LAX Guest Experience Partners Council
June 3, 2019
Project Overview
![Page 2: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/2.jpg)
2
Proposed Project Improvements
2
![Page 3: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/3.jpg)
3 3
Project Elements Terminal Improvements
Terminal 9 (T9) - 12 gate
facility (12 new gates)
Concourse 0 (C0) - 11 gate facility (9 new gates)
All full-service international capabilities
Better guest experience (extra
seating, check-in areas, security screening, charging stations, etc.)
Gates at T9 and C0 will replace
West Remote Gates
Landside Improvements Will serve Terminal 9
Improve CTA access & reduce
congestion on nearby public roads
New APM station at Terminal 9 & pedestrian connector to Terminal 8
Airfield Improvements
Relocate runway exits
Extension and improvement of taxiways
Enhances safety, efficiency and helps reduce delays
![Page 4: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/4.jpg)
4 4
Airfield Improvements
![Page 5: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/5.jpg)
5
Reconfiguration of taxiways/runways to
meet current FAA design standards Improved runway exit configurations
that enhance pilot visibility Decommissioning of taxiways that cross
the runway “high-energy zone” Westerly extension of Taxiway D at ADG
VI standards for operational efficiency and to meet FAA standards Improvements to Taxiways C & D for new
Terminals Relocation of Vehicle Service Roads
Taxiway Improvements – West End
Exit Taxiway Improvements
Airfield Improvements
![Page 6: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/6.jpg)
6 6
Terminal Improvements
![Page 7: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/7.jpg)
7
11 Gates (9 new) for narrowbody planes
Accommodates up to 5 widebody planes
2 Remain-Overnight Aircraft parking
positions Up to 1.2 million sf* (750,000 sf base) International (FIS) capability
4 levels (Ticketing, Concourse, Apron &
Arrivals) Pedestrian corridor to new APM station
No landside access –Passengers
processed through Terminal 1
* With option for an Offices Levels and 20% design contingency
Concourse 0 Conceptual Site Plan
![Page 8: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/8.jpg)
8
Proposed C0 Conceptual View
Proposed T0 Conceptual View
![Page 9: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/9.jpg)
9
12 New Gates for widebody planes
Up to 1.5 million sf* (1.2 million sf base)
International (FIS) capability
4 levels (Ticketing, Concourse, Apron & Arrivals)
Taxiway C improvement and easterly extension – ADG VI FAA design standards with 4-lane VSR
Pedestrian corridor to new APM station
Pedestrian corridor to Central Terminal Area (CTA) over Sepulveda
Landside access to/from roadway system
* With pedestrian corridors and 20% design contingency
Terminal 9 Conceptual Site Plan
![Page 10: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/10.jpg)
10
Proposed T9 Conceptual View
![Page 11: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/11.jpg)
11 11
Landside Improvements
![Page 12: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/12.jpg)
12
Landside Improvements
![Page 13: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/13.jpg)
13
Looking South across roads T9 & C0
![Page 14: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/14.jpg)
14
Looking East Exiting the CTA
![Page 15: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/15.jpg)
15 15
Project Benefits
![Page 16: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/16.jpg)
16
Benefits – Overall Project
Improves Passenger Experience
Improves Community Experience
Enhances Safety & Carrier
Experience
Increases Business
Opportunities
Reduced wait times on tarmac Seamless transition between
international & domestic flights Reduces on-ground travel by
busing from remote gates Contact gates provide better
passenger experience than busing from remote gates
More seating, concessions & retail
Reduced traffic congestion on neighborhood streets
Promotes sustainable practices - minimum LEED Silver certification
Less aircraft idling reduces air pollutant emissions
Connection to the APM & regional mass transit
Increases safety & efficiency
Reduced tarmac wait times Removes remote gates –
less busing Improves taxiways Enhances aircraft movement
New Concessionaires (restaurants & shops)
SBE & job opportunities during construction
Local jobs & local business opportunities
![Page 17: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/17.jpg)
17 17
Next Steps & Proposed Schedule
![Page 18: Project Overview - Microsoft · Project Overview . 2 Proposed Project Improvements 2 . 3 3 Project Elements Terminal Improvements Terminal 9 (T9) - 12 gate facility (12 new gates)](https://reader036.vdocuments.net/reader036/viewer/2022062605/5fd476bb1a0c2a5e50165210/html5/thumbnails/18.jpg)
18
CEQA Process
Q1 Q2 Q1 - Q4 Q1 Q3/Q4 Q4
2019 2019 2019 2019 2020 2020 2020