produced by · 2019. 9. 29. · produced by: monitoring, inspection, milestone certification and...

17
PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (MIMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT – MAY 11, 2017 Transmission Scheme for Excavation and Power from 147MW Patrind Hydro Power Project

Upload: others

Post on 11-Aug-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

PRODUCED BY:

Monitoring, Inspection, Milestone Certification and Design Review(MIMDR) of USAID / Pakistan Energy Office Projects

SITE VISIT REPORT – MAY 11, 2017

Transmission Scheme for Excavation and Power from147MW Patrind Hydro Power Project

Page 2: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

Monitoring, Inspection, Milestone Certification and Design Review(MIMDR) of USAID / Pakistan Energy Office Projects

SITE VISIT REPORT

TRANSMISSION SCHEME FOR EVACUATION OFPOWER FROM 147MW PATRIND HYDRO POWERPROJECT

MAY 11, 2017

MIMDR Project OfficeAA Associates Islamabad,3rd Floor, Waheed Plaza,52 Western Half, Jinnah Avenue,Blue Area Islamabad.Tel: +92 (51) 2605000-2, Fax: +92 (51) 2605003Email:[email protected]

This publication was made possible through support of the American people provided by the U.S. Agency for InternationalDevelopment (USAID). The opinions expressed herein are those of AA Associates and do not necessarily reflect theviews of USAID or the United States Government.

Page 3: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 1

INTRODUCTION

Project Transmission Scheme for Evacuation of Power from 147MW PatrindHydropower Project (HPP)

Visit Date May 11, 2017 Reporting Date May 29, 2017

VisitingEngineer(s)

1. Muhammad Ashraf khan Transmission Expert

2. Imran Syed Ali M&E Expert / DCOP/

PersonnelVisited

1. Muhammad Farhan Sub Divisional Engineer (EHV-I)NTDCL

2. Muhammad Qaisar Surveyor MECON (Pvt.) Ltd.

3. Tanveer Hussain Substation Operator (SSO) In charge132kv Balakot Substation - PESCO.

4. Israr Ahmad Subcontractor’s Engineer

Site(s) Visited

1. 132kV Transmission Line from Patrind HPP to 220kV Mansehra

Substation

2. 132kv Balakot Substation

3. 220/132kv Mansehra Substation

Shaheryar Ayub
Rectangle
Shaheryar Ayub
Rectangle
Page 4: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 2

VISIT OBJECTIVESFollowing were the key objectives of site visit carried out by Transmission Expert of AAAssociates:

1. To monitor the progress of construction activities

2. To observe the challenges in implementation of the activities and to carry outdiscussion/coordination with NTDC to resolve them

VISIT PROCEEDINGSThe team reached Patrind Power House at 11:30 AM on May 11, 2017. 132kV Transmission Linefrom Patrind Hydropower Project to Muzaffarabad-II (Rampur) Substation constructed underNTDC own sources as Phase-I of Transmission Scheme for Evacuation of power from 147MWPatrind Hydro Power Project is complete and energized recently.

132KV TRANSMISSION LINE FROM PATRIND HPP TO 220KV MANSEHRASUBSTATIONThe work on foundations and erection of towers for 132kV Double Circuit Transmission Line fromPatrind HPP to 220kV Mansehra Substation is in progress. The progress achieved so far is:

o Foundation (Conventional) Concreted 126/163o Pile Foundation 12/23o Tower Erected 38/183

Scheduled completion date was April 30, 2017, but the project seems delayed due to followingreasons:

o Sub Divisional Engineer (EHV-I) told that NTDC had to face demand of heavycompensation by some affectees against right of way, eventually resulting in delay inproject execution.

o Batrasi is a “Reserved Forest” in Khyber Pakhtun Khuwa (KP) Province. The Contractor’ssurveyor told that passing of transmission line through Batrasi Forest cannot be avoidedbecause of thick population on alternate route. About eleven (11) towers are proposed tobe located in Batrasi Forest. Delay in settlement/negotiation with KP Forest Departmenthas hindered the project progress.

AA Associates requested Sub Divisional Engineer (EHV-I) NTDC to further search alternate routeto avoid Batrasi Forest, as obtaining permission/No Objection Certificate from Forest Departmentseems to be difficult. Furthermore, because of reserved status of the forest it would be worthwhileto avoid the passage of transmission line through forest. AA Associates will follow-up the matterwith PD office for early resolution of these issues.

Page 5: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 3

132KV BALAKOT SUBSTATION132kV Balakot Substation was visited and it was found to be in a devastated shape as noreconstruction/repair of boundary wall, control building and residential colony was carried out aftersevere earthquake of 2005. The substation was however, operational with battery, control & relaypanels and 11kV metal clad switchgear in a temporary shed without walls. It was observed thatrequired space for extension of switchyard and for location of further terminal tower was notavailable because of surrounding residences.

A new 132kV substation is proposed by NTDC/PESCO at Garhi Habibullah where two 132kV linebays for In/Out of one circuit of 132kV Transmission Line from Patrind HPP to Mansehra can beadded under USAID financing.

PESCO officials at Balakot Substation were not aware of the status of acquisition of land at GarhiHabibullah. Therefore, Executive Engineer (Substation & Transmission Line) Grid SystemOperation PESCO Abbottabad, who is responsible for maintenance of substations andtransmission lines in the area, was contacted on telephone. Even he was not aware of the finalstatus of acquisition of land and timeline for construction of the substation.

220/132 KV MANSEHRA SUBSTATIONThe team reached Mansehra Substation where subcontractor’s engineer was available whoexplained the progress of construction work. It was noted that 220/132kV, 250MVA Transformershave been placed on foundations, grey structure of control building was complete and, erection of220kV & 132kV equipment in switchyard was in progress.

There are six 132kV line bays in the scope of work, which were for interconnection of 132kVTransmission Lines to PESCO’s distribution network. Due to delay in initiating the activitiespertaining to additional two 132kV line bays by NTDC under USAID financing, and urgentrequirement of interconnection of 132kV Double Circuit Transmission Line from Patrind HPP forevacuation of power, two of the line bays being constructed under ADB financing aremarked/reserved for termination of 132kV Double Circuit Transmission Line from Patrind HPP.

However space is available for additional two 132kV line bays, (to be constructed under USAIDfinancing) for which, no activity has yet been initiated by NTDC in spite of repeated requests fromAA Associates to GM (GSC) & CE (Design).

WAY FORWARD AA Associate will contact P.D (EHV-I) NTDCL Islamabad & XEN (EHV-I) Rawalpindi for

timely diversion of the route of 132kV Patrind-Mansehra Transmission Line to avoid itscrossing of Batrasi reserved forest.

Page 6: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 4

AA Associates will contact CE (Development) PESCO to know updates on acquisition ofland and timeline for construction of new 132kV substation at Garhi Habibullah, so that two132kV line bays for In/Out of 132kV Patrind HPP-Mansehra Transmission Line can beinitiated by NTDC accordingly.

AA Associates will pursue the matter with NTDC to initiate the activities for addition of two,132kV line bays at 220kV Mansehra Substation.

Page 7: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 5

PHOTOGRAPHS

132kV T/L emanating from Patrind Power House Terminal Tower of 132kV T/L at Patrind

Discussion about 132kV T/L line route along Foundation of 132kV towerKunhar River

Foundations of towers along the river Kunhar Pile foundation of 132kV Tower

Page 8: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 6

Batrasi Forest 132kV Balakot Substation

Control & Relay Panels in temporary shed at 132kV Switchyard Balakot Substation132kV Balakot Substation

220/132kV Mansehra Substation 11kV Panels at Balakot substation

Page 9: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 7

Control Building at 220/132kV Mansehra 220/132kV Switchyard at Mansehra SubstationSubstation

Page 10: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

MIMDR | SITE VISIT REPORT | MAY 2017 | 8

MIMDR Project Office

AA Associates Islamabad,

3rd Floor, Waheed Plaza,

52 Western Half, Jinnah Avenue,

Blue Area Islamabad.

Page 11: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

Site Visit Report Activity/Award Title : Power Transmission System for Patrind Hydropower Activity AOR/COR/Program manager : Imran Ahmed PIL Signing Date : Sept 1, 2018 Activity End Date : Sept 30, 2020 Visit Date : From: Sept 26, 2018 To: Sept 27, 2018 Visit Site : 132kV Patrind-Mansehra Double Circuit Transmission Line and 220 kV Mansehra Substation Visit Conducted By : Muhammad Ashraf Khan, Sajid Ali Visit Purpose : Activity Monitoring

Site Visit Objective(s):

● Monitoring of progress ● To assess bottlenecks/cause of delay in completion of project.

Status of Progress and Way Forward: Status of Progress of Transmission Line:

- Foundation 160/167 - Pile Foundation 25/25 - Total Foundation constructed 185/192 - Tower Erection 176/192 - Stringing 32km

Status of Line Bays at Mansehra Substation: • Two 132 kV Line Bays already constructed at 220/132 kV Mansehra Substation are reserved for

interconnection of 132 kV Patrind-Mansehra circuits. Installation of line P.T and synchronizing panels is required.

• Procurement of equipment for new line bays is in progress, preliminary construction drawings issued by C.E (Design) NTDC.

Reasons of Delay: The expected completion date of the activities as per PIL is August 2018. The delay is due to following factors: • The terrain involves crossing of river and requires construction of more pile foundations (than

conventional ones) than originally planned. • Unpredictable weather necessitating manual excavation for tower foundation. • Diversion necessary to avoid reserved forest Batrasi. • Right of Way problems on tower no. 110,111,112 in Khyber Pakhtunkhwa area have been solved and

towers will be concreted within next the ten days. • Right of way problems at tower location. 17P,6,7,8 and 11 are complicated: land owners demand

exorbitantly high compensation. NTDC approached Azad Jammu Kashmir (AJK) administration but no resolution so far.

Way Forward: • MIMDR requested site engineers to share next target date completion date of these activities. NTDC

engineer responded that right of way problem of towers concreting in AJK area is complicated. NTDC higher authorities to take up the matter with AJK Government and establish revised completion date(s) accordingly.

Shaheryar Ayub
Rectangle
Shaheryar Ayub
Rectangle
Page 12: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

PHOTOGRAPHS

Fig 1. Line eminating from Patrind Hydropower House Fig 2. 132 kV Transmission Line Patrind to Mansehra

Fig 3. River Crossing of 132 kV Transmission Line Patrind-Mansehra

Fig 4. Pile Foundations of 132 kV Patrind-Mansehra Transmission Line Tower

Fig 5. Space for Additional Line Bays at Mansehra Substation

Fig 6. Terminal Tower of 132 kV Patrind-Mansehra Transmission Line

Page 13: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

Site Visit ReportActivity/Award Title : Power Transmission System for the Patrind Hydropower ActivityProject Management Specialist : Imran AhmedPIL Signing Date : Sept 01, 2018Activity End Date : Sept 30, 2020Visit Date : From: Apr 8, 2019 To: Apr 9, 2019Visit Site : 132kV Patrind-Mansehra Double Circuit Transmission Line and 220 kV Mansehra SubstationVisit Conducted By : Muhammad Rashid Razzaq, Sajid AliVisit Purpose : Activity Monitoring

Site Visit Objective(s):● Monitoring of progress.● To assess bottlenecks/cause of delay in completion of Project.

Status of Progress and Way Forward:Status of Progress of Transmission Line:

- Foundation 165/169- Pile Foundation 25/25- Tower Erection 179/194- Conductor Stringing 37.339km/40.695km- Optical fiber Ground Wire (OPGW )Stringing 37.589km/40.695km

Status of Line Bays at Mansehra Substation: Two 132 kV Line Bays have been constructed, except voltage Transformer, and reserved for

interconnection of 132 kV Patrind-Mansehra circuits. The foundations for two voltage transformersare ready for installation. The process is expected to take a maximum of one weeks after reachingvoltage transformer on site.

Procurement of equipment for new line bays is in progress: C.E (Design) NTDC has issued preliminaryconstruction drawings.

Reasons of Delay:Expected completion date of activities as per PIL was August 2018. The following factors havecontributed to the delay so far: Involvement of more pile foundations in place of conventional ones and crossing of river. The route initially proposed intersected the Batrasi forest reserve, necessitating the need for a

diversion. Tower concreting on tower no. 17P in Azad Kashmir will be carried out within the next ten days, as

Right of Way (ROW) problems have been resolved. Landowners at tower locations 6, 6A, 7 and 8 demanded exorbitantly high compensation for granting

ROW. NTDC approached Azad Jammu Kashmir (AJK) administration for an amicable resolution butmet with no success.

Way Forward: MIMDR met with NTDC site engineer to discuss estimated date(s) of completion for delayed

activities. NTDC maintains that the ongoing ROW issue is complicated and has caused a slow work.Once the issue is resolved, the work is expected to (approximately) a month to complete. NTDChigher authorities plan on following up with the AJK Government to move the issue forward.

Shaheryar Ayub
Rectangle
Shaheryar Ayub
Rectangle
Page 14: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

PHOTOGRAPHS

Fig 1. Line connected to Patrind Hydropower House Fig 2. 132 kV Transmission Line Patrind to Mansehra

Fig 3. Erection work of Tower No. 14P started at 132kV Transmission Line Patrind-Mansehra

Fig 4. Protection panels of 132kV Line bays at 220/132kV Mansehra substation

Fig 5. Foundations of P.Ts is ready at 220/132kV atMansehra Substation

Fig 6. Control panels of two lines at 220/132 kVMansehra substation.

Page 15: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

Site Visit Report Activity/Award Title : Power Transmission System for the Patrind Hydropower Activity AOR/COR/Program Manager : Imran Ahmed Activity Start Date : Sept 1, 2018 Activity End Date : Sept 30,2020 Visit Date : From: Sept 11, 2019 To: Sept 12, 2019 Visit Site : 132 kV Patrind-Mansehra Double Circuit Transmission Line and 220 kV New Mansehra Substation Visit Conducted By : Muhammad Ashraf Khan, Sajid Ali Visit Purpose : Activity Monitoring

Site Visit Objective(s):

● To see completed/pending work on line bays at 220 kV Mansehra Substation ● To monitor progress on transmission line with status of OPGW testing ● To observe the status of establishing telecom link with Patrind HPP. ● To obtain ground information regarding evacuation of power through existing arrangement.

Status of Progress: MIMDR transmission team conducted a visit to 147 MW Patrind Hydropower Project (HPP), 132 kV Patrind to Mansehra transmission line and 220 kV New Mansehra Substation. 147MW Patrind Hydropower Project is presently generating 66.6MW (depend upon availability of water flow) and is being safely evacuated through 132 kV double circuit Patrind - Rampura (Muzaffarabad-II) circuit. However, the Engineer Incharge of O&M Patrind HPP informed MIMDR that tripping is being encountered beyond the 100MW generation, despite the arrangement between IESCO and PESCO through existing the 132 kV network.

Status of Progress of 132 kV Patrind to Mansehra Transmission Line: - Foundation 167/170 - Pile Foundation 20/20 - Total Foundation constructed 187/190 - Tower Erection 187/190 - Stringing of Conductor 39.295km - Stringing of Optical Ground Wire (OPGW) 36.589Km

• Right of Way (ROW) problem at tower location no 6A, 7 and 8 located near Patrind village still persists. The landowner is still resisting, and NTDC remains in touch with AJK administration authorities, which are determined to resolve the issue.

• NTDC intends to start testing of OPGW on completion of the transmission line. • All other problems of ground clearance have been resolved.

Status of 2 No 132 kV Line Bays at 220 kV New Mansehra Substation: • Two, 132 kV line bays numbered as E9 and E10 bays reserved for interconnection with double circuit

Patrind to Mansehra line are already complete. The span from terminal tower to gantry has been strung.

• Potential transformers have been installed. Cabling is in progress. • Control and protection panel are ready for energization.

Shaheryar Ayub
Rectangle
Shaheryar Ayub
Rectangle
Page 16: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

PHOTOGRAPHS

Fig 1. 132 kV Transmission Line Emanating from Patrind Hydropower House

Fig 2. Towers of Patrind to Mansehra Transmission Line

Fig 3. 132 kV Transmission Line Patrind-Mansehra Fig 4. Location of tower 6A, 7 and 8 with ROW issues

Fig 5. Control panels fo Patrind and Rampura Transmission Line at 220 kV Mansehra Substation

Fig 6 Potential Transformers Installed at 132 kV Patrind-Mansehra Transmission Line

Page 17: PRODUCED BY · 2019. 9. 29. · PRODUCED BY: Monitoring, Inspection, Milestone Certification and Design Review (M IMDR) of USAID / Pakistan Energy Office Projects SITE VISIT REPORT

Fig 7 Two Line bays at 220 kV Mansehra Substation Fig 8 Terminal Tower of 132 kV Patrind to Masnehra

Transmission Line at 220 kV Mansehra Substation