3/20/2013 1 talos consult minimizing project and construction risk ... CONSTRUCTION PROJECT DELIVERY Program and Project Management talos consult minimizing project and construction risk ... PROJECT EXECUTION PERIODS Recognising the Principal Project Phases Inception Design Construction Defects Liability Program Management Project Management Pre-Construction Construction Post-Construction

Upload: others

Post on 06-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

1

 

talos consult 

minimizing project and construction risk ...

CONSTRUCTION PROJECT DELIVERY

Program and Project Management

 

talos consult 

minimizing project and construction risk ...

PROJECT EXECUTION PERIODS

Recognising the Principal Project Phases

Inception

Design

Construction

Defects Liability

ProgramManagement

Project Management

Pre-Construction Construction Post-Construction

Page 2: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

2

 

talos consult 

minimizing project and construction risk ...

RETURN ON INVESTMENT

Recognising the bigger pictureEm

plo

yer

Inve

stm

ent

and

Ret

urn

$m

PaybackReturn on Investment

Project Execution Facility Operation

 

talos consult 

minimizing project and construction risk ...

Control/Cost Characteristics

Employer Control Employer Cost

Deg

ree

of

Co

ntr

ol

Co

st o

f C

on

tro

l

Recognising the importance of the early stages

Inception

Design

Construction

Defects Liability

Page 3: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

3

 

talos consult 

minimizing project and construction risk ...

PROGRAM MANAGEMENT

It’s the Program Manager who provides the final focusfor Project commencement

The identification, development and inception of theVarious preliminary elements that will:

Confirm the Feasibility Study

Establish the technical parameters

Establish the commercial parameters

Establish the financial parameters

 

talos consult 

minimizing project and construction risk ...

INCEPTION PERIOD

Land Use

Program Management

Transportation

Life Cycle Costing

Design Standards

Design Management

Project Planning and Controls

Contracts & Packaging

Project Procedures

Summary Cost Plan

Procurement and FacilitationSetting plans and concepts …

Page 4: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

4

 

talos consult 

minimizing project and construction risk ...

PROJECT STRATEGY

The Means of delivering the project

Project Objectives

Project Requirements

RiskManagement

Operations &Maintenance

Legal &Insurance

Financial& Funding

ConceptDesign

SchemeDesign

DetailedDesign

Procurement Construction CommissioningPerformance Test

Handover

Project Team Organisation

EHS/QA Project Control

Creative thinking the Planning challengeWBSOBS

 

talos consult 

minimizing project and construction risk ...

CONTRACTING STRATEGY

Selecting contract packages and payment terms

ConceptDesign

SchemeDesign

DetailedDesign

Procurement Construction CommissioningPerformance Test

Handover

Combinations and choices

Reimbursable Target PerformanceIncentive

Lump Sum

SharedRisk

Page 5: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

5

 

talos consult 

minimizing project and construction risk ...

GENERIC CONTRACT STRUCTURE

CONTRACT

CONDITIONS“LEGAL”

CONTRACT ANNEXESCONTRACT ANNEXES “TECHNICAL”

CONTRACT

COORDINATION PROCEDURES“PROJECT MANAGEMENT”

FORM “THE DEAL”

Determining Contract Type

 

talos consult 

minimizing project and construction risk ...

INVITATION TO TENDER

Employer’s Requirements

Scope of Work

Planning of Work

Services & Supplies

EHS and QA

Sub-Contracts/Orders

DrawingList

ProjectProgram

List of ApprovedSub-Contractors& Suppliers

ContractorDataRequirements

Employer’sFree IssueItems

Technical Specifications and Applicable Codes and Standards

Specifying the Employer’s Requirements …

Form of Tender

Tender Price Breakdown

Schedule of Rates

Daywork Rates

Supplementary Information

Instructions to Tenderers Form of Agreement

Conditions of Contract

General Conditions

Special Conditions

Page 6: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

6

 

talos consult 

minimizing project and construction risk ...

THE PATH TO CONTRACT AWARD

Clarity in Contract execution

ITTCollection

TenderSubmission

Letter ofIntent

Post-TenderMeeting

Letter ofAcceptance

ContractExecution

Contractor 1

Contractor 2

Contractor 3

Contractor 4

Contractor 5

Contractor 2

Maintainingcompetition

 

talos consult 

minimizing project and construction risk ...

PROJECT MANAGEMENT

It’s the Employer who defines the objectives and constraints

The coordination and control of the entireeffort required to achieve a defined objective

within the final approved budget within pre-determined final timescales to the specified standard and quality

Page 7: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

7

 

talos consult 

minimizing project and construction risk ...

The Project Management Triangle

Fixing priorities and getting the balance right

Scopeof Work

QualityPerformance

Cost ScheduleRisk/Uncertainty

Assumptions Expectations

The Business Environment

 

talos consult 

minimizing project and construction risk ...

Key Themes

ExercisingPre-Emptive

Control

ManagingRisk

DeliveringValue forMoney

CommunicatingInformation

Project controlis

paramount …

Page 8: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

8

 

talos consult 

minimizing project and construction risk ...

The Design Management Triangle

Project Manager

Design Consultant Cost Consultant

Minimise Risk Maintain Schedule

Satisfy the Project Brief

Meeting the Employer’s Expectations …

ValueEngineering

 

talos consult 

minimizing project and construction risk ...

The Value Engineering Technique

Investigation

Speculation

Evaluation

Validation

Presentation

Implementation

Six fundamental phases:

Controlling the Risk of Designing the Project …

Page 9: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

9

 

talos consult 

minimizing project and construction risk ...

PROJECT LIFECYCLE

FROM ITT TO CONTRACT AWARD

Employer need to maintain control

Resisting the re-introduction of uncertainty

ITTIssue

Tender Queries& Clarification

Tender Receipt& Evaluation

Post-TenderClarification

ContractNegotiation

ContractAward

What the Employerrequires….

What the Partiesagree…...

 

talos consult 

minimizing project and construction risk ...

IMPACT OF THE TENDER PROCESS

EMPLOYER’S

REQUIREMENTS

Remaining faithful to the Business Case

Employer changes

Employer clarifications

Additional Information

Contractor Queries

Contractor Qualifications

Contractor Alternatives

Contractor Omissions

RISKS

TENDER DOCUMENTS

Page 10: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

10

 

talos consult 

minimizing project and construction risk ...

TENDER EVALUATION

QAHSE

Contractor Key PersonnelManagement Competence

Technical CompetenceMethod of Working

Programme & ResourcesSupplementary Information

Price

Optimum choice on a level playing field

ComplianceAlternatives

Qualifications

Riskand

Reward

 

talos consult 

minimizing project and construction risk ...

FROM CONTRACT AWARD TO PRACTICAL COMPLETION

MAIN CONTRACTOR WORK CYCLE

Identifying deliverables, monitoring performanceand acting on shortfalls

Project Manager control - Employer direction

DetailedEngineering

Procurement Construction Pre-Commissioning

PracticalCompletion

CALCULATIONSSPECIFICATIONS

DRAWINGS

PURCHASE ORDERSSUB CONTRACTORS

ITEMSQUANTITIES

SYSTEMS COMPLETE

Page 11: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

11

 

talos consult 

minimizing project and construction risk ...

CONTRACT CONTROL PROCEDURES

Providing the means of direction and control

Risk Reward

ApprovalsInstructionsDecisionsChangesDelays

EMPLOYER

Change Control

DeliverablesProgrammeScheduleProgress

Performance

CONTRACTOR

Project Control

 

talos consult 

minimizing project and construction risk ...

THE PROJECT CONTROL LOOP

Adjust Compare

CompleteMeasureExecuteRecovery

Plan

DetectPotentialVariation

Maintain the Plan by Controlling the Changes

AcceptNeed forChange

ChangeControl

Procedure

(See next Slide)

Page 12: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

12

 

talos consult 

minimizing project and construction risk ...

A QUALITATIVE LOOK AT PROJECT RISK

Risk Management identifies risks through the progressive use of risk impact matrices (likelihood and impact) for all major packages within a particular project.

Weekly meetings and periodic workshops are scheduled to identify business and project risks, ranging from the translation of the Business Plan into project and design briefs, to procurement strategies for the entire supply chain.  

Risk management then links with Value Engineering and Change Management to deliver optimum solutions.

 

talos consult 

minimizing project and construction risk ...

A QUALITATIVE LOOK AT PROJECT RISK

The normal activities associated with Risk Management are:

1. Establish contacts, roles, responsibilities and communication routes

2. Brainstorm & review any existing risk data. Evaluate project procedures and  Tender or Contract documents for risk exposure, including design, procurement, delivery & installation schedules

3. Develop bespoke probability‐impact matrices and transfer all risks to a comprehensive Master Risk Register

Page 13: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

13

 

talos consult 

minimizing project and construction risk ...

A QUALITATIVE LOOK AT PROJECT RISK

4. Launch the Risk Management Plan, detailing the procedural approach

5. Hold workshops with all involved personnel to review all project requirements

6. Investigate the supply chain, contracts packaging and overall procurement/strategy routes

7. Develop mitigation plans and contingency plans, as necessary

8. Maintain the entire Risk Plan, registers and matrices

 

talos consult 

minimizing project and construction risk ...

RISK ASSESSMENT

Consider any risk that could potentially affect the project objectives – (i.e. brainstorm & make a list)

Decide what the risk might affect … for example …

Time Cost  Quality Scope Supply chain Logistics  Resources Safety / Environment etc ...

Page 14: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

14

 

talos consult 

minimizing project and construction risk ...

RISK ASSESSMENT

External/Strategic/Corporate Business risk – whatever affects our ability tomeet business objectives. These high level risks are managed within thebusiness and cannot be transferred. Such risks include project funding,organizational, political, environmental, cultural, mergers & acquisitions,infrastructure failure, utility Authorities, legislation, changes inmarketplace, security, life safety, functionality and business continuity risks.

It should be possible to mitigate, to a degree, some risks despite beingoutside our control. These are generally business risks (scope) that couldjeopardize the success of the project in terms of viability.

Project/Programme/Operational risk – includes technical, contract, design,market costs, claims, operational issues, schedules/time, resources, quality,procurement; these should be managed by the party best placed to do so.These are project risks that could jeopardize the success of the project in

terms of time, cost, quality or safety.

 

talos consult 

minimizing project and construction risk ...

RISK EVALUATION - QUALITATIVE

The common approach …

Evaluate the probability or likelihood of something happening? Evaluate the impact or consequences of something happening?

A  risk is identified as L=Low,  M=Medium,  H=High, VH= Very High

…green = low     Yellow = Medium    Red = high 

Probability/Impact Low impact Medium impact High impactHardly likely Low risk Low risk Low risk

Not likely Low risk Low risk Medium risk

Maybe Low risk Medium risk Medium/High risk

Likely Low risk Medium/High risk High risk

Highly likely Medium risk High risk Very High risk

BUT  now consider impacts separately for time, cost, quality, scope

Page 15: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

15

 

talos consult 

minimizing project and construction risk ...

RISK EVALUATION – QUANTATIVE

The not so common approach … using refined ranges

• Develop the Probability‐Impact ranges i.e. for time & costs• Probability  x  Impact  = Risk Score• Highly likely (90%) x high impact (80%) = 0.72 = HIGH risk

Probability Risk Score = P x I

90% (0.9) 0.05 0.09 0.18 0.36 0.72

70% (0.7) 0.04 0.07 0.14 0.28 0.56

50% (0.5) 0.03 0.05 0.10 0.20 0.40

30% (0.3) 0.02 0.03 0.06 0.12 0.24

10% (0.1) 0.01 0.01 0.02 0.04 0.08

Impact   = 0.05 0.1 0.2 0.4 0.8

Probability %   +   Impact %   [170]                = Probability Impact Rating(Probability % + Impact %)/2  x  (1/weeks to impact) = Initial risk priority rating (severity)

 

talos consult 

minimizing project and construction risk ...

RISK EVALUATION – REAL OUTPUT

Quantitative MEANINGFUL results:

if cost impact is AED100,000, then cost contingency:

0.9 (Probability) x AED100,000 = AED90,000.

if time impact is 100 man hours, then time contingency:

0.9 (Probability) x 100 hrs = 90 hrs lost time

…Thus providing a simple contingency for cost and time risks …

Page 16: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

16

 

talos consult 

minimizing project and construction risk ...

RISK EVALUATION – MANAGEMENT

• It can be avoided (i.e. remove from scope)

• It can be accepted (possibly with contingency)

• It can be transferred (i.e. specialist subcontractor)

• It can be mitigated – as in reducing operational uncertainty through the application of ProjectProcedures

HOW CAN PROJECT RISK BE MANAGED?

 

talos consult 

minimizing project and construction risk ...

RISK EVALUATION – MANAGEMENT

• When deciding how to manage the risk, consider ...

• What will be done & what is the residual risk?

• Develop contingency options for residual risk?

• Consider secondary risks arising from the contingency options?

• Consider priority and ‘ownership’

• A reiterative process ...

Page 17: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

17

 

talos consult 

minimizing project and construction risk ...

RISK RECORDING

• Ensure  ALL project meetings include an agenda item for “Risk Issues”

• Ensure all risks, unknowns & contentious issues, (also opportunities) are recorded on the Master Risk Register

• Obtain all party buy‐in

• If possible, the Master Risk Register should be stored in a shared area on the network with ‘view only’ permission

 

talos consult 

minimizing project and construction risk ...

RISK MANAGEMENT BENEFITS

… the Risk process and the Change process:

• Employer & other parties receive an early warning;

• Project Team’s pro‐active assessment is made available;

• Project Team’s estimated costs & time impacts are made 

available;

• Project Team’s mitigation & contingency ideas are made 

available;

• Risk can be managed by the Team in a timely manner, and…

• …It satisfies basic obligations for ‘advance notice’ of ‘likely’ 

delay…

Page 18: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

18

 

talos consult 

minimizing project and construction risk ...

RISK MANAGEMENT BENEFITS

Conflict avoidance

• A non‐contentious advance warning

• Pro‐active management of risks (events) to avoid dispute

• Road map to gain early change consensus and approval

• Part of the Risk Management Process for Change

• Adopting a teamwork approach ‐ spirit of cooperation, trust and mutual respect

 

talos consult 

minimizing project and construction risk ...

THE CHANGE CONTROL LOOP

Implement

Change

Detailed

Evaluation

No

Change

EmployerReview

EmployerReview

Preliminary

Evaluation

Identify

ChangeBaseline

ExternalEmployer

Contractor

Maintain the baseline - Update the Business Case

(Start)

Refresh theBaseline

Page 19: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

19

 

talos consult 

minimizing project and construction risk ...

FROM PRACTICAL COMPLETION TO FINAL ACCOUNT

PROJECT LIFECYCLE  

(DEFECTS LIABILITY PERIOD)

Delivered on time?

Project Manager Control - Contractor Action

Commissioning PerformanceTest

WarrantyPeriod

FinalAcceptance

FinalAccount

Performance satisfactory?

Available?Reliable?Maintainable?

Deliveredto budget?

 

talos consult 

minimizing project and construction risk ...

PROJECT CLOSURE

Closing Out the Project and Identifying Residual Issues

Identification

Classification

Strategy

Control Method

Convert Uncertainty to Certainty

Identify /Quantify Change

Formalise Price/Time Adjustment

Claims

And

Disputes

PRE CONTRACT PROJECT EXECUTION POST EXECUTION

ASSESSMENT

IMPLEMENTATION

RECOVERY

RECOURSE

Page 20: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

20

 

talos consult 

minimizing project and construction risk ...

THE PROJECT BALANCE SHEET

EMPLOYER

Scope fully completed?

Completion Date met?

Quality satisfactory?

Performance satisfactory?

Liquidated damages?

Contractor Guarantees/Bonds?

Operating Revenue?

CONTRACTOR

Final Contract Price?

Final Contract Cost?

Claims for additional costs?

Claims for extension of time?

Cost of Claim recovery?

A Preliminary Look at Apparent Inequities

 

talos consult 

minimizing project and construction risk ...

CLAIM ASSESSMENT

The issues involved

The Contractor’s objectives

The basis of the arguments

The weight of supporting evidence

The legal and contractual foundation

The appropriate relief in the circumstances

Realistic assessment - Appropriate response

Page 21: Program Project Management 19-03-2013 › pdf › ICES UAE CPD - Program Project... · 2013-11-11 · Program and Project Management talos ... PROJECT LIFECYCLE FROM ITT TO CONTRACT

3/20/2013

21

 

talos consult 

minimizing project and construction risk ...

CLAIM DEFENCE

Identify the parties’ duties and obligations

Identify performance shortfalls

Establish the link between cause and effect

Separate Employer and Contractor issues

Identify counter arguments and claims

Prepare relevant supporting evidence

Present professionally in writing and pictures

Professional approach ....

 

talos consult 

minimizing project and construction risk ...

SUMMARY

Program Management: The overview function

Project Management: Project(s) control & delivery

The right people doing the right things!

Thank you ... any questions please ...