project research station
TRANSCRIPT
-
8/8/2019 Project Research Station
1/14
1
A new Antarctic ResearchStation
Halley VI
Sian Nash
Project Manager andProcurement Advisor for BAS
The procurement challenge
How to begin
The Competition
The search for a Contractor
Design development andestimating a price
The Contractual solution The Way Forward
Location,
location
-
8/8/2019 Project Research Station
2/14
2
Why Replace Halley?
A window on key climate
change issues Ozone, Climate past and present, Space weather
50 years of continuous research
Halley Research Stations
Halley 1
Halley 2
The Background and the Brief
Halley 4
Halley 3
Halley Research Stations
-
8/8/2019 Project Research Station
3/14
3
Halley 5Winter 2003
Science Platform
Halley Research Stations
0 (km) 10
Halley V
(May 11th 2003)
Halley VI
1958 ice front position
N9 / First Chasm fault line
Upstream limit
1967-1971 rift line
Maximise lifetime
Regard to ice-shelf behaviour
Minimise snow accumulation
Minimise impact on surroundings
Energy efficient and economic to operate
Excellent living and working environment
Innovative but practical
Cost effective and low maintenance
Easy to remove
Requirements for new station
-
8/8/2019 Project Research Station
4/14
4
Meet requirements of Brief, plus..
Remote and hostile environment
Foundations moving at 500 m per year
Delivery of materials to ice shelf
Construction challenge- Start Dec 07,complete Jan 10.
The Design Challenge
The Programme Drivers
1st Sept
Concepts
04/05 05/06 06/07
Con. Dev Enabling Cont.EOIsPlanning
29thJun03/04
Trials & Fabrication
Construction&
DemolitionYr 1
Construction&
DemolitionYr 2
06/07 07/08 08/09 09/10
High Risk of CalvingShipping Construction
10/11
Final InstallationsCommissioning
Demolition
Procurement Strategy Competition
Stage 1 EOIs from Design Teams
Stage 2 Concepts (6 teams)
- EOIs Contractors
Stage 3 Concept Development (3 teams)
(with 3 x Contractor + BAS input)
- Three D&B Tenders to RIBA Stage G
D&B Contract Winning Design Team
-
8/8/2019 Project Research Station
5/14
5
The Design Competition
The three winning designs
Brief- To develop designs toRIBA Stage G
Designers remunerated setfee and procured under PSC
Meanwhile
The Design Commission
-
8/8/2019 Project Research Station
6/14
6
OJEU notice placed
6 E of Is received and evaluated
Only 1 able to provide the Service Leaves a problem
The Search for 3 Contractors
Design development
Engaged single Contractor towork with 3 teams anddevelop designs/ prices
Utilised PSC
Designs returned andreviewed qualitatively andquantitively
Final Choice selected
The Chosen Design
Flexibility
Module A livingaccommodation
Potential to achieve budget
-
8/8/2019 Project Research Station
7/14
7
Winning concept design cost
24.5 m and thereforeunaffordable.
Options to move forwardconsidered
Conclusion to continue andvalue engineer scheme
AffordabilityAffordability
Procurement Reality Competition
Stage 1 EOIs from Design Teams
Stage 2 Concepts
- EOIs Contractors (5 submissions / 1 compliant)
Stage 3 Concept Development
(with 1 x Contractor + BAS input)
Enabling Contract Design RIBA D - G
Negotiate Contract
D&B Contract
The Contract..
Design team now nominated toContractor and continue designdevelopment under PSC
Meanwhile- Contract negotiationsand price challenge continues
-
8/8/2019 Project Research Station
8/14
8
The Construction Contract
Why the ECC NEC?
Most of all- Flexible
International application
Suite of contracts
OGC endorsed
The Construction Contract
Which Main Option
Lump sum?
Target Cost?
Construction
time
Furtherdesign
Detaileddesign
Settarget
Risks withContractor
max
min
Risks with
Employer
Contractor
on board
Possibleoutturn
cost
Stage 4- D&B procurement and
constructionStage 3
3 teams carry
out conceptdevelopment
Target Contract- the process
-
8/8/2019 Project Research Station
9/14
9
Procurement strategy
Target Cost plus
Secondary options
X2- changes in law
X4- Parent Company Guarantee
X5- Sectional Completion
X7- Delay Damages
X15- Limitation of Designers Liability
X16- Retention
X18 Limitation of Liability
Y (UK)2, Y (UK) 3
Procurement Strategy
Pain/ Gain share mechanism
110 %
shareranges
time
the Prices the movingtarget!
compensationevents
40 %
50 %
50 %
100 %
PSPDEmployer
sharepercentage
amount
tendered
total ofthe
Prices
100 %
90 %
80 %
95 %
105 %
75 %
45 %
65 %
Contractor
Contract challenges
1. General
Boundary of site
Risk Register
3. Time
Sectional completion vs Key Dates
Liability for Key Dates
-
8/8/2019 Project Research Station
10/14
10
Contract challenges
4. Testing and Defects
Defect corrections
5. Payment
South African Consortium
Defined cost for failure to achieve sectional
completion or key date assessed at end ofseason
Contract Challenges
6. Compensation Events
Failure of vehicles and plant supplied by Employer
Sea Ice 1999 Sea Ice - 2003
Challenges Just Getting Ashore
Compensation Events- delivery of Contractors cargo
-
8/8/2019 Project Research Station
11/14
11
Delivering the cargo..
Distances can be great
Weather conditions can be
harsh
Abandon CAT !!
Ship
Welcoming committee
Compensation Events Cancellation or delay in transport
provided by Employer
18 Hrs
1 day
1 day
25
days
12 days
16 Hrs
8 Hrs1 Day
1 Day
Compensation Events
All costs associated withincrease in Contractorspersonnel on Brunt iceshelf
Withdrawal of SouthAfrican consortium
-
8/8/2019 Project Research Station
12/14
12
Contract challenges
8. Risks and Insurances
Overall limit of liability
Additional Employers risks
Weather!
Compensation Event assessment using
SSCC Marking and title
Unusual Z clauses
Contract challenges Flexibility of working area
Brunt Ice shelf
UK Port Site
UK consolidation Warehouse and Packingstation
Cape Town Consolidation and Packingstation
Cape Town Port Site
Modification to SCC- allow payment for keypeople
-
8/8/2019 Project Research Station
13/14
13
Final Contract negotiations
Core Clauses and ContractTerms for Option C plus
Professional IndemnityInsurance
Right of Offset
Parent Company Guarantee
Total liability
Liabilities for Key dates
Risks accepted by BAS in association
with Contractor
Bad weather preventingContractor achieving critical path
BAS unable to deliver cargo toHalley VI cargo line
BAS unable to deliver personnelto cargo line
BAS unable to deliver personnelback to UK
BAS vehicles and plant fail
Flavour of other BAS risks Charter ship delayed
Bad weather delays
Additional commercial flights
Fuel costs
Staff recruitment
Project overspend
Programme
Ice shelf calve
-
8/8/2019 Project Research Station
14/14
14
Revised Tender Offer
Single action tender- 3 quotes
required to verify Target Cost
Showstopper: Terms for SouthAfrican Consortium
Final Total of the Prices21.844m
Budget
Construction & Demolition Contract - 22m
Logistics, Vehicles, Accommodation, Design,BAS - 16m
Total - 38m
Sponsorship?
The Way Forward Tricky part done
now just got to build it!