Project ‐ Quarterly Progress Report
Promoter’s Name : RAMKY WAVOO DEVELOPERS PVT.LTD.
Project Name : LEMONGRAZ
Project Registration No : TN/02/BUILDING/0036/2017
Quarter Ending : JANUARY 2020.
A. Sales
Sl.
No.
Description No. Total Area
1. Plots/Flats Booked size wise (As given in Carpet Area
Statement while registering)
114 144780.0 Sq.m
2. Parking Slots 114
3. UDS Registered in Sq. m. 81 2715.46 Sq. m
B. Construction
Sl.No. Description Block/Tower
No. Status
Structure – Stilt to Terrace Floor Completed.
Block Work – 1st to 12th floor block work completed.
Internal Plastering ‐ 1st to 12th floor plastering work completed.
External Plastering ‐ East, West & South and North side of the
building Plastering work completed.
Water Proofing Work ‐ 1st to 12th floor water proofing work
Completed.
1
Stage of
construction
of each
Block/Tower,
Floor wise
Single Block
Corridor Tiling Work ‐ 1st to 12th floor corridor tiling work completed.
Handrail ‐ Staircase ‐ 1, 2, 3 & 4 ‐ Stilt to Terrace Floor Work
Completed
Kitchen Platform ‐ Completed
Joineries ‐ Upto 11th floor completed
Plumbing ‐ Toilets water supply works ‐ 1st to 12th floor work
Completed.
Sewerage Ling Works ‐1st to 12th floor work completed.
Electrical ‐ Fixing of Conduits ‐ 1st to 12th floor completed.
Shaft 1, 2, 3 – Hydrant Valve riser work - Completed
Staircase Fire door Upto 12th floor completed
PA System & Fire alarm conduits Completed
External Hydrant Pipe line 100 % Completed
2nd Putty ‐ 1st to 12th floor 1st coat putty work completed.
Out of 4 lift, 1 Lift 100 % Completed , 1 Test &
Commissioning Pending , balance 2 lift Work In Progress
2
Status of
common
Amenities for
each
Block/Tower,
Item wise
Single
Block
Swimming Pool & Club House ‐ Structural & Block work
completed, Finishing work is in progress.
Stilt floor Plumbing Work Completed, Electrical 75 %
Completed
Stilt floor Fire Fighting – 100 % Completed
Compound Wall – Completed
East Side Security Room- 100% Completed
South Side Security Room 70 % Completed Balance Work
in Progress
West Side Road Work - Completed
North Side Road Work – 80 % Completed
South Side Road Work - Work In Progress
East Side Road Work - Work In Progress
C. Details of Clearances
1. Completion Certificate No. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (only CC No. in Text Format)
2. Compliance Report, if any (Kindly Specify) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
3. Annual Audit Report of Special Account in Form 7 ‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
D. Latest Photo with Date (Atleast from 2 angles) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ (in PDF Format)
Note: Report the above particulars under “Registered Projects” in www.tnrera.in
Reg. No.: TN/02/Building/0036/2017
PROJECT STATUS REPORT
JANUARY- 2020
Lemongraz @ Ambattur
Type Area in Sq ft No of Apt’sNo. of Apt’s
Booked
2BHK 1047 to 1053 61 Nos 56
3BHK (Medium) 1263 to 1295 30 Nos 22
3BHK (Large) 1493 to 1498 28 Nos 25
Duplex 2120 to 2567 6 Nos 3
2BHK with PT 1203 to 1914 4 Nos 1
Total 129 107
Car park Details No. of Lots
Booked
Total No Of Car Park Provided 136 Nos 100
Covered Car Park 49 Nos 42
Surface Car Park 80 Nos 67
Visitor Car Park 7 Nos -
Project Details
FLOOR STRUCTURAL BLOCKWORK PLASTERING (Internal)
STILT 100% 100% 100%
1ST FLOOR 100% 100% 100%
2ND FLOOR 100% 100% 100%
3RD FLOOR 100% 100% 100%
4TH FLOOR 100% 100% 100%
5TH FLOOR 100% 100% 100%
6TH FLOOR 100% 100% 100%
7TH FLOOR 100% 100% 100%
8TH FLOOR 100% 100% 100%
9TH FLOOR 100% 100% 100%
10TH FLOOR 100% 100% 100%
11TH FLOOR 100% 100% 100%
12TH FLOOR 100% 100% 100%
TERRACE FLOOR 100% 100% 100%
Progress Status
FLOOR STRUCTURAL BLOCKWORK FINISHES REMARKS
CLUB HOUSE 100% 100% 85%
SWIMMING POOL 100% 100% 70%
AMENITIES
Progress Status
ACTIVITY PROGRESS STATUS
STRUCTURE WORK (PERGOLA): Pergola 5, 6, 7 – 100 % Completed
Pergola 3, 4 – 100 % Completed
Pergola 1, 2 – 100 % Completed
PARAPET WALL: Pour 1 – 100 % Completed
Pour 2 – 100 % Completed
PLASTERING (External): East, South & West sides of the building – 100 % Completed
North side of the building – 100 % Completed
PLASTERING (Ceiling): 1st to Terrace Floor – 100 % Completed
WATERPROOFING WORKS: 1st to 12th Floor – 100% Completed
PUTTY – 2nd COAT 1st to 12th Floor – 100% Completed
TILING WORKS 1st to 12th Floor – 100% Completed
HANDRAILING Staircase 1,2,3 & 4 – 1st to 12th Floor – 100 % Completed
KITCHEN PLATFORM FIXING: 1st to 12th -100 % Completed
Progress Status
ACTIVITY PROGRESS STATUS
UG SUMP – COVER SLAB Completed
FIXING OF DOORS 1 to 11th Floor – 100 % Completed, 12TH Floor 90 % Completed
EXTERNAL WORKS
Compound Wall Completed
Security Room East Side Security Room- 100% Completed
South Side Security Room 70 % Completed Balance Work in Progress
Road Work • West Side Road Work - Completed
• North Side Road Work – 80 % Completed
• South Side Road Work - Work In Progress
• East Side Road Work - Work In Progress
Progress Status
ACTIVITY PROGRESS STATUS
PLUMBING:
Toilet Water supply Works Upto 12th Floor - Completed
Sewerage line works Upto 12th Floor - Completed
ELECTRICAL:
Fixing of Conduits Upto 12th Floor - Completed
Wiring Work Upto 4th Floor - Completed
FIRE FIGHTING: Shaft 1, 2, 3 – Hydrant Valve riser work - Completed
Staircase Fire door Upto 12th floor completed
PA System & Fire alarm conduits Completed
Terrace – Fire Hydrant pipe line Completed
Pump Room- Erection Completed, Testing & Commissioning Work In Progress
External Hydrant Pipe line 100 % Completed
INSTALLATION OF LIFTS: Out of 4 lift, 1 Lift 100 % Completed , 1 Test & Commissioning Pending , balance 2 lift Work In Progress
STILT FLOOR Plumbing Work Completed, Electrical 75 % Completed
Fire Fighting – 100 % Completed
Progress Status
East Side Elevation
Structural work up to 12th
floor has been completed.
Block work up to 12th floor Completed
Internal Plastering work up to 12th floor Completed
External plastering 100 % completed.
Electrical/Plumbing works Completed
West Side Elevation
Structural work up to 12th
floor has been completed.
Block work up to 12th floor Completed
Internal Plastering work up to 12th floor Completed
External plastering 100 % completed.
Electrical/Plumbing works Completed
North Side Elevation
Structural work up to 12th
floor has been completed.
Block work up to 12th floor Completed
Internal Plastering work up to 12th floor Completed
External plastering 100 % completed.
Electrical/Plumbing work Completed
South Side Elevation
Structural work up to 12th
floor has been completed.
Block work up to 12th floor Completed
Internal Plastering work up to 12th floor Completed
External plastering 100 % completed.
Electrical/Plumbing works in progress.
1st FLOOR
1st FLOOR :
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has been
completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
2nd FLOOR
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been
completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has
been completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
2nd FLOOR :
3rd FLOOR
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been
completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has
been completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
3rd FLOOR :
4th FLOOR
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been
completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has
been completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed .
4th FLOOR :
5th FLOOR
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been
completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has
been completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
5th FLOOR :
6th FLOOR
Structural work has been completed. Block work has been completed. Plastering work has been completed. Ceiling plastering has been completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has been
completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
6th FLOOR :
Upto 12th FLOOR
Structural work has been completed.
Block work has been completed. Plastering work has been
completed. Ceiling plastering has been
completedWaterproofing work has been
completed Tiling work has been completed.Water supply pipeline works has
been completed. Kitchen Platform work has been
completed. Hand railing has been completed. Putty 2nd has been completed
7th FLOOR :
TERRACE FLOOR
Terrace FLOOR :
Block work has been completed
Parapet block work has been completed
Plastering work has been completed
Pergola Work has been completed .
Waterproofing work has been completed
MEP has been completed
TERRACE FLOOR
Terrace FLOOR :
Block work has been completed
Parapet block work has been completed
Plastering work has been completed
Pergola Work has been completed .
Waterproofing work has been completed
MEP work has been completed
TERRACE FLOOR
Terrace FLOOR :
Block work has been completed
Parapet block work has been completed
Plastering work has been completed
Pergola Work has been completed .
Waterproofing work has been completed
MEP work has been completed
AMENITIES
AMENITIES - Swimming Pool :
Structural work has been completed.
Block work has been completed.
Water proofing work is in progress.
AMENITIES
AMENITIES - Swimming Pool :
Structural work has been completed.
Block work has been completed.
Water proofing work is in progress.
AMENITIES
AMENITIES – CLUB HOUSE :
Structural work has been completed.
Block work has been completed.
Plastering work has been completed.
Primer painting work has been completed.
Interior Work in Progress
AMENITIESExternal Development Work
Compound Wall – Completed
East Side Security Room- 100% Completed
South Side Security Room 70 % Completed Balance Work in Progress
West Side Road Work - Completed
North Side Road Work – 80 % Completed
South Side Road Work - Work In Progress
East Side Road Work - Work In Progress
AMENITIESExternal Development Works
Compound Wall – Completed
East Side Security Room- 100% Completed
South Side Security Room 70 % Completed Balance Work in Progress
West Side Road Work - Completed
North Side Road Work – 80 % Completed
South Side Road Work - Work In Progress
East Side Road Work - Work In Progress