procurement risk assessment (final)...procurement risk assessment questionnaire is presented in...

148
Procurement Risk Assessment (Final) Project number: 48358-001 August 2017 PRC: Shanxi Inclusive Agricultural Value Chain Development Project Prepared by the project preparatory technical assistance consultants in coordination with the Shanxi Provincial Project Management Offoce for the Asian Development Bank Shanxi Inclusive Agricultural Value Chain Development Project (RRP PRC 48358)

Upload: others

Post on 30-Sep-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

Procurement Risk Assessment (Final)

Project number: 48358-001 August 2017

PRC: Shanxi Inclusive Agricultural Value Chain Development Project

Prepared by the project preparatory technical assistance consultants in coordination with the Shanxi Provincial Project Management Offoce for the Asian Development Bank

Shanxi Inclusive Agricultural Value Chain Development Project (RRP PRC 48358)

Page 2: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

CURRENCY EQUIVALENTS (as of 29 August 2017)

Currency unit – yuan (CNY) CNY1.00 = $0.1511

$1.00 = CNY6.6183

ABBREVIATIONS

ADB – Asian Development Bank EMP – environment management plan ha – hectare IEE – initial environmental examination km – kilometer LIBOR – London interbank offered rate LID – low-impact development m3 – cubic meter mu – a Chinese unit of measurement (1 mu = 1/15 ha) O&M – operation and maintenance PAC – project agribusiness company or cooperative PAM – project administration manual PPMO – Shanxi Provincial Project Management Office PRC – People’s Republic of China SPG – Shanxi Provincial Government SPS – Safeguard Policy Statement

NOTE

In this report, “$” refers to United States dollars.

This procurement risk assessment is a document of the borrower. The views expressed herein do not necessarily represent those of the Asian Development Bank's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

Procurement Risk Assessment

Project number: 48358-001 August 2017

People’s Republic of China: Shanxi Inclusive Agricultural Value Chain Development Project

Page 4: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the
Page 5: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

TABLE OF CONTENTS

EXECUTIVE SUMMARY ........................................................................................................... 1

I. Introduction ......................................................................................................................... 1

II. Country Procurement Systems ........................................................................................... 1

III. Project Procurement Risk Assessment ............................................................................... 3

V. Project Specific Procurement Thresholds............................................................................ 7

VI. Procurement Plan ............................................................................................................. 8

VII. Conclusion .......................................................................................................................... 9

APPENDIX 1 ............................................................................................................................ 10

Page 6: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the
Page 7: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

EXECUTIVE SUMMARY

1. Overall, the project procurement risk is moderate. The main weakness identified is that all 19 project agribusiness companies and cooperative (PACs) [project implementing units, (PIUs)] lack experience in the public procurement and projects financed by the Asian Development Bank (ADB). This risk will be mitigated through (i) support of procurement agency, which is authorized by the Government of the People’s Republic of China (PRC) for procurement under projects funded by international or bilateral development organizations such as ADB, for PACs, and (ii) capacity building for PACs by an individual procurement specialist to be engaged by ADB.

I. Introduction

2. This report contains findings and observations of a project procurement risk assessment for the Shanxi Inclusive Agricultural Value Chain Development Project. The project is aligned with the following impacts: (i) all rural residents falling below the PRC’s current poverty line and all poor counties lifted out of poverty, and poverty alleviation in all regions achieved; and (ii) rural–urban income disparity narrowed, and the proportion of the population in the middle-income class increased. The project outcome will be income generating opportunities from selected local specialty agricultural products increased. The project particularly aims at strengthening the value chains of local specialty agricultural products with untapped market potential in 17 counties in 6 municipalities. The assessment was prepared in accordance with the Guide on Assessing Procurement Risks and Determining Project Procurement Classification (the Guide).1 3. Preparatory activities included review of project documents; ADB’s ongoing procurement experiences in the PRC; a procurement capacity risk assessment using the project procurement risk assessment questionnaire provided in the Guide; in-depth discussions with the provincial Project Management Office (PPMO) established in Shanxi Provincial Department of Poverty Alleviation and Development (SPADO) of Shanxi Provincial Government (SPG), the executing agency (EA); 17 county Project Management Offices (CPMOs) established in the project county governments [project implementing agencies (IAs)], and 19 PACs (PIUs). The completed project procurement risk assessment questionnaire is presented in Appendix 1.

II. Country Procurement Systems

4. Currently, public procurements in the PRC are governed by two laws: the Tendering and Bidding Law and the Government Procurement Law. The Tendering and Bidding Law was approved by the People’s Congress and promulgated by the President on 30 August 1999. It became effective on 1 January 2000. On 12 December 2011, the State Council promulgated the Regulation on Implementation of the Law of the PRC on Tendering and Bidding that became effective on 1 February 2012. The Government Procurement Law was promulgated on 29 June 2002 and became effective 1 January 2003. It covers requirements for procurements of central and subcentral government-financed goods, civil works, and services. 5. The SPG has also developed various guidelines for implementing the Tendering and Bidding Law in different sectors, including the (i) Shanxi Province Building Projects Tendering and Bidding Management Guidelines (effective on 23 June 1995); (ii) Shanxi Province Water Resource Projects Tendering and Bidding Management Guidelines (1 February 2007); (iii) Shanxi Province Highway Projects Tendering and Bidding Management Guidelines (Trial, 2011); (iv) Communication Projects Tendering and Bidding Management Guidelines (effective on 1 July

1 ADB. 2014. Guide on Assessing Procurement Risks and Determining Project Procurement Classification. Manila.

Page 8: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

2

2014); (v) Shanxi Province Building and Infrastructure Projects Tendering and Bidding Implementation Rules (Trial 2001); etc. 6. The following issues of general procurement environment in the PRC tend to increase procurement risk for this project:

(i) Consulting services are not clearly addressed in the two national procurement laws; (ii) The national procurement laws are not clear for participation of state-owned

enterprises; also the laws are not clear in procurement procedure and method for using international financing organization loan or grant by private companies or cooperatives.

(iii) The laws and regulations do not require collection of nationwide statistics on procurement, and consolidated historical procurement data are not readily available to the public; and

(iv) Comprehensive training program is not available by executing agencies for procurement accreditation or professionalization in the PRC.

7. For the PRC, the country and sector procurement risk preliminary rated by ADB is medium.

PROJECT PROCUREMENT CLASSIFICATION

8. Project procurement classification was not conducted at the concept stage of the project. Based on analysis in Table 1, category B is proposed for the project.

Table 1: Project Procurement Classification

Characteristic Assessor’s Comments and Finding Summary

Is the Procurement Environment Risk for this project assessed as "High" based on the country and sector/agency risk assessments? A ccording to Figure 4 above?

No.

Are multiple (typically more than three) and/or diverse Executing Agencies (EAs) and/or Implementing Agencies (IAs) envisaged during project implementation? Do EAs/IAs lack prior experience in the Asian Development Bank (ADB) project implementation?

Yes, there are one EA that will supervise and guide procurement activities [Shanxi Provincial Government (SPG) represented by the Provincial Project Management Office (PPMO)], 17 IAs that will support and facilitate procurement activities [(project county governments represented by the county project management offices (CPMOs)), and 19 project implementing units (PIUs) that will be responsible for procurement [project agribusiness companies and cooperative (PACs)].

Yes, those PIUs lack prior experience in ADB project implementation while the PPMO and some of CPMOs have experience in ADB and/or the World Bank projects.

Are multiple contract packages and/or complex and high-value contracts expected (compare to recent donor projects in the developing member country (DMC)?

Yes, there will be multiple contract packages, but neither complex nor high-value contracts.

Page 9: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

3

Characteristic Assessor’s Comments and Finding Summary

Does the project plan to use innovative contracts (public–private partnership, Performance-based, Design and Build, operation and maintenance, etc.)?

No.

Are contracts distributed in more than three geographical locations?

Yes, the project will be implemented in 17 counties in Shanxi Province.

Are there significant ongoing contractual and/or procurement issues under the ADB- (or other donor) funded projects? Has mis-procurement been declared in the DMC?

No, there was no such issues under the recent ADB project.

No mis-procurement has been declared in the DMC.

Does the DMC have prolonged procurement lead times, experience implementation delays, or otherwise consistently fail to meet procurement timeframes?

No, procurement lead time tends to be shorter in the past ADB and World Bank projects which the EA was involved than other DMCs.

Do EA/IAs lack capacity to manage new and ongoing procurement? Have EA/IAs requested ADB for procurement support under previous projects?

Yes, PIUs (PACs) lack experience and capacity to manage public procurements. However, the EA that has capacity to manage procurement activities will guide and supervise PIUs’ procurement and IAs that are familiar with public procurement will support PIUs’ procurement.

Though the EA did not require procurement support under the previous ADB project, they will engage a procurement agency that is authorized by the Government of the People’s Republic of China and an individual procurement specialist to support procurement activities under the project particularly support and capacity building for PIUs’ procurement.

OVERALL PROJECT CATEGORIZATION RECOMMENDED:

B

Source: Asian Development Bank.

III. Project Procurement Risk Assessment

A. Overview

1. Organizational and Staff Capacity

9. The EA for the project is SPG; 17 project county governments are the IAs; and 19 PACs are PIUs. A project leading group has been established to provide overall policy guidance, facilitate inter-agency coordination, and resolve any institutional problems affecting project preparation and implementation. The PPMO established within the SPADO will be the leading agency responsible for overall project implementation and management. The PPMO will guide and supervise for all procurement activities under the project. The PPMO will also engage a procurement agency, which is authorized by the People’s Republic of China to support procurement of projects funded by international or foreign development agencies. In each project country government, a CPMO was established to support procurement of PAC(s) in the county.

Page 10: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

4

Each PAC is responsible for its own procurement of goods and works. In addition, an individual procurement specialist will be engaged to support the PPMO’s supervision, monitoring and reporting of procurement activities and capacity building for PACs.

2. Information Management

10. The PPMO have designated personnel and sufficient space and equipment for information management, including record keeping.

3. Procurement Practices

11. The following differences in procurement practices were noted between ADB and PRC: (i) Minimum advertising period is only 20 days for domestic procurements in PRC,

against 42 days for international competitive bidding (ICB) and 30 days for national competitive bidding (NCB) required by ADB; and

(ii) Bid securities are often remitted by cash, which is the most preferred option for most procuring entities in the PRC.

12. Consultant recruitment procedures are not clearly addressed in the PRC’s domestic procurement laws and regulations. Most consultant selection committee (CSC) members are selected by public resources trading center. However, it is likely that some of selected CSC members may not be unfamiliar with the ADB and project requirements for engagement of consulting services, which might cause delays or mistakes in the engagement. 13. The PPMO has agreed to adhere to ADB’s requirements for procurement of works and goods, and consultant recruitments for this project.

4. Effectiveness

14. From responses to the questionnaire, it appears that adequate controls are in place: (i) Shanxi Provincial Audit Department (SPAD) is involved in monitoring and reporting of the project implementation; (ii) there is a formal non-judicial mechanism to deal with complaints associated with domestic procurement under the PRC’s Bidding Law. Hence, an additional control required for procurement management under the project will be ADB’s administration to ensure the project compliance with ADB procurement procedures.

5. Accountability Measures

15. The PPMO will supervise all procurement activities, ensure compliance of the procurement process with regulations, and ensure that information disclosure requirements are followed. The engaged procurement agency will organize all procurement documents, and records all bid opening and evaluation processes. The SPAD’s annual audit will cover all procurement-related transactions, as necessary. General public, private sectors, and peoples’ organizations can submit complaints to the PPMO, IAs, and/or PIUs. 16. Accountability is strengthened by provisions of the PRC’s laws and regulations on sanctions against anticorruption for both bidders and government staff. Moreover, Article 44 of the Tendering and Bidding Law and Article 62 of the Government Procurement Law provide ethical standards for procurement personnel.

Page 11: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

5

B. Strengths

17. A procurement specialist of the project preparatory technical assistance (PPTA) consultant team had provided the PPMO, IAs and PACs key staff with training on ADB’s procurement and consultant recruitment procedures. At project start-up and during project implementation, a procurement consultant will continue such training. The procurement consultant and a procurement agency will provide the PPMO, IAs and PACs with professional services and technical assistances, and ensure that procurements and consultant recruitments for the project will fulfill ADB’s requirements. 18. The PPMO will have the chief responsibility for control and oversight of procurement activities. Other related governmental authorities will also supervise procurement process to prevent corruption. Finance, construction, and other departments/bureaus may supervise public opening and evaluation processes. The Shanxi Provincial Finance Department and separate municipal and/or county finance bureaus will review and approve invoicing and payment against contracts. 19. The PRC’s laws and regulations related to procurement provide procurement-related sanctions for both bidders and government staff. To complement these legal requirements, the PPMOs will ensure all procurement-related work is checked every year by the related responsible governmental department in terms of ethical behavior. 20. The CPMOs will support PACs’ procurement activities and report to the PPMO during the project implementation. The PPMO and the CPMOs have committed to fulfilling ADB’s requirements for all procurements and consultant recruitments for the project.

C. Weaknesses

21. All 19 PACs (PIUs) lack experience in the public procurement and projects financed by the ADB. As the PACs are scattered in 17 project counties across with the province, the PPMO’s supervision to ensure their compliance with ADB’s procurement procedures will be a challenge.

D. Procurement Risk Assessment and Management Plan

22. The Project Procurement Risk Assessment and Management Plan in Table 2 has been prepared based on the procurement risk assessment questionnaire in Appendix 1, following the Guide.

Page 12: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

6

Table 2: Project Procurement Risk Assessment and Management Plan

SL No. Risk

Risk Assessment Mitigation Measures or Risk Management Plan Impact Likelihood Risk

A.2,

A.3

The PACs have insufficient qualified staff to efficiently undertake procurements under the project.

Average Likely Average Mitigation:

- The Individual national procurement specialist shall be engaged in the project, and will provide staff of the PACs and CPMOs with training on procurements and consultant recruitments at project start-up.

- A procurement consultant of the project management support consultant team will continue such training.

- The procurement agency will help them conduct procurement and consultant recruitment under the project.

- ADB to require the following:

Prior Review: all ICB contracts, first NCB contract (works), first NCB and SHP contract (goods and non-consulting services), recruitment of consultants through QCBS, CQS and IC; and

Post Review: subsequent NCB for goods and works, Shopping (works, goods and non-consulting services).

A.2

A.3

A.8

A.9

A.12-17

The PACs and CPMOs have insufficient qualified staff to efficiently undertake procurements, and have not procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit

Average or High

Likely Average Mitigation:

- The individual procurement consultant to provide on-the-job training and guidance during bid document preparation (technical and financial aspects) and bid evaluation, and in addressing ADB’s comments.

- The procurement agency will help them to conduct procurements.

- ADB will continue to give guidance and instructions to the PPMO/PACs.

B.3-6,7

C.1

C.2

C.5

The PACs do not promote non-discriminatory participation and transparent tender processes,

High or Average

Unlikely Average Mitigation:

- PPMO and PACs have promised to follow relevant ADB procedures and requirements.

Page 13: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

7

SL No. Risk

Risk Assessment Mitigation Measures or Risk Management Plan Impact Likelihood Risk

C.7

C.8

C.9

C.14-18

E.5

E.6

or other non-compliance with ADB’s procurement guidelines.

- With help from the individual procurement consultant and the procurement agency, the PPMO will prepare manuals for procurements and consultant recruitments which fulfill ADB’s requirements for non-discriminatory participation and transparent bidding processes at project start-up.

- The individual procurement consultant and project management support consultant team will provide training on procurement and consultant recruitment at project start-up and during project implementation.

- The procurement agency will help them to conduct procurements

- ADB will continue to give guidance and instructions to them.

Monitoring:

- ADB will closely monitor the procurement and consultant recruitment activities.

Overall AVERAGE

High risk has only been identified on the PACs project implementing activities, especially on procurements of works or goods. There are not consultant recruitment requirements for all the PACs.

However, the PPMO who will be assisted by the counties IAs, individual consultants, and the procurement agency to conduct the project implementation and procurement management.

For only some items, average risks have been identified. However, these risks are mostly due to unfamiliarity with ADB’s procedures and requirements. With proper mitigation measures, such as trainings and employing a procurement agency and Individual procurement specialists, these risks can be mitigated.

For other items, risk is low.

Source: Asian Development Bank.

Page 14: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

8

IV. Project Specific Procurement Thresholds

A. Procurement Method and Supervision Thresholds

23. The applicable thresholds are in Table 3.

Table 3: Procurement Method Thresholds

Procurement of Goods and Works

Method Threshold Comments

International Competitive Bidding (ICB) for Works

$40,000,000 and above Invitation for bids, bidding documents, and bid evaluation and recommendation for contract awards will be subject to the Asian Development Bank’s (ADB) prior review.

ICB for Goods $5,000,000 and above The first ICB procurement for goods should be submitted to ADB for prior review and approval. Subsequent ICB procurement documents will be subject to post-review.

National Competitive Bidding (NCB) for Works

Between $100,000 and $39,999,999

The first NCB procurement documents for works should be submitted for prior ADB review and approval. Subsequent NCB procurement documents will be subject to post-review.

NCB for Goods Between $100,000 and $4,999,999

The first NCB procurement documents for goods should be submitted for prior ADB review and approval. Subsequent NCB procurement documents will be subject to post-review.

Shopping for Works Below $100,000 Post-review

Shopping for Goods Below $100,000 Post-review

Consulting Services

Method Comments

Quality-and cost-based selection

$200,000 and above. For the two contracts for (i) advisory services on agriculture value chain development, and (ii) advisory services on piloting the inclusive business mechanism. Six submissions required for prior review and approval by the Asian Development Bank: Submission 0 (budget, terms of reference), Submission 1 (short-list, draft request for proposal), Submission 2 (evaluation of technical proposals), Submission 3 (evaluation of financial proposals and overall ranking), Submission 4 (draft negotiated contract), and Submission 5 (signed contract).

Source: Asian Development Bank.

V. Procurement Plan

24. Scope of procurement. Works and goods will be for construction or purchasing are based on the PAC’s subproject design and investment. Consulting services will be for project implementation and procurement management, external resettlement monitoring and evaluation, environmental supervision, financial and disbursement management, etc. 25. Packaging. The project has a total of 40 contract packages, including 3 international competitive bidding packages, 34 national competitive bidding packages, 1 shopping package, and 2 consulting services packages. A summary of the contract packages is provided below. The draft procurement plan is included in the project administration manual.

Page 15: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

9

Table 4: Breakdown of Number of Packages

General Description Estimated Value

(Cumulative $'000) Estimated Number

of Contracts Procurement

Method

Works (more than 1 million) 31,484,000 11 NCB

(Less than 1 million) 1,607,900 3 NCB

Subtotal—Works: 33,091,900 14

Goods (more than 1 million) 41,113,500 15 NCB

17,968,800 3 ICB

(Less than 1 million) 4,882,500 5 NCB

52,800 1 SHP

Subtotal—Goods: 64,017,600 24

Consultant Services

Advisory services on agriculture value chain development

1,000,000 1 QCBS

Advisory services on piloting inclusive business mechanism

1,250,000 1 QCBS

Subtotal—Consulting Services:

2,250,000 2

Overall Total: 99,359,500 40

ICB = international competitive bidding, NCB = national competitive bidding, QCBS = quality- and cost-based selection, SHP = shopping. Source: Asian Development Bank estimates.

26. Advance action and retroactive financing. All advance contracting will be undertaken in conformity with ADB’s Procurement Guidelines (2015, as amended from time to time) and ADB’s Guidelines on the Use of Consultants (2013, as amended from time to time). The issuance of invitations to bid (for procurement) or the issuance of the invitations for expression of interest (for consulting services) under advance contracting will be subject to ADB’s approval. The executing agency, SPG, had been advised that approval of advance contracting does not commit ADB to finance the project. Retroactive financing will be limited to $2,250,000 of eligible expenditures for Consulting Services incurred under the Project before the loan effective date, but not earlier than 12 months before the loan agreement is signed.

VI. Conclusion

27. The PPMO, which has recent experience with ADB-funded projects, will guide and supervisor PACs’ procurements of works and goods, and carry out consultant recruitment for the project. The CPMOs will support PACs’ procurement activities and report to the PPMO. Overall, the project procurement risk is moderate. The main weakness identified is that all 19 PACs (PIUs) lack experience in the public procurement and projects financed by the ADB. This risk will be mitigated through (i) support of procurement agency and (ii) capacity building for PACs by an individual procurement specialist to be engaged by ADB.

Page 16: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

10

APPENDIX 1: Project Procurement Risk Assessment Questionnaire

Participants:

PPMO = Shanxi Provincial Project Management Office under the Shanxi Provincial Poverty Alleviation and Development Office (PPMO)

Implementing Agencies2 (Municipality/County): (1) Changzhi/Qin County, (2) Datong/Guangling County, (3) Datong/Datong County, (4) Jinzhong/Taigu County, (5) Jinzhong/Heshun County, (6) Linfen/Fenxi County, (7) Linfen/Fushan County, (8) Linfen/Quwo County, (9) Linfen/Xiangning County, (10) Linfen/Yaodu District, (11) Lvliang/Liulin County, (12) Lvliang/Shilou County, (13)Yuncheng/Ruicheng County, (14) Yuncheng/Xinjiang County, (15) Yuncheng/Yanhu District, (16) Yuncheng/Yuanqu County, (17) Yuncheng/Jishan County.

Project Agribusiness Companies and Cooperative: (1) Shanxi Qinzhouhuang Millet Group Co., Ltd. (QZHM); (2) Guangling Kitano Edible Fungus Industrial Development Co., Ltd. (GLKT); (3) Shanxi Phoenix Wine Industry Co., Ltd. (PHNX); (4) Shanxi Juxin Weiye Agricultural and Science & Technology Development Co., Ltd. (JXWY); (5) Heshun County Lvhe Ecological Agriculture & Livestock Development Co. Ltd. (HSLH); (6) Fenxi Hongchang Breeding Co., Ltd. (FXHC); (7) Fushan Guhuan Husbandry Sci. & Tech. Co., Ltd. (FSGH); (8) Quwo Lvheng Agricultural Development Co., Ltd. (QWLH); (9) Shanxi Qierkang Elaeagnus Biological Products Co. (QIEK); (10) Linfen Zhongde Farming Technology Development Co., Ltd. (LFZD); (11) Liulin Fuzhongyuan Agricultural Development Co., Ltd. (LFZY); (12) Shilou Shude Jujube industry Co., Ltd. (SLSD); (13) Shanxi Tianzhirun Date Processing Co., Ltd. (TZRD); (14) Xinjiang Hefeng Grain Planting Technology Cooperatives (XJHF); (15) Shanxi Xinjiang Vegetable Industry Development Co., Ltd. (XJVI); (16) Shanxi Kaisheng Fertilizers Group Co., Ltd. (KSFC); (17) Yuncheng Xinke Taifang Vegetable Trading Co., Ltd. (XKTF); (18) Shanxi Shanlihong Food Co., Ltd. (SLHC); (19) Shanxi Jinglong Group Jinghua Livestock and Poultry Products Development Co., Ltd. (JLJH).

2 Only Lvliang Municipal Project Management Office (MPMO) under Lvliang Poverty Alleviation Office and Fenxi County Project Management Office (CPMO) under county Poverty Alleviation Bureau submitted their questionnaire. Other IAs did not provide any feedback.

Page 17: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

11

Annex 1-1: Executing Agency Capacity Assessment Questionnaire —Shanxi Provincial Project Management Office (PPMO) under the Shanxi Poverty

Alleviation and Development Office

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency

Shanxi Provincial Project Management Office under Shanxi Provincial Poverty Alleviation and Development Office (PPMO)

Position or Title Section Chief, Senior engineer

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

above 20 years of the respondent

Low

A.2. How many staff in the procurement department/unit are:

2 persons, belong to the Section of construction

Average i. Full Time? 2

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No, the procurement unit belongs to the Section of Construction Average

A.9. If yes, what type of procurement does it undertake?

Works, Goods and Services

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

PPMO Director Low

Page 18: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

12

A.11. Do the procurement positions in the agency have job descriptions, which outline specific roles, minimum technical requirements and career routes?

Yes Low

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No up to date It covers foreign-assisted project

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No up to date It covers foreign-assisted project

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

purchasing director

Low

A.19. Who approves the procurement specifications?

purchasing director

A.20. Who drafts the bidding documents? purchasing director

A.21. Who manages the sale of the bidding documents?

purchasing director

A.22. Who identifies the need for consulting services requirements?

purchasing director

Average A.23. Who drafts the terms of reference (TOR)? purchasing director

A.24. Who prepares the request for proposals (RFPs)?

purchasing director

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 15 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

Page 19: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

13

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

No Average

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

Yes, ADB-financed Comprehensive Agricultural Development Project and Shanxi Integrated Agricultural Development Project

Average

C.2. If the above answer is yes, what were the major challenges?

Nothing particular

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

15 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? anyone

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Average

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

the expert of Experts Database based on China Tendering & Bidding Law

Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

final decision Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

20 days above Average

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No Average

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

Inventory Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

Page 20: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

14

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

Yes, ADB-financed Shanxi Integrated Agricultural Development Project

Average

C.23. If the above answer is yes, what were the major challenges?

Compliance with ADB’s procedures related to consultant services engagement

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No response (does not understand the question)

High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

do not have similar experience to select consultants.

High

C.28. Do firms have to pay for the RFP

document?? same as above High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

same as above High

C.30. Are pre-proposal visits and meetings arranged?

same as above

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

same as above

C.32. To whom are the minutes distributed?

C.33. Are all queries from consultants answered/addressed in writing?

same as above High

C.34. Are the technical and financial proposals required to be in separate envelopes?

same as above High

C.35. Are proposal securities required? same as above High

C.36. Are technical proposals opened in public? same as above High C.37. Are minutes of the technical opening

distributed? same as above

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

same as above

High C.39. Who determines the final technical ranking and how?

same as above

C.40. Are the technical scores sent to all firms? same as above

C.41. Are the financial proposal opened in public?

same as above High

C.42. Are minutes of the financial opening distributed?

same as above

Page 21: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

15

C.43. How is the financial evaluation completed?

same as above High

C.44. Are face to face contract negotiations held?

same as above High

C.45. How long after financial evaluation is negotiation held with the selected firm?

same as above High

C.46. What is the usual basis for negotiation? same as above High

C.47. Are minutes of negotiation taken and signed?

same as above High

C.48. How long after negotiation is the contract signed?

same as above High

C.49. Is there an evaluation system for measuring the outputs of consultants?

same as above High

Payments

C.50. Are advance payments made Yes Low

C.51. What is the standard period for payment included in contracts?

No response

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

A long time

C.53. When late payment is made, are the beneficiaries paid interest?

sometime

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Purchasing director Yes he does.

Low

Page 22: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

16

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

a) Bidding document, invitation to pre-qualify or RFP

Purchasing Unit chief

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Purchasing director

c) Evaluation reports Bid Evaluation Committee

d) Notice of award Purchaser

e) Invitation to consultants to negotiate Purchaser

f) Contracts Purchaser

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Low

C. Procurement Practices Average, but on consulting services is high.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Average

Page 23: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

17

Annex 1-2: Executing Agency Capacity Assessment Questionnaire — Lvliang Municipal Project Management Office (MPMO) under Lvliang Poverty

Alleviation Office

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Lvliang Municipal Project Management Office under Lvliang Poverty Alleviation Office (MPMO)

Position or Title Section Chief, Engineer

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

10 Low

A.2. How many staff in the procurement department/unit are:

2 persons

Average i. Full Time? /

ii. Part Time? 2

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes Low

A.9. If yes, what type of procurement does it undertake?

Works, Goods and Services

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of EA Low

Page 24: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

18

A.11. Do the procurement positions in the agency have job descriptions, which outline specific roles, minimum technical requirements and career routes?

Yes Low

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

purchasing director

Low

A.19. Who approves the procurement specifications?

purchasing director

A.20. Who drafts the bidding documents? Procurement Agent

A.21. Who manages the sale of the bidding documents?

Procurement Agent

A.22. Who identifies the need for consulting services requirements?

purchasing director

Average A.23. Who drafts the terms of reference (TOR)? purchasing director

A.24. Who prepares the request for proposals (RFPs)?

purchasing director

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 15 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

Page 25: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

19

B.7. Are copies of invoices included with the contract papers?

No Average

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

Yes, WB financed water saving & irrigation project

Average

C.2. If the above answer is yes, what were the major challenges?

Do not adapt to the WB program

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

15 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? Bid evaluation committee, procurement agent, bidders

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Average

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

the expert of Experts Database based on China Tendering & Bidding Law

Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

final decision Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

20 days above Average

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response Average

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

as inventory Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

Page 26: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

20

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

Yes High

C.23. If the above answer is yes, what were the major challenges?

Domestic and international coordination

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes, as the Invitation for Bids Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? Do not know High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

Do not know High

C.28. Do firms have to pay for the RFP

document?? Do not know High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Do not know High

C.30. Are pre-proposal visits and meetings arranged?

Do not know

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

Do not know

C.32. To whom are the minutes distributed? Do not know

C.33. Are all queries from consultants answered/addressed in writing?

Do not know High

C.34. Are the technical and financial proposals required to be in separate envelopes?

Do not know High

C.35. Are proposal securities required? Do not know High

C.36. Are technical proposals opened in public? Do not know High C.37. Are minutes of the technical opening

distributed? Do not know

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Do not know

High C.39. Who determines the final technical ranking and how?

Do not know

C.40. Are the technical scores sent to all firms? Do not know

C.41. Are the financial proposal opened in public?

Do not know

High C.42. Are minutes of the financial opening distributed?

Do not know

C.43. How is the financial evaluation completed?

Do not know High

Page 27: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

21

C.44. Are face to face contract negotiations held?

Do not know High

C.45. How long after financial evaluation is negotiation held with the selected firm?

Do not know High

C.46. What is the usual basis for negotiation? Do not know High

C.47. Are minutes of negotiation taken and signed?

Do not know High

C.48. How long after negotiation is the contract signed?

Do not know High

C.49. Is there an evaluation system for measuring the outputs of consultants?

Do not know High

Payments

C.50. Are advance payments made Yes Low

C.51. What is the standard period for payment included in contracts?

Except the quality security, other payment shall be finished before the contract completed.

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

A long time

C.53. When late payment is made, are the beneficiaries paid interest?

sometime

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Purchasing director Yes he does.

Low

E.5. Which of the following actions require approvals outside the procurement unit or the

Low

Page 28: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

22

evaluation committee, as the case may be, and who grants the approval?

(a) Bidding document, invitation to pre-qualify or RFP

Purchasing Unit chief

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Purchasing director

(c) Evaluation reports Bid Evaluation Committee

(d) Notice of award Purchaser

(e) Invitation to consultants to negotiate Purchaser

(f) Contracts Purchaser

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Average

C. Procurement Practices Average, but on consulting services is high.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Average

Page 29: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

23

Annex 1-3: Executing Agency Capacity Assessment Questionnaire — Fenxi County Project Management Office (CPMO) under County Poverty Alleviation

Bureau

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency CPMO - Fenxi County Project Management Office under county Poverty Alleviation Bureau

Position or Title Name (Wang Wenbing)

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

5 years Average

A.2. How many staff in the procurement department/unit are:

Average i. Full Time? /

ii. Part Time?

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

General Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

No Average

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes, the procurement unit is belong to the government

Average

A.9. If yes, what type of procurement does it undertake?

Equipment, train and third party services

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of county Low

Page 30: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

24

A.11. Do the procurement positions in the agency have job descriptions, which outline specific roles, minimum technical requirements and career routes?

No Low

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Yes

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Yes

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

County poverty alleviation bureau

Average

A.19. Who approves the procurement specifications?

County finance bureau

A.20. Who drafts the bidding documents? Third-party service unit

A.21. Who manages the sale of the bidding documents?

Third-party service unit

A.22. Who identifies the need for consulting services requirements?

County government procurement center

Average A.23. Who drafts the terms of reference (TOR)? County poverty alleviation bureau

A.24. Who prepares the request for proposals (RFPs)?

County poverty alleviation bureau

B. Information Management

B.1. Is there a referencing system for procurement files?

No High

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 15 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

Page 31: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

25

B.7. Are copies of invoices included with the contract papers?

No Average

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

No High

C.5. Are all queries from bidders replied to in writing?

No

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? Relevant unit

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Average

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

professional Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

final decision Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No Average

C.18. Are there established goods receiving procedures?

No High

C.19. Are all goods that are received recorded as assets or inventory in a register?

as assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 32: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

26

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No High

C.28. Do firms have to pay for the RFP

document?? No High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No response High

C.30. Are pre-proposal visits and meetings arranged?

No response

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

No response

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

No response High

C.34. Are the technical and financial proposals required to be in separate envelopes?

No response High

C.35. Are proposal securities required? No response High

C.36. Are technical proposals opened in public? No response

High C.37. Are minutes of the technical opening distributed?

No response

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response High

C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

No response High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

Page 33: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

27

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

No response High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

No response

C.53. When late payment is made, are the beneficiaries paid interest?

No response

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

No response High

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No response High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No response High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

County government procurement center

Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

(a) Bidding document, invitation to pre-qualify or RFP

No response

Page 34: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

28

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

(c) Evaluation reports No response

(d) Notice of award No response

(e) Invitation to consultants to negotiate No response

(f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Average

C. Procurement Practices High, especially on consulting services and payment

D. Effectiveness High

E. Accountability Measures High

OVERALL RISK RATING High

Page 35: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

29

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (01) Shanxi Qinzhouhuang Millet Group Co., Ltd. (QZHM)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Qinzhouhuang Millet Group Co., Ltd. (QZHM)

Position or Title Mr. Li Renyu

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

5 years Average

A.2. How many staff in the procurement department/unit are:

No response

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor High

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

/ Average

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

bidding

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

To the general manager Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 36: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

30

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Entrusted agency have

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

/

A.18. Who drafts the procurement specifications?

Entrusted agency

High

A.19. Who approves the procurement specifications?

Entrusted agency

A.20. Who drafts the bidding documents? Engaged professional agency

A.21. Who manages the sale of the bidding documents?

Engaged professional agency

A.22. Who identifies the need for consulting services requirements?

Engaged professional agency

Low A.23. Who drafts the terms of reference (TOR)? Engaged professional agency

A.24. Who prepares the request for proposals (RFPs)?

Engaged professional agency

B. Information Management

B.1. Is there a referencing system for procurement files?

No response High

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? According to the regulation Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 37: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

31

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

/

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

/ High

C.4. Is there a minimum period for preparation of bids and if yes how long?

/ Average

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? No

High C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? Deputy General manager or above

C.12. Are the minutes free of charge? /

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

permanent committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Professional qualification Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Yes Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

Yes Average

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

Page 38: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

32

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

Yes Average

C.23. If the above answer is yes, what were the major challenges?

/

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

/ High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

Professional persons Low

C.26. What criteria is used to evaluate EOIs? / High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

/ High

C.28. Do firms have to pay for the RFP

document?? / High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Related technical persons

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? / High

C.36. Are technical proposals opened in public? / High C.37. Are minutes of the technical opening

distributed? /

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

/

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response

High C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

No response High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

C.46. What is the usual basis for negotiation? / High

Page 39: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

33

C.47. Are minutes of negotiation taken and signed?

/ High

C.48. How long after negotiation is the contract signed?

/ High

C.49. Is there an evaluation system for measuring the outputs of consultants?

/ High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

/

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

/

C.53. When late payment is made, are the beneficiaries paid interest?

No

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

/ High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

/ High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

/ High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

/ High

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

/ High

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

No response High

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low a) Bidding document, invitation to pre-

qualify or RFP Professional agency

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Professional agency

Page 40: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

34

c) Evaluation reports Professional agency

d) Notice of award Professional agency

e) Invitation to consultants to negotiate Professional agency

f) Contracts Professional agency

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity High

B. Information Management Average

C. Procurement Practices High.

D. Effectiveness High

E. Accountability Measures High

OVERALL RISK RATING High

Page 41: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

35

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (02) Guangling Kitano Edible Fungus Industrial Development Co., Ltd. (GLKT)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Guangling Kitano Edible Fungus Industrial Development Co., Ltd. (GLKT)

Position or Title No response

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

10 years Low

A.2. How many staff in the procurement department/unit are:

2 persons

Low a) Full Time? 1

b) Part Time? 1

c) Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

Shopping

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 42: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

36

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Yes

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Yes

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

Technical department

Low

A.19. Who approves the procurement specifications?

Vice president of producing and technology superior

A.20. Who drafts the bidding documents? Supply unit

A.21. Who manages the sale of the bidding documents?

Supply unit

A.22. Who identifies the need for consulting services requirements?

Technical department

Low A.23. Who drafts the terms of reference (TOR)? Vice president

A.24. Who prepares the request for proposals (RFPs)?

Technology supervisor

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 5 years Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

B.7. Are copies of invoices included with the contract papers?

No High

Page 43: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

37

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

No High

C.5. Are all queries from bidders replied to in writing?

No

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? Yes

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? No

High C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? No response

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

Individual Average

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Experts with relevant qualification

Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Additional Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

Assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

Page 44: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

38

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? No response High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No response High

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Suppliers who have interesting

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? No Low

C.36. Are technical proposals opened in public? Yes Low C.37. Are minutes of the technical opening

distributed? Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

No

High C.39. Who determines the final technical ranking and how?

Technical department

C.40. Are the technical scores sent to all firms? No

C.41. Are the financial proposal opened in public?

Yes

Low C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

Quality and technical indicator High

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

2 weeks Low

C.46. What is the usual basis for negotiation? Technical Low

Page 45: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

39

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

2 weeks Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No Average

Payments

C.50. Are advance payments made No response Average

C.51. What is the standard period for payment included in contracts?

Advance payment, arrivals payment and acceptance payment

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

1 month

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No Average

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No Average

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

a) Bidding document, invitation to pre-qualify or RFP

No response

Page 46: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

40

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Average

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures High

OVERALL RISK RATING High

Page 47: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

41

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (03) Shanxi Phoenix Wine Industry Co., Ltd. (PHNX)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Phoenix Wine Industry Co., Ltd. (PHNX)

Position or Title Manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

15 years Low

A.2. How many staff in the procurement department/unit are:

5 persons

Low d) Full Time? Y

e) Part Time? /

f) Seconded? /

A.3. Does the procurement staff have English language proficiency?

General Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

Packaging material

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

No Average

Page 48: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

42

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

General manager

Low

A.19. Who approves the procurement specifications?

Board of director

A.20. Who drafts the bidding documents? Procurement manager

A.21. Who manages the sale of the bidding documents?

Procurement manager

A.22. Who identifies the need for consulting services requirements?

No response

High A.23. Who drafts the terms of reference (TOR)? No response

A.24. Who prepares the request for proposals (RFPs)?

No response

B. Information Management

B.1. Is there a referencing system for procurement files?

No response High

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? Yes Low

B.4. Are copies of bids or proposals retained with the evaluation?

No High

B.5. Are copies of the original advertisements retained with the pre-contract papers?

No High

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 49: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

43

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

No Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

High C.8. Can late bids be accepted? Yes

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? No

Average C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? No

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

Manager and board of director Average

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No response Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

additional approvals Average

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

30 days Low

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

No response High

C.20. Is the agency/procurement department familiar with letters of credit?

No response High

C.21. Does the procurement department register and track warranty and latent defects liability periods?

No response High

Consulting Services

Page 50: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

44

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No response High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? No response High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No response High

C.30. Are pre-proposal visits and meetings arranged?

No response

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

No response

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

No response High

C.34. Are the technical and financial proposals required to be in separate envelopes?

No response High

C.35. Are proposal securities required? No response High

C.36. Are technical proposals opened in public? No response High C.37. Are minutes of the technical opening

distributed? No response

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

No response

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response

High C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

No response High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

C.46. What is the usual basis for negotiation? No response High

Page 51: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

45

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

No response High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

1 month

C.53. When late payment is made, are the beneficiaries paid interest?

No

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

No response High

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No Average

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager, board of director

Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low a) Bidding document, invitation to pre-

qualify or RFP Yes

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Yes

Page 52: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

46

c) Evaluation reports Yes

d) Notice of award Yes

e) Invitation to consultants to negotiate Yes

f) Contracts Yes

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management High

C. Procurement Practices High

D. Effectiveness High

E. Accountability Measures Average

OVERALL RISK RATING High

Page 53: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

47

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (04) Shanxi Juxin Weiye Agricultural and Science & Technology Development Co., Ltd.

(JXWY)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Juxin Weiye Agricultural and Sci & Tech Development Co., Ltd. (JXWY)

Position or Title Vice president

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

Yes Low

A.2. How many staff in the procurement department/unit are:

5 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

No Average

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No Average

A.9. If yes, what type of procurement does it undertake?

No response

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 54: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

48

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

No response

High

A.19. Who approves the procurement specifications?

No response

A.20. Who drafts the bidding documents? agent

A.21. Who manages the sale of the bidding documents?

No response

A.22. Who identifies the need for consulting services requirements?

Vice president

High A.23. Who drafts the terms of reference (TOR)? No response

A.24. Who prepares the request for proposals (RFPs)?

No response

B. Information Management

B.1. Is there a referencing system for procurement files?

No Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

No Average

B.3. For what period are records kept? No Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

No Average

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

B.7. Are copies of invoices included with the contract papers?

No High

Page 55: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

49

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No High

C.4. Is there a minimum period for preparation of bids and if yes how long?

No High

C.5. Are all queries from bidders replied to in writing?

No

C.6. Does the bidding document state the date and time of bid opening?

No High

C.7. Is the opening of bids done in public? No

High C.8. Can late bids be accepted? No response

C.9. Can bids be rejected at bid opening? No response

C.10. Are minutes of the bid opening taken? No response

High C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? No response

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

No response High

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No response High

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No response High

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

Assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

No response High

C.21. Does the procurement department register and track warranty and latent defects liability periods?

No response High

Page 56: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

50

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No response High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? No response High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No response High

C.30. Are pre-proposal visits and meetings arranged?

No response

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

No response

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

No response High

C.34. Are the technical and financial proposals required to be in separate envelopes?

No response High

C.35. Are proposal securities required? No response High

C.36. Are technical proposals opened in public? No response

High C.37. Are minutes of the technical opening distributed?

No response

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

No response

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response High

C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

No response High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

Page 57: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

51

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

No response High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

No response

C.53. When late payment is made, are the beneficiaries paid interest?

No response

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

No response High

D.2. Does the agency monitor and track its contractual payment obligations?

No response High

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No response High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No response High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No response High

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No response High

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No response High

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

No response High

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

No response

High

a) Bidding document, invitation to pre-qualify or RFP

No response

Page 58: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

52

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Average

C. Procurement Practices High.

D. Effectiveness High

E. Accountability Measures High

OVERALL RISK RATING High

Page 59: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

53

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (05) Heshun County Lvhe Ecological Agriculture & Livestock Development Co. Ltd.

(HSLH)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Heshun County Lvhe Ecological Agriculture & Livestock Development Co. Ltd. (HSLH)

Position or Title Director

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

10 years Low

A.2. How many staff in the procurement department/unit are:

2 人

Average 1) Full Time? √

2) Part Time?

3) Seconded?

A.3. Does the procurement staff have English language proficiency?

Poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

/

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

board of directors Low

Page 60: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

54

A.11. Do the procurement positions in the agency have job descriptions, which outline specific roles, minimum technical requirements and career routes?

Yes Low

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

/

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

/

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

Department of purchasing

Average

A.19. Who approves the procurement specifications?

Board of directors

A.20. Who drafts the bidding documents? Office

A.21. Who manages the sale of the bidding documents?

Office

A.22. Who identifies the need for consulting services requirements?

Technical Department

High A.23. Who drafts the terms of reference (TOR)? Office

A.24. Who prepares the request for proposals (RFPs)?

Office

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 2 years Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

Page 61: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

55

B.7. Are copies of invoices included with the contract papers?

Yes Low

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

/

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

Yes, 30 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? Director

C.12. Are the minutes free of charge? No

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

Ad-hoc Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Personal who has relevant special skill

Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Yes Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

Assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 62: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

56

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

/

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? / High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

Actual experience High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Director manager

C.33. Are all queries from consultants answered/addressed in writing?

No High

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Average C.39. Who determines the final technical ranking and how?

CSC

C.40. Are the technical scores sent to all firms? No

C.41. Are the financial proposal opened in public?

No Average

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

CSC Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

15 working days Low

Page 63: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

57

C.46. What is the usual basis for negotiation? Qualification certificate High

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

7 working days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No High

Payments

C.50. Are advance payments made No High

C.51. What is the standard period for payment included in contracts?

After acceptance of goods

Average C.52. On average, how long is it between receiving a firm’s invoice and making payment?

3 days

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No response High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No response High

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

No response

High

a) Bidding document, invitation to pre-qualify or RFP

No response

Page 64: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

58

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Low

C. Procurement Practices Average, for Consulting Services is high

D. Effectiveness Average

E. Accountability Measures High

OVERALL RISK RATING High

Page 65: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

59

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (06) Fenxi Hongchang Breeding Co., Ltd. (FXHC)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Fenxi Hongchang Breeding Co., Ltd. (FXHC)

Position or Title Name: Fu Zhenjun

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

7-8 years Low

A.2. How many staff in the procurement department/unit are:

About 800 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

No Average

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

No

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

No High

A.11. Do the procurement positions in the agency have job descriptions, which outline

No High

Page 66: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

60

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

No

High

A.19. Who approves the procurement specifications?

No

A.20. Who drafts the bidding documents? Entrust professional persons or institution

A.21. Who manages the sale of the bidding documents?

No

A.22. Who identifies the need for consulting services requirements?

General Manager

Average A.23. Who drafts the terms of reference (TOR)? According to General Manager’s instruction

A.24. Who prepares the request for proposals (RFPs)?

According to General Manager’s instruction

B. Information Management

B.1. Is there a referencing system for procurement files?

No Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

50% Average

B.3. For what period are records kept? No idea High

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

No High

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

B.7. Are copies of invoices included with the contract papers?

No response High

Page 67: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

61

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No High

C.4. Is there a minimum period for preparation of bids and if yes how long?

No High

C.5. Are all queries from bidders replied to in writing?

No

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Average C.8. Can late bids be accepted? No covered

C.9. Can bids be rejected at bid opening? No covered

C.10. Are minutes of the bid opening taken? No covered

High C.11. Who may have a copy of the minutes? No covered

C.12. Are the minutes free of charge? No covered

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

No covered High

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No covered High

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No covered High

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No covered High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No covered High

C.18. Are there established goods receiving procedures?

No covered High

C.19. Are all goods that are received recorded as assets or inventory in a register?

No covered High

C.20. Is the agency/procurement department familiar with letters of credit?

No covered High

C.21. Does the procurement department register and track warranty and latent defects liability periods?

No covered High

Page 68: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

62

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No High

C.28. Do firms have to pay for the RFP

document?? No High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No High

C.30. Are pre-proposal visits and meetings arranged?

No

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

No

C.32. To whom are the minutes distributed? No

C.33. Are all queries from consultants answered/addressed in writing?

No High

C.34. Are the technical and financial proposals required to be in separate envelopes?

No High

C.35. Are proposal securities required? No High

C.36. Are technical proposals opened in public? No

High C.37. Are minutes of the technical opening distributed?

No

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

No

High C.39. Who determines the final technical ranking and how?

No

C.40. Are the technical scores sent to all firms? No

C.41. Are the financial proposal opened in public?

No High

C.42. Are minutes of the financial opening distributed?

No

C.43. How is the financial evaluation completed?

No High

C.44. Are face to face contract negotiations held?

No High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No High

Page 69: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

63

C.46. What is the usual basis for negotiation? No covered High

C.47. Are minutes of negotiation taken and signed?

No covered High

C.48. How long after negotiation is the contract signed?

No covered High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No covered High

Payments

C.50. Are advance payments made No covered High

C.51. What is the standard period for payment included in contracts?

No covered

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

No covered

C.53. When late payment is made, are the beneficiaries paid interest?

No covered

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

No covered High

D.2. Does the agency monitor and track its contractual payment obligations?

No covered High

D.3. Is a complaints resolution mechanism described in national procurement documents?

No covered High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No covered High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No covered High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No covered High

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No covered High

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No covered High

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager High

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

a) Bidding document, invitation to pre-qualify or RFP

No covered

Page 70: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

64

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No covered

c) Evaluation reports No covered

d) Notice of award No covered

e) Invitation to consultants to negotiate No covered

f) Contracts No covered

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No covered High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No covered High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management High

C. Procurement Practices High.

D. Effectiveness High

E. Accountability Measures High

OVERALL RISK RATING High

Page 71: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

65

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (07) Fushan Guhuan Husbandry Science & Technology Co., Ltd. (FSGH)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Fushan Guhuan Husbandry Sci. & Tech. Co., Ltd. (FSGH)

Position or Title Manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

15 years Low

A.2. How many staff in the procurement department/unit are:

3 persons

Low i. Full Time? 1

ii. Part Time? 2

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

High

A.9. If yes, what type of procurement does it undertake?

No response

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 72: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

66

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

Low

A.19. Who approves the procurement specifications?

Board of director

A.20. Who drafts the bidding documents? Purchasing Department

A.21. Who manages the sale of the bidding documents?

Head of unit

A.22. Who identifies the need for consulting services requirements?

Deputy of unit

Low A.23. Who drafts the terms of reference (TOR)? Deputy of unit

A.24. Who prepares the request for proposals (RFPs)?

Deputy of unit

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

No Average

B.3. For what period are records kept? No response High

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 73: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

67

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

3 months Average

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? Yes

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Professional class Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Final Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

inventory Average

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 74: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

68

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No response High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Evaluation committee

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Low

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

No response Average

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

Yes, 10 days Low

Page 75: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

69

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

10 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

Yes Low

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

Average C.52. On average, how long is it between receiving a firm’s invoice and making payment?

10 working days

C.53. When late payment is made, are the beneficiaries paid interest?

No

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No response High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No response

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Board of director Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

a) Bidding document, invitation to pre-qualify or RFP

Yes

Page 76: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

70

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Yes

c) Evaluation reports Yes

d) Notice of award Yes

e) Invitation to consultants to negotiate Yes

f) Contracts Average

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Low

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Average

Page 77: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

71

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (08) Quwo Lvheng Agricultural Development Co., Ltd. (QWLH)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Quwo Lvheng Agricultural Development Co., Ltd. (QWLH)

Position or Title Manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

3 years High

A.2. How many staff in the procurement department/unit are:

3 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Lack of ability Average

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

material

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 78: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

72

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

General manager

Low

A.19. Who approves the procurement specifications?

Board of director

A.20. Who drafts the bidding documents? General manager

A.21. Who manages the sale of the bidding documents?

Procurement department

A.22. Who identifies the need for consulting services requirements?

Procurement department

Low A.23. Who drafts the terms of reference (TOR)? General manager

A.24. Who prepares the request for proposals (RFPs)?

General manager

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 3 years Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 79: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

73

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

3 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

High C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? General manager

C.12. Are the minutes free of charge? No

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

permanent committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Experts with relevant qualification

Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No Average

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

30 days Low

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

Yes Low

C.18. Are there established goods receiving procedures?

No Average

C.19. Are all goods that are received recorded as assets or inventory in a register?

inventory Average

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

Page 80: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

74

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

Not clear High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? General manager

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes Low C.37. Are minutes of the technical opening

distributed? Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Evaluation committee

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes

Low C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

Evaluation committee Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

Yes Low

C.46. What is the usual basis for negotiation? Public and fair Low

Page 81: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

75

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

3 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No Average

Payments

C.50. Are advance payments made No response Average

C.51. What is the standard period for payment included in contracts?

1 week

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

1 week

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No Average

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Legal person High

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High a) Bidding document, invitation to pre-

qualify or RFP No response

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

Page 82: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

76

c) Evaluation reports No response

d) Notice of award Project manager

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Average

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures Average

OVERALL RISK RATING Average

Page 83: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

77

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (9) Shanxi Qierkang Elaeagnus Biological Products Co. (QIEK)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Qierkang Elaeagnus Biological Products Co. (QIEK)

Position or Title Deputy general manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

13 years Low

A.2. How many staff in the procurement department/unit are:

3 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

general Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

No Average

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Average

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

Self procurement

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

General manager Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 84: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

78

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes, but no for ADB loan

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

General manager

Low

A.19. Who approves the procurement specifications?

Board of director

A.20. Who drafts the bidding documents? purchasing and contract department

A.21. Who manages the sale of the bidding documents?

Third party institution

A.22. Who identifies the need for consulting services requirements?

Producing department

Average A.23. Who drafts the terms of reference (TOR)? Producing department

A.24. Who prepares the request for proposals (RFPs)?

Producing department

B. Information Management

B.1. Is there a referencing system for procurement files?

No Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 5 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

No Average

Page 85: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

79

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

No Average

C.5. Are all queries from bidders replied to in writing?

No response

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

High C.8. Can late bids be accepted? Yes

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? Bidding committee

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Professional person Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

additional approvals Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

Yes Low

C.18. Are there established goods receiving procedures?

No Average

C.19. Are all goods that are received recorded as assets or inventory in a register?

inventory Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 86: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

80

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

Yes, finance and lawyer Low

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

Resources data base High

C.28. Do firms have to pay for the RFP

document?? No Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

No

C.32. To whom are the minutes distributed? No

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Average C.37. Are minutes of the technical opening distributed?

No

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Yes, evaluation committee

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Average

C.42. Are minutes of the financial opening distributed?

No

C.43. How is the financial evaluation completed?

By committee Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

immediately Low

Page 87: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

81

C.46. What is the usual basis for negotiation? Control the least bid price High

C.47. Are minutes of negotiation taken and signed?

No High

C.48. How long after negotiation is the contract signed?

2-3 weeks Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No High

Payments

C.50. Are advance payments made Yes Average

C.51. What is the standard period for payment included in contracts?

Not necessarily

Average C.52. On average, how long is it between receiving a firm’s invoice and making payment?

Not necessarily

C.53. When late payment is made, are the beneficiaries paid interest?

No

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Average

a) Bidding document, invitation to pre-qualify or RFP

No need

Page 88: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

82

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No need

c) Evaluation reports No need

d) Notice of award No need

e) Invitation to consultants to negotiate No need

f) Contracts Contract department

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Low

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Average

Page 89: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

83

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (10) Linfen Zhongde Farming Technology Development Co., Ltd. (LFZD)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Linfen Zhongde Farming Technology Development Co., Ltd. (LFZD)

Position or Title Procurement manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

19 years Low

A.2. How many staff in the procurement department/unit are:

2 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

General Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

Tangible goods purchasing and intangible service procurement

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 90: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

84

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Will be covered the foreign financed project

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Will be covered the foreign financed project

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

Procurement manager

Low

A.19. Who approves the procurement specifications?

Chairman of Board of director

A.20. Who drafts the bidding documents? Procurement Agent

A.21. Who manages the sale of the bidding documents?

Procurement Agent

A.22. Who identifies the need for consulting services requirements?

Linfen Zhongde Farming Technology Development Co.

Low A.23. Who drafts the terms of reference (TOR)? Procurement manager

A.24. Who prepares the request for proposals (RFPs)?

Procurement manager

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 15 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 91: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

85

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

25 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Average C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? Bidders, ADB and relevant supervisory units

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

Ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Experts selected from governmental database

Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Additional approvals Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

Works: 110 days Goods: 110 days Services: 105 days

Low

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

Yes Low

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

Assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 92: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

86

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

Yes Low

C.26. What criteria is used to evaluate EOIs? Standard in written Low

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

QCBS Low

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Construction unit, Consulting company, and supervision unit

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes Low C.37. Are minutes of the technical opening

distributed? Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Evaluation committee, by comprehensive score method

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes

Low C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

Evaluation committee Low

C.44. Are face to face contract negotiations held?

Yes Low

Page 93: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

87

C.45. How long after financial evaluation is negotiation held with the selected firm?

One week Low

C.46. What is the usual basis for negotiation? Qualification, quality and cost Low

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

20 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

Yes Low

Payments

C.50. Are advance payments made Yes Low

C.51. What is the standard period for payment included in contracts?

According to the payment schedule

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

1 week

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Chairman of Board of directors Yes

Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

No response Low

Page 94: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

88

a) Bidding document, invitation to pre-qualify or RFP

No response

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts Chairman of Board of directors

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No Average

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Low

C. Procurement Practices Low

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Low

Page 95: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

89

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (11) Liulin Fuzhongyuan Agricultural Development Co., Ltd. (LFZY)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Liulin Fuzhongyuan Livestock Breeding Cooperative (LFZY)

Position or Title Office director

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

6 years Average

A.2. How many staff in the procurement department/unit are:

3 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

Basic communication capacity Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

Equipment, material

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

Chairman of Board Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 96: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

90

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No response

A.18. Who drafts the procurement specifications?

Logistics department

Average

A.19. Who approves the procurement specifications?

No response

A.20. Who drafts the bidding documents? office

A.21. Who manages the sale of the bidding documents?

office

A.22. Who identifies the need for consulting services requirements?

office

Low A.23. Who drafts the terms of reference (TOR)? office

A.24. Who prepares the request for proposals (RFPs)?

office

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 10 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 97: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

91

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No response Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

1 month Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No response Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

additional approvals Average

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

inventory High

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Average

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 98: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

92

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

Yes, by logistical, office, general manager and project department person

Low

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Project management and other departments

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes Low C.37. Are minutes of the technical opening

distributed? Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes

Low C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

Yes Low

Page 99: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

93

C.45. How long after financial evaluation is negotiation held with the selected firm?

0.5 month Low

C.46. What is the usual basis for negotiation? Public and fair Average

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

10 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

Yes Low

Payments

C.50. Are advance payments made Yes Low

C.51. What is the standard period for payment included in contracts?

No response

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

2 days

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

Page 100: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

94

a) Bidding document, invitation to pre-qualify or RFP

No response

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports Yes

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts Yes

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Low

C. Procurement Practices Average.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Low

Page 101: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

95

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (12) Shilou Shude Jujube Industry Co., Ltd. (SLSD)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shilou Shude Jujube industry Co., Ltd. (SLSD)

Position or Title Financial personnel

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

8 years Low

A.2. How many staff in the procurement department/unit are:

200 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

Do not understand High

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

No

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

No Average

Page 102: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

96

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

purchasing director

High

A.19. Who approves the procurement specifications?

purchasing director

A.20. Who drafts the bidding documents? Financial personnel

A.21. Who manages the sale of the bidding documents?

Financial personnel

A.22. Who identifies the need for consulting services requirements?

Financial personnel

High A.23. Who drafts the terms of reference (TOR)? Financial personnel

A.24. Who prepares the request for proposals (RFPs)?

Financial personnel

B. Information Management

B.1. Is there a referencing system for procurement files?

No High

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 10 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

No High

B.5. Are copies of the original advertisements retained with the pre-contract papers?

No High

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No High

B.7. Are copies of invoices included with the contract papers?

No High

Page 103: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

97

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

No

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No High

C.4. Is there a minimum period for preparation of bids and if yes how long?

No High

C.5. Are all queries from bidders replied to in writing?

No

C.6. Does the bidding document state the date and time of bid opening?

No High

C.7. Is the opening of bids done in public? No

High C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? Chief of the unit

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Chief of the unit High

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No Low

C.18. Are there established goods receiving procedures?

No High

C.19. Are all goods that are received recorded as assets or inventory in a register?

Assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

No Average

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 104: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

98

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

Yes, financial and technical persons

Low

C.26. What criteria is used to evaluate EOIs? Price and quality Low

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No High

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Everyone on meeting

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Chief of technical department

C.40. Are the technical scores sent to all firms? No

C.41. Are the financial proposal opened in public?

No High

C.42. Are minutes of the financial opening distributed?

No

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

15 days Average

Page 105: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

99

C.46. What is the usual basis for negotiation? Price, quality and after-services Average

C.47. Are minutes of negotiation taken and signed?

No High

C.48. How long after negotiation is the contract signed?

15 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No Average

Payments

C.50. Are advance payments made 3 months Average

C.51. What is the standard period for payment included in contracts?

7 days

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

7 days

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

No High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No Average

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No Average

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Chief of unit Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

a) Bidding document, invitation to pre-qualify or RFP

Yes

Page 106: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

100

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Yes

c) Evaluation reports Yes

d) Notice of award Yes

e) Invitation to consultants to negotiate Yes

f) Contracts Yes

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management High

C. Procurement Practices High.

D. Effectiveness High

E. Accountability Measures Low

OVERALL RISK RATING High

Page 107: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

101

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (13) Shanxi Tianzhirun Date Processing Co., Ltd. (TZRD)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Tianzhirun Date Processing Co., Ltd. (TZRD)

Position or Title No response

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

15 years Low

A.2. How many staff in the procurement department/unit are:

3 persons

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

Normal Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Low

A.9. If yes, what type of procurement does it undertake?

bidding

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 108: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

102

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

Head of unit

Low

A.19. Who approves the procurement specifications?

Head of unit

A.20. Who drafts the bidding documents? purchasing department and office

A.21. Who manages the sale of the bidding documents?

Office

A.22. Who identifies the need for consulting services requirements?

Head of unit

Low A.23. Who drafts the terms of reference (TOR)? purchasing department and office

A.24. Who prepares the request for proposals (RFPs)?

office

B. Information Management

B.1. Is there a referencing system for procurement files?

No Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? Permanent Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 109: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

103

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

No response Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? No

High C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? /

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

/ Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Additional approval Average

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response Average

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response Average

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

as inventory Average

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 110: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

104

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No Average

C.23. If the above answer is yes, what were the major challenges?

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

Temporary hired High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

No

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

No

C.32. To whom are the minutes distributed?

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Professional organizations

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Low

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

By evaluation meeting Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

7 working days Low

Page 111: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

105

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No High

C.48. How long after negotiation is the contract signed?

3 working days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

yes Low

Payments

C.50. Are advance payments made No Low

C.51. What is the standard period for payment included in contracts?

According to the working period

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

Within one month

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Purchasing director. Yes he does.

Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

(a) Bidding document, invitation to pre-qualify or RFP

Yes. Third party with relevant qualification

Page 112: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

106

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

(c) Evaluation reports No response

(d) Notice of award Yes, the head of PAC

(e) Invitation to consultants to negotiate No response

(f) Contracts Yes, the head of PAC

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Low

C. Procurement Practices Average

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Low

Page 113: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

107

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (14) Xinjiang Hefeng Grain Planting Technology Cooperatives (XJHF)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Xinjiang Hefeng Grain Planting Technology Cooperatives (XJHF)

Position or Title Legal Person

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

8 years Low

A.2. How many staff in the procurement department/unit are:

2 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Average

A.9. If yes, what type of procurement does it undertake?

Negotiation within shareholders

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 114: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

108

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.14. Is there a procurement process manual for consulting services?

No response

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No response

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No response

A.18. Who drafts the procurement specifications?

No response

High

A.19. Who approves the procurement specifications?

No response

A.20. Who drafts the bidding documents? No response

A.21. Who manages the sale of the bidding documents?

No response

A.22. Who identifies the need for consulting services requirements?

No response

High A.23. Who drafts the terms of reference (TOR)? No response

A.24. Who prepares the request for proposals (RFPs)?

No response

B. Information Management

B.1. Is there a referencing system for procurement files?

No response Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 15 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 115: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

109

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No response High

C.4. Is there a minimum period for preparation of bids and if yes how long?

No response High

C.5. Are all queries from bidders replied to in writing?

No response

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? public

C.12. Are the minutes free of charge? No

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Professional technical person Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Final decision Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

as assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 116: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

110

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Who participate the meeting

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? No response Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response High

C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

Yes Average

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

Page 117: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

111

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

No response High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

No response

C.53. When late payment is made, are the beneficiaries paid interest?

No response

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

No response High

D.2. Does the agency monitor and track its contractual payment obligations?

No response High

D.3. Is a complaints resolution mechanism described in national procurement documents?

No response High

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No response High

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No response High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No response High

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No response High

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No response High

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

No response High

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

a) Bidding document, invitation to pre-qualify or RFP

No response

Page 118: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

112

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management High

C. Procurement Practices High

D. Effectiveness High

E. Accountability Measures High

OVERALL RISK RATING High

Page 119: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

113

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (15) Shanxi Xinjiang Vegetable Industry Development Co., Ltd. (XJVI)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Xinjiang Vegetable Industry Development Co., Ltd. (XJVI)

Position or Title No response

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

25 years Low

A.2. How many staff in the procurement department/unit are:

8 persons

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

general Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

No

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the Chairman of the board of directors

Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 120: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

114

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

Chief of Purchasing Department

Low

A.19. Who approves the procurement specifications?

Chief of Purchasing Department

A.20. Who drafts the bidding documents? Market manager

A.21. Who manages the sale of the bidding documents?

Market manager

A.22. Who identifies the need for consulting services requirements?

Chief of Purchasing Department

Average A.23. Who drafts the terms of reference (TOR)? Chairman of the board of directors

A.24. Who prepares the request for proposals (RFPs)?

Chief of Purchasing Department

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? Long time Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 121: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

115

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

/

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

15 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Average C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? bidders

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

permanent committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Integrity and honest and loyal to the enterprise, through a variety of procurement skills for cost reduction and priority principle, the total cost of unity and cooperation, innovation, seek progress, strong adaptability

Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

Yes Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No Average

C.18. Are there established goods receiving procedures?

Yes Low

C.19. Are all goods that are received recorded as assets or inventory in a register?

As assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

Page 122: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

116

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? /

C.33. Are all queries from consultants answered/addressed in writing?

Part of them Average

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes Low C.37. Are minutes of the technical opening

distributed? Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes

Low C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

No response High

Page 123: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

117

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

15 days Low

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

15 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

Yes Low

Payments

C.50. Are advance payments made Yes Low

C.51. What is the standard period for payment included in contracts?

Confirmed by two parties

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

10 days

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Purchasing director Yes he does.

Low

E.5. Which of the following actions require approvals outside the procurement unit or the

Low

Page 124: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

118

evaluation committee, as the case may be, and who grants the approval?

a) Bidding document, invitation to pre-qualify or RFP

No

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No

c) Evaluation reports No

d) Notice of award No

e) Invitation to consultants to negotiate No

f) Contracts No

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Low

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Average

Page 125: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

119

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (16) Shanxi Kaisheng Fertilizers Group Co., Ltd. (KSFC)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Kaisheng Fertilizers Group Co., Ltd. (KSFC)

Position or Title Project Manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

18 years Low

A.2. How many staff in the procurement department/unit are:

5 persons

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

poor Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No response Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No, the unit in charge of procurement

Average

A.9. If yes, what type of procurement does it undertake?

No response

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the General Manager Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 126: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

120

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

Yes

Low

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

Yes

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

Yes

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

purchasing department

Low

A.19. Who approves the procurement specifications?

General manager

A.20. Who drafts the bidding documents? Project manager

A.21. Who manages the sale of the bidding documents?

General manager

A.22. Who identifies the need for consulting services requirements?

Project manager

Low A.23. Who drafts the terms of reference (TOR)? Project manager

A.24. Who prepares the request for proposals (RFPs)?

Project manager

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 5 years Low

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 127: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

121

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

/

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

3-5 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Average C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? Awarded bidder

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Engineer qualification Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

General manager Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

1- for works, 15-20 days 2-for goods, 10-15 days

Low

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

/ Average

C.18. Are there established goods receiving procedures?

/ Average

C.19. Are all goods that are received recorded as assets or inventory in a register?

No response Average

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 128: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

122

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

/

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? No High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

/ High

C.28. Do firms have to pay for the RFP

document?? Yes Average

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Relevant persons

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Project manager

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Low

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

Yes Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

Immediately Low

Page 129: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

123

C.46. What is the usual basis for negotiation? Technical and prices Low

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

Immediately Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No Average

Payments

C.50. Are advance payments made / Low

C.51. What is the standard period for payment included in contracts?

One year

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

One year

C.53. When late payment is made, are the beneficiaries paid interest?

Immediately conduct communication with the beneficiaries

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General Manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

(a) Bidding document, invitation to pre-qualify or RFP

By public resource trading center

Page 130: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

124

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

By public resource trading center

(c) Evaluation reports By public resource trading center

(d) Notice of award By public resource trading center

(e) Invitation to consultants to negotiate /

(f) Contracts /

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Low

C. Procurement Practices Average

D. Effectiveness Low

E. Accountability Measures Low

OVERALL RISK RATING Low

Page 131: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

125

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (17) Yuncheng Xinke Taifang Vegetable Trading Co., Ltd. (XKTF)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Yuncheng Xinke Taifang Vegetable Trading Co., Ltd. (XKTF)

Position or Title Administration Department Manager

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

10 years Low

A.2. How many staff in the procurement department/unit are:

4 persons

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

Basic skilled Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes

Average

A.9. If yes, what type of procurement does it undertake?

No response

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

Yes Low

Page 132: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

126

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

High

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

No

A.18. Who drafts the procurement specifications?

General manager

Low

A.19. Who approves the procurement specifications?

General manager

A.20. Who drafts the bidding documents? purchasing manager

A.21. Who manages the sale of the bidding documents?

purchasing department

A.22. Who identifies the need for consulting services requirements?

purchasing manager

Average A.23. Who drafts the terms of reference (TOR)? purchasing manager

A.24. Who prepares the request for proposals (RFPs)?

purchasing manager

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 3 years Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 133: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

127

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No response High

C.4. Is there a minimum period for preparation of bids and if yes how long?

No response High

C.5. Are all queries from bidders replied to in writing?

No response

C.6. Does the bidding document state the date and time of bid opening?

No response High

C.7. Is the opening of bids done in public? No response

High C.8. Can late bids be accepted? No response

C.9. Can bids be rejected at bid opening? No response

C.10. Are minutes of the bid opening taken? No response

High C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? No response

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

No response High

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

No response High

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No response High

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No response High

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

No response High

C.20. Is the agency/procurement department familiar with letters of credit?

No response High

C.21. Does the procurement department register and track warranty and latent defects liability periods?

No response High

Page 134: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

128

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No response High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No response High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? No response High

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

No response High

C.30. Are pre-proposal visits and meetings arranged?

No response

High C.31. Are minutes prepared and circulated after pre-proposal meetings?

No response

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

No response High

C.34. Are the technical and financial proposals required to be in separate envelopes?

No response High

C.35. Are proposal securities required? No response High

C.36. Are technical proposals opened in public? No response

High C.37. Are minutes of the technical opening distributed?

No response

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

No response

High C.39. Who determines the final technical ranking and how?

No response

C.40. Are the technical scores sent to all firms? No response

C.41. Are the financial proposal opened in public?

No response High

C.42. Are minutes of the financial opening distributed?

No response

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

No response High

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

Page 135: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

129

C.46. What is the usual basis for negotiation? No response High

C.47. Are minutes of negotiation taken and signed?

No response High

C.48. How long after negotiation is the contract signed?

No response High

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response High

C.51. What is the standard period for payment included in contracts?

No response

High C.52. On average, how long is it between receiving a firm’s invoice and making payment?

No response

C.53. When late payment is made, are the beneficiaries paid interest?

No response

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

Yes Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager; Yes. Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

No needed

Average

(a) Bidding document, invitation to pre-qualify or RFP

Page 136: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

130

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

(c) Evaluation reports

(d) Notice of award

(e) Invitation to consultants to negotiate

(f) Contracts

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response Average

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response Average

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Average

B. Information Management Low

C. Procurement Practices High

D. Effectiveness Low

E. Accountability Measures Average

OVERALL RISK RATING High

Page 137: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

131

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (18) Shanxi Shanlihong Food Co., Ltd. (SLHC)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Shanlihong Food Co., Ltd. (SLHC)

Position or Title The finance director

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

10 years Low

A.2. How many staff in the procurement department/unit are:

5 persons

Low i. Full Time? Yes

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

general Low

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

No Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

No

Average

A.9. If yes, what type of procurement does it undertake?

/

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

The chief of unit Low

A.11. Do the procurement positions in the agency have job descriptions, which outline

No Average

Page 138: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

132

specific roles, minimum technical requirements and career routes?

A.12. Is there a procurement process manual for goods and works?

No

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

No

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

General engineer

Low

A.19. Who approves the procurement specifications?

General engineer

A.20. Who drafts the bidding documents? Project manager

A.21. Who manages the sale of the bidding documents?

Project manager

A.22. Who identifies the need for consulting services requirements?

Project manager

Low A.23. Who drafts the terms of reference (TOR)? Project manager

A.24. Who prepares the request for proposals (RFPs)?

No response

B. Information Management

B.1. Is there a referencing system for procurement files?

No Average

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

No Average

B.3. For what period are records kept? Yes Average

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes Low

B.7. Are copies of invoices included with the contract papers?

Yes Low

Page 139: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

133

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

High

C.2. If the above answer is yes, what were the major challenges?

No

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

No Average

C.4. Is there a minimum period for preparation of bids and if yes how long?

Yes Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? Yes

C.9. Can bids be rejected at bid opening? Yes

C.10. Are minutes of the bid opening taken? Yes

Low C.11. Who may have a copy of the minutes? Project manager

C.12. Are the minutes free of charge? Yes

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

ad-hoc committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

According to the requirements Low

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No need Low

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

Yes Low

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

No Average

C.18. Are there established goods receiving procedures?

No Average

C.19. Are all goods that are received recorded as assets or inventory in a register?

As assets Low

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 140: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

134

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

No High

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No High

C.26. What criteria is used to evaluate EOIs? According to requirements High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

/ High

C.28. Do firms have to pay for the RFP

document?? Yes Average

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Average C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? Participate meeting persons

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Evaluation committee

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Low

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

Yes Low

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

Subject to the time schedule Low

Page 141: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

135

C.46. What is the usual basis for negotiation? In general Low

C.47. Are minutes of negotiation taken and signed?

No High

C.48. How long after negotiation is the contract signed?

15 days Average

C.49. Is there an evaluation system for measuring the outputs of consultants?

No Average

Payments

C.50. Are advance payments made / Low

C.51. What is the standard period for payment included in contracts?

One year

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

One year

C.53. When late payment is made, are the beneficiaries paid interest?

Immediately conduct communication with the beneficiaries

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

No Average

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

No Average

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

No Average

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

No High

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

No Average

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

No High

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No Average

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

Project manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

Low

(a) Bidding document, invitation to pre-qualify or RFP

Project manager

Page 142: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

136

(b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

Yes

(c) Evaluation reports /

(d) Notice of award /

(e) Invitation to consultants to negotiate /

(f) Contracts /

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

Yes Low

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

Yes Low

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Average

C. Procurement Practices Average

D. Effectiveness Average

E. Accountability Measures Average

OVERALL RISK RATING Average

Page 143: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

137

Annex 2: Procurement Capacity Assessment Questionnaire by 19 PACs — (19) Shanxi Jinglong Group Jinghua Livestock and Poultry Products Development Co.,

Ltd. (JLJH)

Risk Ratings Extremely High High Average Low

I. Specific Assessment and Ratings

Name of Agency Shanxi Jinglong Group Jinghua Livestock and Poultry Products Development Co., Ltd. (JLJH)

Position or Title Finance Director

Question Answer/Finding Risk

A. Organizational and Staff Capacity

A.1. How many years experience does the head of the procurement department/unit have in a direct procurement role?

21 years Low

A.2. How many staff in the procurement department/unit are:

6 persons

Low i. Full Time? Y

ii. Part Time? /

iii. Seconded? /

A.3. Does the procurement staff have English language proficiency?

No response Average

A.4. Are the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

Yes Low

A.5. Does the unit have adequate facilities, such as PCs, internet connections, photocopy facilities, printers, etc., to undertake the planned procurement?

Yes Low

A.6. Does the agency have a procurement training program?

Yes Low

A.7. Does the agency have a Procurement Committee that is independent from the head of the agency?

Yes Low

A.8. Does the agency have a procurement department/unit, including a permanent office that performs the function of a Secretariat for the Procurement Unit, and which serves as the main support unit of the Procurement Committee?

Yes Average

A.9. If yes, what type of procurement does it undertake?

No response

A.10. At what level does the department/unit report (to the head of agency, deputy etc.)?

to the head of unit Low

Page 144: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

138

A.11. Do the procurement positions in the agency have job descriptions, which outline specific roles, minimum technical requirements and career routes?

Yes Low

A.12. Is there a procurement process manual for goods and works?

Yes

Average

A.13. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No

A.14. Is there a procurement process manual for consulting services?

No response

A.15. If there is a manual, is it up to date and does it cover foreign-assisted projects?

No response

A.16. Are there standard documents in use, such as Standard Procurement Documents/Forms, and have they been approved for use on ADB funded projects?

Yes

A.17. Does the TOR follow a standard format such as background, tasks, inputs, objectives and outputs?

Yes

A.18. Who drafts the procurement specifications?

purchasing director

Low

A.19. Who approves the procurement specifications?

General manager

A.20. Who drafts the bidding documents? purchasing director

A.21. Who manages the sale of the bidding documents?

Purchasing department clerk

A.22. Who identifies the need for consulting services requirements?

Purchasing department clerk

Low A.23. Who drafts the terms of reference (TOR)? purchasing director

A.24. Who prepares the request for proposals (RFPs)?

purchasing director

B. Information Management

B.1. Is there a referencing system for procurement files?

Yes Low

B.2. Are there adequate resources allocated to record keeping infrastructure, which includes the record keeping system, space, equipment and personnel to administer the procurement records management functions within the agency?

Yes Low

B.3. For what period are records kept? 12 months High

B.4. Are copies of bids or proposals retained with the evaluation?

Yes Low

B.5. Are copies of the original advertisements retained with the pre-contract papers?

Yes Low

B.6. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

No response Average

Page 145: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

139

B.7. Are copies of invoices included with the contract papers?

No response Average

C. Procurement Practices

Goods and Works

C.1. Has the agency undertaken foreign-assisted procurement of goods or works recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No

Average

C.2. If the above answer is yes, what were the major challenges?

No response

C.3. Is there a systematic process to identify procurement requirements (for a period of one year or more)

Yes Low

C.4. Is there a minimum period for preparation of bids and if yes how long?

3 days Low

C.5. Are all queries from bidders replied to in writing?

Yes

C.6. Does the bidding document state the date and time of bid opening?

Yes Low

C.7. Is the opening of bids done in public? Yes

Low C.8. Can late bids be accepted? No

C.9. Can bids be rejected at bid opening? No

C.10. Are minutes of the bid opening taken? Yes

Average C.11. Who may have a copy of the minutes? No response

C.12. Are the minutes free of charge? No

C.13. Who undertakes the evaluation of bids (individual(s), permanent committee, ad-hoc committee)?

permanent committee Low

C.14. What are the qualifications of the evaluators with respect to procurement and the goods and/or works under evaluation?

Experts Average

C.15. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

No response High

C.16. Using at least three real examples, how long does it normally take from the issuance of the invitation for bids up to contact effectiveness?

No response High

C.17. Are there processes in place for the collection and clearance of cargo through ports of entry?

Yes Low

C.18. Are there established goods receiving procedures?

No response High

C.19. Are all goods that are received recorded as assets or inventory in a register?

No response High

C.20. Is the agency/procurement department familiar with letters of credit?

Yes Low

C.21. Does the procurement department register and track warranty and latent defects liability periods?

Yes Low

Page 146: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

140

Consulting Services

C.22. Has the agency undertaken foreign- assisted procurement of consulting services recently (last 12 months, or last 36 months)? (If yes, please indicate the names of the development partner/s and the Project/s.)

No High

C.23. If the above answer is yes, what were the major challenges?

No response

C.24. Are assignments and requests for expressions of interest (EOIs) advertised?

Yes Low

C.25. Is a consultants’ selection committee formed with appropriate individuals, and what is its composition (if any)?

No response High

C.26. What criteria is used to evaluate EOIs? No response High

C.27. Historically, what is the most common method used (QCBS, QBS, etc.) to select consultants?

No response High

C.28. Do firms have to pay for the RFP

document?? Yes Low

C.29. Does the proposal evaluation criteria follow a pre-determined structure and is it detailed in the RFP?

Yes Low

C.30. Are pre-proposal visits and meetings arranged?

Yes

Low C.31. Are minutes prepared and circulated after pre-proposal meetings?

Yes

C.32. To whom are the minutes distributed? No response

C.33. Are all queries from consultants answered/addressed in writing?

Yes Low

C.34. Are the technical and financial proposals required to be in separate envelopes?

Yes Low

C.35. Are proposal securities required? Yes Low

C.36. Are technical proposals opened in public? Yes

Low C.37. Are minutes of the technical opening distributed?

Yes

C.38. Do the financial proposals remain sealed until technical evaluation is completed?

Yes

Low C.39. Who determines the final technical ranking and how?

Yes

C.40. Are the technical scores sent to all firms? Yes

C.41. Are the financial proposal opened in public?

Yes Low

C.42. Are minutes of the financial opening distributed?

Yes

C.43. How is the financial evaluation completed?

No response High

C.44. Are face to face contract negotiations held?

Yes Low

C.45. How long after financial evaluation is negotiation held with the selected firm?

No response High

Page 147: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

141

C.46. What is the usual basis for negotiation? Public and fair Average

C.47. Are minutes of negotiation taken and signed?

Yes Low

C.48. How long after negotiation is the contract signed?

3 days Low

C.49. Is there an evaluation system for measuring the outputs of consultants?

No response High

Payments

C.50. Are advance payments made No response Average

C.51. What is the standard period for payment included in contracts?

7 days

Low C.52. On average, how long is it between receiving a firm’s invoice and making payment?

7 days

C.53. When late payment is made, are the beneficiaries paid interest?

Yes

D. EFFECTIVENESS

D.1. Is contractual performance systematically monitored and reported?

Yes Low

D.2. Does the agency monitor and track its contractual payment obligations?

Yes Low

D.3. Is a complaints resolution mechanism described in national procurement documents?

Yes Low

D.4. Is there a formal non-judicial mechanism for dealing with complaints?

Yes Low

D.5. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes Low

E. Accountability measures

E.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes Low

E.2. Are those involved with procurement required to declare any potential conflict of interest and remove themselves from the procurement process?

Yes Low

E.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) that are outside of the budgeting process?

No Low

E.4. Who approves procurement transactions, and do they have procurement experience and qualifications?

General manager Low

E.5. Which of the following actions require approvals outside the procurement unit or the evaluation committee, as the case may be, and who grants the approval?

High

a) Bidding document, invitation to pre-qualify or RFP

No response

Page 148: Procurement Risk Assessment (Final)...procurement risk assessment questionnaire is presented in Appendix 1. II. Country Procurement Systems 4. Currently, public procurements in the

142

b) Advertisement of an invitation for bids, pre-qualification or call for EOIs

No response

c) Evaluation reports No response

d) Notice of award No response

e) Invitation to consultants to negotiate No response

f) Contracts No response

E.6. Is the same official responsible for: (i) authorizing procurement transactions, procurement invitations, documents, evaluations and contracts; (ii) authorizing payments; (iii) recording procurement transactions and events; and (iv) the custody of assets?

No response High

E.7. Is there a written auditable trail of procurement decisions attributable to individuals and committees?

No response High

II. General Ratings

Criterion Risk

A. Organizational and Staff Capacity Low

B. Information Management Average

C. Procurement Practices Average, but in consultant selection is high.

D. Effectiveness Low

E. Accountability Measures High

OVERALL RISK RATING High