project risk management
TRANSCRIPT
PROJECT RISK MANAGEMENT
Presented byNeenu BabuRoll no: 28S3 MBA
Introduction
• Project risk management is the Art and science of planning, organizing, securing and managing resources (Management) to manage the effects of uncertainties on objectives (Risk)of a temporary endeavor (project).
• Notion of project risk= f(likelihood, impact)• The likelihood is some problematic error will occur• The Impact of the event if it does occur
Process of risk management
• Risk identification• Risk assessment• Risk response planning
Risk identification Risk identification is the critical first step of
the risk management process. The objective of risk identification is the early and continuous identification of events that, if they occur, will have negative impacts on the project's ability to achieve performance or capability outcome goals.
Sources of risk
• Internal risk• External risk
Internal risk
• Risk originated inside the project
• Market risk
• Technical risk
Market risk• Risk of not fulfilling either market needs or the requirements
particular customersSources• Incompletely or inadequately defined market or customer
needs and requirements• Failure to identify changing needs and requirements• Failure to identify newly introduced products by competitors
Market risk can be reduced by thoroughly and accurately defining needs and requirements at the start of the project and continuously monitoring and updating requirements as needed throughout the project
Technical risk• It is the risk of not meeting time, cost, or performance
requirements due to technical problems with the end item or project activities
Factors effecting technical risk• Maturity• Complexity• Quality• concurrency
External risk• Risk that stem from sources outside the project• Sources• Market conditions• Competitors’ action• Government regulations• Interest rate• Decision made by senior management • Customer needs and behavior• Supplier relations• weather• Labor availability
Risk Identification techniques• Project risks are identified from analysis of he numerous
documents reviewed or prepared during project conception and definition.• Report from past project• List of user needs and requirements• Work package definitions• Cost estimates• Schedules• Schematic and models of end item
Risk assessmentDepends on three things• Risk likelihood• Risk impact• Risk consequences
Risk likelihood
• It is the probability that a hazard or risk factor will actually materialize
• Expressed as a numerical value between 1 and 0Or
• Qualitative rating such as high, medium or low
Risk impact• It is the impact of risk.• Risk impact of projects is specified in terms of time, cost and performance
measures• Risk impact can be expressed as qualitative rating such as high, medium
and low• Also can be expressed as a numerical measure between 0 and1• 0- not serious• 1- catastrophicExample• Insufficient number of skilled labor staff a project has the impact of
extending the schedule or preventing the project from meeting user requirements
Risk consequenceRisk consequence is the function of risk likelihood and
risk impact• Expressed as single numerical rating system• Value ranging between 1 and 0• Risk consequence= impact * likelihood
Risk priority• Project are subjected to numerous risk• Risk consequences of project have been computed • Give rank according to the risk • More attention given to project with highest risk • Project team members, managers, subcontractors and
consumers review them to ensure everyone’s awareness so that appropriate risk response can be planned
Risk response planning• Addresses the matter of how to deal with risk• Ways of dealing with risk• Transfer the risk• Avoid the risk• Reduce the risk• Preparing contingency plan• Accept risk
Transfer the risk• Risk can be transferred partly or fully from the
customers to the contractor or vice versaBy using
• Contractual incentives• Warranties• Penalties attached to the project performance, cost, or
scheduled measure
Avoid the riskRisk can be avoided by
• altering the original project concept• Changing contractors• Safety procedures
Reduce riskWays to reduce the risk• Employ the best technical team• Use mature, computer aided system engineering tools• Use parallel development on high risk task• Provide the technical team with adequate incentives for
success• Hire outside specialists for critical review and assessment of
work• Perform extensive test and evaluations• Minimize system complexity• Use design margins
Contingency planning • It can be post ad hoc remedial action to compensate
for the risk impact, an action taken in parallel to the original plan or a preventive action taken parallel to the original plan or a preventive action initiated by preliminary risk symptoms to mitigate the risk impact
Accept risk• Not all impacts are severe or fatal, and if the cost of
avoiding, reducing, or transferring the risk exceeds the benefit then do nothing
Risk management principles• Create a risk management plan• The risk profile for each risk should include likelihood, cost
and schedule impact and contingencies to be invoked• Risk officer• The budget and schedule should include a calculated risk
reserve, which is a buffer of money, time and other resources for dealing with risk as they materialize
• Risk must be continuously monitored• Establish communication channels• Specify procedures to ensure accurate, comprehensive project
documentation.
conclusionProject risk management maximizes the areas of project over which internal stake holders control the outcomes, and minimize the areas over which stake holders have absolutely no control. It involve identify the risk, assessing them, and planning the appropriate responses.
Reference
• John M Nicholas- project management for business and technology, principles and practice , 2nd edition prentice hall of India private limited , New Delhi- 110001, 2002