proposed comprehensive development at wo …...on 12 november 2010, the contractor issued a letter...

73
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 (Rev. A) February 2011 Report No.: 266567/16/A

Upload: others

Post on 08-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long

Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 (Rev. A)

February 2011

Report No.: 266567/16/A

Page 2: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5
Page 3: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

i

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Content Chapter Title Page

Executive Summary iv

1. Introduction 1 1.1 Background________________________________________________________________________ 1 1.2 Project Organization _________________________________________________________________ 1 1.3 Environmental Status in the reporting period ______________________________________________ 1 1.4 Summary of EM&A Requirements ______________________________________________________ 1 1.5 Recommended Mitigation Measures_____________________________________________________ 2

2. Summary of Monitoring Results 4 2.1 Air Quality Monitoring ________________________________________________________________ 4 2.2 Construction Noise Monitoring _________________________________________________________ 4 2.3 Water Quality Monitoring______________________________________________________________ 4 2.4 Ecological Monitoring ________________________________________________________________ 4 2.5 Landscape and Visual Monitoring_______________________________________________________ 5

3. Environmental Site Inspection and Audit 8 3.1 Site Inspection _____________________________________________________________________ 8 3.2 Solid and Liquid Waste Management Status ______________________________________________ 8

4. Report on Non-compliance and Complaints 9 4.1 Record on Non-compliance of Action and Limit Levels_______________________________________ 9 4.2 Record on Environmental Complaints received ___________________________________________ 11 4.3 Follow-up actions taken _____________________________________________________________ 11

5. Future Key Issues 12 5.1 Construction Works for the Coming Months ______________________________________________ 12 5.2 Key Issues for the Coming Months _____________________________________________________ 12 5.3 Conclusions and Recommendations____________________________________________________ 12

Tables

Table 1.1: Summary of Impact EM&A Requirements_________________________________________________ 2 Table 2.1: Construction Audit Summary on Landscape and Visual ______________________________________ 5 Table 4.1: Comparison of monitoring data of Suspended Solids ________________________________________ 9 Table 4.2: Summary of exceedance investigations _________________________________________________ 10

List of Figures

Figure 1.1 General Site Layout and Locations of Monitoring Stations

Figure 2.1 Survey Area and Transect Walked

Page 4: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

ii

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

List of Appendices

Appendix A Project Organization Chart

Appendix B Tentative Construction Programme

Appendix C Action and Limit Levels for Construction Phase

Appendix D Graphical plots of the monitoring results

Appendix E Summary of Ecological Monitoring results

Appendix F Environmental Mitigation Measures - Implementation Status

Page 5: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

iii

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Executive Summary

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co. Ltd.

to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit

(EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development

at Wo Shang Wai, Yuen Long.

This is the 3rd

Quarterly EM&A Summary report and this report summarises the findings on EM&A during

the period from 1 November 2010 to 31 January 2011.

On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference

to the EP Condition 3.3 to 3.5. In accordance with EP Condition 3.6, the evidence of completion has been

certified by the ET Leader and verified by the IEC before submitting to the Director of Environmental

Protection (the Director).

Exceedance of Action and Limit Levels

The Action levels of Air Quality (1-hr TSP) were exceeded on 7 Dec 2010 at the four monitoring stations

(ASR1, ASR2A, ASR3, ASR4). The summary of exceedance is provided in Section 2.1. Investigations on

the exceedance showed that the unfavourable wind direction on the date of exceedance may have carried

pollutants from Shenzhen and caused short term deterioration of air quality in the project area. The

exceedance was not considered to be related to the project.

There was no breach of Action or Limit levels for Noise (as Leq) in the reporting month.

Action and Limit Level exceedances of pH, DO, turbidity and SS were recorded at water quality monitoring

stations. The summary of measured water quality is presented in Section 2.3. Investigations on the

exceedance showed that the exceedances were not related to the Project and may have been due to

external factors including natural variations and other unknown factors such as pond fish culture activities

and high fish activities in the ditch.

Implementation of mitigation measures

Site audits were carried out on a weekly basis during the monitoring period to confirm the implementation

of environmental mitigation measures undertaken by the Contractor in the reporting period. The status of

implementation of mitigation measures in the site is shown in Appendix F.

Record of Complaints

There was no record of complaints received in the reporting period.

Future Key Issues

The major site works to be commissioned in the coming three months include installation of band drain, trial

embankment for ground improvement and site formation (filling). Potential environmental impacts due to

the construction activities, including air quality, noise, water quality, ecology and landscape and visual, will

be monitored.

Page 6: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

iv

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Environmental mitigation measures will be implemented on site as recommended and weekly site audits

will be carried out to ensure that the environmental conditions are acceptable.

Page 7: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

1

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

1.1 Background

In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site in

Yuen Long at Wo Shang Wai. An Environmental Impact Assessment (EIA) was carried out under the EIA

Ordinance (EIAO) since then and the Environmental Permit (EP-311/2008B) for construction of the

comprehensive development in Wo Shang Wai was granted by EPD on 29 July 2010. The Project involves

the residential development and associated infrastructure and wetland restoration area and linear

landscape area. The construction works under the Environmental Permit commenced on 12 May 2010.

Heng Shung Construction Co. Ltd. was commissioned as the Contractor for the Project. Mott MacDonald

Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co. Ltd. to undertake the

Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-

construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai,

Yuen Long.

This report summarises the findings during the period from 1 November 2010 to 31 January 2011.

1.2 Project Organization

The organisation chart and lines of communication with respect to the on-site environmental management

structure together with the contact information of the key personnel are shown in Appendix A.

1.3 Environmental Status in the reporting period

During the reporting period, construction works of the Project undertaken include:

� Site formation for Wetland Restoration Area (WRA) (up to 15 November 2011);

� Band drain installation;

� Trial embankment for ground improvement; and

� Site formation (filling)

The Construction Works Programme of the Project is provided in Appendix B. The general layout plan of

the Project site is shown in Figure 1.1.

On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference

to the EP Condition 3.3 to 3.5. In accordance with EP Condition 3.6, the evidence of completion has been

certified by the ET Leader and verified by the IEC before submitting to the Director of Environmental

Protection (the Director).

1.4 Summary of EM&A Requirements

The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and

landscape and visual as specified in the approved EM&A Manual.

A summary of impact EM&A requirements is presented in Table 1.1 below:

1. Introduction

Page 8: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

2

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Table 1.1: Summary of Impact EM&A Requirements

Parameters Descriptions Locations Frequencies

24-Hour TSP ASR1, ASR2A, ASR3, ASR4 Once every 6 days Air Quality

1-Hour TSP ASR1, ASR2A, ASR3, ASR4 3 times every 6 days

Noise Leq, 30min NSR1, NSR3, NSR5, NSR7 Weekly

Water Quality

Dissolved Oxygen (DO), temperature, pH, suspended solids

(SS) and Biological Oxygen Demand (BOD)

MP1 to MP6 3 days per week

Birds Within the Project Area and Assessment Area of 500m

Weekly

Dragonflies and Butterflies Within the Project Area and Assessment Area of 500m

Once per month during Mar and Sep to November, and

twice per month during Apr to Aug

Herpetofauna Within the Project Area and Assessment Area of 500m

Once per month during Apr to Nov

Water quality of WRA Wetland Restoration Area

After filling of WRA with water, monthly for in situ water quality and every size months (end of

wet season and end of dry season) for laboratory testing

Ecology

Site Inspections Within the Project Area and Assessment Area of 500m

Weekly

Landscape and Visual

Auditing of protection of existing trees, the transplanting of existing

trees, the creation of new wetland, the planting of new trees and shrubs

and other landscape and visual mitigation measures

CM1 to CM10 and OM1 to OM7 within the Project Area

Site inspections once every two weeks during construction phase; once every two months

during operational phase

The Environmental Quality Performance Limits for air quality, noise and water quality are shown in

Appendix C.

1.5 Recommended Mitigation Measures

The EM&A programme followed the recommended mitigation measures in the EM&A manual. The EM&A

requirements as well as the summary of implementation status of the environmental mitigation measures

are provided in Appendix F. In particular, the following mitigation measures were brought to attention

during the site audits during the reporting period:

Air Quality

• All stockpiles should be covered by tarpaulin or kept wet by water spraying;

• All vehicles should be washed to remove any dusty materials before leaving the construction sites;

• the portion of road leading the construction site that is within 30m of a designated vehicle entrance

or exit should be kept clear of dusty materials;

• Sufficient water spraying should be provided at haul road to reduce dust emission; and

• Ensure proper functioning of the wheel wash facility.

Page 9: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

3

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Noise

• Mobile plant should be sited as far away from NSRs as possible;

• Plant known to emit noise strongly in one direction should be orientated to direct noise away from

the NSRs; and

• The construction activities should be better scheduled to reduce noise nuisance.

Water Quality

• Water accumulated in the site (including water inside drip trays) should be cleared frequently;

• Ensure proper functioning of the wastewater treatment facility;

• Silt and debris should be removed from the temporary drainage channel regularly; and

• Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be

filled with suitable materials.

Waste management

• Reuse the excavated materials as far as practical to reduce the amount of waste disposal;

• Ensure drip trays are provided for chemical containers to prevent leakage or soil contamination;

• All plants and vehicles should be properly maintained to prevent oil leakage;

• Oil stains on soil should be cleared by disposal of contaminated soil; and

Page 10: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

4

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

2.1 Air Quality Monitoring

Results and graphical plots of 1-hour TSP and 24-hr TSP at the four monitoring locations are summarised

in are shown in Appendix D. The Action levels of 1-hr TSP were exceeded for all the monitoring events on

7 December 2010 at the 4 air quality monitoring stations.

The weather conditions in the reporting period were generally fine and sunny with relatively lower humidity

and occasional strong wind. For details of wind speed and direction during the monitoring period, please

refer to the Monthly EM&A reports.

2.2 Construction Noise Monitoring

The construction noise monitoring results and graphical plots are shown in Appendix D. No exceedance

(Action/Limit Level) of construction noise was recorded in the reporting period.

2.3 Water Quality Monitoring

The water quality monitoring results and the graphical plots of the monitoring data are shown in Appendix

D.

Exceedances of pH, DO, turbidity and SS were observed. For MP1 to MP3, there were frequent

exceedances of action and limit levels for pH. There were a few occasions of exceedance of action and

limit levels of SS and turbidity at MP2 while two exceedances of limit levels of DO were found at MP3 in

December 2010. On the other hand, exceedances of pH were observed at MP4 to MP6 representing the

ditch at the north of the site from early December 2010 onward. For MP5, there was one occasion of

exceedance of action level of turbidity on 24 November 2010.

2.4 Ecological Monitoring

2.4.1 Monitoring of Birds

Monitoring was undertaken following the survey methodology in the EM&A Manual. The Wetland

Restoration Area (hereafter WRA) was also surveyed during the reporting period as the area became

accessible and site formation works for WRA has been completed. Low intensity monitoring of the WRA

was undertaken (on a monthly basis) to monitor faunal usage of the newly formed cells; monitoring

intensity will follow that outlined in the EM&A Manual at the completion of the WRA. A transect was

followed in the bird surveys (see Figure 2.1).

All bird species of conservation importance and/or wetland dependent were identified and enumerated.

Flying birds were not recorded unless they were foraging and associated with the habitat (such as swifts).

Further, notable bird observations during other surveys were also recorded. A summary of survey data is

provided in Appendix E.

A total of 42, 52 and 39 bird species (30, 34 and 21 in WRA) were recorded in the survey area in

November, December 2010 and January 2011 respectively. Among the birds surveyed in the WRA, 17, 27

2. Summary of Monitoring Results

Page 11: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

5

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

and 18 bird species of conservation importance and/or wetland-dependence were recorded in November,

December 2010 and January 2011 respectively.

In January 2011, species prone to disturbance were also recorded regularly on-site; these include three

duck species and five ardeid species. It is also of note that high numbers of ardeids (comprising mainly

Little Egret and one Black-faced Spoonbill) were recorded roosting in one of the adjacent fish ponds (Pond

52), indicating that disturbance from the construction site was not an issue.

Species and numbers recorded in this survey period are typical of fish pond area during the winter months

indicating that birds in the area are not presently being adversely affected by the construction of the

Wetland Restoration Area.

2.4.2 Monitoring of Herpetofauna

One day-time herpetofauna survey was conducted in November 2010. No amphibian species or reptile

species were recorded in the survey period.

One Red-eared Slider Trachemys scripta was found in the ponds within the survey area during the bird

survey conducted on the 20 November. This species is widely disturbed in Hong Kong and is exotic to

Hong Kong.

A summary of the survey findings are provided in Appendix E.

2.4.3 Monitoring of Dragonfly and Butterfly

Monitoring of dragonflies and butterflies was conducted once in November 2010. A total of nine dragonfly

species and ten butterfly species were recorded, and eight dragonfly species and four butterfly species

were recorded in the WRA. All species recorded were common and widespread and recorded in low to very

low numbers.

No dragonfly and butterfly surveys were scheduled in the December 2010 and January 2011. A summary

of the survey findings are provided in Appendix E.

2.4.4 Monitoring of Mammal

Monitoring of mammal was conducted concurrently with other surveys. No mammals were recorded in the

survey period.

2.5 Landscape and Visual Monitoring

The audit was undertaken with references to the specific mitigation measures recommended in Section

10.2 of the EM&A Manual and the audit results are summarized as below:

Table 2.1: Construction Audit Summary on Landscape and Visual

Area of Works Items to be Monitored

Page 12: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

6

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Works Area The boundaries of the works area have been established on site in accordance

with the contract documents and approved plans (EP), and the limit of current

heavy construction activity is now confined to within the site hoardings (North

side of the site / access road) and the noise barriers (other sides of the site).

Minor works such as horticultural maintenance of the planting and transplanted

trees, and boundary fence repair was proceeding along the Royal Palms - Palm

Springs boundary.

No construction works were observed to have exceeded the site boundaries.

Moreover, no construction was carried out at the wetland restoration area after

15 November 2010.

Protection of all trees and woodland blocks to be retained

Trees to be retained within the site, located northeast boundary alongside

wetland restoration area, have been identified and protected by temporary

protective fencing.

Streams The works site is encircled by a berm to intercept surface water and prevent it

from washing off into any of the neighboring sites. Surface water is collected

within the site in a temporary drainage channel. Gravels beds and barriers have

been installed to filter site runoff, sedimentation tanks provided to enable

primary treatment before discharge to mains drains.

Clearance of existing vegetation

Site clearance was completed prior to the commencement of construction. A

bed of existing Phragmites reeds which have been retained within a fenced off

area at the centre of the site and some reed clumps have been reused in the

vegetation of the wetland restoration area.

Transplanting of trees

Tree transplanting has been completed, with the trees relocated to various

points within the planting strip along the southern boundary of the site, outside

the noise barrier. The trees continue to re-establish well.

Topsoil stripping Suitable pond bund and pond bottom material excavated and stockpiled from

the original site has now been re-used in the formation of the wetland areas.

Active dust suppression measures are still being adopted along internal site

access tracks.

New buildings No new permanent buildings have yet been constructed on site.

Boundaries Hoardings have been erected along most of the boundaries of the site.

Installation of new fence between the future residential sites and the constructed

wetland area is complete. Fence has been being painted green to match with

the surrounding vegetated environment.

Noise Barrier Noise barriers have been installed along the southern and western boundaries

of the site in accordance with the contract requirements.

The noise barrier design complies with the mitigation requirements, with upper 6

to 7m portion of the barrier being made from a translucent material with green

tinted (to match with the environment). Supporting GMS structure, likewise, has

been painted green.

Night-time lighting No night-time works were reported to have been carried out during the

monitoring period.

Page 13: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

7

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Landscape and wetland treatments

Continuous belt of screen planting along the southern and western boundaries

of the site has been completed. The formation, soiling and water control

structures for all cells of the wetland restoration area has been completed. Rain

water has partially filled some wetland cells. The clumps of Phragmites australis

reeds from the original site have been successively translocated to the edge of

the ponds in wetland restoration area.

No construction was carried out at the wetland restoration area after 15

November 2010.

Soiling The soiling for the advance planting strip has been completed. Some bricks

have been installed to create a stronger edge of planting bed and to prevent soil

erosion. The soil placement and grading for the wetland restoration area is

complete.

Plant supply The plant material used for the Advance Planting Strip along the southern and

western boundaries of the site are all common species and came from

commercial sources.

Details of the procurement of special plant material for the wetland areas are to

be provided in Spring 2011, when nursery supplies become available.

Planting The total number of trees that will reach a minimum of 10m in the advance

planting strip meet the contract requirements. The tree species are all from the

approved list. This planting should achieve the required screening effect.

Health condition of recently transplanted trees (Eucalyptus) should be monitored

closely and identified die-back trees may need to be replanted.

Overhanging trees from adjacent properties had been cut back to allow more

light to the shrubs within the Advance Planting Strip. The overhanging trees will

need to be pruned regularly if situation is allowed. Replacement or repairing

works should be carried for those shrubs of poor health.

Establishment Works

The advance planting, the compensatory planting and the transplanted trees

have not yet been hand over for maintenance, the planting works are under

supervision onsite to ensure that the requirements of the approved planting

proposal are met. The advance planting is currently being maintained by the

landscape sub-contractor.

Page 14: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

8

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

3.1 Site Inspection

The ET had carried out construction phase weekly site inspections on 3, 10, 19 and 26 November 2010; 1,

10, 15, 21 and 30 December 2010; and 5, 12, 19, 26 and 31 January 2011. All observations have been

recorded in the site inspection checklist and passed to the Contractor together with the appropriate

recommended mitigation measures where necessary.

3.2 Solid and Liquid Waste Management Status

The Contractor has been registered as a chemical waste producer for the Project. Construction and

demolition (C&D) material sorting was carried out on site. A sufficient number of receptacles were available

for general refuse collection.

As advised by the Contractor, 0 tonnes C&D material were generated on site and disposed off at Public Fill

Reception Facilities at Tuen Mun Area 38 during the period. No metals was generated and collected by

registered recycling collector. No paper cardboard packing and plastic were generated on site and

collected by registered recycling collector. No chemical waste was generated and collected by licensed

chemical waste collector. 22.3 tonnes of other types of wastes (e.g. general refuse) was generated on site

and disposed of at North East New Territories (NENT) Landfill.

The Contractor is advised to maintain on site waste sorting and recording system and maximize

reuse/recycling of C&D wastes.

3. Environmental Site Inspection and Audit

Page 15: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

9

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

4.1 Record on Non-compliance of Action and Limit Levels

4.1.1 Record of Non-compliance

The Action levels of 1-hr TSP were exceeded for all the monitoring events on 7 December 2010 at the 4 air

quality monitoring stations.

There is no breach of Action or Limit Levels for Noise monitoring in the reporting period.

Exceedances of Action and Limit Levels were recorded for Water Quality at MP1, MP2, MP3, MP4, MP5

and MP6 on different monitoring dates.

Exceedances of pH, DO, turbidity and SS were observed. For MP1 to MP3, there were frequent

exceedances of action and limit levels for pH. There were a few occasions of exceedance of action and

limit levels of SS and turbidity at MP2 while two exceedances of limit levels of DO were found at MP3 in

December 2010. On the other hand, exceedances of pH were observed at MP4 to MP6 representing the

ditch at the north of the site from early December 2010 onward. For MP5, there was one occasion of

exceedance of action level of turbidity on 24 November 2010.

4.1.2 Constructional Impacts on Water Quality

In order to determine the constructional impacts on water quality, the suspended solids level, which is a

good indicator of the quality of effluent from construction site, is selected for assessment. The average

value of suspended solids (SS) for water quality monitoring stations (MP1 – MP6) during baseline

monitoring and construction phase monitoring for the reporting period are listed in Table 4.1 below.

Table 4.1: Comparison of monitoring data of Suspended Solids

Average levels of Suspended Solids (mg/L)

Monitoring Stations During Baseline Monitoring

During Construction Phase Monitoring for the reporting period

Within 130% of mean value of Baseline data?

MP1 103.5 45.9 Yes

MP2 60.1 53.5 Yes

MP3 49.5 20.5 Yes

MP4 36.9 24.1 Yes

MP5 47.7 28.8 Yes

MP6 54.1 29.3 Yes

The average levels of suspended solids during the reporting period were within 130% of the baseline

values. Although there were exceedances of water quality parameters, the above statistics show that the

water quality during the reporting period has not significantly worsen when compared with the baseline

condition.

It was noted that during the reporting period, all the water quality parameters monitored have been

influenced by the natural environment and other external factors and exceedances of criteria were resulted.

The exceedances have been investigated and are described in below section.

4. Report on Non-compliance and Complaints

Page 16: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

10

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

4.1.3 Exceedance Investigations

Air Quality

From investigation, the Contractor implemented air quality mitigation measures as recommended in EIA

report which include paving the vehicle washing area and site entrance, and keeping clear of the portion of

road leading the construction site from dusty materials, limiting vehicle speed to below 10 kph except on

completed access roads, and washing every vehicle to remove any dusty materials from its body and

wheels before leaving the construction sites. During the dry season, the Contractor has also made use of

the excavated fish pond clay to mix with the other imported soil materials to form the top layer of the works

area. The mixed soil layer was able to maintain higher moisture content and it generated less fugitive dust

from observations of the site inspection. In addition, water spraying has been provided by the Contractor at

various locations in the site on 7 Dec 2010 from photo record, including works area and haul road, to

further suppress dust.

The possible causes of exceedances have been investigated and reported to the IEC during construction

phase monitoring. From the record of the Hong Kong Observatory, there was moderate to strong wind on 7

Dec 2010. The prevailing wind direction became north to northeast starting from 6 Dec 2010 and the

direction was unchanged at the time of monitoring. Due to the close proximity of the site to the border with

mainland China and the unfavourable wind direction, it was believed that the wind blowing from north has

carried suspended particulates from Shenzhen and caused a short term deterioration of air quality. Record

of 24-hr TSP on 7 Dec 2010 showed that the average daily dust level remained at normal level (the 24-hr

TSP ranged from 79 to 93 µg/m3 for the 4 stations).

Consider the mitigation measures undertaken and the adverse wind condition, the exceedances were

considered not due to construction works.

Water Quality

From investigation, the Contractor has implemented water quality mitigation measures as recommended in

the EIA report, including the provision of temporary drainage facility and associated treatment facility. Sand

bags are in place in the temporary drainage channel to enhance the desilting efficiency. The Contractor

further enhanced the water quality mitigation measures by erecting several segments of rock bunds at the

discharge outlet to avoid site runoff draining directly to the northern ditches.

The possible causes of exceedances have been investigated and reported to the IEC during construction

phase monitoring. The exceedance investigations have also been included in the monthly EM&A report and

some of them are extracted and summarised in Table 4.1. The causes of some of the exceedances were

unknown but all of them were considered not related to the project. For detail, please refer to the previous

monthly EM&A reports.

Table 4.2: Summary of exceedance investigations

Descriptions of exceedances

Possible causes Exceedance related to project?

Exceedance of pH at MP1, MP2

The exceedance may have been caused by natural variations or other unknown factors.

No, as there was no direct discharge from the site to the ditch where MP1 and MP2 are located.

Exceedance of turbidity and SS on 6 and 15 Dec 2010 and turbidity on 22

The exceedance may have been caused by natural variations or other unknown factors such as high fish activities.

Ditto.

Page 17: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

11

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Descriptions of exceedances

Possible causes Exceedance related to project?

Dec 2010 at MP2

Exceedances of pH and DO at MP3 in Dec 2010

The exceedance maybe due to natural variation or other unknown factors such as pond fish culture activities.

No, noting that the fish pond (MP3) was being separated from the construction site by the WRA since November 2010.

Exceedance pH at MP4, MP5 and MP6

The exceedance may have been caused by natural variations or other unknown factors.

No, as there was also only small amount of site runoff generated and discharged in the dry season and considered the similar or lower pH compared with other monitoring stations.

Exceedance of turbidity at MP5 on 24 Nov 2010

The increase in turbidity at MP5 was due to some unknown factors.

No, since SS was not exceeded.

Conclusively, all of the exceedances were caused by external factors including natural variation and other

unknown factors such as pond fish culture activities. Moreover, as noted by monitoring team during on-site

sampling, no direct muddy water discharge was observed from the site. The exceedances were considered

not due to construction works.

4.2 Record on Environmental Complaints received

No environmental complaint was received this month.

4.3 Follow-up actions taken

Although it is considered that the exceedances were not related to the Project, the Contractor was

reminded to implement the air and water quality mitigation measures in accordance with the

recommendation stated in Section 3.6.1 and 5.6.1 – 5.6.4 of the EIA Report respectively as far as

practicable and regular spot check would be conducted on the nearby discharge by Contractor and inform

ET for investigation.

During the dry season, the Contractor has made use of the excavated fish pond clay to mix with the other

imported soil materials to form the top layer of the works area. The mixed soil layer was able to maintain

higher moisture content and it generated less fugitive dust from observations of the site inspection.

To cater for the site runoff in the previous months, the Contractor has further enhanced the water quality

mitigation measures by erecting several segments of rock bunds at the discharge outlet to avoid site runoff

draining directly to the northern ditches.

It was also advised that the operation condition of the Wastewater Treatment Facilities should be checked

regularly to ensure proper functioning of the plant and good quality of effluent discharge.

Page 18: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

12

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

5.1 Construction Works for the Coming Months

The major site works to be commissioned in the coming three months include:

� Installation of band drain;

� Trial embankment for ground improvement; and

� Site formation (Filling)

5.2 Key Issues for the Coming Months

Key issues to be considered in the coming three months include:

� Generation of dust from activities on-site (esp. stockpiling for Trial Embankment);

� Noise impact from operating equipment and machinery on-site;

� Generation of site surface runoffs and wastewater from activities on-site;

� Sorting, recycling, storage and disposal of general refuse and construction waste from activities on-

site; and

� Management of chemicals and avoidance of oil spillage on-site.

5.3 Conclusions and Recommendations

5.3.1 Conclusions

The EM&A programme as recommended in the EM&A manual has been undertaken in the reporting

period.

Monitoring of Air Quality, Noise, Water Quality, Ecology and Landscape and Visual impacts due to the

Project was under way. In particular, the 1-hr TSP, 24-hr TSP, noise level (as Leq) and water quality

parameters (such as pH, DO and SS) under monitoring have been checked against established Action and

Limit levels.

The Action levels of Air Quality (1-hr TSP) were exceeded on 7 Dec 2010 at the four monitoring stations.

Investigations on the exceedance showed that the unfavourable wind direction on the date of exceedance

may have carried pollutants from Shenzhen and caused short term deterioration of air quality in the project

area. The exceedance was not considered to be related to the project.

There was no breach of Action or Limit levels for Noise (as Leq) in the reporting month.

Action and Limit Level exceedances of pH, DO, turbidity and SS were recorded at water quality monitoring

stations. However, Investigations on the exceedance showed that the exceedances were not related to the

Project and may have been due to external factors including natural variations and other unknown factors

such as pond fish culture activities and high fish activities in the ditch.

5. Future Key Issues

Page 19: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

13

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

5.3.2 Recommendations

With considerations on the construction activities and environment, the following recommendations were

provided:

Air Quality

• All stockpiles should be covered by tarpaulin or kept wet by water spraying;

• All vehicles should be washed to remove any dusty materials before leaving the construction sites;

• the portion of road leading the construction site that is within 30m of a designated vehicle entrance or exit

should be kept clear of dusty materials;

• Sufficient water spraying should be provided at haul road to reduce dust emission; and

• Ensure proper functioning of the wheel wash facility.

Noise

• Mobile plant should be sited as far away from NSRs as possible;

• Plant known to emit noise strongly in one direction should be orientated to direct noise away from the NSRs;

and

• The construction activities should be better scheduled to reduce noise nuisance.

Water Quality

• Water accumulated in the site (including water inside drip trays) should be cleared frequently;

• Ensure proper functioning of the wastewater treatment facility; and

• Silt and debris should be removed from the temporary drainage channel regularly.

Waste management

• Reuse the excavated materials as far as practical to reduce the amount of waste disposal;

• Ensure drip trays are provided for chemical containers to prevent leakage or soil contamination;

• All plants and vehicles should be properly maintained to prevent oil leakage; and

• Oil stains on soil should be cleared by disposal of contaminated soil.

Page 20: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5
Page 21: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Legends:

Air Quality Monitoring

Stations

Noise Monitoring Stations

Water Quality Monitoring

Stations

Site Boundary

HENG SHUNG CONSTRUCTION CO. LTD

PROPOSED COMPREHENSIVE DEVELOPMENT

AT WO SHANG WAI, YUEN LONG

General Site Layout and

Locations of Monitoring

Stations

Figure 1.1

NSR1 (Construction Phase)

NSR3

NSR5 NSR7

NSR1 ASR1

ASR4

ASR3

ASR2A

Page 22: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Figure 2.1

Page 23: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Contact information:

Company Position Name Telephone / Mobile

Profit Point Enterprises

Limited

Project Manager Mr Kelvin Lau 2908 8114

Heng Shung Construction

Co. Ltd. (The Contractor)

Assistant Construction Manager Ms Lynne Hung 2908 2391

Heng Shung Construction

Co. Ltd. (The Contractor)

Site Agent Mr Poon Man Ho 9426 3533

Heng Shung Construction

Co. Ltd. (The Contractor)

Environmental Officer Mr. Lun Ho Yin 9866 7497

ENVIRON Hong Kong Ltd

(IEC)

Independent Environmental

Checker

Mr David Yeung 3743 0788

Mott MacDonald Hong Kong

Ltd. (ET)

ET Team Leader Ms Florence Yuen 2828 5768

Appendix A. Project Organization Chart

Line of Reporting

Line of Communication

Project Proponent

Profit Point Enterprises Limited

The Contractor

Heng Shung Construction Co. Ltd.

ET Leader

Mott MacDonald Hong Kong Limited

IEC

ENVIRON Hong Kong Limited

Environmental Protection Department

Page 24: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Page 25: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Appendix B. Tentative Construction Programme

Page 26: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

ID Task Name Working Start Finish

0 Wo Shang Wai Construction Phase 1205days

Tue 01/06/10 Fri 30/05/14

1

2 Install Band Drain 317 days Tue 01/06/10 Thu 30/06/11

3 Trial Embankment 300 days Thu 17/06/10 Sat 25/06/11

4 Site Formation 1029 days Mon 03/01/11 Fri 30/05/14

5 Filling 899 days Mon 03/01/11 Mon 30/12/13

6 Excavations for construction of footing 833 days Mon 05/09/11 Fri 30/05/14

Install Band Drain

Trial Embankment

Filling

Excavations for construction of footing

Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q22011 2012 2013 20

Task Milestone Summary

Wo Shang Wai Construction Works Programme

Page 1

Project : Wo Shang WaiRevision : EPrint Date : Mon 14/02/11

Page 27: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Air Quality

Action and Limit Levels for 24-hour TSP

Monitoring Station Action Level (µµµµg/m3) Limit Level (µµµµg/m3)

ASR1 226 260

ASR2A 213 260

ASR3 205 260

ASR4 237 260

Action and Limit Levels for 1-hour TSP

Monitoring Station Action Level (µµµµg/m3) Limit Level (µµµµg/m3)

ASR1 378 500

ASR2A 357 500

ASR3 358 500

ASR4 372 500

Noise

Action and Limit Levels for Construction Noise

Time Period Action Level Limit Level

NSR1, NSR3, NSR5, NSR7

0700 – 1900 hours on normal weekdays

When one documented complaint is received from any one of the sensitive receivers

75 dB(A)

Water Quality

Action and Limit Levels for Water Quality

Parameters DO in mg/L Turbidity in NTU SS in mg/L pH

Action Level

Limit Level

Action Level

Action Level

Action Level

Limit Level

Action Level

Limit Level

MP1 1.23 1.17 173 177 231 299

MP2 1.04 0.89 132 163 170 209

MP3 6.85 6.65 64 67 65 66

MP4 3.91 3.82 60 64 50 53

MP5 4.13 3.87 81 84 66 69

MP6 4.61 4.52 94 96 75 75

< 5.5 or > 7.5

< 4.0 or > 8.0

Appendix C. Action and Limit Levels for Construction Phase

Page 28: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Page 29: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Appendix D. Summary and Graphical plots of the monitoring results

Page 30: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Page 31: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 1 of 28

Air Quality (1-hr TSP)

Station ASR1

Start Finish TSP

Concentration Weather Action Level Limit Level

Date Time Time (µg/m3) Condition (µg/m

3) (µg/m

3)

3-Nov-10 8:52 9:52 320 Sunny 378 500 3-Nov-10 9:52 10:52 305 Sunny 378 500

3-Nov-10 10:52 11:52 288 Sunny 378 500

9-Nov-10 9:12 10:12 180 Sunny 378 500

9-Nov-10 10:12 11:12 183 Sunny 378 500

9-Nov-10 11:12 12:12 182 Sunny 378 500

15-Nov-10 9:06 10:06 224 Sunny 378 500

15-Nov-10 10:06 11:06 204 Sunny 378 500

15-Nov-10 11:06 12:06 219 Sunny 378 500

19-Nov-10 9:11 10:11 269 Sunny 378 500

19-Nov-10 10:11 11:11 258 Sunny 378 500

19-Nov-10 11:11 12:11 268 Sunny 378 500

25-Nov-10 9:13 10:13 210 Sunny 378 500

25-Nov-10 10:13 11:13 215 Sunny 378 500

25-Nov-10 11:13 12:13 199 Sunny 378 500

1-Dec-10 9:06 10:06 197 Sunny 378 500

1-Dec-10 10:06 11:06 211 Sunny 378 500

1-Dec-10 11:06 12:06 235 Sunny 378 500

7-Dec-10 9:04 10:04 454 Sunny 378 500

7-Dec-10 10:04 11:04 422 Sunny 378 500

7-Dec-10 11:04 12:04 456 Sunny 378 500

13-Dec-10 9:17 10:17 115 Fine 378 500

13-Dec-10 10:17 11:17 104 Fine 378 500

13-Dec-10 11:17 12:17 108 Fine 378 500

17-Dec-10 9:19 10:19 128 Sunny 378 500

17-Dec-10 10:19 11:19 120 Sunny 378 500

17-Dec-10 11:19 12:19 121 Sunny 378 500

23-Dec-10 9:11 10:11 248 Sunny 378 500

23-Dec-10 10:11 11:11 325 Sunny 378 500

23-Dec-10 11:11 12:11 318 Sunny 378 500

29-Dec-10 9:14 10:14 166 Sunny 378 500

29-Dec-10 10:14 11:14 158 Sunny 378 500

29-Dec-10 11:14 12:14 150 Sunny 378 500

4-Jan-11 9:14 10:14 190 Cloudy 378 500

4-Jan-11 10:14 11:14 182 Cloudy 378 500

4-Jan-11 11:14 12:14 177 Cloudy 378 500

10-Jan-11 9:03 10:03 315 Sunny 378 500

10-Jan-11 10:03 11:03 327 Sunny 378 500

10-Jan-11 11:03 12:03 313 Sunny 378 500

14-Jan-11 9:13 10:13 359 Sunny 378 500

14-Jan-11 10:13 11:13 344 Sunny 378 500

14-Jan-11 11:13 12:13 356 Sunny 378 500

20-Jan-11 9:12 10:12 332 Sunny 378 500

20-Jan-11 10:12 11:12 345 Sunny 378 500

20-Jan-11 11:12 12:12 337 Sunny 378 500

26-Jan-11 9:06 10:06 283 Sunny 378 500

26-Jan-11 10:06 11:06 264 Sunny 378 500

26-Jan-11 11:06 12:06 266 Sunny 378 500

Min. 41 Max. 327

Average 116

Values Bold indicate Action Level exceedance.

Page 32: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 2 of 28

Air Quality (1-hr TSP)

Station ASR2A

Start Finish TSP

Concentration Weather Action Level Limit Level

Date Time Time (µg/m3) Condition (µg/m

3) (µg/m

3)

3-Nov-10 13:24 14:24 188 Sunny 378 500 3-Nov-10 14:24 15:24 194 Sunny 378 500

3-Nov-10 15:24 16:24 181 Sunny 378 500

9-Nov-10 13:32 14:32 133 Sunny 378 500

9-Nov-10 14:32 15:32 137 Sunny 378 500

9-Nov-10 15:32 16:32 126 Sunny 378 500

15-Nov-10 13:20 14:20 155 Sunny 378 500

15-Nov-10 14:20 15:20 147 Sunny 378 500

15-Nov-10 15:20 16:20 144 Sunny 378 500

19-Nov-10 13:27 14:27 206 Sunny 378 500

19-Nov-10 14:27 15:27 202 Sunny 378 500

19-Nov-10 15:27 16:27 211 Sunny 378 500

25-Nov-10 13:30 14:30 154 Sunny 378 500

25-Nov-10 14:30 15:30 151 Sunny 378 500

25-Nov-10 15:30 16:30 146 Sunny 378 500

1-Dec-10 13:19 14:19 159 Sunny 378 500

1-Dec-10 14:19 15:19 165 Sunny 378 500

1-Dec-10 15:19 16:19 169 Sunny 378 500

7-Dec-10 13:10 14:10 376 Sunny 378 500

7-Dec-10 14:10 15:10 391 Sunny 378 500

7-Dec-10 15:10 16:10 405 Sunny 378 500

13-Dec-10 13:26 14:26 79 Fine 378 500

13-Dec-10 14:26 15:26 86 Fine 378 500

13-Dec-10 15:26 16:26 83 Fine 378 500

17-Dec-10 13:25 14:25 105 Sunny 378 500

17-Dec-10 14:25 15:25 112 Sunny 378 500

17-Dec-10 15:25 16:25 117 Sunny 378 500

23-Dec-10 13:25 14:25 252 Sunny 378 500

23-Dec-10 14:25 15:25 241 Sunny 378 500

23-Dec-10 15:25 16:25 227 Sunny 378 500

29-Dec-10 13:19 14:19 67 Sunny 378 500

29-Dec-10 14:19 15:19 84 Sunny 378 500

29-Dec-10 15:19 16:19 97 Sunny 378 500

4-Jan-11 13:05 14:05 174 Cloudy 357 500

4-Jan-11 14:05 15:05 162 Cloudy 357 500

4-Jan-11 15:05 16:05 158 Cloudy 357 500

10-Jan-11 13:10 14:10 275 Sunny 357 500

10-Jan-11 14:10 15:10 287 Sunny 357 500

10-Jan-11 15:10 16:10 299 Sunny 357 500

14-Jan-11 13:22 14:22 307 Sunny 357 500

14-Jan-11 14:22 15:22 315 Sunny 357 500

14-Jan-11 15:22 16:22 319 Sunny 357 500

20-Jan-11 13:13 14:13 297 Sunny 357 500

20-Jan-11 14:13 15:13 301 Sunny 357 500

20-Jan-11 15:13 16:13 313 Sunny 357 500

26-Jan-11 13:17 14:17 261 Sunny 357 500

26-Jan-11 14:17 15:17 245 Sunny 357 500

26-Jan-11 15:17 16:17 242 Sunny 357 500

Min. 67 Max. 405

Average 201

Values Bold indicate Action Level exceedance.

Page 33: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 3 of 28

Air Quality (1-hr TSP)

Station ASR3

Start Finish TSP

Concentration Weather Action Level Limit Level

Date Time Time (µg/m3) Condition (µg/m

3) (µg/m

3)

3-Nov-10 13:08 14:08 225 Sunny 358 500 3-Nov-10 14:08 15:08 198 Sunny 358 500

3-Nov-10 15:08 16:08 208 Sunny 358 500

9-Nov-10 13:17 14:17 128 Sunny 358 500

9-Nov-10 14:17 15:17 150 Sunny 358 500

9-Nov-10 15:17 16:17 139 Sunny 358 500

15-Nov-10 13:05 14:05 165 Sunny 358 500

15-Nov-10 14:05 15:05 175 Sunny 358 500

15-Nov-10 15:05 16:05 168 Sunny 358 500

19-Nov-10 13:13 14:13 238 Sunny 358 500

19-Nov-10 14:13 15:13 227 Sunny 358 500

19-Nov-10 15:13 16:13 221 Sunny 358 500

25-Nov-10 13:16 14:16 146 Sunny 358 500

25-Nov-10 14:16 15:16 132 Sunny 358 500

25-Nov-10 15:16 16:16 166 Sunny 358 500

1-Dec-10 13:05 14:05 181 Sunny 358 500

1-Dec-10 14:05 15:05 179 Sunny 358 500

1-Dec-10 15:05 16:05 175 Sunny 358 500

7-Dec-10 12:56 13:56 405 Sunny 358 500

7-Dec-10 13:56 14:56 403 Sunny 358 500

7-Dec-10 14:56 15:56 386 Sunny 358 500

13-Dec-10 13:10 14:10 84 Fine 358 500

13-Dec-10 14:10 15:10 85 Fine 358 500

13-Dec-10 15:10 16:10 90 Fine 358 500

17-Dec-10 13:11 14:11 117 Sunny 358 500

17-Dec-10 14:11 15:11 115 Sunny 358 500

17-Dec-10 15:11 16:11 110 Sunny 358 500

23-Dec-10 13:12 14:12 233 Sunny 358 500

23-Dec-10 14:12 15:12 241 Sunny 358 500

23-Dec-10 15:12 16:12 219 Sunny 358 500

29-Dec-10 13:03 14:03 90 Sunny 358 500

29-Dec-10 14:03 15:03 96 Sunny 358 500

29-Dec-10 15:03 16:03 104 Sunny 358 500

4-Jan-11 12:55 13:55 177 Cloudy 358 500

4-Jan-11 13:55 14:55 167 Cloudy 358 500

4-Jan-11 14:55 15:55 183 Cloudy 358 500

10-Jan-11 12:54 13:54 288 Sunny 358 500

10-Jan-11 13:54 14:54 298 Sunny 358 500

10-Jan-11 14:54 15:54 292 Sunny 358 500

14-Jan-11 13:03 14:03 315 Sunny 358 500

14-Jan-11 14:03 15:03 318 Sunny 358 500

14-Jan-11 15:03 16:03 327 Sunny 358 500

20-Jan-11 12:58 13:58 311 Sunny 358 500

20-Jan-11 13:58 14:58 313 Sunny 358 500

20-Jan-11 14:58 15:58 319 Sunny 358 500

26-Jan-11 13:02 14:02 262 Sunny 358 500

26-Jan-11 14:02 15:02 266 Sunny 358 500

26-Jan-11 15:02 16:02 270 Sunny 358 500

Min. 84 Max. 405

Average 211

Values Bold indicate Action Level exceedance.

Page 34: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 4 of 28

Air Quality (1-hr TSP)

Station ASR4

Start Finish TSP

Concentration Weather Action Level Limit Level

Date Time Time (µg/m3) Condition (µg/m

3) (µg/m

3)

3-Nov-10 8:58 9:58 277 Sunny 372 500 3-Nov-10 9:58 10:58 319 Sunny 372 500

3-Nov-10 10:58 11:58 299 Sunny 372 500

9-Nov-10 9:21 10:21 185 Sunny 372 500

9-Nov-10 10:21 11:21 174 Sunny 372 500

9-Nov-10 11:21 12:21 177 Sunny 372 500

15-Nov-10 9:21 10:21 248 Sunny 372 500

15-Nov-10 10:21 11:21 259 Sunny 372 500

15-Nov-10 11:21 12:21 242 Sunny 372 500

19-Nov-10 9:18 10:18 223 Sunny 372 500

19-Nov-10 10:18 11:18 222 Sunny 372 500

19-Nov-10 11:18 12:18 214 Sunny 372 500

25-Nov-10 9:18 10:18 190 Sunny 372 500

25-Nov-10 10:18 11:18 172 Sunny 372 500

25-Nov-10 11:18 12:18 169 Sunny 372 500

1-Dec-10 9:10 10:10 145 Sunny 372 500

1-Dec-10 10:10 11:10 155 Sunny 372 500

1-Dec-10 11:10 12:10 174 Sunny 372 500

7-Dec-10 9:10 10:10 413 Sunny 372 500

7-Dec-10 10:10 11:10 422 Sunny 372 500

7-Dec-10 11:10 12:10 417 Sunny 372 500

13-Dec-10 9:22 10:22 96 Fine 372 500

13-Dec-10 10:22 11:22 84 Fine 372 500

13-Dec-10 11:22 12:22 98 Fine 372 500

17-Dec-10 9:28 10:28 116 Sunny 372 500

17-Dec-10 10:28 11:28 110 Sunny 372 500

17-Dec-10 11:28 12:28 114 Sunny 372 500

23-Dec-10 9:16 10:16 305 Sunny 372 500

23-Dec-10 10:16 11:16 297 Sunny 372 500

23-Dec-10 11:16 12:16 290 Sunny 372 500

29-Dec-10 9:18 10:18 136 Sunny 372 500

29-Dec-10 10:18 11:18 142 Sunny 372 500

29-Dec-10 11:18 12:18 105 Sunny 372 500

4-Jan-11 9:19 10:19 135 Cloudy 372 500

4-Jan-11 10:19 11:19 141 Cloudy 372 500

4-Jan-11 11:19 12:19 149 Cloudy 372 500

10-Jan-11 9:09 10:09 284 Sunny 372 500

10-Jan-11 10:09 11:09 302 Sunny 372 500

10-Jan-11 11:09 12:09 298 Sunny 372 500

14-Jan-11 9:21 10:21 348 Sunny 372 500

14-Jan-11 10:21 11:21 345 Sunny 372 500

14-Jan-11 11:21 12:21 351 Sunny 372 500

20-Jan-11 9:16 10:16 346 Sunny 372 500

20-Jan-11 10:16 11:16 337 Sunny 372 500

20-Jan-11 11:16 12:16 334 Sunny 372 500

26-Jan-11 9:10 10:10 245 Sunny 372 500

26-Jan-11 10:10 11:10 251 Sunny 372 500

26-Jan-11 11:10 12:10 242 Sunny 372 500

Min. 84 Max. 422

Average 231

Values Bold indicate Action Level exceedance.

Page 35: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 5 of 28

Air Quality (1-hr TSP)

Page 36: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 6 of 28

Air Quality (1-hr TSP)

Page 37: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 7 of 28

Air Quality (24-hr TSP)

Station ASR1

Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)

Date Time Date Time Initial Final Initial Final

Sampling Time (hrs) Initial Final Average

Conc. (µg/m

3)

Weather Condition

Action Level

Limit Level

3-Nov-10 9:42 4-Nov-10 9:42 2.8259 2.9767 10478.68 10502.68 24.00 1.2000 1.2000 1.2000 87 Sunny 226 260

9-Nov-10 9:54 10-Nov-10 9:54 2.7946 2.9414 10502.68 10526.68 24.00 1.2000 1.2000 1.2000 85 Sunny 226 260

15-Nov-10 9:49 16-Nov-10 9:49 2.8535 2.9975 10526.68 10550.68 24.00 1.2000 1.2000 1.2000 83 Sunny 226 260

19-Nov-10 9:19 20-Nov-10 9:19 2.8574 3.0114 10550.68 10574.68 24.00 1.2600 1.2600 1.2600 85 Sunny 226 260

25-Nov-10 9:57 26-Nov-10 9:57 2.8110 3.0411 10574.68 10598.68 24.00 1.2600 1.2600 1.2600 127 Sunny 226 260

1-Dec-10 9:50 2-Dec-10 9:50 2.8613 3.0226 10598.68 10622.68 24.00 1.2600 1.2600 1.2600 89 Sunny 226 260

7-Dec-10 9:53 8-Dec-10 9:53 2.8641 3.0277 10622.68 10646.68 24.00 1.2600 1.2600 1.2600 90 Sunny 226 260

13-Dec-10 10:03 14-Dec-10 10:03 2.8473 3.0017 10646.68 10670.68 24.00 1.2600 1.2600 1.2600 85 Sunny 226 260

17-Dec-10 9:27 18-Dec-10 9:27 2.8351 3.0077 10670.68 10694.68 24.00 1.2600 1.2600 1.2600 95 Sunny 226 260

23-Dec-10 9:56 24-Dec-10 9:56 2.8459 2.9967 10694.68 10718.68 24.00 1.2600 1.2600 1.2600 83 Sunny 226 260

29-Dec-10 9:59 30-Dec-10 9:59 2.8490 3.0067 10718.68 10742.68 24.00 1.2600 1.2600 1.2600 87 Sunny 226 260

4-Jan-11 9:59 5-Jan-11 9:59 2.8355 2.9969 10742.68 10766.68 24.00 1.2600 1.2600 1.2600 89 Cloudy 226 260

10-Jan-11 9:51 11-Jan-11 9:51 2.8709 3.0227 10766.68 10790.68 24.00 1.2400 1.2400 1.2400 85 Sunny 226 260

14-Jan-11 9:20 15-Jan-11 9:20 2.8055 2.9827 10790.68 10814.68 24.00 1.2400 1.2400 1.2400 99 Sunny 226 260

20-Jan-11 9:55 21-Jan-11 9:55 2.8701 3.0369 10814.68 10838.68 24.00 1.2400 1.2400 1.2400 93 Sunny 226 260

26-Jan-11 9:52 27-Jan-11 9:52 2.8114 2.9874 10838.68 10862.68 24.00 1.2400 1.2400 1.2400 99 Sunny 226 260

Min 83

Max 127

Average 91

Page 38: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 8 of 28

Air Quality (24-hr TSP)

Station ASR2A

Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)

Date Time Date Time Initial Final Initial Final

Sampling Time (hrs) Initial Final Average

Conc. (µg/m

3)

Weather Condition

Action Level

Limit Level

3-Nov-10 13:24 4-Nov-10 13:24 2.8449 2.9769 13918.45 13942.45 24.00 1.2500 1.2500 1.2500 73 Sunny 213 260

9-Nov-10 13:32 10-Nov-10 13:32 2.8325 2.9709 13942.45 13966.45 24.00 1.2500 1.2500 1.2500 77 Sunny 213 260

15-Nov-10 13:20 16-Nov-10 13:20 2.8669 2.9981 13966.45 13990.45 24.00 1.2500 1.2500 1.2500 73 Sunny 213 260

19-Nov-10 13:26 20-Nov-10 13:26 2.8844 3.0014 13990.45 14014.45 24.00 1.2500 1.2500 1.2500 65 Sunny 213 260

25-Nov-10 13:30 26-Nov-10 13:30 2.8614 3.0119 14014.45 14038.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260

1-Dec-10 13:19 2-Dec-10 13:19 2.8411 3.0097 14038.45 14062.45 24.00 1.2500 1.2500 1.2500 94 Sunny 213 260

7-Dec-10 13:19 8-Dec-10 13:19 2.8350 2.9968 14062.45 14086.45 24.00 1.2500 1.2500 1.2500 90 Sunny 213 260

13-Dec-10 13:26 14-Dec-10 13:26 2.8047 2.9566 14086.45 14110.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260

17-Dec-10 13:24 18-Dec-10 13:24 2.8570 3.0117 14110.45 14134.45 24.00 1.2500 1.2500 1.2500 86 Sunny 213 260

23-Dec-10 13:25 24-Dec-10 13:25 2.8903 3.0511 14134.45 14158.45 24.00 1.2500 1.2500 1.2500 89 Sunny 213 260

29-Dec-10 13:19 30-Dec-10 13:19 2.8460 2.9967 14158.45 14182.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260

4-Jan-11 13:05 5-Jan-11 13:05 2.8490 3.0152 14182.45 14206.45 24.00 1.2500 1.2500 1.2500 92 Cloudy 213 260

10-Jan-11 13:10 11-Jan-11 13:10 2.8473 3.0071 14206.45 14230.45 24.00 1.2800 1.2800 1.2800 87 Sunny 213 260

14-Jan-11 13:21 15-Jan-11 13:21 2.8409 3.0121 14230.45 14254.45 24.00 1.2800 1.2800 1.2800 93 Sunny 213 260

20-Jan-11 13:13 21-Jan-11 13:13 2.8339 2.9925 14254.45 14278.45 24.00 1.2800 1.2800 1.2800 86 Sunny 213 260

26-Jan-11 13:16 27-Jan-11 13:16 2.8527 3.0127 14278.45 14302.45 24.00 1.2400 1.2800 1.2400 90 Sunny 213 260

Min 65

Max 94

Average 84

Page 39: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 9 of 28

Air Quality (24-hr TSP)

Station ASR3

Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)

Date Time Date Time Initial Final Initial Final

Sampling Time (hrs) Initial Final Average

Conc. (µg/m

3)

Weather Condition

Action Level

Limit Level

3-Nov-10 13:08 4-Nov-10 13:08 2.8634 3.0061 4140.69 4164.69 24.00 1.2700 1.2700 1.2700 78 Sunny 205 260

9-Nov-10 13:17 10-Nov-10 13:17 2.7997 2.9333 4164.69 4188.69 24.00 1.2700 1.2700 1.2700 73 Sunny 205 260

15-Nov-10 13:05 16-Nov-10 13:05 2.8627 3.0112 4188.69 4212.69 24.00 1.2700 1.2700 1.2700 81 Sunny 205 260

19-Nov-10 13:12 20-Nov-10 13:12 2.8713 3.0047 4212.69 4236.69 24.00 1.2800 1.2800 1.2800 72 Sunny 205 260

25-Nov-10 13:15 26-Nov-10 13:15 2.8336 2.9828 4236.69 4260.69 24.00 1.2800 1.2800 1.2800 81 Sunny 205 260

1-Dec-10 13:04 2-Dec-10 13:04 2.8767 3.0319 4260.69 4284.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260

7-Dec-10 12:55 8-Dec-10 12:55 2.8746 3.0195 4284.69 4308.69 24.00 1.2800 1.2800 1.2800 79 Sunny 205 260

13-Dec-10 13:09 14-Dec-10 13:09 2.8996 3.0290 4308.69 4332.69 24.00 1.2800 1.2800 1.2800 70 Sunny 205 260

17-Dec-10 13:11 18-Dec-10 13:11 2.8814 3.0400 4332.69 4356.69 24.00 1.2800 1.2800 1.2800 86 Sunny 205 260

23-Dec-10 13:12 24-Dec-10 13:12 2.8667 3.0211 4356.69 4380.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260

29-Dec-10 13:02 30-Dec-10 13:02 2.8334 2.9886 4380.69 4404.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260

4-Jan-11 12:54 5-Jan-11 12:54 2.8521 3.0117 4404.69 4428.69 24.00 1.2800 1.2800 1.2800 87 Cloudy 205 260

10-Jan-11 12:54 11-Jan-11 12:54 2.8864 3.0396 4428.69 4452.69 24.00 1.2000 1.2000 1.2000 89 Sunny 205 260

14-Jan-11 13:03 15-Jan-11 13:03 2.8229 2.9960 4452.69 4476.69 24.00 1.2000 1.2000 1.2000 100 Sunny 205 260

20-Jan-11 12:57 21-Jan-11 12:57 2.8525 3.0072 4476.69 4500.69 24.00 1.2000 1.2000 1.2000 90 Sunny 205 260

26-Jan-11 13:01 27-Jan-11 13:01 2.8339 2.9966 4500.69 4524.69 24.00 1.2000 1.2000 1.2000 94 Sunny 205 260

Min 70

Max 100

Average 83

Page 40: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 10 of 28

Air Quality (24-hr TSP)

Station ASR4

Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)

Date Time Date Time Initial Final Initial Final

Sampling Time (hrs) Initial Final Average

Conc. (µg/m

3)

Weather Condition

Action Level

Limit Level

3-Nov-10 8:51 4-Nov-10 8:51 2.8371 2.9921 11339.86 11363.86 24.00 1.1500 1.1500 1.1500 94 Sunny 237 260

9-Nov-10 9:12 10-Nov-10 9:12 2.8063 2.9577 11363.86 11387.86 24.00 1.1500 1.1500 1.1500 91 Sunny 237 260

15-Nov-10 9:06 16-Nov-10 9:06 2.8808 3.0191 11387.86 11411.86 24.00 1.1500 1.1500 1.1500 84 Sunny 237 260

19-Nov-10 9:12 20-Nov-10 9:12 2.8309 2.9912 11411.86 11435.86 24.00 1.1800 1.1800 1.1800 94 Sunny 237 260

25-Nov-10 9:12 26-Nov-10 9:12 2.8624 3.0059 11435.86 11459.86 24.00 1.1800 1.1800 1.1800 84 Sunny 237 260

1-Dec-10 9:05 2-Dec-10 9:05 2.8234 2.9716 11459.86 11483.86 24.00 1.1800 1.1800 1.1800 87 Sunny 237 260

7-Dec-10 9:03 8-Dec-10 9:03 2.8914 3.0494 11483.86 11507.86 24.00 1.1800 1.1800 1.1800 93 Sunny 237 260

13-Dec-10 9:16 14-Dec-10 9:16 2.8671 3.0011 11507.86 11531.86 24.00 1.1800 1.1800 1.1800 79 Sunny 237 260

17-Dec-10 9:18 18-Dec-10 9:18 2.8214 2.9901 11531.86 11555.86 24.00 1.1800 1.1800 1.1800 99 Sunny 237 260

23-Dec-10 9:11 24-Dec-10 9:11 2.8735 3.0346 11555.86 11579.86 24.00 1.1800 1.1800 1.1800 95 Sunny 237 260

29-Dec-10 9:14 30-Dec-10 9:14 2.8751 3.0306 11579.86 11603.86 24.00 1.1800 1.1800 1.1800 92 Sunny 237 260

4-Jan-11 9:13 5-Jan-11 9:13 2.8241 2.9962 11603.86 11627.86 24.00 1.1800 1.1800 1.1800 101 Cloudy 237 260

10-Jan-11 9:03 11-Jan-11 9:03 2.8221 2.9759 11627.86 11651.86 24.00 1.2300 1.2300 1.2300 87 Sunny 237 260

14-Jan-11 9:12 15-Jan-11 9:12 2.8513 3.0201 11651.86 11675.86 24.00 1.2300 1.2300 1.2300 95 Sunny 237 260

20-Jan-11 9:11 21-Jan-11 9:11 2.8762 3.0127 11675.86 11699.86 24.00 1.2300 1.2300 1.2300 77 Sunny 237 260

26-Jan-11 9:06 27-Jan-11 9:06 2.8227 2.9861 11699.86 11723.86 24.00 1.2300 1.2300 1.2300 92 Sunny 237 260

Min 77

Max 101

Average 90

Page 41: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 11 of 28

Air Quality (24-hr TSP)

Page 42: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 12 of 28

Air Quality

Page 43: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 13 of 28

Noise

Station NSR1

Noise Level for 30 min, dB(A)

Date Start Time End Time

Leq L10 L90

Wind Speed (m/s)

Weather Condition

Limit Level

3-Nov-10 13:29 13:59 50 52 47 0.4 Sunny 75

9-Nov-10 13:37 14:07 50 50 45 0.2 Sunny 75

15-Nov-10 13:27 13:57 50 51 48 0.2 Sunny 75

25-Nov-10 13:36 14:06 50 52 45 0.2 Sunny 75

1-Dec-10 13:24 13:54 50 51 41 0.2 Sunny 75

7-Dec-10 13:16 13:46 49 51 44 0.4 Sunny 75

13-Dec-10 13:31 14:01 49 50 42 0.2 Fine 75

23-Dec-10 13:31 14:01 47 48 44 0.2 Sunny 75

29-Dec-10 13:23 13:53 49 51 43 0.3 Sunny 75

4-Jan-11 13:11 13:41 50 52 45 0.3 Cloudy 75

10-Jan-11 13:17 13:47 63 66 50 0.2 Sunny 75

20-Jan-11 13:18 13:48 54 56 49 0.2 Sunny 75

26-Jan-11 13:21 13:51 51 52 44 0.2 Sunny 75

Station NSR3

Noise Level for 30 min, dB(A)

Date Start Time End Time

Leq L10 L90

Wind Speed (m/s)

Weather Condition

Limit Level

3-Nov-10 14:31 15:01 52 53 50 0.2 Sunny 75

9-Nov-10 14:39 15:09 50 51 47 0.2 Sunny 75

15-Nov-10 14:29 14:59 51 52 47 0.2 Sunny 75

25-Nov-10 14:38 15:08 50 52 46 0.3 Sunny 75

1-Dec-10 14:28 14:58 50 51 50 0.2 Sunny 75

7-Dec-10 14:18 14:48 54 55 47 0.4 Sunny 75

13-Dec-10 14:33 15:03 49 51 46 0.3 Fine 75

23-Dec-10 14:33 15:03 50 52 47 0.2 Sunny 75

29-Dec-10 14:29 14:59 48 50 46 0.2 Sunny 75

4-Jan-11 14:16 14:46 49 51 47 0.2 Cloudy 75

10-Jan-11 14:18 14:48 50 52 47 0.2 Sunny 75

20-Jan-11 14:20 14:50 50 51 48 0.2 Sunny 75

26-Jan-11 14:25 14:55 46 48 41 0.3 Sunny 75

Page 44: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 14 of 28

Noise

Station NSR5

Noise Level for 30 min, dB(A)

Date Start Time End Time

Leq L10 L90

Wind Speed (m/s)

Weather Condition

Limit Level

3-Nov-10 9:03 9:33 57 60 54 0.4 Sunny 75

9-Nov-10 9:22 9:52 56 58 51 0.3 Sunny 75

15-Nov-10 9:13 9:43 57 58 53 0.4 Sunny 75

25-Nov-10 9:20 9:50 55 57 52 0.4 Sunny 75

1-Dec-10 9:13 9:43 52 54 49 0.3 Sunny 75

7-Dec-10 9:15 9:45 57 58 54 0.5 Sunny 75

13-Dec-10 9:25 9:55 52 54 48 0.4 Fine 75

23-Dec-10 9:18 9:48 55 57 52 0.3 Sunny 75

29-Dec-10 9:21 9:51 55 57 53 0.4 Sunny 75

4-Jan-11 9:22 9:52 62 64 57 0.4 Cloudy 75

10-Jan-11 9:13 9:43 54 57 53 0.2 Sunny 75

20-Jan-11 9:19 9:49 55 58 52 0.3 Sunny 75

26-Jan-11 9:14 9:44 57 60 53 0.2 Sunny 75

Station NSR7

Noise Level for 30 min, dB(A)

Date Start Time End Time

Leq L10 L90

Wind Speed (m/s)

Weather Condition

Limit Level

3-Nov-10 10:17 10:47 65 68 63 0.7 Sunny 75

9-Nov-10 10:34 11:04 64 66 61 0.3 Sunny 75

15-Nov-10 10:30 11:00 64 66 61 0.5 Sunny 75

25-Nov-10 10:26 10:56 64 66 61 0.8 Sunny 75

1-Dec-10 10:17 10:47 64 66 61 0.4 Sunny 75

7-Dec-10 10:17 10:47 64 66 60 0.9 Sunny 75

13-Dec-10 10:30 11:00 64 66 60 0.6 Fine 75

23-Dec-10 10:33 11:03 64 66 60 0.6 Sunny 75

29-Dec-10 10:25 10:55 64 66 61 0.5 Sunny 75

4-Jan-11 10:37 11:07 65 67 62 0.6 Cloudy 75

10-Jan-11 10:22 10:52 63 65 60 0.5 Sunny 75

20-Jan-11 10:28 10:58 65 67 61 0.5 Sunny 75

26-Jan-11 10:23 10:53 64 66 61 0.5 Sunny 75

Page 45: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 15 of 28

Noise

Page 46: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 16 of 28

Noise

Page 47: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 17 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP1

1/11/2010 23.9 7.6 5.2 63.2 16.3 2 10.5

3/11/2010 23.1 7.7 5.0 59.3 15.0 2.5 11.5

5/11/2010 20.8 7.8 5.5 62.7 29.6 2.5 24

8/11/2010 23.7 7.7 4.8 56.8 95.9 3 103.5

10/11/2010 24.4 7.8 6.7 80.9 45.8 3 36.5

12/11/2010 23.1 7.8 7.6 88.3 84.9 6 93

15/11/2010 23.8 7.9 7.2 84.6 80.0 6.5 80

17/11/2010 23.8 8.0 6.3 74.1 15.9 2 10

19/11/2010 24.4 7.8 5.8 70.2 40.3 2 33.5

22/11/2010 23.4 7.5 6.1 73.5 94.4 4.5 113.5

24/11/2010 22.7 7.9 5.9 67.7 63.7 4 75

26/11/2010 21.6 7.5 4.7 53.8 21.1 2.5 20

29/11/2010 22.5 7.6 4.7 54.8 21.9 2 17.5

1/12/2010 23.1 7.9 6.85 80.2 37.45 2.5 42.5

3/12/2010 23.2 8.3 6.3 74 31.2 2.5 35

6/12/2010 23.2 8.5 7.25 84.85 100.5 6 140

8/12/2010 21.1 8.1 7.15 80.75 55.9 4 51

10/12/2010 21.7 8.7 7.195 81.9 71.6 5.5 45.5

13/12/2010 23 8.1 7.5 87.75 67.75 5 65

15/12/2010 21.9 8.2 5.55 63.35 74.05 3 69.5

17/12/2010 17.3 8.3 6.115 64.05 27.2 3 23

20/12/2010 21.1 8 4.1 46.95 47.75 2.5 39.5

22/12/2010 20.4 8.6 7.15 79.55 79.45 5.5 82.5

24/12/2010 20.5 8.1 7.15 79.05 70.6 5.5 64.5

28/12/2010 19 8.3 7.1 76.65 81.7 3.5 91

30/12/2010 17.8 8.4 5.95 62.3 87.9 3.5 87

3/1/2011 17.2 8.6 6.9 71.1 66.6 5 63

5/1/2011 16.9 8.4 7.6 78.2 27.2 4 29

7/1/2011 11.8 8.4 10.0 92.4 32.9 10.5 24.5

10/1/2011 12.6 8.3 10.0 94.9 7.2 2 4.5

12/1/2011 11.1 8.7 9.4 85.9 11.4 2 5

14/1/2011 12.7 8.7 11.1 105.3 9.1 2 6

17/1/2011 12.4 7.9 7.1 69.2 28.3 5 34.5

19/1/2011 14.8 8.4 10.3 102.3 20.1 5.5 29

21/1/2011 15.4 6.8 10.1 102.4 7.6 4.5 2

24/1/2011 13.9 7.0 9.6 92.9 14.2 2.5 8

26/1/2011 13.9 7.3 9.1 88.5 13.9 2 13

28/1/2011 15.3 7.9 8.1 81.3 32.6 5.5 38

31/1/2011 14.6 7.8 5.1 49.8 64.6 6 68

Average 19.4 8.0 7.0 76.0 46.0 3.9 45.9

Action Level - <5.5 or >7.5 <1.23 - >173 - >231

Limit Level - <4.0 or >8.0 <1.17 - >177 - >299

Page 48: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 18 of 28

Water Quality

Temperature at MP1

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP1

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP1

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

y

Turbidity at MP1

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP1

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP1

0

20

40

60

80

100

120

140

160

180

200

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, m

g/L

Page 49: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 19 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP2

1/11/2010 23.2 7.6 5.6 66.7 7.3 2 5.5

3/11/2010 23.4 7.5 5.7 67.9 14.3 2 10.5

5/11/2010 21.5 7.5 5.5 63.6 35.1 2 33

8/11/2010 23.9 7.6 5.9 69.9 80.8 3.5 87

10/11/2010 24.2 7.8 6.8 80.2 82.1 3.5 69.5

12/11/2010 23.0 7.7 7.5 86.5 72.0 5 83

15/11/2010 24.1 7.7 7.2 84.9 75.8 6 57

17/11/2010 23.1 7.9 6.6 76.9 29.0 2 23.5

19/11/2010 23.6 7.7 6.2 73.2 65.4 4 63.5

22/11/2010 23.3 7.4 6.6 77.6 71.6 4 78

24/11/2010 23.0 7.7 6.5 75.0 61.2 3 64.5

26/11/2010 21.7 7.5 4.8 55.4 32.3 2.5 29

29/11/2010 22.6 7.6 5.9 69.0 16.3 2 15.5

1/12/2010 23.3 7.8 6.85 81.05 33.55 2 41.5

3/12/2010 22.7 7.9 6.45 75 57.9 3 66.5

6/12/2010 23.3 8 7.4 86.9 207.5 8 247.5

8/12/2010 21.3 8 7.5 84.75 42.25 4 39.5

10/12/2010 22 8.2 7.19 82.4 70.25 5 65

13/12/2010 22.7 8.2 7.15 82.75 64.75 5 60

15/12/2010 22.2 8.1 6.35 72.75 206.5 6 226

17/12/2010 18.9 8.4 6.75 72.75 67.3 6.5 81

20/12/2010 20.9 8.3 5.35 59.95 50.95 3.5 39.5

22/12/2010 20.5 8.3 7.65 84.85 135 7 143

24/12/2010 20.7 8 7.43 83.05 48.4 5.5 48.5

28/12/2010 18.7 8.2 7.45 80 92.75 4 115.5

30/12/2010 18.1 8 6.25 66.35 52.55 2 56

3/1/2011 17.0 8.3 7.4 76.9 33.5 4 28.5

5/1/2011 16.7 8.2 7.9 81.2 27.5 4.5 27

7/1/2011 12.3 8.2 9.8 92.3 10.6 2 10

10/1/2011 12.5 8.1 10.1 95.8 10.6 2 8

12/1/2011 11.5 8.3 9.0 83.0 8.4 2 7

14/1/2011 12.6 8.3 10.6 101.1 8.4 2 6

17/1/2011 12.5 7.8 5.3 52.1 31.7 5.5 35

19/1/2011 15.0 8.3 10.1 100.9 5.8 2 4.5

21/1/2011 15.8 7.0 9.6 96.3 9.5 2 8.5

24/1/2011 14.1 7.1 9.4 91.4 11.6 2 8.5

26/1/2011 14.4 7.5 9.2 90.2 11.7 2 12

28/1/2011 16.5 7.8 8.2 83.0 31.9 5.5 30.5

31/1/2011 14.2 7.5 4.5 44.0 49.0 5 53.5

Average 19.5 7.9 7.2 78.1 51.9 3.7 53.5

Action Level - <5.5 or >7.5 <1.04 - >132 - >170

Limit Level - <4.0 or >8.0 <0.89 - >163 - >209

Page 50: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 20 of 28

Water Quality

Temperature at MP2

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP2

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP2

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

Turbidity at MP2

0.0

50.0

100.0

150.0

200.0

250.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP2

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP2

0

50

100

150

200

250

300

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, m

g/L

Page 51: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 21 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP3

1/11/2010 19.9 7.8 8.1 89.3 13.0 4 12

3/11/2010 20.9 7.8 8.2 91.4 16.2 5 14

5/11/2010 20.0 7.7 7.1 79.0 19.0 6 13.5

8/11/2010 21.4 7.4 7.8 87.8 25.8 5.5 16

10/11/2010 22.9 7.5 8.4 98.0 22.3 5 12.5

12/11/2010 22.7 7.4 8.0 93.1 29.7 6 25

15/11/2010 23.9 7.4 8.2 97.1 30.3 6 25.5

17/11/2010 22.9 7.7 9.1 106.2 30.9 6 23

19/11/2010 23.7 7.6 8.3 98.1 34.8 8 33

22/11/2010 22.4 7.6 8.4 98.6 33.6 7.5 35.5

24/11/2010 22.0 7.5 7.5 86.2 39.0 10 37

26/11/2010 20.7 7.6 8.1 90.0 38.5 10 33

29/11/2010 22.5 8.6 10.7 126.7 41.5 7.5 42

1/12/2010 22.6 7.5 8.75 101.2 35.85 10 30.5

3/12/2010 22.6 8.2 9.35 109.2 38 11.5 33.5

6/12/2010 21.9 7.7 7.55 86.7 41 11.5 43.5

8/12/2010 18.7 7.9 8 86.75 37.3 3.5 39

10/12/2010 18.6 7.8 8.46 91.05 35.95 10 35.5

13/12/2010 21.1 7.8 8.55 96.85 31.7 7.5 22

15/12/2010 19.7 8.1 6.55 72.55 42.15 10 24.5

17/12/2010 14 8 10.85 106 38.05 9 26

20/12/2010 18.3 7.8 10.65 113.8 28.35 7 15

22/12/2010 17.6 7.8 8.5 89.8 27.35 7 12

24/12/2010 18.1 7.7 7.55 80.6 29.85 6 18

28/12/2010 14.1 8.2 6.25 61.25 30.25 3 7.5

30/12/2010 15.7 7.6 7.15 72.45 33.45 3 11.5

3/1/2011 13.5 7.9 8.7 84.2 37.8 3 15.5

5/1/2011 12.3 7.9 9.3 87.5 39.6 4 14.5

7/1/2011 11.8 8.6 9.3 86.3 34.4 3 11

10/1/2011 12.2 8.1 9.8 92.0 29.1 2.5 12

12/1/2011 10.7 8.2 9.4 85.2 25.8 2 9.5

14/1/2011 12.5 8.2 9.7 91.8 23.1 2 7.5

17/1/2011 11.6 8.3 10.5 96.9 22.7 3 15.5

19/1/2011 14.8 8.1 8.1 80.2 16.0 2.5 7

21/1/2011 15.2 7.1 9.6 95.6 15.9 2.5 6.5

24/1/2011 13.8 7.2 8.2 79.2 14.3 2 9.5

26/1/2011 13.8 7.4 8.0 77.3 14.4 2 10.5

28/1/2011 15.5 7.6 7.9 79.8 22.5 3 17.5

31/1/2011 13.7 7.6 10.3 99.5 23.9 5 22

Average 18.0 7.8 8.6 90.9 29.3 5.7 20.5

Action Level - <5.5 or >7.5 <6.85 - >64 - >65

Limit Level - <4.0 or >8.0 <6.65 - >67 - >66

Page 52: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 22 of 28

Water Quality

Temperature at MP3

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP3

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP3

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

Turbidity at MP3

0.0

20.0

40.0

60.0

80.0

100.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP3

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP3

0

20

40

60

80

100

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, mg

/L

Page 53: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 23 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP4

1/11/2010 22.4 7.5 7.0 80.0 40.4 2 29.5

3/11/2010 21.7 7.4 5.1 58.0 53.9 2.5 39

5/11/2010 20.1 7.5 5.8 63.7 28.2 3 15

8/11/2010 23.6 7.3 5.6 65.2 38.1 2 22.5

10/11/2010 24.3 7.4 6.6 78.8 29.2 2 15.5

12/11/2010 24.4 7.5 7.3 87.2 30.8 3 18.5

15/11/2010 25.1 7.2 6.4 77.0 34.9 4 23

17/11/2010 22.9 7.4 5.5 63.8 42.5 2 26

19/11/2010 24.6 7.4 6.4 75.9 46.8 3.5 34

22/11/2010 22.6 7.5 5.2 62.3 32.7 2 24

24/11/2010 22.5 7.4 6.4 73.7 42.9 4 30.5

26/11/2010 20.5 7.5 6.6 72.9 35.6 3 23.5

29/11/2010 22.8 7.9 7.4 85.5 32.7 2 23

1/12/2010 23.3 7.3 6.25 73.2 26.2 2.5 20

3/12/2010 23.8 7.7 6.15 73.55 26.75 2 19

6/12/2010 21.8 7.6 5.35 60.75 26.85 5 16

8/12/2010 19 7.8 6.95 75.85 36.05 4 23

10/12/2010 18.4 7.5 5.03 54 29.95 3 22.5

13/12/2010 21.9 7.9 7.8 89.4 40.75 9 33

15/12/2010 20.2 7.8 5.15 57.6 58.4 3 29

17/12/2010 12.3 8.1 10.245 96.35 22.8 3 9.5

20/12/2010 20.8 7.8 6.05 68.1 25.15 2 15.5

22/12/2010 19.8 7.7 6.35 69.8 44.35 2 31.5

24/12/2010 18.4 7.5 4.25 46.1 36.7 2 25.5

28/12/2010 11.7 8.1 5.5 50.8 23.65 2.5 17

30/12/2010 15.3 7.5 5.65 57.05 34.85 2 24.5

3/1/2011 12.0 7.8 8.6 80.3 36.8 2 29

5/1/2011 12.2 7.9 10.0 94.1 22.1 5 17

7/1/2011 11.2 7.9 8.4 77.3 28.8 2 18.5

10/1/2011 12.8 7.9 6.8 64.3 33.7 5.5 24.5

12/1/2011 8.1 8.2 11.0 93.4 22.7 5 17

14/1/2011 15.0 8.1 11.5 114.6 32.6 8.5 27

17/1/2011 11.9 8.0 11.8 110.6 30.6 15.5 31

19/1/2011 17.6 7.9 8.4 89.3 59.5 4 50

21/1/2011 15.3 6.9 8.7 88.0 44.4 2 32.5

24/1/2011 15.1 7.1 6.0 59.3 20.8 3 18

26/1/2011 13.1 7.4 6.5 62.2 37.8 2 30

28/1/2011 15.8 7.3 6.2 63.0 27.5 3 19.5

31/1/2011 13.1 7.3 8.8 84.8 17.3 3 14

Average 18.4 7.6 7.0 74.3 34.2 3.5 24.1

Action Level - <5.5 or >7.5 <3.91 - >60 - >50

Limit Level - <4.0 or >8.0 <3.82 - >64 - >53

Page 54: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 24 of 28

Water Quality

Temperature at MP4

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP4

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP4

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

Turbidity at MP4

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP4

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP4

0

20

40

60

80

100

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, m

g/L

Page 55: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 25 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP5

1/11/2010 21.8 7.2 7.4 84.3 43.3 2 30.5

3/11/2010 21.4 7.3 7.0 80.0 32.5 3.5 22.5

5/11/2010 19.8 7.2 6.6 72.1 31.9 6 19.5

8/11/2010 23.5 7.3 5.9 69.6 40.4 2 20

10/11/2010 23.8 7.3 7.0 83.7 27.3 2 15

12/11/2010 23.5 7.4 8.0 95.1 32.1 2 21.5

15/11/2010 24.9 7.5 8.8 106.1 35.5 2 20.5

17/11/2010 22.9 7.4 7.3 84.8 30.8 2 16.5

19/11/2010 24.9 7.2 6.6 79.8 31.6 2 20.5

22/11/2010 22.4 7.4 7.2 83.7 48.9 5 38.5

24/11/2010 22.1 7.4 6.2 71.1 83.4 4 50

26/11/2010 20.2 7.3 7.1 78.3 55.8 2 35.5

29/11/2010 22.9 7.4 5.3 61.7 33.9 3.5 25

1/12/2010 22.5 7.2 6.5 75.8 34.4 4 21

3/12/2010 22.9 7.4 6.95 81.45 33.8 3.5 24

6/12/2010 21.7 7.7 6.55 75.55 30.7 7 30

8/12/2010 18.1 7.7 7.75 83.5 39.95 6 26.5

10/12/2010 18 7.6 7.26 77.95 46.5 8.5 31.5

13/12/2010 21.8 7.7 6.35 72.95 36.8 2.5 21.5

15/12/2010 20.1 7.8 6.05 67.55 65.55 2 42.5

17/12/2010 12.4 8.2 10.35 97 26.45 3 13.5

20/12/2010 20.9 7.6 6.25 70.35 35 2 23

22/12/2010 19.7 7.8 6.55 72.75 63.6 4 52

24/12/2010 18.6 7.6 5.05 54.9 49.25 2 39

28/12/2010 10.8 7.7 7.15 64.95 26.5 2 15

30/12/2010 15.8 7.5 6.35 64.5 69.7 2.5 54.5

3/1/2011 12.3 7.8 8.2 77.0 39.1 2 25.5

5/1/2011 12.6 8.0 9.1 86.5 33.2 5 27

7/1/2011 11.1 7.9 8.6 79.1 29.0 2 19

10/1/2011 12.4 7.7 9.5 89.7 41.5 8.5 33

12/1/2011 7.8 8.3 13.4 113.0 42.9 11 33.5

14/1/2011 15.7 8.6 11.5 116.9 65.1 10 53.5

17/1/2011 11.8 8.1 12.3 115.4 28.5 12.5 34

19/1/2011 17.8 7.9 8.4 89.4 67.9 4 66

21/1/2011 15.5 7.1 9.1 92.3 37.0 2 22.5

24/1/2011 15.3 7.0 6.8 68.7 34.8 2 27.5

26/1/2011 12.9 7.9 7.1 67.5 28.7 2 19.5

28/1/2011 16.0 7.3 6.3 65.0 26.8 2 21

31/1/2011 13.3 7.2 8.3 80.3 16.9 2 11.5

Average 18.3 7.6 7.6 80.8 40.4 3.9 28.8

Action Level - <5.5 or >7.5 <4.13 - >81 - >66

Limit Level - <4.0 or >8.0 <3.87 - >84 - >69

Page 56: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 26 of 28

Water Quality

Temperature at MP5

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP5

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP5

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

Turbidity at MP5

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP5

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP5

0

20

40

60

80

100

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, mg

/L

Page 57: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 27 of 28

Water Quality

Notes:

Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.

Monitoring Date

Temp (oC)

pH Dissolved Oxygen (mg/L)

DOS (%)

Turbidity (NT)

BOD (mg/L)

Suspended Solids (mg/L)

MP6

1/11/2010 21.6 7.3 7.3 83.9 35.9 2 25.5

3/11/2010 21.1 7.4 7.4 83.7 40.5 3 29

5/11/2010 19.5 7.3 6.5 71.8 38.8 6 27.5

8/11/2010 23.4 7.4 6.3 73.5 59.4 2 34.5

10/11/2010 23.9 7.4 6.9 82.2 37.2 3 21.5

12/11/2010 22.8 7.5 8.7 101.7 60.0 2 39.5

15/11/2010 24.3 7.7 10.1 122.8 42.0 3 27.5

17/11/2010 22.6 7.3 7.1 82.9 41.3 2 23.5

19/11/2010 24.5 7.3 7.5 90.8 42.6 2 28.5

22/11/2010 22.8 7.5 7.3 83.8 55.9 6.5 43.5

24/11/2010 22.0 7.5 6.5 75.0 78.6 7 49

26/11/2010 20.0 7.3 6.4 70.1 63.6 2 40

29/11/2010 21.3 7.5 5.7 65.1 42.6 2 30.5

1/12/2010 22.2 7.3 6.25 73.1 30.95 3 20.5

3/12/2010 23.1 7.5 8.05 94.95 45.7 10 30

6/12/2010 21.9 7.8 6.15 73.7 33.15 4.5 25

8/12/2010 17.9 7.7 8 86.05 40.85 5.5 26

10/12/2010 18.2 7.9 6.815 73.45 46.9 2 31.5

13/12/2010 21.7 7.7 6.2 70.95 38.1 2 23

15/12/2010 19.9 7.9 5.85 65 90.25 2 57

17/12/2010 10.6 8.2 10.5 95 23.4 3 13

20/12/2010 21 7.7 6.75 76.65 38.25 2 24

22/12/2010 19.3 7.9 6.25 68.7 85.1 3.5 58

24/12/2010 18.9 7.6 5.25 57.05 39.25 2 28

28/12/2010 11.8 7.7 7.85 74 18.2 2 15.5

30/12/2010 15.4 7.6 6.45 65.55 64.15 2 48

3/1/2011 13.1 7.6 7.4 71.4 39.7 2 26.5

5/1/2011 13.2 8.5 8.0 77.0 39.5 2 22.5

7/1/2011 11.5 8.0 8.2 75.7 50.8 2 33.5

10/1/2011 12.8 7.8 7.9 75.7 28.7 2 20.5

12/1/2011 9.3 8.1 9.4 83.1 26.7 3.5 15

14/1/2011 15.4 8.7 11.2 113.5 25.0 7.5 19.5

17/1/2011 12.5 8.0 10.1 95.1 50.9 5 45

19/1/2011 17.2 7.8 8.3 87.1 34.8 3 24

21/1/2011 15.4 7.2 9.2 93.7 37.6 2 21

24/1/2011 15.4 7.4 7.0 70.4 54.2 2 43

26/1/2011 13.2 8.0 6.7 64.0 23.2 2 16.5

28/1/2011 16.3 7.4 5.9 60.8 30.6 2 23.5

31/1/2011 13.5 7.2 8.4 82.8 19.4 2 14

Average 18.2 7.7 7.5 79.8 43.4 3.2 29.3

Action Level - <5.5 or >7.5 <4.61 - >94 - >75

Limit Level - <4.0 or >8.0 <4.52 - >96 - >75

Page 58: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

Page 28 of 28

Water Quality

Temperature at MP6

7.0

12.0

17.0

22.0

27.0

32.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Te

mp

era

ture

, d

eg

. C

pH at MP6

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

pH

Dissolved Oxygen (DO) at MP6

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Dis

so

lve

d O

xy

ge

n (

DO

), m

g/L

Turbidity at MP6

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

Tu

rbid

ity

, N

TU

BOD at MP6

0

2

4

6

8

10

12

14

16

18

20

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

BO

D

Suspended Solids (SS) at MP6

0

20

40

60

80

100

1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011

Date

SS

, m

g/L

Page 59: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Table E1. Summary of bird monitoring in the Survey Area

Nov 2010

Species Name Scientific Name

Conservation Status

(2) Survey

(3) Mean

(4)

Little Grebe Tachybaptus ruficollis LC, (1) 4 43.3

Great Cormorant Phalacrocorax carbo PRC, (1) 4 10.0

Grey Heron Ardea cinerea PRC, (1) 4 18.0

Great Egret Egretta alba PRC, (1) 4 10.0

Intermediate Egret Egretta intermedia RC, (1) 3 1.3

Little Egret Egretta garzetta PRC, (1) 4 41.3

Chinese Pond Heron Ardeola bacchus PRC, (1) 4 36.3

Black-crowned Night Heron Nycticorax nycticorax LC, (1) 1 0.3

Black-faced Spoonbill Platalea minor PGC, (1) 3 5.3

Northern Shoveler Anas clypeata RC, (1) 4 1.5

Besra Accipiter virgatus - 1 0.3

Common Buzzard Buteo buteo - 1 0.3

White-breasted Waterhen Amaurornis phoenicurus (1) 4 2.5

Common Moorhen Gallinula chloropus (1) 4 19.0

Pheasant-tailed Jacana Hydrophasianus chirurgus LC, (1) 1 0.3

Greater Painted-Snipe Rostratula benghalensis LC, (1) 1 0.3

Black-winged Stilt Himantopus himantopus RC, (1) 4 5.8

Little Ringed Plover Charadrius dubius LC, (1) 4 9.8

Kentish Plover Charadrius alexandrinus RC, (1) 1 0.3

Spotted Redshank Tringa erythropus RC, (1) 1 0.3

Common Redshank Tringa totanus RC, (1) 1 0.3

Marsh Sandpiper Tringa stagnatilis RC, (1) 3 2.5

Common Greenshank Tringa nebularia RC, (1) 4 3.5

Green Sandpiper Tringa ochropus (1) 4 7.3

Wood Sandpiper Tringa glareola LC, (1) 4 8.3

Common Sandpiper Actitis hypoleucos (1) 4 20.5

Common Snipe Gallinago gallinago (1) 2 1.0

Temminck’s Stint Calidris temminckii LC, (1) 3 3.3

Pied Kingfisher Ceryle rudis (LC), (1) 1 0.3

Common Kingfisher Alcedo atthis (1) 4 7.8

White-throated Kingfisher Halcyon smyrnensis (LC) 4 2.0

Pale Martin Riparia diluta - 1 0.5

Yellow Wagtail Motacilla flava (1) 4 23.5

Grey Wagtail Motacilla cinerea (1) 1 0.5

Richard's Pipit Anthus richardi - 4 8.0

Red-throated Pipit Anthus cervinus LC 3 1.3

Black-browed Reed Warbler Acrocephalus bistrigiceps - 1 0.8

Oriental Reed Warbler Acrocephalus orientalis - 1 0.3

Zitting Cisticola Cisticola juncidis LC 4 2.8

Red-billed Starling Sturnus sericeus GC 4 46.8

White-cheeked Starling Sturnus cineraceus PRC 2 2.8

Appendix E. Summary of Ecological Monitoring results

Page 60: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Collared Crow Corvus torquatus LC, NT 3 1.5

Total no. of species 42

Dec 2010

Species Name Scientific Name

Conservation Status

(2) Survey

(3) Mean

(4)

Little Grebe Tachybaptus ruficollis LC, (1) 5 30.6

Great Cormorant Phalacrocorax carbo PRC, (1) 5 15.4

Grey Heron Ardea cinerea PRC, (1) 5 15.4

Great Egret Egretta alba PRC, (1) 5 8.2

Intermediate Egret Egretta intermedia RC, (1) 2 0.4

Little Egret Egretta garzetta PRC, (1) 5 23.6

Cattle Egret Bubulcus ibis (LC), (1) 1 0.6

Chinese Pond Heron Ardeola bacchus PRC, (1) 5 15.2

Black-faced Spoonbill Platalea minor PGC, (1) 2 1.4

Northern Shoveler Anas clypeata RC, (1) 1 0.2

Osprey Pandion haliaetus RC 3 0.6

Black Kite Milvus migrans (RC) 2 0.6

Water Rail Rallus aquaticus LC, (1) 2 0.4

White-breasted Waterhen Amaurornis phoenicurus (1) 3 0.8

Common Moorhen Gallinula chloropus (1) 5 16.6

Black-winged Stilt Himantopus himantopus RC, (1) 2 2.0

Pied Avocet Recurvirostra avosetta RC,(1) 3 1.2

Little Ringed Plover Charadrius dubius LC, (1) 5 17.4

Spotted Redshank Tringa erythropus RC, (1) 1 0.2

Common Greenshank Tringa nebularia RC, (1) 5 3.0

Green Sandpiper Tringa ochropus (1) 5 7.2

Wood Sandpiper Tringa glareola LC, (1) 5 8.4

Common Sandpiper Actitis hypoleucos (1) 5 14.8

Pintail/Swinhoe's Snipe Gallinago stenura/megala (1) 1 0.6

Common Snipe Gallinago gallinago (1) 1 0.2

Temminck's Stint Calidris temminckii LC, (1) 3 3.6

Pied Kingfisher Ceryle rudis (LC), (1) 1 0.2

Common Kingfisher Alcedo atthis (1) 5 6.0

White-throated Kingfisher Halcyon smyrnensis (LC) 2 1.0

Yellow Wagtail Motacilla flava (1) 5 25.8

Grey Wagtail Motacilla cinerea (1) 2 0.6

Richard's Pipit Anthus richardi - 5 10.0

Red-throated Pipit Anthus cervinus LC 3 2.8

Buff-bellied Pipit Anthus rubescens LC 2 1.0

Daurian Redstart Phoenicurus auroreus - 1 0.2

Common Stonechat Saxicola torquata - 3 1.6

Zitting Cisticola Cisticola juncidis LC 4 3.2

Red-billed Starling Sturnus sericeus GC 5 153.2

White-cheeked Starling Sturnus cineraceus PRC 3 5.0

Collared Crow Corvus torquatus LC, NT 4 1.8

Total no. of species 41

Jan 2011

Species Name Scientific Name

Conservation Status

(2) Survey

(3) Mean

(4)

Page 61: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Little Grebe Tachybaptus ruficollis LC, (1) 4 18.0

Great Cormorant Phalacrocorax carbo PRC, (1) 4 12.5

Grey Heron Ardea cinerea PRC, (1) 4 9.3

Great Egret Egretta alba PRC, (1) 4 11.3

Intermediate Egret Egretta intermedia RC, (1) 2 1.5

Little Egret Egretta garzetta PRC, (1) 4 75.0

Chinese Pond Heron Ardeola bacchus PRC, (1) 4 22.3

Black-faced Spoonbill Platalea minor PGC, (1) 2 13.3

Osprey Pandion haliaetus RC 1 0.3

Common Buzzard Buteo buteo - 1 0.3

Eastern Water Rail Rallus indicus LC,(1) 1 0.3

White-breasted Waterhen Amaurornis phoenicurus (1) 4 2.5

Common Moorhen Gallinula chloropus (1) 4 18.3

Black-winged Stilt Himantopus himantopus RC, (1) 1 0.3

Little Ringed Plover Charadrius dubius LC, (1) 4 9.0

Common Greenshank Tringa nebularia RC, (1) 4 3.3

Green Sandpiper Tringa ochropus (1) 4 4.0

Wood Sandpiper Tringa glareola LC, (1) 3 3.3

Common Sandpiper Actitis hypoleucos (1) 4 9.8

Pintail/Swinhoe's Snipe Gallinago stenura/ Gallinago megala

(1) 1 0.3

Common Snipe Gallinago gallinago (1) 1 0.3

Temminck's Stint Calidris temminckii LC, (1) 4 3.8

Black-headed Gull Larus ridibundus PRC, (1) 1 0.3

Common Kingfisher Alcedo atthis (1) 3 3.0

White-throated Kingfisher Halcyon smyrnensis (LC) 1 0.3

Yellow Wagtail Motacilla flava (1) 4 14.8

Red-throated Pipit Anthus cervinus LC 1 0.3

Zitting Cisticola Cisticola juncidis LC 2 0.8

Red-billed Starling Sturnus sericeus GC 4 277.5

White-cheeked Starling Sturnus cineraceus PRC 2 5.8

Collared Crow Corvus torquatus LC, NT 3 1.3

Total no. of species 31

(1) indicates wetland-dependant or -associated species. (2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2010). (3) indicates number of surveys recorded within the survey period. (4) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys.

Table E2. Summary of bird monitoring in the WRA

Nov 2010

Species Name Scientific Name Conservation

Status (2)

Survey(3)

Total(4)

Records outside survey

(5)

Grey Heron Ardea cinerea PRC, (1) 2 1.0

Great Egret Egretta alba PRC, (1) - - � Intermediate Egret Egretta intermedia RC, (1) - - � Little Egret Egretta garzetta PRC, (1) - - � Chinese Pond Heron Ardeola bacchus PRC, (1) 1 1.0 � Black Kite Milvus migrans (RC) - - �

Page 62: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Common Kestrel Falco tinnunculus - 2 1.0

Black-winged Stilt Himantopus himantopus

RC, (1) - - �

Little Ringed Plover Charadrius dubius LC, (1) 2 24.5 �

Common Greenshank Tringa nebularia RC, (1) 1 0.5 �

Green Sandpiper Tringa ochropus (1) 1 1.0

Wood Sandpiper Tringa glareola LC, (1) - - �

Common Sandpiper Actitis hypoleucos (1) 1 0.5

Pintail/Swinhoe's Snipe Gallinago stenura/ Gallinago megala

(1) 1 0.5

Common Snipe Gallinago gallinago (1) - - �

Temminck’s Stint Calidris temminckii LC, (1) 1 0.5 �

Pied Kingfisher Ceryle rudis (LC), (1) - - � White-throated Kingfisher Halcyon smyrnensis (LC) - - � Yellow Wagtail Motacilla flava (1) 2 14.5 � White Wagtail Motacilla alba - 0 0.0 � Richard's Pipit Anthus richardi - 2 1.5 � Olive-backed Pipit Anthus hodgsoni - 1 0.5

Red-throated Pipit Anthus cervinus LC 2 2.5

Buff-bellied Pipit Anthus rubescens LC 2 1.5

Common Stonechat Saxicola torquata - 1 0.5 � Plain Prinia Prinia inornata - - - �

Dusky Warbler Phylloscopus fuscatus

- - - �

Little Bunting Emberiza pusilla - 1 0.5

Scaly-breasted Munia Lonchura punctulata - - - � Eurasian Tree Sparrow Passer montanus - - - �

No. of Species Recorded 30

Dec 2010

Species Name Scientific Name Conservation

Status (2)

Survey(3)

Total(4)

Records outside survey

(5)

Grey Heron Ardea cinerea PRC, (1) 3 1.6 �

Great Egret Egretta alba PRC, (1) 1 0.4 �

Intermediate Egret Egretta intermedia RC, (1) - - �

Little Egret Egretta garzetta PRC, (1) 2 1.8 �

Chinese Pond Heron Ardeola bacchus PRC, (1) 1 0.2

Eurasian Wigeon Anas penelope RC, (1) 1 1.6

Common Teal Anas crecca RC, (1) - - �

Northern Pintail Anas acuta RC,(1) 1 0.2

Osprey Pandion haliaetus RC 1 0.2

Black Kite Milvus migrans (RC) - - �

Common Kestrel Falco tinnunculus - 2 0.4 �

Black-winged Stilt Himantopus himantopus RC, (1) - - �

Pied Avocet Recurvirostra avosetta RC, (1) 1 0.2

Little Ringed Plover Charadrius dubius LC, (1) 4 7.4 �

Kentish Plover Charadrius alexandrinus RC, (1) - - �

Marsh Sandpiper Tringa stagnatilis RC, (1) - - �

Page 63: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Common Greenshank Tringa nebularia RC, (1) - - �

Green Sandpiper Tringa ochropus (1) 2 0.4

Wood Sandpiper Tringa glareola LC, (1) 0 0.0 �

Common Sandpiper Actitis hypoleucos (1) 3 1.0

Temminck's Stint Calidris temminckii LC, (1) - - �

Spotted Dove Steptopelia chinensis - - - �

Pied Kingfisher Ceryle rudis (LC), (1) 1 0.2

Common Kingfisher Alcedo atthis (1) 2 0.4

Yellow Wagtail Motacilla flava (1) 5 10.2 �

Grey Wagtail Motacilla cinerea (1) 1 0.2

White Wagtail Motacilla alba (1) 2 1.8 �

Richard's Pipit Anthus richardi - 3 0.8 �

Red-throated Pipit Anthus cervinus LC 2 1.2 �

Common Stonechat Saxicola torquata - 3 1.0 �

Plain Prinia Prinia inornata - - - �

Eurasian Tree Sparrow Passer montanus - - - �

Large-billed Crow Corvus macrorhynchos - 1 0.4

Collared Crow Corvus torquatus LC, NT 1 0.2

No. of Species Recorded 34

Jan 2011

Species Name Scientific Name Conservation

Status (2)

Survey(3)

Total(4)

Records outside survey

(5)

Little Grebe Tachybaptus ruficollis LC, (1) 1 0.5

Great Cormorant Phalacrocorax carbo PRC, (1) 3 0.8

Grey Heron Ardea cinerea PRC, (1) 4 2.0

Great Egret Egretta alba PRC, (1) 4 14.0

Intermediate Egret Egretta intermedia RC, (1) 3 1.7

Little Egret Egretta garzetta PRC, (1) 4 8.0

Black-faced Spoonbill Platalea minor PGC, (1) 1 0.3

Eurasian Wigeon Anas penelope RC, (1) 1 2.5

Common Teal Anas crecca RC, (1) 1 1.0

Northern Pintail Anas acuta RC, (1) 1 7.0

Black Kite Milvus migrans (RC) 2 0.8

Common Kestrel Falco tinnunculus - 3 1.0

Little Ringed Plover Charadrius dubius LC, (1) 2 3.8

Green Sandpiper Tringa ochropus (1) 1 0.5

Pied Kingfisher Ceryle rudis (LC), (1) 1 0.3

Common Kingfisher Alcedo atthis (1) 2 0.5

Yellow Wagtail Motacilla flava (1) 4 15.0

Richard's Pipit Anthus richardi - 2 0.5

Red-throated Pipit Anthus cervinus LC 1 0.5

Common Stonechat Saxicola torquata - 3 1.0

Collared Crow Corvus torquatus LC, NT 1 0.3

N/A

No. of Species Recorded 21

(1) indicates wetland-dependant or -associated species. (2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2010). (3) indicates number of surveys recorded within the survey period.

Page 64: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

(4) refers to the total number of individuals recorded in the survey (5) includes observations during other surveys and/or site visits.

Summary of herpetofauna surveys: Species Name Scientific Name Nov 2010 – Jan 2011

Conservation Status(1)

Survey

(2) Mean

(3)

Amphibians

(No Records)

Survey(2)

Mean(3)

Reptiles

(No Records)

(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)

Summary of mammals:

Common Name Scientific Name

Conservation Status

(1) Nov 2010 – Jan 2011

No Records)

Summary of insect surveys conducted in the nearby fish ponds:

Common Name Scientific Name Nov 2010

Conservation Status

(1)

Survey(2)

Mean(3)

Odonate 5

Common Bluetail Aschnura senegalensis - 1 1

Crimson Darter Crocothemis servilia - 1 1

Green Skimmer Orthetrum sabina - 1 4

Wandering Glider Pantala flavescens - 1 6

Saddlebag Glider Tramea virginia - 1 3

Butterfly 8

Unidentified Swift Pelopidas sp. - 1 1

Red-base Jezebel Delias pasithoe - 1 1

Indian Cabbage White Pieris canidia - 1 17

Common Grass Yellow Eurema hecabe - 1 6

Unidentified Cerulean Jamides sp. - 1 2

Pale Grass Blue Zizeeria maha - 1 7

Common Tiger Danaus genutia - 1 1

Blue-Spotted Crow Euploea midamus - 1 1 (1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Wilson (2004) and Young & Yiu (2002). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)

Page 65: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Summary of insect surveys conducted in the WRA

Common Name Scientific Name Nov 2010

Conservation Status

(1)

Survey(2)

Mean(3)

Odonate 8

Common Bluetail Aschnura senegalensis - 1 8

Pale-spotted Emperor Anax guttatus - 1 1

Lesser Emperor Anax parthenope - 1 1

Crimson Darter Crocothemis servilia - 1 3

Blue Percher Diplacodes trivialis - 1 2

Common Red Skimmer Orthetrum pruinosum - 1 1

Green Skimmer Orthetrum sabina - 1 30

Wandering Glider Pantala flavescens - 1 25

Butterfly 4

Common Straight Swift Parnara guttatus - 1 1

Lemon Emigrant Catopsilia pomona - 1 1

Common Grass Yellow Eurema hecabe - 1 4

Blue-Spotted Crow Euploea midamus - 1 2 (1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Wilson (2004) and Young & Yiu (2002). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)

Page 66: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5
Page 67: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011

Appendix F. Environmental Mitigation Measures - Implementation Status

Page 68: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5
Page 69: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

- 1 -

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status

Air Quality – Recommended Mitigation Measures Air Quality Mitigation Measures during construction Implementation Status

• use of effective dust screens, sheeting or netting to be provided to enclose dry scaffolding which may be provided from the ground floor level of the building or if a canopy is provided at the first floor level, from the first floor level, up to the highest level (maximum four floors for this Project) of the scaffolding where scaffolding is erected around the perimeter of a building under construction;

N/A

• dump trucks for material transport should be totally enclosed using impervious sheeting; �

• any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

P

• dusty materials remaining after a stockpile is removed should be wetted with water; �

• the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with e.g. concrete, bituminous materials or hardcore or similar;

• the portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;

P

• stockpile of dusty materials to be either covered entirely by impervious sheeting, placed in an area sheltered on the top and the 3 sides; or sprayed with water so as to maintain the entire surface wet;

N/A

• all dusty materials to be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;

• vehicle speed to be limited to 10 kph except on completed access roads; �

• every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites;

• the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

• the working area of excavation should be sprayed with water immediately before, during and immediately after (as necessary) the operations so as to maintain the entire surface wet;

Odour mitigation measures

• all malodorous excavated material should be placed as far as possible from any ASRs; N/A

• the stockpiled malodorous material should be removed from site as soon as possible; and N/A

• the stockpiled malodorous material should be covered entirely by plastic tarpaulin sheets. N/A

Noise – Recommended Mitigation Measures Noise Mitigation Measures during construction Implementation Status

• only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;

• machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

• plant known to emit noise strongly in one direction should, where possible, be orientated to direct noise away from the NSRs;

• silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction period;

• mobile plant should be sited as far away from NSRs as possible; �

Page 70: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

- 2 -

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status

• material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities; and

• The Contractor shall at all times comply with all current statutory environmental legislation.

Selection of quieter plant and working methods The Contractor shall obtain particular models of plant that are quieter than standards given in GW-TM. The list of assumed quieter plants can be found in the Table 4–14 of the EIA report. The Contractor shall select from the available models achieving the assumed sound levels while making reference to the GW-TM and BS5228: Part 1: 1997

N/A

Use of Noise Barriers Noise barriers are proposed along the site boundary to block the direct line of sight from the most affected NSRs to the major noise contribution construction phases. The height of the noise barriers ranged from 9-10m. The noise barriers shall be built before the commencement of construction works in order to ensure protection to nearby NSRs. The noise barrier should have a surface density of at least 10kg/m

2 or material providing

equivalent transmission loss. The noise barriers and hoardings should have no gaps and openings to avoid noise leakage.

P

Water Quality – Recommended Mitigation Measures Water Quality Mitigation Measures during construction Implementation Status

• The site should be confined to avoid silt runoff to the site. �

• No discharge of silty water into the storm drain and drainage channel within and the vicinity of the site.

• Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials.

• Stockpiles to be covered by tarpaulin to avoid spreading of materials during rainstorms; N/A

• Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;

• Chemical waste containers shall be labelled with appropriate warning signs in English and Chinese to avoid accidents. there shall also be clear instructions showing what action to take in the event of an accidental;

• Storage areas shall be selected at safe locations on site and adequate space shall be allocated to the storage area;

• Any construction plant which causes pollution to the water system due to leakage of oil or fuel shall be removed off-site immediately;

• Spillage or leakage of chemical waste to be controlled by using suitable absorbent materials;

• Chemicals will always be stored on drip trays or in bunded areas where the volume is 110% of the stored volume;

P

• Regular clearance of domestic waste generated in the temporary sanitary facilities to avoid waste water spillage.

• Temporary sanitary facilities to be provided for on-site workers during construction. �

• Temporary drainage channel and associated facilities will be provided to collect the surface runoff generated within the Project Area during the construction phase.

• Sandbags or silt traps will need to be placed to avoid silt runoff to the drainage channel draining the water in the northern ditch. Draining of the ditches should avoid rainy weather.

• Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels.

Page 71: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

- 3 -

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status

Waste Management – Recommended Mitigation Measures Waste Management Mitigation Measures during construction Implementation Status

Site Clearance Waste

• The major construction works of Wo Shang Wai is in the development of residential buildings and other associated facilities (club house, tennis courts, etc). The amount of site clearance works will be limited with the exception of the excavated materials. The thin layer of vegetation removed can be stored and reused for landscaping.

Excavated Materials The intention is to maximize the reuse of the excavated materials on-site as fill materials.

Imported Filling Material The excavated/imported filling material may have to be temporarily stockpiled on-site for the construction of road embankment and foundation of viaduct substructure. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials at during wet season should be avoided as far as practicable.

N/A

Construction and Demolition Materials Careful design, planning and good site management can minimise over-ordering and generation of waste materials such as concrete, mortars and cement grouts. The design of formwork should maximise the use of standard wooden panels so that high reuse levels can be achieved. Alternatives such as steel formwork of plastic facing should be considered to increase the potential for reuse.

The Contractor should reuse any C&D material on-site. C&D waste should be segregated and stored in different containers to other wastes to encourage the re-use or recycling of materials and their proper disposal.

Chemical Waste For those processes which generate chemical waste, it may be possible to find alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical waste.

N/A

Containers used for the storage of chemical wastes should:

• be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed:

• have a capacity of less than 450 litres unless the specification have been approved by the EPD; and

• display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations,

The storage area for chemical wastes should:

• be clearly labelled and used solely for the storage of chemical waste; �

• be enclosed on at least 3 sides; �

• have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area whichever is the greatest;

• have adequate ventilation; �

• be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and

• be arranged so that incompatible materials are adequately separated. �

Disposal of chemical waste should:

• be via a licensed waste collector; and �

• be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers, or

N/A

• to be reuser of the waste, under approval from the EPD. N/A

Page 72: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

- 4 -

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status

General Refuse Should be stored in enclosed bins or compaction units separate from C&D and chemical wastes. The Contractor should employ a reputable waste collector to remove general refuse from the site, separate from C&D and chemical wastes, on a regular basis to minimise odour, pest and litter impacts. Burning of refuse on construction sites is prohibited by law.

P

Disposal of Excavated Sediment at Sea

The requirements and procedures for excavated sediment disposal are specified under the ETWB TCW No. 34/2002 and PNAP 252. The management of the excavation, use and disposal of sediment is monitored by Fill Management Committee, whilst the licensing of marine dumping is the responsibility of the Director of Environmental Protection (DEP).

N/A

The excavated sediment would be loaded onto barges or other appropriate vessel and transported to the designated marine disposal site. Category L sediment and Category M sediment passing the biological test would be suitable for disposal at a gazetted open sea disposal ground. Category M sediment failing the biological test and Category H sediment passing the biological test would require confined marine disposal.

N/A

During transportation and disposal of the dredged sediment, the following measures should be taken to minimize potential impacts on water quality: -

N/A

• Bottom opening transport vessels should be fitted with tight fitting seals to prevent leakage of material. Excess material should be cleaned from the decks and exposed fittings of vessels before the vessel is moved.

N/A

• Monitoring of the barge loading should be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels should be equipped with automatic self-monitoring devices as specified by the DEP.

N/A

Ecology – Recommended Mitigation Measures Ecology Mitigation Measures during construction Implementation Status

Clear Definition of Site Limit

Clear definition of the site limit should be provided in order to minimize and confine the disturbance during the construction period, especially the northern limit of the Site which is adjacent to fishponds within the Conservation Area (CA) zone and are considered to be ecological sensitive receivers.

During wetland construction stage the WRA boundary will be delineated using a temporary hoarding in order to reduce disturbance to off-site habitats and wildlife. During the establishment phase this hoarding will be replaced with a 1 m high chain-link fence in order to reduce disturbance to the WRA through access by humans and dogs, and a hoarding will be established around the residential construction site.

Dust and Noise Suppression and Avoidance of Water Pollution

Good site practices of dust and noise suppression should be strictly implemented to ensure that disturbance is minimized to acceptable levels. Mitigation measures for the off-site disturbance impacts on the fishponds in the CA include hoarding at the northern site boundary during construction of the WRA to reduce noise and dust impacts to the adjacent habitats. Through the use of quieter plant and temporary/movable noise barriers, the noise level would be reduced significantly to an acceptable level. Hoarding at the northern boundary should be replaced with a 1 m high chain-link fence following construction and the WRA will then act as a buffer between the existing wetland areas and the residential part of the site until construction is completed. Hoarding will be retained between the WRA and ongoing construction work to avoid visual disturbance and reduce noise and dust emissions. Pollution of watercourses and sedimentary runoff will be minimized by good site practice, especially the containment of water and sediment within the site for removal.

These standard noise and air and water quality site practices are considered to be effective measures for minimizing the disturbance impact during the construction period.

Planning of Construction Schedule

Page 73: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5

- 5 -

Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status

The construction of the proposed project should be scheduled in phases. Because mitigation is preferably carried out in advance of the main works rather than after the completion of works, the construction of the WRA will commence at the start of the project. Construction work within the WRA is scheduled to take place in a single wet season, followed by 1.5 years of wetland establishment. During the wetland establishment period no noisy work will be undertaken within the WRA to minimize the disturbance to off-site habitats and wildlife.

Reusing Onsite Materials

Soil and plants on-site should be reused (e.g. used as fill material) as far as practical. Stock piles of these reusable materials should be stored in an appropriate area on-site. In particular, the re-use of the wetland soils and topsoil should be considered.

Construction of the Wetland Restoration Area The WRA will be operational within 2.5 yrs from the commencement of construction (1 year for site formation and 1.5 years for establishment) and will compensate for the predicted ecological impacts of the proposed development.

Landscape and Visual – Recommended Mitigation Measures Landscape and Visual Mitigation Measures during construction Implementation Status

CM1- The construction area and contractor’s temporary works areas should be minimised to avoid impacts on adjacent landscape.

CM2 - Screening of construction works by hoarding / noise barriers. �

CM3 - Reduction of construction period to practical minimum. �

CM4 - Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where the soil material meets acceptable criteria and where practical. The Contract Specification shall include storage and reuse of topsoil as appropriate.

CM5 - Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone).

CM6 – Advance screen planting of noise barriers �

CM7 - Control night-time lighting and glare by hooding all lights. �

CM8 - Ensure no run-off into streams adjacent to the Project Area. �

CM9 - Protection of existing trees on boundary of site shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at S16 and Tree Removal Application stage).

CM10 - Trees unavoidably affected by the works shall be transplanted where practical. Trees should be transplanted straight to their destinations and not held in a nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, if applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme.

Legend:

� Implemented × Not implemented P Partially implemented N/A Not applicable