Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 1
Project : AllenSolly Store, Commercial Street, Bangalore
Project Manager : Bipin Barma
Area of the store : 2000sft
Budget Approved : 80 Lakhs
Execution Period : 35 days
Location : High Street , in one of the costliest area of Bangalore.
Project Objectives :
• To execute the project in a span of 35 days in comparision to the regular project duration of 50 days to save the dead
rent and to start the business as early as possible.(within the specified budget & Quality Standards)
• It should be one of the best store in the high street with ACP cladded Facade and back lit LED Signages, best interiors
for superior customer shopping experience
QN-1 : Describe what made the project manager for the project effective or ineffective.
Effectiveness is defined as being “a measure of the quality of attainment in meeting objectives; to be distinguished
from efficiency which is measured by the volume of output achieved for the input used”
Here in this case effective project management means whether or not the project met its stated goals and whether
the project Manager managed the project effectively.
� The following Qualities and deliveries made the Project Manager effective in the process of executing the project .
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 2
�
(In the following pages ,each of the above heads are been described how it helped the project manager during the execution
process and the improvements that could have been stressed upon.)
Knowledge &
Skills
Participative in
decision-making
Leadership &
Ownership
Meeting
Success Criteria
Delivering Value
Managing Risks
& Conflicts
Team Work Managing
Relationship
Effective Project Manager
Sense of
responsibility
Delegation of
Power
1. Time : Execution should
complete in 35 days
2. Cost : Capex Spent to be
within the approved budget of
80 Lakhs
3. Scope : Design to meet the
guidelines of New identity -
High Street
4. Quality : To be the best in
standards ( in comparison to
the competitors)
5. Visual Merchandising &
Facade : has to be distinctive
(standing out)
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 3
Knowledge & Skills (project manager is an Architect with formal project management credentials)
� To execute a retail store following basic skills are must
1. Understanding of design ,capability of customising minor details as per site conditions
2. Drawing reading (Auto Cad files) and making the Contractor understand what exactly to be done
3. Making Drawings –the main mode of communication
4. MS Project – execution Plan developement & tracking
5. MS office- for detail calculations and financial spread sheet presentations
6. Knowledge of materials, cost & availibility- procurement best practices
7. Leadership skill, team work culture, conflict handling capabilities and negotiation skills – helped the project
manager making the best use of all resources to achieve the project Goals.
� Area of improvement :
o Political skills – ability to build a power base and establish the right connections with upper management.
Sense of responsibility (Lead from the front)
� Project Manager was influential and one point of contact to all external and internal stakeholders for
information transfer and decision making,
� This created a transperent environment where accuracy of all data (whether it is the target dates of mile
stones, Cash flow requirements ,cost differntial values ,risk assesment etc.) remain stable.
� If there is an scope change ,design change or cost over run - every department (visual merchandising,
Opertaion, Vendors) could communicate to him for change requests having an faith it will be processed as
per organisational best practise.
� A well defined RAM (Responsibility Allocation Matrix) was prepared and followed so that each
stakeholder understands his accountibility and deliverables in accomplishing the project.
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 4
Participative in decision making
� All designs and cost related planning exercises used to go through the project manager ,he used to be the formal signoff
authority of every action that is going to be implemented .
� Being participative he could logically analyse every dimensions of actions before being getting executed ,this helped
eliminating the prevailing errors and risks
Leadership & Ownership
Through Leadership The project manager had to provide direction to all stake holders, energize others, and obtainin their
voluntary commitment to the over all vision of the project .
The mjor areas where Leadership is driven by the project manager :
� Motivating Others
� Managing Change
� Developing People
� Building Power Bases
� Understanding Behavioural styles
� Managing the Team
� Providing Project Leadership
� Managing Project Politics
� Developing Personal Effectiveness
� Managing Project Conflicts
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 5
Meeting Sucess Criteria:
� Following objectives were set and achieved :
� Time : Execution completed in 35 days ,handed over to operation on time for opening
� Cost : Capex Spent was within the approved budget of 80 Lakhs (76 lakhs)
� Scope : Design was made as per the guidelines of New identity - High Street , (store came out very well and
got awarded by the President )
� Quality : Over all execution quality was up to the standards in comparision to the other competitors.
� Visual Merchandising & Facade : New glazing with spider fittings ,Facade -ACP cladded, signage - 3D back
lit,Fore court newly paved, Interiors –new visuals been put, Luxurious Lounge been created , The Store came
out very well and opened with increased footfall.
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 6
Delivering Values : “Professionalism ,Integrity ,Corporate Values and problem solving” were the three major areas which
demanded value addition.The project manager could extract all these values from all the stakeholders throughout the project
life cycle.
0 1 2 3 4 5 6
Mean Values
Project Managerial effectiveness through Value addition
E
F
F
E
C
T
I
V
E
N
E
S
S
Critical
Zone
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 7
Managing Risks and Conflicts :
Following were the major risks handled carefully by the project manager.
1. Scope Creep : Initiation of change request form to tap time and cost impact due to changes and approval of the same
before /during execution.
a. Facade implementation cost increased twice than that was planned earlier
b. Gnerator Space re designed due to increase in size of the Machine
2. Police and Traffic issues :
a. Bribing of more than 3 Lakhs to police to move raw materials to the site during day time and to continue fit out
work in the day time.(Contingencies cap increased to 10% of the total Capex)
3. Conflicts between Contractors & departments : (difference of opinion)
a. Reduction of execution time, resulted conflicts between the contractors -through discussion & re evaluating the
dependencies every week the PM could reduce the friction for smoother execution.
� Conflict management is a critical activity which requires in depth evaluation of the Cause and require delicate handling to
keep the motivation up of all stakeholders.Most of the times it generates high level of negative energy in the project
environment. Not all who involved in the process express their desire and emotion openly and becomes difficult to
understand the issue at grass root level.
� The following is one of the frame work that could help resolving the conflicts by ( FORCING ,COLLBORATING,COPROMISING
,AVOIDING AND ACCOMODATING )- various issues.
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 8
Conflict handling Frame Work
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 9
Managing relationship, delegation of Power and Team Work
� Relationship Management through TO & RO bifurcation
� In this project environment ,relationship with vendors, external consultants,local authorities (external
stakeholders )- is mostly Task Oriented (TO) and the relationship with departments ,Team members
,management (internal stake holders) is Relationship Oriented (RO)
� Relationships:
�
Related
(high -RO)
Integrated
( high- TO
& RO)
Separated
(Low- TO
& RO)
Dedicated
(High -RO)
Relationship
Orientation
(RO)
Feelings,
mutual- trust, &
encouragement
Task Orientation (TO) – Plan, Organise & Control
Present Case
1. Relationship with
external stakeholders t
handled through proper
Planning ,Organising
and Control
2. Relationship with
Internal Stake holders
handled through
mutual trust
development
,encouragement and
caring the feelings
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 10
� Delegation of Power or Authority: (through various levels)
Creating Six levels of authority and delegating Power :
Levels Results
Level 1:
look into the problem; report all; decide what to do.
Seek Approval for
Authority
Level 2:
look into the problem; let the PM know alternative actions including pros and cons of each;
recommend one for his approval.
Justify the logic and be
authorised to implement
Level 3:
look into the problem; let the PM know what is to be done ; don’t take action until PM approves.
Seek Approval for
Authority
Level 4:
look into the problem; let the PM know what is intended to be done ; do it unless PM says “No.”
You are authorised no
further approval required
Level 5:
take action; let the PM know what you did.
Authorised ,but keep
reporting
Level 6:
take action; no further contact with PM is required
You are empowered to
do so
The Project Manager always remained as a power house of all authorities, with his due approval unless mentioned in the
Responsibility allocation Matrix the power or authority to take a decision can be shifted from one person to other.
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 11
� Team Work :
Undestanding the importance of team work, following guidelines were followed throughout the Project Life Cycle.
� Seeking out other’s opinions and involvement in matters that concern them before making decisions or plans final.
� Trusting the team to develop a consensus on an issue, even if it takes a little more time.
� Voluntarily offering your own relevant experiences, ideas and findings to colleagues who could use them.
� Acknowledging a colleague’s contribution sharing the credit
� Being non defensive and receptive to the suggestions, ideas opinions and needs of colleagues. Making the effort to
understand before criticising.
� Considering impact of your plans on others.
� Being unwilling to criticise a third party who isn’t present, not gossiping.
� Coming prepared to present or participate when you have a role in meetings.
� Expressing appreciation for teamwork extended to you that was helpful.
� Identifying and helping pick up loose ends even though they may not be your responsibility.
� Keeping people advised of changes, developments and new information on a task or project.
� Being supportive of the team’s objectives once they are set.
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 12
Summary :
With thorough evaluation of all steps we can conclude that the effectiveness of the Project Manager or any stakeholder who is
involved in the Project delivery need to have the following Values :
1. Integrated
2. Dedicated
3. Developer
4. Executive
5. Benevolent Autocrat
Related
Separated
Integrated
Dedicated
Developer
Bureaucrat
Executive
Benevolent
Autocrat
Missionary
Developer
Compro -
miser
Autocrat
RO –
Relationship
Oriented
TO – Task
Oriented
MORE
EFFECTIVE (ME)
LESS EFFECTIVE
(LE)
January 19, 2012
Bipin Barma
Project Manager Delivering Project Success Assignment by Prof. Prbhakaran
References : Class Materials ,Google, Wiki & Blogs 13
THE OUTCOME :
AllenSolly Store
Commercial
Street, Bangalore