project : science and technology ... : science and technology development project (pdst) project...

39
AFRICAN DEVELOPMENT BANK PROJECT : SCIENCE AND TECHNOLOGY DEVELOPMENT PROJECT (PDST) PROJECT APPRAISAL REPORT OSHD DEPARTMENT October 2015 Translated Document

Upload: dinhkhanh

Post on 05-Apr-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

AFRICAN DEVELOPMENT BANK

PROJECT : SCIENCE AND TECHNOLOGY DEVELOPMENT PROJECT (PDST)

PROJECT APPRAISAL REPORT

OSHD DEPARTMENT

October 2015

Translated Document

Table des matières

(Currency Equivalents, Fiscal year, Weights and measures, Acronyms and Abbreviations,

Project Information Sheet, Executive Summary, Results-based Logical Framework,

Implementation Schedule…………………………………………………………………(i-vii)

I. STRATEGIC THRUST AND RATIONALE............................................................................................ 1

1.1 PROJECT LINKAGES WITH COUNTRY STRATEGY AND OBJECTIVES ............................................................ 1

1.2 RATIONALE FOR BANK INTERVENTION ...................................................................................................... 2

1.3 AID COORDINATION .................................................................................................................................. 3

II. PROJECT DESCRIPTION ........................................................................................................................ 4

2.1 PROJECT COMPONENTS ............................................................................................................................. 4

2.2 TECHNICAL SOLUTIONS ADOPTED AND ALTERNATIVES EXPLORED .......................................................... 5

2.3 PROJECT TYPE ........................................................................................................................................... 6

2.4 PROJECT COST AND FINANCING ARRANGEMENTS ................................................................................ 6

2.5 PROJECT TARGET AREA AND BENEFICIARIES ............................................................................................ 1

2.6 PARTICIPATORY APPROACH FOR PROJECT IDENTIFICATION, DESIGN AND IMPLEMENTATION ................... 2

2.7 KEY PERFORMANCE INDICATORS .............................................................................................................. 3

2.8 BANK GROUP EXPERIENCE AND LESSONS REFLECTED IN PROJECT DESIGN .............................................. 3

III. PROJECT FEASIBILITY…………………………………………………………………………… 4

3.1 ECONOMIC AND FINANCIAL PERFORMANCE .............................................................................................. 4

3.2 ENVIRONMENTAL AND SOCIAL IMPACT ..................................................................................................... 5

IV. PROJECT IMPLEMENTATION ............................................................................................................ 8

4.1 IMPLEMENTATION ARRANGEMENTS .......................................................................................................... 8

4.2 PROJECT MONITORING AND EVALUATION ............................................................................................... 10

4.3 GOVERNANCE .......................................................................................................................................... 11

4.4 SUSTAINABILITY ...................................................................................................................................... 11

4.5 RISK MANAGEMENT ................................................................................................................................ 11

4.6 KNOWLEDGE BUILDING ........................................................................................................................... 12

V. LEGAL FRAMEWORK ......................................................................................................................... 12

5.1 LEGAL INSTRUMENT ................................................................................................................................ 12

5.2 CONDITIONS FOR BANK INTERVENTION .................................................................................................. 12

5.3 COMPLIANCE WITH BANK POLICIES ........................................................................................................ 13

VI. RECOMMENDATION............................................................................................................................. 13

ANNEX I : COUNTRY COMPARATIVE SOCIO-ECONOMIC INDICATORS

ANNEX II : PORTFOLIO OF ACTIVE NATIONAL PROJECTS AS AT 30 JUNE 2015

ANNEX III : MATRIX OF DEVELOPMENT PARTNERS’ ACTIVITIES IN ANGOLA

ANNEX IV : MAP OF THE PROJECT AREA

ANNEX V : BRIEF PRESENTATION OF PROCUREMENT ARRANGEMENTS

ANNEX VI : RATIONALE FOR FINANCING 90% OF PDST COST WITH ADB RESOURCES

LIST OF TABLES

TABLE 2.1 : PROJECT COMPONENTS

TABLE 2.2 : PROJECT ALTERNATIVES EXPLORED AND REASONS FOR REJECTION

TABLE 2.3 : PROJECT COST BY COMPONENT (IN USD THOUSAND)

TABLE 2.4 : SOURCES OF FINANCING (IN USD THOUSAND)

TABLE 2.5 : PROJECT COST BY EXPENDITURE CATEGORY (IN USD THOUSAND)

TABLE 2.6 : EXPENDITURE SCHEDULE BY COMPONENT (IN USD THOUSAND)

TABLE 2.7 : PROJECT COST BY EXPENDITURE CATEGORY AND BY SOURCE OF FINANCING

(IN USD THOUSAND)

TABLE 3.1 : KEY ECONOMIC AND FINANCIAL DATA

TABLE 4.1 : MONITORING PHASES AND FEEDBACK LOOP

LIST OF GRAPHS

GRAPH I : GENDER-BASED EDUCATIONAL PROFILE, 2009

Currency Equivalents

(July 2015)

Currency Unit = AON

UA 1 = AON 170.6809

UA 1 = USD 1.40639

UA 1 = EUR 1.25694

Fiscal Year

1 January – 31 December

Weights and Measures

1 metric tonne = 2 204 pounds

1 kilogramme (kg) = 2.200 pounds

1 metre (m) = 3.28 feet

1 millimetre (mm) = 0.03937 inch

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

ii

ACRONYMS AND ABBREVIATIONS

AFD : French Development Agency

ADB : African Development Bank

AIA : Angolan Industrial Association

CPIA : Country Policy and Institutional Assessment

CSP : Country Strategy Paper

DNPAIA : National Directorate of Environmental Impact Prevention and Assessment

ESMP : Environmental and Social Management Plan

EU : European Union

IAPI : Angolan Institute of Industrial Property

IFE : Instituto do Fomento Empresarial

IMF : International Monetary Fund

IPS : International Patent System

JAS : Joint Assistance Strategy

KSI : Key Sector Indicators

M & E : Monitoring and Evaluation

M/W : Men/Women

ME : Minister of the Environment

MINEDUC : Ministry of Education

MINESUP : Ministry of Higher Education

MININDUST : Ministry of Industry

MST : Minister of Science and Technology

MUSD : Million US dollars

NDP : National Development Plan

NGO : Non-Governmental Organization

OPSCOM : Operations Committee

OSHD : Human Development Department

OSVP : Vice-Presidency, Sector Operations

PDST : Science and Technology Development Project

PIP : Public Investment Programme

PMT : Project Management Team

RAS : Regional Assistance Strategy

TFP : Technical and Financial Partner

UA : Unit of Account

UNESCO : United Nations Educational, Scientific and Cultural Organization

USD : United States Dollar

WB : World Bank

WDI : World Development Indicators

iii

Project Information Sheet

Client Information Sheet

BORROWER : Republic of Angola

EXECUTING AGENCY : Ministry of Science and Technology

Financing Plan

Source of Financing

Amount

Instrument

ADB USD 90 M1 Loan

Government USD 10 M Counterpart Contribution

TOTAL COST USD 100 M

ADB Financing Information

Loan Currency : USD

Interest Rate Type : Floating base rate with a free rate-fixing option

Base Rate : 6-month Libor

Lending Margin : 60 basis points (bps)

Financing Margin : Calculated twice a year

Commitment Charge : N/A

Other Charges : N/A

Tenor : Up to 20 years

Grace Period : Up to 5 years

FRR, NPV (baseline scenario) : 33%, USD 142,865,951

ERR (baseline scenario) : 24.5%

Timeframe – Main Milestones (Expected)

Project Appraisal June 2015

Negotiations September 2015

Project Approval October 2015

Effectiveness January 2016

Mid-term Review July 2018

Completion December 2020

Last Disbursement March 2021

1 The rationale for financing 90% of project cost with ADB resources is presented in Annex VI.

iv

EXECUTIVE SUMMARY

Project Overview

The Science and Technology Development Project (PDST) will cover the entire national

territory. Its overall expected outcomes are: (i) constructing and equipping the Mabubas

Science and Technology Park; (ii) financing scholarships and research projects; (iii)

implementing promotional activities and strengthening women’s participation in scientific,

technological and innovative activities; (iv) skills development in secondary education; and

(v) intellectual property management support.

The project will mainly benefit 155 researchers (at least 55% of them women) who will

be trained, 40 teams whose research projects will be financed and 125 girls who will be

awarded scholarships for secondary education. The business incubator that will be

established in the technology park will enable young Angolans to conduct tests, develop

prototypes and start their businesses. Lastly, the project will benefit the entire private sector

through the support that will be provided to it by the technology park for its research and

development activities.

Needs Assessment

The PDST’s objective is to contribute to diversifying the Angolan economy by

promoting technological innovation and improving the productivity and competitiveness

of enterprises in non-oil priority sectors. Indeed, scientific and technological development

is one of the main thrusts of the 2013-2017 National Development Plan (NDP). However,

global comparative indicators show that the country’s performance in terms of innovation is

weak due to poor research infrastructure and equipment as well as lack of research skills.

Bank’s Value Added

The Bank has experience in the design and implementation of science and technology

development projects as well as in sector policy dialogue and strategic thinking. Thus, it

has approved many higher education, science and technology projects in various countries.

Over the last three years, it also organized two African fora on science, technology and

innovation which focused on the sharing of ideas and experience as well as the conduct of

many analytical works.

Knowledge Management

The main project objective is to build knowledge, given the sector targeted and the

nature of activities to be financed. The project will help to build knowledge through the

identification of technological solutions to business problems, transfer of technology and

innovations that will be supported by the business incubator. It will also support knowledge

building by training many engineers and researchers. Lastly, it will provide various forms of

technical assistance for building a science and technology park, appraising research projects,

strengthening the framework for training secondary school teachers, establishing an industrial

property database, etc.

v

Angola: Science and Technology Development Project

Results-Based Logical Framework

Country and Project Name: Angola - Science and Technology Development Project

Project Goal: Contribute to economic diversification through scientific and technological innovation

RESULTS CHAIN

PERFORMANCE INDICATORS MEANS OF

VERIFICATION

RISKS /

MITIGATION

MEASURES Indicators

(including ISC)

Baseline

Situation Target

IMP

AC

T

The weight of the

non-oil sector in the

economy is increased

The non-oil sector’s

share in GDP

59.4% in

2013(a) 74.5% in 2030(b)

IMF statistics

INE statistics

MINEC reports

OU

TC

OM

ES

Increased patent

application

Number of patent

applications under IPS 3 in 2013(c)

175 in 2023(d)

(160 in 2020)

IPS, MST, Ministry of

Industry

Risk: low private sector

involvement in the

activities of the

technology park

Mitigation measures:

legal autonomy of the

park and involvement of

the private sector in the

design and management

of the park

Increase in the

availability of

researchers

Number of full-time

equivalent researchers

per million inhabitants

57 in 2011,

32% of them

women(e)

75 in 2023, 40% of

them women(f)

(70 in 2020, 37.5%

of them women)

UNESCO, MST,

Ministry of Higher

Education (MINESUP)

OU

TP

UT

S

Component1: Support for Research Activities

The Mabubas

Technology Park is

constructed, equipped

and operationalized

Numbers of research

centres constructed,

equipped and

operationalized

0 in 2015 1 in 2018 MST reports

Risk: low rate of

retention of researchers

trained under the

project.

Mitigation measure:

signing of a ten-year

contract of employment

for scholarship

recipients

Researchers and

research engineers

are trained(g)

Number of master’s,

doctorate and post-

doctorate scholarships

awarded and

percentage of female

recipients

0 in 2015

155 in 2020 (80 in

2018), at least 55%

of them women

MST data

MINESUP data

Research projects are

financed(h)

Number of projects and

percentage of women

among team leaders

0 in 2015

40 in 2020 (20 in

2018), of which at

least 50% of teams

are headed by

women

MST data

MINESUP data

Component 2: Creation of an Environment Conducive to the Development of Science, Technology and Innovation

A system of training

in methodology is

established

Number of teaching

methodologists trained

and have assumed duty

0 in 2015 54 in 2018, at least

25 of them women

MINEDUC data

MINESUP reports

Secondary school

laboratories are

equipped

Number of laboratories

equipped 0 in 2015

18 laboratories, that

is 1 per province in

2019

MINEDUC reports

An equipment

maintenance system

is established

Number of databases

established and

inventories carried out

0 in 2015

One database is

established in 2017

and two inventories

carried out in 2020

MST report

MINEDUC report

MINESUP report

Technicians and

teachers are trained in

equipment

maintenance and use

Number of laboratory

technicians and teachers

trained

0 in 2015

18 laboratory

technicians trained

in 2016 and 108

teachers trained in

2018

MST report

MINEDUC report

MINESUP report

OU

TP

UT

S

Academic

counsellors are

trained

Number of academic

counsellors trained and

have assumed duty

0 in 2015 54 in 2018, at least

30 of them women

MINEDUC data

MINESUP reports

The industrial

property database is

established

Existence of an

industrial property

database

Non-existent in

2015

1 database

established in 2017

MININDUST and MST

reports

National Science, Number of awards given 0 in 2015 8 in 2020 (4 in 2018) MININDUST and MST

reports

vi

Technology and

Innovation awards

A national scientific

data management

policy is developed

Existence of a national

scientific data

management policy

Non-existent in

2015

1 policy developed

in 2017

MST, MINESUP and

MININDUST reports

Component 3: Project Management

Procurement

activities are carried

out

Update rate of the

Procurement Plan

Prepared in

2015

PP updated at least

once annually PP

Risks: procurement

delays and low

disbursement

Mitigation measures:

recruitment of PMT

members on a

competitive basis,

performance contracts,

procedures manual

Project activities are

physically

implemented

Percentage of activities

implemented 0 in 2015

20% annually, on

average MST reports

The project is

financially

implemented

Project disbursement

rate 0 in 2015

20% annually, on

average

Early warning system

(EWS)

Project financial

management is

ensured

Number of audit reports

validated

An audit firm

recruited in

2016

5 annual audit

reports validated Progress reports

Project monitoring

and evaluation is

carried out

Frequency of

preparation of

monitoring and

evaluation reports

Evaluation

system

established in

2016

Quarterly progress

reports, a medium-

term monitoring and

evaluation report

and a final report

prepared

Mission aide-memoire

KE

Y A

CT

IVIT

IES

COMPONENTS RESOURCES

Component 1: Support for Research Activities

Component 2: Creation of an Environment Conducive to the Development of Science,

Technology and Innovation

Component 3: Project Management

ADB: USD 90 million

Counterpart contribution: USD 10 million

Component 1: USD 74.552 million

Component 2: USD 19.934 million

Component 3: USD 5.514 million

Total: USD 100 million

(a): IMF data, (b): Estimate based on IMF data, (c): IPS data, (d): estimate based on IPS and World Bank data (e): UNESCO and MST data, (f) estimate

based on UNESCO and World Bank data.

(g) and (h): the sectors concerned by scholarships and research projects are the activities of the Science and Technology Park, namely agribusiness,

biotechnology and health, energy and environment, information and communication technologies, nanotechnology and mechatronics

vii

Implementation Schedule

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF

DIRECTORS CONCERNING A PROPOSAL FOR AN ADB LOAN TO FINANCE

THE SCIENCE AND TECHNOLOGY DEVELOPMENT PROJECT IN THE

REPUBLIC OF ANGOLA

Management submits the following report and recommendation concerning a proposal to

grant a USD 90 million ADB loan to the Republic of Angola to finance the Science and

Technology Development Project (PDST).

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 Despite the remarkable growth of the non-oil sector of the economy over the

last decade, Angola’s economy is still heavily dependent on the oil sector. In fact,

although non-oil GDP recorded an average annual growth of 12.8% between 2003 and 2013,

the oil sector still accounts for 40.6% of national GDP and more than 90% of exports2.

1.1.2 In addition, despite these genuine macro-economic achievements, the social

situation is by far worse than that of countries with a comparable level of income. The

under-five mortality rate is 167.4 deaths per 1,000 live births, as against 43.4 per 1,000 in

middle-income countries. Life expectancy at birth in Angola is 51.9 years, whereas it is 70

years on average in middle-income countries. In the area of education, the primary school

completion rate in Angola is 54.3%, as against 95.6% in middle-income countries.

Concerning workforce, the unemployment rate is only 5.2% in all middle-income countries,

whereas it is 26%3 in Angola.

1.1.3 Considering the need to reduce poverty, the country has prepared a National

Development Plan (NDP) covering the 2013-2017 period, which seeks to promote human

development and the well-being of Angolans, improve the quality of life and combat

hunger and extreme poverty. It comprises eight main thrusts for Angola’s development,

namely: (i) ensuring national unity and cohesion; (ii) building a democratic and participatory

society to guarantee fundamental freedoms and rights and civil society development; (iii)

promoting human development and the well-being of Angolans to improve the quality of life

and combat extreme poverty; (iv) fostering sustainable, competitive and equitable

development to guarantee the future of coming generations; (v) promoting the development

of science, technology and innovation; (vi) supporting entrepreneurship and private sector

development; (vii) ensuring the harmonious development of the national territory; and (viii)

promoting the competitive integration of the Angolan economy into the global and regional

contexts.

1.1.4 The PDST will contribute to developing science, technology and innovation in

Angola and its activities are in line with Thrusts 5 and 6 of the NDP. It will directly

contribute to Thrust 5 by supporting research and the development of scientific and

technological skills as well as promoting science, technology and innovation. It will also

contribute to Thrust 6, considering the impact of technological innovation on economic

diversification and growth through productivity and competitiveness gains.

1.1.5 The project is also aligned with the Republic of Angola’s Country Strategy Paper

(CSP) 2011-2015. It is in keeping with Pillar 1 of the 2011-2015 CSP, which seeks to boost the

competitiveness of the national economy. The Bank’s operations under this pillar are aimed

2 Estimate based on the World Development Indicators (WDI) and International Monetary Fund (IMF) data. 3 African Economic Outlook 2015.

2

at supporting the Government’s efforts to promote economic diversification and private

sector development, entrepreneurship and job creation. It is also in line with Pillar II whose

objective is to support economic infrastructure development by building technology park

infrastructure. Lastly, the PDST is included in the Lending Programme considered under the

2013 Mid-Term Review of the CSP.

1.1.6 Lastly, the project is consistent with the Bank’s 2013-2022 Strategy, the Human

Capital Strategy for Africa and the Gender Strategy. In fact, skills and technology

development are among the operational priorities of the Bank’s 2013-2022 Strategy. The

Bank’s Human Capital Strategy is the operational framework for achieving this priority. This

strategy specifies that the Bank will support high-impact investments in education, science and

technology in order to assist Regional Member Countries (RMCs) to move up the value chain

to efficiency- and innovation-driven economies. Investments in skills and technology

development in all RMCs will foster innovation, competitiveness and the creation of job

opportunities, especially in the areas of agri-business and agro-processing, biotechnology and

engineering, particularly industrial production and ICT.

1.1.7 Specifically, the Human Capital Strategy states that the Bank will step up its

support to science, technology and innovation (STI) by continuing to finance the

development and implementation of projects focusing on: (i) skills development in science,

technology and mathematics; (ii) research, innovation and connection to global knowledge

systems; and (iii) outreach to communities and the private sector. It will also finance

programmes for women scientists, particularly by granting graduate and postgraduate

fellowships. The project is also in line with the Bank’s Gender Strategy whose second pillar

concerning economic empowerment recommends the application of good practices by the Bank

within the framework of science and technology development activities, particularly through

scholarship programmes aimed at reducing gender inequalities in this domain, with emphasis

on higher education, science and technology.

1.2 Rationale for Bank Intervention

1.2.1 Innovation contributes to both growth and economic diversification. In fact, it

yields increasing returns which increase the knowledge stock. Firms are interdependent,

hence each firm’s innovation activities benefit all firms in the long run when the knowledge

related to such innovation is disseminated, thus steering the economy on the path of growth

by improving business productivity and competitiveness. In addition, innovation contributes

to the production of new goods and services or adoption of new production techniques, thus

fostering the emergence of new industries as well as new trades, and hence economic

diversification.

1.2.2 Overall, global comparative indicators show that the country’s research and

innovation performance is weak. Angola is on the bottom rung of countries in terms of key

indicators relating to the impact of science and technology on productive activities such as

innovation capacity (142nd out of 144 countries with a score of 2.7 on a scale of 1 to 7),

quality of scientific research institutions (a score of 1.9) and collaboration between academic

institutions and the industrial private sector in research and development (a score of 2). These

results are due to poor research infrastructure and equipment as well as inadequate science

and technology skills, as the level of education of nearly 50% of researchers and university

teachers is below the master’s degree.

1.2.3 The project will contribute to national efforts to develop and improve the

quality of scientific and technological research, as well as innovation capacity. Local

initiatives in this area include the adoption in 2011 of the National Science, Technology and

3

Innovation Policy as well as the Science and Technology Act which defines the legal

framework for STI. The National Science, Technology and Innovation Policy lays emphasis

on the procurement of equipment needed for quality research, the upgrading of human

resources, the promotion of a scientific culture, intellectual property, technology transfer,

cooperation in science and technology, and the strengthening of the regulatory framework.

1.2.4 The Bank has considerable experience in the design and implementation of

projects related to the development of science and technology as well as in sector policy

dialogue and strategic thinking. It has therefore approved many higher education, science

and technology projects in several East and Southern African countries (Kenya, Rwanda,

Uganda, Malawi, Ghana, etc.). Over the last three years, it also organized two African fora on

science, technology and innovation to promote the sharing of ideas and experience and

carried out many analytical works in this sector.

1.2.5 The lessons learned from these operations were reflected in the design of the

PDST. These lessons indicate, among other things: (i) the positive impact of the existence of

an integrated national science, technology and innovation policy with clearly defined

priorities; (ii) the need for greater coordination between government entities, training and

research institutions, the industrial sector and professional organizations; (iii) poor research

infrastructure and equipment; (iv) inadequate research skills; and (v) weak mechanisms for

the evaluation of sector plans and programmes.

1.2.6 Lastly, the project is in line with other operations already approved by the

Bank in Angola, notably the Project to Build Institutional Capacity for Private Sector

Development (aimed at diversifying the national economy by building the capacity of the

Ministry of Economy which supports private sector development) as well as the study on

costs, financing and private sector involvement in higher education and research.

1.3 Aid Coordination

1.3.1 Angola has no formal aid coordination mechanism, but informal meetings are

held occasionally and thematic working groups meet when necessary. The volume of

development assistance to the country represents less than 3% of the national budget. The

main development partners that are active in Angola are the European Union (EU), Norway,

the World Bank, UNICEF, ADB and bilateral creditors such as China, Brazil, Portugal,

Germany and Spain. Their activities mainly focus on agriculture, water and sanitation, private

sector development, health, and capacity building.

1.3.2 Angola recently received support from the European Union, the French

Cooperation Agency and the Japanese Cooperation Agency in the specific area of

science, technology and innovation to train secondary school teachers in the teaching of

science. The country also receives technical assistance from UNESCO and the World

Intellectual Property Organization (WIPO). The outcomes of such interventions include the

establishment of the Malanje Higher Institute of Food Technology (it offers short courses in

higher education and some beneficiaries could win scholarships under this project to further

their studies at the master’s or doctorate degree level), the training of 15 master’s and

doctorate degree students, the training of teaching methodologists, etc.

1.3.3 The PDST complements the operations of other partners involved in the

development of science, technology and innovation. Thus, while UNESCO and WIPO

provide technical support to Angola respectively in higher education (master’s and doctorate

degrees) and intellectual property management, the project will provide financial support in

each of these two areas and coordinate activities. Similarly, while support provided by the

4

French Cooperation Agency and the European Union for research mainly targets agriculture,

the project will focus on biotechnology and health, energy and environment, information and

communication technologies, nanotechnology and mechatronics as well as agribusiness.

Lastly, considering that Angola has received support from the Japanese Cooperation Agency

for the short-term training, in Kenya, of teaching methodologists in science subjects, this

project will contribute to establishing a sustainable system for long-term courses in the

methodology of teaching science.

Sector or Sub-sector*

Science, technology and innovation

Stakeholders - Public Expenditure

Government (2012) Donors Amount Duration

0.7% of GDP European Union 4 EUR million 2014 - 2020

French Cooperation EUR 1.7 million 2009 - 2014

Level of Aid Coordination

Existence of thematic working groups No

Existence of a comprehensive sector programme Yes

Role of ADB in aid coordination Informal coordination

1.3.4 The identification of PDST activities took advantage of the outcomes of

consultations with the Japanese Cooperation Agency, the French Cooperation Agency,

the European Union and the World Bank. The discussions held with these partners during

project preparation helped to ensure project complementarity with other operations relating to

the development of science, technology and innovation in Angola.

II. PROJECT DESCRIPTION

2.1 Project Components

2.1.1 The project’s goal is to contribute to economic diversification through scientific

and technological innovation. Specifically, this involves: (i) supporting the implementation

of scientific and technological research activities in priority areas to diversify the economy

(agribusiness, biotechnology and health, energy, information and communication

technologies, etc.); and (ii) creating an environment conducive to the development of science,

technology and innovation.

2.1.2 The project will be implemented over a five-year period. Its components and

activities are summarized in the table below.

5

Table 2.1

Project Components Component Cost Description

1. Support

for Research

Activities

USD

74.552

million

This component will: (i) build and equip Mabubas Technology Park; (ii) grant 155

scholarships (at least 55% of them for women) at the master’s, doctoral and post-

doctoral levels for the training of researchers (and research engineers) selected on a

competitive basis in the following sectors: agribusiness, biotechnology and health,

energy and environment, information and communication technologies,

nanotechnology and mechatronics; (iii) finance 40 research projects (50% of whose

teams are headed by a woman) selected on a competitive basis in the following areas:

agribusiness, biotechnology and health, energy and environment, information and

communication technologies, nanotechnology and mechatronics; and (iv) finance 125

scholarships for girls in secondary education.

2. Creation of

an Environment

Conducive to the

Development of

Science, Technology

and Innovation

USD

19.934

million

This component will: (i) establish a national system for training teaching

methodologists in science and technology; (ii) equip 18 laboratories in secondary

schools located in provincial capitals; (iii) establish a laboratory-equipment-

maintenance system; (iv) train 18 laboratory technicians and 108 teachers in

laboratory equipment maintenance and use; (v) train 54 academic counsellors (at least

30 of them women); (vi) establish an industrial property database; (vii) design a

national scientific data management policy; (viii) institute national science,

technology and innovation awards; (ix) carry out science, technology and innovation

promotional activities; and (x) support intellectual property management.

3. Project

Management and

Evaluation

USD

5.514

million

This component will establish a system for assessing the impact of science,

technology and innovation development programmes that mainstream the gender

dimension. It will also establish a suitable mechanism for the overall coordination and

monitoring of project implementation. This mechanism is described in §4.1.1 below

and in Annex V. The main activities will be: providing equipment, technical

assistance, monitoring and evaluation, auditing, and project operation.

2.2 Technical Solutions Adopted and Alternatives Explored

2.2.1 During project preparation, several options concerning project objectives and

scope of activities, design and implementation arrangements were considered.

2.2.2 Regarding project objectives, the Government’s request concerned only the

construction of the technology park. However, project design was based on the fact that

besides infrastructure, the technology park and the research sector as a whole will also need

human resources. In addition, the development of science and technology requires many

other elements (industrial property management, promotion of science, technology and

innovation, improvement of the regulatory framework, private sector involvement, etc.).

These different elements were discussed with the Government and their consideration helped

to define the project components retained.

2.2.3 Concerning project design, the idea of extending and equipping an existing

research centre instead of building new infrastructure was considered. However, visits to

several existing research institutions located mainly in urban areas revealed major constraints

in terms of availability of space and the impracticality of extending them, hence the option to

build new infrastructure for a science and technology park.

2.2.4 Regarding project implementation arrangements, the alternative of recruiting a

consulting firm for fiduciary management of the project was explored but rejected

because past experiences produced negative results and also because it requires national

capacity building.

6

2.2.5 Table 2.2 below presents the alternatives explored and reasons for rejection.

Table 2.2

Project Alternatives Explored and Reasons for Rejection Alternative Brief Description Reasons for Rejection

Limiting the project to the

construction of the

infrastructure of the

technology and industrial

park

The Government’s request to

limit the project to the

construction and equipping of a

technology park

The human resource needs of the

technology park have to be taken into

account

Need to consider other crucial

dimensions in the development of

science, technology and innovation:

industrial property management,

regulatory framework, promotion of

science, technology and innovation,

etc.

Expand and equip an

existing research centre

Construct other buildings on a

site that already hosts a

research centre

Spatial constraints in an urban centre

limit the possibility of expansion

Recruitment of a consulting

firm for fiduciary

management of the project

Recruitment of a consulting

firm to carry out project

procurement and financial

management given the weak

capacity of MST

The use of this approach in the past

produced negative results

Need to build the capacity of MST

2.3 Project Type

The PDST is an investment project financed with ADB loan resources. It seeks to support

the Government’s efforts to develop science and technology and promote innovation. The

investment envisaged will particularly help to strengthen and improve the framework of

scientific and technological research and create a more favourable national framework for the

development of science, technology and innovation.

2.4 Project Cost and Financing Arrangements

The total project cost, net of taxes and customs duties, is estimated at USD 100 million,

of which USD 65 million in foreign exchange (65%) and USD 35 million in local

currency (35%). This cost is shared between the ADB and the country at 90% and 10%,

respectively. The rationale for this cost sharing is presented in Annex VI. The cost includes a

5% provision for physical contingencies and a provision for price escalation representing

14.32% of the base cost for expenditure in foreign exchange and in local currency.

Table 2.3: Project Cost by Component (in Thousand USD)

Components Foreign

Exchange

Local

Currency Total

% Foreign

Exchange

1. Support for Research Activities 45 370 18 000 63 370 72%

2. Creation of an Environment Conducive to

the Development of Science, Technology and

Innovation 6 660 9 353 16 013

42%

3. Project Management and Evaluation 3 360 1 065 4 425 76%

Base Cost 55 390 28 418 83 808 65%

Provision for Physical Contingencies (5%) 2 770 1 421 4 190

Provision for Price Escalation (14.32%) 6 832 5 169 12 001

Total Project Cost 64 992 35 008 100 000

1

Table 2.4: Sources of Financing (in Thousand USD)

Sources of Financing Foreign

Exchange

Local

Currency Total % Total

ADB 62 888 27 112 90 000 90%

Government of Angola 2 104 7 896 10 000 10%

Total Project Cost 64 992 35 008 100 000

Table 2.5: Project Cost by Expenditure Category (in Thousand USD)

Expenditure Categories Foreign Exchange Local Currency Total % Foreign Exchange

Works 26 250 9 250 35 500 74%

Goods 5 400 1 038 6 438 84%

Services 13 940 745 14 685 95%

Operating Costs 0 828 828 0%

Miscellaneous 9 800 16 558 26 358 37%

Base Cost 55 390 28 418 83 808 65%

Provision for

Implementation

Contingencies (5%)

2 770 1 421 4 190

Provision for Price

Escalation (14.32%) 6 832 5 169 12 001

Total Project Cost 64 992 35 008 100 000

Table 2.6: Expenditure Schedule by Component (in Thousand USD)

Components 2016 2017 2018 2019 2020 Total

1. Support for Research Activities 21 610 16 920 16 440 4 200 4 200 63 370

2. Creation of an Environment Conducive to the

Development of Science, Technology and

Innovation

3 632 5 041 3 511 2 190 1 640 16 013

3. Project Management and Evaluation 1 228 1 141 866 626 566 4 425

Base Cost 26 470 23 102 20 816 7 016 6 406 83 808

Provision for Implementation Contingencies (5%) 2 523 555 441 351 320 4 190

Provision for Price Escalation (14.32%) 3 710 1 652 1 988 2 146 2 506 12 001

Total Project Cost 29 739 27 694 23 823 9 512 9 232 100 000

Table 2.7: Project Cost by Expenditure Category and by Source of Financing (in Thousand USD)

ADB Government of Angola Total

Foreign

Exchange

Local

Currency Total

Foreign

Exchange

Local

Currency Total

Foreign

Exchange

Local

Currency Total

Works 29 492 10 392 39 884 0 0 0 29 492 10 392 39 884

Goods 6 205 1 143 7 347 0 124 124 6 205 1 266 7 471

Services 14 354 346 14 701 2 104 537 2 640 16 458 883 17 341

Operating Costs 0 614 614 0 444 444 0 1 058 1 058

Miscellaneous 12 837 14 617 27 454 0 6 792 6 792 12 837 21 408 34 245

Total 62 888 27 112 90 000 2 104 7 896 10 000 64 992 35 008 100 000

2.5 Project Target Area and Beneficiaries

2.5.1 Although the project covers the entire national territory, the science and

technology park will be constructed in the municipality of Bara do Dande. This

municipality, which is located in Bengo Province, has many advantages in terms of the

location of the science and technology park. From the academic standpoint, the province is

home to the second campus (currently being completed) of the Agostinho Neto University,

which is the country’s main State university, and the park will be constructed near the

campus, in the Mabubas municipality. From the Economic point of view, Angolan authorities

plan to construct a new port in the municipality of Barra do Dande to decongest the existing

port of Luanda whose limited capacity cannot handle the ever-growing demand. Lastly, it

should be noted that the Angolan Government has established a special economic zone (SEZ)

2

between the provinces of Luanda and Bengo, whose infrastructure seems to be a factor of

competitiveness, innovation and job creation.

2.5.2 The main project beneficiaries are the 155 researchers (at least 55% of them

women) who will be trained under the project, the 40 research teams whose research

projects will be financed and the 125 girls who will be awarded scholarships for

secondary education. Young Angolans will take advantage of the workshop and business

incubator activities envisaged in the technology park (one enterprise per sector will be

incubated year) to conduct tests, develop prototypes and start their businesses. In addition, the

project will be beneficial to the private sector as a whole through the support that the science

and technology park will provide for their research and development activities. The project

will also contribute to skills development by reinforcing the science, technology and

industrial innovation teacher-training system through its support to the intellectual property

management system.

2.6 Participatory Approach for Project Identification, Design and Implementation

2.6.1 The project preparation mission fielded in March 2015 held several working

sessions with all project beneficiary entities and stakeholders. This approach, which was

renewed during the appraisal phase in June 2015, helped to deepen, retain and validate the

main project thrusts. The various beneficiary entities presented their capacity building needs

in the form of quantified targeted actions.

2.6.2 Given its objectives, the PDST’s success necessitates the fostering of strong

public-private partnership on the objectives of the technology park during project design

and implementation and particularly during the operation of the technology park so as to

ensure its smooth management, the identification of the most relevant research projects to be

financed, etc.

2.6.3 Since the objective of the technology park is to contribute to private sector

development, discussions were held with the Angolan Industrial Association on the

project’s relevance. Consultations were also held with research institutions, the ministries

involved in the project, other technical and financial partners and local civil society

organizations during which project activities were defined in light of national priorities and

ongoing initiatives. The various stakeholders consulted recognized the relevance of the PDST

objectives, especially skills training and the creation of an environment conducive to the

development of science, technology and innovation. These consultations helped to prioritize

the mobilization of technical assistance for the establishment of the technology park as well

as the strengthening of mechanisms for training secondary school teachers in science and

technology, and support for academic-counselling activities. Specific discussions held on

gender issues resulted in the inclusion in project activities of the financing of scholarships for

girls in secondary schools and a cohort study on gender-based disparities in science and

technology in secondary schools.

2.6.4 The participatory approach adopted during project preparation will be

maintained during its implementation and in the operation of the science and

technology park. Accordingly, the representatives of the private sector will be involved in

the management of the technology park which will be autonomous from the legal viewpoint,

the selection of research projects to be financed and the definition of the technology park’s

work programme.

3

2.7 Key Performance Indicators

2.7.1 The performance indicators identified and expected outcomes at project

completion are those presented in the results-based logical framework. They will be

assessed by the monitoring and evaluation specialist to be recruited from within the project

management team. The monitoring and evaluation system will be informed by project

beneficiary entities. Key project performance indicators are presented in the box below.

Box: Key Performance Indicators Impact Indicators The share of the non-oil sector in GDP rises from 59.4% in 2013 to 74.5% in 2030.

Outcome Indicators The number of patent applications filed under IPS increases from 3 in 2013 to 175 in 2023;

The number of full-time equivalent researchers per million inhabitants, 40% of them women, increases

from 57 in 2011 to 75 in 2023.

Output Indicators The technology park is built, equipped and operationalized in 2018;

155 researchers (and research engineers), at least 55% of them women, are trained in 2020 in agribusiness,

biotechnology and health, energy and environment, information and communication technologies,

nanotechnology and mechatronics;

40 research projects, of which at least 50% of the teams are headed by women, are financed in 2020;

54 teaching methodologists, at least 25 of them women, are trained in 2018;

18 laboratories in secondary schools in provincial capitals are equipped by 2019;

A research equipment database is established in 2017 and two inventories are carried out in 2020;

18 laboratory technicians and 108 teachers are trained in laboratory equipment maintenance and use in

2018;

54 academic counsellors, at least 30 of them women, are trained in 2018;

An intellectual property database is established in 2017;

8 national science, technology and innovation awards are given by 2020;

A national scientific data management policy is developed in 2017.

2.8 Bank Group Experience and Lessons Reflected in Project Design

2.8.1 The operations portfolio in Angola is characterized by persistent project

implementation challenges due to delays related to the use of relevant national

procedures. The average age of projects is 5.3 years. Portfolio performance is considered

fairly satisfactory with an average score of 2.31 for ongoing projects. The active portfolio has

a problematic project and a potentially problematic project. The proportion of projects at risk

in the portfolio is 10.5%. The country portfolio review conducted in December 2014

identified challenges concerning the Government and the Bank. Special emphasis should be

laid on actions to build the capacity of project management teams in procurement and

financial management. In addition, it is necessary to conclude performance contracts in order

to improve project implementation. The country portfolio performance review helped to

prepare an action plan with specific measures to be implemented within a specified period by

the Government and the Bank.

2.8.2 The lessons learned from these operations underscore the need to recruit

permanent staff who are familiar with Bank procurement, financial management and

monitoring and evaluation procedures and have a good command of Portuguese, in addition

to the Bank’s working languages. In this respect, there are plans to recruit three technical

assistants who are familiar with Bank procurement, financial management and monitoring

and evaluation procedures. Besides providing support for project implementation, they will

train MST staff in these different areas in order to create a pool of experts and sustain project

achievements. In addition, it will be necessary to regularly supervise and monitor the

implementation of their recommendations.

4

III. PROJECT FEASIBILITY

3.1 Economic and Financial Performance

Economic Performance

3.1.1 The project will have a significant impact on the diversification of the national

economy by promoting inclusive growth. It will contribute to identifying innovative

solutions for enterprises in the agribusiness, biotechnology and health, energy and

environment, information and communication technologies, nanotechnology and

mechatronics sectors through the research and development activities of the technology park.

Given the employment potential in these sectors, the project will contribute to reducing

unemployment and increasing productivity. Overall, it will help to enhance the

competitiveness of local enterprises.

3.1.2 The project will support the development of scientific skills and

entrepreneurship, private sector development and job creation. The project will

contribute to developing skills in science and technology by financing scholarships in higher

and secondary education (for girls), supporting the system for training secondary school

teachers in science and technology, equipping laboratories in secondary schools, and

supporting counselling services. Economically, the project will support the establishment and

development of innovative enterprises, the development of entrepreneurship as well as job

creation through technology and industrial enterprise incubation and support of

entrepreneurial activities. The economic rate of return of the project is estimated at 24.5%,

which is higher than the capital opportunity cost (20%). Consequently, the project is

economically viable.

Financial Performance

3.1.3 The PDST is financially profitable with a net present value (NPV) which,

although underestimated, is more than the project investment cost. The analysis focuses

exclusively on the cost of constructing the science and technology park, training researchers

and financing research projects, which represents 66% of total project cost. Concerning

investment, the analysis also takes into account the cost of operating the technology park. The

income stream comprises: (i) salaries paid by the enterprises that will be set up within the

framework of park incubation activities through other research and development projects

implemented in the park; and (ii) income derived from rental of the offices, workshops and

laboratories of the science and technology park. The assumptions retained in terms of

employment are 25 jobs created annually thanks to the park for a salary level corresponding

to the average salary paid to public sector employees. The park’s service life is 25 years. In

light of the assumptions retained, the Net Present Value stands at USD 142.9 million. Details

of the FRR and the ERR are presented in Annex B7

5

Table 3.1

Key Economic and Financial Data Variables / Assumptions Values

Number of direct jobs created annually 25

Activity time (years) 30

Average annual salary (USD) 39 560

Service life of the technology park (year) 25

Office, workshop and laboratory occupancy rate 80%

Discount rate (%) 20 %4

Technology park construction, depreciation and operating cost (I, USD) 107 266 479

NPV (USD) 142 865 951

FRR 33%

ERR 24.5 %

3.2 Environmental and Social Impact

3.2.1 The PDST has been classified under Environmental Category 2 according to

the Bank’s environmental and social procedures on account of its limited negative

environmental impacts mainly linked to the construction of the science and technology

park, which is the subject of Component 1 of the project "Support for Research Activities".

Given the nature of technology park construction activities and the environment concerned,

the Operational Safeguards applicable to the PDST are: OS-1 “Environmental Assessment”;

OS-3 “Biodiversity and Ecosystem Services”; OS-5 “Working Conditions, Health and

Safety”. However, not all of them are applied systematically. The ESMP presents mitigation

measures to ensure project compliance with the operational safeguards and Angola’s

regulations. Additional projects will be conducted during project implementation.

Environment

3.2.2 Conducted on the basis of project documents and the visit to the site of the

future Science and Technology Park, the assessment shows that project activities will

have limited negative biophysical and social impacts. In fact, the site identified for the

construction of the Science and Technology Park is found on the location reserved for the

expansion of the existing academic zone in Mabubas Council, Dande Municipality. The

negative environmental impacts will be those from site and access road construction works.

They will include dust particles during construction, noises and vibrations from construction

works, loss of biophysical and ecological resources, water and soil pollution, impacts on the

health and safety of workers and communities, etc. The negative impacts are linked to: (i) the

risk of displacement, destruction of property and disruption of socio-economic activities; (ii)

the risk of social conflict resulting from the non-employment of the local labour force; and

(iii) pollution and nuisances from the movement of vehicles carrying supplies to the

construction site. The potential negative impacts during the operation phase include: the

production of solid wastes and waste water, reduced drinking water and energy supply and

lower safety levels. As indicated in the ESMP, these few negative impacts could easily be

mitigated or minimized through the application of site management rules. The summary of

the ESMP has been approved by ORQR and will be published on the Bank’s web site.

Climate Change

3.2.3 The project has no high climate change risk. In fact, the project will not entail

large-scale deforestation or disturbance of river beds, which could have affected overall

project climate risk assessment. The only activity with a climate risk is the deforestation of

4 By way of comparison, the discount rate of the National Bank of Angola (Central Bank) stood at 9.92% at the end of 2014 (United Nations

Statistics Division) and the interest rate on bank loans amounted to 16.4% in 2014 (World Bank).

6

the site needed for the construction of the science and technology park. It is not a large-scale

activity and its impact will be minimized through measures aimed at reducing the

deforestation zone and the reforestation of the developed site. Furthermore, the project will

support the enhancement of environmental education in the academic zone within which the

science and technology park is found. Moreover, environment, energy and climate change

will be among the research sectors covered by the activities of the science and technology

park. Education could play an important role in reducing the negative impacts of extreme

climatic events.

Social Issues

3.2.4 During the period following the restoration of peace in 2002, Angola’s economy was

very dynamic, recording a growth rate above the regional average. However, this macro-

economic performance has produced very little impact on the income and well-being of poor

people. Unemployment is also a major concern as most of the unemployed are youths and

least skilled persons. The Government believes that these problems can be solved within the

framework of a comprehensive policy comprising investment in human resources through

support for scientific research and technology development, which are required to foster

sustained economic growth and social development. The project’s positive impacts concern

its three phases and are mainly: entrepreneurship development, job creation and

unemployment reduction (the science and technology park could contribute to incubating an

enterprise per year and per sector of activity, which, given the size of an SME, could

represent at least 50 direct jobs per year), stimulation of the local and regional economy,

increased income, improved living conditions and poverty reduction; greater access to

drinking water, electricity and healthcare services by the local communities; improved quality

of education in schools in the academic zone; opening up of the area and improved

movement of the local people, and better gender mainstreaming in the science, technology

and innovation sector. Many of the project’s negative social impacts are linked to: (i) the risk

of displacement, destruction of property and disruption of socio-economic activities; (ii) the

risk of social conflict resulting from the non-employment of the local labour force; and (iii)

pollution and nuisances from the movement of vehicles carrying supplies to the construction

site.

Gender Issues

3.2.5 Available data show that men and women represent 68% and 32%,

respectively, of researchers in the country. This situation illustrates the wide gender-based

disparities in research activities which the project is expected to contribute to reducing with

time. It could be considered that gender-based disparities in science, technology and

innovation mainly, or even exclusively, concern higher education and research institutions.

However, it is worthwhile bearing in mind that the participation of individuals in research

activities is contingent on their past experience which significantly influences the probability

of their being involved or not in science, technology and innovation at the higher level. In this

respect, the low representation of women in scientific and technological research has two

main causes: (i) it is probably due to overall gender disparities in terms of the level of

educational attainment (for example, if few women reach the higher education level, they will

necessarily be insufficiently represented in research irrespective of their training); or (ii) it is

more probably linked to women’s low propensity for scientific and technological training,

even where they have a high level of education. However, available statistical data allow for

the analysis of only the issue of gender-based levels of education.

7

Graph 1

Gender-Based Educational Profile, 2009

Girls Boys

Access to primaryEducation

Completoin of primaryEducation

Access to secondaryEducation 1

Completion of secondaryEducation 1

%

Level of Education

Source: Data from the UNESCO Institute of Statistics

3.2.6 Graph 1 shows wide gender-based disparities in primary school enrolment in

Angola, with contrasting trends in the first cycle of secondary education. In fact, the girl-

boy parity index regarding access to primary education is 0.854, showing that an average of

854 girls go to school for 1,000 boys. This disparity level increases slightly between the

beginning and the end of primary education, with the parity index dropping to 0.805 at

primary school completion. However, given the low transition between the end of primary

education and the beginning of secondary education for boys, the rate of access by girls to

secondary education is higher than that of boys, standing at 22 %, as against 16 %.

3.2.7 Available fragmented information helps to learn useful lessons for project

design. In fact, it shows that actions limited to higher education would only have limited

impact on gender disparities in research, given that such disparities are the result, at least

partly, of a process which begins from primary education.

3.2.8 The envisaged project will contribute to reducing gender-based disparities in

science, technology and innovation by financing scholarships and research projects. These activities to be carried out under Component 1 of the project will lead to the training of

80 women in fields related to project-targeted economic sectors as well as the financing of

125 scholarships for girls in scientific and technological fields in secondary education. The

project will also help to finance 20 research projects selected on a competitive basis, but

whose teams will be headed by women, in order to contribute to women’s leadership in the

research sector and the development of research teams led by women. Lastly, to fill the

knowledge gap identified in this section, the project will finance the conduct of a survey on

gender-based disparities in science and technology. The total cost of gender-based disparity

reduction activities is USD 8.542 million.

Involuntary Resettlement

3.2.9 Given that land has been provided to the Ministry of Science and Technology

by the Dande Municipality for the construction of the science and technology park, the

project will not entail the displacement of persons. Project-financed activities will be

carried out on public land already allocated for that purpose. However, resettlement issues

must be taken into account when temporary or permanent roads and temporary areas for

storage of materials will be defined. All physical or economic displacements should be

avoided.

8

IV. PROJECT IMPLEMENTATION

4.1 Implementation Arrangements

Project Coordination and Management

4.1.1 The Directorate of Planning of the Ministry of Science and Technology (MST) will

be responsible for project implementation. To facilitate smooth project implementation, the

MST will appoint a project coordinator, a financial management officer, a procurement officer

and a monitoring and evaluation officer. The terms of reference and CVs for these various

positions will be submitted for Bank approval. Moreover, given that the MST has never

implemented a project financed by a multilateral development bank, its services do not have

the required capacity for project implementation. The project team will, therefore, be backed

by technical assistants to be recruited on a competitive basis following an invitation for bids.

This technical assistance will be financed with Bank resources and will comprise three

specialists in the following areas: procurement, financial management, and monitoring and

evaluation. The institutional framework is described in detail in Technical Annex B3.

4.1.2 Given the number of institutions involved in project implementation, a Project

Steering Committee will be established. It will be chaired by the Ministry of Science and

Technology, and comprise the various institutions concerned. Besides the Ministry of

Science and Technology, the Steering Committee will comprise notably the Ministry of

Higher Education, the Ministry of Education, the Ministry of Industry and the Ministry of

Environment. The committee will be responsible for overall project orientation and its role

will be to facilitate consultations. It will validate the annual work plan and its budget, and

approve the annual technical and financial implementation report. The project team will

provide secretarial services for the committee which will meet once every six months.

Procurement Arrangements

4.1.3 All procurements of goods and services financed with ADB resources will be

done in accordance with Bank Rules of Procedure for the Procurement of Goods and

Works (May 2008 Edition, revised in July 2012) or, as appropriate, Bank Rules of Procedure

for the Use of Consultants (May 2008 Edition, revised in July 2012), using Bank standard

bidding documents. Only suppliers, entrepreneurs and consultants from Bank member

countries as well as goods manufactured in and works and services supplied from these

countries will be eligible for ADB financing.

4.1.4 The procurement specialist appointed by the Ministry of Science and

Technology must take several training courses in Bank Procurement Rules of

Procedure (especially during Bank fiduciary clinics and missions), and be supported by a

technical assistant. Technology park construction works as well as park and laboratory

equipment will be procured through international competitive bidding (ICB). A procurement

plan will be prepared and submitted for Bank approval. The procurement plan will cover an

initial period of 18 months and updated every year or, as appropriate, throughout the project

duration. The summary of procurement terms and conditions are outlined in Annex V and the

detailed procurement methods presented in Technical Annex B5.

Financial Management

4.1.5 The financial management (FM) of the Ministry of Science and Technology (MST)

under the Science and Technology Development Project (PDST) was evaluated by the Bank’s

Procurement and Fiduciary Services Department (ORPF.2), in accordance with the Financial

9

Management Policies for Operations Financed by the African Development Bank Group

(2014), the Financial Management Manual for Public Sector Operations financed by the

African Development Bank Group (2014) and the Guidelines for Financial Management and

Financial Analysis of Bank Group Operations (2014).

The findings of the evaluation of the financial management system (which comprised a

review of the budget system, accounting, internal control, flow of funds, financial reports and

audit of financial statements) revealed that the existing arrangements do not meet Bank

minimum requirements for ensuring that project funds are efficiently and economically used

for the purpose for which they are intended. On the whole, the residual risk level of financial

management is deemed moderate. The financial management arrangements for mitigating

risks are summarized below.

Budget System: the annual project budget will be prepared on the basis of Government’s

policy guidelines and the applicable national regulations. The applicable procedures for

annual project budget preparation will be taken from the administrative, accounting and

financial procedures manual to be prepared and completed within the six (6) months

following project launching. The annual project work plans and budgets will be prepared by

the Project Executing Agency with the support of all beneficiaries of project resources, and

then submitted to the Project Steering Committee and the Bank for approval.

Accounting System: the accounting system to be established for the PDST could be cash

accounting and the accounting principles could be those in force in Angola, which are similar

to international public sector accounting standards (IPSAS). This accounting system will

have to be automated. Hence, the project will acquire an automated accounting package

which will be used to record all transactions and report, in due course, on the management of

project funds. An administrative, accounting and financial procedures manual for the project

will be prepared by a consultant and will contain, in the form of clear and precise

instructions, all routine project operations and financial information disclosure obligations.

Internal Control and Administrative and Accounting Management (AAM): for the

purposes of this project, the Bank will carry out regular supervision in the form of reviews of

documents and procedures, and regular field visits to ensure that the Project Executing

Agency administers the appropriate internal control systems and complies with the main

procedures. The administrative, accounting and financial procedures to be followed by the

Project Executing Agency will be documented in the Administrative, Accounting and

Financial Procedures Manual that will be prepared for this project.

4.1.6 Disbursements under this project will be in accordance with the rules and

procedures set out in the Bank’s disbursement manual. The payment methods adopted

under this project for expenditure to be financed with loan resources are the direct payment

method, the reimbursement method and the special account method. The special project

account will be opened in a commercial bank under terms and conditions acceptable to the

Bank. The Bank will issue a disbursement letter describing the project disbursement process

in detail.

4.1.7 The Project Executing Agency will be required to submit consolidated

quarterly progress reports comprising all the sources of financing and project

expenditure during the quarter. This report must be submitted to the Bank within 45 days

following the end of each quarter. In addition, at the end of each financial year, the Project

Executing Agency must produce annual financial statements in accordance with international

public sector accounting standards (IPSAS) relating to financial information using the cash

accounting method. These statements will comprise at least: (i) a statement of resources

received and payments made under the project during the year; (ii) a statement of certified

expenditure for the period; (iii) a comparative statement of the project budget and effective

10

expenditure; (iv) a statement of commitments for the period; (v) the accounting principles

adopted and related explanatory notes; and (vi) a declaration by the official of the Project

Executing Agency stipulating that project funds have been used for the intended purposes

specified in the project financing agreement.

4.1.8 The annual project financial statements will be audited by an independent

private external auditor recruited on a competitive basis. The external auditor will be

recruited nine months after project launching. The project financial statements will be audited

in accordance with Bank-approved audit terms of reference, and the audits will be conducted

in accordance with international standards of auditing (ISA) as promulgated by the

International Federation of Accountants (IFAC), and the audit report, including the letter to

Management, will be submitted to the Bank no later than 6 (six) months after the end of the

financial year under review, in accordance with the financial clauses of the legal agreements.

Audit costs will be paid with ADB loan resources.

4.2 Project Monitoring and Evaluation

4.2.1 The MST and the Bank will jointly ensure project monitoring and evaluation.

To that end, the Country Office will play a crucial role. The Country Office’s role

primarily concerns dialogue with the national party, this role being more important in this

case given the linguistic context. It also concerns support to the project management team

through regular training in Bank procurement, financial management and disbursement

procedures.

4.2.2 A monitoring and evaluation specialist will ensure the internal monitoring and

evaluation of project activities and project logical framework indicators. Under the

supervision of the Project Coordinator, the management team will prepare quarterly and

annual progress reports which will be submitted to the Bank. All reports must comply with

Bank formats. Gender-disaggregated data will be provided in the reports. Supplementary

basic data will be collected, as appropriate, in accordance with the performance indicators

adopted for the project.

4.2.3 The external monitoring and evaluation system will be designed on the basis of

the outcome and output indicators defined in the logical framework. In addition, the

Bank will undertake at least two (2) supervision missions yearly. The Bank Country Office in

Angola (AOFO) will coordinate all monitoring missions and also ensure close project

implementation monitoring. At the end of thirty (30) months of implementation, the project

will undergo a mid-term review which will examine the progress made in relation to the

logical framework indicators and the annual activity plans. The borrower and the Bank will

jointly prepare the project completion report. The implementation schedule of the main

activities is summarized as follows:

Table 4.1: Monitoring Phases and Feedback Loop Duration Phase Monitoring Activities/Feedback Loop

October 2015 Loan Approval by the

Board of Directors

Answers to Questions by Executive Directors, Notification to

Government

January 2016 Launching Mission Project Launching Mission, Training of Project Team Members

2016-2020 Implementation of

Activities Supervision Missions, Disbursements, Audits

July 2018 Mid-term Review Update on Project Progress, Project Modifications.

December 2020 Completion Report Review of Project Achievements, Analysis of Disparities Between

Objectives and Achievements, Lessons to be Learned

March 2021 Project Closure Closing of Accounts, Cancellation of Balances, Repayment to the Bank

of Special Account Balances, Where Applicable

11

4.2.4 Impact assessment will be part and parcel of monitoring and evaluation. To that

end, the project will support the establishment of an intellectual property database, as well as

a business development database relating to the activities of the science and technology park

and research centres in general. These information systems will thus help to assess long-term

project impacts, notably through the establishment of start-ups, their development and

lifespan, the number of jobs created, the income they will generate, etc.

4.3 Governance

4.3.1 The Bank’s experience in Angola shows serious difficulties in project

implementation. Moreover, the Ministry of Science and Technology, which will be

responsible for project implementation, is a newly created ministry with no experience in the

implementation of projects financed by multilateral development banks.

4.3.2 The procurement, financial management, disbursement procedure and

monitoring and evaluation technical capacity of the services of the Ministry of Science

and Technology will be built. In PDST implementation, the Bank’s usual internal accounts

control and audit system will be used throughout project implementation. In this connection,

measures will be taken under the PDST to mitigate the risk related to the project fiduciary

framework, especially through Bank control of the procurement process by issuing no

objection opinions on competitive bidding documents, proposals for contract award,

contracting and contracts, disbursement procedures, as well as supervision missions and

annual external project audits.

4.3.3 Concerning project financial governance, the Ministry of Science and

Technology will keep separate project accounts using software acquired with ADB loan

resources for cost accounting and the production of reports showing expenditure by

component, by category and by source of financing. Project accounts will be audited annually

by an external auditing firm recruited for that purpose. Financial and audit reports will be

submitted to the Bank within the six months following closure of the accounting year.

4.4 Sustainability

4.4.1 Project sustainability will be ensured by the park’s administrative and financial

autonomy, the implementation of income-generating activities, as well as the policy and

financial priority given to the development of science and technology. In fact, the legal

status provided for the operation of the science and technology park is that of a private non-

profit association which enables it to enjoy administrative and financial autonomy and, thus,

be able to adapt to changes in the economic context in which its activities are to be

implemented. This autonomy will also enable it to generate own resources as provided for in

its objectives. Own resource-generating activities will include: implementation of research

projects financed by enterprises, conduct of tests and certification, training activities, hiring

of technology park halls, etc.

4.5 Risk Management

4.5.1 The project implementation risks identified are linked to the capacity of the

Ministry of Science and Technology and to project design elements. The risks include: (i)

low private sector involvement in technology park activities; (ii) weak institutional capacity

and lack of skilled human resources for project implementation and monitoring and

evaluation; and (iii) low retention of researchers trained under the project. The table below

presents measures to mitigate the risks identified.

12

Risk Level Mitigation Measure

Low private sector involvement in

technology park activities Moderate

Granting legal and financial autonomy to the science and

technology park

Industrial private sector involvement in technology park

design and project implementation

Weak institutional capacity and

lack of skilled human resources

for project implementation and

monitoring and evaluation

High

Establishment of an appropriate implementation

mechanism and recruitment of qualified specialists to back

MST in project implementation

Low retention of researchers

trained under the project High

Provision of sufficient incentives to retain trained

researchers, including a ten-year contract of employment

4.6 Knowledge Building

Knowledge building is the main project objective, given the sector and nature of the

activities financed. The project will contribute to knowledge building through the

identification of technological solutions to the problems of enterprises, technology transfer

and innovations which will be backed by the industrial incubator. It will also support

knowledge building by training many engineers and researchers in the targeted economic

sectors. Lastly, the project will provide various forms of technical assistance for research

project assessment, strengthening the framework for the training of secondary school

teachers, establishing the industrial property database, etc.

V. LEGAL FRAMEWORK

5.1 Legal Instrument

The financing instrument proposed to the Republic of Angola is a USD 90 million ADB loan.

5.2 Conditions for Bank Intervention

5.2.1 Conditions Precedent to Loan Effectiveness: ADB loan effectiveness shall be

subject to fulfilment by the Borrower of the conditions set forth in Section 12.01 of Bank Group

General Conditions Applicable to Loan Agreements and Guarantee Agreements.

5.2.2 Conditions Precedent to First Disbursement of Loan Resources: in addition to loan

agreement effectiveness, the first disbursement of loan resources shall be subject to fulfilment by

the Borrower, to the Bank’s satisfaction, of the following conditions: (i) appointment of a

project coordinator, whose qualifications and experience would have been considered

acceptable by the Bank; (ii) recruitment, on a competitive basis, of a financial management

specialist and a procurement specialist, with the requisite qualifications and experience; (iii)

opening of a special account, in a bank acceptable to the ADB, to receive project resources;

and (iv) forwarding to the Bank, evidence that the project site has been put at the disposal of

MST and that it is authorized to use and build on the said site set aside for the Science and

Technology Park..

5.2.3 Other Conditions: the other conditions are: (i) preparation and adoption of the

Administrative and Financial Procedures Manual no later than twelve months following

effectiveness of the project; (ii) purchase and installation of the accounting software no later

than twelve months after effectiveness of the project; and (iii) appointment of Bank-approved

private external auditors within nine months following effectiveness of the project; and (iv)

forwarding to the Bank, no later than twenty four months after effectiveness of the project,

the title deeds indicating that the MST is the legal owner of the site earmarked for

construction of the Science and Technology Park..

13

5.3 Compliance with Bank Policies

This project is consistent with applicable Bank policies. It will be implemented within the

framework of the Bank’s intervention strategy in Angola contained in the 2011-2015 CSP as

well as the Bank’s 2013-2022 Strategy.

VI. RECOMMENDATION

Management recommends that the Board of Directors approve the proposal to grant a USD

90 million ADB loan to the Republic of Angola for the purpose and under the conditions set

forth in this report.

I

Annex

Country Comparative Socio-economic Indicators

Year Angola Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 1 247 30 067 80 386 53 939Total Population (millions) 2014 22,1 1 136,9 6,0 1,3Urban Population (% of Total) 2014 61,5 39,9 47,6 78,7Population Density (per Km²) 2014 17,8 37,8 73,3 24,3GNI per Capita (US $) 2013 5 170 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 70,0 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 46,2 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 ... 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 149 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 43,4 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 3,1 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 4,3 3,4 2,5 0,7Population < 15 y ears (%) 2014 47,3 40,8 28,2 17,0Population >= 65 y ears (%) 2014 2,4 3,5 6,3 16,3Dependency Ratio (%) 2014 91,0 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 98,4 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 22,4 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 52,3 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 53,8 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 43,5 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 13,6 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 101,6 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 167,4 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 5,8 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 460,0 411,5 230,0 17,0Women Using Contraception (%) 2014 17,7 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 16,6 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 166,0 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 47,3 50,6 67,7 ...Access to Safe Water (% of Population) 2012 54,3 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 44,0 51,3 57 69Access to Sanitation (% of Population) 2012 60,1 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 2,4 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 320,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 85,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 91,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 15,6 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 2 400 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 2,5 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 140,5 106,3 109,4 101,3 Primary School - Female 2011-2014 109,6 102,6 107,6 101,1 Secondary School - Total 2011-2014 31,5 54,3 69,0 100,2 Secondary School - Female 2011-2014 24,8 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 36,8 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 70,6 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 82,5 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 59,1 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 3,5 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 3,9 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,5 43,4 43,4 28,9Forest (As % of Land Area) 2012 46,7 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 1,5 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

AngolaCOMPARATIVE SOCIO-ECONOMIC INDICATORS

septembre 2015

0

20

40

60

80

100

120

140

2000

2005

2008

2009

2010

2011

2012

2013

Infant Mortality Rate( Per 1000 )

Angola Africa

0

1000

2000

3000

4000

5000

6000

2000

2005

2007

2008

2009

2010

2011

2012

2013

GNI Per Capita US $

Angola Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

4,0

2000

2005

2008

2009

2010

2011

2012

2013

2014

Population Growth Rate (%)

Angola Africa

01020304050607080

2000

2005

2008

2009

2010

2011

2012

2013

2014

Life Expectancy at Birth (years)

Angola Africa

II

Annex II

Portfolio of Active National Projects as at 30 June 2015

Operation Approval Date Amount

Approved

Amount

Disbursed

Disbursement

Rate

Closing

Date Age Status

Agricultural Sector

BOM JESUS Rural Development Project 24/11/2005 17 200 000 9457040.3 54.98 30/06/2016 9.60 NON PP / NON PPP

Study on Agricultural Development in Cabinda Province 22/12/2014 420 045 0 0.00 30/06/2016 0.52

Fisheries Sector Support Project 15/05/2013 20 000 000 0 0.00 30/06/2019 2.12

Water and Sanitation Sector

Sumbe Water Supply, Sanitation and Institutional Support

Project 28/11/2007 12 000 000 4207222.42 35.06 31/12/2016 7.59 NOT PP / NOT PPP

Institutional Support for Sustainable Urban Water Supply

and Sanitation Service Delivery 01/04/2015 100 120 370 0 0.00 31/12/2020 0.24

Energy Sector

Electricity Sector Reform Support Programme 13/05/2014 711 045 379 426627227.4 60.00 20/12/2016 1.13 NOT PP / NOT PPP

Environment Sector

Environment Sector Support Project 11/03/2009 12 000 000 5175900.07 43.13 31/12/2015 6.30 NOT PP / NOT PPP

Social Sector

Poverty Reduction Institutional Capacity Building 23/02/2011 4 920 000 2097193.61 42.63 31/12/2015 4.35 NOT PP / NOT PPP

Study on Higher Education Financing and Private Sector

Involvement 14/02/2014 398 478 0 0.00 31/12/2014 1.37

Transport Sector

Study to Update the National Transport Sector Master Plan 17/09/2013 2 900 000 0 0.00 31/12/2016 1.78 PP

Multi-sector

Financial Management Support Project 14/11/2007 5 900 000 861198.08 14.60 31/12/2016 7.63 NOT PP / NOT PPP

Private Sector Development Institutional Capacity Building

Project 17/09/2014 17 670 900 0 0.00 31/12/2019 0.78 NOT PP / NOT PPP

Total

904 575 171 448 425 782 49.57

3.62

* SAP: PP (Problematic Project); PPP (Potentially Problematic Project); ARP (At-Risk Project = Project Classified as PP or PPP) ; S (Satisfactory Project)

III

Annex III

Matrix of Development Partners’ Activities in Angola

Thrust Areas

Bilateral Partners Multilateral Partners

Ger

man

y

Bel

giu

m

Sp

ain

Fra

nce

Ital

y

Isra

ël

Net

her

lan

ds

Po

lan

d

Po

rtu

gal

Un

ited

Kin

gd

om

Sw

eden

Jap

an

Un

ited

Sta

tes

No

rway

Den

mar

k

Bra

zil

Ind

ia

Ch

ina

AD

B

Eu

rop

ean

Un

ion

UN

DP

UN

ICE

F

ILO

Wo

rld

Ban

k T

O

T

A

L

Agriculture X X X X X X X X X X X 11

Capacity Building X X X X X X X X X X X X X X 14

Civil Society Reinforcement X X X X X X X X X X X 11

Decentralization X X X X X X X X X X 10

Economic Growth X X X 3

Economic Management Policies X X X X X 5

Education, Science and Technology X X X X 4

Energy X X X X X 5

Environment X X X X X X X 7

Fisheries X X 2

Food Security X X X X X 5

Health and HIV/AIDS X X X X X X X X X X X X 12

Human Rights and Democracy X X X X X X X X 8

Justice X X X X X 5

Oil Sector X X X 3

Governance X X 2

Private Sector Development X X X X X X X X 8

Public Administration X X X X X X 6

Public Finance Management X X X X 4

Regional Integration and Trade X X X X 4

Roads and Transport X X X 3

Telecommunications and Information Technologies X 1

Water and Sanitation X X X X X X X X X X 10

Other Areas

Demining X X X 3

Gender X X 2

Urban Development X 1

Youth Employment and Sport X X 2

IV

Annex IV

Map of the Project Area

Warning: This map has been provided by the staff of the African Development Bank exclusively for the use of the readers of

the report to which it is attached. The names used and the borders shown do not imply on the part of the ADB Group and its

members any judgment concerning the legal status of a territory or any approval or acceptance of these borders.

V

Annex V

Brief Presentation of Procurement Arrangements

USD Million

Use of

NPP or

NPS

Use of Bank

Rules of

Procedure

Contracts

not Financed

by the Bank

Total

1. Works

1.1 Construction of Technology Park 39.323 39.323

1.2 Development Works (Water, Electricity, etc.) 0.562 562

2. Goods

2.1 Procurement of Furniture (Technology Park) 1.124 1.685

2.2 Laboratory Equipment 3.932 3.932

2.3 Research Equipment (Small Capital Goods and

Sundry Equipment) 0.639 0.639

2.4 Secondary School Laboratory Equipment,

including Training in their Use 1.383 1.383

2.5 Reinforcement of Intellectual Property

Management: Establishment of an Intellectual

Property Database (Equipment)

0.240 0.240

2.6 IAPI Equipment 0.112 0.112

2.7 Computer Hardware (Project) 0.056 0.056

2.8 Vehicles (Project) 0.067 0.067

2.9 Procurement of 3 Computer Stations for

Computerized Accounting and Management System 0.013 0.013

2.10 Database on Business Development and Job

Creation (Equipment) 0.115 0.115

3. Consultancy Services

3.1 Studies and Works Supervision by Engineering

Firms 3.932 3.932

3.2 Technical Assistance for Construction of

Technology Park 1.142 1.142

3.3 Cohort Study on Gender-based Disparities in

Science and Technology 0.432 0.432

3.4 Establishment of a National System for Training

in Methodology (Preparation of Modules and

Training) 2.995 2.995

3.5 Training of Laboratory Technicians: Consultants 0.404 0.404

3.6 Establishment of an Equipment Maintenance

System (Technology Park, Existing Research Centres

and Secondary Schools): Consultant (Including

Database and Inventory of Existing Equipment)

0.288 0.288

3.7 Support to Counselling Services: Preparation of

Modules and Trainer (Consultants and Training of

Trainees)

1.939 1.939

3.8 Creation of the Technology Park Website 0.432 0.432

3.9 Production of a Cartoon on Science and

Technology 0.270 0.270

3.10 Reinforcement of Intellectual Property

Management: Establishment of an Intellectual

Property Database (Design - Consultant) 0.404 0.404

3.11 Training of IAPI Senior Officers 0.112 0.112

3.12 Analyses of National Intellectual Property

Systems and Proposal for Improvement 0.288 0.288

3.13 Development of a National Scientific Data

Management Policy 0.288 0.288

3.14 Procurement Specialist (TA) 0.888 0.888

3.15 Financial Management Specialist (TA) 0.888 0.888

3.16 Accounting and Financial Management 0.066 0.066

VI

Software (formatting, Licencing, Training)

3.17 Preparation of a Project Administrative and

Financial Procedures Manual 0.067 0.067

3.18 Monitoring and Evaluation Specialist (TA) 0.888 0.888

3.19 Database on Business Development and Job

Creation (Consultant) 0.441 0.441

3.20 Project Mid-term Review 0.153 0.153

3.21 Final Project Evaluation 0.173 0.173

3.22 Project Auditing 0.639 0.639

4. Miscellaneous

4.1 Environmental and Social Impacts 1.124 1.124

4.2 Reinforcement of Research Teams (MA,

Engineering, Doctorate and Post-doctorate

Scholarships) and Research Project Financing 14.233 14.233

4.3 Scholarships and Research Project Financing

(Gender) 8.110 8.110

4.4 Trainee Scholarships (National System for

Training in Methodology) 1.603 1.603

4.5 Training of Laboratory Technicians: Trainee

Scholarships 0.081 0.081

4.6 Support to Counselling Services: Organization of

Regional Counselling Seminars 2.932 2.932

4.7 National Science and Innovation Awards 1.054 1.054

4.8 Organization of Inventors’ Fair 0.616 2.581 3.197

4.9 Science and Technology Promotion (Debates,

Feature Articles, Conferences, Drama, etc.) 0.639 0.639

4.10 Organization of a National Science and

Technology Conference 0.639 0.639

4.11 Reinforcement of Intellectual Property

Management: Dissemination of National and

International Regulations and Procedures (Seminar) 0.633 0.633

4.12 Functioning of PMT (Office Equipment and

Consumables, Communication, Vehicle

Maintenance, Upkeep, Fuel, Insurance, Daily

Subsistence Allowance)

0.291 0.291

4.13 Project Coordinator 0.153 0.153

4.14 Financial Management Specialist (Civil

Servant) 0.115 0.115

4.15 Monitoring and Evaluation Specialist (Civil

Servant) 0.115 0.115

4.16 Procurement Specialist (Civil Servant) 0.115 0.115

4.17 PMT Secretary 0.115 0.115

4.18 PMT Driver 0.153 0.153

Grand TOTAL : 0.614 89.386 10.000 100.000

VII

Annex VI

Rationale for Financing 90% of PDST Cost with ADB Resources

After 27 years of civil war, Angola has overcome many handicaps to become the third

economic power in Africa, behind Nigeria and South Africa. According to data contained in

the National Science, Technology and Innovation Policy (PNCTI, Política Nacional de

Ciência, Tecnologia e Inovação), at independence in 1975, there were only three university

graduates in Angola, against 5 000 in 2002 when peace was restored. However, much effort is

still required for Angola to acquire the capacity needed to implement and take advantage of

the National Science, Technology and Innovation Policy. A number of studies conducted by

international organizations on innovation issues, systematically rank Angola at the bottom of

the innovation classification list. So, according to data from the Global Competitiveness

Report 2014-2015 (published by the World Economic Forum), Angola is ranked at the bottom

of the list of countries with respect to key indicators of the impact of science and technology

on productive activities, notably: innovation capacity (142nd out of 144 countries surveyed,

with an average score of 2.7 on a scale of 1 to 7); quality of scientific research institutions

(142nd out of 144 countries, with an average score of 1.9); and collaboration between

university institutions and the industrial private sector in research and development (142nd out

of 144 countries surveyed, with an average score of 2).

The project will contribute to Government’s efforts to reduce poverty through industrial

development and economic diversification. This project mainly seeks to create the necessary

conditions for science, technology and innovation to have a greater impact on the national

economy. In so doing, the Bank intends to establish appropriate entities to foster the

development of a knowledge-based society and ensure the transfer of its benefits to the entire

economy. The project was prepared in a context of a sharp drop in oil prices which recently

compelled the Government to reduce the price of oil in the 2015 State Budget, adopting a

price assumption of USD 40 per barrel, against USD 80 initially projected. Given such

adjustment of major macro-economic impacts, the Government was forced to significantly

reduce its expenditure. With a projected average price of USD 55 per barrel in 2015, the

country should record a huge budget deficit of about USD 14 billion (that is 7.6% of GDP),

which reduces the leeway for expenditure in general, and investment in particular.

In light of the foregoing, it is proposed that 90% of total project cost be financed with an

African Development Bank loan, and 10% with national counterpart contribution instead of

the 50% required in the case of the Republic of Angola. This request is the result of the sharp

decrease in total public revenue (a shortfall of about 35.7% compared with revenue for 2014)

owing to falling oil prices. In fact, the share of the State budget allocated for science,

technology and innovation dropped from 0.54% in 2014 to 0.3% in 2015. Nevertheless, the

Government attaches special importance to the promotion of science, technology and

innovation as attested to by the National Development Plan (NDP) 2013-2017 and the

National Skills Development Plan (Plano Nacional de Formação de Quadros - PNFQ). As

underscored in the policy on expenditure eligible for Bank Group financing, the country’s

commitment should not only be measured by the Government’s counterpart contribution, but

also by its strategic commitment to the project’s development goal.

VIII

1. Country’s Commitment to Implementing its Comprehensive Development

Programme

Despite real macro-economic progress (12.8% non-oil GDP annual growth between 2003 and

2013), Angola’s social situation is by far worse than in countries with a comparable level of

income. There are great income inequalities, with the wealthiest 10% possessing one third of

total national income. The incidence of poverty is estimated at 37% of the total population,

60% of whom live in rural areas. The under-five mortality rate is 167.4 deaths per 1000 live

births, against 43.4 per 1000 in middle–income countries. Thus, life expectancy at birth in

Angola is 51.9 years, whereas it is 70 years on average in middle-income countries. In the

area of education, the primary school completion rate in Angola is 54.3 %, against 95.6% in

middle-income countries. Concerning employment, the unemployment rate is only 5.2% in all

middle-income countries, whereas it is 26 %5 in Angola.

To achieve human development and reduce poverty, the country has prepared a National

Development Plan (NDP) 2013-2017 which seeks to promote human development and the

well-being of Angolans, improve the quality of life and combat hunger and extreme poverty.

It comprises eight main thrusts for Angola’s development, namely: (i) ensuring national unity

and cohesion; (ii) building a democratic and participatory society to guarantee fundamental

freedoms and rights, and civil society development; (iii) promoting human development and

the well-being of Angolans to improve the quality of life and combat extreme poverty; (iv)

fostering sustainable, competitive and equitable development to guarantee the future of

coming generations; (v) promoting the development of science, technology and innovation;

(vi) supporting entrepreneurship and private sector development; (vii) ensuring the

harmonious development of the national territory; and (viii) promoting the competitive

integration of the Angolan economy into the global and regional contexts.

Summary of National Development Plan 2013-2017 Implementation: Angola’s National

Development Plan 2013-2017 provides for the implementation of 390 structuring projects for

an estimated total cost of USD 63 billion (of which 84.5% of public financing and 15.5% of

private financing). Priority projects concern energy (67.3%), the water sector (11.2%) and

programmes for the reconstruction of secondary, higher and vocational training centres

(7.8%). NDP 2013-2017 implementation has been impeded by the drop in tax revenue owing

to falling oil prices. Nonetheless, the Government has already made progress in the energy

sector and committed about USD 12 billion for the period 2011-2018 in the construction of

new hydroelectric dams and the rehabilitation of small hydroelectric systems and thermal

power plants. The total amount of investments required in the energy sector stands at USD 23

billion for the entire NDP implementation cycle. The Government also invested about USD

2.2 billion in the water sector over the 2011-2014 period. Other projects costing USD 3.7

billion are awaiting financing with the support of development partners. Angola has also

made considerable progress towards financing infrastructure reconstruction and expansion,

especially roads, ports, railways and telecommunications. Although the country currently

spends close to USD 4.3 billion in infrastructure annually, there is need to improve

management and maintenance. The Government has realized the need for economic

diversification and has embarked on a number of infrastructure projects to link urban and

rural areas and promote the development of agriculture and entrepreneurship in order to foster

job creation. A total of 39 projects with the potential to foster structural transformation have

been identified. On the whole, NDP 2013-2017 implementation has fallen short of

expectations and the goal of increasing the average GDP growth rate to 7% may be

5 African Economic Outlook 2015

IX

jeopardized by the currently unfavourable macro-economic environment. For example, in

2015, the Government has already been forced to reduce total expenditure by about USD 14

billion, after halving its oil price assumptions to USD 40 per barrel. This adjustment is

expected to increase the budget deficit to 7% of GDP in 2015, against 3.1% in 2014, and

reduce the capacity to invest in structural transformation projects, particularly in the

construction, energy, water, education and health sectors.

The science, technology and innovation sector in particular has been given pride of place in

the industrialization and economic diversification strategy. The sector has also been given

prominence in the National Skills Development Plan (PNFQ). The plan thus comprises an

action plan for training and building the capacity of higher education teachers and researchers.

According to PNFQ, Angola should produce 130 doctorate and 480 master’s degree holders

by 2017. In addition, the National Science, Technology and Innovation Policy provides for

the preparation of an Annual Science, Technology and Innovation Plan (PLANCTI, Plano

Annual de Ciência, Tecnologia e Inovação) comprising concrete short-term projects. Hence,

the National Technology Centre and the National Centre for Information Technologies were

established or rehabilitated in 2011.

Mechanisms being prepared could contribute to better incorporating science, technology and

innovation initiatives into the economy. They include the law on scientific research and

technology, as well as the National Science and Technology Development Fund. In addition,

private investments in science, technology and innovation should be stimulated following the

recent approval of two important measures. Firstly, there is the establishment of FACRA,

Angola’s pioneer venture capital fund, with USD 250 million to invest in innovative

technologies and, secondly, the law on sponsorship (Lei do Mecenato) which allows for the

deduction of expenses from its taxes to support science, technology and innovation.

2. Financing Allocated by the Country to the Sector Targeted by Bank Assistance

The achievement of these objectives will require investments in physical infrastructure as well

as policy and sector reform measures to ensure the long-term viability and contribution of the

sector to the entire economy. In that connection, for the period 2013-2017, the National

Development Plan allocates an indicative amount of USD 80 million for the implementation

of the National Science, Technology and Innovation Policy, which represents 0.13% of total

NDP disbursement. The PNFQ provides for an additional allocation of USD 230 million to

science, technology and innovation. According to PLANCTI 2013, nearly USD 680 million

has been allocated to STI projects, of which USD 420 million to ongoing projects. The PNFQ

is mainly financed by each Ministry, while coordination activities are the responsibility of the

Presidency which allocated USD 250 million for 2015.

3. Country’s Budget Situation and Debt Level

According to African Economic Outlook (AEO) 2015, the current low oil prices should lead

to a significant public expenditure reduction in Angola and a resulting slowdown in GDP

growth to 3.8% in 2015, recording a decline compared with the 4.5% growth rate in 2014.

The overall budget balance, which showed a surplus over the last four years, recorded a

deficit of about 2.8% of GDP in 2014 which is expected to worsen to 7.6% of GDP in 2015.

The country’s international reserves, which stood at USD 26 billion at end-December 2013 (6

months of import cover), have already declined to USD 3 billion since June 2014. Falling oil

prices will also lead to a 28.4% reduction in foreign exchange reserves compared with 2014.

They are expected to stand at USD 19.2 billion in 2015 on average (about 5.6 months of

import cover). This decline in foreign exchange reserves will have a negative impact on the

X

nominal exchange rate of the local currency which is expected to depreciate by 11% to 114

AON/USD at end-2015, and further depreciate by 6% in 2016 owing to the drop in oil

revenue.

In such a context, the country’s current capacity to mobilize resources for financing project

national counterpart contributions is limited. In fact, the drop in oil prices should worsen the

country’s current account deficit from 2.7% in 2014 to 5.9%, according to AEO estimates.

The resulting decrease in revenue has already reduced Government’s capacity to mobilize

resources to finance major infrastructure projects and capacity building initiatives. Some

infrastructure development programmes being implemented in the road, energy and

telecommunications sectors, including social (health, education, water and sanitation)

infrastructure, have thus been postponed due to lack of resources. The proposed project could

make an essential contribution to enable the Government to continue its economic

diversification and poverty reduction efforts. This project should help to build the foundation

for science, technology and innovation to have a greater impact on economic activities

through the contribution of new technologies to the economy, skills development and job

creation for inclusive growth.

Despite the prospect of budgetary constraints and a difficult external position, Angola’s

external debt appears to be sustainable, although it is expected to increase from 22.1% of

GDP in 2013 to 29.2% of GDP in 2016. Moreover, the total public debt is also expected to

increase from 34.6% of GDP in 2014 to 40.3 % of GDP in 2016, as shown in Table A1

below.

Table A1

Angola’s Debt Sustainability Indicators

Description 2010 2011 2012 2013 2014 2015 (p) 2016 (p)

External Debt* 17.9 21.1 22.7 27.4 32.9 38.3 44.3

Internal Debt* 15.0 12.5 11.4 15.5 15.3 16.7 17.0

PV of Debt as % of GDP 39.8 32.2 29.6 34.6 36.6 38.8 40.3

PV of Debt as % of Exports 35.3 31.0 31.8 39.6 48.6 47.2 49.1

Debt Servicing as % of Exports 9.6 2. 4 8.5 4.4 6.5 6.9 7.5

Source: IMF Estimates, PV: Present Value, *: USD Billion, (p): Projections

Debt Management Capacity: the Government recently introduced significant debt

management improvements. In August 2014, the authorities started formulating a medium-

term debt strategy. This strategy is in keeping with Angola’s macro-economic framework and

defines medium-term objectives of currency mix and debt maturity structure, an element

which is currently lacking. The debt strategy is also expected to play an important role in

continuing the de-dollarization process. Meanwhile, Angola’s total stock of public debt

continues to increase and should reach USD 45.1 billion (about 44% of GDP) by the end of

2015, against USD 36.6 billion in 2014 (26.9% of GDP). This stock of debt comprises USD

21 billion (20.5% of GDP) of internal debt and USD 24 billion (23.4% of GDP) of external

debt. The increase in the stock of debt is due to domestic and foreign loans recently contracted

to finance various development projects, given the reduction in oil revenue. On the whole,

Angola currently does not run any risk of debt overhang, and it is considered, based on recent

debt sustainability analyses (by the Government and the International Monetary Fund), that

the country’s debt will remain within sustainable limits in the medium term.

Scope of Project Financing by External Partners: Official Development Assistance (ODA)

to Angola is insignificant, representing less than 2.1% of GDP. After many years of emphasis

XI

on social development projects, some major multilateral development partners have pooled

their efforts to improve joint financing of public investment expenditure management

programmes and, especially, infrastructure programme reforms. For example, the Japanese

Agency for International Development (JICA) recently approved a development policy loan

of USD 200 million following Bank approval of USD one billion to support the energy sector

reform. The World Bank has also approved a USD 450 million budget support programme

based on the operational framework of Angola’s Bank-prepared Country Strategy Paper

(CSP). Other development partners such as the European Investment Bank (EIB) and the

French Development Agency (AFD) are also exploring the possibility of investing in the

energy sector, especially in renewable energy, and have expressed interest in building on the

Bank’s experience through its CSP in order to jointly design future operations in the sector.

Conclusion

The Government of Angola has demonstrated its commitment to science, technology and

innovation through its development programme and the resources allocated to the sector.

Ninety per cent of the PDST cost will be financed with African Development Bank resources,

while the remaining 10% will be defrayed by the Government of Angola, instead of 50% as

provided for in Directive ADB/BD/WP/2007/106/Rev.2 - ADF/BD/WP/2007/72/Rev.2 of 2

May 2008 on the policy relating to expenditure eligible for Bank Group financing. This

financing breakdown takes into account: (i) the size of the project, the current commitment

levels, national budgetary constraints and the unfavourable macro-economic prospects; and

(ii) Angola’s 2005 financial parameters which allow the Bank to finance up to 100% of

project costs in the country.