project report on thermal plant
TRANSCRIPT
Training Report On Water Treatment and Coal testing At Guru Nanak Dev Thermal Plant Bathinda
Submitted By: Mahinder Singh UE89034
Under the guidance of
Mrs. Er. Mechanical Dptt. Add. S.E. T.T. cell GNDTP,Bathinda
Department of Mechanical Engineering
U.I.E.T. PANJAB UNIVERSITY, CHANDIGARH
ACKNOWLEDGEMENT
DECLARATION
I hereby declare that the project work entitled ‘Water treatment and coal testing’
is an authentic record of my own work carried out at Bathinda as requirements of
six months Industrial Training for the award of the degree of B.E. at University
Institute of Engineering & Technology, Panjab University, Chandigarh under the
guidance of Er. T.N.Bansal and Mrs. Anjali Gupta, during 1jan-24May 2012.
student
Date: 28May2012
Certified that the above statement made by the student is correct to the best of
our knowledge and belief.
Mrs. Er.
Mechanical Dptt. Add. S.E. T.T.cell
UIET GNDTP, Bathinda
INTRODUCTION
Guru Nanak Dev Thermal Power Plant is a coal-based plant. The
requirement of coal for four units based on specific fuel consumption of 0.60 kg /
kWh . The conveying and crushing system will have the same capacity as that of
the unloading system. The coal comes in as large pieces. This coal is fed to
primary crushers, which reduce the size of coal pieces from 400mm to 150mm.
Then the coal is sent to secondary crusher through forward conveyors where it is
crushed from 150mm to 20mm as required at the mills. Then the coal is sent to
boilers with the help of primary fans. The coal is burnt in the boiler. Boiler
includes the pipes carrying water through them; heat produced from the
combustion of coal is used to convert water in pipes into steam. This steam
generated is used to run the turbine. When turbine rotates, the shaft of
generator, which is mechanically coupled to the shaft of turbine, gets rotated so,
three phases electric supply is produced.
The basic requirements are:-
Fuel (coal)
Boiler
Steam turbine
Generator
Ash handling system
Unit auxiliaries
HISTORY
.
Due to high rate of increasing population day by day, widening gap between
power demand and its availability was one the basic reason for envisaging the
G.N.D.T.P. for the state of Punjab. The other factors favoring the installation of
the thermal power station were low initial cost and comparatively less
gestation period as compared to hydro electric generating stations. The
foundation stone of G.N.D.T.P. at bathinda was laid on 19th November 1969,
the auspicious occasion of 500th birth anniversary of great Guru Nanak Dev Ji.
The historic town of bathinda was selected for this first and prestigious
thermal project of the state due to its good railway connections for fast
transportations of coal, availability of canal water and proximity to load center.
The total installed capacity of the power station 440MW with four units of
110MW each. The first unit of the plant was commissioned in September, 1974.
Subsequently second, third and fourth units started generation in September
1975, March 1978, January 1979 respectively. The power available from this plant
gives spin to the wheels of industry and agricultural pumping sets.
LANDMARKS ACHIEVED
G.N.D.T.P. won an award of Rs. 3.16 crores from Govt. of India for better
performance in 1983-84.
It achieved a rare distinction of scoring hart Rick by winning meritorious
productivity awards of Govt. of India, Ministry of Energy for year 1987,
1988 and 1989 due to its better performance.
It again won meritorious productivity awards during the year 1992-1993
and 1993-94 and has become entitled for the year 1996-1997 for better
performance.
It also won awards for reduction in fuel oil consumption under Govt. of
India incentive scheme years from 1992-1993 (awards money for 1992,
1993 and 1994 already released for 1995, 1996 and 1997 under the
consideration of Govt. of India).
G.N.D.T.P. had achieved a generation of 2724240 LU’s (at a PLf of 70%)
and registering an oil consumption as low as 1.76ml/kwh during the year
1993-94 has broken all previous records of performance since the inception
of plant.
WORKING AT GNDTP
Coal received from collieries in the rail wagon is mechanically unloaded by
Wagon Tippler and carried by belt Conveyor System Boiler Raw Coal Bunkers after
crushing in the coal crusher. The crushed coal when not required for Raw Coal
Bunker is carried to the coal storage area through belt conveyor. The raw coal
feeder regulates the quantity of coal from coal bunker to the coal mill, where the
coal is pulverized to a fine powder. The pulverized coal is then sucked by the
vapour fan and finally stored in pulverized coal bunkers. The pulverized coal is
then pushed to boiler furnace with the help of hot air steam supplied by primary
air fan. The coal being in pulverized state gets burnt immediately in the boiler
furnace, which is comprised of water tube wall all around through which water
circulates. The water gets converted into steam by heat released by the
combustion of fuel in the furnace. The air required for the combustion if coal is
supplied by forced draught fan. This air is however heated by the outgoing flue
gases in the air heaters before entering the furnace.
The products of combustion in the furnace are the flue gases and the ash.
About 20% of the ash falls in the bottom ash hopper of the boiler and is
periodically removed mechanically. The remaining ash carried by the flue gases, is
separated in the electrostatic precipitators and further disposed off in the ash
damping area. The cleaner flue gases are let off to atmosphere through the
chimney by induced draught fan.
The chemically treated water running through the water walls of boiler
furnace gets evaporated at high temperature into steam by absorption of furnace
heat. The steam is further heated in the super heater. The dry steam at high
temperature is then led to the turbine comprising of three cylinders. The thermal
energy of this steam is utilized in turbine for rotating its shaft at high speed. The
steam discharged from high pressure (H.P.) turbine is returned to boiler reheater
for heating it once again before passing it into the medium pressure (M.P.)
turbine. The steam is then let to the coupled to turbine shaft is the rotor of the
generator, which produces electricity. The power from the generator is pumped
into power grid system through the generator transformer by stepping up the
voltage.
The steam after doing the useful work in turbine is condensed to water in the
condenser for recycling in the boiler. The water is pumped to deaerator from the
condenser by the condensate extraction pumps after being heated in the low
pressure heater (L.P.H) from the deaerator, a hot water storage tank. The boiler
feed pump discharge feed water to boiler at the economizer by the hot flue gases
leaving the boiler, before entering the boiler drum to which the water walls and
super heater of boiler are connected.
The condenser is having a large number of brass tubes through which the
cold water is circulated continuously for condensing the steam passing out sides
the surface of the brass tubes, which has discharged down by circulating it
through the cooling tower shell. The natural draught of cold air is created in the
cooling tower, cools the water fall in the sump and is then recirculated by
circulating water pumps to the condenser.
PLANT’S SALIENT FEATURES
PROJECT AREA:-
Power plant 238 acres
Ash disposal 845
Lake 180
Residential colony 285
Marshalling yard 256
Total area 1804
TOTAL COST:- Rs. 115 crores
STATION CAPACITY:- four units of 110MW. Each
BOILER:-
Manufacturers B.H.E.L.
Maximum continuous rating (M.C.R.) 375 T/hr.
Superheater outlet pressure 139 kg/cm²
Reheater outlet pressure 33.8 kg/cm²
Final superheater/reheater temperature 540C
Feed water temperature 240C
Efficiency 86%
Coal consumption per day per unit 1400 tones (Approximate)
STEAM TURBINE:-
Manufacturers B.H.E.L.
Rated output 110 MW.
Rated speed 3000 r.p.m.
Number of cylinders three
Rated pressure 130 kg/cm²
Rated temperature 535C
Condenser vacuum 0.9 kg/cm²
GENERATOR:-
Manufacturers B.H.E.L.
Rated output
(Unit- 1 & 2) 125000KVA
(Unit -3 & 4) 137000KVA
Generator voltage 11000 volts
Rated phase current
(Unit –1 & 2) 6560 Amps.
(unit –3 & 4) 7220 Amps.
Generator cooling hydrogen
BOILER FEED PUMPS:-
Number per unit two of 100% duty each
Type centrifugal
Rated discharge 445 T/hr.
Discharge head 1960 MWC.
Speed 4500 r.p.m.
CIRCULATING WATER PUMPS:-
Numbers for two units five of 50% duty each
Type mixed flow
Rated discharge 8600 T/hr.
Discharge head 24 MWC.
COOLING TOWERS:-
Numbers four
Water cooled 18000 T/hr.
Cooling range 10C
Height 120/122 metres
COAL PULVERISING MILLS:-
Numbers three per unit
Type drum-ball
Rated output 27 T/hr.
Coal bunkers 16 per unit
RATING OF 6.6 KV AUXILLIARY MOTORS:-
Coal mill 630 KW
Vapour fan 320 KW
C.W. Fan 800/746 KW
Coal crusher 520 KW
Primary air fan 320 KW
Forced draught fan 320 KW
Boiler feed pump 3500 KW
Induced draught fan 900/1000 KW
Condensate pump 175 KW
DIFFERENT CELLS OF PLANT
CHP (Coal Handling Plant)
The G.N.D.T.P. units are primarily coal-fired units and the coal consumption at
maximum continuous rating (M.C.R.) per unit is about 58 T/Hr. the coal used at
G.N.D.T.P. is of bituminous and sub-bituminous type and this is received from
some collieries of M.P. and Bihar.
UNLOADING OF COAL:-
In order to unload coal from the wagons, two Rotaside Tipplers of Elecon
make are provided. Each is capable of unloading 12 open types of wagons per
hour. Normally one tippler will be in operation while the other will be standby.
The loaded wagons are brought to the tippler side by the loco shunters. Then with
the help of inhaul beetle one wagon is brought on the tippler table. The wagon is
then tilted upside down and emptied in the hopper down below. The tippler is
equipped with the integral weighbridge machine. This machine consists of a set of
weighing levers centrally disposed relative to tippler. The rail platform rests on
the weighing girders and free from rest of the tippler when the wagon is being
weighed. After weighing the loaded wagons is tipped and returned empty to the
weighing girders and again weighed. Thus the difference of the gross weight and
the tare weight gives the weight of the wagon contents. The tipplers are run by
motors of 80 H.P. each through gears only.
IMPROVED DESIGN OF WAGON TIPPLER :-
We under the new scheme, propose to raise the level of hopper to the
ground level. Correspondingly, the level of the platform of wagon tippler will also
have to be adjusted. Also the building structure covering the hopper and tripper
will be done away with keeping the hopper open. In this way the screen of the
hopper becomes accessible to pay loader trucks. Now, when the screen gets
blocked, a pay loader truck can be employed which will lift all the over sized coal
and take it to a suitable place where it can be broken either manually or by a
crusher. Thus it will save time as the trolleys can be emptied faster, saving
damages.
USE OF LOAD CELL TYPE WEIGHBRIDGE FOR WEIGHMENT IN MOTION :-
Load ceil type weighbridges are sometimes called dynamic weighbridge because
the wagons can be handled over them at a maximum speed of up to 12 m.p.h.
They consists of two platforms one for gross and one for tare weights. Each
wagon weight is automatically printed out and so is the railway loop. First the
gross weights are established and memorized, then the train is moved over the
rail track hopper for discharge, after the empty train is moved out over the tare
weighbridge platform where the tare weights are printed out. Finally the total net
weight is computed and printed out. The load cells at each weighbridge are
connected to a digitizer suitable for converting the analogue output of the load
cell into digital form.
Wagon Tippler
When coal reaches the plant, normal size of coal is about 500mm primary
crusher 120mm secondary crusher 25mm coal mill pulvarised coal
,feeded in boiler.
Before this boiler is preheated with oil upto 3500c,then oil supply is cut down.
Conveyer Belt
Boilers
It is a single drum, balanced draught, natural circulation, reheat type, vertical
combustion chamber consists of seamless steel tubes on all its sides through
which water circulates and is converted into steam with the combustion of fuel.
The temperature inside the furnace where the fuel is burnt is of the order of
1500C. The entire boiler structure is of 42meter height.
BOILER CHIMNEY:-
The flue from the boiler, after removal of ash in the precipitators, is let off to
atmosphere through boiler chimney, a tall Ferro-concrete structure standing as
high as the historic Qutab Minar. Four chimneys, one for each unit, are installed.
The chimney is lined with fire bricks for protection of Ferro-concrete against hot
flue gases. A protective coating of acid resistant paint is applied outside on its top
10 meters.
Boilers burn the fuel transferred from the tank and use the resulting heat to
convert water into steam. Inside the boilers are tens of thousands of water-
carrying tubes. When combustion commences, the temperature inside the boilers
rises to between 1,100 and 1,500°C, the water inside the tubes is turned into
high-temperature and high-pressure steam, and the steam is transferred to the
steam turbines.
CIRCULATING WATER PUMP:-
Two nos. of circulating water pumps provided for each unit, circulate water
at the rate of 17200 T/hr. in a closed cycle comprising of Turbine Condenser and
Cooling Tower. An additional Circulating Water Pump provided serves by for two
units. The water requirement for bearing cooling of all the plant auxiliaries is also
catered by these pumps.
Boiler
Boiler specifications
Feed water temperature 240C
Final super heater/reheater temperature 540C
Super heater outlet pressure 139kg/cm²
Efficiency 86%
Coal consumption per day per unit 1400 tones (Approximate)
Turbines
The steam rotates the turbine blades at a high speed of 3,000 rpm. This turns the
power generator, which is directly connected to the turbines, and electricity is
produced as a result. This electric power is then delivered along power
transmission lines and through substations to the homes of customers.
Turbine is a prime mover for the Generator in the power plant. In steam turbine,
the potential energy of steam is transformed into kinetic energy and later in its
turn is transformed into the mechanical energy of the rotation of the turbine
shaft. The common types of turbines are:-
IMPULSE TURBINE:- In this type of turbine, steam expands in the
nozzles and its pressure does not alter as it moves over the blades.
REACTION TURBINE:- In this type of turbine, the steam expands
continuously as it passes over the blades and thus there is a gradual fall in
pressure during expansion.
IMPULSE TURBINE
REACTION TURBINE
Different types of steam turbines are used in Thermal Power Plant but the
ones which are used at G.N.D.T.P. are categorized as follows:-
Sr. No. Type of Turbine Turbines at G.N.D.T.P.
1. Horizontal/Vertical Horizontal
2. Single/Multi-cylinder Multi-cylinder (3-cylinder)
3. Impulse/Reaction Impulse
4. Condensing/Non-condensing Condensing
5. Reheat/Non-reheat Reheat
6. Regenerative/Non- Regenerative With bypass (ST-1)
7. With bypass/Without bypass Without bypass (ST-2)
MAIN TECHNICAL DATA
a) The basic parameters:
Rated output measured at Terminal of the generator. 110.000KW
Economical output. 95.000KW
Rated speed. 3.000RPM
Rated temp. of stearn just before the stop valve. 535C
Max Temp. of steam before the stop valve. 545C
Rated pressure of steam before the MP casing. 31.63C
Max. pressure of steam before the MP casing 35C
Rated temp. of steam before the MP casing. 535C
Max. temp. of steam before the MP casing. 545C
b) System of turbine:
4 Governing valves +2 interceptor valves HP cylinder- 2 Row Curtis wheel +8
moving wheels.
Wt. Of HP rotor approx. 5,500 Kg.
MP cylinder - 12 Moving wheels.
Wt. Of MP rotor. Approx. 11,000 Kg.
LP cylinder - 4 Moving wheels of double flow design.
Wt. Of MP rotor approx. 24,000 Kg.
Direction of the turbine rotation - To the right, when looking at the turbine from
the front bearing pedestal.
General Specifications of Turbine
Manufacturers B.H.E.L.
Rated output 110 MW.
Rated speed 3000 r.p.m.
Number of cylinders three
Rated pressure 130 kg/cm²
Rated temperature 535C
TURBO-GENERATOR:- The hydrogen-cooled generator is directly coupled to the turbine shaft
rotating at speed of 3000 rpm generating electricity at 11000 volts. The turbine is
horizontal, three casings, reheat, steam condensing, regenerative and of impulse
type equipped with a precise oil operated speed governor. The generated voltage
is stepped by unit power transformer to state grid system.
Circulating water pump:-
Two nos. of circulating water pumps provided for each unit, circulate water
at the rate of 17200 T/hr. in a closed cycle comprising of Turbine Condenser and
Cooling Tower. An additional Circulating Water Pump provided serves by for two
units. The water requirement for bearing cooling of all the plant auxiliaries is also
catered by these pumps.
NEED OF A CONDENSER:- A condenser where the exhaust steam from the turbine
is condensed, operates at a pressure lower than atmosphere. There are two
objects of using a condenser in a steam plant. There are two objects of using a
condenser in a steam plant:-
- To reduce the turbine exhaust pressure so as to increase the specific output
of turbine. If the CW cooling water temperature in a condenser is low
enough. It creates a back pressure (vacuum) for the turbine. This pressure is
equal to the saturation pressure corresponding to the condensing steam
temperature. Which is a function of cooling water temperature. It is known
that the enthalpy drop or turbine work per unit pressure drop is much
greater at the low pressure end than at the high pressure end of a turbine.
- A condenser by lowering the back pressure say 1.013 to 0.074 bar, thus
increases the plant efficiency and reduces the steam flow for a given
output. The lower the pressure, the greater the output and efficiency. It is
important to use lowest possible cooling water temperature.
This reduces the temperature rise of cooling water in the condenser tubes
to 5-8C so that the tube outer surface temperature remains low and
consequently, the condensing steam temperature is low and vacuum is
high.
- To recover high quality feed water in the form of condenser and feed it
back to the steam generator without any further treatment.
As a result only the make up water to replenish the water losses in the
cyclic plant needs be treated.
TYPES:- There are two broad classifications:-
a) Direct contact type condenser:- where the condensate and cooling
water directly mix and come out as a single stream.
b) Surface condenser:- which are shell and tube heat exchangers where the
two fluids do not come in direct contact and heat released by the
condensation of steam is transferred through walls of the tubes into the
cooling water continuously circulating inside them.
DIRECT CONTACT CONDENSERS:-
- Spray condenser
- Barometric condenser
- Jet condenser
In the spray condenser, the cooling water is sprayed into the steam. Steam by
mixing directly with cold water gets condensed. The exhaust steam from the
turbine at state 2 mixes with cooling water at state 5 to produce saturated
water at state 3, which is pumped to state 4.
In barometric condenser, the cooling water is made to fall in a series of
baffles to expose large surface area for the steam fed from below to come in
direct contact. The steam condenses and falls in a tail pipe to the hot well
below. By virtue of its static head, the tail pipe compresses the mixture to
atmospheric pressure.
In a jet condenser, the height of the tail pipe is reduced by replacing it with a
diffuser. The diffuser helps raising the pressure in a short distance than a tail
pipe.
SURFACE CONDENSERS:- Surface condenser is another type of condenser used
in power plants. In GURU NANAK DEV THERMAL PLANT surface condensers are
used. These are essentially shell and tube heat exchangers. For the
convenience of cleaning and maintenance cooling water flows through the
tubes and steam condenses outside the tubes. In our plant surface condenses
two passes of water boxes on each side. The hot well acts as a reservoir of the
condensate. The condenser plays a vital role. In our plant two surface
condensers are used in one plant’s unit. There are 6800 tubes in one
condenser.
CONDENSER
CONDENSATE CYCLE:- Steam after working in the three casings of the turbine
i.e. H.P., M.P. and L.P. casing is considered in two surface condensers in each
unit installed just below the L.P. turbine’s exhaust hood. The condenser so to
call hot well from where it is pumped up to deaerator by condensate
extraction pumps through different heating stages. The different heating
stages through which the condensate flows and gets heated up gradually
before finally reaching the deaerator (feed water tank) are as below:-
HEATING STAGE TEMP. RISE AT FULL LOAD
Main steam jet air ejector 43-48C
LPH-1 and LPH-2 48-73C
Chimney steam condenser 73-80C
Gland steam condenser 73-80C
LPH-3 80-97C
LPH-4 97-121C
LPH-5 121-152C
Deaerator 152-158C
The temperature rise of the condensate after passing through above heating
stages is from 45C at hot well to 145C at the deaerator (feed water tank). The
feed water tank acts as a feed water storage vessel and deaerator functions to
remove dissolved oxygen in the feed water.
CONDENSER:- The function of the surface condenser is to condense the steam
exhausted from the L.P. casing and to create vacuum in order to increase the
heat drop. Capacity of each hot well is 6200 liters and the temperature of
condensate in the hot well is about 40-45C.
PARTICULARS OF CONDENSATE:-
EXTRACTION PUMP:-
Number of pumps: 3 for each unit with 50% capacity each, one stand by.
Number of stages: 6
Discharge pressure: 20.5-24.5 kg/cm²
Suction pressure: -0.8 to –0.9 kg/cm²
STEAM JET AIR EJECTOR:-
The main function of steam jet air ejector is to maintain the vacuum in the
steam condenser by ejecting the air and non-condensate gases. The steam from
pressure reducing station is supplied to steam jet air ejector. This steam when
passed through the nozzles in a venturi develops pressure drop, which causes the
air and non considerable gases to rush from the condenser, thus maintaining the
required vacuum in the condenser. After that heat of this steam is utilized in
heating up the main condensate flowing through in the steam jet air ejector. The
steam jet air ejector is built up in the condenser.
LOW PRESSURE HEATERS:-
There are five numbers of L.P. heaters through which the main condensate
flows and gets heated up gradually in each stage of heaters before finally going to
the deaerator.
The L.P. heaters 1 and 2 are in two parts and placed in the exhaust hood of
condenser i.e. exhaust hood of L.P. turbine and are connected in series. L.P.H.-3,
L.P.H.-4 and L.P.H.-5 are placed in chimney steam condenser and gland steam
condenser in the condensate flow circuit. The charging steam to these heaters is
given from the steam extractions taken from the L.P. & M.P. cylinders of the
turbine. Steam extraction to L.P.H.-1 is taken from L.P. casing in two parallel
flows, same in L.P.H.-2. Steam to L.P.H.-3 is also taken from L.P. casing. Where as
steam to L.P.H.-4 and L.P.H.-5 is taken from M.P. casing.
The main condensate gets heated up by about 100C after passing through these
heating stages. The condensate of heating steam in these L.P. heaters is known as
drip.
CHIMNEY STEAM CONDENSER:-
It is a sort of heater in which waste chimney steam, taken from the outer leaks
of the gland seals of H.P., M.P. and L.P. cylinders of the turbine, is utilized in
heating up the main condensate. The drip of chimney steam condenser is
generally mixed with air and is collected in impure condensate tank from where it
is pumped to floor drains.
GLAND STEAM CONDENSER:-
It is also a sort of heaters, steam to gland steam condenser is taken from inner
leaks of the sealing glands of H.P. and front gland of M.P. cylinders of the turbine
and after heating the main condensate, the drip of gland steam condenser being
pure, is directly taken to the hot well.
Cooling towers:-
Cooling Towers
Cooling Towers of the power plant are the land mark of the Bathinda City
even for a far distance of 8-10 kilometers. One cooling tower is provided for each
unit for cooling 18000 tones of water per hour by 10C. cooling towers are
massive Ferro-concrete structure having hyperbolic profile creating natural
draught of air responsible for achieving the cooling effect. Cooling tower is as high
as 40 storey building.
Ash precipitators
WORKING PRINCIPLE OF ESP
The electrostatic precipitator installed at GNDTP,Bathinda units to extract
dust, utilizes electrostatic forces to separate dust particles from the gas be
cleaned. The gas is conducted to a chamber containing “Curtains” of vertical steel
plates. These curtains divide the chamber into a number of parallel gas passages.
A frame with secured wires is located within each passage. All the frames are
linked to each passage. The frames are linked to each other to form a rigid
framework.
The entire frame works is held in place by four support insulators, which is
electrically from all, which are grounded.
A high voltage direct current is applied between the framework the ground
thereby creating a strong electrical field between the wires in the framework and
the steel curtains. The electrical become strongest near the surface of the wires,
so strong that an electrical discharge. The corona “discharge” develops along the
wires. The gas is ionized in the corona discharge and large quantity of positive and
negative ions are formed. The positive ions are immediately attracted towards the
negative wires by the strength of the field indicate the negative ions however
have to traverse the entire space between the electrodes to reach positive
curtains.
Enroute towards the steel curtains, the ions collide and adhere to the
particles in the gas. The particles thereby become electrically charged and also
begin to travel in the same direction as the ions towards the steel curtains. The
electrical force on each particle becomes much greater than the gravitational
force on the particle. The speed of migration towards to steel curtains is therefore
much greater than the speed of sedimentation in free fall.
The fly ash carried by outgoing flue gases is arrested at two stages. In the
mechanical precipitators, the coarse ash particles are separated out by centrifugal
action. In the Electrostatic Precipitators, the finer ash particles in the flue gases
are made to pass through high voltage electric field, where these particles get
ionized and are attracted towards the collecting electrodes. The dry ash is
collected in the hoppers underneath and further deposited off in Ash Disposal
Area.
Project
Water treatment and Coal testing
Boiler is the heart of thermal plant, its main purpose is to convert water into steam.
N a t u r a l w a t e r i s a v a i l a b l e i n abundance, but it contains impurities in many forms which are as following types.
Types of impurities….
Water hardness is primarily because of calcium and magnesium minerals, and hardness is responsible for scale formation.
Carbonates or temporary hardness- ‘Ca’ and ‘Mg’ bicarbonates are responsible for alkaline hardness, but on applying heat release CO2
and form soft scale.
Non-Carbonates or permanent hardness- due to presence of salt of calcium and magnesium but in form of sulphates and chlorides. On applying heat these ppt. out and form hard scale, which is difficult to remove.
Water Alkalinity is because of bicarbonates, carbonates.
Alkalinity can convert to CO2 in steam. This causes corrosion.
When pH is below the recommended range chances of corrosion increases, and when it is above recommended value then chances of scaling increases.
Boiler scale lowers heat transfer due to low thermal conductivity. Heat transfer may be reduced as much as 5-10% by the presence of scale.
Due to scaling following are the negative effects on the working of plant
a. increased fuel bill by decreasing the operating efficiencyb. thermal damagec. increased cleaning time and cleaning costsd. reduced working life of a boiler.
Pre Treatment of Water
Clarifier (Alum dosing)
To make water free from suspended, colloidal and organic impurities, process involved in pre-treatment are:-
Canal water
Lake-1 Lake-2 Lake-3
Intake pump house
Clear well
A) Settling and Coagulation-
Coagulant (turbidity, micro-organisms) reacts with the alkalinity of the water to form a gelatinous precipitate
Clear well
Clear well Pump
Sand Filters
Sand filtersB) Filtration-
Passage of fluid through a porous medium using sand filter arrangement to remove matters holding suspension.
ii i iii
1. Suspended silt
2. Clay
3. Colloids
4. Micro organisms including algae, bacteria and virus
Demineralisation System
The process of demineralisation water by ion exchange comprises of:-
•Conversion of salts to their corresponding acids by hydrogen cat-ion exchanger.
•Removal of acids by anion exchangers.
•The two exchangers are normally in series. Normally cat-ion precedes the anionexchanger
Major ion exchange materials are synthetic resins made by the polymerization of various organic compounds, resins have strong affinity to attract the +ve charge towards itself.
Most frequently used compounds are:-
1. Styrene
2. Die vinyl – Benzene
DM Plant Layout
Cation exchanger mainly removes Calcium, Magnesium, sulfates, chloride, nitrates and sodium salts alkalinity from raw water.
In cation exchanger positive ion of the salt is exchanged by theH+ ion
On discharging, it is charged with 400Kg of 30%Hcl.
Cation Exchanger
Carbon dioxide generated by dissociation of carbonic acid at cation outlet
water, is removed by degasser system.
Water from outlet of cation exchanger is made to fall from a height,
and a pressurized air is blown upstream of the water flow to separate
gases.
Degasser Blower
Degasser Tank
Anion exchangers remove the highly dissociated acids (like H2So4, HNo3,
Hcl) from the effluent of cation exchanger.
In anion exchanger negative charged part of the salt is exchanged by
the OH- ion.
On discharging, it is charged with 200Kg of 47.5%NaOH.
Anion Exchanger
Mixed-bed DeionisationEffluent water after anion exchanger may still have some salts due to them its conductivity is around 14-15 micro.mhos. 7 < pH <10, so it is further passed through Mixed Bed Deioniser, as shown below. The mixed bed mixture of Cation and Anion resins form infinite numbers of demineralising stages through which DM water passing and thus removing the traces of minerals. By this method demineralised water of extremely pure quality is achieved.
Mix bed deioniser
On discharging, it is charged with 100kg injection of each Hcl and NaOH.
GNDTP has 2 units of DM Plant, each having capacity of 40 tonns/hr
DM water storage tank have capacity of 2456m3
Max running hrs 5(one unit)
Charging Hcl(400kg in cation exchanger)
NaOH (200kg in anion exchanger)
Hcl and NaOH (100kg each in mixed bed)
Treated water has pH 6.8-7.2 , conductivity < 1 micro.mhos
Cation Exchanger
Anion Exchanger
Mix bed deioniser
DM Water Storage Tank
Degasser
Water from sand filters
Hcl charging tank connected with cation exchanger
NaOH charging tank connected with anion exchanger
Coal Testing
Preparation of coal sample
360Kg of Raw coal
Feed size - up to 300mm
Capacity – 20mT/hr
Product size – 50mm
Rejected
X
Coning and quartering - in this method, we divide the total amount of coal in 4 equal parts as shown, then we ignore the 1st & 3rd part. After taking 2nd
Jaw Crusher - I
1 2
4 3
Conning & Quartering
& 4th part together (total mass 180Kg) we again use above method to take another half of earlier collected mass ‘X’ another half of it, but now we ignore 2nd and 3rd part and take 1st and 4th part and get a mass of 90kg.
With the output of jaw crusher – I, we do coning & quartering 2 times and hence we get sample of 90Kg.
Coal product produced by this jaw crusher is of size of 50mm.
This 90kg of coal is further crushed in Jaw Crusher – II, which having the capacity of 1 mT/hr
Jaw crusher - I
90Kg coal
(size-50mm)
Jaw Crusher –II
Feed size – 50mm
Capacity – 1mT/hr
Product Size- 12.5mm
Two times conning & quartering
22.5Kg Coal sample of size 12.5mm
22.5Kg Coal sample of size 12.5mm
Jaw Crusher - III
Feed size – 12.5mm
Product Size – 6mm
One time conning & quartering
11Kg sample of coal of size 6mm
11Kg sample of coal of size 6mm
Jaw Crusher - IV
Feed Size - 6mm
Product Size – 3mm
Conning & Quartering two times 2Kg sample of coal having size of 3mm
2Kg sample of coal having size of 3mm
Now coal sample of mass 2kg having size of 212microns is sent to chemical department for testing.
Coal used is Bituminous having following specifications
Grinder
Feed Size – 3mm
Product Size -212microns.
Coal powder having size of 212microns
Carbon = (60-70) %
Ash = (30-40) %
Moisture < (2) %
Calorific Value = (3500-4500) Kcal/Kg
Coal testing is done to check the grading of the coal.
We check the moisture, ash and volatile content of the coal.
Moisture Content Test
1gm sample of powdered coal is weighed and taken in the silicon dish. Then this sample is heated in oven at 1100C for 1hr.then sample is taken out and again weighed. Loss of weight is the water content.
Ash Content Test
In this test 1gm sample of powdered coal is weighed and taken in the silicon dish. Then this sample is heated in oven at 8100c
for 1hr.then Sample is taken out and again weighed. Remaining is the only ash content.
Volatile Matter Test
For this test 1-gram sample of powdered coal
is taken. This sample is taken in a silicon crucible dish and heated at 900C for 7
minutes. Then the remaining amount of sample is noted and the losses are noted.
Volatile metals are Hg and NH3
Conclusion
Spending my six months of training in Guru Nanak Dev Thermal Plant, Bathinda, I concluded that this is a very excellent industry of its own type. They have achieved milestones in the field of power generation. They guide well to every person in the industry i.e. trainees or any worker. I had an opportunity to work in various sections namely coal handling plant, Boiler section, Turbine section, De-mineralized water plant, Ash handling plant etc. while attending various equipments and machines. I had got an endeverous knowledge about the handling of coal, various processes involved like unloading, belting, crushing and firing of coal. The other machines related to my field that I got familiar with boiler, turbine, compressors, condenser etc. I found that there existed a big gap between the working in an institute workshop and that in the industry. Above all the knowledge about the production of electricity from steam helped me a lot to discover and sort out my problems in my mind related to the steam turbine, their manufacture, their capacity, their angle of blades and their manufacturing. The training that I had undergone in this industry will definitely help me to apply theoretical knowledge to the practical situation with confidence.