project research station

Upload: shaymal-kohli

Post on 29-May-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Project Research Station

    1/14

    1

    A new Antarctic ResearchStation

    Halley VI

    Sian Nash

    Project Manager andProcurement Advisor for BAS

    The procurement challenge

    How to begin

    The Competition

    The search for a Contractor

    Design development andestimating a price

    The Contractual solution The Way Forward

    Location,

    location

  • 8/8/2019 Project Research Station

    2/14

    2

    Why Replace Halley?

    A window on key climate

    change issues Ozone, Climate past and present, Space weather

    50 years of continuous research

    Halley Research Stations

    Halley 1

    Halley 2

    The Background and the Brief

    Halley 4

    Halley 3

    Halley Research Stations

  • 8/8/2019 Project Research Station

    3/14

    3

    Halley 5Winter 2003

    Science Platform

    Halley Research Stations

    0 (km) 10

    Halley V

    (May 11th 2003)

    Halley VI

    1958 ice front position

    N9 / First Chasm fault line

    Upstream limit

    1967-1971 rift line

    Maximise lifetime

    Regard to ice-shelf behaviour

    Minimise snow accumulation

    Minimise impact on surroundings

    Energy efficient and economic to operate

    Excellent living and working environment

    Innovative but practical

    Cost effective and low maintenance

    Easy to remove

    Requirements for new station

  • 8/8/2019 Project Research Station

    4/14

    4

    Meet requirements of Brief, plus..

    Remote and hostile environment

    Foundations moving at 500 m per year

    Delivery of materials to ice shelf

    Construction challenge- Start Dec 07,complete Jan 10.

    The Design Challenge

    The Programme Drivers

    1st Sept

    Concepts

    04/05 05/06 06/07

    Con. Dev Enabling Cont.EOIsPlanning

    29thJun03/04

    Trials & Fabrication

    Construction&

    DemolitionYr 1

    Construction&

    DemolitionYr 2

    06/07 07/08 08/09 09/10

    High Risk of CalvingShipping Construction

    10/11

    Final InstallationsCommissioning

    Demolition

    Procurement Strategy Competition

    Stage 1 EOIs from Design Teams

    Stage 2 Concepts (6 teams)

    - EOIs Contractors

    Stage 3 Concept Development (3 teams)

    (with 3 x Contractor + BAS input)

    - Three D&B Tenders to RIBA Stage G

    D&B Contract Winning Design Team

  • 8/8/2019 Project Research Station

    5/14

    5

    The Design Competition

    The three winning designs

    Brief- To develop designs toRIBA Stage G

    Designers remunerated setfee and procured under PSC

    Meanwhile

    The Design Commission

  • 8/8/2019 Project Research Station

    6/14

    6

    OJEU notice placed

    6 E of Is received and evaluated

    Only 1 able to provide the Service Leaves a problem

    The Search for 3 Contractors

    Design development

    Engaged single Contractor towork with 3 teams anddevelop designs/ prices

    Utilised PSC

    Designs returned andreviewed qualitatively andquantitively

    Final Choice selected

    The Chosen Design

    Flexibility

    Module A livingaccommodation

    Potential to achieve budget

  • 8/8/2019 Project Research Station

    7/14

    7

    Winning concept design cost

    24.5 m and thereforeunaffordable.

    Options to move forwardconsidered

    Conclusion to continue andvalue engineer scheme

    AffordabilityAffordability

    Procurement Reality Competition

    Stage 1 EOIs from Design Teams

    Stage 2 Concepts

    - EOIs Contractors (5 submissions / 1 compliant)

    Stage 3 Concept Development

    (with 1 x Contractor + BAS input)

    Enabling Contract Design RIBA D - G

    Negotiate Contract

    D&B Contract

    The Contract..

    Design team now nominated toContractor and continue designdevelopment under PSC

    Meanwhile- Contract negotiationsand price challenge continues

  • 8/8/2019 Project Research Station

    8/14

    8

    The Construction Contract

    Why the ECC NEC?

    Most of all- Flexible

    International application

    Suite of contracts

    OGC endorsed

    The Construction Contract

    Which Main Option

    Lump sum?

    Target Cost?

    Construction

    time

    Furtherdesign

    Detaileddesign

    Settarget

    Risks withContractor

    max

    min

    Risks with

    Employer

    Contractor

    on board

    Possibleoutturn

    cost

    Stage 4- D&B procurement and

    constructionStage 3

    3 teams carry

    out conceptdevelopment

    Target Contract- the process

  • 8/8/2019 Project Research Station

    9/14

    9

    Procurement strategy

    Target Cost plus

    Secondary options

    X2- changes in law

    X4- Parent Company Guarantee

    X5- Sectional Completion

    X7- Delay Damages

    X15- Limitation of Designers Liability

    X16- Retention

    X18 Limitation of Liability

    Y (UK)2, Y (UK) 3

    Procurement Strategy

    Pain/ Gain share mechanism

    110 %

    shareranges

    time

    the Prices the movingtarget!

    compensationevents

    40 %

    50 %

    50 %

    100 %

    PSPDEmployer

    sharepercentage

    amount

    tendered

    total ofthe

    Prices

    100 %

    90 %

    80 %

    95 %

    105 %

    75 %

    45 %

    65 %

    Contractor

    Contract challenges

    1. General

    Boundary of site

    Risk Register

    3. Time

    Sectional completion vs Key Dates

    Liability for Key Dates

  • 8/8/2019 Project Research Station

    10/14

    10

    Contract challenges

    4. Testing and Defects

    Defect corrections

    5. Payment

    South African Consortium

    Defined cost for failure to achieve sectional

    completion or key date assessed at end ofseason

    Contract Challenges

    6. Compensation Events

    Failure of vehicles and plant supplied by Employer

    Sea Ice 1999 Sea Ice - 2003

    Challenges Just Getting Ashore

    Compensation Events- delivery of Contractors cargo

  • 8/8/2019 Project Research Station

    11/14

    11

    Delivering the cargo..

    Distances can be great

    Weather conditions can be

    harsh

    Abandon CAT !!

    Ship

    Welcoming committee

    Compensation Events Cancellation or delay in transport

    provided by Employer

    18 Hrs

    1 day

    1 day

    25

    days

    12 days

    16 Hrs

    8 Hrs1 Day

    1 Day

    Compensation Events

    All costs associated withincrease in Contractorspersonnel on Brunt iceshelf

    Withdrawal of SouthAfrican consortium

  • 8/8/2019 Project Research Station

    12/14

    12

    Contract challenges

    8. Risks and Insurances

    Overall limit of liability

    Additional Employers risks

    Weather!

    Compensation Event assessment using

    SSCC Marking and title

    Unusual Z clauses

    Contract challenges Flexibility of working area

    Brunt Ice shelf

    UK Port Site

    UK consolidation Warehouse and Packingstation

    Cape Town Consolidation and Packingstation

    Cape Town Port Site

    Modification to SCC- allow payment for keypeople

  • 8/8/2019 Project Research Station

    13/14

    13

    Final Contract negotiations

    Core Clauses and ContractTerms for Option C plus

    Professional IndemnityInsurance

    Right of Offset

    Parent Company Guarantee

    Total liability

    Liabilities for Key dates

    Risks accepted by BAS in association

    with Contractor

    Bad weather preventingContractor achieving critical path

    BAS unable to deliver cargo toHalley VI cargo line

    BAS unable to deliver personnelto cargo line

    BAS unable to deliver personnelback to UK

    BAS vehicles and plant fail

    Flavour of other BAS risks Charter ship delayed

    Bad weather delays

    Additional commercial flights

    Fuel costs

    Staff recruitment

    Project overspend

    Programme

    Ice shelf calve

  • 8/8/2019 Project Research Station

    14/14

    14

    Revised Tender Offer

    Single action tender- 3 quotes

    required to verify Target Cost

    Showstopper: Terms for SouthAfrican Consortium

    Final Total of the Prices21.844m

    Budget

    Construction & Demolition Contract - 22m

    Logistics, Vehicles, Accommodation, Design,BAS - 16m

    Total - 38m

    Sponsorship?

    The Way Forward Tricky part done

    now just got to build it!