Project planni n g End date Uniqueness High complexity Start Date Project Product It has to respect a certain budget 1. Quality means meeting sponsor’s criteria 2. Quality means that the product will respect the specifications QUALITY COST TIME It has a precise start and end date Initiation Plan & Design Closing Monitoring &Control ExecutionTRANSCRIPT
Project planning
What is a project?
Start Date
End date
Project Product
A temporary endeavor undertaken to create an
unique product, service or result.*
* PMI Definition
Uniqueness
High complexity
But in the end …a project is constrained by …
COST
TIME
QUALITY
Project
It has a precise start and end date
It has to respect a certain budget 1. Quality means meeting sponsor’s criteria
2. Quality means that the product will respect the specifications
Project Management Process Groups
Execution
Monitoring &Control
Initiation Plan & Design Closing
Project Management Knowledge Areas
Project Integration Management
Project Scope Management
Project Time Management
Project Communication Management
Project Risk Management
Project Human Resources
Management
Project Procurement Management
Project Cost Management
Project Quality Management
Rules of the WBS : 1. Project Management will always be
on the WBS 1. Every Level 1 deliverable has to
have an owner 3. Each deliverable has to appear only
once within the WBS 4. Work packages are the lowest- level
items
What is WBS?
Project Product
Deliverable 1
Sub D 1.1 Sub D 1.2
Deliverable 2
Sub D 2.2. Sub D 2.1
Act 2.1.1 Act 2.1.2
Work Break Down Structure is a deliverable oriented tool that defines the
total scope of project
Project Charter or Business Case
Feasibility Phase
• Is my project result adding value to my organization?
• Implementation Efforts overcome the result?
• Is it a long term result and helps me reach a
sustainable development?
• Is my concept the best one for reaching the
requested result?
We have a project! How do we deal with it now?
Planning
Risk Plan
Communication Plan
Human Resources Plan
Time Schedule
Quality Control Plan
Purchasing Plan
Change Management Plan
Communication Management
• Communication means reaching all your Stakeholders
• 90% of a Project success is due to communication
Stakeholders Identification
Communication Plan
Tracking
Time Management
Activity Definition
Activity Sequencing
Activity Resource Estimation
Activity Duration Estimation
Schedule Development
Time Management – Critical Path
Activity A ( 2 days) can start right away
Activity B ( 3 days) and Activity C ( 2 days) can start after Activity A is finished
Activity D ( 5 days) can start after Activity B is finished
Activity E ( 1 day) and Activity F ( 4 days ) can start after Activity C is finished
Activity G ( 2 days)can start after Activity E is finished
Activity H( 3 days) can start after Activity F is finished
Activity I ( 2 days) can start after Activity D, G, H are finished
After Activity I the project is complete
What is the critical path and what is it’s duration?