progress control - mansosp.mans.edu.eg/elbeltagi/cb517p ch7.pdf · 2016-09-29 · 4 29/09/2016 emad...
Embed Size (px)
TRANSCRIPT
1
Progress ControlProgress Control
29/09/2016 Emad Elbeltagi 2
Progress ControlProgress Control
SITE DOCUMENTS
Managing Changes? Updating? Corrective
Actions?
Work Status? Comparing Planned
versus Actual?
Time Extension? Extra Cost? Saving All As-Built
Details? Lessons Learned?
Delay Responsibility? Productivity Assessment?
2
Emad Elbeltagi 3
Progress ControlProgress Control
??
?
Reactionary Mgt Pro-Active Mgt
- JOB DIARY- WEEKLY REPORT- PROGRESS CHART- PROGRESS PLAN- RECORD PLANS- MEASUREMENT
BOOKS OR SHEETS- TEST RECORDS
29/09/2016
29/09/2016 Emad Elbeltagi 4
Objective of Project ControlObjective of Project Control
Progress ControlProgress Control
Accurately follow the project plan
Update the project plan based on the new circumstances
Monitor actual site progress and keep track of resources
Comparing actual versus planed progress
Forest the cost and timing to completion
Take corrective actions to bring time and cost close to plan
Accurately follow the project plan
Update the project plan based on the new circumstances
Monitor actual site progress and keep track of resources
Comparing actual versus planed progress
Forest the cost and timing to completion
Take corrective actions to bring time and cost close to plan
3
29/09/2016 Emad Elbeltagi 5
Progress ControlProgress ControlProblems During Construction
Construction is dusty, dirty, and Complex operation
Despite the good planning, many activities consume more time than planned
Frequent changes are introduced to the scope of work
Some trades proceed slower than required, thus
produce delays
Dealing with suppliers and subcontractors is not easy
Problems During Construction
Construction is dusty, dirty, and Complex operation
Despite the good planning, many activities consume more time than planned
Frequent changes are introduced to the scope of work
Some trades proceed slower than required, thus
produce delays
Dealing with suppliers and subcontractors is not easy
29/09/2016 Emad Elbeltagi 6
Progress ControlProgress Control
All the previously mentioned factors result in Schedule delays and cost overruns
Thus , progress control is
needed
All the previously mentioned factors result in Schedule delays and cost overruns
Thus , progress control is
needed
4
29/09/2016 Emad Elbeltagi 7
Gathering data to help in project controlGathering data to help in project control
Progress ControlProgress Control
Bi-weekly or monthly meeting should take place
Report on work done till to-date
Problems causing delays
Define responsibilities
Work of next time period
Actions needed to correct delays and cost overruns
Good documentations help in settling claims
Bi-weekly or monthly meeting should take place
Report on work done till to-date
Problems causing delays
Define responsibilities
Work of next time period
Actions needed to correct delays and cost overruns
Good documentations help in settling claims
29/09/2016 Emad Elbeltagi 8
Progress ControlProgress ControlMeasuring Work ProgressMeasuring Work Progress
Units completed
Incremental Milestone
Start/Finish
Supervisor Opinion
Cost Ratio
Weighted of Equivalent Units
Units completed
Incremental Milestone
Start/Finish
Supervisor Opinion
Cost Ratio
Weighted of Equivalent Units
5
29/09/2016 Emad Elbeltagi 9
Progress ControlProgress ControlMeasuring Work Progress: Measuring Work Progress:
Units completed: For activities with easily measured
units of work (e.g., pile driving)
% Complete = Units Completed / Total Units
Incremental Milestone: Activities with a set of
milestones each is assigned a percentage (e.g.,
Equipment installation)
Inspection 15% Alignment 50%
Installment 80% Testing 100%
Units completed: For activities with easily measured
units of work (e.g., pile driving)
% Complete = Units Completed / Total Units
Incremental Milestone: Activities with a set of
milestones each is assigned a percentage (e.g.,
Equipment installation)
Inspection 15% Alignment 50%
Installment 80% Testing 100%
29/09/2016 Emad Elbeltagi 10
Progress ControlProgress ControlMeasuring Work Progress: Measuring Work Progress: Start-Finish: For short activities, work progress measured
as 0% or 100% when completed. Medium-duration activities,
work measured as 50% or 100% when completed. Other
percentages could be set based on an activity duration.
Cost Ratio: Activities budgeted based on cost and involve
long time (e.g., Project management, quality assurance)
% Complete = Actual Cost (or hrs) of Work to Date/Forecast at
Completion
Start-Finish: For short activities, work progress measured
as 0% or 100% when completed. Medium-duration activities,
work measured as 50% or 100% when completed. Other
percentages could be set based on an activity duration.
Cost Ratio: Activities budgeted based on cost and involve
long time (e.g., Project management, quality assurance)
% Complete = Actual Cost (or hrs) of Work to Date/Forecast at
Completion
6
29/09/2016 Emad Elbeltagi 11
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
The original plan is considered as the baseline
schedule
Baseline will be used to compare actual progress
Frequent updating is necessary to make the
schedule realistic
The original plan is considered as the baseline
schedule
Baseline will be used to compare actual progress
Frequent updating is necessary to make the
schedule realistic
29/09/2016 Emad Elbeltagi 12
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
Reasons for schedule update
Change in actual activity duration or network logic
Procurement delays
Sudden changes of labor availability
Accidents
Strikes
Change in design
Reasons for schedule update
Change in actual activity duration or network logic
Procurement delays
Sudden changes of labor availability
Accidents
Strikes
Change in design
7
29/09/2016 Emad Elbeltagi 13
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
Data date (Updating date)
The date in which data are collected form site
Based on this date, activities will be classifies as:
Completed activities
In-progress Activities
Future activities
Data date (Updating date)
The date in which data are collected form site
Based on this date, activities will be classifies as:
Completed activities
In-progress Activities
Future activities
29/09/2016 Emad Elbeltagi 14
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
Updating date
0 1 2 3 4 5 6 7 8 9 10 11 12
Completed activities
In-progress activities
Future activities
AB
CD
EF
GHI
8
29/09/2016 Emad Elbeltagi 15
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
Completed activities
Duration = Remaining Duration = 0
Percent complete = 100 %
Set an actual start date
Set an actual finish date
Completed activities
Duration = Remaining Duration = 0
Percent complete = 100 %
Set an actual start date
Set an actual finish date
29/09/2016 Emad Elbeltagi 16
Progress ControlProgress ControlSchedule UpdatingSchedule Updating
In-progress activities
Duration = Remaining duration
Percent complete = Completed duration/actual duration
Set an actual start date
In-progress activities
Duration = Remaining duration
Percent complete = Completed duration/actual duration
Set an actual start dateFuture activities
Duration = Remaining duration
Percent complete = 0%
Future activities
Duration = Remaining duration
Percent complete = 0%
9
29/09/2016 Emad Elbeltagi 17
Progress ControlProgress ControlSchedule Updating: ExampleSchedule Updating: Example
Activity Duration (Weeks) Predecessors Resource (units/week)
ABCDEFGHIJKLMN
02532666427322
-111223445, 66, 72, 82, 8, 910, 11, 12, 13
00221231042240
Same as example 6.1 page 89Same as example 6.1 page 89
29/09/2016 Emad Elbeltagi 18
Progress ControlProgress ControlSchedule Updating: ExampleSchedule Updating: Example
Updating report at end of week 5 Activities B, C, D, and E have been completed Activity F is ready to start at beginning of week 6 Activity G will not start until end of week 7 Remaining duration of activity H is 4 weeks Remaining duration of activity I is 3 weeks Activity J has been omitted It is decided to shorten activity K by 2 weeks Volume of work in activity L has been increased by
33% approximately
Updating report at end of week 5 Activities B, C, D, and E have been completed Activity F is ready to start at beginning of week 6 Activity G will not start until end of week 7 Remaining duration of activity H is 4 weeks Remaining duration of activity I is 3 weeks Activity J has been omitted It is decided to shorten activity K by 2 weeks Volume of work in activity L has been increased by
33% approximately
10
29/09/2016 Emad Elbeltagi 19
Progress ControlProgress ControlSchedule Updating: ExampleSchedule Updating: Example
A (0)0 0
0 0
F (6)5 11
2 8B (2)
3 5
0 2
D (3)6 9
0 3
I (4)12 16
3 7
G (6)5 11
5 11
H (6)9 15
3 9
M (2)16 18
9 11
J (2)16 18
8 10
L (3)15 18
9 12
K (7)11 18
11 18N (2)
18 20
18 20C (5)
0 5
0 5
E (2)14 16
2 4
29/09/2016 Emad Elbeltagi 20
Progress ControlProgress ControlSchedule Updating: ExampleSchedule Updating: Example
A G (6)7
F (6)5
H (4)5
B
D
K (5)
I (3)5
N (2)C
E
M (2)
L (4)
11
13
9
8
13 18
9 13
9 11
18 20
2018
18
18
1813
14
16
13
13
14
1613
10
7
7
11
Earned Value ManagementEarned Value Management
29/09/2016 Emad Elbeltagi 22
Progress ControlProgress ControlEarned Value management: Why? Earned Value management: Why?
Course corrections are easier when you have time to make
small adjustments
Its too late when youre this close to the iceberg!
12
29/09/2016 Emad Elbeltagi 23
Progress ControlProgress ControlEarned Value management: Why? Earned Value management: Why?
Early and accurate identification of trends and
problems
Accurate picture of contract status: cost and schedule
Basis for course correction
Supports mutual goals of contractor and customer
bring project in on schedule and cost
Early and accurate identification of trends and
problems
Accurate picture of contract status: cost and schedule
Basis for course correction
Supports mutual goals of contractor and customer
bring project in on schedule and cost
29/09/2016 Emad Elbeltagi 24
Progress ControlProgress ControlEarned Value management: Why? Earned Value management: Why?
Earned Value establishes a baseline to measure
progress
Earned Value is key concept:
how much progress did I make against my
original plan?
expressed in dollars or hours
Earned Value establishes a baseline to measure
progress
Earned Value is key concept:
how much progress did I make against my
original plan?
expressed in dollars or hours
13
29/09/2016 Emad Elbeltagi 25
Earned value: basic elementsEarned value: basic elementsInformationTermApr.
What is the estimated value of the work planned to be done
Planned value PV(BCWS)
What is the estimated value of the work actually accomplished
Earned value EV(BCWP)
What is the actual cost incurred Actual cost AV(ACWP)
How much did we budget for the total job Budget at completion
BAC
What do we currently expect the total project to accomplish
Estimate at completion
EAC
From this point on, how much more do we expect to be at end of the project
Estimate to completion
ETC
How much over or under budget do we expect to be at end of the project
Variance at completion
VAC
29/09/2016 Emad Elbeltagi 26
Progress ControlProgress ControlEarned Value managementEarned Value management
Budgeted Cost of Work Scheduled (BCWS): measures What is
Planned in terms of budget cost of the work that should take place
(i.e., according to the baseline schedule of the work)
Budgeted Cost of Work Performed (BCWP) (Earned Value):
measures What is Done in terms of budget cost of the work that
has actually been accomplished to date
Actual Cost of Work Performed (ACWP): measures What is
Paid in terms of actual cost of the work that has actually been
accomplished to date
Budgeted Cost of Work Scheduled (BCWS): measures What is
Planned in terms of budget cost of the work that should take place
(i.e., according to the baseline schedule of the work)
Budgeted Cost of Work Performed (BCWP) (Earned Value):
measures What is Done in terms of budget cost of the work that
has actually been accomplished to date
Actual Cost of Work Performed (ACWP): measures What is
Paid in terms of actual cost of the work that has actually been
accomplished to date
14
29/09/2016 Emad Elbeltagi 27
Term FormulaCV
Cost variance EV AV
SVSchedule variance
EV PV
CPI Cost performance
index
EV/AV
SPI Schedule performance
index
EV/PV
EACEstimate at completion
BAC/CPI
ETCEstimate to completion
EAC - AV
VACVariance at completion
BAC EAC
Earned value: basic elementsEarned value: basic elements
29/09/2016 Emad Elbeltagi 28
Progress ControlProgress ControlEarned Value managementEarned Value management
Time
Money
Schedule VarianceACWP
BCWS
BCWP (EV) Cost Varianc
e
SV > 0 ahead of schedule, and SV < 0 behind schedule
CV > 0 cost saving, and CV < 0 cost overruns
15
Congratulation, You have got a new contract
hmm... 4 substations4 months to do it all....
K$ 400 budget....This is going to be tough!
Its my pleasure to award you this contract
for erection of (4 Pcs) substations
What is the total job supposed to cost?
What is the value of the contract at cost?
Earned Value: ExampleEarned Value: Example
Budgeted Cost of Work Schedule (PV)
Month # 1PV = $100,000
Month # 2PV = $100,000
Month # 3PV = $100,000
Month # 4PV = $100,000
Total Budget = 400 K$
Total PV = 400 K$
Schedule time = 4 months
PV is aggregated and summed as the performance measurement baseline
Earned Value: ExampleEarned Value: Example
16
month 1PV = $100,000 month 2PV = $100,000
month 3PV = $100,000
month 4PV = $100,000
Total Budget = $400,000to be spent over 4 months
I plan to complete 1substation pear month with
estimated cost of $100,000.PV each month = $100,000
each dollar of PV represents a specific dollar of month scope
Budgeted Cost of Work Schedule (PV)
Earned Value: ExampleEarned Value: Example
month 1PV = $100,000
month 3PV = $100,000
Were at the end of theThird month , but only
2.5 substations is completed. Value of work performed = 280 K$
EARNED VALUEconcept
You earn value the same wayas it was budgeted in baseline
Budgeted Cost of Work Performed (EV)
Earned Value: ExampleEarned Value: Example
17
Status at the end of month 3
Month 4Month 3Month 2Month 1Task
Complete , Spent 100 K$S. FSubst.# 1
Complete , Spent 120 K$FS. PFSubst.# 2
Half done , Spent 60 K$PS..S..PFSubst.# 3
Not yet started PS PF Subst.# 4
Earned Value: ExampleEarned Value: Example
Answer Calculation K$ Apr.
300000 $ 100 +100 +100PV
250000 $ Complete + Complete +Half done 100 +100 +50
EV
280000 $ 100 + 120 + 60 AV
400000 $100 + 100 + 100 +100BAC
- 30000 $ 250 280 CV
0.893250 /280 CPI
- 50000 $250 - 300SV
0.833250 /300SPI
447900 $400/0.893EAC
167900 $447.9 -280 ETC
-47900 $400 447.9 VAC
Earned Value: ExampleEarned Value: Example
18
Cost variance at the end of the third month is
- 30000 K$ , And by this way we will be over budget by 47900 K$ to complete
the project
actual expenditures vs. budget
Actual Cost of Work Performed (AV)
Earned Value: ExampleEarned Value: Example
Estimate at Completion (EAC)
Just a few little glitches. We should be able to do the complete job.acklets see, for about 30000
$K
Earned Value: ExampleEarned Value: Example