project management - not just for work - 23rd april 2015
TRANSCRIPT
Project Management –
Not Just for Work
Barnaby Beere Freelance Project Manager
23rd April 2015
Overview
• Themes
• Background
• “Hard” project – construction of new
facilities
• “Soft” project – creation of a joint venture
company
• Challenge to Project Managers
• Questions?
Themes
• Project Management
• Economics
• Cooperation
• Managing change
• Stakeholder engagement
• Environmental issues
• Concrete, drainage, floodlighting, pitch surfaces …
Why do Project Management
outside of work?
• PM is a skill, and skills need practice
• Opportunity to use your skills to do
something constructive and positive for
your local community
• Make new friends!
Wotton Community Sports Foundation
• Charity with a 999-year lease on a 38 acre site outside Wotton-under-Edge – “New Road site”
• Purpose is to develop and provide sports and recreational facilities for the local community
New Road Site, original layout Red line shows site boundary
New Road site, current
Skatepark
Astro pitch
3G pitch Attenuation ponds
Rugby pitch
What do I do and how did I get
involved?
• Skate park project in neighbouring village
• The benefits of cooperation, and
economies of scale
• The difficulty in raising ~£1.6m
• Missing a great opportunity to shut up
• Eventual success!
“Hard” project – creation of new
facilities
• Lack of sports / playing facilities in local
area
• 38-acre site donated as part of S106
• “If we build it, they will come”
• Difficulties in obtaining funding from Sport
England, Football Foundation, England
Hockey
• A new approach, and a generous donation
Construction of Artificial Pitches
Lessons Learned 1
• To keep project teams motivated, you
really need some “wins” along the way
Construction
• The Law of Comparative Advantage and the
importance of being a good client
• Getting to the start line - the benefit of
hard deadlines
• Building a delivery team
– How do you know when you’ve got the
right supply chain?
– Agreeing the end point
• Celebrating the success!
Opening Ceremony - Sept 2013
Facilities in use
Lesson Learned 2
Impatience is a virtue!
Interim Solutions - power
• No mains connection in time for grand opening September 2013
• Would mean that floodlights unusable, would reduce usability (value) of facility significantly
• Rented temporary power 50 KVA generator • Was on site from September 2013 - February
2014
Like this one, but blue ....
Lesson Learned 3
• Best kind of problems are those that can be solved with the application of money
• “Count of Monte Cristo theory of project management”
Concrete example
• In order to put construct this ramp:
– Identify the need
– Agree a specification with the user
– Ensure that we had sufficient funds to pay for the work
– Engage a contractor
– Agree a start and finish date for the work
– Monitor and accept the work
– Pay the contractor
Interim Solutions part 2 • Planning permission for site development includes
changing room and pavillion
Interim Solutions
More construction - skatepark
• Effective procurement process - the benefits of experience
• Success breeds success - proven track record of delivery
• Seed capital - easier when you’ve got a source of revenue income
• Raising >£60k in 9 months • Unexpected early start and early completion
Skatepark Opening Ceremony - March 2015
Positive Externalities
Attenuation Ponds, Trees
“Soft” project – taking on the
management of the sports centre
• Adjacent sports centre owned by KLBS,
managed by Stroud District Council
• Lack of marketing, opportunity to
cooperate and deliver better service
• The challenges of organisational change
• “How hard can it be to set up a new
business?”
• Early successes
Organisational structure
Learning from Experience,
Best Practice
• Docs on Charity Commission website – Choosing to Collaborate: Helping you succeed
• Docs on APM website – Directing Change - A guide to governance of project
management
– Co-directing Change - A guide to the governance of
multi-owned projects
• Benchmarking visits to similar local
facilities
Change project
• Long buildup, short execution
• Challenges in building a business case
• Getting two governing bodies to agree -
stepwise progress
• Building consensus, overcoming
resistance
• The benefits of hard deadlines pt 2
• Implementation challenges
• Joining the 21st century
Post-implementation
Social Media
Linked Twitter and Facebook pages for both Sport Wotton and WCSF - Twitter accounts also post automatically to websites
Some things take longer than you expect ...
• Procurement, configuration, installation and commissioning of new IT, website, telephone system
• Opening a bank account - turned into the critical path activity (90 days!)
• Preparation for TUPE transfer of existing staff
Things we’ve had to do to take over
the sports centre • Establish a new company, c/w PAYE number, bank
account etc
• Prepare a business plan c/w financial forecasts
• Set up a pension plan for employees
• TUPE transfer existing employees to the new company
• Make arrangements for handling cash
• Set up a website
• Get a logo and branded workwear
• Recruit a manager
• Undertake advertising and marketing
Lesson Learnt 4
• Change is messy and difficult, and challenges people in ways that can make them feel profoundly uncomfortable
• But, that doesn’t mean that you shouldn’t do it ...
Social Capital
• The expected collective or economic benefits derived from the preferential treatment and cooperation between individuals and groups
• “bonding” and “bridging” • The importance of strong and weak network
links
Things I’ve been able to practice
• Procurement and contract management • Building supply chains • Leadership, delegation, chairing meetings • Applying economic theories in practice • Financial management • Civil engineering • Networking • Planning law • Charity law • Websites, marketing, Twitter
Next Steps - Access Path for Skatepark
A Shameless Appeal for Funds
• We urgently need to build an path to provide a safe access route into our site for skatepark users
• Cost estimate £95k (of which just under £10k already raised or pledged)
• Can be offset by donations of building materials – 250 tonnes of Type 1 sub-base material – 35 cubic metres of Tarmac – 1000 metres of pre-cast concrete edging kerbs – 80 cubic metres of concrete – 1000 square metres of geotextile membrane – 20 lighting bollards and 1000 metres of lighting cable
• Would your company like to sponsor a yard of path, or could you donate some of the above materials?
The Challenge
• Project Managers have specific skills that can be used for the benefit of society
• What are you going to do? • How are you going to improve your
community? • What are you going to create?
Thank you! If you’re interested: Wotton Community Sports Foundation http://www.wcsf.org.uk Twitter: @WCSF_Wotton Facebook: WCSF - Wotton Community Sports Foundation Sport Wotton Ltd http://www.sportwotton.co.uk Twitter: @SportWotton Facebook: Wotton Community Sports Centre
Barnaby Beere [email protected] LinkedIn: barnabybeere