auxiliary equipment required for checking the operating performance of each scale or other measuring device. Each weighing unit shall include visible springless dial which shall indicate the scale load at all stages of the weighing operation, or shall include a beam scale with a beam balance indicator which will show the scale in balance at zero load and at any beam setting. The indicator shall have an over and under travel equal to at least 5 percent of the capacity of the beam. The weighing equipment shall be arranged so that the plant operator can conveniently observed all dials or indicators.

6. Recorders: a. An accurate recorder or recorders shall produce a graphical or digital record of the scale reading

after each of the aggregates and cementing materials have been batched prior to delivery to the mixer and after the batchers have been discharged ( return to zero reference ). The weights or volume of water and admixtures shall also be recorded if batched at a central batching plant.

b. The recorder shall be housed in a cabinet which shall be capable of being locked. c. The charts or tapes shall clearly indicate the different types of mixes used by stamped letters,

numerals, colored ink or by other suitable means. d. The charts or tapes shall be so marked that variations in batch weights of each type of mix can

be readily observed. e. The charts of tapes shall show time of day ( stamped or pre-printed ) at intervals of not more

than 15 minutes f. The recorded charts or tapes shall become the property of the PMO. g. The recorders shall be placed in a position. Convenient for observation by the plant operator and

the PMO. h. All weighing, indicating, recording and control equipment shall be sufficiently protected against

exposures to dust, moisture and vibration so that there is no interference with proper operation of the equipment.

Page 130: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

130

i. The recorded weights or volumes when compared to the weights or volumes actually batched shall be within the following limits of accuracy.

Materials Percent

Cement 2

Water 2

Aggregate 4

Admixtures 6

405.11.3 CONCRETE MIXERS Stationary mixers, truck mixers, or paving mixers of approved design. The mixers shall have a rated capacity of at least 0.76 cu. m. of mixed concrete, and shall not be charged in excess of the capacity recommended by the manufacturer. Mixers shall be capable of combining the material into a uniform mixture and of discharging this mixture without segregation. Stationary and paving mixers if used shall be provided with an acceptable device to lock the discharge mechanism until the required mixing time has elapsed. The mixing plant shall include device for automatically counting the total number of batches of concrete mixed. The mixers shall be operated at the drum or mixing blade speed designated by the manufacturer on the name plate. The mixing period specified herein are predicated on proper control of the speed of rotation of the mixer drum or blades, and on proper introduction of the materials into the mixer. The acceptability of truck mixers will be determined by uniformity tests as required by ASTM C 94, the mixing time for stationary or paving mixers will be increased when such increase is necessary to secure the required uniformity and consistency of the concrete. Excessive over-mixing requiring additions of water will not be permitted. The mixers and mixer drums shall be maintained unsatisfactory operating condition and mixer shall be kept free of hardened concrete. Mixer blades shall be replaced when worn more than 10 percent of their dept. Should any mixer at any time produce unsatisfactory results, its use shall be promptly discontinued until it is repaired. 1. Stationary Mixers: The mixing time for each batch after all solid materials are in the mixer,

provided that all of the mixing water is introduced before one-fourth of the mixing time has elapsed, shall be one minute for mixers having a capacity of 0.76 cu. m. and for mixers of larger capacities the mixing time shall be increased by 15 second for each additional 0.76 cu. m. or fraction thereof concrete mixed. When stationary mixer is used for partial mixing of the concrete (shrink mixed) the mixing time in the stationary mixer may be reduced to the minimum necessary to item the ingredients (about 30 seconds).

2. Truck Mixers: Conform to the requirements of ASTM C94 including requirements or

uniformity of concrete. When a truck mixer is used either for complete mixing (transit mixed) or to finish the partial mixing done in a stationary mixer, in absence of uniformity test data, each batch of concrete shall be mixed not less than 70 nor more than 100 revolutions of the drum at the rate of rotation designated by the manufacturer of the equipment as mixing speed and at the capacity designated in ASTM C94. If the batch is at least 0.38 cu. m. less than the rated capacity, in the absence of uniformity test data, the number of revolutions at mixing speed may be reduced to not less than 50. Any additional mixing shall be done at the speed designated by the manufacturer of the equipment at agitating speed. Each truck shall be equipped with two counters from which it shall be possible to determine the number of revolutions at mixing speed and the number of revolutions at agitating speed.

Page 131: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

131

3. Vehicles used in transporting materials from the batching plant to the mixers shall have bodies or compartments of adequate capacity to carry the materials and to deliver each batch, separate and intact to the mixer. Bulk cement shall be transported from the batching plant to the mixers in separate closed boxes or compartments, or shall be transported, mixed with the aggregates or placed between layers of aggregates in batch trucks having windproof and rain-proof covers as weather conditions require. Concrete containing batched cement and aggregates shall be placed within the time specified in paragraph: Time interval between mixing and placing under paragraph PLACING CONCRETE. Serially numbered tickets shall be provided for each delivery of batched cement and aggregates and before discharging any batch in mixer. Tickets shall be stamped by time clock to show date and time the loading of each truck was completed. One ticket shall be given to the Engineer before discharging any batch into the mixer.

3. Paving Mixers used at the site of the work: For paving use, paving mixers shall be equipped with

boom and bottom-drum bucket to handle the concrete from the mixer to the form. The bucket shall be of adequate size to handle the complete batch of concrete mixed, and the boom shall be of sufficient length to permit discharge of the concrete into its final position in the form. Paving mixers may be either single compartment drum or multiple compartment drum type.

A sled or box of suitable size shall be attached to the mixer under the bucket so as to catch any spillage of concrete that may occur when the mixer if discharging into the bucket. For use other than paving, the boom is not required; the mixer may discharge directly into the bucket to be used for final placement. Multiple compartment drum paving mixers shall be properly synchronized, and the mixing time shall be determined by including the time required to transfer the concrete between compartment of the drum. If no uniformity test data are available, the mixing time for each; batch, after all solid materials are in the mixer drum, provided that all the mixing water is introduced before one-fourth of the mixing time has elapsed, shall be 1 minute for mixers having a capacity of 0.76 cu. m. and for mixers of larger capacities, the minimum mixing times shall be increased 15 seconds for each additional 0.76 cu. m. or fraction thereof of concrete mixed.

5. Sampling: Provide suitable facilities and labor for obtaining representative samples of

concrete for the Contractor’s quality control and the Employer’s quality assurance testing. The Contractor shall furnish all necessary platform, tools, and equipment for obtaining samples.

405.12 JOINTS 405.12.1 No reinforcement, corner protection angles or other fixed metal items shall be run

continuous through joints containing expansion-joint filler, through crack-control joints in slabs on grade and vertical surfaces.

405.12.2 Pre-molded Expansion Joint Filler 1. Joints with Joint Sealant: At expansion joints in concrete slabs to be exposed, and at the other

joints indicated to receive joint sealant, pre-molded expansion-joint filler strips shall be installed at the proper level below the elevation with a slightly tapered, dressed-and-oiled wood strip temporarily secured to the top thereof to form a groove, when surface dry, shall be cleaned of foreign matter, loose particles, and concrete protrusions, then filled approximately flush with joint sealant so as to be slightly concave after dying.

Page 132: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

132

2. Finish of concrete at joints: Edges of exposed concrete slabs along expansion joints shall be nearly finished with a slightly rounded edging tool.

405.12.3 Construction Joints: Unless otherwise specified herein, all construction joints shall

be subjected to approval of the Engineer. Concrete shall be placed continuously so that the unit will be monolithic in construction. Fresh concrete may be placed against adjoining units, provided the set concrete is sufficiently hard not to be injured thereby. Joints not indicated shall be made and located in a manner not to impair strength and appearance of the structure. Placement of concrete shall be at such rate that surfaces of concrete no carried to joint levels will not have attained initial set before additional concrete is placed thereon. Lifts shall terminate at such levels as are indicated or as to conform structural requirements as directed. If horizontal construction joints are required, a strip of 25 mm square-edge lumber, beveled to facilitate removal shall be tacked to the inside of the forms at the construction joint. Concrete shall be placed to a point 25 mm above the underside of the strip. The strip shall be removed 1 hour after the concrete has been placed, any irregularities in the joint line shall be leveled off with a wood float, and all laitance removed. Prior to placing and additional concrete, horizontal construction joints shall be prepared as specified in “BONDING”.

405.12.4 Crack-control joints in slabs on grade are specified in paragraph. SLAB ON GRADE. 405.12.5 Water stops shall be installed so as to form a continuous water-tight diaphragm.

Adequate provision shall be made to support and completely protect the water stops during the progress of the work. Joints and splices shall made as follows:

Copper shall be soldered or blazed. When stainless steel is used, splicers, shall be lapped and welded, and brazing shall be in conformance with the manufacturer’s recommendations. 405.13 INSTALLATION OF ANCHORAGE ITEMS 405.13.1 Slots: Adequate inserts shall be provided for anchoring members at openings. Slots

and dowels shall be provided for anchoring ends and tops of masonry partitions abutting concrete.

405.13.2 Inserts for hangers for piping and mechanical fixtures and their installation shall be as specified under “PLUMBING”. 405.14 PREPARATION FOR PLACING Hardened concrete, debris and foreign materials shall be removed from interior of forms and from inner surface of mixing and conveying equipment. Reinforcement shall be secured in position, and shall be inspected, and approved before placing concrete. Runways shall be provided for wheeled concrete-handling equipment; such equipment shall not be supported on reinforcement. 405.15 PLACING CONCRETE 405.15.1 Concrete shall be handled from mixer to transport to place of final deposit in a

continuous manner, as rapidly as practicable and without segregation of loss of ingredient until the approved unit of work is completed. Placing will not be permitted when the sun, heat wind or limitations of facilities furnished by the Contractor prevent

Page 133: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

133

proper finishing and curing of the concrete. Concrete shall be placed in the forms, as close as possible in final position, in uniform approximately horizontal layers not over 400 mm deep. Forms splashed with concrete and reinforcement splashed with concrete of form coating shall be cleaned in advance of placing of subsequent lifts. Concrete shall not be allowed to drop freely more than 1.5 m. in unexposed work nor more than 1.0 m in exposed work; where greater drops are required, tremie or other approved means shall be employed. The discharge of the tremies shall be controlled so that the concrete may be effectively compacted into horizontal layers no more than 400 mm thick, and the spacing of the tremies shall be such that segregation does not occur. Concrete to receive other construction shall be screeded to the proper level to avoid excessive shimming or grouting. Conduits and pipes shall not be embedded in concrete unless specifically indicated.

405.15.2 Time Interval between Mixing and Placing: Concrete mix in stationary mixers and transported by non-agitating equipment shall be placed in the forms within 45 minutes from the tie ingredients are charged into the mixing drum. Concrete transported in truck mixers or truck agitators shall be delivered to the site of work discharge in the forms within 45 minutes from the time that ingredients are discharge into the mixing drum. Concrete shall be placed in the forms within 15 minutes after discharge from the mixer at the job site. 405.15.3 Hot Weather Requirements: Temperature of concrete during the period of mixing transport and or placing shall not be permitted to rise above 16 degree Celsius. Any batch of concrete which had reached a temperature greater than 35 degree Celsius any time in the aforesaid period shall not be placed but shall be rejected, and shall not thereafter be used in any part of the permanent works. 1. Control Procedures: Provide water cooler facilities and procedures to control or reduce the temperature of cement, aggregates and mixing handling equipment to such temperature that, at all times during mixing, transporting, handling and placing, the temperature of the concrete shall not be greater than 36 degree Celsius. 2. Cold Joints and Shrinkage: Where cold joints tend to form or where surfaces and dry too rapidly or plastic shrinkage cracks ten to appear, concrete shall be kept moist by fog sprays and other approved means, applied shortly after placement, and before finishing. 3. Supplementary Precautions: When the aforementioned precautions are not sufficient to satisfy the requirements herein above, they shall be supplemented by restricting work to evening or night. Procedure shall conform to American Concrete Institute Standard ACI 305. 405.15.4 Earth-foundation placement: Concrete footings, exterior slabs and exterior foundations receiving equipment to machinery shall be placed upon undisturbed surfaces conforming to Section EXCAVATION FILLING, AND BACKFILLING. The surfaces shall be clean free from mud and water. Waterproof paper, polyethylene sheeting of nominal 0.4mm minimum thickness shall be laid over dry or impervious surfaces receiving concrete. Such material is of a type specified for curing concrete except that the polyethylene sheet may be other than white. The concrete footings and exterior slabs and foundation may be placed directly over impervious surfaces that are thoroughly moistened by not muddy at the time concrete is placed. 405.15.5 Conveying Concrete by Chute, Conveyor or Pump: chute, conveyor, or pump may convey Concrete if approved in writing. In requesting approval, the Contractor shall submit his entire plan

Page 134: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

134

of operation from time of discharge of concrete from the mixer to final placement in the forms, and the steps to be taken to prevent the formation of cold joints, in case the transporting of concrete by chute, conveyors and pump shall be capable of expeditiously placing concrete at the rate most advantageous to good workmanship. Approval will not be given for chutes of conveyors requiring changes in the concrete materials or design mix for efficient operation. 1. Chutes and Conveyors: Chutes shall be of steel or steel lined wood, round in cross section rigid

in construction, and protected from overflow. Conveyors shall be designed and operated and chute sections shall be set to assure a uniform flow of concrete from mixer to final place of deposit without segregation or ingredients, loss of mortar, or change of slump. The discharge portions of each chute or convey shall be provide with a device to prevent segregation. The chute and conveyor shall be thoroughly cleaned before and after each run. Waste material and flushing water shall be discharged outside the forms.

2. When using tilted chutes, the inclination should not be flatter than (1) vertical and two (2)

horizontal. From the outlet/mouth of the chute to the concrete surface the maximum allowable height shall be 1.50m.

3. Pumps shall be operated and maintained so that a continuous stream of concrete is delivered

into the forms without air pocket, segregation or change in slump. When pumping is completed concrete remaining in the pipeline shall be ejected, and wasted without contamination of concrete already placed. After each operation, equipment shall be thoroughly cleaned and the flushing water shall be splashed outside the forms.

405.5.16 Placing concrete through reinforcement: Where congestion of the steel or other

conditions will make placing or compactions of concrete difficult, a layer of mortar shall be first deposited in forms to a depth of approximately 25 cm.

Mortar proportions shall be the same as the concrete minus the coarse aggregate. 405.16 COMPACTION 405.16.1 Immediately after placing, each layer of concrete vibrator supplemented by hand spading, rodding, and tamping. Tappings or other external vibration of forms will not be permitted unless specifically approved by the Engineer. Vibrators shall not be used to transport concrete inside forms. Internal vibrators submerged in concrete shall maintain speed of not less than 7,000 impulses per minute. The vibrating equipment shall be at all times being adequate in number of units and power to properly consolidate all concrete. 405.16.2 Spare units shall be on hand as necessary to ensure such adequacy. Duration of vibrating equipment shall be limited to time necessary to produce satisfactory consolidation without causing objectionable segregation. The vibrator shall not be inserted into lower coursed that have begun to set. Vibrators shall be applied at uniformly spaced points not further apart than the visible effectiveness of the machine. 405.17 BONDING Before depositing new concrete on or against concrete that has set, the surfaces of the set concrete shall be thoroughly cleaned so as to expose the coarse aggregate and be free of laitance, coatings,

Page 135: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

135

foreign matter and loose particles. Forms shall be re-tightened. The cleaned surfaces shall be moistened, but shall be without free water when concrete is placed. 405.18 SLABS ON GRADE 405. Capillary water barrier or sub-grade shall conform. Section EXCAVATION AND BACKFILLING

FOR BUILDINGS. 405.18.2 Vapor Barrier: Immediately prior to placing concrete, the capillary water barrier or sub-grade under slabs within the building shall be covered with a vapor barrier. Punctures and tears shall be patched. Edges shall be lapped not less than 100 mm and end joints shall be lapped not less than 150 mm. Edges and lapped joints shall be sealed with a pressure sensitive tape, not less than 50 mm wide, compatible with the membrane. 405.18.3 Concrete shall be compacted, screeded to grade, and prepared for the specified finish. Concrete shall be placed continuously so that each unit of operation will be monolithic in construction. Concrete shall be placed in alternate check-board pattern termination at crack-control joints and with construction joints or may be placed in alternative paving lanes as limited by expansion and contraction joints and with construction joints or provide panels of size specified. Crack-control joints shall be expansion, contraction, or construction joints. Joints not shown shall be located at column centerlines and at intermediate intervals so that such panel shall not be more than 55 square meter in area. Panels shall be approximately square with dimension of one side not more than 7.5 meter. Forms shall remain in place for at least 12 hours after concrete placement. 405.18.4 Construction joints may be formed by the insertion of hard-pressed fiberboard strips inserted in the plastic concrete or may be cut with an approved concrete-sawing matching after the concrete has set. Unless otherwise indicated or directed, the joints shall be 3 mm wide and depth equal to approximately `1/4 of the slab thickness or of the maximum size of the coarse aggregated whichever is greater. a. Fiberboard joints: Fiberboard strips shall be of the required dimensions and as long as

practicable. After the first floating, the concrete shall be grooved with a total at the desired joint locations to a depth approximately equal to the width of the strip. The strip shall be inserted in the groove, using a U-shape device of sheet metal fitted over the top of the strip to maintain true alignment until the top edge of the strip is flush with the surface of the slab.

b. When the concrete has set sufficiently to retain the strip, the sheet metal device shall be

withdrawn. The slab shall be floated and finished as specified, using an edging tool on each side of the inserted joint strip where slabs will be left exposed to view.

405.18.5 Sealing: Concrete joints, where sawed or formed, 13 m. shall be filled with joint sealant except where floor covering is required. 405.19 SETTING OF BASE PLATES 405.19.1 Preparation: After being plumbed and properly positioned, base plates shall be provided with full bearing with damp-pack bedding mortar, except where expansive grout is indicated. The space between the top of concrete or masonry bearing surfaces and the bottom of the plate shall be approximately 1/24 of the width of the plate, but not less than 13 mm for plates

Page 136: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

136

less than 30 cm wide. Concrete surfaces shall be rough clean free of oil, grease, and laitance, and shall be damp. Metal surfaces shall be clean and free of oil, grease and rust. 405.19.2 Mortar: Damp-pack bedding mortar shall consist of one part Portland cement and 2.5 parts of fine aggregates, suitable to the work required, proportioned by weight and not more than 17 liters of water per bag of cement. The space between the top of the plate shall be packed with the bedding mortar by tamping or ramming with a bar or rod until the voids are completely filled. 405.19.3 Expansive Grout: Grout shall derive its expansive proper ties from the liberation of gas into the mixture during and after mixing. Thi9s includes typically, and chemical reaction of metallic aluminum with alkali hydroxides in solution which causes the evolution of hydrogen gas. Expansion of such materials may be expected to continue after the gas liberating mechanism has been exhausted or until the mixture has solidified to such an extent that the tendency for the evolving gas to expand is effectively registered by the stiffness of the grout.

a. When tested as provided for herein, and expansive grout shall meet the following performance requirements:

Expansion, 28 days, % max…………..0.40 min…………. 0.03

b. It will be the Contractor’s responsibility to supply the necessary manufacturer’s certificates. 405.20 FINISHES OF CONCRETE 405.20.1 Within 12 hours after forms are removed, surface defects shall be remedied as specified herein. Temperature of the concrete, ambient air and mortar during remedial work including curing shall be above 10 deg. Celsius. Fine and loose material shall be removed. Honeycomb, aggregate pockets, voids over 13 mm in diameter, and holes left by the rods or bolts shall be cut out to solid concrete, reamed, thoroughly wetted brush-coated with neat cement grout, and filled with mortar. Mortar shall be a stiff mix of 1 part portland cement to not more than 2 parts fine aggregate passing the No. 16 mesh sieve, and minimum amount of water. The color of the mortar shall be match the adjoining concrete color. Mortar shall be thoroughly compacted in place. Holes passing entirely through walls shall be completely filled from the inside face by forcing mortar through to the outside face. Holes which do not pass entirely through wall shall be packed full. Patchwork shall be finished flush and in the same plane adjacent surfaces. Exposed patchwork shall be finish to match adjoining surfaces in texture and color. Patchwork shall be damp cured for 72 hours. Ambient temperature shall be not less than 10 deg. Celsius. Dusting of finish surfaces with dry material or adding water to concrete surfaces will not be permitted. 405.21 CONCRETE FINISHES FOR SLABS 405.21.1 Slabs Receiving Concrete Paving: After concrete is placed and consolidated slab shall be screeded or struck off. No further finish is required. 405.21.2 Smooth Finish: Required only where specified; screed concrete and float to required level with no coarse aggregate visible. After surface moisture has disappeared and laitance has been remove, the surface shall be finished by float and steel trowel.

Page 137: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

137

405.21.3 Broom Finish: Required for paving, stairs and landing; the concrete shall be screeded and floated to required finish level with no coarse aggregate visible. After the surface shall be float finished to an even, smooth finish. The floated surfaces shall be broomed with a fiber bristle brush in a direction transverse to the direction of the main traffic. 405.21.4 Tolerance: Smooth and broom finished surfaces shall be true to plane with no deviation in excess of 3 mm in any direction when tested with a 3 m straight edge. 405.22 FINISHES OF CONCRETE OTHER THAN FLOOR SLABS 405.22.1 Within 12 hours after forms are removed, surface defects shall be remedied as specified herein. Honeycomb, aggregate, pockets, voids over 12 mm in diameter, and holes left by the rods or bolts shall be cut out to solid concrete, reamed, thoroughly wetted, brush-coated with neat cement grout, and filled with mortar. Mortar shall be a stiff mix of 1 part Portland cement to not more than 2 parts fine aggregate passing the No. 16 mesh sieve, and minimum amount of water using white Portland cement for all or part of the cement so that when dry, the color of the mortar shall match the adjoining concrete color. Mortar shall be thoroughly compacted in place. Holes passing entirely through walls shall be completely filled from the inside face by forcing mortar through to the outside face. Holes that do not pass entirely through the wall shall be packed full. Patch-work shall be damp-cured for 72 hours. Protruding portions of bar supports shall be ground flush with concrete surfaces that will be exposed, painted, or plastered directly. 405.22.2 Smooth Finish: After the above operations have been completed, smooth finish shall be given to interior and exterior concrete surfaces that are to be painted or exposed to view. Smooth finish shall consist of thoroughly wetting and then brush-coating the surfaces with cement grout composed by volume of 1 part Portland cement to not more than 2 parts fine aggregate passing the No. 30 mesh sieve and mixed with water to the consistency of thick paint. White Portland cement shall be used for all or part of the cement, proportioned by the trial mixes, so that the final color of grout when dry, will be approximately the same as the color of the surrounding concrete. Grout shall be cork or wood-floated to fill all pits and air bubbles; and surfaces rubbed with burlap to remove any visible grout film. The grout shall be kept damp by means of fog spray during the setting period. The finish of any area shall be completed in the same day and the limits of a finished area shall be made at natural breaks in the finished surfaces. 405.22.3 Rough Slab Finish: Slab to receive fill and setting beds shall be screeded with straight-edges to bring the surface to the required finish plane with no aggregates visible. 405.22.4 Broom finish shall be given to a exterior surfaces except concrete stair treads, entrances, and landings for buildings. The concrete shall be screeded and floated to the required finish level with no coarse aggregate visible. After the surface moisture has disappeared and laitance has been remove, surfaces shall be steel-troweled to an even, smooth finish. The troweled surfaces shall be broomed with a fiber-bristle brush in a direction transverse to that of the main traffic. 405.23 CURING 405.23.1 Concrete shall be protected against moisture rapid temperature change, mechanical injury from rain of flowing water, for a minimum period of time given below:

Page 138: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

138

Type I Cement 7 days 405.22.2 Concrete shall be maintained in a moist condition at temperature above 10 degree Celsius throughout the specified curing period and until remedial work is started under paragraph FINISHES OF CONCRETE. Curing activities shall be started as soon as free water has disappeared from the surface of the concrete after placing and finishing. Formed under surface shall moist cure with forms in place for the full curing period, by other approved means. Curing shall be accomplished by any of the following methods or combination thereof, as approved. 405.23.3 Moist Curing: Unformed surfaces shall be covered with burlap or mats, wetted before placing and overlapped at least 150 mm. Burlap or mats shall be kept continually wet and in intimate contact with the surface. Where formed shall be kept continually wet. If the forms are removed before the end of the curing period, curing shall be continued on unformed surfaces, using suitable materials. 405.23.4 Impervious sheet Curing: All surfaces shall be thoroughly wetted with a fine spray of water and be completely covered with waterproof paper, polyethylene sheeting or with polyethylene coated burlap having the burlap thoroughly water saturated before placing. Covering shall be laid with light-colored side up. Covering shall be lapped not less than 300 mm and securely weighted down or shall be lapped not less than 100 mm and taped to form a continuous cover with completely closed joints. Sheets shall be weighted to prevent displacement or billowing from winds. Covering shall be folded down over exposed edges of slabs and secured by approved means. Sheets shall be immediately repaired or replaced if tears or holes appear during the curing period. 405.23.5 Membrane-forming Curing Compound: Before applying curing compound, tops of joints that are to receive sealant shall be tightly closed with temporary material to prevent entry of the compound and to prevent moisture loss during the curing period. The compound shall be applied on damp surfaces as soon as the moisture film has disappeared. The curing compound shall be applied by power spraying using a spray nozzle equipped with a wind guard. The compound shall be applied in a two-coat, continuous operation at a coverage of not more than 10 sq. m. per liter for each coat. When application is made by hand sprayers the second coat shall be applied in a direction approximately at right angles to the direction of the first coat, the compound shall form a uniform, continuous, adherent film that shall not check, crack, or peel and shall be free from pinholes or other imperfections. Surfaces subjected to rain fall within 3 hours after compound has been applied, or surface damaged by subsequent construction operations within the curing period, shall be immediately re-sprayed at the rate specified above. Membrane forming curing compound shall not be used on surface that depends on adhesion of bonding to the concrete. Membrane forming curing compound shall not be used on surfaces that are maintained at curing temperature with free steam. Where membrane-forming curing compounds are permitted, permanently exposed surfaces shall be cured by use of a non-pigmented membrane-forming curing compound containing a fugitive dye. Where non-pigmented type curing compounds are used, the concrete surface shall be shaded from the direct rays of the sun for the curing period. Surfaces coated with curing compound shall be kept free of foot and vehicular traffic, and from other courses of abrasion and contamination during the curing period. 405.24 SETTING BEDS Required over slabs for floor finished other than concrete are covered under other sections of these specifications in which the floor finish is specified.

Page 139: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

139

405.25 METHOD OF MEASUREMENT The quality of structural concrete to be paid for will be the final quantity placed and accepted in the completed structure. No deduction will be made for the volume occupied by pipe less than 100 mm (4 inches) in diameter or by reinforcing steel, anchors, conduits, weep holes, or expansion joint materials. 405.26 BASIS OF PAYMENT The accepted quantities, measured as prescribed in Section 405.25, shall be paid for at the contract unit price for each of the pay items listed below, which is included in the Bill of Quantities. Payment shall constitute full compensation for furnishing, placing and finishing concrete including all labor, equipment, tools and incidentals necessary to complete the work prescribed in this item. Payment will be under:

Item No. Description Unit of Measurement

405 (1) Concrete Class A-A Cu. m.

405 (2) Concrete Class A Cu. m.

405 (3) Concrete Class B Cu. m.

405 (4) Concrete Class C Cu. m.

405 (5) Seal Concrete Cu. m.

Page 140: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

140

ITEM – 401 REINFORCING STEEL

401.1 DESCRIPTION

This item shall consist of furnishing, bending, fabricating and placing of steel reinforcement of the type, size, shape and grade required in accordance with this Specification and in conformity with the requirements shown on the Plans or as directed by the Engineer.

401.2 MATERIAL REQUIREMENTS

401.2.1 GENERAL

All materials shall conform to the requirements hereinafter given. Certified tests report (mill test or other) shall be submitted to the Engineer for all reinforcement steel used. These tests shall show the results of all chemical and physical tests made.

401.2.2 BAR REINFORCEMENT

Reinforcement bars of concrete shall be deformed billet-steel bars conforming to the requirements specified in ASTM A 615 or AASHTO M 31 DSB 275, PS 681-04-02 unless otherwise shown on the Drawings or required by the Engineer. The use of cold twisted bars is not permitted. If not otherwise shown on the Drawings or in the Special Specification the deformed reinforcement steels shall be grade 40. Bar reinforcement shall be shipped in standard bundled, tagged and marked in accordance with the Code of Standard Practice of the Concrete Reinforcement Steel Institute.

Table 401-1 Deformed Bar designation Numbers, Nominal Weights, Nominal Dimensions and Deformation Requirements

Nominal Dimension Deformation Requirements, mm

Bar Designation No. b

Nominal Weight lb./ft.

Diameter

(inches)

Cross-sectiona

l Area (sq.in.)

Perimeter

(inches)

Maximum

Average Spacing

Minimum

Average Height

Maximum Gap

3 0.376 0.375 0.44 4.478 0.262 0.045 0.443

4 .668 0.500 0.20 4.571 0.350 0.020 0.491

5 4.043 0.625 0.34 4.963 0.350 0.020 0.491

6 4.502 0.750 0.44 2.356 0.525 0.038 0.286

Page 141: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

141

7 2.044 0.875 0.60 2.949 0.612 0.044 0.334

8 2.670 4.000 0.79 3.442 0.700 0.050 0.383

9 3.400 4.428 4.00 3.544 0.790 0.056 0.431

10 4.303 4.270 4.27 3.990 0.889 0.061 0.487

11 5.313 4.440 4.56 4.430 0.987 0.071 0.540

14 7.650 4.693 2.25 5.320 4.485 0.085 0648

18 13.600 2.257 4.00 7.090 4.580 0.402 0.864

401.2.3 WIRE AND WIRE MESH

Wire and wire mesh shall conform to AASHTO M to 55. The type of mesh shall be as indicated on the drawings and approved by the Engineer. Tire wires shall conform to AASHTO M 32.

401.2.4 BAR-MAT REINFORCEMENT

Bar-mat reinforcement for concrete shall conform to AASHTO M 45.

401.2.4 STRUCTURAL SHAPES

Structural shapes used as reinforcement in concrete shall conform to ASTM A 36.

401.2.5 SAMPLING

Reinforcing bars will be sampled by the Engineer at the source of supply or at the point of distribution, and the Contractor shall notify the Engineer in advance to permit sampling and testing before shipment is made. Two or more samples from each size shall be taken at random representing five tons of fraction thereof each size.

401.3 CONSTRUCTION REQUIREMENTS

401.3.1 ORDER LIST FOR BENT BARS

Before materials are ordered, all order list and bending diagrams shall be furnished by the Contractor, for the approval of the Engineer. The approval of order lists and bending diagrams by the Engineer shall in no way relieve the Contractor of responsibility for the correctness of such lists and diagrams. Any expenses incident to the revisions of materials furnished in accordance with such lists and diagrams to make them comply with the Drawings shall be borne by the Contractor.

Page 142: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

142

401.3.2 FABRICATION

Bent bar reinforcement shall be cold bent to the shapes shown on the drawings or required by the Engineer. Bars shall be bent around a circular pin having the following diameters (D) in relation to the diameter of the bar (d):

Nominal Diameter d, mm Pin Diameter (D)

Bars 10 to 20 inclusive D-6d

Bars 25 and 28 D-8d

Bars 32 and greater D-10d

Bends and hooks in stirrups or ties may be bent to the diameter of principal bar enclosed therein.

401.3.3 PROTECTION OF MATERIAL

Steel reinforcement shall be protected at all times from injury. When placed in the work, it shall be free from dirt, detrimental scale, paint, oil or other foreign matter. However, when steel had, on its surface, easily removable and detrimental rust, loose scale, or dust, it shall be cleaned by a satisfactory method, approved by the Engineer.

Steel reinforcement shall be stored above the surface of the ground upon platforms, skids, or other supports and shall be protected as far as practicable from mechanical injury and surface deterioration caused by exposure to conditions producing rust. Rust, surface seams, surface irregularities or mill scale will not be cause for seams, rejection, provided the minimum dimensions, cross-sectional area and tensile properties of a hard wire brushed specimen meets the physical requirements for the size and grade of steel specified.

401.3.4 PLACING AND FASTENING

All steel reinforcement shall be accurately placed in the position shown on the Drawings or required by the Engineer and firmly held there during the placing and setting of the concrete. Bars shall be tied at all intersections except where spacing is less than 300 mm in each direction, when alternate intersections shall be tied. Ties shall be fastened on the inside.

Distance from the forms shall be maintained by means of stays, blocks, ties, hangers, or other approved supports. Blocks for holding reinforcement from contact with the forms shall be pre-cast mortar blocks of approved shape and dimensions or approved chairs. Layers of bars shall be separated by pre-cast mortar blocks or by other equally suitable devices. The use of pebbles, pieces of broken stone or brick, metal pipe and wooden blocks or metal chairs shall not be permitted. Unless otherwise shown on the Drawings or required by the Engineer, the minimum distance between bars shall be 40 mm. Reinforcement in any member shall be placed and when inspected and approved by the Engineer before the placing or concrete begins. Concrete placed in violation of this provision may be rejected and removal may be required. If fabric reinforcement is shipped in rolls, it shall be straightened before being placed. Bundled bars shall be tied together at not more than 1.8m. intervals.

Page 143: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

143

401.3.5 SPLICING

All reinforcement shall be furnished in the full lengths indicated on the Plans. Splicing of bars, except where shown on the Plans, will not be permitted without the written approval of the Engineer. Splices shall be staggered as far as possible and with a minimum separation of not less than 40 bar diameters. Not more than one third of the bars may be spliced in the same cross-section, except where shown on the Plans.

Unless otherwise shown on the Plans, bars shall be lapped a minimum distance of :

Special type min. lap

Grade 40 min. lap min. lap

Grade 60 min. lap

But not less than

Tension 24 bar diameter 36 bar diameter 300 mm

Compression

20 bar diameter 24 bar diameter 300 mm

In lapped splices, the bars shall be placed in contact and wired together. Lapped splices will not be permitted at locations where the concrete section is insufficient to provide a minimum clear distance of one and one third the maximum size of coarse aggregate between the splice and the nearest adjacent bar. Welding of reinforcing steel shall be done only if detailed on the Plans or if authorized by the Engineer in writing. Spiral reinforcement shall be spliced by lapping at least one and a half turns or by butt welding unless otherwise shown on the Plans.

401.3.6 LAPPING OF BAR MAT

Sheets of mesh or bar-mat reinforcement shall overlap each other sufficiently to maintain a uniform strength and shall be securely fastened at the ends and edges. The overlap shall not be less than one mesh in width.

401.4 METHOD OF MEASUREMENT

The quantity of reinforcing steel to be paid for will be the final quantity placed and accepted in the completed structure.

No measurement or payment will be made for splices added by the Contractor for his convenience.

When there is no time for reinforcing steel in the Bill of Quantities, cost will be considered as incidental to the other items in the Bill of Quantities.

401.5 BASIS OF PAYMENT

The accepted quantity, measured as prescribed in Section 401.4, shall be paid for at the contract unit price for Reinforcing Steel which price and payment shall be full compensation for furnishing and

Page 144: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

144

placing all materials, including all labor, equipment, tools and incidentals necessary to complete the work prescribed in this Item.

Payment will be made under:

Pay Item Number Description Unit of Measurement

401 kilogram Reinforcing Steel Kilogram

Page 145: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

145

ITEM – 704 RUBBER FENDER

704.1 SCOPE OF WORK

Work under this item includes. Drilling of anchor holes and installation of rubber fender to be furnished by the Contractor.

Rubber fender to be furnished by the Contractor include accessories for anchor plugs and bolts to be placed on the existing reinforced concrete (R.C) superstructure of the wharf; and all necessary machine instrument materials and the spare parts for anchor hole drilling.

704.2 MATERIALS

Trade names of materials herein are intended only to show the standard of the materials on which the design of the particular work is based and also to avoid ambiguous description in the Specifications. The indication of trade names therefore, shall in no way be considered to limit the acceptability of other products or better functions, performances, reliability and durability.

704.2.1 Acceptable Manufacturer’s shall be those approved by the “Engineer”.

704.2.2 Products

1. Rubber Fender

Rubber Fender shall be of “V Type” conforming to dimension as shown on the Plans:

Size : 250H x 1500L or as shown on Plans

Reaction Force : not more than 14.5 ton/m at 45% deflection

Energy Absorption : Not less than 0.90 ton-meter/m at 45% deflection

2. Anchor plug and bolt

Bolt, washer and taper pin : Galvanized mild steel (JIS G 3101)

Page 146: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

146

Sieve : Stainless Steel (JIS G 4303)

3. Anchor hole drilling machine

a. Diamond drill machine with proper number of diamond bits (048.5 mm), accessories

instruments and spare parts. b. Hammer drill machine, with proper number of drill bits and anchor with bolts (017.5

mm), accessories, instrument and spare parts.

704.3 MILL TEST CERTIFICATES

Unless this requirement is waived in writing by the “Engineer”, two (2) copies of mill test reports shall be submitted by the Contractor certifying that materials meet the specified standards.

704.4 TEST AND INSPECTION

Inspection of all materials and methods of fabrication shall be carried out by the Contractor. However, the “Engineer” reserves the right to inspect all facilities at any time during the manufacture to ensure that the materials and the workmanship are in accordance with the Specifications and the best shop practices.

704.5 INSTALLATION/CONSTRUCTION METHODS

All materials shall be installed at the locations shown in the Plans in accordance with the approved manufacturer’s instruction and shop drawings, and as directed by the “Engineer”.

704.6 MEASUREMENT AND PAYMENT

The quantity of supply, delivery, handling of rubber fenders including accessories for anchor plugs and bolts and all necessary machine instruments, materials and the spare parts for anchor hole drilling to be paid for shall be measured per number of rubber fender actually installed and accepted by the “Engineer”.

This price will be full compensation for furnishing all materials, labor, tools, installation and other incidental expenses necessary to complete the work.

Page 147: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development

147

Section VII. Drawings

Page 148: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development
Page 149: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development
Page 150: Procurement of INFRASTRUCTURE PROJECTS - DOTr - …dotr.gov.ph/images/Public_Bidding/CivilWorks/Maritime... ·  · 2016-09-08PHILIPPINE BIDDING DOCUMENTS (As Harmonized with Development