Project – 3 stars Hotel - 4 stories - ”Vigla”Consultancy, Supervising and Construction Management
2004-2006
![Page 2: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/2.jpg)
Owners
Vigla Touristic Company Ltd.
Consultants and Supervisor Engineers
Design and construction Management
Angelos Papavasileiou
Civil-Structural-Architectural Engineer
Angelos Papavasileiou Surveying and Geoinformatics Engineer
Georgios Iliopoulos Geologist Engineer
Euaggelos Mermigas Mechanical Engineer
Orestis Basileios Electrical Engineer
Vlachavas Dimitrios
![Page 3: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/3.jpg)
Project InformationLocation: Greece, Thessaly, Trikala, Pirra
![Page 4: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/4.jpg)
Building Information4 Stories -3 Stars Hotel
-2 Basement Level for general facilities use -1 Basement Level for spa and Gym facilities 0 Floor Level for Reception, Lobby, Restaurant, Bar, Coffee, Areas 1 Upper Floor for Rooms 2 Roof Level
417 m2 per Floor
1650 m2 all levels of Hotel Budget 2.250.000 Euros
![Page 5: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/5.jpg)
Technical Challenges
High falling gradient field
Unstable climate/weather conditions
Headwaters control
Rain water control
Rock falls in Construction site
Slow moving underground clay layers
Layers of earth fill in the area of excavation
Big rocks in the excavation area
Low Tension of ground σ=0,11MPa and Soil elastic modulus K=400 KPa/cm
Long distance of concrete construction site more than 60 Kilometres
![Page 6: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/6.jpg)
Construction Management challenges
Long distance of Supplies contractors of the construction materials .
High material transfer cost.
4 months stop in the winder period.
Health and Safety challenges
Long distance from Hospital in the accident conditions .
High falling gradient field.
Quick daily change of the weather conditions.
![Page 7: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/7.jpg)
Phase 1 - Excavation
![Page 8: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/8.jpg)
Phase 1 - Excavation
![Page 9: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/9.jpg)
Phase 2 – Setting out – Foundations
![Page 10: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/10.jpg)
Phase 2 –Foundations
![Page 11: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/11.jpg)
Phase 3 –
Roof Basement-2
![Page 12: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/12.jpg)
Phase 3 – Basement -2
![Page 13: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/13.jpg)
Phase 3 –
Roof Basement -1
![Page 14: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/14.jpg)
Phase 3 –
Roof Ground Floor
![Page 15: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/15.jpg)
Phase 3 –
Roof Floor 2 (2 parts)
![Page 16: Progect Vigla_NEW](https://reader034.vdocuments.net/reader034/viewer/2022042701/55cec41cbb61eb4d1d8b45fb/html5/thumbnails/16.jpg)
Phase 4 –
Walls -Roofs