Progress Report 2013
Baltic Retreat 2013 NCU Estonia 6th September 2013
Taisi ValdloThe NCU of Estonia
Overview • Total allocation for Estonia is CHF 39 920 000, total net amount available is
CHF 37 920 000
• 18 project agreements have been signed covering the total CHF 37 920 000 (100% of the total allocation).
• Reimbursements together with advance payments have been received in the amount of ~ CHF 17 173 939,31 (45%)
• Due to the end of commitment period on 14th June 2012, an amendment No II of Annex 1 to the Framework Agreement was signed on 7th June 2012. The amendment concerned reallocations in the section of Thematic Focus and Indicative Financial Allocations and no new eligible projects were included.
Completed projectsProject Grant (CHF) Implementation period
Project Preparation Facility 107 377,86 23.02.2009-31.07.2011 Project completion report approved on 30.01.2012
Judges conference in Tartu 91 625,76
02.06.2010-31.12.2010
Project completion report approved on 26.04.2011
Automated gait orthosis treatment
344 341,4508.11.2010-31.08.2011
Project completion report approved on 13.12.2011
License plate recognition system on public roads
460 000
25.04.2011 – 31.03.2013
Project completion report submitted to Switzerland on
01.07.2013
Improvement of court hearings 550 000
10.02.2012-31.07.2013 Project completion report is being
prepared
Project Grant (CHF) Implementation period
Procurement of forensic science equipment
3 500 000 28.05.2009 – 31.12.2014 Utilising reserves
Financial reporting and auditing standards
1 800 00023.01.2009 – 31.01.2014
Procurement issues. Prolongation is being drafted
Building children’s homes for children without parental care
5 640 000 08.11.2010-31.08.2011Utilising reserves
Ambulances and the integrated national communication system of alarm services
1 280 00025.02.2010 – 30.06.2014
Procurement issues and software development
Information and communication technology systems of Emergency Respond Centre
2 013 99425.02.2010 – 31.12.2014
Procurement issues and software development. Utilising reserves.
Increasing fire safety in nursing homes and hospitals 1 390 431
30.11.2010– 31.12.2013Procurement issues. Prolongation
is being drafted
Semi-compulsory treatment for
drug-addicted offenders950 000
03.08.2011-31.12.2014Issues with getting patients to
treatment
Project Grant (CHF) Implementation period
AFM microscopy 250 000 24.11.2011-31.12.2013
Energy efficiency in public buildings and development of new building standards
6 500 00025.05.2012 – 30.11.2015Issues with procurements.
Won’t affect deadline.
Enhancing public environmental
monitoring capacities
8 500 00024.11.2011-31.07.2015
NGO Fund2 500 000
24.11.2011-31.07.2015
Scholarship Fund1 973 337
15.05.2009-31.12.2016
Technical Assistance 85 000 15.05.2009-13.06.2017
Publicity
• The webpage introducing the Estonian-Swiss cooperation programme can be found by visiting www.fin.ee/shveits (or www.swiss-contribution.ee which leads to the previously mentioned page in English and in Estonian). The webpage contains main information on the projects, agreements and other relevant information concerning implementation of the Estonian-Swiss cooperation programme.
• Administrative bodies communicate important information through special mailing lists which enable quick communication of information concerning general issues of the cooperation programme
• In order to reach the right target group the promotion concerning the projects is also done through specific channels like professional unions, information lists etc.
Opening ceremony of Viljandi and Saarepeedi Children’s Homes – March 9, 2012
2 family houses have been constructed and furnished in Viljandi. The children (15 per house) have moved into the houses. 2 family houses have been constructed and furnished in Saarepeedi . The children (16) have moved into the houses.
The opening ceremony of both Saarepeedi and Viljandi family houses took place on March 9th 2012. Minister of Social Affairs of Estonia Mr Hanno Pevkur handing
over the ceremonial key on the opening ceremony of the Saarepeedi Children’s Homes on 9th March 2012
Opening Ceremony of the Juuru Children’s Homes – October 30, 2012
Väätsa
5 family houses have been constructed and furnished in Juuru. 19 children have moved into the houses. Some children are still to be relocated..
Opening Ceremony of Elva Children’s Homes – December 21st 2012
Minister of Social Affairs of Estonia Mr Taavi Rõivas opens the ceremony on 21st December 2012. 2 family houses have been constructed and furnished in Elva. The children (16 per house) have moved into the houses and have settled in.
Monitoring
• Intermediate Body– Eligibility check (incl. copies of the invoices)– Monitoring of results– Spot checks
• Paying Authority– Check of Reimbursement Request and Financial Progress section in Interim Report (list of
expenditures)– Spot checks
• NCU– Check of Interim Reports (comparing physical progress and financial progress, list of
expenditures, compliance with the agreement)– Steering committee meetings– Spot checks – Monitoring of Annual Reports (cooperating with the State Budget
Department)
Steering commitee meetings
• Project steering commitee meetings take place in the environmental monitoring programme, fire safety project, energy efficiency project, treatment of drug offenders project, and a joint steering committe for Emergency Respond Centre’s and ambulances project.
• The meetings take place quarterly or each half year.
• This year (2013) there has been eight steering committe meetings.
• NCU representative and when possible a SCO representative will attend the meetings as observers.
Site Visits
• Nationally the responsibility for conducting site visits is on the Intermediate Bodies.
• They plan the visits and inform the NCU of the date, giving the NCU and/or SCO an opportunity to participate.
Ministy of Environment’s site visit photos – sub-project 5 – July 23 2013
The plane carrying the airborne spectrometer in Tallinn airport. Whenever there is wheather , the plane will fly.
Photos of the installed videoconferencing equipment
Working plan for 2013
2013 and beyond
• Implementation of all the projects has started in 2012. Our goal is to conclude all projects of the Cooperation Programme by the end of 2015.
• Prolongations– Finalising the prolongation of the Fire Safety project and the Financial
Reporting project is underway.
– Treatment for drug offenders project will definately be prolonged in 2014.
• Completions– AFM-MFM microscopy project is on schedule to complete their activities
on 31st December 2013.
– Scheduled to be completed by 31st December 2014 - Increasing fire safety project, ambulances and the integrated national communication system of alarm services project, information and communication systems of Emergency Respond Centre project and the procurement of forensic science equipment project
Thank you for your attention!