project management: a managerial approach chapter 8 scheduling
TRANSCRIPT
Project Management: A Managerial Approach
Chapter 8
Scheduling
Overview
• WBS to Schedule Process
• PERT
• Schedule Types
• CPM
Scheduling
• A schedule is the conversion of a project action plan into an operating timetable
• It serves as the basis for monitoring and controlling project activity
• Taken together with the plan and budget, it is probably the major tool for the management of projects
Scheduling
• In a project environment, the scheduling function is more important than it would be in an ongoing operation
• Projects lack the continuity of day-to-day operations and often present much more complex problems of coordination
Chapter 8-2
Scheduling
• The basic approach of all scheduling techniques is to form a network of activity and event relationships
• This network should graphically portray the sequential relations between the tasks in a project
• Tasks that must precede or follow other tasks are then clearly identified in time as well as function
Chapter 8-3
Types of Scheduling
• Operation Scheduling: a type of scheduling that assigns jobs to machines or workers to job. Operation schedule is crucial because many performance measures such as on-time delivery, inventory levels, the manufacturing cycle time, cost and quality, relate directly to the scheduling of each production lot.
• Workforce Scheduling: a type of scheduling that determine when employee work. Workforce scheduling is equally crucial because measures of performance such as customer waiting time, waiting-line length, utilization, cost, and quality related to the availability of the servers
Chapter 8-2
Techniques of Scheduling
• Gantt Chart
• Network Techniques: PERT & CPMBoth of the techniques is called diagramed technique of
scheduling which possesses the following benefits:
– It is a consistent framework for planning, scheduling, monitoring, and controlling the project
– It illustrates the interdependence of all tasks, work packages, and work elements
Chapter 8-2
Scheduling• Network benefits (cont.):
– It aids in ensuring that the proper communications take place between departments and functions
– It determines an expected project completion date
– It identifies so-called critical activities that, if delayed, will delay the project completion time
– It identifies activities with slack that can be delayed for specific periods without penalty
Chapter 8-5
Scheduling
• Network benefits (cont.):– It determines the dates on which tasks may be
started or must be started if the project is to stay on schedule
– It illustrates which tasks must be coordinated to avoid resource timing conflicts
– It illustrates which tasks may run, or must be run, in parallel to achieve the predetermined project completion date
– It relieves some interpersonal conflict by clearly showing task dependencies
Chapter 8-6
Gantt chart
Advantages
-Gantt charts are quite commonly used. They provide an easy graphical representation of when activities (might) take place.
-Simple& quickest method.
Limitations
- Do not clearly indicate details regarding the progress of activities
- Do not give a clear indication of interrelation ship between the separate activities
Simple Schedule – Gantt Chart
Network Techniques: PERT and CPM
• With the exception of Gantt charts, the most common approach to scheduling is the use of network techniques such as PERT and CPM
• The Program Evaluation and Review Technique (PERT) was developed by the U.S. Navy in 1958
• The Critical Path Method (CPM) was developed by DuPont, Inc during the same time period
Chapter 8-7
Network Techniques: PERT and CPM
• PERT has been primarily used for research and development projects
• CPM was designed for construction projects and has been generally embraced by the construction industry
• The two methods are quite similar and are often combined for educational presentation
Chapter 8-8
Scheduling Terminology
• Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete
• Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources.
• Network - The combination of all activities and events define the project and the activity precedence relationships
Scheduling Terminology
• Path - The series of connected activities (or intermediate events) between any two events in a network
• Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event
Chapter 8-10
Scheduling Terminology
• An activity can be in any of these conditions:– It may have a successor(s) but no predecessor(s) -
starts a network
– It may have a predecessor(s) but no successor(s) - ends a network
– It may have both predecessor(s) and successor(s) - in the middle of a network
Steps in CPM Scheduling
• 1. Specify the individual activities.
• 2. Determine the sequence of those activities.
• 3. Draw a network diagram.
• 4. Estimate the completion time for each activity.
• 5. Identify the critical path (longest path through the network)
• 6. Update the CPM diagram as the project progresses.
Drawing Networks
• Activity-on-Arrow (AOA) networks use arrows to represent activities while nodes stand for events
• Activity-on-Node (AON) networks use nodes to represent activities with arrows to show precedence relationships
• The choice between AOA and AON representation is largely a matter of personal preference
Chapter 8-12
The Project Network
• Use of nodes and arrows
Arrows An arrow leads from tail to head directionally– Indicate ACTIVITY, a time consuming effort
that is required to perform a part of the work.
Nodes A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start and/or finish.
Activity on Node & Activity on Arrow
Activity on Node
- A completion of an activity is represented by a node
Activity on Arrow
- An arrow represents a task, while a node is the completion of a task
- Arrows represent order of events
Activity Code
Activity Duration in days Depends on
A Prepare Technical Specifications 10 -----
B Tender Processing 25 A
C Release of work order 3 B
D Supply of Boiler equipment 60 C
E Supply of Auxiliaries 20 C
F Supply of pipes & pipe fittings 10 C
G Civil Work 15 C
H Installation of Auxiliary equipment & piping
5 E,F&G
I Installation of Boiler 10 D&H
J Testing and commissioning 2 I
Requirements: 1. Draw a network diagram
2. Find out the critical Path.
Hypothetical Network
G
B
H
IA
D
6
Start CE
F
J End10 25 3
60
20
10
15 5
5
5
10
2
End of the Lesson