Project Management Plan
For
- <CUSTOMER> -
Revision 1.0
Customer - Project Manager
Vendor - Project Manager
Date 2014
Project Management Plan Page ii
ii
Table of Contents
1. Overview ................................................................................................................... 3 1.1. Project Purpose, Objectives, and Success Criteria ............................................ 3 1.2. Project Deliverables ........................................................................................... 3 1.3. Assumptions, Dependencies, and Constraints .................................................. 3
2. Project Organization ................................................................................................ 5 2.1. Team Structure .................................................................................................. 5 2.2. Roles and Responsibilities ................................................................................. 6
3. Managerial Process Plans ....................................................................................... 7 3.1. Staffing Plan ...................................................................................................... 7 3.2. End User Training Plan ...................................................................................... 8 3.3. Detailed Monitoring Plan .................................................................................... 9 3.4. Communication and Reporting Plan .................................................................. 9 3.5. Risk Management Plan .................................................................................... 12 3.6. Issue Resolution Plan ...................................................................................... 12 3.7. Project Close-Out Plan .................................................................................... 13 Appendix A – Project Plan ....................................................................................... 16 Appendix B – Detailed Monitoring Plan .................................................................... 17 Appendix C – Change Request Form ...................................................................... 18 Appendix D – Risk and Issue Management Templates ........................................... 19 Appendix E – Progress Reporting Template ............................................................ 21 Appendix F – Meeting Minutes Template ................................................................. 24
Project Management Plan Page 3
3
1. Overview
The Company Intro in Brief
1.1. Project Purpose, Objectives, and Success Criteria
Project Purpose The purpose of this project is to implement ERP - at <Customer>, which will help <CUSTOMER> to
improve its operational efficiency, enhance productivity and control over operations by adopting industries
best practices embedded in ERP business process. And to provide the project management tasks in
support of the overall project and the various phases of implementation.
Objectives and Success Criteria
The project covers the following high level objectives:
• Process Improvement by implementing industry’s best practices
• Improve administrative (cross functional) collaboration
• Transfer user skill sets
• Automated accounting rules and chart of accounts classifications
• Implementation of <xyz Product>
- Financials
- Purchasing
- Inventory
- Sales Order Management
1.2. Project Deliverables
Following are the key deliverables of the project:
Deliverable Recipients Delivery
Date
Delivery
Method Comments
Task
Id
Project Preparation <CUSTOMER> Jan-11 2014 Memo for
confirmation /
Site Inspection
16
ABC Execution <CUSTOMER> Feb-22 2014 On Server 51
Validation & Acceptance
Testing
<CUSTOMER> Mar-02 2014 Acceptance
Certificate
63
Post Execution Activities <CUSTOMER> Mar-29 2014 On Test
Server /
Acceptance
Certificate
68
1.3. Assumptions, Dependencies, and Constraints
Assumptions
Project Management Plan Page 4
4
• <CUSTOMER> shall provide proper working space and other resources to <VENDOR> team. • <CUSTOMER> shall provide timely response to information request and required approvals to
go-forward from <VENDOR> within 3 business days. • <CUSTOMER> shall provide the personnel / executive support and access as reasonably
requested by <VENDOR> to meet the identified timelines for this project • <CUSTOMER> shall ensure participation of its staff in the coordination meetings to ensure quick
decision making and timely approvals to avoid any project delays. • Any delay / operational hindrance in providing information and/or sign-off shall consequently
result in delay in the overall project and should not be included in the time line. This may have material affect on the contract executed by <VENDOR> and <CUSTOMER>.
• There shall be adequate involvement from IT and Business Management for interviews, facilitation sessions, and project guidance and the involvement of key IT-Business liaisons to gather the information required to perform the assignment.
• <CUSTOMER> shall provide access to any work previously performed on related projects that could be of use to <VENDOR> such as presentations, project schedules, BPR and business plans, etc.
• <CUSTOMER> shall provide access to documentation of processes and manuals, related performance measures and any current state reports/studies.
• <CUSTOMER> shall assign a full-time project manager to this project to assist with data gathering, interviews and any other reasonable assistance required for this project
• <CUSTOMER> project management office shall arrange the time and place with the interviewers as per the project plan
• <VENDOR> shall deploy its people in accordance with the project plan/Staffing Plan (2.3) • <CUSTOMER> will provide balances as of Mar-31 2014 for go-live activities. • Oracle System will go-live in April. <CUSTOMER> will run parallel system till Jun-30 2014 and
from Jul-01 2014 legacy system will be shutdown.
Dependencies
• <VENDOR> team will be dependent on <CUSTOMER> team for information and the decisions
where needed.
• <VENDOR> team deliverables will be dependent on <CUSTOMER> response i.e. document
acceptance / signoff.
Constraints
• Availability of <CUSTOMER> SMEs
Project Management Plan Page 5
5
2. Project Organization
2.1. Team Structure
Project Management Plan Page 6
6
2.2. Roles and Responsibilities
Project Director: is responsible for: • Securing funds and resources for the project • Participate in project planning (high level) and the development of the Project Management
Plan • Serving as level 2 escalations for <CUSTOMER> .
• Provides support for the Project Manager; assists with major issues, problems, and policy
conflicts; removes obstacles; is active in planning the scope; approves scopes changes;
signs off on major deliverables; and signs off on approvals to proceed to each succeeding
project phase.
Solution Architect: is responsible for: • Ensuring timely delivery of technical deliverables. • Clearing hindrances/road blocks and ensuring timely availability of resources. • Reviewing the project’s progress. • Assist in project implementation to achieve the project objective. • Identify risks and issues and help in resolutions.
Project Manager: is responsible for: • Serving as the focal point for all communication between (CUSTOMER > and <VENDOR>. • Track timelines, budgets, risks and monitor overall progress of the project. • Serving as level 1 escalation for < CUSTOMER >. • Providing regular updates to <CUSTOMER>and meeting with <CUSTOMER>PMO. • Provisioning of signoffs on deliverables by Business/technical stakeholders.
• Assure speedy resolution to issues and provide guidance to the consultants.
Track Leads: is responsible for: • Overseeing support resources and checking quality of deliverables. • Interacting with senior <CUSTOMER>end users as required. • Identify risks and issues and help in resolving them.
• Assure speedy resolution to issues and provide guidance to the consultants.
Consultants: are responsible for: • Data gathering, entering setup data and executing the application. • Resolving functional issues reported by < CUSTOMER>. • Interacting with <CUSTOMER>Analysts and End Users to resolve issues. • Logging service requests with Oracle support services.
Developer: is responsible for: • Understanding the report development requirements of < CUSTOMER>. • Developing customized reports
DBA/System Administrator: is responsible for: • ERP Server Administration. • Operation of Storage and Backup systems. • Systems Patching. • Running Oracle utilities such as adadmin and adpatch and backup/recovery.
Project Management Plan Page 7
7
Managerial Process Plans
2.3. Staffing Plan
<VENDOR> will allocate following team members to the implementation project:
<VENDOR> Team
Sr. # Resource Name Role Cell # Utilization Days
1 Senior Solution Architect/Manager 40% 24
2 Project manager 35% 21
3 Track Lead SCM 80% 49
4 SCM Consultant 30% 18
5 SCM Consultant 100% 61
6 SCM Consultant 70% 43
7 Track Lead Financials 80% 49
8 Financials Consultant 100% 61
9 Financials Consultant 100% 61
10 DBA/System Administrator 20% 12
11 Developer 100% 61
<CUSTOMER> Team
Sr. # Resource Name Role Cell #
1 Project Manager
2 Manager IT Infrastructure
3 Financials Support
4 SCM Support
5 Project Lead
6 Financials User
7 Financials User
8 Financials User
9 SCM User
10 SCM User
Project Management Plan Page 8
8
2.4. End User Training Plan
End user trainings will be conducted by <VENDOR> Functional consultants of implemented modules via
online workflows and videos that are available on the accelerator website. These training sessions will
equip the <CUSTOMER> team with the project methodology, solution overview, functionality and its
usage. Training will be provided to a maximum of 20 users and a maximum of 5 days session will be
allocated for Business User Training. The training schedule is as follows:
Sr. # Activity Duration Start Date End Date
1 User Training (Financials & SCM) 5 days 18-Mar-13 24-Mar-13
2.5. Training Plan
Project Management Plan Page 9
9
Detailed Monitoring Plan
The Project Management Team is responsible for planning all project activities and ensuring that these
activities are completed within the targeted timeframes. To support this objective, the <VENDOR> Project
Manager will develop and maintain a Detailed Monitoring Plan (DMP), as outlined in Appendix B of this
document. (Work packages will be broken down into activities as project moves on in the DMP)
1. The <VENDOR> Project Manager will regularly update the Detailed Monitoring Plan. Following
each major update, these documents will be communicated to all project team members. 2. It is the responsibility of each functional team leader to communicate the status of activities listed
in the detailed monitoring plan and directly within their area of responsibility back to the <VENDOR> Project Manager.
2.6. Communication and Reporting Plan
Change Management Procedure <VENDOR> will also establish the Change Management Mechanism to be defined in the Project Management Plan. If either Party requires a change to the initial Project scope, their representatives will raise a formal “Change Request”. The change will be referred to as any requirement out of the initial scope of the project. Change request procedure will comprise of following high level activities:
• Written request with clear definition of change following the agreed upon process in place will be initiated by the respective stakeholder
• Duly approved by project manager / or authorized representatives from each party Impact analysis to be conducted by <VENDOR> Project Manager and concerned team (this must include impact upon Scope, Schedule, Budget and Quality)
• Review and approval/rejection of the request based on the Impact Analysis by <VENDOR> team • All changes will be recorded along with serial number
If changes are rejected, reason of rejection and its consequences shall be recorded. If changes are accepted, Project Plan shall be amended in order to accommodate the approved change. Escalation Procedure The following escalation procedure will be followed to:
1. Level 1: If an issue is not resolved to the satisfaction of <CUSTOMER>, it will be escalated to the <VENDOR> Project Manager by the <CUSTOMER> Project Manager.
2. Level 2: If an issue cannot be mutually resolved between the <VENDOR> Project Manager and the <CUSTOMER> Project Manager, it will be raised to the level of Project Director for <VENDOR>.
3. Level 3: If an issue cannot be resolved by the <VENDOR> Project Director, it will be escalated to the <VENDOR> Country Manager and <CUSTOMER> CEO
Acceptance Procedure Deliverable Acceptance Procedure The following procedure will be followed on the submission of deliverable materials:
All Deliverable Materials submitted to <CUSTOMER> by <VENDOR> will be signed off by <CUSTOMER> within three working days from the date of submission. If we did not receive any comments / feedback, it is deemed as accepted. Once observation is rectified it will be considered approved.
Unless written comments or objections are provided for any of the Deliverable Materials within the same duration by <CUSTOMER>, such documents will be deemed to have been signed off and accepted.
Where written comments are received by <VENDOR> within the stipulated timeframe, the <VENDOR> Project Manager shall agree with the <CUSTOMER> Project Manager what corrective actions need to be taken in order for the Deliverable to be deemed acceptable and
Project Management Plan Page 10
10
subject to the agreed changes the <CUSTOMER> team will accept the Deliverable on re-submittal. intervention
Reporting Plan
Each <VENDOR> Track-lead will submit a weekly progress report to the <VENDOR> Project Manager
using the Progress Status Report template shown in Appendix E: Progress Reporting Template
This report will record the:
Status of work performed during the last weeks;
Planned activities that were not achieved;
Planned activities for the coming weeks
Key issues currently being faced and the actions required to resolve these issues;
Progress according to milestones; and Key meetings attended.
Communication Plan Following is the communication plan that would be used by both team to monitor and control the progress of the project and ensure timely delivery of project deliverables:
Type of
Communication
Communication
Schedule
Typical
Communication
Mechanism
Who Initiates Recipient
Status Report Weekly Team meeting Project Managers <CUSTOMER>
Project Manager
Detailed Monitoring
Plan
Weekly Email <VENDOR>
Project Manager
<CUSTOMER> and
<VENDOR> Project
Director
Project Review Bi-weekly Face to face <VENDOR>
Project Manager
<VENDOR> Project
Team
Steering Committee
Meeting
Every three week Members Meeting Project Directors Project Manager
Risk Mitigation
Status
As project
progresses, we
would analyze and
eliminate risk
accordingly.
Email and Personal
meetings
Responsible
team member
Project Managers
Requirement
Changes
As project
progresses, we
would analyze and
eliminate risk
accordingly.
Email and change
control tool
Project Director Project Director
Project Management Plan Page 11
11
Steering Committee Members
S. # Members Role
CEO
CFO
CIO
<CUSTOMER> Project Manager
< VENDOR> Project Manager
<CUCTOMER> Power User
<VENDOR> Project Director
Project Management Plan Page 12
12
2.7. Risk Management Plan
Risks are formally identified by the project management team at the start of the project. Risk is recorded in the Risk/Issue Record Form and listed on the Risk Register. During each subsequent fortnightly project management meeting, the project management team will meet to review the effectiveness of the management of the known risks, to identify any new risks and agree the actions required to mitigate all risks.
At any stage during the course of the project, a project team member can identify a new risk. Following discussion with the project manager, the identifier may be requested to define the risk using the Risk/Issue Record Form presented in Appendix D: Risk and Issue Management Templates
This must be immediately forwarded to the Team Project Manager.
The Project Manager will register the risk on the Risk and Issue Register and assign the next sequential number to the Risk Record Form.
Risks will be formally discussed by the <CUSTOMER> and <VENDOR> project managers at each fortnightly project management meeting or more frequently if necessary. During this meeting each risk will be prioritized by assessing the:
1. Probability of the risk becoming an issue 2. Impact on the success of the project, should the risk become an issue.
Priority H Will require actions to be performed immediately to mitigate the risk
Priority M Will require actions to be performed as soon as possible, typically within 1 week.
Priority L Will not require immediate or urgent action at this stage, but will still require monitoring
Mitigating actions will be agreed by the Project Management Team, assigning a responsible person and a
target date for completing the action. The <VENDOR> Project Manager will record the assigned actions
and their status on the Agreed Action List
The <VENDOR> Project Manager will distribute the Agreed Action List to all project participants following the project management meeting. Each person assigned a responsibility for performing a risk mitigating action (the “responsible person”) will be required to complete the action before the target completion date and communicate the status back to the “Accountable” person.
The responsible person will verify that the action has been completed, and will ensure that the Agreed Action List is updated before the next project management meeting.
The Project Managers will review the risks listed within the Risk & Issue Register and Agreed Action List
on a fortnightly basis to ensure that risks are being managed and that agreed actions have been
completed.
2.8. Issue Resolution Plan
An issue can be noticed by any project team member or stakeholder external to the core project team. All issues must be communicated immediately to the Project Management Team using the Risk/Issue Report Form presented in Appendix D: Risk and Issue Management Templates
The <VENDOR> Project Manager will review the issue and assign it the next available serial number in the Risk and Issue Register and will update the register with the details of the issue.
The Project Managers will meet fortnightly to formally review the project issues, or on an ad-hoc basis depending on the nature and severity of the issue. During these discussions, they will prioritize each issue as follows:
Priority H Will require actions to be performed immediately to mitigate the risk
Project Management Plan Page 13
13
Priority M Will require actions to be performed urgently or as soon as possible,
typically within 1 week.
Priority L Will not require immediate or urgent action at this stage, but will still
require monitoring
Based on the priority of the issue, the project managers will agree on actions that need to be taken and assign accountability and target completion dates to each action.
The <VENDOR> project manager will update the Action List and distribute to all project team members following the fortnightly meeting, or issue specific actions on an ad-hoc basis as necessary.
Each person assigned a responsibility for performing an action (the “responsible person”) will be required to complete the action before the target completion date and communicate the status back to the “accountable person”.
The person accountable will verify that the action has been completed, and will ensure that the Agreed Action List and Issue Register are updated before the next project management meeting. These updates will include capturing:
Change to the status of the action Change to the status or priority of an issue The date the issue was closed and the nature of the resolution
The Project Managers will review the Risk and Issue Register and Agreed Action List on a fortnightly basis to ensure that risks are being managed and that agreed actions have been completed.
2.9. Project Close-Out Plan
The Project Review Meeting (PRM) will be convened by arrangement to review project compliance in an
assessment process for the project closure.
The project manager, project sponsor and the project business stakeholders all attend. The purpose of
the meeting is to:
Close out the project with the sponsor and stakeholders;
Communicate the change in project status to the project sponsor and business stakeholders;
Provide an orderly transition of the product from build to Go-Live; and
<VENDOR> Project Manager will publish an agenda at least one week in advance of the meeting and invite project participants.
<VENDOR> Responsibilities
Ensure the Solution is Deployed on the Production Environment;
Ensure the end-user training is completed;
Lead Final Acceptance Testing during this Phase;
Schedule and conduct Project Implementation Review meeting; and
Prepare for project closure.
<CUSTOMER> Responsibilities
Be actively involved in the Go-Live phase;
Ensure that the provision and data entry of Live Transaction is being done in the system by <CUSTOMER> staff; and
Monitor performance of the implemented solution.
<VENDOR> will provide a Project Closure Report to the <CUSTOMER> team as a result of this activity.
Project Management Plan Page 14
14
Project Close-out Acceptance
This activity will be considered complete when <VENDOR> has delivered all Deliverable in section 1.2
and the solution is accepted by <CUSTOMER> team.
Project Management Plan Page 15
15
Revision History
Name Date Reason for Changes Version
Dec-14 2014 initial draft 1.0
Project Management Plan Page 16
16
Appendix A – Project Plan
Project Management Plan Page 17
17
Appendix B – Detailed Monitoring Plan
Project Management Plan Page 18
18
Appendix C – Change Request Form
Completed by: Completed on (date):
Change Request No: Assigned by Project Manager
Change Title:
Source:
Name of individual who
raised the change request
Status:
Raised, Under Review,
Under Analysis, Closed
Priority: H/M/L
Expected response time:
Change description (detailed if possible):
Change Analysis
Prepared by: Prepared on:
Impact of change on the plan and resource requirements:
Expected costs & benefits of implementing the change (narrative) :
List of controlled items affected by the change:
Estimated effort to modify the controlled items:
Estimated Cost
Change decision:
Implement, Postpone, Reject
Decided by: Date:
Justification:
Implementation assigned to:
Project Management Plan Page 19
19
Appendix D – Risk and Issue Management Templates
Risk or Issue? Choice of Risk or Issue Risk ID: Assigned by Project
Manager
Risk Title Priority
Brief Description of Risk Assigned by
Project Manager H,M or L
Background
Describe the background to the risk or issue
Risk Description Probability
Describe the risk or issue being faced High
Moderate
Low
Impact if Risk becomes an Issue Impact on 7 Keys Y/N Impact
Describe the consequence of the risk materializing, or the
consequences of the current issue being faced.
Select which of the 7 Keys this is impacting on.
Stakeholders Y/N
High
Moderate
Low
Business Benefit Y/N
Work Schedule Y/N
Team Y/N
Scope Y/N
Risk Mitigation Y/N
Other Y/N
ID Proposed Actions to Mitigate Risk Date
1 Propose what should be / is being done to mitigate the risk or resolve the issue,
indicating the date before which it should be completed
2
Risk Control Record
Track:
Raised by: Date:
Accepted by: Date:
Closed by: Date:
Additional
Comments:
Project Management Plan Page 20
20
Risk / Issue
ID Risk / Issue Title Date
Raised Assigned
to Probability Impact Status
Date Closed
Priority
1
2
3
4
5
ID Description of
Action Track
Raise
d by Responsible
Date
Raise
d
Target
Complete
Revise
d Date
Current
Status
Date
Closed
Risk /
Issue Priority Comments
Days
Overdue
1
2
3
4
5
Project Management Plan for <Customer> Page 21
21
Appendix E – Progress Reporting Template
<CUSTOMER> Project Report
Period Covering:
Produced By : <VENDOR> Project Manager
Distribution List
1. Results Last Period
Tasks completed and deliverables produced:
Please find below the accomplishments of the project team during the period specified above and tasks to be accomplished in the following two weeks from XXXXX to XXXXXX
Tasks Completed/Started
* Key, P: prepared, D: Delivered or Conducted, A: Approved, NR: Not required
Status
P D A
Project Management
Oracle Financials
Oracle Supply Chain
Technical
Project Management Plan for <Customer> Page 22
22
2. Planned deliverables next week
Tasks for the next two weeks Planned
Completion Responsibility / Comments
Project Management
Financials
Supply Chain
Technical
3. Issues and risks that can be handled within the project
Issues Identified, Impact & Resolution:
Issues Identified Impact Status Resolution
Issues Register Please refer the attached Risks & Issues Register
Impact: MAJOR, SIGINIFICANT, AND MINOR
4. Progress according to milestones
Overall status:
Milestone Name Baseline
Date
Current
Planned
Date
Actual Date Current
Status
Project Management Plan for <Customer> Page 23
23
5. Key Meetings attended this week
Details of Meetings / Workshop
SL. NO.
Track Process Area Meeting/
Workshop Date
Meeting / Workshop
Status
1
2
3
Project Management Plan for <Customer> Page 24
24
Appendix F – Meeting Minutes Template
Meeting Details
Objective:
Date: Time:
Location: Track:
Participants:
<CUSTOMER> Participants <VENDOR> Participants
Name Role Name Role
Objectives:
Meeting Agenda:
Item Topic Start Time Duration
1
2
3
End Time:
Project Management Plan for <Customer> Page 25
25
Meeting Minutes
No Discussion Topic / Key Decisions made Responsibility
1
2
3
Agreed Actions:
No. Description of Action Responsibility Completion Date
1
2
3
Other Notes:
Attachments: