project management professional (pmp_) mps-unascapacitalumno2
TRANSCRIPT
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
1/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
2/184
30-Jan-
Subprojects
An independently manageable component of an existing project.
Can have smaller subprojects.
Subprojects can be contracted:
External enterprise.
Another functional unit in the organization.
Example: Creating interior design for a solar powered car.
Subprojects contracted to vendors:
Designing of seats.
Air-conditioning system.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
Project Management
The application ofknowledge, skills, tools, and techniques to
project activities to meet project requirements. (According to the PMI)
Managing projects typically involves:
1. Scheduling.
2. Identifying requirements.
3. Establishing objectives.
4. Balancing quality, scope, time, and cost.
5. Addressing the concerns and expectations of the
stakeholders.
Example: Project manager responsibilities include:
Communicate cross-functionally.
Managepeople who do not report directly.
Deliver the work on time, within specified budget and quality specifications.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
3/184
30-Jan-
Programs and Portfol ios
A group of relatedprojects that have a common objective.
Offergreat control over constituent projects and deliver benefitsthat the organization can use to meet its goals.
Lesson 1 - Topic A: Identify Project Management Processes
Portfolio
A collection ofprojects, programs, and other workto achieve the strategic
business objectives of an organization.
Generally managed by a senior manager or senior management teams.
Programs
Ing. Moises Palomino Suarez
Project M anagement Offi ce (PMO)
A centralized, permanent, ongoing administrative unit of a
department that serves to improveproject management performancewithin an organization.
Example: Newspaper chain needs to decrease costs.
PMO introduced standardized processes for:A)Calculating, leveling, loading, and developingproject budgets.
B)Updatingproject schedules.
C)Developingproject data references.
D)Organizingbest practices sharing sessions.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
4/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
5/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
6/184
30-Jan-
Project Management Processes
All the activities that underlie the effective practice of projectmanagement.
Producesproject and product deliverables.
The project management processes
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
Project Management I nputs, Tools and Techni ques, and
Outputs
The relationship between project management inputs, tools and techniques, and outputs
Project management processes are implemented through inputs, tools and
techniques, and outputs.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
7/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
8/184
30-Jan-
Enterpri se Envi ronmental Factors
Internal or external factors.
Havepositive or negative influence on projects. Support or limit the project management options.
Examples include:
Organizational culture.
The human resources pool.
Marketplace conditions.
Stakeholder risk tolerances.
Political situations.
Project management information systems.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
Organizational Process Assets
Assets that influence project success.
Examples include:
Policies.
Procedures.
Guidelines.
Formal and informal plans.
Lessons learned documents.
Historical information.
Completed schedules.
Earned value data.
Risk data.
Two categories of organizational process assets:
Processes and procedures.
Corporate knowledge base.
Lesson 1 - Topic A: Identify Project Management Processes
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
9/184
30-Jan-
Interpersonal Skills
Ability to work harmoniously and efficiently.
Interpersonal skills include:
Leadership.
Team building.
Motivation.
Communication.
Influencing.
Decision making.
Political and cultural awareness - Ccia.
Negotiation.
Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager
Ing. Moises Palomino Suarez
Leadership Skills Ability to guide and inspire others to achieve results.
Ability to lead include:
Learning from one's mistakes.
Building relationships.
Taking initiatives.
Inspiring others through positive influence.
Establish rapport, enhance credibility, and gain others' trust.
Leadership capabilities are critical at the beginning of a project or phase.
Effectively communicate the vision.
Motivate and inspire team members for higher project performance.
Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager
Ing. Moises Palomino Suarez
http://images.google.com/imgres?imgurl=http://amphetamines.com/president-kennedy.jpg&imgrefurl=http://www.amphetamines.com/john-kennedy.html&usg=__YiAATcT8o8DTSR8frECIJDrr8_g=&h=472&w=614&sz=15&hl=en&start=8&um=1&tbnid=CaZykpSHsNheaM:&tbnh=105&tbnw=136&prev=/images?q=kennedy&hl=en&sa=N&um=1http://images.google.com/imgres?imgurl=http://amphetamines.com/president-kennedy.jpg&imgrefurl=http://www.amphetamines.com/john-kennedy.html&usg=__YiAATcT8o8DTSR8frECIJDrr8_g=&h=472&w=614&sz=15&hl=en&start=8&um=1&tbnid=CaZykpSHsNheaM:&tbnh=105&tbnw=136&prev=/images?q=kennedy&hl=en&sa=N&um=1 -
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
10/184
30-Jan-
Communication Skil ls
Ensure everyone is kept informed, knows exactly what to do, and has all of
the information to do their jobs. Clear expression of ideas.
Effective communication is the ability to:
Motivate.
Delegate.
Organize.
Solve problems.
Obtain information.
Use effective listening techniques to:
Manage conflicts. Take appropriate decisions.
Provide suitable solutions.
Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager
Ing. Moises Palomino Suarez
Decision Making Skil ls
Decisions are the result of collaboration and negotiation.
Establish credibility to affect the decision-making process.
Employ sound decision making skills.
Engage in active collaboration.
Foster critical thinking when interacting with project team.
Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
11/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
12/184
30-Jan-
The Project Management Framework (Cont.)
Knowledge Areas Project Management Process Groups
InitiatingProcess Group
Planning
Process Group
Executing
Process Group
Monitoring &Controlling
Process Group
ClosingProcess Group
Project HumanResourceManagement
Develop Human Resource Plan Acquire Project Team
Develop Project Team
Manage Project Team
ProjectCommunicationsManagement
IdentifyStakeholders
Plan Communicat ions Distribute Informat ion
Manage StakeholderExpectations
ReportPerformance
Project RiskManagement
Plan Risk Management
Identify Risks
Perform Qualitative RiskAnalysis
Perform Quantitative RiskAnalysis
Plan Risk Responses
Monitor andControl Risks
ProjectProcurementManagement
Plan Procurements Conduct Procurements Administer Procurements
CloseProcurements
Lesson 2 - Topic A: Examine the Project Management Context.
Ing. Moises Palomino Suarez
Relationships Among Project, Program, and
Portfolio Management
Projects are generally managed through programs and portfolios.
Projects are at the lowest level, programs in the next level, andportfolios at the top of the hierarchy.
Information flows from higher to lower levels during initial phases and
from lower to higher levels during later phases.
Relationships among individual projects and programs and portfolios
are interrelated with the organizational strategies and priorities.
Lesson 2 - Topic A: Examine the Project Management Context.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
13/184
30-Jan-
Project Selection Criteria
The act of choosing a project from among competing proposals.
Example: Integrating customer and financial databases.
Criteria include:
Links to the strategic goal of increased technological advantage.
Can be produced using only internal resources.
Meets goal of increasing new sales revenue by 10%.
Lesson 2 - Topic B: Examine Project Selection
Ing. Moises Palomino Suarez
Project Selection Methods
Any systematic approach used to analyze the value of a proposed project
in orderto choose among competing proposals.
Example: Opportunity to implement two new projects but has resources
for only one by the end of a fiscal year.
Prioritization based on:
A. Projected cost analysis.
B. Projected duration analysis.
C. Projected financial benefits analysis.
Lesson 2 - Topic B: Examine Project Selection
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
14/184
30-Jan-
Scoring and Rating Systems
Use mathematical modeling to find the best available solution or outcome.
System Description
Decision tree Selection criteria arranged along the branches of a tree flowchart.
Criteria profiling Project criteria are scored for comparison.
Weighted factor Different criteria may be weighted and scored for comparison
Q-sorting Groups of people rate the relative priority of a number of projects.
Delphi technique Experts are located remotely and remain anonymous, yet participate ingroup decision making. Consensus is achieved through group ranking.
Lesson 2 - Topic B: Examine Project Selection
Ing. Moises Palomino Suarez
Feasibility Analysis An analysis that provides technical and operational data to management to
make a decision about project selection.
Includes:
Problem description.
Summary of historical data.
Evaluation of available technologies.
Evaluation of organizations technical capabilities.
Cost and time estimates.
Assumptions and constraints. Recommendations.
Statement of project goals and milestones.
Lesson 2 - Topic B: Examine Project Selection
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
15/184
30-Jan-
Cost-Benefit Analysis
A comparison ofthe estimated costs versus the predicted benefits of a
project. Helps decision makers make informed choices about project selection.
Example: Increased e-commerce capability for retail organization.
The rough cost estimates are:
Predicted cost = $25K in the next five years.
Predicted increase in sales: 5% of $1 million = $50K.
Predicted net benefit = $25K.
Lesson 2 - Topic B: Examine Project Selection
Ing. Moises Palomino Suarez
A document that:
Describes the products or services that the project will supply.
Defines the business need that it is designed to meet.
Specifies the work that will be done during the project.
Project statement of work for the OGC PM Training Roll-Out project
Lesson 2 - Topic C: Prepare a Project Statement of Work.
Project Statements of Work (SOW)
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
16/184
30-Jan-
Business Requirements
Pressing organizational needs or market stimuli that drive decision makers
to sponsor projects and to prioritize competing projects.
Example: Business forces.
Business requirements may include forces such as:
Market demands
Organizational needs
Customer requests
Technological advances
Legal requirements
Social needs
Lesson 2 - Topic C: Prepare a Project Statement of Work.
Ing. Moises Palomino Suarez
How to Prepare a Project Statement of WorkGuidelines
Review the product description.
Consult technical experts.
Determine appropriate SOW format.
Present the information in a logical sequence.
Use consistent terminology and level of detail throughout the SOW.
Determine if collateral services are required.
Determine the acceptable criteria.
Make sure the SOW includes key elements such as resource requirements /
estimated hours of work.
Ensure that the SOW is complete, correct, and understandable.
Lesson 2 - Topic C: Prepare a Project Statement of Work.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
17/184
30-Jan-
A document that provides a clear, concise description of the
business needs that the project is intended to address.
Project charter for the OGC PM Training Roll-Out project
Lesson 2 - Topic D: Create a Project Charter.
Project Charter
Ing. Moises Palomino Suarez
The Develop Project Charter Process
Helps formally launch and authorize a new project or to authorize an existing
project to continue into its next phase.
Lesson 2 - Topic D: Create a Project Charter.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
18/184
30-Jan-
Business Case
A document that:
A. Justifies investments ($) made for a project.B. Describes how a particular investment is in accordance to the
organization's policy.
Example: Business case for a geothermal energy project.
The business case includes:
I. Technical, investment, and regulatory factors influencing the project.
II. Cost estimates to justify the investments made for the project.
Lesson 2 - Topic D: Create a Project Charter.
Ing. Moises Palomino Suarez
Business Case Components
System Description
Business need Substantiates ( ) the business reason for conducting the project.
Project contribution Determines the project's contribution toward (->)the organization'sobjectives.
Stakeholders Lists the project stakeholders, their expectations, and contribution towardthe project.
Constraints Compiles the limitations of the project.
Strategic risks Lists the risks that the project may face and the possible risk managementmeasures.
Benefits evaluation Analyzes and outlines the key benefits to be obtained.
Project roles Lists the members of the project team and their respective job roles in theproject.
Benefits realization plan Provides an outline of the benefits realization plan.
Contingency plan Outlines the alternate solutions for unplanned accidents.
Lesson 2 - Topic D: Create a Project Charter.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
19/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
20/184
30-Jan-
Stakeholder Analysis
The formal process ofidentifying all of the stakeholders of a project.
The stakeholder analysis process
Lesson 2 - Topic E: Identify Project Stakeholders.
Ing. Moises Palomino Suarez
Stakeholder Register A document that identifies stakeholders of a project with information that
includes their identification, assessment, and stakeholder classification.
Stakeholder register for the OGC PM Training Roll-Out project
Lesson 2 - Topic E: Identify Project Stakeholders.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
21/184
30-Jan-
The Stakeholder Analysis Matrix
A document that describes the strategies to manage the stakeholders of a
project.
A template for the stakeholder analysis matrix
Stakeholder Stakeholder Interest(s) Assessment of Impact Potential Strategies
Lesson 2 - Topic E: Identify Project Stakeholders.
Stakeholder Management Strategy
A management strategy that is created to ensure maximum support and to
minimize the negative impacts of stakeholders throughout the entire project
life cycle.
A typical stakeholder management strategy document can include:
Stakeholder identification.
Stakeholder map.
Stakeholder analysis influence and importance matrix.
Stakeholder list.
Stakeholder communication. Communication efficiency.
Lesson 2 - Topic E: Identify Project Stakeholders.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
22/184
30-Jan-
Lesson 3: Planning Project Work
Topic A: Identify the Elements of a ProjectManagement Plan
Topic B: Document Stakeholder Requirements
Topic C: Create a Scope Statement
Topic D: Develop a Work Breakdown Structure (WBS)
Ing. Moises Palomino Suarez
Project Management Framework
Knowledge Areas
Project Management Process Groups
Initiating Process
Group
Planning
Process Group
Executing
Process Group
Monitoring &
Controlling Process
Group
Closing Process
Group
Project IntegrationManagement
Develop Project
Charter
Develop Project
Management Plan
Direct and Manage
Project Execution
Monitor and Control
Project Work
Perform Integrated
Change Control
Close Project or
Phase
Project ScopeManagement
Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Project TimeManagement
Define ActivitiesSequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
Control Schedule
Project CostManagement
Estimate Costs
Determine BudgetControl Costs
Project QualityManagement Plan Quality
Perform Quality
Assurance
Perform Quality
Control
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
23/184
30-Jan-
Project Management Framework (Cont.)
Project Management Process Groups
ProjectProcurementManagement
Project RiskManagement
ProjectCommunicationsManagement
Project HumanResourceManagement
Knowledge Areas
Monitor and
Control Risks
Plan Risk Management
Identify Risks
Perform Qualitative Risk
Analysis
Perform Quantitative Risk
Analysis
Plan Risk Responses
Report
Performance
Distribute Information
Manage Stakeholder
Expectations
Plan CommunicationsIdentify
Stakeholders
Acquire Project Team
Develop Project Team
Manage Project Team
Develop Human Resource Plan
Administer
Procurements
Monitoring &Controlling
Process Group
Plan Procurements
Planning
Process Group
Conduct Procurements
Executing
Process Group
InitiatingProcess Group
Close
Procurements
ClosingProcess Group
Ing. Moises Palomino Suarez
Includes:
Processes, tools, techniques, tasks.
Change and configuration management plans.
Performance measurement baselines.
Stakeholder communication.
Project life cycle.
Plan for issues. (??)
Example: Supermarket chain Processes and tools for reducing checkout line time.
Hiring, checkout expansion, change control board.
Manager meetings, plan for open issues.
Cost management plan, quality assurance management plan.
Lesson 3 - Topic A: Identify the Elements of a Project Management Plan.
The Project Management Plan
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
24/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
25/184
30-Jan-
The Collect Requi rements Process
Project manager defines and documents the stakeholders' needs
and expectations to meet project objectives.
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
Facil i tated Workshops
Are group sessions that:
Bring together key multidisciplinary or cross functional stakeholders.
Define the project or product requirements for the project.
Example: Conducting facilitated workshops for OGC's Warehouse
Management Software project.
Stakeholders include:
Staff of the Process Development and Implementation department.
Key project managers. Administration personnel.
Key PMO staff.
Chief of the Business Transformation team.
Discussions highlight the stakeholder differences.
Enables reconciliation of the stakeholder differences.
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
26/184
30-Jan-
Requirements Documentation
Describes how individual requirements meet the business
requirements of the project. The requirements documented must be:
Unambiguous
Traceable
Complete
Consistent
Acceptable to key stakeholders
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
Requirements Documentation (Cont.)
A sample requirements documentation
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
27/184
30-Jan-
Requirements Management Plans
A plan that describes how the project requirements throughout the
project life cycle will be: Analyzed.
Documented.
Managed.
Phase-to-phase relationships between various phases strongly
influence how requirements are managed.
Components of the plan include:
Methods to plan, track, and report requirement activities.
Configuration management related activities.
Process for requirements prioritization.
Project or product related metrics. Traceability matrix for requirements.
Example: Requirements management plan for OGC's Warehouse
Management Software project.
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
The Requir ements Traceabili ty Matrix
A tabular document that links the project or product requirements to
their origin and traces them throughout the project life cycle.
Links each requirement to the:
Business and project objectives.
WBS.
Product design and development.
Test scenarios.
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
28/184
30-Jan-
The Requir ements Traceabili ty Matrix (Cont.)
A sample requirements traceability matrix
Lesson 3 - Topic B: Document Stakeholder Requirements.
Ing. Moises Palomino Suarez
The Proj ect Scope Statement
Defines the project and what it does and does not need to accomplish.
Created at an early stage in the project.
Reflects the stakeholders common understanding of major activities
to be performed.
Typically includes:
Project objectives, deliverables, and requirements.
Project constraints and assumptions.
Product acceptance criteria.
Lesson 3 - Topic C: Create a Scope Statement.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
29/184
30-Jan-
The Project Scope Statement (Cont.)
A sample project scope statement
Lesson 3 - Topic C: Create a Scope Statement.
Ing. Moises Palomino Suarez
Components of the Scope Statement
Content Description
Project objectives The measurable success criteria for the project.
Product descriptionThe characteristics of the product, service, or result of the project
undertaken.
Project requirements The conditions or capabilities the deliverables of the project must meet.
Project deliverablesAny tangible, measurable result or outcome required to complete a
project or portion of a project.
Project boundaries The parameters of what is and what is not included within a project.
Product acceptance
criteria
The process and criteria for accepting finished products or services
resulting from a project.
Project constraints Factors that limit the way that the project can be approached.
Project assumptionsStatements that must be taken to be true in order for the planning to
begin.
Lesson 3 - Topic C: Create a Scope Statement.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
30/184
30-Jan-
3
The Define Scope Process
The project manager defines the scope of the project and finalizes a
project scope statement. Scope definitions are shaped (part) by the deliverables, assumptions, and
constraints that are documented during project initiation.
Lesson 3 - Topic C: Create a Scope Statement.
Ing. Moises Palomino Suarez
Techniques for Al ternatives Identi fi cation
Methods for generating as many alternative solutions and plans as
possible during project planning.
Technique Description
Lateral thinkingA creative approach to problem solving in which the team attempts to think
about a problem in new ways and generate a fresh solution.
Brainstorming
A general creativity technique for generating possible alternatives. The goal
is to generate as many ideas as possible from as many team members aspossible.
Delphi techniqueA group technique that extracts and summarizes anonymous group input to
choose among various alternatives.
Lesson 3 - Topic C: Create a Scope Statement.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
31/184
30-Jan-
3
Work Br eakdown Structures (WBS)
Helps to identify deliverables
Subdivides
project
work into
smaller
pieces
Maps to
project
scope
statement
Lesson 3 - Topic D: Develop a Work Breakdown Structure.
Ing. Moises Palomino Suarez
The Create WBS Process
The method of dividing the project deliverables into smaller, more
manageable components.
Helps create a deliverable-oriented hierarchical decomposition of
work to be executed by the project team.
Lesson 3 - Topic D: Develop a Work Breakdown Structure.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
32/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
33/184
30-Jan-
3
Lesson 4: Developing Project
Schedules
Topic A: Create an Activity List
Topic B: Create a Project Schedule Network Diagram
Topic C: Estimate Activity Resources
Topic D: Estimate Duration for Project Activities
Topic E: Develop a Project Schedule
Topic F: Identify the Critical Path
Topic G: Optimize the Project Schedule Topic H: Establish a Schedule Baseline
Ing. Moises Palomino Suarez
The Project Management Framework
Knowledge Areas
Project Management Process Groups
Initiating Process
Group
Planning
Process Group
Executing
Process Group
Monitoring &
Controlling Process
Group
Closing Process
Group
Project IntegrationManagement
Develop Project
Charter
Develop Project
Management Plan
Direct and Manage
Project Execution
Monitor and Control
Project Work
Perform Integrated
Change Control
Close Project or
Phase
Project ScopeManagement
Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Project TimeManagement
Define ActivitiesSequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
Control Schedule
Project CostManagement
Estimate Costs
Determine BudgetControl Costs
Project QualityManagement Plan Quality
Perform Quality
Assurance
Perform Quality
Control
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
34/184
30-Jan-
3
The Project Management Framework (Cont.)
Project Management Process Groups
ProjectProcurementManagement
Project RiskManagement
ProjectCommunicationsManagement
Project HumanResourceManagement
Knowledge Areas
Monitor and
Control Risks
Plan Risk Management
Identify Risks
Perform Qualitative Risk
Analysis
Perform Quantitative Risk
Analysis
Plan Risk Responses
Report
Performance
Distribute Information
Manage Stakeholder
Expectations
Plan CommunicationsIdentify
Stakeholders
Acquire Project Team
Develop Project Team
Manage Project Team
Develop Human Resource Plan
Administer
Procurements
Monitoring &Controlling
Process Group
Plan Procurements
Planning
Process Group
Conduct Procurements
Executing
Process Group
InitiatingProcess Group
Close
Procurements
ClosingProcess Group
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
Activ i t ies
Element of project work that requires an action to produce a
deliverable.
Have an expected duration.
Consume budget and/or human resources.
Are named in verb-noun format.
Example: Activities in a company project.
Revise user manual.
Make a sales presentation.
Reserve conference room. Revise user manualExpected duration determined by (whatever)
Verb (Action) Noun (Deliverable)
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
35/184
30-Jan-
3
Work Package
Planned work or deliverables.
Lowest-level component of the work breakdown structure. Cost and schedule can be easily estimated.
A work breakdown structure showing the work packages
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
The 8/80 Rule
A general guideline regarding work packages: they require more
than 8, but fewer than 80, hours of effort to complete.
Helps project managers create work package lists.
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
36/184
30-Jan-
3
The Define Activi ties Process
The process of identifying and documenting specific activities that must be
performed to produce the project's deliverables.
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
How to Defi ne Activi ties
Guidelines
Gather the inputs and materials you need.
Analyze and decompose each work package of the WBS into activities
that will be required to produce the deliverable.
Consult records of similar projects to identify possible activities.
Consult subject matter experts about unfamiliar material.
Evaluate all constraints and assumptions for their possible impact on
activity definition.
Evaluate the activity list, once each work package is decomposed to
activities.
Example: Web design company creating an activity list for design
work package.
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
37/184
30-Jan-
3
Completed WBS Table
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
The Sequence Activities Process
A planning process that involves identifying and documenting interactivity
dependencies among project activities for the purpose of creating the
project schedule.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
38/184
30-Jan-
3
Acti vity Dependencies
A logical relationship that exists between two project activities.
Example: An architects vision for room layouts.
Functionality of the design:
a) Framed structure.
b) Walls, windows, roof.
Structure in place:
a) Reassess the plans.
b) Determine modifications.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
Types of Activi ty Dependencies
Dependency Description
Mandatory Inherent to the work itself and are usually affected by physical constraints.
Discretionary Defined by the project and project management team at their discretion.
External Contingent on inputs from outside the project activit ies.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
39/184
30-Jan-
3
Precedence Relationship
The logical relationship between two activities that describes the
sequence in which the activities should be carried out.
Example: Drywall installation must finish before painting can
begin.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
Precedence Relationship Types
Relationship Description
Finish-to-Start (FS) Activity A must finish before activity B can start.
Finish-to-Finish (FF) Activity A must finish before activity B can finish.
Start-to-Start (SS) Activity A must start before activity B can start.
Start-to-Finish (SF) Activity A must start before activity B can finish.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
40/184
30-Jan-
4
Lag
A delay in the start of a successor activity.
FS relationship with lag
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
Lead
A change in a logical relationship that allows the successor activity
to start before the predecessor activity ends in an FS relationship.
Implemented when a successor activity needs to be accelerated in
order to shorten the overall project schedule.
FS relationship with lead
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
41/184
30-Jan-
4
Project Schedule Network Diagrams
Graphical representation of the sequence of project activities and the
dependencies among them. Read from left to right or top to bottom.
May include the entire project or specific parts of it.
A project schedule network diagram
Lesson 4 - Topic A: Create an Activity List.
Ing. Moises Palomino Suarez
Precedence Diagramming M ethod (PDM )
Produces a project schedule network diagram that uses rectangular boxes,
or nodes, to represent activities and arrows to represent precedence
relationships between activities.
Characteristics:
Reads from left to right.
Shows duration in nodes.
Created manually or with software.
Report a group of related activities as an aggregate activity.
Use all precedence relationship types.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
42/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
43/184
30-Jan-
4
How to Create a Project Schedule Network
Diagram
To create a PDM project schedule network diagram:
Determine the dependencies among project activities using youractivity list and product descriptions.
Identify predecessor and successor activities.
Create nodes for all activities with no predecessor activities or
dependencies.
Create nodes for all activities that are successor activities.
Draw arrows from the predecessor activities to the successor activities.
Continue drawing the network diagram, working from left to right until all
activities are included on the diagram and the precedence relationships are
indicated by arrows.
Include any known lags or leads.
Verify the accuracy of your diagram.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
Completed Network Diagram
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
44/184
30-Jan-
4
Project Resources
Any useful material object or person needed for project completion.
Include labor, materials, facilities, equipment, consultants, services,supplies, and utilities.
Example: Resources for a health and wellness seminar project.
Conference room.
Brochures, pamphlets, other materials.
Visiting consultants.
Vendors.
Lesson 4 - Topic B: Create a Project Schedule Network Diagram.
Ing. Moises Palomino Suarez
The Estimate Activity Resources Process
Involves determining specific resources necessary for completing project
activities.
Lesson 4 - Topic C: Estimate Activity Resources.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
45/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
46/184
30-Jan-
4
How to Est im ate Act iv i ty Resourc es
Guidelines
Determine what resources are necessary.
Determine what quantity of resources are necessary.
Generate possible alternatives for unavailable resources.
Analyze the scope statement to ensure youve identified all the
resources.
Consider organizational policies that could affect resource acquisition
and usage.
Identify and use expert judgement resources.
Analyze the resources already available.
Lesson 4 - Topic C: Estimate Activity Resources.
Ing. Moises Palomino Suarez
The Estimate Acti vity Durations Process
The act of estimating the quantity of work that is required to complete
individual project activities using the available resources.
Lesson 4 - Topic D: Estimate Duration for Project Activities.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
47/184
30-Jan-
4
How to Est imate Durat ion for Project Act iv i t ies
Guidelines
Involve the work package owners.
Consult historical information.
Determine how you want to quantify the work.
Consider resource requirements and capabilities.
Determine the appropriate estimation method to use.
Modify the constraints and assumptions from the other planning
processes.
Verify the accuracy of your estimates.
Consider the need for reserve time.
Example: Activity estimates for creating website include design work,
resources, and work units.
Lesson 4 - Topic D: Estimate Duration for Project Activities.
Ing. Moises Palomino Suarez
Project Schedules
The plan for starting and finishing activities on specific dates and in
a certain sequence.
Used to:
Coordinate activities into a master plan.
Track schedule performance.
A project schedule for a website design project (deliverable categories in bold)
Lesson 4 - Topic E: Develop a Project Schedule.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
48/184
30-Jan-
4
The Develop Schedule Process
The act of defining specific start and end dates for each project activity.
Lesson 4 - Topic E: Develop a Project Schedule.
Ing. Moises Palomino Suarez
Standard Schedule Diagramming Notations
Relationship Description
ES Early start. The earliest time an activity can s tart.
EF Early finish. The earliest time an act ivity can finish.
LF Late finish. The latest time an activity can finish.
LS Late start. The latest time an activity can start.
DUDuration. The number of work periods required for
completion of an activity.
Lesson 4 - Topic E: Develop a Project Schedule.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
49/184
30-Jan-
4
The Crit ical Path
Path with the longest total duration.
Has no scheduling flexibility.
1[6W] + 2[4W] + 4[3w] + 6[1W] = 14 Weeks
1[6W] + 3[5W] + 5[4w] + 6[1W] = 16 Weeks Critical Path
A network diagram showing the critical path of activities
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Schedule Netwo rk Analysis
Technique used to calculate the theoretical early and late start and
finish dates for all project activities.
Four methods:
Critical Path Method (CPM).
Critical chain method.
What-if scenario.
Resource leveling.
Example: A marketing campaign schedule.
Involves:
Using software to create request for proposals.
Launching campaign.
Estimating slack.
Adjusting activities.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
50/184
30-Jan-
5
The Crit ical Path Method (CPM)
A schedule network analysis method.
Uses sequential finish-to-start network logic. Calculates one early and late start and finish dates for each activity.
Uses a single duration estimate.
Critical path method involves calculating one early and late start and finish date for each activity
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Schedule Formats
Bar chart:
Shows start and end dates, duration, order.
Can show precedence relationships.
Can show percentage completion; actual progress.
Used to present project status to management.
A bar chart
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
51/184
30-Jan-
5
Schedule Formats (Cont.)
Milestone chart:
Provides summary level view of projects milestones.
Uses icons or symbols.
Shows the projects overall schedule.
A milestone chart
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Schedule Formats (Cont.)
Project schedule network diagram with dates:
Assigns start and finish dates to activities.
Communicates project status in terms of activity precedence relationships.
A project schedule network diagram with dates
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
52/184
30-Jan-
5
How to Develop a Project Schedule
To develop a draft project schedule:
Perform a mathematical analysis to determine the time periodswithin which activities could be scheduled once resource limits and
other known constraints are applied.
Evaluate the possible impact of any constraints and assumptions on
schedule development.
Consider the availability of your resources.
Consult project calendars and assign dates to activities.
Calculate possible project durations under different assumptions
using simulation.
Consider external resource date constraints, if applicable.
Select project management software that best meets the needs andbudget of your project.
Review rough drafts of the schedule with the project team, sponsor,
and customer.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
How to Develop a Project Schedule (Cont.)
To develop a draft project schedule:
Choose the format in which youll publish the schedule.
Distribute the preliminary schedule to all program office personnel,
functional team members, functional management, and the
customer or sponsor to obtain approval.
Following approval, baseline the schedule and distribute to the
team.
Example: Mathematical analysis to determine project schedulingactivities.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
53/184
30-Jan-
5
Completed Project Schedule
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Criti cal Activities
The activities on the critical path.
Have ES = LS and EF = LF.
Critical activities in a project
Critical Activities:
A, B, F, G, H
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
54/184
30-Jan-
5
How to Identi fy the Cri tical Path
To identify the critical path for a project with FS relationships:
1. Conduct a forward pass to determine ES and EF times for each activity.2. Perform a backward pass to determine LS and LF times for each.
3. Calculate float.
4. Identify the critical path as the path with the longest total duration and zero
float.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Schedule Compress ion
The shortening of the project schedule without affecting the project
scope.
Two methods:
Fast-tracking
Crashing
Example: Schedule compression for building and installing cabinets.
Involves carpenter and sub-contractor.
Sub-contractor installs cabinets while carpenter builds.
Changes precedence.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
55/184
30-Jan-
5
Fast-Tracking
The process of compressing total project duration.
Perform sequential activities concurrently.
Example: Fast-tracking activities for launching a new product.
Product and user manual developed concurrently.
Project duration shortened.
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
Crashing
Analyzes cost and schedule trade-offs to determine how to obtain
the greatest amount of schedule compression for the least
incremental cost.
Involves allocating more resources to activities on the critical path.
Crash costs of a website project
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
56/184
30-Jan-
5
Crash Cost Plott ing Metho ds
Techniques for analyzing the crash costs through a graph or visual
representation.
Crash costs plotted on a graph
Lesson 4 - Topic F: Identify the Critical Path.
Ing. Moises Palomino Suarez
How to Optimi ze the Project Schedule
To compress the project schedule:
1. Consider your resource leveling options.
2. Consider fast-tracking the project.
3. Analyze activities on the critical path to determine if crashing the schedulewill produce a viable option.
4. Analyze each activity on the critical path to determine whether reducingscope is a viable option for reducing duration.
5. Recalculate the critical path after compressing the schedule.
6. Review any schedule changes with key stakeholders.
7. Revise the schedule and distribute to the team.
Example: Optimizing the schedule of a website design project.
Involves:
Drafting schedule compressed one week.
Analyzing critical path.
Fast-tracking activities.
Lesson 4 - Topic G: Optimize the Project Schedule.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
57/184
30-Jan-
5
Criti cal Path Activity
Lesson 4 - Topic G: Optimize the Project Schedule.
Ing. Moises Palomino Suarez
Calculated Crash Costs Per Week
Lesson 4 - Topic G: Optimize the Project Schedule.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
58/184
30-Jan-
5
Completed Crash Plot
Lesson 4 - Topic G: Optimize the Project Schedule.
Ing. Moises Palomino Suarez
Schedule Basel ines
The management-approved version of the project schedule.
Drawn from the schedule network analysis.
Provides basis for measuring and reporting schedule performance.
A chart showing a schedule baseline
Lesson 4 - Topic H: Establish a Schedule Baseline.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
59/184
30-Jan-
5
Lesson 5: Developing Cost Estimates
and Budgets
Topic A: Estimate Project Costs
Topic B: Estimate the Cost Baseline
Topic C: Reconcile Funding and Costs
Ing. Moises Palomino Suarez
The Project Management Framework
Knowledge Areas
Project Management Process Groups
Initiating Process
Group
Planning
Process Group
Executing
Process Group
Monitoring &
Controlling Process
Group
Closing Process
Group
Project IntegrationManagement
Develop Project
Charter
Develop Project
Management Plan
Direct and Manage
Project Execution
Monitor and Control
Project Work
Perform Integrated
Change Control
Close Project or
Phase
Project ScopeManagement
Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Project TimeManagement
Define ActivitiesSequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
Control Schedule
Project CostManagement
Estimate Costs
Determine BudgetControl Costs
Project QualityManagement Plan Quality
Perform Quality
Assurance
Perform Quality
Control
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
60/184
30-Jan-
The Project Management Framework (Cont.)
Project Management Process Groups
ProjectProcurementManagement
Project RiskManagement
ProjectCommunicationsManagement
Project HumanResourceManagement
Knowledge Areas
Monitor and
Control Risks
Plan Risk Management
Identify Risks
Perform Qualitative Risk
Analysis
Perform Quantitative Risk
Analysis
Plan Risk Responses
Report
Performance
Distribute Information
Manage Stakeholder
Expectations
Plan CommunicationsIdentify
Stakeholders
Acquire Project Team
Develop Project Team
Manage Project Team
Develop Human Resource Plan
Administer
Procurements
Monitoring &Controlling
Process Group
Plan Procurements
Planning
Process Group
Conduct Procurements
Executing
Process Group
InitiatingProcess Group
Close
Procurements
ClosingProcess Group
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
The Est imate Costs Process
The process of projecting the total expenditures necessary for the
completion of your project.
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
61/184
30-Jan-
Common Estimate Types
Type or Level of Accuracy Description or Accuracy Rating
Rough Order of Magnitude
(ROM)
Developed without basis of detailed data and often based on very high level
historical data, expert judgment, or a costing model. Accuracy:
-50 percent to +100 percent.
Budgetary Often used for appropriation purposes. Accuracy: -10 to +25 percent.
Range of estimateOften used as an alternative to ROM where the accuracy of the estimate is
not well known. Accuracy: 35 percent.
Approximate estimateBased on more information than ROM estimates, but still lacks the detail
required for high accuracy. Accuracy: 15 percent.
Definitive estimate (or control
or detailed)
Developed by estimating the cost for each work package in the WBS.
Accuracy: - 5 percent to + 10 percent.
Phased estimate (or rollingwave or moving window) Allows the use of ROM or approximate estimates for some later parts of thework. Accuracy: 5 percent to 15 percent.
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
Analogous Est imat ing
A method of cost estimating.
Managers use experience, historical information, expert judgment.
Determines a total project cost or time estimate.
Apportions total across the major categories of work.
Used when:
Only a limited amount of detailed information is available.
Similar project is available for comparison.
Estimators have appropriate experience.
Example: A web design firm uses analogous estimating to produce
cost and time estimates for new accounts.
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
62/184
30-Jan-
Bottom-Up Estimating
Estimates the cost for each work package.
Estimates are then rolled up or aggregated. Used when:
More detail is available about the work packages.
More accurate estimates are needed.
There is time to invest in making the estimates.
Example: A caterer using the bottom-up estimating technique based on a
detailed WBS for a large corporate event.
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
Parametri c Estimating
A technique used to predict total project costs by using the project's
characteristics in a mathematical model.
Managers do a statistical analysis using historical information
about scope, cost, budget, and duration.
A sample parametric estimating
Lesson 5 - Topic A: Estimate Project Costs.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
63/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
64/184
30-Jan-
The Determine Bu dget Process
The process of allocating the overall cost estimates to individual
activities or work packages across the project life cycle.
Lesson 5 - Topic B: Estimate the Cost Baseline.
Ing. Moises Palomino Suarez
Funding Limit Reconcili ation
A method of adjusting spending, scheduling, and resource allocation
in order to bring expenditures into alignment with budgetary
constraints.
Example: A customer wants to spread project costs over two quarters.
$250,000 during Q1.
$350,000 during Q2.
Q1: $250,000 Q2: $350,000
Lesson 5 - Topic B: Estimate the Cost Baseline.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
65/184
30-Jan-
Cost Assignment Methods
Cost Assignment Method Description
50/50 percent rule50 percent credit is given when the activity begins and 50 percent credit
is given when the work is completed.
Percentage completed ruleCompletion percentages are estimated and assessed at specified reporting
intervals. This is perhaps the most commonly used rule.
Weighted milestones
The total work package value is divided up and assigned to milestone
intervals within the work package. The value is earned when the
milestone is achieved.
Lesson 5 - Topic B: Estimate the Cost Baseline.
Ing. Moises Palomino Suarez
How to Estimate the Cost Basel ine
To estimate a cost baseline:
1. Gather the inputs you will need, such as the WBS, project schedule, cost
estimates, and risk management plan.
2. Determine when activities will be taking place.
3. Allocate funds for each activity or work package for the time period in
which they will be taking place.
4. Consider adding in a contingency amount.
5. Total the costs for each time period.
6. Plot the costs on a chart to create an S-curve of the baseline.
7. Publish and distribute the cost baseline to the appropriate project
stakeholders.
Lesson 5 - Topic B: Estimate the Cost Baseline.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
66/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
67/184
30-Jan-
Topic A: Create a Quality Management Plan
Topic B: Document the Project Roles,
Responsibilities, and Reporting Relationships
Topic C: Create a Communications
Management Plan
Lesson 6: Planning Project Quality, Staffing, and
Communications
Ing. Moises Palomino Suarez
The Project Management Framework
Knowledge Areas
Project Management Process Groups
Initiating Process
Group
Planning
Process Group
Executing
Process Group
Monitoring &
Controlling Process
Group
Closing Process
Group
Project IntegrationManagement
Develop Project
Charter
Develop Project
Management Plan
Direct and Manage
Project Execution
Monitor and Control
Project Work
Perform Integrated
Change Control
Close Project or
Phase
Project ScopeManagement
Collect Requirements
Define Scope
Create WBS
Verify Scope
Control Scope
Project TimeManagement
Define ActivitiesSequence Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop Schedule
Control Schedule
Project CostManagement
Estimate Costs
Determine BudgetControl Costs
Project QualityManagement Plan Quality
Perform Quality
Assurance
Perform Quality
Control
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
68/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
69/184
30-Jan-
Quality Management Plans
Describe for the project stakeholders the teams approach to
implement the quality policy. Outline (esq) how quality control and quality assurance will be
performed.
Example: Clothing manufacturers labor cost reduction.
Quality management plan includes:
How quality control and assurance would be performed.
Who would be responsible for quality control.
How, when, and to what degree they would conduct inspections.
How the team would respond to quality issues.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
The Plan Quality Process The process of putting plans into place to ensure that a project will satisfy
its stated objectives or business needs.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
70/184
30-Jan-
7
Process Improvement Planning
The process of analyzing and identifying areas of improvement inproject processes.
Enumerating an action plan based on the project goals andidentified issues.
Involves: Describing operational theories and project roles and responsibilities.
Identifying long and short-term goals.
Describing process improvement objectives and activities.
Identifying risks and resource requirements.
Determining process improvement activities.
Creating a process improvement plan.
Receiving approval from stakeholders and senior managers. Executing the process improvement plan.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Process Improvement Plan
Describes the steps to analyze and determine areas ofimprovements in project process.
Areas of process improvements include:Process boundaries.
Process configuration.
Process metrics.Targets for improved performance.
Example: Reviewing the existing product testingprocess in a software
development company.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
71/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
72/184
30-Jan-
7
The ISO 9000 Series
A quality system standard that is applicable toany product, service, or process in the world.
Developed by ISO, a consortium ofapproximately 100 of the worlds industrialnations.
Does not guarantee that an organization willproduce quality products or services.
Simply confirms that appropriate systems arein place.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Cost of Quality The total cost of effort needed to achieve an acceptable level of
quality in the projects product or service.
Different types of costs
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
73/184
30-Jan-
7
Checklists
A job aid that prompts employees to perform activities according to
a consistent quality standard.Obtain a printout of the image specifications from the graphics database. Use this
checklist to ensure that the images are ready to be handed off to the programmer.
# Item Y/N
1 Does the image match the description in the database?
2 Does the style meet the specifications for the course or lesson?
3 Does the quality of the image meet the standards set for the course?
4 Is the image size correct?
5 Is the correct border on the image?
6 Is the image in the correct palette?
7 Is the opacity correct (transparent or opaque)?
8 Is the bit-depth correct?
A checklist for printing image
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Flowchart
A diagram that shows the relationships of
various elements in a system or process.
Two flowcharting techniques:
Cause-and-effect diagram.
Process or system flowchart.
Helps identify potential quality problems and
possible effects of the problems.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
74/184
30-Jan-
7
Process Flowchart Shows the sequence of events and flow of inputs and outputs between
elements in a process or system.
Has a definite beginning and end.
A sample process flowchart
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Cause-and-Effect Diagram A diagram that shows the relationships of various elements in a system or
process.
A cause-and-effect diagram
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
75/184
30-Jan-
7
Control Charts
UCL
Indicates Instability
LCL
UCL
LCL
X X
Variability above the upper control limit (UCL)
A graph used to analyze and communicate the variability of a process or
project activity over time. Shows the potential capability of the process.
Suggests the range of variability in the process.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Control Charts (Cont.)
UCL
Indicates Instability
LCL
UCL
LCL
X X
Variability below the lower control limit (LCL)
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
76/184
30-Jan-
7
Benchmarking
A method of addressing the evaluation of a groups business or
project practices in comparison to those of other groups. Used to identify best practices in order to meet or exceed them.
Example: Benchmarking the espresso-based beverages based on
the performance of Seattle-based Starbucks Corp.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
Design of Experiments (DOE) A technique to systematically identify varying levels of independent
variables.
Example: Creating a new style of jar in a cannery.
Creation involves:
Determining the optimum torque size.
Testing torque with spindle speed and conveyor speed.
Determining adjustments to these settings.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
77/184
30-Jan-
7
How to Create a Quality Management PlanGuidelines
Review the organizations quality policy and determine how yourproject team will implement the policy.
Review the product description to identify customer/stakeholderquality requirements.
Determine the cost of quality trade-offs.
Review the quality management plan.
Example: Creating a quality management plan by a project team.
Creation involves: Determining that a quality policy is available.
Assigning roles and responsibilities. Assigning project quality assurance coordinator.
Repeating the design process and peer plan reviews.
Lesson 6 - Topic A: Create a Quality Management Plan.
Ing. Moises Palomino Suarez
The Develop Human Resource Plan Process The process of identifying, documenting, and assigning project roles,
responsibilities, and reporting relationships.
Commonly performed during early project phases.
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
78/184
30-Jan-
7
Organizational Structures
Dictates how the various groups and individuals within an organization
interrelate.
CFO CIO
Department Head
VP HR
Employee
CEO
Employee
Employee
Department Head
Employee Employee
Employee
Department Head
A sample organizational structure
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
Organizational Structure Types
Item Y/N
Functional organization
Each department carries out specific activities.
Reporting is hierarchical.
PMs authority is low, relative to functional manager.
Projectized organization
PM and core project team operate as a separate
unit.
PM has significant authority and independence.
Matrix organization Individuals report upwards and also horizontally.
Composite organization Combination of all other types.
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
79/184
30-Jan-
7
Organization Chart A visual representation of the projects organizational structure.
Clearly assigns project tasks to team members.
A functional organization chart
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
Organization Chart (Cont.)
A projectized organization chart
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
80/184
30-Jan-
8
Organization Chart (Cont.)
A matrix organization chart
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
Relative Authority in Organizational Structures
The project managers authority relative to thefunctional managers authority over the projectand the project team.
Example: Companies with different organizationalstructures.
An auto manufacturing company with functionalorganizational structure and hierarchicalmanagement.
A web design company with projectizedorganizational structure.
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
81/184
30-Jan-
8
Project Interfaces
Various reporting relationships that occurwithin the project as well as the boundaries ofthe project.
Classified as:
Organizational
Technical
Interpersonal
LogisticalPolitical
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
Responsibility Assignment Matrix (RAM) A chart that links key project stakeholders to specific project deliverables or
activities by assigning responsibility to an individual stakeholder for each
element of work.
Project
Manager
Engineering
Manager
Quality
Assurance
Manager
Purchasing
Manager
Manufacturing
Manager
Create Blueprints S A P P
Manufacture
BreadboardS A P P
Test Breadboard S P A P
Order
ComponentsS P P A P
Assemble S P A
S = Sign-off
A = Accountable
P = Participant
A sample Responsibility Assignment Matrix
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
82/184
30-Jan-
8
Staffing Management Plan
Forecast what types of staff will work on the project, when they will
be needed, how they will be recruited onto the project, and whenthey will be released from the project.
Example: Writing a companys 100th anniversary book.
Staffing management plan includes:
External resources.
Internal resources with specialized knowledge.
Who would be needed.
When they would be needed.
What they would contribute.
How long they would participate.
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
Staffing Management Plan Components
Staff acquisition
Timetable
Release criteria
Training needs
Recognition and rewards
Compliance
Safety
Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
83/184
30-Jan-
8
Communications Management Plan
Describes the project teams approach to communicate project
information.
Example: Communications management plan for a companys
annual meeting.
The plan includes:
Regularly scheduled status meetings.
Distribution of the meeting minutes.
Email distribution list.
All stakeholders and resources included on communications.
Lesson 6 - Topic C: Create a Communications Management Plan.
Ing. Moises Palomino Suarez
The Plan Communications Process The process of ensuring timely and appropriate generation, collection,
dissemination, storage, and ultimate disposition of project information.
Lesson 6 - Topic C: Create a Communications Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
84/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
85/184
30-Jan-
8
Communications Technologies
The technologies used for communications planning: websites, email,
instant messaging, phones, video conferencing.
Lesson 6 - Topic C: Create a Communications Management Plan.
Ing. Moises Palomino Suarez
Activity Form Responsible Frecuency Audiency
Team
tracking
Meeting Project Manager Weekly Team work
Project Manager
Analyst
Leader
Program
Leader
User
Expert
Programmers
Board
Analysts
How to Create a Communications Management Plan
Lesson 6 - Topic C: Create a Communications Management Plan.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
86/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
87/184
30-Jan-
8
Knowledge Areas
Project Management Process Groups
InitiatingProcess Group
Planning
Process Group
Executing
Process Group
Monitoring &
ControllingProcess Group
ClosingProcess Group
Project HumanResourceManagement
Develop Human Resource
Plan
Acquire Project Team
Develop Project Team
Manage Project Team
ProjectCommunicationsManagement
Identify
StakeholdersPlan Communications
Distribute
Information
Manage Stakeholder
Expectations
Report
Performance
Project RiskManagement
Plan Risk Management
Identify Risks
Perform Qualitative Risk
Analysis
Perform Quantitative
Risk Analysis
Plan Risk Responses
Monitor and
Control Risks
ProjectProcurementManagement
Plan ProcurementsConduct
Procurements
Administer
Procurements
Close
Procurements
The Project Management Framework (Cont.)
Risks
An uncertain event with positive or negative
impact.
Primary components include:
A measure of probability that the risk event will
occur.
The impact of the risk occurring on a project.
Example: The threat of rain is a risk when
planning an outdoor festival that could
seriously affect attendance and revenue.
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
88/184
30-Jan-
8
High-level process with five sub-phases:
The project risk management process with the five main sub-phases
Project Risk ManagementLesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
Business risk:
Inherent in business.
All projects have potential for loss or profit.
Example: Purchasing inventory without guaranteed sales.
Insurable risk:
Only the potential for loss.
No potential for profit.
Insurance may be purchased to offset losses.
Example: Loss of inventory due to fire.
Business Risk vs. Insurable Risk
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
89/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
90/184
30-Jan-
9
Document that describes the teams approach to
identifying risks. Identifies methodology, approaches, and tools.
Documents roles and responsibilities.
Identifies budgeting and scheduling.
Identifies risk categories.
Example: Entrepreneurs seeking funding from venturecapitalists for building an amusement park.
Risk management plan will include:Losses due to employee theft as business risk.
Liabilities for park ride injuries as insurable risks.
Risk Management Plan
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
The Plan Risk Management ProcessThe process of deciding how to plan and execute
the risk management activities for a project.
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
91/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
92/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
93/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
94/184
30-Jan-
9
Impact Rating Impact Level Definition
1 Very lowIf this risk occurs, the impact on the projects objectives would
be minor and not noticeable outside the project.
3 LowIf this risk occurs, the impact on the projects objectives would
be minor but noticeable to customer or sponsor.
5 Moderate
If this risk occurs, the impact on the projects objectives would
be significant and would create customer or sponsor
dissatisfaction with the project.
7 High
If this risk occurs, the impact on the project would be
significant and would create major customer or sponsor
dissatisfaction. The project would be in jeopardy.
9 Very high If this risk occurs, the impact would be catastrophic.The project would be cancelled.
Impact Scales
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
Type Description
KnownItems that you are aware of and that will affect you, but you have no
control over.
Known-unknown Items that will affect you, although you are not able to predict how orhow much they will affect you.
Unknown-unknown Items beyond your ability to foresee.
Levels of Uncertainty
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
95/184
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
96/184
30-Jan-
9
Classification Description
Risk-averter Not likely to take a risk that is considered a high risk.
Risk-seekerAccepts an uncertain outcome and may be willing to take a high risk
regardless of the consequences.
Risk-neutral Tolerance to risk is proportional to the amount of money at stake.
Levels of Risk Tolerance
Lesson 7 - Topic A: Examine a Risk Management Plan .
Ing. Moises Palomino Suarez
Early warning signs or indications that risk will occur.
External factors include:
Changes in the legislation.
Internal factors include:
Changes in staffing.
Changes in governance.
Changes in funding.
Example: For a documentary program production, a television writers strike
would be a trigger and involves positive and negative risks.
Triggers
Lesson 7 - Topic B: Identify Project Risks and Triggers .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
97/184
30-Jan-
9
The Identify Risks Process
An iterative process of identifying the risksand triggers facing a project.
Lesson 7 - Topic B: Identify Project Risks and Triggers .
Ing. Moises Palomino Suarez
Technique Description
BrainstormingUsed to identify overall project risks or may focus in on the risks
within a particular project segment or work package.
Delphi techniqueGenerates a consensus among project risk experts who
anonymously submit their risk list to a facilitator.
Interviewing
Used to get information from people with a wide experience across
many projects.
Root cause analysisUsed to identify problems, discover the root cause, and develop
corrective actions.
Information-Gathering Techniques
Lesson 7 - Topic B: Identify Project Risks and Triggers .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
98/184
30-Jan-
9
Identifies and categorizes risks, potential risk responses, triggers.
Updated as risk categories change. Risk responses from the initial risk register are used in the risk
response planning process.
Updated risk register is provided to the project team members.
A sample risk register
Risk Registers
Lesson 7 - Topic B: Identify Project Risks and Triggers .
Ing. Moises Palomino Suarez
Risk Category Examples
Technical, quality, or
performance risks
Technical changes.
Changes to industry standards during the project.
Reliance on unproven or complex technology.
Unrealistic performance goals.
Project management risks
Inadequate time and resource allocation.
Ineffective project plan development.
Poor cost estimates.
Organizational risks
Resource conflicts with other projects.
Inadequate project funding.
Inconsistent management support.
External risks
Union issues.
Change of management in customers organization.
Regional security issues.
Risk Categories
Lesson 7 - Topic B: Identify Project Risks and Triggers .
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
99/184
30-Jan-
9
A technique to determine the probability ofoccurrence and the impact of identified risk.
Determine the risk exposure of the project bymultiplying the probability and impact.
Example: An event management companyplanning a jazz concert in a
particular coastal city where there is a threatof bad weather.
Qualitative Risk AnalysisLesson 7 - Topic C: Perform Qualitative Risk Analysis.
Ing. Moises Palomino Suarez
The Perform Qualitative Risk Analysis Process
The process of assessing, ranking, and
prioritizing risks for subsequent analysis.
Lesson 7 - Topic C: Perform Qualitative Risk Analysis.
Ing. Moises Palomino Suarez
-
7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2
100/184
30-Jan-
10
Evaluation of the usefulness of data concerning risk.
Examining data includes: Amount of data available.
Quality of data available.
Source of information.
Legitimacy of data.
Dependability of data. (trusted)
Example: Risk assessment performed for a restaurant chains new site
development.
Risk Data Quality Assessment
Lesson 7 - Topic C: Perform Qualitative Risk Analysis.
Ing. Moises Palomino Suarez
A simplified probability and impact risk rating matrix
Probability and Impact Risk