Kenya Project Status Dec. 2014

Page 2: Project Status 1

2

Entrance wall; entrance gate design

Entrance wall condition before

Page 3: Project Status 1

3

Entrance wall condition after

Page 4: Project Status 1

EATL Office

Office conditions before

Page 5: Project Status 1

5

The side view of the office block, the entrance view

off the Administration block and the door step

made of marble with painting works complete

Office Block: aluminum cladding complete; AC installation complete, entry staircase done.

Page 6: Project Status 1

6

Reception Area of Office Block - before

Page 7: Project Status 1

7

Office Block – Reception Area

Page 8: Project Status 1

8

Office Block – Reception Area

Page 9: Project Status 1

9

Office Block – Interior staircase - before

Page 10: Project Status 1

10

Office Block – Interior staircase; the

correction of the previous status

Page 11: Project Status 1

11

Office Partitions Inside Office Block - Before

Page 12: Project Status 1

12

Office Block – all interior works complete; tint, and repainting of the office walls

Page 13: Project Status 1

13

Office meeting room before

Page 14: Project Status 1

14

Office meeting room after

Page 15: Project Status 1

Loading Bay

Before.

Page 16: Project Status 1

16

Loading Bay: access and observation platform complete; loading headers & valve

installation complete

Loading Bay

Page 17: Project Status 1

17

Loading Bay

Before.

After.

Page 18: Project Status 1

18

Entry weigh bridge: Before

Entry weighbridge

Page 19: Project Status 1

19

Entry Weigh Bridge & Cabin – After; Painting is complete. Installation of side beams to guard

vehicle is complete.

Entry weighbridge

Page 20: Project Status 1

20

Boundary Wall before

Page 21: Project Status 1

21

Street Lights

Installation of the street lights is complete.

Page 22: Project Status 1

22

Boundary Wall After.

Painting of the boundary wall is complete

Page 23: Project Status 1

23

Generator Room/ Oil Tank: before

Generator Room

Page 24: Project Status 1

24

Generator Room with diesel tank on top; the road is ready.

Generator Room

Page 25: Project Status 1

25

Generator Room with diesel tank on top

Generator Room

Page 26: Project Status 1

26

Before: With no paint and testing of RO & boiler was not done; pipe lines to RO was not

complete

Boiler and RO Plant House

Page 27: Project Status 1

27

Boiler & RO installation complete; water line to boiler and RO complete; insulation of steam

line in progress.

Boiler and RO Plant House

Page 28: Project Status 1

28

Installed RO and Boiler; Heavy fuel and water overhead tanks complete.

Boiler and RO Plant House

Page 29: Project Status 1

29

Weigh bride cabin with internet and

telephone.

Page 30: Project Status 1

30

Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank. - before

Page 31: Project Status 1

31

Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank.

Page 32: Project Status 1

32

Before; the weighbridge was not installed

Public Wash Room

Page 33: Project Status 1

33

wash Hand basins, toilets, overhead tanks and shower heads completed

Public Wash Room

Page 34: Project Status 1

34

Pump House

Page 35: Project Status 1

35

Tank farm MCC installed successfully – was moved from the temporary location (transformer

room) to here permanently. Foundation of the pump house is complete and fitting of the Header.

Pump House

Page 36: Project Status 1

36

Entry Guard House Before

Page 37: Project Status 1

37

Entry Guard house – ready with telephone and internet cable for connecting CCTV screen or

desktop to monitor trucks way in and out.

Entry Guard House

Page 38: Project Status 1

38

Exit Guard house – Side View

Exit Guard House

Page 39: Project Status 1

39

Before.

KRA Office & Transformer room

Page 40: Project Status 1

40

Ready with both AC, Telephone and internet point.

KRA Office

Page 41: Project Status 1

41

Transformer Room

Page 42: Project Status 1

42

Tank 1:

Tanks

Page 43: Project Status 1

43

Tank 2: Before

Tanks

Page 44: Project Status 1

44

Tank 3: Before

Tanks

Page 45: Project Status 1

45

Tank 4: Before

Tanks

Page 46: Project Status 1

46

Tanks Side view

Tanks

Page 47: Project Status 1

47

Tanks Side view

Tanks

Page 48: Project Status 1

48

Water Tank & Chimney for the boiler: 100% complete

Tanks

Page 49: Project Status 1

49

Pipe installation at the water tank. Successfully installed

Piping

Page 50: Project Status 1

50

Fire hydrant and product line from tanks to

loading bay

Piping

Page 51: Project Status 1

51

Road Works 100% done

Roads

Page 52: Project Status 1

52

Fire hydrant pipe before

Fire Hydrant pipes before and water line

from the county 100% complete

Page 53: Project Status 1

53

Fire hydrant pipe after

Page 54: Project Status 1

54

Insulation of steam lines complete

Pipe Insulation

Page 55: Project Status 1

55

Pipe Insulation

Page 56: Project Status 1

56

Will be used to trap any oil spillage from the tanks

Dyke Wall

Page 57: Project Status 1

57

To direct water away from the compound

Water Drainage before

Page 58: Project Status 1

58

Water Drainage after

Page 59: Project Status 1

59

Fire Hydrant line from the back side of the tank farm is 75% complete.Water transfer line from Tank 1 to tank 7 is on-going.

Page 60: Project Status 1

60

Installation of the agitators as per the required recommendations is complete in

phase one.