Page 1: Project ATLAS: Improving Project Development through GIS

Project ATLAS: Improving Project

Development through GIS

Ryan Arthur, NCDIT Transportation GIS Unit

Eric Wilson, GeoDecisions, GIS Technical Project Lead

2/13/2019

Page 2: Project ATLAS: Improving Project Development through GIS

Project Delivery at NCDOT- The Process

NCDOT - Project ATLAS

• Step 1: Planning

– Comprehensive Transportation Planning (20-25 years)

• Step 2: Prioritization and Programming

– State Transportation Improvement Program (10 years)

• Step 3: Project Development and Env. Analysis

– Project is funded and proposed project is evaluated for environmental

impacts (NEPA/SEPA)

• Step 4: Design

• Step 5: Property Acquisition

• Step 6: Construction

2

Page 3: Project ATLAS: Improving Project Development through GIS

How does NCDOT measure up?

NCDOT - Project ATLAS

3

Page 4: Project ATLAS: Improving Project Development through GIS

How did ATLAS get started?

• August 2017, the Environmental Analysis

Unit (EAU) here at NCDOT approached

the GIS Unit to help them make project

delivery more efficient.

• The EAU are heavy GIS users (predictive

modeling, field verifications, impact maps)-

they wanted to leverage this powerful tool

to improve project delivery.

NCDOT – Project ATLAS

4

Page 5: Project ATLAS: Improving Project Development through GIS

Where does ATLAS fit into Project Delivery

at NCDOT?

NCDOT - Project ATLAS

• Step 1: Planning

– Comprehensive Transportation Planning (20-25 years)

• Step 2: Prioritization and Programming

– State Transportation Improvement Program (10 years)

• Step 3: Project Development and Env. Analysis

– Project is funded and proposed project is evaluated for environmental

impacts

• Step 4: Design

• Step 5: Property Acquisition

• Step 6: Construction

5

Page 6: Project ATLAS: Improving Project Development through GIS

Secretary’s Priorities

NCDOT – Project ALTAS

6

Page 7: Project ATLAS: Improving Project Development through GIS

NCDOT - Project ATLAS

7

• Goal is to streamline project development by utilizing GIS tools, applications, and data

• Adheres to Secretary’s Priorities for Improved Program Delivery

• Accelerated project delivery has strong economic impact and enhances NC’s economic competitiveness

Page 8: Project ATLAS: Improving Project Development through GIS

Current State of Project

Development

NCDOT - Project ATLAS

8

Page 9: Project ATLAS: Improving Project Development through GIS

Future Projects

NCDOT - Project ATLAS

9

Page 10: Project ATLAS: Improving Project Development through GIS

Starting Out

NCDOT - Project ATLAS

10

What does expediting project

delivery really mean?

Isn't "everything" we do related to project delivery?

Who is involved in project delivery?

Where is the data to support this?

What have other DOT's done?

Page 11: Project ATLAS: Improving Project Development through GIS

Disciplines involved

NCDOT – Project ATLAS

11

Page 12: Project ATLAS: Improving Project Development through GIS

Current State of Project

Development- No standards for required deliverables

- There is a central repository for project’s and their associated non-

spatial data (PDF’s, Word Doc’s etc.) (No spatial data is collected.)

- There is a business process, but it is mostly manual

- GIS data used to do reports is not standard across projects or firms

working on projects.

- Data is downloaded and worked on in ArcMap and becomes out of date

- There is no spatial context for a project or past projects and no

central repository for related spatial data

- There are a series of enterprise applications that support different

aspects project delivery but these applications are not integrated

NCDOT - Project ATLAS

12

Page 13: Project ATLAS: Improving Project Development through GIS

Drawings to Diagrams

NCDOT - Project ATLAS

13

Page 14: Project ATLAS: Improving Project Development through GIS

Overall Picture Takes Shape

NCDOT - Project ATLAS

14

• Over 80 interviews with business

units across the agency by October

2017.

• Understanding emerges that there

are deficiencies with many aspects of

the project development process- not

just data itself

• The Project Managers need better

information before a project begins...

"An informed scoping meeting"

Page 15: Project ATLAS: Improving Project Development through GIS

NCDOT - Project ATLAS

15

Page 16: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

16

Page 17: Project ATLAS: Improving Project Development through GIS

Initial Cataloging of Data

17

NCDOT - Project ATLAS

Page 18: Project ATLAS: Improving Project Development through GIS

• 27 Parent Agencies

• 54 Root Web Service Locations

• 563 Total Layers

• 140 Used in Screening a project

NCDOT – Project ATLAS

18

Screening Layers Top 5 ContributorsLayers Top 5 Contributors

Data Facts

Organization CountNCDOT, GIS Unit 154US Geological Survey (USGS) 75NC Center for Geographic Information and Analysis (CGIA) 74

NC Department of Environmental Quality (DEQ) 60

US Department of Homeland Security (DHS) 33

Organization Count

NC Department of Environmental Quality (DEQ) 30

NC Center for Geographic Information and Analysis (CGIA) 21

US Geological Survey (USGS) 18NCDOT, GIS Unit 14US Army Corps of Engineers (USACE) 10

Page 19: Project ATLAS: Improving Project Development through GIS

19

NCDOT - Project ATLAS

Page 20: Project ATLAS: Improving Project Development through GIS

Data Breakdown

NCDOT – Project ATLAS

20

Page 21: Project ATLAS: Improving Project Development through GIS

Data Breakdown

NCDOT – Project ATLAS

21

Page 22: Project ATLAS: Improving Project Development through GIS

Data Developed through ATLAS

130 New Layers are being created

Project Atlas Overview and Update

22

Page 23: Project ATLAS: Improving Project Development through GIS

GIS Specific Goals Developed

23

# Business Goal

1.Provide the transportation project community a searchable gateway to all spatial data used in project delivery at NCDOT.

2.Create a tool that screens NCDOT STIP projects against spatial project data for significant impact areas.

3. Provide a platform for project managers to view their project, their project’s impacts, and other significant information related to managing that project.

4. Stand-up an enterprise GIS SDE for NCDOT project data.

5. Create enterprise GIS data for project delivery.

NCDOT - Project ATLAS

Page 24: Project ATLAS: Improving Project Development through GIS

From Goals to Tools

Search Tool

April 2019

A gateway to search and retrieve verifiable, current and accurate project related data.

Addresses NCDOT’s need to have consistent data available to Project Managers and Consultants.

Screening Tool

April 2019

A powerful web-based tool to evaluate potential impacts to NCDOT projects using GIS data and predictive modeling.

Allows Project Managers and NCDOT Consultants to understand and coordinate earlier about challenges projects will encounter.

ATLAS Workbench

April 2019

A unified toolset for Project Managers to assess and monitor their projects via the web.

Allows Project Managers and Consultants a common platform to access current project data, historic project data, current deliverable status, and visualize project progress.

Team is also supporting: Automation, Data Creation, and Post Deployment App Management Tool.

NCDOT - Project ATLAS

Page 25: Project ATLAS: Improving Project Development through GIS

Search Tool

• Key Functionality

– Search for data by document type, DOT

discipline, and keyword

– Download data package in GBD and DGN

formats

– View data package on a map

NCDOT - Project ATLAS

25

Page 26: Project ATLAS: Improving Project Development through GIS

26

NCDOT - Project ATLAS

Page 27: Project ATLAS: Improving Project Development through GIS

27

NCDOT - Project ATLAS

Page 28: Project ATLAS: Improving Project Development through GIS

NCDOT - Project ATLAS

28

Page 29: Project ATLAS: Improving Project Development through GIS

NCDOT - Project ATLAS

29

Page 30: Project ATLAS: Improving Project Development through GIS

Screening Tool

• Key Functionality

– Screen against 60+ key data layers for area

impacts

– Ability to screen STIP and SPOT projects,

uploaded study area, or draw a study area

– Produce screening report that measures

impact totals by individual data set

– Provide ability to download impacts data sets

– View impact data on a map

NCDOT – Project ATLAS

30

Page 31: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

31

Page 32: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

32

Page 33: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

33

Page 34: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

34

Page 35: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

35

Page 36: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

36

Page 37: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

37

Page 38: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

38

Page 39: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

39

Page 40: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

40

Page 41: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

41

Page 42: Project ATLAS: Improving Project Development through GIS

ATLAS Workbench

• Key Functionality

– Flexible in conjunction with policy changes

– Advanced Map Viewer

– Integration with SharePoint (Scoping and

PreConstruction)

– Ingestion of standard deliverable data (PDF

and spatial data deliverables)

– View your project within the context of

surrounding projects and data for those

projects

NCDOT – Project ATLAS

42

Page 43: Project ATLAS: Improving Project Development through GIS

43

NCDOT – Project ATLAS

Page 44: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

44

Page 45: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

45

Page 46: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

46

Page 47: Project ATLAS: Improving Project Development through GIS

SharePoint PreCon Site

U-1234

Plants

Species

Wetlands

Etc.

ATLAS Workbench

U-1234

NCDOT Enterprise Database

1) Has the plant survey been conducted during appropriate season?

1) Yes2) No

Upload PDF Report________Upload Spatial Data_________

GP Service

GP Service

Web Map Service

QA/QC’s data-naming

convention, correct TIP etc.

QA/QC’s data-schema validation,

correct TIP

Workbench: Data Flow

NCDOT – Project ATLAS

ATLAS

Page 48: Project ATLAS: Improving Project Development through GIS

Workbench – Snowball Effect

NCDOT – Project ATLAS

48

Put Data into Action

Harvest Project Data

Establish Project Data Repository

Build Tools to Enforce Standards

Development of Standards

Page 49: Project ATLAS: Improving Project Development through GIS

Application Management Tool

• Key Functionality

– Add/remove layers

– Manage deliverables types

– Manage workbench questions

– Update About, Application Disclaimers,

Additional Resources, and Help

NCDOT – Project ATLAS

49

Page 50: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

50

Page 51: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

51

Page 52: Project ATLAS: Improving Project Development through GIS

NCDOT – Project ATLAS

52

Page 53: Project ATLAS: Improving Project Development through GIS

ATLAS in the GIS Landscape

NCDOT – Project ATLAS

53

Page 54: Project ATLAS: Improving Project Development through GIS

Importance of continued data

access

NCDOT – Project ATLAS

54

NCDOT’s ATLAS Webservices

Page 55: Project ATLAS: Improving Project Development through GIS

Important Notes on ATLAS

NCDOT – Project ATLAS

• We are not eliminating field work

– Field work is still a major component of all projects. For the first

time we will be capturing this data for all projects undergoing

environmental evaluation.

• We are not eliminating jobs

– We are helping project teams do their jobs more effectively and

efficiently.

• We are pushing more work earlier in the process to help scheduling,

budgeting and scoping

• We are helping to deliver better projects within our program delivery

goals by:

– Improving GIS data and management

– Improving processes