productivity improvement

11
MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L PRODUCTIVITY IMPROVEMENT PRESENT METHOD Component Name : U- Bolt Component weight : 6Kgs Number of Castings per Mold : 2nos. Total Good Casting wt : 12Kgs Total Pouring wt : 20kgs Yield : 60%

Upload: bebe

Post on 15-Jan-2016

41 views

Category:

Documents


0 download

DESCRIPTION

PRODUCTIVITY IMPROVEMENT. PRESENT METHOD Component Name: U- Bolt Component weight: 6Kgs Number of Castings per Mold : 2nos. Total Good Casting wt : 12Kgs Total Pouring wt : 20kgs Yield : 60%. Picture shows Metal Filling at various intervals - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

PRODUCTIVITY IMPROVEMENT PRESENT METHODComponent Name : U- BoltComponent weight : 6KgsNumber of Castings per Mold : 2nos.Total Good Casting wt : 12KgsTotal Pouring wt : 20kgsYield : 60%

Page 2: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Metal Filling at various intervalsThe colour scale shows the temperature at each location

Picture shows Metal Filling at various intervalsThe colour scale shows the temperature at each location

Page 3: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Solidification at various intervalsThe colour scale shows the % of Liquid metal available

Picture shows Solidification at various intervalsThe colour scale shows the % of Liquid metal available

Page 4: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Hotspot inside the Casting & FeederHotspot specifies the isolated regions and solidification time

Picture shows Hotspot inside the Casting & FeederHotspot specifies the isolated regions and solidification time

Page 5: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows the possible porosity areasPicture shows the possible porosity areas

Page 6: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

PROPOSED METHODComponent Name : U- BoltComponent weight : 6KgsNumber of Castings per Mold increased to : 4nos from 2nos.Total Good Casting wt increased to : 24KgsTotal Pouring wt : 37.5kgsYield increased to : 64% from 60%

PRODUCTIVITY IMPROVEMENT

Page 7: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Metal Filling at various intervalsThe colour scale shows the temperature at each location

Picture shows Metal Filling at various intervalsThe colour scale shows the temperature at each location

Page 8: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Solidification at various intervalsThe colour scale shows the % of Liquid metal available

Picture shows Solidification at various intervalsThe colour scale shows the % of Liquid metal available

Page 9: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows Hotspot inside the Casting & FeederHotspot specifies the isolated regions and solidification time

Picture shows Hotspot inside the Casting & FeederHotspot specifies the isolated regions and solidification time

Page 10: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Picture shows the possible porosity areasPicture shows the possible porosity areas

Page 11: PRODUCTIVITY IMPROVEMENT

MAGNA M a g n a D i g i t e c h I n d i a P r i v a t e L i m i t e d

Result after implementation of this method

1.Number of good casting per mold increased to 4 from 22.Yield improved by 4% from present method3.Additional cost spent on 2 cores and one sleeve per mold will be taken care by productivity increase.

Result after implementation of this method

1.Number of good casting per mold increased to 4 from 22.Yield improved by 4% from present method3.Additional cost spent on 2 cores and one sleeve per mold will be taken care by productivity increase.