Total PetrochemicalsDeep Conversion Project Port Arthur, Texas$59,700,000 Contract Value
Fluor
20 Month Duration
818,800 Workhours
182,667 LF of Piping –Spools
10,393 Pipe Welds -233,609 Dia. Weld Inches
1,286 Hydrostatic Test Packages
• Brownfield project
• Turner set up Contractor Safety Awareness program to include all site contractors
• 134 pipe rack modules
• 2,237 tons of field erected structural steel
Zero Lost Time Accidents