![Page 1: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/1.jpg)
American PropertyDevelopment Corporation
Project Management Procurement Procedures
![Page 2: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/2.jpg)
Strategy for Failure
No procurement or contract strategy plan has in place.
When procurement or contract strategies was used, the plans was substandard making the project a failure.
Inferior procurement and contract strategy plans used. Projects were finished after completion date, costing the company millions.
Failures were commonplace due to the lack of a proper procurement procedures, as each division ran the projects how it wanted.
The following presentation will highlight what the company needs to do to follow a path to success and streamline the procurement and contract strategy processes for APDC to increase revenues and decrease failures.
Reasons for Previous Failures
![Page 3: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/3.jpg)
Overview
The value of the procurement professional to an organization is enhanced by:
Understanding the project management process.
Utilization of specific procurement tools at specific steps during the project life cycle.
These steps include Negotiation, Solicitation Methods, Cost/Price Analysis and Total Cost of Ownership
An understanding of the benefit of integrating the procurement tools, as opposed to having the procurement process occur in isolation, i.e., the project manager and the procurement professional working in “silos”. (Hairston 2005)
Role of the
Project Manager
in relation to
Procurement
![Page 4: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/4.jpg)
The Five Steps of the Procurement Process
Select Supplier
Produce Agreement
Administer Daily
Assess Performance
Procurement Chart
![Page 5: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/5.jpg)
Project Management Process
Initiation
Planning
Closeout
![Page 6: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/6.jpg)
Desktop Scheduling Tool
Linked
Fast
Integrated
![Page 7: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/7.jpg)
Lean Solutions
Achievable ROI
Reduce Cycle Time
Increased Profitability and Quality
![Page 8: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/8.jpg)
Roles and Responsibilities
Team Project Manager
Project TeamMembers
Project Sponsor
Proposal Team
Selection Committee
Customer
CustomerReps
Final Customer Decision Maker
![Page 9: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/9.jpg)
Discussion Points
There is commonality between the processes and there is a need for both processes. (Parker 1998)
In the execution of a project, procurement value comes from understanding.
![Page 10: Project Management Procurement Procedures. Strategy for Failure No procurement or contract strategy plan has in place. When procurement or contract](https://reader036.vdocuments.net/reader036/viewer/2022082518/56649e765503460f94b77fed/html5/thumbnails/10.jpg)
References
Hairston, Robert J. (2005) Integrating Procurement & Project Management, retrieved from the worldwide web on January 19, 2009 from www.ism.ws/files/pubs/proceedings/behairston.pdfProject Management Handbook, Project Management Institute/Jossey-Bass Publishers, 1998
Glenn M. Parker, Cross-Functional Teams, Jossey-Bass Publishers, 1994 J. Davidson Frame, Managing Projects in Organizations, Jossey-Bass
Publishers, 1995 Jack R. Meredith/Samuel J. Mantel, Jr, Project Management: A
Managerial Approach, JohnWiley & Sons, Inc., 2000
A Guide to the Project Management Body of Knowledge (PMBOK Guide), Project
Management Institute, 2000 Joseph L. Cavinato, Ralph G. Kauffman, The Purchasing Handbook 6th
Edition, 1999 Guiding Successful Six Sigma Projects, Oriel Incorporated, 2002