608 ParkwayCoppell, Texas
75219
BeganMay 27th 2014
CompletedJune 18th 2014
Property RehabilitationRental Unit
Project
The rehabilitation consisted of 42 individual items targeted for repair and/or replacement.Items included:Electrical-replaced all fixturesPlumbing-replaced all fixtures1 exterior door replacement3 interior door slabs1 interior door replacementInterior door knobsExterior door locksDoor stops throughoutCabinet refinishing throughtoutPaint scheme requirements:Satin on wallsSemi-gloss in wet areasOil based semi-gloss on doors and trim
EntryBottom of front door rotten, patches in concrete from foundation repair, and fascia board with water damage, gutter missing.
Entry
Replaced front door with 6 panel pre-hung metal door and painted. Replaced fascia board and painted, installed gutter, and floated concrete at entry.
220 Volt 50 AmpStove Receptacle
Safety Violationwill not pass City of Coppell inspection
Stove ReceptacleReplaced receptacle box, mounted at stud in wall. Repaired drywall, texture and paint.
Centerpieceof
Living Room
Centerpiece of Living Room
Kitchen
Kitchen
Installed backsplash tile to match fireplace
Master Bathroom
MasterBathroom
Lighting
Lighting
Garage
Garage