project management professional (pmp_) mps-unascapacitalumno2

Upload: bryan-cortez

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    1/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    2/184

    30-Jan-

    Subprojects

    An independently manageable component of an existing project.

    Can have smaller subprojects.

    Subprojects can be contracted:

    External enterprise.

    Another functional unit in the organization.

    Example: Creating interior design for a solar powered car.

    Subprojects contracted to vendors:

    Designing of seats.

    Air-conditioning system.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

    Project Management

    The application ofknowledge, skills, tools, and techniques to

    project activities to meet project requirements. (According to the PMI)

    Managing projects typically involves:

    1. Scheduling.

    2. Identifying requirements.

    3. Establishing objectives.

    4. Balancing quality, scope, time, and cost.

    5. Addressing the concerns and expectations of the

    stakeholders.

    Example: Project manager responsibilities include:

    Communicate cross-functionally.

    Managepeople who do not report directly.

    Deliver the work on time, within specified budget and quality specifications.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    3/184

    30-Jan-

    Programs and Portfol ios

    A group of relatedprojects that have a common objective.

    Offergreat control over constituent projects and deliver benefitsthat the organization can use to meet its goals.

    Lesson 1 - Topic A: Identify Project Management Processes

    Portfolio

    A collection ofprojects, programs, and other workto achieve the strategic

    business objectives of an organization.

    Generally managed by a senior manager or senior management teams.

    Programs

    Ing. Moises Palomino Suarez

    Project M anagement Offi ce (PMO)

    A centralized, permanent, ongoing administrative unit of a

    department that serves to improveproject management performancewithin an organization.

    Example: Newspaper chain needs to decrease costs.

    PMO introduced standardized processes for:A)Calculating, leveling, loading, and developingproject budgets.

    B)Updatingproject schedules.

    C)Developingproject data references.

    D)Organizingbest practices sharing sessions.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    4/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    5/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    6/184

    30-Jan-

    Project Management Processes

    All the activities that underlie the effective practice of projectmanagement.

    Producesproject and product deliverables.

    The project management processes

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

    Project Management I nputs, Tools and Techni ques, and

    Outputs

    The relationship between project management inputs, tools and techniques, and outputs

    Project management processes are implemented through inputs, tools and

    techniques, and outputs.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    7/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    8/184

    30-Jan-

    Enterpri se Envi ronmental Factors

    Internal or external factors.

    Havepositive or negative influence on projects. Support or limit the project management options.

    Examples include:

    Organizational culture.

    The human resources pool.

    Marketplace conditions.

    Stakeholder risk tolerances.

    Political situations.

    Project management information systems.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

    Organizational Process Assets

    Assets that influence project success.

    Examples include:

    Policies.

    Procedures.

    Guidelines.

    Formal and informal plans.

    Lessons learned documents.

    Historical information.

    Completed schedules.

    Earned value data.

    Risk data.

    Two categories of organizational process assets:

    Processes and procedures.

    Corporate knowledge base.

    Lesson 1 - Topic A: Identify Project Management Processes

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    9/184

    30-Jan-

    Interpersonal Skills

    Ability to work harmoniously and efficiently.

    Interpersonal skills include:

    Leadership.

    Team building.

    Motivation.

    Communication.

    Influencing.

    Decision making.

    Political and cultural awareness - Ccia.

    Negotiation.

    Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager

    Ing. Moises Palomino Suarez

    Leadership Skills Ability to guide and inspire others to achieve results.

    Ability to lead include:

    Learning from one's mistakes.

    Building relationships.

    Taking initiatives.

    Inspiring others through positive influence.

    Establish rapport, enhance credibility, and gain others' trust.

    Leadership capabilities are critical at the beginning of a project or phase.

    Effectively communicate the vision.

    Motivate and inspire team members for higher project performance.

    Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager

    Ing. Moises Palomino Suarez

    http://images.google.com/imgres?imgurl=http://amphetamines.com/president-kennedy.jpg&imgrefurl=http://www.amphetamines.com/john-kennedy.html&usg=__YiAATcT8o8DTSR8frECIJDrr8_g=&h=472&w=614&sz=15&hl=en&start=8&um=1&tbnid=CaZykpSHsNheaM:&tbnh=105&tbnw=136&prev=/images?q=kennedy&hl=en&sa=N&um=1http://images.google.com/imgres?imgurl=http://amphetamines.com/president-kennedy.jpg&imgrefurl=http://www.amphetamines.com/john-kennedy.html&usg=__YiAATcT8o8DTSR8frECIJDrr8_g=&h=472&w=614&sz=15&hl=en&start=8&um=1&tbnid=CaZykpSHsNheaM:&tbnh=105&tbnw=136&prev=/images?q=kennedy&hl=en&sa=N&um=1
  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    10/184

    30-Jan-

    Communication Skil ls

    Ensure everyone is kept informed, knows exactly what to do, and has all of

    the information to do their jobs. Clear expression of ideas.

    Effective communication is the ability to:

    Motivate.

    Delegate.

    Organize.

    Solve problems.

    Obtain information.

    Use effective listening techniques to:

    Manage conflicts. Take appropriate decisions.

    Provide suitable solutions.

    Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager

    Ing. Moises Palomino Suarez

    Decision Making Skil ls

    Decisions are the result of collaboration and negotiation.

    Establish credibility to affect the decision-making process.

    Employ sound decision making skills.

    Engage in active collaboration.

    Foster critical thinking when interacting with project team.

    Lesson 1 - Topic C: Identify the Interpersonal Skills for a Project Manager

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    11/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    12/184

    30-Jan-

    The Project Management Framework (Cont.)

    Knowledge Areas Project Management Process Groups

    InitiatingProcess Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &Controlling

    Process Group

    ClosingProcess Group

    Project HumanResourceManagement

    Develop Human Resource Plan Acquire Project Team

    Develop Project Team

    Manage Project Team

    ProjectCommunicationsManagement

    IdentifyStakeholders

    Plan Communicat ions Distribute Informat ion

    Manage StakeholderExpectations

    ReportPerformance

    Project RiskManagement

    Plan Risk Management

    Identify Risks

    Perform Qualitative RiskAnalysis

    Perform Quantitative RiskAnalysis

    Plan Risk Responses

    Monitor andControl Risks

    ProjectProcurementManagement

    Plan Procurements Conduct Procurements Administer Procurements

    CloseProcurements

    Lesson 2 - Topic A: Examine the Project Management Context.

    Ing. Moises Palomino Suarez

    Relationships Among Project, Program, and

    Portfolio Management

    Projects are generally managed through programs and portfolios.

    Projects are at the lowest level, programs in the next level, andportfolios at the top of the hierarchy.

    Information flows from higher to lower levels during initial phases and

    from lower to higher levels during later phases.

    Relationships among individual projects and programs and portfolios

    are interrelated with the organizational strategies and priorities.

    Lesson 2 - Topic A: Examine the Project Management Context.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    13/184

    30-Jan-

    Project Selection Criteria

    The act of choosing a project from among competing proposals.

    Example: Integrating customer and financial databases.

    Criteria include:

    Links to the strategic goal of increased technological advantage.

    Can be produced using only internal resources.

    Meets goal of increasing new sales revenue by 10%.

    Lesson 2 - Topic B: Examine Project Selection

    Ing. Moises Palomino Suarez

    Project Selection Methods

    Any systematic approach used to analyze the value of a proposed project

    in orderto choose among competing proposals.

    Example: Opportunity to implement two new projects but has resources

    for only one by the end of a fiscal year.

    Prioritization based on:

    A. Projected cost analysis.

    B. Projected duration analysis.

    C. Projected financial benefits analysis.

    Lesson 2 - Topic B: Examine Project Selection

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    14/184

    30-Jan-

    Scoring and Rating Systems

    Use mathematical modeling to find the best available solution or outcome.

    System Description

    Decision tree Selection criteria arranged along the branches of a tree flowchart.

    Criteria profiling Project criteria are scored for comparison.

    Weighted factor Different criteria may be weighted and scored for comparison

    Q-sorting Groups of people rate the relative priority of a number of projects.

    Delphi technique Experts are located remotely and remain anonymous, yet participate ingroup decision making. Consensus is achieved through group ranking.

    Lesson 2 - Topic B: Examine Project Selection

    Ing. Moises Palomino Suarez

    Feasibility Analysis An analysis that provides technical and operational data to management to

    make a decision about project selection.

    Includes:

    Problem description.

    Summary of historical data.

    Evaluation of available technologies.

    Evaluation of organizations technical capabilities.

    Cost and time estimates.

    Assumptions and constraints. Recommendations.

    Statement of project goals and milestones.

    Lesson 2 - Topic B: Examine Project Selection

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    15/184

    30-Jan-

    Cost-Benefit Analysis

    A comparison ofthe estimated costs versus the predicted benefits of a

    project. Helps decision makers make informed choices about project selection.

    Example: Increased e-commerce capability for retail organization.

    The rough cost estimates are:

    Predicted cost = $25K in the next five years.

    Predicted increase in sales: 5% of $1 million = $50K.

    Predicted net benefit = $25K.

    Lesson 2 - Topic B: Examine Project Selection

    Ing. Moises Palomino Suarez

    A document that:

    Describes the products or services that the project will supply.

    Defines the business need that it is designed to meet.

    Specifies the work that will be done during the project.

    Project statement of work for the OGC PM Training Roll-Out project

    Lesson 2 - Topic C: Prepare a Project Statement of Work.

    Project Statements of Work (SOW)

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    16/184

    30-Jan-

    Business Requirements

    Pressing organizational needs or market stimuli that drive decision makers

    to sponsor projects and to prioritize competing projects.

    Example: Business forces.

    Business requirements may include forces such as:

    Market demands

    Organizational needs

    Customer requests

    Technological advances

    Legal requirements

    Social needs

    Lesson 2 - Topic C: Prepare a Project Statement of Work.

    Ing. Moises Palomino Suarez

    How to Prepare a Project Statement of WorkGuidelines

    Review the product description.

    Consult technical experts.

    Determine appropriate SOW format.

    Present the information in a logical sequence.

    Use consistent terminology and level of detail throughout the SOW.

    Determine if collateral services are required.

    Determine the acceptable criteria.

    Make sure the SOW includes key elements such as resource requirements /

    estimated hours of work.

    Ensure that the SOW is complete, correct, and understandable.

    Lesson 2 - Topic C: Prepare a Project Statement of Work.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    17/184

    30-Jan-

    A document that provides a clear, concise description of the

    business needs that the project is intended to address.

    Project charter for the OGC PM Training Roll-Out project

    Lesson 2 - Topic D: Create a Project Charter.

    Project Charter

    Ing. Moises Palomino Suarez

    The Develop Project Charter Process

    Helps formally launch and authorize a new project or to authorize an existing

    project to continue into its next phase.

    Lesson 2 - Topic D: Create a Project Charter.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    18/184

    30-Jan-

    Business Case

    A document that:

    A. Justifies investments ($) made for a project.B. Describes how a particular investment is in accordance to the

    organization's policy.

    Example: Business case for a geothermal energy project.

    The business case includes:

    I. Technical, investment, and regulatory factors influencing the project.

    II. Cost estimates to justify the investments made for the project.

    Lesson 2 - Topic D: Create a Project Charter.

    Ing. Moises Palomino Suarez

    Business Case Components

    System Description

    Business need Substantiates ( ) the business reason for conducting the project.

    Project contribution Determines the project's contribution toward (->)the organization'sobjectives.

    Stakeholders Lists the project stakeholders, their expectations, and contribution towardthe project.

    Constraints Compiles the limitations of the project.

    Strategic risks Lists the risks that the project may face and the possible risk managementmeasures.

    Benefits evaluation Analyzes and outlines the key benefits to be obtained.

    Project roles Lists the members of the project team and their respective job roles in theproject.

    Benefits realization plan Provides an outline of the benefits realization plan.

    Contingency plan Outlines the alternate solutions for unplanned accidents.

    Lesson 2 - Topic D: Create a Project Charter.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    19/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    20/184

    30-Jan-

    Stakeholder Analysis

    The formal process ofidentifying all of the stakeholders of a project.

    The stakeholder analysis process

    Lesson 2 - Topic E: Identify Project Stakeholders.

    Ing. Moises Palomino Suarez

    Stakeholder Register A document that identifies stakeholders of a project with information that

    includes their identification, assessment, and stakeholder classification.

    Stakeholder register for the OGC PM Training Roll-Out project

    Lesson 2 - Topic E: Identify Project Stakeholders.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    21/184

    30-Jan-

    The Stakeholder Analysis Matrix

    A document that describes the strategies to manage the stakeholders of a

    project.

    A template for the stakeholder analysis matrix

    Stakeholder Stakeholder Interest(s) Assessment of Impact Potential Strategies

    Lesson 2 - Topic E: Identify Project Stakeholders.

    Stakeholder Management Strategy

    A management strategy that is created to ensure maximum support and to

    minimize the negative impacts of stakeholders throughout the entire project

    life cycle.

    A typical stakeholder management strategy document can include:

    Stakeholder identification.

    Stakeholder map.

    Stakeholder analysis influence and importance matrix.

    Stakeholder list.

    Stakeholder communication. Communication efficiency.

    Lesson 2 - Topic E: Identify Project Stakeholders.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    22/184

    30-Jan-

    Lesson 3: Planning Project Work

    Topic A: Identify the Elements of a ProjectManagement Plan

    Topic B: Document Stakeholder Requirements

    Topic C: Create a Scope Statement

    Topic D: Develop a Work Breakdown Structure (WBS)

    Ing. Moises Palomino Suarez

    Project Management Framework

    Knowledge Areas

    Project Management Process Groups

    Initiating Process

    Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &

    Controlling Process

    Group

    Closing Process

    Group

    Project IntegrationManagement

    Develop Project

    Charter

    Develop Project

    Management Plan

    Direct and Manage

    Project Execution

    Monitor and Control

    Project Work

    Perform Integrated

    Change Control

    Close Project or

    Phase

    Project ScopeManagement

    Collect Requirements

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

    Project TimeManagement

    Define ActivitiesSequence Activities

    Estimate Activity

    Resources

    Estimate Activity

    Durations

    Develop Schedule

    Control Schedule

    Project CostManagement

    Estimate Costs

    Determine BudgetControl Costs

    Project QualityManagement Plan Quality

    Perform Quality

    Assurance

    Perform Quality

    Control

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    23/184

    30-Jan-

    Project Management Framework (Cont.)

    Project Management Process Groups

    ProjectProcurementManagement

    Project RiskManagement

    ProjectCommunicationsManagement

    Project HumanResourceManagement

    Knowledge Areas

    Monitor and

    Control Risks

    Plan Risk Management

    Identify Risks

    Perform Qualitative Risk

    Analysis

    Perform Quantitative Risk

    Analysis

    Plan Risk Responses

    Report

    Performance

    Distribute Information

    Manage Stakeholder

    Expectations

    Plan CommunicationsIdentify

    Stakeholders

    Acquire Project Team

    Develop Project Team

    Manage Project Team

    Develop Human Resource Plan

    Administer

    Procurements

    Monitoring &Controlling

    Process Group

    Plan Procurements

    Planning

    Process Group

    Conduct Procurements

    Executing

    Process Group

    InitiatingProcess Group

    Close

    Procurements

    ClosingProcess Group

    Ing. Moises Palomino Suarez

    Includes:

    Processes, tools, techniques, tasks.

    Change and configuration management plans.

    Performance measurement baselines.

    Stakeholder communication.

    Project life cycle.

    Plan for issues. (??)

    Example: Supermarket chain Processes and tools for reducing checkout line time.

    Hiring, checkout expansion, change control board.

    Manager meetings, plan for open issues.

    Cost management plan, quality assurance management plan.

    Lesson 3 - Topic A: Identify the Elements of a Project Management Plan.

    The Project Management Plan

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    24/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    25/184

    30-Jan-

    The Collect Requi rements Process

    Project manager defines and documents the stakeholders' needs

    and expectations to meet project objectives.

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

    Facil i tated Workshops

    Are group sessions that:

    Bring together key multidisciplinary or cross functional stakeholders.

    Define the project or product requirements for the project.

    Example: Conducting facilitated workshops for OGC's Warehouse

    Management Software project.

    Stakeholders include:

    Staff of the Process Development and Implementation department.

    Key project managers. Administration personnel.

    Key PMO staff.

    Chief of the Business Transformation team.

    Discussions highlight the stakeholder differences.

    Enables reconciliation of the stakeholder differences.

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    26/184

    30-Jan-

    Requirements Documentation

    Describes how individual requirements meet the business

    requirements of the project. The requirements documented must be:

    Unambiguous

    Traceable

    Complete

    Consistent

    Acceptable to key stakeholders

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

    Requirements Documentation (Cont.)

    A sample requirements documentation

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    27/184

    30-Jan-

    Requirements Management Plans

    A plan that describes how the project requirements throughout the

    project life cycle will be: Analyzed.

    Documented.

    Managed.

    Phase-to-phase relationships between various phases strongly

    influence how requirements are managed.

    Components of the plan include:

    Methods to plan, track, and report requirement activities.

    Configuration management related activities.

    Process for requirements prioritization.

    Project or product related metrics. Traceability matrix for requirements.

    Example: Requirements management plan for OGC's Warehouse

    Management Software project.

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

    The Requir ements Traceabili ty Matrix

    A tabular document that links the project or product requirements to

    their origin and traces them throughout the project life cycle.

    Links each requirement to the:

    Business and project objectives.

    WBS.

    Product design and development.

    Test scenarios.

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    28/184

    30-Jan-

    The Requir ements Traceabili ty Matrix (Cont.)

    A sample requirements traceability matrix

    Lesson 3 - Topic B: Document Stakeholder Requirements.

    Ing. Moises Palomino Suarez

    The Proj ect Scope Statement

    Defines the project and what it does and does not need to accomplish.

    Created at an early stage in the project.

    Reflects the stakeholders common understanding of major activities

    to be performed.

    Typically includes:

    Project objectives, deliverables, and requirements.

    Project constraints and assumptions.

    Product acceptance criteria.

    Lesson 3 - Topic C: Create a Scope Statement.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    29/184

    30-Jan-

    The Project Scope Statement (Cont.)

    A sample project scope statement

    Lesson 3 - Topic C: Create a Scope Statement.

    Ing. Moises Palomino Suarez

    Components of the Scope Statement

    Content Description

    Project objectives The measurable success criteria for the project.

    Product descriptionThe characteristics of the product, service, or result of the project

    undertaken.

    Project requirements The conditions or capabilities the deliverables of the project must meet.

    Project deliverablesAny tangible, measurable result or outcome required to complete a

    project or portion of a project.

    Project boundaries The parameters of what is and what is not included within a project.

    Product acceptance

    criteria

    The process and criteria for accepting finished products or services

    resulting from a project.

    Project constraints Factors that limit the way that the project can be approached.

    Project assumptionsStatements that must be taken to be true in order for the planning to

    begin.

    Lesson 3 - Topic C: Create a Scope Statement.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    30/184

    30-Jan-

    3

    The Define Scope Process

    The project manager defines the scope of the project and finalizes a

    project scope statement. Scope definitions are shaped (part) by the deliverables, assumptions, and

    constraints that are documented during project initiation.

    Lesson 3 - Topic C: Create a Scope Statement.

    Ing. Moises Palomino Suarez

    Techniques for Al ternatives Identi fi cation

    Methods for generating as many alternative solutions and plans as

    possible during project planning.

    Technique Description

    Lateral thinkingA creative approach to problem solving in which the team attempts to think

    about a problem in new ways and generate a fresh solution.

    Brainstorming

    A general creativity technique for generating possible alternatives. The goal

    is to generate as many ideas as possible from as many team members aspossible.

    Delphi techniqueA group technique that extracts and summarizes anonymous group input to

    choose among various alternatives.

    Lesson 3 - Topic C: Create a Scope Statement.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    31/184

    30-Jan-

    3

    Work Br eakdown Structures (WBS)

    Helps to identify deliverables

    Subdivides

    project

    work into

    smaller

    pieces

    Maps to

    project

    scope

    statement

    Lesson 3 - Topic D: Develop a Work Breakdown Structure.

    Ing. Moises Palomino Suarez

    The Create WBS Process

    The method of dividing the project deliverables into smaller, more

    manageable components.

    Helps create a deliverable-oriented hierarchical decomposition of

    work to be executed by the project team.

    Lesson 3 - Topic D: Develop a Work Breakdown Structure.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    32/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    33/184

    30-Jan-

    3

    Lesson 4: Developing Project

    Schedules

    Topic A: Create an Activity List

    Topic B: Create a Project Schedule Network Diagram

    Topic C: Estimate Activity Resources

    Topic D: Estimate Duration for Project Activities

    Topic E: Develop a Project Schedule

    Topic F: Identify the Critical Path

    Topic G: Optimize the Project Schedule Topic H: Establish a Schedule Baseline

    Ing. Moises Palomino Suarez

    The Project Management Framework

    Knowledge Areas

    Project Management Process Groups

    Initiating Process

    Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &

    Controlling Process

    Group

    Closing Process

    Group

    Project IntegrationManagement

    Develop Project

    Charter

    Develop Project

    Management Plan

    Direct and Manage

    Project Execution

    Monitor and Control

    Project Work

    Perform Integrated

    Change Control

    Close Project or

    Phase

    Project ScopeManagement

    Collect Requirements

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

    Project TimeManagement

    Define ActivitiesSequence Activities

    Estimate Activity

    Resources

    Estimate Activity

    Durations

    Develop Schedule

    Control Schedule

    Project CostManagement

    Estimate Costs

    Determine BudgetControl Costs

    Project QualityManagement Plan Quality

    Perform Quality

    Assurance

    Perform Quality

    Control

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    34/184

    30-Jan-

    3

    The Project Management Framework (Cont.)

    Project Management Process Groups

    ProjectProcurementManagement

    Project RiskManagement

    ProjectCommunicationsManagement

    Project HumanResourceManagement

    Knowledge Areas

    Monitor and

    Control Risks

    Plan Risk Management

    Identify Risks

    Perform Qualitative Risk

    Analysis

    Perform Quantitative Risk

    Analysis

    Plan Risk Responses

    Report

    Performance

    Distribute Information

    Manage Stakeholder

    Expectations

    Plan CommunicationsIdentify

    Stakeholders

    Acquire Project Team

    Develop Project Team

    Manage Project Team

    Develop Human Resource Plan

    Administer

    Procurements

    Monitoring &Controlling

    Process Group

    Plan Procurements

    Planning

    Process Group

    Conduct Procurements

    Executing

    Process Group

    InitiatingProcess Group

    Close

    Procurements

    ClosingProcess Group

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

    Activ i t ies

    Element of project work that requires an action to produce a

    deliverable.

    Have an expected duration.

    Consume budget and/or human resources.

    Are named in verb-noun format.

    Example: Activities in a company project.

    Revise user manual.

    Make a sales presentation.

    Reserve conference room. Revise user manualExpected duration determined by (whatever)

    Verb (Action) Noun (Deliverable)

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    35/184

    30-Jan-

    3

    Work Package

    Planned work or deliverables.

    Lowest-level component of the work breakdown structure. Cost and schedule can be easily estimated.

    A work breakdown structure showing the work packages

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

    The 8/80 Rule

    A general guideline regarding work packages: they require more

    than 8, but fewer than 80, hours of effort to complete.

    Helps project managers create work package lists.

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    36/184

    30-Jan-

    3

    The Define Activi ties Process

    The process of identifying and documenting specific activities that must be

    performed to produce the project's deliverables.

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

    How to Defi ne Activi ties

    Guidelines

    Gather the inputs and materials you need.

    Analyze and decompose each work package of the WBS into activities

    that will be required to produce the deliverable.

    Consult records of similar projects to identify possible activities.

    Consult subject matter experts about unfamiliar material.

    Evaluate all constraints and assumptions for their possible impact on

    activity definition.

    Evaluate the activity list, once each work package is decomposed to

    activities.

    Example: Web design company creating an activity list for design

    work package.

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    37/184

    30-Jan-

    3

    Completed WBS Table

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

    The Sequence Activities Process

    A planning process that involves identifying and documenting interactivity

    dependencies among project activities for the purpose of creating the

    project schedule.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    38/184

    30-Jan-

    3

    Acti vity Dependencies

    A logical relationship that exists between two project activities.

    Example: An architects vision for room layouts.

    Functionality of the design:

    a) Framed structure.

    b) Walls, windows, roof.

    Structure in place:

    a) Reassess the plans.

    b) Determine modifications.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

    Types of Activi ty Dependencies

    Dependency Description

    Mandatory Inherent to the work itself and are usually affected by physical constraints.

    Discretionary Defined by the project and project management team at their discretion.

    External Contingent on inputs from outside the project activit ies.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    39/184

    30-Jan-

    3

    Precedence Relationship

    The logical relationship between two activities that describes the

    sequence in which the activities should be carried out.

    Example: Drywall installation must finish before painting can

    begin.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

    Precedence Relationship Types

    Relationship Description

    Finish-to-Start (FS) Activity A must finish before activity B can start.

    Finish-to-Finish (FF) Activity A must finish before activity B can finish.

    Start-to-Start (SS) Activity A must start before activity B can start.

    Start-to-Finish (SF) Activity A must start before activity B can finish.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    40/184

    30-Jan-

    4

    Lag

    A delay in the start of a successor activity.

    FS relationship with lag

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

    Lead

    A change in a logical relationship that allows the successor activity

    to start before the predecessor activity ends in an FS relationship.

    Implemented when a successor activity needs to be accelerated in

    order to shorten the overall project schedule.

    FS relationship with lead

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    41/184

    30-Jan-

    4

    Project Schedule Network Diagrams

    Graphical representation of the sequence of project activities and the

    dependencies among them. Read from left to right or top to bottom.

    May include the entire project or specific parts of it.

    A project schedule network diagram

    Lesson 4 - Topic A: Create an Activity List.

    Ing. Moises Palomino Suarez

    Precedence Diagramming M ethod (PDM )

    Produces a project schedule network diagram that uses rectangular boxes,

    or nodes, to represent activities and arrows to represent precedence

    relationships between activities.

    Characteristics:

    Reads from left to right.

    Shows duration in nodes.

    Created manually or with software.

    Report a group of related activities as an aggregate activity.

    Use all precedence relationship types.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    42/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    43/184

    30-Jan-

    4

    How to Create a Project Schedule Network

    Diagram

    To create a PDM project schedule network diagram:

    Determine the dependencies among project activities using youractivity list and product descriptions.

    Identify predecessor and successor activities.

    Create nodes for all activities with no predecessor activities or

    dependencies.

    Create nodes for all activities that are successor activities.

    Draw arrows from the predecessor activities to the successor activities.

    Continue drawing the network diagram, working from left to right until all

    activities are included on the diagram and the precedence relationships are

    indicated by arrows.

    Include any known lags or leads.

    Verify the accuracy of your diagram.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

    Completed Network Diagram

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    44/184

    30-Jan-

    4

    Project Resources

    Any useful material object or person needed for project completion.

    Include labor, materials, facilities, equipment, consultants, services,supplies, and utilities.

    Example: Resources for a health and wellness seminar project.

    Conference room.

    Brochures, pamphlets, other materials.

    Visiting consultants.

    Vendors.

    Lesson 4 - Topic B: Create a Project Schedule Network Diagram.

    Ing. Moises Palomino Suarez

    The Estimate Activity Resources Process

    Involves determining specific resources necessary for completing project

    activities.

    Lesson 4 - Topic C: Estimate Activity Resources.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    45/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    46/184

    30-Jan-

    4

    How to Est im ate Act iv i ty Resourc es

    Guidelines

    Determine what resources are necessary.

    Determine what quantity of resources are necessary.

    Generate possible alternatives for unavailable resources.

    Analyze the scope statement to ensure youve identified all the

    resources.

    Consider organizational policies that could affect resource acquisition

    and usage.

    Identify and use expert judgement resources.

    Analyze the resources already available.

    Lesson 4 - Topic C: Estimate Activity Resources.

    Ing. Moises Palomino Suarez

    The Estimate Acti vity Durations Process

    The act of estimating the quantity of work that is required to complete

    individual project activities using the available resources.

    Lesson 4 - Topic D: Estimate Duration for Project Activities.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    47/184

    30-Jan-

    4

    How to Est imate Durat ion for Project Act iv i t ies

    Guidelines

    Involve the work package owners.

    Consult historical information.

    Determine how you want to quantify the work.

    Consider resource requirements and capabilities.

    Determine the appropriate estimation method to use.

    Modify the constraints and assumptions from the other planning

    processes.

    Verify the accuracy of your estimates.

    Consider the need for reserve time.

    Example: Activity estimates for creating website include design work,

    resources, and work units.

    Lesson 4 - Topic D: Estimate Duration for Project Activities.

    Ing. Moises Palomino Suarez

    Project Schedules

    The plan for starting and finishing activities on specific dates and in

    a certain sequence.

    Used to:

    Coordinate activities into a master plan.

    Track schedule performance.

    A project schedule for a website design project (deliverable categories in bold)

    Lesson 4 - Topic E: Develop a Project Schedule.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    48/184

    30-Jan-

    4

    The Develop Schedule Process

    The act of defining specific start and end dates for each project activity.

    Lesson 4 - Topic E: Develop a Project Schedule.

    Ing. Moises Palomino Suarez

    Standard Schedule Diagramming Notations

    Relationship Description

    ES Early start. The earliest time an activity can s tart.

    EF Early finish. The earliest time an act ivity can finish.

    LF Late finish. The latest time an activity can finish.

    LS Late start. The latest time an activity can start.

    DUDuration. The number of work periods required for

    completion of an activity.

    Lesson 4 - Topic E: Develop a Project Schedule.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    49/184

    30-Jan-

    4

    The Crit ical Path

    Path with the longest total duration.

    Has no scheduling flexibility.

    1[6W] + 2[4W] + 4[3w] + 6[1W] = 14 Weeks

    1[6W] + 3[5W] + 5[4w] + 6[1W] = 16 Weeks Critical Path

    A network diagram showing the critical path of activities

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Schedule Netwo rk Analysis

    Technique used to calculate the theoretical early and late start and

    finish dates for all project activities.

    Four methods:

    Critical Path Method (CPM).

    Critical chain method.

    What-if scenario.

    Resource leveling.

    Example: A marketing campaign schedule.

    Involves:

    Using software to create request for proposals.

    Launching campaign.

    Estimating slack.

    Adjusting activities.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    50/184

    30-Jan-

    5

    The Crit ical Path Method (CPM)

    A schedule network analysis method.

    Uses sequential finish-to-start network logic. Calculates one early and late start and finish dates for each activity.

    Uses a single duration estimate.

    Critical path method involves calculating one early and late start and finish date for each activity

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Schedule Formats

    Bar chart:

    Shows start and end dates, duration, order.

    Can show precedence relationships.

    Can show percentage completion; actual progress.

    Used to present project status to management.

    A bar chart

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    51/184

    30-Jan-

    5

    Schedule Formats (Cont.)

    Milestone chart:

    Provides summary level view of projects milestones.

    Uses icons or symbols.

    Shows the projects overall schedule.

    A milestone chart

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Schedule Formats (Cont.)

    Project schedule network diagram with dates:

    Assigns start and finish dates to activities.

    Communicates project status in terms of activity precedence relationships.

    A project schedule network diagram with dates

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    52/184

    30-Jan-

    5

    How to Develop a Project Schedule

    To develop a draft project schedule:

    Perform a mathematical analysis to determine the time periodswithin which activities could be scheduled once resource limits and

    other known constraints are applied.

    Evaluate the possible impact of any constraints and assumptions on

    schedule development.

    Consider the availability of your resources.

    Consult project calendars and assign dates to activities.

    Calculate possible project durations under different assumptions

    using simulation.

    Consider external resource date constraints, if applicable.

    Select project management software that best meets the needs andbudget of your project.

    Review rough drafts of the schedule with the project team, sponsor,

    and customer.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    How to Develop a Project Schedule (Cont.)

    To develop a draft project schedule:

    Choose the format in which youll publish the schedule.

    Distribute the preliminary schedule to all program office personnel,

    functional team members, functional management, and the

    customer or sponsor to obtain approval.

    Following approval, baseline the schedule and distribute to the

    team.

    Example: Mathematical analysis to determine project schedulingactivities.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    53/184

    30-Jan-

    5

    Completed Project Schedule

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Criti cal Activities

    The activities on the critical path.

    Have ES = LS and EF = LF.

    Critical activities in a project

    Critical Activities:

    A, B, F, G, H

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    54/184

    30-Jan-

    5

    How to Identi fy the Cri tical Path

    To identify the critical path for a project with FS relationships:

    1. Conduct a forward pass to determine ES and EF times for each activity.2. Perform a backward pass to determine LS and LF times for each.

    3. Calculate float.

    4. Identify the critical path as the path with the longest total duration and zero

    float.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Schedule Compress ion

    The shortening of the project schedule without affecting the project

    scope.

    Two methods:

    Fast-tracking

    Crashing

    Example: Schedule compression for building and installing cabinets.

    Involves carpenter and sub-contractor.

    Sub-contractor installs cabinets while carpenter builds.

    Changes precedence.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    55/184

    30-Jan-

    5

    Fast-Tracking

    The process of compressing total project duration.

    Perform sequential activities concurrently.

    Example: Fast-tracking activities for launching a new product.

    Product and user manual developed concurrently.

    Project duration shortened.

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    Crashing

    Analyzes cost and schedule trade-offs to determine how to obtain

    the greatest amount of schedule compression for the least

    incremental cost.

    Involves allocating more resources to activities on the critical path.

    Crash costs of a website project

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    56/184

    30-Jan-

    5

    Crash Cost Plott ing Metho ds

    Techniques for analyzing the crash costs through a graph or visual

    representation.

    Crash costs plotted on a graph

    Lesson 4 - Topic F: Identify the Critical Path.

    Ing. Moises Palomino Suarez

    How to Optimi ze the Project Schedule

    To compress the project schedule:

    1. Consider your resource leveling options.

    2. Consider fast-tracking the project.

    3. Analyze activities on the critical path to determine if crashing the schedulewill produce a viable option.

    4. Analyze each activity on the critical path to determine whether reducingscope is a viable option for reducing duration.

    5. Recalculate the critical path after compressing the schedule.

    6. Review any schedule changes with key stakeholders.

    7. Revise the schedule and distribute to the team.

    Example: Optimizing the schedule of a website design project.

    Involves:

    Drafting schedule compressed one week.

    Analyzing critical path.

    Fast-tracking activities.

    Lesson 4 - Topic G: Optimize the Project Schedule.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    57/184

    30-Jan-

    5

    Criti cal Path Activity

    Lesson 4 - Topic G: Optimize the Project Schedule.

    Ing. Moises Palomino Suarez

    Calculated Crash Costs Per Week

    Lesson 4 - Topic G: Optimize the Project Schedule.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    58/184

    30-Jan-

    5

    Completed Crash Plot

    Lesson 4 - Topic G: Optimize the Project Schedule.

    Ing. Moises Palomino Suarez

    Schedule Basel ines

    The management-approved version of the project schedule.

    Drawn from the schedule network analysis.

    Provides basis for measuring and reporting schedule performance.

    A chart showing a schedule baseline

    Lesson 4 - Topic H: Establish a Schedule Baseline.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    59/184

    30-Jan-

    5

    Lesson 5: Developing Cost Estimates

    and Budgets

    Topic A: Estimate Project Costs

    Topic B: Estimate the Cost Baseline

    Topic C: Reconcile Funding and Costs

    Ing. Moises Palomino Suarez

    The Project Management Framework

    Knowledge Areas

    Project Management Process Groups

    Initiating Process

    Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &

    Controlling Process

    Group

    Closing Process

    Group

    Project IntegrationManagement

    Develop Project

    Charter

    Develop Project

    Management Plan

    Direct and Manage

    Project Execution

    Monitor and Control

    Project Work

    Perform Integrated

    Change Control

    Close Project or

    Phase

    Project ScopeManagement

    Collect Requirements

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

    Project TimeManagement

    Define ActivitiesSequence Activities

    Estimate Activity

    Resources

    Estimate Activity

    Durations

    Develop Schedule

    Control Schedule

    Project CostManagement

    Estimate Costs

    Determine BudgetControl Costs

    Project QualityManagement Plan Quality

    Perform Quality

    Assurance

    Perform Quality

    Control

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    60/184

    30-Jan-

    The Project Management Framework (Cont.)

    Project Management Process Groups

    ProjectProcurementManagement

    Project RiskManagement

    ProjectCommunicationsManagement

    Project HumanResourceManagement

    Knowledge Areas

    Monitor and

    Control Risks

    Plan Risk Management

    Identify Risks

    Perform Qualitative Risk

    Analysis

    Perform Quantitative Risk

    Analysis

    Plan Risk Responses

    Report

    Performance

    Distribute Information

    Manage Stakeholder

    Expectations

    Plan CommunicationsIdentify

    Stakeholders

    Acquire Project Team

    Develop Project Team

    Manage Project Team

    Develop Human Resource Plan

    Administer

    Procurements

    Monitoring &Controlling

    Process Group

    Plan Procurements

    Planning

    Process Group

    Conduct Procurements

    Executing

    Process Group

    InitiatingProcess Group

    Close

    Procurements

    ClosingProcess Group

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

    The Est imate Costs Process

    The process of projecting the total expenditures necessary for the

    completion of your project.

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    61/184

    30-Jan-

    Common Estimate Types

    Type or Level of Accuracy Description or Accuracy Rating

    Rough Order of Magnitude

    (ROM)

    Developed without basis of detailed data and often based on very high level

    historical data, expert judgment, or a costing model. Accuracy:

    -50 percent to +100 percent.

    Budgetary Often used for appropriation purposes. Accuracy: -10 to +25 percent.

    Range of estimateOften used as an alternative to ROM where the accuracy of the estimate is

    not well known. Accuracy: 35 percent.

    Approximate estimateBased on more information than ROM estimates, but still lacks the detail

    required for high accuracy. Accuracy: 15 percent.

    Definitive estimate (or control

    or detailed)

    Developed by estimating the cost for each work package in the WBS.

    Accuracy: - 5 percent to + 10 percent.

    Phased estimate (or rollingwave or moving window) Allows the use of ROM or approximate estimates for some later parts of thework. Accuracy: 5 percent to 15 percent.

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

    Analogous Est imat ing

    A method of cost estimating.

    Managers use experience, historical information, expert judgment.

    Determines a total project cost or time estimate.

    Apportions total across the major categories of work.

    Used when:

    Only a limited amount of detailed information is available.

    Similar project is available for comparison.

    Estimators have appropriate experience.

    Example: A web design firm uses analogous estimating to produce

    cost and time estimates for new accounts.

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    62/184

    30-Jan-

    Bottom-Up Estimating

    Estimates the cost for each work package.

    Estimates are then rolled up or aggregated. Used when:

    More detail is available about the work packages.

    More accurate estimates are needed.

    There is time to invest in making the estimates.

    Example: A caterer using the bottom-up estimating technique based on a

    detailed WBS for a large corporate event.

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

    Parametri c Estimating

    A technique used to predict total project costs by using the project's

    characteristics in a mathematical model.

    Managers do a statistical analysis using historical information

    about scope, cost, budget, and duration.

    A sample parametric estimating

    Lesson 5 - Topic A: Estimate Project Costs.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    63/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    64/184

    30-Jan-

    The Determine Bu dget Process

    The process of allocating the overall cost estimates to individual

    activities or work packages across the project life cycle.

    Lesson 5 - Topic B: Estimate the Cost Baseline.

    Ing. Moises Palomino Suarez

    Funding Limit Reconcili ation

    A method of adjusting spending, scheduling, and resource allocation

    in order to bring expenditures into alignment with budgetary

    constraints.

    Example: A customer wants to spread project costs over two quarters.

    $250,000 during Q1.

    $350,000 during Q2.

    Q1: $250,000 Q2: $350,000

    Lesson 5 - Topic B: Estimate the Cost Baseline.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    65/184

    30-Jan-

    Cost Assignment Methods

    Cost Assignment Method Description

    50/50 percent rule50 percent credit is given when the activity begins and 50 percent credit

    is given when the work is completed.

    Percentage completed ruleCompletion percentages are estimated and assessed at specified reporting

    intervals. This is perhaps the most commonly used rule.

    Weighted milestones

    The total work package value is divided up and assigned to milestone

    intervals within the work package. The value is earned when the

    milestone is achieved.

    Lesson 5 - Topic B: Estimate the Cost Baseline.

    Ing. Moises Palomino Suarez

    How to Estimate the Cost Basel ine

    To estimate a cost baseline:

    1. Gather the inputs you will need, such as the WBS, project schedule, cost

    estimates, and risk management plan.

    2. Determine when activities will be taking place.

    3. Allocate funds for each activity or work package for the time period in

    which they will be taking place.

    4. Consider adding in a contingency amount.

    5. Total the costs for each time period.

    6. Plot the costs on a chart to create an S-curve of the baseline.

    7. Publish and distribute the cost baseline to the appropriate project

    stakeholders.

    Lesson 5 - Topic B: Estimate the Cost Baseline.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    66/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    67/184

    30-Jan-

    Topic A: Create a Quality Management Plan

    Topic B: Document the Project Roles,

    Responsibilities, and Reporting Relationships

    Topic C: Create a Communications

    Management Plan

    Lesson 6: Planning Project Quality, Staffing, and

    Communications

    Ing. Moises Palomino Suarez

    The Project Management Framework

    Knowledge Areas

    Project Management Process Groups

    Initiating Process

    Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &

    Controlling Process

    Group

    Closing Process

    Group

    Project IntegrationManagement

    Develop Project

    Charter

    Develop Project

    Management Plan

    Direct and Manage

    Project Execution

    Monitor and Control

    Project Work

    Perform Integrated

    Change Control

    Close Project or

    Phase

    Project ScopeManagement

    Collect Requirements

    Define Scope

    Create WBS

    Verify Scope

    Control Scope

    Project TimeManagement

    Define ActivitiesSequence Activities

    Estimate Activity

    Resources

    Estimate Activity

    Durations

    Develop Schedule

    Control Schedule

    Project CostManagement

    Estimate Costs

    Determine BudgetControl Costs

    Project QualityManagement Plan Quality

    Perform Quality

    Assurance

    Perform Quality

    Control

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    68/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    69/184

    30-Jan-

    Quality Management Plans

    Describe for the project stakeholders the teams approach to

    implement the quality policy. Outline (esq) how quality control and quality assurance will be

    performed.

    Example: Clothing manufacturers labor cost reduction.

    Quality management plan includes:

    How quality control and assurance would be performed.

    Who would be responsible for quality control.

    How, when, and to what degree they would conduct inspections.

    How the team would respond to quality issues.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    The Plan Quality Process The process of putting plans into place to ensure that a project will satisfy

    its stated objectives or business needs.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    70/184

    30-Jan-

    7

    Process Improvement Planning

    The process of analyzing and identifying areas of improvement inproject processes.

    Enumerating an action plan based on the project goals andidentified issues.

    Involves: Describing operational theories and project roles and responsibilities.

    Identifying long and short-term goals.

    Describing process improvement objectives and activities.

    Identifying risks and resource requirements.

    Determining process improvement activities.

    Creating a process improvement plan.

    Receiving approval from stakeholders and senior managers. Executing the process improvement plan.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Process Improvement Plan

    Describes the steps to analyze and determine areas ofimprovements in project process.

    Areas of process improvements include:Process boundaries.

    Process configuration.

    Process metrics.Targets for improved performance.

    Example: Reviewing the existing product testingprocess in a software

    development company.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    71/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    72/184

    30-Jan-

    7

    The ISO 9000 Series

    A quality system standard that is applicable toany product, service, or process in the world.

    Developed by ISO, a consortium ofapproximately 100 of the worlds industrialnations.

    Does not guarantee that an organization willproduce quality products or services.

    Simply confirms that appropriate systems arein place.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Cost of Quality The total cost of effort needed to achieve an acceptable level of

    quality in the projects product or service.

    Different types of costs

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    73/184

    30-Jan-

    7

    Checklists

    A job aid that prompts employees to perform activities according to

    a consistent quality standard.Obtain a printout of the image specifications from the graphics database. Use this

    checklist to ensure that the images are ready to be handed off to the programmer.

    # Item Y/N

    1 Does the image match the description in the database?

    2 Does the style meet the specifications for the course or lesson?

    3 Does the quality of the image meet the standards set for the course?

    4 Is the image size correct?

    5 Is the correct border on the image?

    6 Is the image in the correct palette?

    7 Is the opacity correct (transparent or opaque)?

    8 Is the bit-depth correct?

    A checklist for printing image

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Flowchart

    A diagram that shows the relationships of

    various elements in a system or process.

    Two flowcharting techniques:

    Cause-and-effect diagram.

    Process or system flowchart.

    Helps identify potential quality problems and

    possible effects of the problems.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    74/184

    30-Jan-

    7

    Process Flowchart Shows the sequence of events and flow of inputs and outputs between

    elements in a process or system.

    Has a definite beginning and end.

    A sample process flowchart

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Cause-and-Effect Diagram A diagram that shows the relationships of various elements in a system or

    process.

    A cause-and-effect diagram

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    75/184

    30-Jan-

    7

    Control Charts

    UCL

    Indicates Instability

    LCL

    UCL

    LCL

    X X

    Variability above the upper control limit (UCL)

    A graph used to analyze and communicate the variability of a process or

    project activity over time. Shows the potential capability of the process.

    Suggests the range of variability in the process.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Control Charts (Cont.)

    UCL

    Indicates Instability

    LCL

    UCL

    LCL

    X X

    Variability below the lower control limit (LCL)

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    76/184

    30-Jan-

    7

    Benchmarking

    A method of addressing the evaluation of a groups business or

    project practices in comparison to those of other groups. Used to identify best practices in order to meet or exceed them.

    Example: Benchmarking the espresso-based beverages based on

    the performance of Seattle-based Starbucks Corp.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    Design of Experiments (DOE) A technique to systematically identify varying levels of independent

    variables.

    Example: Creating a new style of jar in a cannery.

    Creation involves:

    Determining the optimum torque size.

    Testing torque with spindle speed and conveyor speed.

    Determining adjustments to these settings.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    77/184

    30-Jan-

    7

    How to Create a Quality Management PlanGuidelines

    Review the organizations quality policy and determine how yourproject team will implement the policy.

    Review the product description to identify customer/stakeholderquality requirements.

    Determine the cost of quality trade-offs.

    Review the quality management plan.

    Example: Creating a quality management plan by a project team.

    Creation involves: Determining that a quality policy is available.

    Assigning roles and responsibilities. Assigning project quality assurance coordinator.

    Repeating the design process and peer plan reviews.

    Lesson 6 - Topic A: Create a Quality Management Plan.

    Ing. Moises Palomino Suarez

    The Develop Human Resource Plan Process The process of identifying, documenting, and assigning project roles,

    responsibilities, and reporting relationships.

    Commonly performed during early project phases.

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    78/184

    30-Jan-

    7

    Organizational Structures

    Dictates how the various groups and individuals within an organization

    interrelate.

    CFO CIO

    Department Head

    VP HR

    Employee

    CEO

    Employee

    Employee

    Department Head

    Employee Employee

    Employee

    Department Head

    A sample organizational structure

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

    Organizational Structure Types

    Item Y/N

    Functional organization

    Each department carries out specific activities.

    Reporting is hierarchical.

    PMs authority is low, relative to functional manager.

    Projectized organization

    PM and core project team operate as a separate

    unit.

    PM has significant authority and independence.

    Matrix organization Individuals report upwards and also horizontally.

    Composite organization Combination of all other types.

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    79/184

    30-Jan-

    7

    Organization Chart A visual representation of the projects organizational structure.

    Clearly assigns project tasks to team members.

    A functional organization chart

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

    Organization Chart (Cont.)

    A projectized organization chart

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    80/184

    30-Jan-

    8

    Organization Chart (Cont.)

    A matrix organization chart

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

    Relative Authority in Organizational Structures

    The project managers authority relative to thefunctional managers authority over the projectand the project team.

    Example: Companies with different organizationalstructures.

    An auto manufacturing company with functionalorganizational structure and hierarchicalmanagement.

    A web design company with projectizedorganizational structure.

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    81/184

    30-Jan-

    8

    Project Interfaces

    Various reporting relationships that occurwithin the project as well as the boundaries ofthe project.

    Classified as:

    Organizational

    Technical

    Interpersonal

    LogisticalPolitical

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

    Responsibility Assignment Matrix (RAM) A chart that links key project stakeholders to specific project deliverables or

    activities by assigning responsibility to an individual stakeholder for each

    element of work.

    Project

    Manager

    Engineering

    Manager

    Quality

    Assurance

    Manager

    Purchasing

    Manager

    Manufacturing

    Manager

    Create Blueprints S A P P

    Manufacture

    BreadboardS A P P

    Test Breadboard S P A P

    Order

    ComponentsS P P A P

    Assemble S P A

    S = Sign-off

    A = Accountable

    P = Participant

    A sample Responsibility Assignment Matrix

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    82/184

    30-Jan-

    8

    Staffing Management Plan

    Forecast what types of staff will work on the project, when they will

    be needed, how they will be recruited onto the project, and whenthey will be released from the project.

    Example: Writing a companys 100th anniversary book.

    Staffing management plan includes:

    External resources.

    Internal resources with specialized knowledge.

    Who would be needed.

    When they would be needed.

    What they would contribute.

    How long they would participate.

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

    Staffing Management Plan Components

    Staff acquisition

    Timetable

    Release criteria

    Training needs

    Recognition and rewards

    Compliance

    Safety

    Lesson 6 - Topic B: Document the Project Roles, Responsibilities, and Reporting Relationships.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    83/184

    30-Jan-

    8

    Communications Management Plan

    Describes the project teams approach to communicate project

    information.

    Example: Communications management plan for a companys

    annual meeting.

    The plan includes:

    Regularly scheduled status meetings.

    Distribution of the meeting minutes.

    Email distribution list.

    All stakeholders and resources included on communications.

    Lesson 6 - Topic C: Create a Communications Management Plan.

    Ing. Moises Palomino Suarez

    The Plan Communications Process The process of ensuring timely and appropriate generation, collection,

    dissemination, storage, and ultimate disposition of project information.

    Lesson 6 - Topic C: Create a Communications Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    84/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    85/184

    30-Jan-

    8

    Communications Technologies

    The technologies used for communications planning: websites, email,

    instant messaging, phones, video conferencing.

    Lesson 6 - Topic C: Create a Communications Management Plan.

    Ing. Moises Palomino Suarez

    Activity Form Responsible Frecuency Audiency

    Team

    tracking

    Meeting Project Manager Weekly Team work

    Project Manager

    Analyst

    Leader

    Program

    Leader

    User

    Expert

    Programmers

    Board

    Analysts

    How to Create a Communications Management Plan

    Lesson 6 - Topic C: Create a Communications Management Plan.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    86/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    87/184

    30-Jan-

    8

    Knowledge Areas

    Project Management Process Groups

    InitiatingProcess Group

    Planning

    Process Group

    Executing

    Process Group

    Monitoring &

    ControllingProcess Group

    ClosingProcess Group

    Project HumanResourceManagement

    Develop Human Resource

    Plan

    Acquire Project Team

    Develop Project Team

    Manage Project Team

    ProjectCommunicationsManagement

    Identify

    StakeholdersPlan Communications

    Distribute

    Information

    Manage Stakeholder

    Expectations

    Report

    Performance

    Project RiskManagement

    Plan Risk Management

    Identify Risks

    Perform Qualitative Risk

    Analysis

    Perform Quantitative

    Risk Analysis

    Plan Risk Responses

    Monitor and

    Control Risks

    ProjectProcurementManagement

    Plan ProcurementsConduct

    Procurements

    Administer

    Procurements

    Close

    Procurements

    The Project Management Framework (Cont.)

    Risks

    An uncertain event with positive or negative

    impact.

    Primary components include:

    A measure of probability that the risk event will

    occur.

    The impact of the risk occurring on a project.

    Example: The threat of rain is a risk when

    planning an outdoor festival that could

    seriously affect attendance and revenue.

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    88/184

    30-Jan-

    8

    High-level process with five sub-phases:

    The project risk management process with the five main sub-phases

    Project Risk ManagementLesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

    Business risk:

    Inherent in business.

    All projects have potential for loss or profit.

    Example: Purchasing inventory without guaranteed sales.

    Insurable risk:

    Only the potential for loss.

    No potential for profit.

    Insurance may be purchased to offset losses.

    Example: Loss of inventory due to fire.

    Business Risk vs. Insurable Risk

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    89/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    90/184

    30-Jan-

    9

    Document that describes the teams approach to

    identifying risks. Identifies methodology, approaches, and tools.

    Documents roles and responsibilities.

    Identifies budgeting and scheduling.

    Identifies risk categories.

    Example: Entrepreneurs seeking funding from venturecapitalists for building an amusement park.

    Risk management plan will include:Losses due to employee theft as business risk.

    Liabilities for park ride injuries as insurable risks.

    Risk Management Plan

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

    The Plan Risk Management ProcessThe process of deciding how to plan and execute

    the risk management activities for a project.

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    91/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    92/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    93/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    94/184

    30-Jan-

    9

    Impact Rating Impact Level Definition

    1 Very lowIf this risk occurs, the impact on the projects objectives would

    be minor and not noticeable outside the project.

    3 LowIf this risk occurs, the impact on the projects objectives would

    be minor but noticeable to customer or sponsor.

    5 Moderate

    If this risk occurs, the impact on the projects objectives would

    be significant and would create customer or sponsor

    dissatisfaction with the project.

    7 High

    If this risk occurs, the impact on the project would be

    significant and would create major customer or sponsor

    dissatisfaction. The project would be in jeopardy.

    9 Very high If this risk occurs, the impact would be catastrophic.The project would be cancelled.

    Impact Scales

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

    Type Description

    KnownItems that you are aware of and that will affect you, but you have no

    control over.

    Known-unknown Items that will affect you, although you are not able to predict how orhow much they will affect you.

    Unknown-unknown Items beyond your ability to foresee.

    Levels of Uncertainty

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    95/184

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    96/184

    30-Jan-

    9

    Classification Description

    Risk-averter Not likely to take a risk that is considered a high risk.

    Risk-seekerAccepts an uncertain outcome and may be willing to take a high risk

    regardless of the consequences.

    Risk-neutral Tolerance to risk is proportional to the amount of money at stake.

    Levels of Risk Tolerance

    Lesson 7 - Topic A: Examine a Risk Management Plan .

    Ing. Moises Palomino Suarez

    Early warning signs or indications that risk will occur.

    External factors include:

    Changes in the legislation.

    Internal factors include:

    Changes in staffing.

    Changes in governance.

    Changes in funding.

    Example: For a documentary program production, a television writers strike

    would be a trigger and involves positive and negative risks.

    Triggers

    Lesson 7 - Topic B: Identify Project Risks and Triggers .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    97/184

    30-Jan-

    9

    The Identify Risks Process

    An iterative process of identifying the risksand triggers facing a project.

    Lesson 7 - Topic B: Identify Project Risks and Triggers .

    Ing. Moises Palomino Suarez

    Technique Description

    BrainstormingUsed to identify overall project risks or may focus in on the risks

    within a particular project segment or work package.

    Delphi techniqueGenerates a consensus among project risk experts who

    anonymously submit their risk list to a facilitator.

    Interviewing

    Used to get information from people with a wide experience across

    many projects.

    Root cause analysisUsed to identify problems, discover the root cause, and develop

    corrective actions.

    Information-Gathering Techniques

    Lesson 7 - Topic B: Identify Project Risks and Triggers .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    98/184

    30-Jan-

    9

    Identifies and categorizes risks, potential risk responses, triggers.

    Updated as risk categories change. Risk responses from the initial risk register are used in the risk

    response planning process.

    Updated risk register is provided to the project team members.

    A sample risk register

    Risk Registers

    Lesson 7 - Topic B: Identify Project Risks and Triggers .

    Ing. Moises Palomino Suarez

    Risk Category Examples

    Technical, quality, or

    performance risks

    Technical changes.

    Changes to industry standards during the project.

    Reliance on unproven or complex technology.

    Unrealistic performance goals.

    Project management risks

    Inadequate time and resource allocation.

    Ineffective project plan development.

    Poor cost estimates.

    Organizational risks

    Resource conflicts with other projects.

    Inadequate project funding.

    Inconsistent management support.

    External risks

    Union issues.

    Change of management in customers organization.

    Regional security issues.

    Risk Categories

    Lesson 7 - Topic B: Identify Project Risks and Triggers .

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    99/184

    30-Jan-

    9

    A technique to determine the probability ofoccurrence and the impact of identified risk.

    Determine the risk exposure of the project bymultiplying the probability and impact.

    Example: An event management companyplanning a jazz concert in a

    particular coastal city where there is a threatof bad weather.

    Qualitative Risk AnalysisLesson 7 - Topic C: Perform Qualitative Risk Analysis.

    Ing. Moises Palomino Suarez

    The Perform Qualitative Risk Analysis Process

    The process of assessing, ranking, and

    prioritizing risks for subsequent analysis.

    Lesson 7 - Topic C: Perform Qualitative Risk Analysis.

    Ing. Moises Palomino Suarez

  • 7/30/2019 Project Management Professional (PMP_) MPS-UNASCAPACITalumno2

    100/184

    30-Jan-

    10

    Evaluation of the usefulness of data concerning risk.

    Examining data includes: Amount of data available.

    Quality of data available.

    Source of information.

    Legitimacy of data.

    Dependability of data. (trusted)

    Example: Risk assessment performed for a restaurant chains new site

    development.

    Risk Data Quality Assessment

    Lesson 7 - Topic C: Perform Qualitative Risk Analysis.

    Ing. Moises Palomino Suarez

    A simplified probability and impact risk rating matrix

    Probability and Impact Risk