progressive collapse analysis of cross laminated … · progressive collapse analysis of cross...

1
PROGRESSIVE COLLAPSE ANALYSIS OF CROSS LAMINATED TIMBER STRUCTURES Emily SR Pepper a and Dr Christian Málaga-Chuquitaype a a Emerging Structural Technologies Research Group, Department of Civil Engineering, Imperial College London. INTRODUCTION A study on the response of a 12 storey cross laminated timber (CLT) structure designed by TRADA [1] was conducted. This consisted of a series of nonlinear dynamic analyses on the sub-assemblage models shown in Figure 1. The connection idealizations follow those specified by Gavric et al. [2] MAIN FLOOR EXTERIOR WALL REMOVAL Parametric studies were conducted on the wall and slab thicknesses. It was found that the wall thicknesses did not contribute to reducing the vertical displacement. When the support load removal time interval was 1.0s, increasing the slab thickness from 125mm to 320mm was found to reduce the vertical displacement to 320mm from 3.37m. This was not sufficient when the support load removal time interval was increased to 0.01s, or when considering non-rigid connections. Therefore, perimeter walls were added (with thicknesses of 125mm) to the original design to study the effectiveness of deep beam action in CLT structures. FIGURE 1 – LOCAL MODELS DEEP BEAM ACTION – SENSITIVITY AND EFFECTIVENESS The contribution of deep beam actions from the perimeter wall were studied. This was done by including perimeter walls with a thickness of 125mm (Figure 3). Two scenarios were studied, one where the main floor interior wall was assumed to fail (top left), and the other where a main floor edge wall was assumed to fail (top left). The floor loading seen in the figures was determined by means of static analyses. Global models (right) were also employed to verify the dynamic response of the building. MAIN FLOOR INTERIOR WALL REMOVAL Parametric studies were conducted on the wall and slab thicknesses for both models, used to simulate the effects of increasing the respective structural element stiffness (Figure 2). Support load removal time intervals between 1.0s and 0.01s were employed. ACKNOWLEDGEMENTS The authors would like to acknowledge the support from the IStructE through a MSc Research Grant. REFERENCES [1] TRADA Technology. (2009) Worked example: 12-storey building of cross-laminated timber (Eurocode 5). TTJ - the Timber Industry Magazine. [2]Gavric, I., Fragiacomo, M. & Ceccotti, A. (2015) Cyclic behaviour of typical metal connectors for cross-laminated (CLT) structures. Materials and Structures. 48 (6), 1841-1857. doi: 10.1617/s11527-014-0278-7. FIGURE 2 – INTERIOR WALL REMOVAL PARAMETRIC STUDIES The top figure shows the results of the parametric study with relation to increasing the wall thickness. Increasing the exterior wall thickness was found to reduce the vertical displacement by 57% for a respective increase in the thickness of 108%. Increasing the interior wall thickness did not contribute substantially to reducing the vertical deflection. It was found that increasing the perimeter wall thickness was necessary to engage the slab in catenary action. Without the increased wall stiffness, lateral deflections in the perimeter wall would be as much as 1m in magnitude. The bottom figure shows the study conducted with relation to increasing the slab thickness. This was conducted with an increased perimeter wall thickness of 260mm. It was found that with an increase of 84% of the slab thickness, the vertical deflection can be reduced by 73%. 1.80 1.37 1.24 1.02 1.36 1.20 1.02 0.80 1.00 1.20 1.40 1.60 1.80 2.00 100 150 200 250 300 Vertical Downward Displacement (m) Wall Thickness (mm) External Wall Thickness Only, Internal Wall t = 140 mm 1.02 0.79 0.51 0.39 0.27 0.00 0.20 0.40 0.60 0.80 1.00 1.20 100 150 200 250 Vertical Downward Displacement (m) Slab Thickness (mm) FIGURE 3 – DEEP BEAM ACTION SENSITIVITY STUDY 0.04 0.10 0.20 0.30 0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0% 20% 40% 60% 80% 100% Vertical Downward Displacement (m) Percentage of Base Perimeter Wall Present A sensitivity study on the percentage of the main floor perimeter walls present (with the removal taking place from the bottom upward) was conducted. This was completed with rotationally and translationally rigid connections. The support load removal time interval was 0.01s. As it can be seen in Figure 3, the response of the structure is highly sensitive to a reduction in the presence of the perimeter wall due to deep beam action. Slab and wall thicknesses did not need to be modified to reduce the deflection of the structure, given the smaller magnitude of the vertical displacements observed. Perimeter Wall Scenario Maximum vertical displacement (m) Upper Perimeter Wall -0.17 Lower Perimeter Wall -0.10 Upper and Lower Perimeter Wall -0.05 TABLE 1 – EDGE DISPLACEMENT VERSUS PERIMETER WALL SCENARIO In order to study the possibility of allowances for openings in the perimeter walls, a comparison of the influence of the presence of the upper storey and the lower storey perimeter walls in isolation were reviewed, as well as the influence of both. In these scenarios 100% of the perimeter walls were present and a stiffness multiplication factor of 14 was applied to the original connections (as per convergence necessity when 100% of the main floor perimeter wall alone was present). Given that convergence was reached when the upper storey perimeter walls were considered in isolation, it is possible to allow for openings in the main floor perimeter walls provided that sufficient upper storey capacity is provided. TABLE 2 – NET CONNECTION FORCE AND BENDING MOMENTS IN CONNECTIONS Original Connection Configuration Connection Max. Net Force (N) Force at Failure (N) Interior Angle Bracket 17135.3 11070.0 Edge Angle Bracket 16495.2 0.0 Perimeter A. Bracket 20499.2 0.0 Continuous Slab Configuration Interior Angle Bracket 13839.7 3720.1 Edge Angle Bracket 16535.4 0.0 Perimeter A. Bracket 19527 0.0 Rigid Connection Configuration Slab-to-slab 5123.7 N/A Interior Angle Bracket 15488.8 N/A Edge Angle Bracket 33031.1 N/A Perimeter A. Bracket 486014.0 N/A Original Connection Configuration Connection Max. Moment (Nm) Moment at Fail. (Nm) Interior Angle Bracket 50327.1 50327.1 Edge Angle Bracket 4533.8 0.0 Perimeter A. Bracket 75.1 0.0 Continuous Slab Configuration Interior Angle Bracket 26076.5 26076.5 Edge Angle Bracket 1517.8 0.0 Perimeter A. Bracket 325.94 0.0 Rigid Connection Configuration Slab-to-slab 2847.7 N/A Interior Angle Bracket 2914.5 N/A Edge Angle Bracket 5302.3 N/A Perimeter A. Bracket 236.2 N/A In order to determine where the connection stiffness was at a maximum, the maximum net forces and bending moments were observed when 100% of the main floor perimeter wall was present. As it can be seen in Table 2, the maximum forces were observed in the edge angle bracket and the maximum bending moments were observed in the interior angle bracket. Therefore, development and further research into detailed rotational stiffness and connection strength of CLT angle brackets should be conducted. It may be noted that the distribution of forces and moments along the slab edge above the removed wall were distributed like that observed in a simply supported beam. The distribution of forces and moments along the perimeter wall edge was similar to that of a cantilever beam, a) b)

Upload: others

Post on 07-Jul-2020

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROGRESSIVE COLLAPSE ANALYSIS OF CROSS LAMINATED … · progressive collapse analysis of cross laminated timber structures Emily SR Pepper a and Dr Christian Málaga-Chuquitaype a

PROGRESSIVE COLLAPSE ANALYSIS OF CROSS LAMINATED TIMBER STRUCTURES

Emily SR Peppera and Dr Christian Málaga-Chuquitaypea

a Emerging Structural Technologies Research Group, Department of Civil Engineering, Imperial College London.

INTRODUCTIONA study on the response of a 12 storey cross laminated timber (CLT) structuredesigned by TRADA [1] was conducted. This consisted of a series of nonlineardynamic analyses on the sub-assemblage models shown in Figure 1. Theconnection idealizations follow those specified by Gavric et al. [2]

MAIN FLOOR EXTERIOR WALL REMOVALParametric studies were conducted on the wall and slab thicknesses. It was found thatthe wall thicknesses did not contribute to reducing the vertical displacement. When thesupport load removal time interval was 1.0s, increasing the slab thickness from125mm to 320mm was found to reduce the vertical displacement to 320mm from3.37m.

This was not sufficient when the support load removal time interval was increased to0.01s, or when considering non-rigid connections. Therefore, perimeter walls wereadded (with thicknesses of 125mm) to the original design to study the effectiveness ofdeep beam action in CLT structures.

FIGURE 1 – LOCAL MODELS

DEEP BEAM ACTION – SENSITIVITY AND EFFECTIVENESSThe contribution of deep beam actions from the perimeter wall were studied. This wasdone by including perimeter walls with a thickness of 125mm (Figure 3).

Two scenarios were studied, one where the main floor interior wall was assumed to fail (topleft), and the other where a main floor edge wall was assumed to fail (top left). The floorloading seen in the figures was determined by means of static analyses. Global models (right)were also employed to verify the dynamic response of the building.

TABLE 1

MAIN FLOOR INTERIOR WALL REMOVALParametric studies were conducted on the wall and slab thicknesses for bothmodels, used to simulate the effects of increasing the respective structural elementstiffness (Figure 2). Support load removal time intervals between 1.0s and 0.01swere employed.

ACKNOWLEDGEMENTSThe authors would like to acknowledge the support from the IStructE through a MScResearch Grant.

REFERENCES[1] TRADA Technology. (2009) Worked example: 12-storey building of cross-laminated timber (Eurocode 5). TTJ -the Timber Industry Magazine.

[2]Gavric, I., Fragiacomo, M. & Ceccotti, A. (2015) Cyclic behaviour of typical metal connectors for cross-laminated(CLT) structures. Materials and Structures. 48 (6), 1841-1857. doi: 10.1617/s11527-014-0278-7.

FIGURE 2 – INTERIOR WALL REMOVAL PARAMETRIC STUDIES

The top figure shows the results of theparametric study with relation toincreasing the wall thickness. Increasingthe exterior wall thickness was found toreduce the vertical displacement by 57%for a respective increase in the thicknessof 108%. Increasing the interior wallthickness did not contribute substantiallyto reducing the vertical deflection. It wasfound that increasing the perimeter wallthickness was necessary to engage theslab in catenary action. Without theincreased wall stiffness, lateraldeflections in the perimeter wall wouldbe as much as 1m in magnitude.

The bottom figure shows the studyconducted with relation to increasing theslab thickness. This was conducted withan increased perimeter wall thickness of260mm. It was found that with anincrease of 84% of the slab thickness,the vertical deflection can be reduced by73%.

1.80

1.37

1.24

1.02

1.36

1.20

1.020.80

1.00

1.20

1.40

1.60

1.80

2.00

100 150 200 250 300

Verti

cal D

ownw

ard

Dis

plac

emen

t (m

)

Wall Thickness (mm)

External Wall Thickness Only, Internal Wall t = 140 mm

1.02

0.79

0.510.39

0.27

0.00

0.20

0.40

0.60

0.80

1.00

1.20

100 150 200 250

Verti

cal D

ownw

ard

Dis

plac

emen

t (m

)

Slab Thickness (mm)

FIGURE 3 – DEEP BEAM ACTION SENSITIVITY STUDY

0.04

0.10

0.20

0.30

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0% 20% 40% 60% 80% 100%

Verti

cal D

ownw

ard

Dis

plac

emen

t (m

)

Percentage of Base Perimeter Wall Present

A sensitivity study on the percentage of themain floor perimeter walls present (with theremoval taking place from the bottomupward) was conducted. This was completedwith rotationally and translationally rigidconnections. The support load removal timeinterval was 0.01s.

As it can be seen in Figure 3, the responseof the structure is highly sensitive to areduction in the presence of the perimeterwall due to deep beam action.

Slab and wall thicknesses did not need to bemodified to reduce the deflection of thestructure, given the smaller magnitude of thevertical displacements observed.

Perimeter Wall Scenario Maximum vertical displacement (m)Upper Perimeter Wall -0.17Lower Perimeter Wall -0.10

Upper and Lower Perimeter Wall -0.05

TABLE 1 – EDGE DISPLACEMENT VERSUS PERIMETER WALL SCENARIO

In order to study the possibility of allowances for openings in the perimeter walls, a comparison of theinfluence of the presence of the upper storey and the lower storey perimeter walls in isolation werereviewed, as well as the influence of both. In these scenarios 100% of the perimeter walls werepresent and a stiffness multiplication factor of 14 was applied to the original connections (as perconvergence necessity when 100% of the main floor perimeter wall alone was present).

Given that convergence was reached when the upper storey perimeter walls were considered inisolation, it is possible to allow for openings in the main floor perimeter walls provided that sufficientupper storey capacity is provided.

TABLE 2 – NET CONNECTION FORCE AND BENDING MOMENTS IN CONNECTIONS

Original Connection ConfigurationConnection Max. Net Force (N) Force at Failure (N)

Interior Angle Bracket 17135.3 11070.0Edge Angle Bracket 16495.2 0.0Perimeter A. Bracket 20499.2 0.0

Continuous Slab ConfigurationInterior Angle Bracket 13839.7 3720.1Edge Angle Bracket 16535.4 0.0Perimeter A. Bracket 19527 0.0

Rigid Connection ConfigurationSlab-to-slab 5123.7 N/A

Interior Angle Bracket 15488.8 N/AEdge Angle Bracket 33031.1 N/APerimeter A. Bracket 486014.0 N/A

Original Connection ConfigurationConnection Max. Moment (Nm) Moment at Fail. (Nm)

Interior Angle Bracket 50327.1 50327.1Edge Angle Bracket 4533.8 0.0Perimeter A. Bracket 75.1 0.0

Continuous Slab ConfigurationInterior Angle Bracket 26076.5 26076.5Edge Angle Bracket 1517.8 0.0Perimeter A. Bracket 325.94 0.0

Rigid Connection ConfigurationSlab-to-slab 2847.7 N/A

Interior Angle Bracket 2914.5 N/AEdge Angle Bracket 5302.3 N/APerimeter A. Bracket 236.2 N/A

In order to determine where theconnection stiffness was at a maximum,the maximum net forces and bendingmoments were observed when 100% ofthe main floor perimeter wall was present.

As it can be seen in Table 2, the maximumforces were observed in the edge anglebracket and the maximum bendingmoments were observed in the interiorangle bracket.

Therefore, development and furtherresearch into detailed rotational stiffnessand connection strength of CLT anglebrackets should be conducted.

It may be noted that the distribution offorces and moments along the slab edgeabove the removed wall were distributedlike that observed in a simply supportedbeam. The distribution of forces andmoments along the perimeter wall edgewas similar to that of a cantilever beam,

a)

b)