ROAD SAFETY AUDIT MANAGEMENT SURVEY
INTRODUCTION
Road Safety Audit is a formal examination of a future road or traffic project, or an existing road, in which
an independent, qualified team looks at the project’s crash potenial and safety performance. The road
safety audit may investigate general safety conditions, or it may focus on specific concerns or users.
OBJECTIVE:
To examine the safety level in the campus
To suggest improvements for safety purpose
To minimize accident risks on adjacent road network
To promote safety of all road users on new and existing roads of the campus
METHODOLOGY:
Dividing campus into number of stretches – In this road safety audit management survey we are
focusing on two routes:- Main Road (Main gate to Hostel thirteen)
- Hostel 10 to devi temple
Visual surveying roads of the campus
Identifying Problems and suggesting improvements
Report Presentation (Data and photographs)
1) MAIN ROAD (Main gate to Hostel 13):
DATA ANALYSIS AND FINDINGS:
a) Tilted Parking Sign Board
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 2/8
Suggestion:
Parking sign board should be revamped, so that it is visible to the road users.
b) Speed Restriction Board and No Horn Sign
c) Broken Pavement near main gate:
Suggestion: Pavement should be repaired, so that it can be used by pedestrians
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 3/8
d) NO PARKING Sign Board at the main gate – Parking is allowed at the main gate, therefore
wrong sign board
Suggestion: Parking Sign Board should be changed from NO PARKING to PARKING
e) Nhi chamka
Suggestion:
Double lines should be made single.
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 4/8
f) Broken pavement: Pavement on the left side of Hostel 10 road is broken which can lead to
accidents
Suggestion: Pavement should be repaired to avoid any mishap
g) Convo (nhi chamka)
h) Dangerous Shoulder Drop off between NCC and footer field area
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 5/8
i) In front of H-11 tree between the shoulder:
Suggestion:
j) Trees between the sidewalk on Hostel 8 to Hostel 6 road
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 6/8
Suggestion:
k) In front of Hostel 8 second gate, sidewalk obstruction due to construction work.
Suggestion:
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 7/8
l) Double lines not visible near football ground, speed limit sign board should also be there on this
intersection
Suggestion: Double lines should be made properly and a sign board indicating the speed restrictions
must be placed
m) Gutters and trees obstructing the sidewalk and shoulder near Hostel 5 road
2.) DEVI TEMPLE ROAD:
8/2/2019 Project Traffics
http://slidepdf.com/reader/full/project-traffics 8/8
a) Single line indicates that overtaking is allowed but the width of the road is too less to allow
overtaking of vehicle.
Suggestion:
Either Double lines should be made or else road width should be increased
b) Improper divider