proposal to construct
TRANSCRIPT
Prepared For:
City of Flint P.O. Box 99
Flint, MI 48501-0099
Flint River Watershed Coalition
432 N. Saginaw St. Suite 1001
Flint MI 48502
Prepared By:
Gary M. Lacy, P.E. Recreation
Engineering and Planning
485 Arapahoe Ave. Boulder, CO 80302
(303) 545-5883
Conceptual Design Report for the
Hamilton Dam Modifications Project
Flint, Michigan
November, 2008
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883
Table of Contents Introduction..................................................................................................................................... 1
Background..................................................................................................................................... 3
Economic Benefit............................................................................................................................ 6
Site Description............................................................................................................................... 7
Project Description........................................................................................................................ 11
Anticipated Use............................................................................................................................. 13
Accessibility.................................................................................................................................. 14
Maintenance.................................................................................................................................. 15
Costs.............................................................................................................................................. 15
Future Work .................................................................................................................................. 15
Conclusion .................................................................................................................................... 16
Appendix 1. Conceptual Cost Estimate ....................................................................................... 17
Appendix 2. Concept Plan ........................................................................................................... 19
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 1
Introduction
Built in 1920, the Hamilton Dam is located on the Flint River as it flows through the City
of Flint, Michigan. It once served not only as a dam, but a pedestrian bridge as well.
Today, however, this river-wide dam obstructs the river’s flow, presents dangerous
structural weaknesses and is a threat to public safety. Because of this current state of
disrepair, the Michigan Department of Environmental Quality has mandated the
Hamilton Dam be replaced. Recreation Engineering and Planning was contracted to
create a conceptual design for such replacement that would provide a unique recreational
whitewater opportunity in Flint.
The purpose of this project is to replace the current dam with a structurally and
hydraulically sound structure that maintains adequate upstream pool elevation, allows for
the City of Flint to pump water for a backup water system, maintain adequate bank head
pressure to not allow contaminates into the river, provide reasonable fish passage, and
provide a recreational amenity. Similar dams in cities across the country have been
converted to provide attractive recreational amenities while improving safety and
maintaining the purpose of the dam. The resulting improvements not only provide for
increased safety in the river, but serve as an attraction to residents and visitors who seek
whitewater for recreation, events, and competition. The net effect of such improvements
results in transforming a failing dam into a popular community attraction that stimulates
the local economy.
This report presents a conceptual plan and cost estimate for the construction of
improvements to the Hamilton Dam on the Flint River in Flint, Michigan. The
conceptual plan consists of recreational boating improvements as well as related bank and
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 2
access improvements. The proposed improvements will create a whitewater paddling
amenity for the local community and a resource for the region. The site is ideal due to
the amount of available gradient, flow and its location adjacent to the University and
downtown area. Adjacent infrastructure including parking, restrooms, lodging and
restaurants help make this site an outstanding location for this project.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 3
Background
Many communities across North America are looking to their river corridors, historically
centers of industry, as the heart of urban renewal plans. Rivers can serve as the catalyst
for economic development, and as the dominant natural feature of communities,
accessible river corridors with recreational amenities are key anchors. Whitewater Parks
and Courses are increasingly being explored and built by communities looking to create a
unique attraction and recreational opportunity of national importance.
The term “whitewater park” is analogous to a brand name that has been generally applied
to river access improvement projects all over the US. These projects are located in
diverse communities, with diverse goals. The common thread among all of these projects
is that elements of a public river corridor had become a liability. Whitewater parks
convert river corridors and failing dams from liabilities, to amenities that provide
recreational opportunities and economic stimulus.
Whitewater parks are an emerging trend in North America that provides river related
recreation near a population center. Whitewater parks vary in length from the longest, 1
mile, to the shortest, 1 single feature, but all meet the same goal: attracting diverse users
to a single destination where they can recreate without the logistical issues involved in
more traditional, point A to point B river trips.
These parks can be constructed in all types of rivers and can be designed to achieve a
range of different outcomes. In-stream modification, as seen in the Salida Whitewater
Park, consists of a feature created with carefully placed, native boulders within the
existing channel. The appropriateness of this type of improvement is based on the
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 4
availability of flow, the gradient of the stream in the immediate vicinity of the drop
structure, and the geotechnical makeup of the substrata of the river.
In-stream whitewater improvements are popular in appropriate rivers around the western US. This
structure is located in the Arkansas River in Salida, Colorado.
Dam modification whitewater parks are also a commonly pursued option, whereby an
existing dam is retrofitted with drop structures to create a whitewater course on the
backside of a dam. Dam modifications, like the Rio Vista Dam shown in the photo
below, serve to eliminate structural stability issues and mitigate existing navigability
hazards while maintaining the existing use of the dam and not negatively impacting the
floodplain. These projects are appropriate when a dam’s function needs to be maintained
but the downstream edge of the dam can be modified for navigation, recreation and fish
passage, or when the crest of a dam can be lowered and the vertical fall of the dam can be
redistributed through a longer reach.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 5
This whitewater park in San Marcos, Texas is an example of a dam modification project. The original crest of this dam and its diversion capabilities are maintained while the vertical drop on the back side of the dam is redistributed in a drop/pool sequence.
Diverse communities ranging in population and geographic characteristics are turning to
their rivers as a source of recreation, education, and local pride. Whitewater parks attract
citizens of all ages and socio-economic backgrounds. The operation of these parks across
the country has shown that these types of projects provide a number of benefits including
new recreational opportunities, economic stimulus, enhanced aquatic habitat and
environmental education opportunities.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 6
Economic Benefit
There is substantial, empirical evidence that river access improvements can have
significant, positive, economic benefits, for a local community. Whitewater Parks attract
a desirable demographic of users between the ages of 25-45 with disposable income and
the willingness to travel in pursuit of this specific recreational activity. Golden, Colorado
commissioned an economic impact study in the year 2000 for a whitewater park that was
built in 1996. At the time of the study, the project was shown to have an annual
economic impact of between $1.4million-$2million to the local community. This study
was for a stream which has a usable season of three months. The whitewater park in
Reno, Nevada has a projected economic impact of $18million over the first decade and
contributes to a $9million economic impact of the, annual, three day, Reno River
Festival.
The Truckee River Whitewater Park at Wingfield, Reno Nevada.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 7
Site Description
Flint River and
Hamilton Dam Project
Hamilton Dam project site. (Source Google Earth)
The location for improvements is at the existing Hamilton Dam located on the Flint River
in Flint, Michigan. Due to the site’s location adjacent to the University of Michigan and
Downtown Flint, it is expected to attract a diverse number of users.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 8
As built drawings of the existing Hamilton Dam. (Source US Army Corps of Engineers.)
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 9
Monthly Mean Streamflow: USGS 04148500 Flint River near Flint, MI from 1932-2007
0
500
1000
1500
2000
Jan
Feb
Mar
Apr
May Ju
n
Jul
Aug
Sep Oct
Nov
Dec
month
cfs
Mean-monthly flows at the proposed project site from October, 1926 through September, 1960. (source: http://waterdata.usgs.gov/nwis/monthly.)
Flows at the site vary from around 1500 cubic feet per second (cfs) in the early spring,
down to around 250 cfs in mid-summer to early fall. Peak streamflow data is shown in
Error! Reference source not found.. Extreme flood flows have historically reached
above 15,000 cfs in the Flint River. However, flows usually peak in the range of 4,000
cfs.
This historic flow data suggests that the project would be useable 12 months a year,
weather permitting. The most popular seasons for usage would during the spring and
summer months. Use of similar projects typically follows the hydrograph. When flows
are higher more experienced users will use the facility; when flows are lower during the
summer months less experienced users and bank-based users will frequent the site.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 10
Historical peak streamflows at the proposed project site (source: waterdata.usgs.gov, station USGS 04148500 Flint River Near Flint, Michigan.)
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 11
Project Description
Conceptual Plan for the proposed improvements at Hamilton Dam.
This plan illustrates the proposed layout of the suggested improvements at the Hamilton
Dam. A full-page version of this drawing is available in Appendix 1. The general layout
provides for three whitewater features/grade control structures located in the main
channel of the river adjacent to the University. Each feature would consist of a drop
structure with approximately two feet of head. The first structure will be located at the
existing dam, with the crest being approximately two feet lower than the existing crest.
The final two structures will be located downstream from the existing dam, upstream of
the Harrison Street Bridge.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 12
Typical profile view of a low-head dam modified for fish passage and safety.
The crest of this low head dam was similarly modified for safe passage.
A new pedestrian bridge would be constructed at the location of the dam, with trail
extensions to connect the park on river right with existing trails on river left. Selective
bank access improvements and bank terracing will be included on both banks between
the dam and the Harrison Street Bridge. This terracing will provide safe river access and
improve public safety while maintaining existing flood protection.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 13
Completed bank terracing at Reach of the Flint River that the Truckee Whitewater Park in Reno, NV. would benefit from bank terracing.
Anticipated Use
This project will serve many users and
purposes. The primary purpose of the
modifications is to replace the aging and
deteriorating dam with a structurally and
hydraulically sound structure.
Additionally, the site will be designed as an
attraction to whitewater enthusiasts such a
kayakers, canoeists and rafters. The
character of the features created by e
the drop structures will evolve as the flow
rates at the site increase and decrease
throughout the year. At lower flows th
park will provide recreation opportunities for less experienced river users as well as
intermediate and expert users who come to the site for fitness and practice. At higher
s
ach of
e Paddlers at the Pueblo Whitewater Park
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 14
flows of over 1000 cfs the more powerful whitewater features will create a regio
for intermediate and expert users while still allowing use of the project by inexperienc
users.
nal draw
ed
The design can also accommodate upstream fish passage. Future design phases will need
to consider the specific needs of critical local fish species. Generally, the proposed grade
control structures can provide short sections of both higher velocity flow and velocity
shelters to facilitate upstream fish movement.
Accessibility
The site is immediately accessible through the University of Michigan-Flint campus and
the downtown area. Access points would be constructed both upstream and downstream
of the whitewater features to allow for ingress and egress to and from the river.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 15
Maintenance
In-stream improvements are virtually maintenance-free. Regular inspections should be
scheduled to evaluate any significant erosion during the first year and every year
thereafter. Tree, ice and woody debris will be passed in the course of normal flows, but
should be removed if suspended during high-use times as they represent an immediate in-
stream hazard. Maintenance of the existing park will require typical park maintenance
for parking areas, restrooms, etc.
Costs
See the attached cost estimate. Normally, the bulk of this cost is in construction of in-
channel improvements. In-stream drops and pools should be constructed, along with any
related paths/ access ways, during low-flow periods. Reduction in rock costs through
donated or stored rock can have a significant impact on the total cost of the project.
Future Work
If the City decides to go forward with this project, future tasks include but are not
necessarily limited to:
• Detail Design
• Flood/Fluid Modeling
• Permit Applications
• Construction and Bid Documents
• Construction Phase Services
These tasks are categorized in Design and Construction Phase Services, as listed in the
attached cost estimate. It is recommended that the design team open a dialogue with
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 16
related planning and government agencies as soon as possible following the decision to
proceed, as it is often imperative that these stakeholders be included in the design
process.
Conclusion
Cost effective, recreational safety improvements can be made at the Hamilton Dam site.
These improvements will provide a solution to the structural stability concerns at the
Hamilton Dam, remove an existing hazard and provide a recreational amenity that will
attract recreational users and their families throughout the region, to Flint. The proposed
improvements will preserve the base of the existing dam while gradually redistributing
the vertical fall to eliminate the existing powerful hydraulic. The hydraulics formed by
the whitewater structures will be user friendly and will not act to keep inexperienced
boaters or users of inflatable craft trapped. Many communities have found that
whitewater parks not only solve safety issues, but also draw residents as well as visitors
to the river, thus providing an economic driver for the local community. . Similar
improvements have had enormous impacts on the quality of life and local economies of
communities throughout the country. REP’s $170,000 whitewater park in Golden,
Colorado has had an estimated 1.7 to 2 million dollar per year impact on the local
economy. Similar estimates have been made for our parks in Breckenridge and Vail.
Another project, a two-channel whitewater park on the Truckee River at Wingfield Island
in Reno, Nevada, has transformed a neglected and denuded section of downtown into a
revitalized urban greenway with walking paths, shaded riverside seating, and picnic areas
all surrounded by world-class whitewater. Just like the cities mentioned above, Flint has
the potential to create a world-class recreational amenity that could benefit the entire
community. For these reasons REP recommends including recreational improvements in
the modification of the Hamilton Dam.
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 17
Appendix 1. Conceptual Cost Estimate
Item # Description Estimated Quantity Unit Unit PriceItem Total
Price
1 Mobilization L.S. L.S. $50,000 $50,0
2
Dewater (During low-flow) open obermyer gates, construct coffer dams and area pumping.
L.S. L.S. $240,000 $240,000
3
Demo existing Bridge/Dam super structure and Gates
00
-leave concrete abutment walls and ogee crest.
L.S. L.S. $140,000 $140,000
4Grouted rock drop structures:
4A
At Dam Face
1,100cubic yards
grouted rock
$190 $209,00
4B
Drop # 2
1,600cubic yards
grouted rock
$190 $304,00
4C
Drop # 3
1,000cubic yards
grouted rock
$190 $190,00
5Boulder edge and terracing 1,400 LF $160 $224,000
6Large Random Boulders 20 L.S. $400 $8,000
Flint Michigan-Hamilton Dam Cost Estimate
0
0
0
11/3/2008
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 18
7miscellaneous heavy Equipment cost/hour
240 hours $180 $43,2
8
landscape restoration and miscellaneous signage, put-ins, take-outs and trails
L.S. hours $90,000 $90,0
$1,498,200
9 Contingency 25% $374,550
10Design and Permitting 16% $239,712
$2,112,462
11Pedestrain Bridge replacement L.S. $200,000
$190 $180 $400
Itemized costs:Grouted Rock costs per cubic yardHeavy equipment cost/hourLarge Random Boulders
Subtotal
Total
00
00
Recreation Engineering and Planning
485 Arapahoe Ave Boulder | CO | 80302
(303) 545-5883 19
Appendix 2. Concept Plan