project cost control

27
1 Project Cost Control

Upload: krysta

Post on 19-Mar-2016

56 views

Category:

Documents


0 download

DESCRIPTION

Project Cost Control. Reasons for Project Cost Control. PROGRESS PAYMENTS CHANGE IMPACT CONFORMANCE TO PLAN PROJECT FINAL COST PROJECT DATE OF COMPLETION. Reasons For Project Cost Control. PLANNING PERFORMANCE MEASURING PERFORMANCE COMPARING ACTUAL AND - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project  Cost Control

11

Project Cost

Control

Page 2: Project  Cost Control

22

PROGRESS PAYMENTS CHANGE IMPACT CONFORMANCE TO PLAN PROJECT FINAL COST PROJECT DATE OF COMPLETION

Reasons for Project

Cost Control

Page 3: Project  Cost Control

33

PLANNING PERFORMANCE MEASURING PERFORMANCE COMPARING ACTUAL AND PLANNED PERFORMANCE ADJUSTING PLANS AS REQUIRED

Reasons For Project Cost Control

Page 4: Project  Cost Control

44

REDUCTION OF COMPLEXITYREDUCTION OF COMPLEXITY SHORT PLANNING INTERVALSSHORT PLANNING INTERVALS COST ESTIMATING SIMPLIFICATIONCOST ESTIMATING SIMPLIFICATION COST COLLECTION SIMPLIFICATIONCOST COLLECTION SIMPLIFICATION COST / SCHEDULINGCOST / SCHEDULING

WORK BREAKDOWN

Page 5: Project  Cost Control

55

COST: DEVIATION FROM BUDGET.DEVIATION FROM BUDGET. NO CONSIDERATION FORNO CONSIDERATION FOR PLANNED SEQUENCE.PLANNED SEQUENCE.

A COMPARISON BETWEEN PLANNED AN SCHEDULED ACTIVITIES.

SCHEDULE:

VARIANCES

Page 6: Project  Cost Control

66

TIME PERIOD

100

90

80

70

60

50

40

30

20

10

%COSTREPORT

DATE %COST

BEHINDSCHEDULE

BCWS

ACWP AVACCOUNT.VARIANCE

CVCOSTVARIANCETO DATESV

SCHEDULEVARIANCE

BCWP (EARNED VALUE)

5 1510

BAC

Page 7: Project  Cost Control

77

Progress by

DISCIPLINE

Page 8: Project  Cost Control

88

ENGINEERING

Page 9: Project  Cost Control

99

DRAWING MILESTONES

START DRAFT - 20%

DRAFT COMPLETE - 65%

OFFICE CHECK - 80%

OWNER REVIEW - 85%

FINAL DRAFT - 90%

APPROVAL WITH HOLDS - 95%

FINAL OWNER APPROVAL - 100%

Page 10: Project  Cost Control

1010

BUDGETEDMANHOURSDISCIPLINE

CIVIL

ARCHITECTURAL

STRUCTURAL

MECHANICAL

PIPING

ELECTRICAL

INSTRUMENTATION

20

35

20

20

50

40

15

200

1250

2500

1250

1500

4000

3000

1500

15000

8.3

16.7

8.3

10.0

26.7

20.0

10.0

100TOTAL ENGINEERING VALUE

DISCIPLINE WGT. VALUE

%ESTIMATEDDRAWINGS

Page 11: Project  Cost Control

1111

TOTALPIPE

DWGS.

START DRAFT

DRAFT COMPLETE

OFFICE CHECK

OWNER REVIEW

FINAL DRAFT

APPRV. W/ HOLDS

FINAL APPROVED

50

50

50

50

50

50

50

4.0

6.5

8.0

8.5

9.0

9.5

20.0

TOTAL PIPING DISCIPLINE PROGRESS 65.5

MILESTONE DISCIPLINE %COMPLETE

DWGS. INMILESTONE

10

5

5

5

5

5

10

MILESTONEVALUE

%20

65

80

85

90

95

100

Page 12: Project  Cost Control

1212

PROJECTCONTRIBUTION

WEIGHTEDVALUE

CIVIL

ARCHITECTURAL

STRUCTURAL

MECHANICAL

PIPING

ELECTRICAL

INSTRUMENTATION

8.3

16.7

8.3

10.0

26.7

20.0

10.0

7.5

11.7

6.6

7.5

17.4

12.0

5.0

TOTAL ENGINEERING PROGRESS 67.7%

DISCIPLINE %COMPLETE

90

70

80

75

65.5

60

50

Page 13: Project  Cost Control

1313

PROCUREMENTMEASUREMENT

Page 14: Project  Cost Control

1414

MATERIAL TAKE OFFS PURCHASE REQUISITIONS PURCHASE ORDERS

PROCUREMENTMEASUREMENT

Page 15: Project  Cost Control

1515

FUNCTION% WEIGHTED

VALUEESTIMATEDMANHOURSFUNCTIONS ESTIMATED

QUANTITIES

MATERIAL TAKE-OFF (DWGS)

PURCHASE REQUISITIONS

PURCHASE ORDERS

400

700

400

26.6

46.7

26.7

TOTAL PROCUREMENT VALUE 1500 100

150

200

100

Page 16: Project  Cost Control

1616

150

75

50%

DRAWINGS REQUIRING TO'S

DRAWING WITH TO'S COMPLETE

PHYSICAL PROGRESS

TAKE OFFS

Page 17: Project  Cost Control

1717

PURCHASEREQUISITIONS

200

50

25%

ESTIMATED PR's

PR's APPROVED FOR PURCHASE

PHYSICAL PROGRESS

Page 18: Project  Cost Control

1818

PURCHASEORDERS

28 PO's OUT OF 100 = 14%

1 MILLION DOLLARS EXPLANTEDOUT OF 50 MILLI0NS = 1%

PHYSICAL PROGRESS = 14 + 1 = 15%

QUANTITY PLACED = 50%DOLLAR VALUE SHIPPED = 50%

Page 19: Project  Cost Control

1919

FUNCTIONS %COMPLETEWEIGHTED

VALUEPROCUREMENTCONTRIBUTION

MATERIAL TAKE-OFFS

PURCHASE REQUISITIONS

PURCHASE ORDERS

TOTAL PROCUREMENT PROGRESS 29.0

50

25

15

26.6

46.7

26.7

13.3

11.7

4.0

Page 20: Project  Cost Control

2020

MOBILIZATION & GRADE

FOUNDATION COMPLETE

STRUCTURAL COMPLETE

EQUIPMENT ERECTION COMPLETE

PIPING COMPLETE

ELECTRICAL COMPLETE

MECHANICAL COMPLETION

COMMISSIONING

5

12

9

14

25

17

13

5

TOTAL PROJECT VALUE 40000 100

WEIGHTEDPERCENTAGE

2000

4800

3600

5600

1000

6800

5200

2000

ESTIMATEDMANHOURSMILESTONE

Page 21: Project  Cost Control

2121

WEIGHTED%

MOBILIZATION& GRADING

FOUNDATION

STRUCTURAL STEEL

EQUIPMENT ERECTION

5

12

9

14

5

9.6

2.7

1.4

TOTAL PHYSICAL PROGRESS 18.7

PROJECTCONTRIBUTION

100

80

30

10

%COMPLETEMILESTONE

Page 22: Project  Cost Control

2222

TOTALENGINEERING

PROGRESS

Page 23: Project  Cost Control

2323

TOTAL CONTRACT

DESIGN/ENGINEERINGOVERALL COMPLETE

WEIGHTEDVALUE%

ENGINEERING

PROCUREMENT

90.9

9.1

60.6

2.6

PROGRESS 16500 100 63.2

PROJECTCONTRIBU-

TION

BUDGETEDMANHOURS

15000

1500

67.7

29.0

%COMPLETE

Page 24: Project  Cost Control

2424

PRODUCTIVITYPRODUCTIVITY

PROFILESPROFILES

Page 25: Project  Cost Control

2525

FACTORS AFFECTINGPRODUCTIVITY PROFILES

PROJECT LOCATION JOB COMPLEXITY WORKING HOURS LABOR DENSITY SUPERVISION QUALITY WEATHER MIXTURE OF NATIONALITIES DISCIPLINE

Page 26: Project  Cost Control

2626

THEORETICAL% BUDGET MANHOURS UTILIZED

10 20 30 40 50 60 70 80 90 100

1.2

1.1

1.O

0.9

0.8

0.7

0.6

0.5

12 23 33 42 50 57 63 76 87 100

**

**

**

** *

*

PRODUCTIVITY

PHYSICAL COMPLETION%

Page 27: Project  Cost Control

2727

CREDITBY EARNEDMANHOURS

2000 MHRS

1000 MHRS

1000 MHRS

ORIGINAL ESTIMATE

ESTIMATE REMAINING

EARNED