Procurement presentation
Introduction to the new procurement
arrangements in the RBL
![Page 2: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/2.jpg)
Agenda
• What is meant by Procurement• RBL Sourcing strategy• Basic Procurement Routes• Process – How it works• RBL Procurement process • High value / More complex procurement• Procurement Intranet support• Contracts Database• Requests for Quotes• Formal Procurement Routes • Proactis -Placing a Purchase Order / Receipting / Payment• Next steps• Support
![Page 3: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/3.jpg)
Why are you here ?
• Who — and what — is this introductory presentation for?
• Good procurement skills help everyone involved in procurement to make the most of the available budgets — to ensure that the goods and services purchased are through compliant processes, obtain the best value for money, and will support the Legion in meeting its objectives and obligations as effectively as possible.
![Page 4: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/4.jpg)
Introduction
• What is procurement?
'Procurement' means the whole process of buying orpurchasing — goods, works or services.
It includes • the identifying of what you need• the options and choices you have• the process of purchasing your goods or services• disposal / replacement of the item you purchased • Procurement may also include inventory control, receiving,
inspection, management, store keeping, salvage and disposal.
![Page 5: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/5.jpg)
RBL Sourcing Strategy
• Existing Suppliers on Contracts database • Access to Framework Contracts• Previously Used Suppliers through Open competition• Requests for Quotations - small value• Invitations to Tender – larger values• EU tender process
![Page 6: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/6.jpg)
Basic Procurement Routes
• Under £1000 - receipts• Over £1000 under £25,000 - 3 quotes• Over £25,000 - via Procurement team
• Over £140,000 - probable EU tender
![Page 7: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/7.jpg)
Process – How it works
Undertake the following :
Identify the need (and budget)
Adhere to Financial levels of Procurement
Raise an order through Proactis
Receipt an Order
Handle queries (troubleshoots)
Payments
![Page 8: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/8.jpg)
RBL Procurement Process
Identify need to procure goods or services (including do you have the budget)
Is there a FRAMEWORK supplier in place
What is the total (whole contract)
cost of the purchase ?
Under 100O
Over £25000 Mandatory to
refer to Procurement
Team
Require 3 written quotes (Refer to RFQ Log)
Procurement team to decide sourcing route
Evaluate responses(copy to be retained by
Procurement Team)
Place Order Through Proactis
Receipt Order
Over £1000 but under £25000
delegated spend limit
Obtain at least 3 prices
Evaluate responses
Place OrderThrough Proactis
Receipt Order
Place Order
Receipt Order
NoYes
![Page 9: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/9.jpg)
Higher Value/ More Complex Procurement
• Over £25,000 total Contract value Mandatory involvement of
Procurement
• Less than £25,000 but complex / high risk involvement of Procurement
team or Legal
• Contract approval for Contracts over £25,000 (with certain exemptions on
Property related contracts) must be through Procurement team who will
liaise with Legal and arrange appropriate signing and distribution of
contracts
![Page 10: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/10.jpg)
Procurement Intranet Support
![Page 11: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/11.jpg)
Contracts Database
![Page 12: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/12.jpg)
Request for Quote Process
![Page 13: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/13.jpg)
Placing Orders
![Page 14: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/14.jpg)
Next steps
• Directorate/ Divisional individual seminars• Roll out to regions• Updating of Procurement intranet pages• Regular newsletters and workshops• Reviewing of Purchasing strategy as RBL Corporate
strategy refocuses
![Page 15: Procurement Presentation rbl](https://reader036.vdocuments.net/reader036/viewer/2022081504/55c4d9a7bb61eb5c0f8b470f/html5/thumbnails/15.jpg)
Support
• Share knowledge with your team/ colleagues
Procurement Contacts• Frank Wright tel: 020 3207 (W) e-mail: [email protected]• Julie Batty tel: 020 3207 2289 (W) e-mail: [email protected]• Linda Bates tel: 01954 231819 (H) e-mail: [email protected]• Adeline Orife tel: 020 3207 2135 (W) e-mail: [email protected]