project cost management sections of this presentation were adapted from a guide to the project...
TRANSCRIPT
Project Cost Management
Sections of this presentation were adapted from A Guide to the Project Management
Body of Knowledge 3rd Edition, Project Management Institute Inc., © 2004
Project Cost Management
“The processes involved in planning, estimating, budgeting, and controlling costs so that the budget can be completed within the approved budget”
Why Do We Manage Cost?
Part of triple constraint, can’t manage one without the others (scope, time, and quality)
Plots of cost and scope against plan can help spot problems early
Cumulative Value
Time
Planned Value (PV)
Actual Costs (AC)
Earned Value (EV)
Today
Is this project over/under budget?
Is it ahead of/behind schedule?
Cost Management Key Terms
PV - Planned Value, estimated value of the planned work
EV – Earned Value, estimated value of work done
AC – Actual Cost, what you paid
BAC – Budget at Completion, the budget for the total job
EAC –Estimate at Completion, what is the total job expected to cost?
ETC – Estimate to Complete, forecasted costs to complete job
VAC – Variance at Completion, how much over/under budget do we expect to be?
How Do We Manage Cost?
Three processes Cost Estimating Cost Budgeting Cost Control
Cost Estimating
Cost Budgeting
Cost Control
Cost EstimatingEnterprise Environmental Factors
Organizational Process Assets
Project Scope Statement
Analogous estimating
Determine resource cost rates
Bottom up estimating
Parametric estimating
Project management software
Vendor bid analysis
Reserve analysis
Cost of quality
Inputs OutputsTools & Techniques
Work Breakdown Structure
WBS Dictionary
Cost Estimating
Cost Budgeting
Cost Control
Project Management Plan• Schedule Mgmt
Pln
• Staffing Mgmt Pln
• Risk Register
Activity Cost Estimates
Activity Cost Estimates Supporting Detail
Requested Changes
Cost Management Plan Updates
Estimating Methods
Analogous (Top Down) estimating – Managers use expert judgment or similar project costs [quick, less accurate]Bottom-Up estimating – People doing work estimate based on WBS, rolled up into project estimate [slow, most accurate]Parametric estimating – Use mathematical model (i.e. cost per sq ft). [accuracy varies] Two types:
Regression analysis – based on analysis of multiple data pointsLearning Curve – The first unit costs more than the 100th, forecasts efficiency gains
Estimating Methods
Vendor Bid Analysis – Estimating using bids + allowances for gaps in bid scope [slow, accuracy depends on gaps]Reserve Analysis – Adding contingency to each activity cost estimates as zero duration item [slow, overstates cost]
Cost Budgeting
Project Scope StatementCost aggregation
Reserve analysis
Parametric estimating
Funding limit reconciliationInputs
OutputsTools & Techniques
Cost Estimating
Cost Budgeting
Cost Control
Cost Baseline
Project Funding Requirements
Cost Management Plan Updates
Requested Changes
Work Breakdown Structure
WBS Dictionary
Activity Cost Estimates
Activity Cost Estimates Supporting Detail
Project Schedule
Resource Calendars
Contract
Cost Management Plan
Cost Budgeting
Budgeting is allocating costs to work packages to establish a cost baseline to measure project performanceRemember Contingency items are for unplanned but required changes it is not to cover things such as:
Price escalation Scope & Quality Changes
Funding Limit Reconciliation – Smoothing out the project spend to meet management expectations
Cost ControlCost Baseline
Project Funding Requirements
Performance Reports
Cost change control system
Performance measurement analysis
Forecasting
Project performance reviews
Project management software
Variance management
Inputs OutputsTools & Techniques
Work Performance Information
Approved Change Requests
Cost Estimating
Cost Budgeting
Cost Control
Project Management Plan
Cost Estimate Updates
Cost Baseline UpdatesPerformance Measurements
Forecasted Completion
Requested Changes
Recommended Corrective Actions
Organizational Process Assets Updates
Project Management Plan Updates
Earned Value
Progress is compared against the baseline to determine whether project is ahead of or behind planPercent complete can be difficult to measure, some managers use rules
50/50 Rule – Assumed 50% complete when task started, final 50% at completion
20/80 Rule – 20% at start 0/100 Rule – No credit until complete
Planned Value (PV) – Budgeted CostEarned Value (EV) – Actual work completedActual Cost (AC) – Costs incurredEstimate to Complete (ETC) – What’s LeftEstimate at Completion (EAC) – What final cost will be
Earned Value Graph
Variance at Completion
(VAC)
Target Cost &
Schedule
Schedule Variance (Time)
Planned Value (PV)
Earned Value (EV)
Earned Value Formulas
NAME FORMULA NOTESCost Variance (CV) EV-AC Negative = Over budget
Positive = Under budget
Schedule Variance (SV)
EV-PV Negative = Behind Schedule Positive = Ahead of Schedule
Cost Performance Index (CPI)
EV/AC How much are we getting for every dollar we spend?
Schedule Perform Index (SPI)
EV/PV Progress as % against plan
Estimate to Complete (ETC)
EAC-AC How much more do we have to spend?
Variance at Completion (VAC)
BAC-EAC At the end of the day, how close will we be to plan?
Estimate at Completion (EAC)
See following slide
Earned Value Formulas (Cont’d)
NAME FORMULA NOTESEstimate at Completion (EAC)
BAC/CPI Use if no variances from BAC have occurred
AC+ATC Use when original estimate was bad. Actuals + New estimate
AC+BAC-EV Use when current variances are not expected to be there in the future
AC+(BAC-EV)/CPI Use when current variances are expected to continue
Barn Exercise
You have a project to build a new barn. The specs for building the barn are to construct 4 sides and then an angled roof. Each side of the barn is to take one day to build as is the roof. The budgeted amount is $2,000 per side and $2000 applied to the roof cost. The sides are to be completed one after the other. Today is the end of day four.
Tricks for Earned Value
EV is always firstVariance = EV minus somethingIndex = EV divided by somethingIf the formula relates to cost use ACIf the formula relates to schedule use PVInterpreting results: negative is bad and positive is goodInterpreting results: greater than one is good, less than one is bad
PV
AC ETCEAC
BACProject Start
Current Status
Terms to Remember
Present ValueNet Present Value (NPV)Internal Rate of Return (IRR)Payback PeriodBenefit Cost Ratio = BCR>1, Payback is greater than the costOpportunity CostSunk Cost
Working CapitalStraight Line DepreciationAccelerated Depreciation
Double Declining Balance Sum of Years Digits
Value Analysis (Value Engineering)
You won’t be calculating most of these numbers on the test, just remember the concepts for general questions
Answers to Questions
1 – C
2 – D
3 – B
4 – A
5 – C
6 – B
7 – C
8 – A
Answers to Questions (Cont’d)What is: Calculation: Answer: Interpretation of Answer:
PV $500+$500+$500 $1,500 We should have completed $1500
EV $500+$500+$250 $1,250 We actually completed $1,250 worth of work
AC $500+$1000+$250 $1,750 We have actually spent $1,750
BAC $500+$500+$500+$500 $2,000 Our project budget is $2000
CV $1,250 - $1,750 -$500 We are over budget by $500
CPI $1,250/$1,750 0.714 We are only getting $0.71 out of every dollar that we are spending on the project
SV $1,250 - $1,500 -$250 We are behind schedule
SPI $1,250/$1,500 0.833 We are progressing at 83% of the planned rate
EAC $2,000/0.714 $2,801 We currently estimate the project will cost $2,801
ETC $2,801-$1,750 $1,051 We need to spend $1,051 to finish the project
VAC $2,000 - $2,801 -$801 We currently expect to be $801 over budget when the project is completed