proposed comprehensive development at wo …...on 12 november 2010, the contractor issued a letter...
TRANSCRIPT
![Page 1: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/1.jpg)
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long
Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 (Rev. A)
February 2011
Report No.: 266567/16/A
![Page 2: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/2.jpg)
![Page 3: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/3.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
i
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Content Chapter Title Page
Executive Summary iv
1. Introduction 1 1.1 Background________________________________________________________________________ 1 1.2 Project Organization _________________________________________________________________ 1 1.3 Environmental Status in the reporting period ______________________________________________ 1 1.4 Summary of EM&A Requirements ______________________________________________________ 1 1.5 Recommended Mitigation Measures_____________________________________________________ 2
2. Summary of Monitoring Results 4 2.1 Air Quality Monitoring ________________________________________________________________ 4 2.2 Construction Noise Monitoring _________________________________________________________ 4 2.3 Water Quality Monitoring______________________________________________________________ 4 2.4 Ecological Monitoring ________________________________________________________________ 4 2.5 Landscape and Visual Monitoring_______________________________________________________ 5
3. Environmental Site Inspection and Audit 8 3.1 Site Inspection _____________________________________________________________________ 8 3.2 Solid and Liquid Waste Management Status ______________________________________________ 8
4. Report on Non-compliance and Complaints 9 4.1 Record on Non-compliance of Action and Limit Levels_______________________________________ 9 4.2 Record on Environmental Complaints received ___________________________________________ 11 4.3 Follow-up actions taken _____________________________________________________________ 11
5. Future Key Issues 12 5.1 Construction Works for the Coming Months ______________________________________________ 12 5.2 Key Issues for the Coming Months _____________________________________________________ 12 5.3 Conclusions and Recommendations____________________________________________________ 12
Tables
Table 1.1: Summary of Impact EM&A Requirements_________________________________________________ 2 Table 2.1: Construction Audit Summary on Landscape and Visual ______________________________________ 5 Table 4.1: Comparison of monitoring data of Suspended Solids ________________________________________ 9 Table 4.2: Summary of exceedance investigations _________________________________________________ 10
List of Figures
Figure 1.1 General Site Layout and Locations of Monitoring Stations
Figure 2.1 Survey Area and Transect Walked
![Page 4: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/4.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
ii
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
List of Appendices
Appendix A Project Organization Chart
Appendix B Tentative Construction Programme
Appendix C Action and Limit Levels for Construction Phase
Appendix D Graphical plots of the monitoring results
Appendix E Summary of Ecological Monitoring results
Appendix F Environmental Mitigation Measures - Implementation Status
![Page 5: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/5.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
iii
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Executive Summary
Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co. Ltd.
to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit
(EM&A) for both pre-construction and construction phases of the Proposed Comprehensive Development
at Wo Shang Wai, Yuen Long.
This is the 3rd
Quarterly EM&A Summary report and this report summarises the findings on EM&A during
the period from 1 November 2010 to 31 January 2011.
On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference
to the EP Condition 3.3 to 3.5. In accordance with EP Condition 3.6, the evidence of completion has been
certified by the ET Leader and verified by the IEC before submitting to the Director of Environmental
Protection (the Director).
Exceedance of Action and Limit Levels
The Action levels of Air Quality (1-hr TSP) were exceeded on 7 Dec 2010 at the four monitoring stations
(ASR1, ASR2A, ASR3, ASR4). The summary of exceedance is provided in Section 2.1. Investigations on
the exceedance showed that the unfavourable wind direction on the date of exceedance may have carried
pollutants from Shenzhen and caused short term deterioration of air quality in the project area. The
exceedance was not considered to be related to the project.
There was no breach of Action or Limit levels for Noise (as Leq) in the reporting month.
Action and Limit Level exceedances of pH, DO, turbidity and SS were recorded at water quality monitoring
stations. The summary of measured water quality is presented in Section 2.3. Investigations on the
exceedance showed that the exceedances were not related to the Project and may have been due to
external factors including natural variations and other unknown factors such as pond fish culture activities
and high fish activities in the ditch.
Implementation of mitigation measures
Site audits were carried out on a weekly basis during the monitoring period to confirm the implementation
of environmental mitigation measures undertaken by the Contractor in the reporting period. The status of
implementation of mitigation measures in the site is shown in Appendix F.
Record of Complaints
There was no record of complaints received in the reporting period.
Future Key Issues
The major site works to be commissioned in the coming three months include installation of band drain, trial
embankment for ground improvement and site formation (filling). Potential environmental impacts due to
the construction activities, including air quality, noise, water quality, ecology and landscape and visual, will
be monitored.
![Page 6: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/6.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
iv
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Environmental mitigation measures will be implemented on site as recommended and weekly site audits
will be carried out to ensure that the environmental conditions are acceptable.
![Page 7: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/7.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
1
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
1.1 Background
In March 2005, the Project Proponent, Profit Point Enterprises Limited, acquired the development site in
Yuen Long at Wo Shang Wai. An Environmental Impact Assessment (EIA) was carried out under the EIA
Ordinance (EIAO) since then and the Environmental Permit (EP-311/2008B) for construction of the
comprehensive development in Wo Shang Wai was granted by EPD on 29 July 2010. The Project involves
the residential development and associated infrastructure and wetland restoration area and linear
landscape area. The construction works under the Environmental Permit commenced on 12 May 2010.
Heng Shung Construction Co. Ltd. was commissioned as the Contractor for the Project. Mott MacDonald
Hong Kong Ltd. (“MMHK”) has been commissioned by Heng Shung Construction Co. Ltd. to undertake the
Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for both pre-
construction and construction phases of the Proposed Comprehensive Development at Wo Shang Wai,
Yuen Long.
This report summarises the findings during the period from 1 November 2010 to 31 January 2011.
1.2 Project Organization
The organisation chart and lines of communication with respect to the on-site environmental management
structure together with the contact information of the key personnel are shown in Appendix A.
1.3 Environmental Status in the reporting period
During the reporting period, construction works of the Project undertaken include:
� Site formation for Wetland Restoration Area (WRA) (up to 15 November 2011);
� Band drain installation;
� Trial embankment for ground improvement; and
� Site formation (filling)
The Construction Works Programme of the Project is provided in Appendix B. The general layout plan of
the Project site is shown in Figure 1.1.
On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference
to the EP Condition 3.3 to 3.5. In accordance with EP Condition 3.6, the evidence of completion has been
certified by the ET Leader and verified by the IEC before submitting to the Director of Environmental
Protection (the Director).
1.4 Summary of EM&A Requirements
The EM&A programme requires environmental monitoring of air quality, noise, water quality, ecology and
landscape and visual as specified in the approved EM&A Manual.
A summary of impact EM&A requirements is presented in Table 1.1 below:
1. Introduction
![Page 8: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/8.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
2
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Table 1.1: Summary of Impact EM&A Requirements
Parameters Descriptions Locations Frequencies
24-Hour TSP ASR1, ASR2A, ASR3, ASR4 Once every 6 days Air Quality
1-Hour TSP ASR1, ASR2A, ASR3, ASR4 3 times every 6 days
Noise Leq, 30min NSR1, NSR3, NSR5, NSR7 Weekly
Water Quality
Dissolved Oxygen (DO), temperature, pH, suspended solids
(SS) and Biological Oxygen Demand (BOD)
MP1 to MP6 3 days per week
Birds Within the Project Area and Assessment Area of 500m
Weekly
Dragonflies and Butterflies Within the Project Area and Assessment Area of 500m
Once per month during Mar and Sep to November, and
twice per month during Apr to Aug
Herpetofauna Within the Project Area and Assessment Area of 500m
Once per month during Apr to Nov
Water quality of WRA Wetland Restoration Area
After filling of WRA with water, monthly for in situ water quality and every size months (end of
wet season and end of dry season) for laboratory testing
Ecology
Site Inspections Within the Project Area and Assessment Area of 500m
Weekly
Landscape and Visual
Auditing of protection of existing trees, the transplanting of existing
trees, the creation of new wetland, the planting of new trees and shrubs
and other landscape and visual mitigation measures
CM1 to CM10 and OM1 to OM7 within the Project Area
Site inspections once every two weeks during construction phase; once every two months
during operational phase
The Environmental Quality Performance Limits for air quality, noise and water quality are shown in
Appendix C.
1.5 Recommended Mitigation Measures
The EM&A programme followed the recommended mitigation measures in the EM&A manual. The EM&A
requirements as well as the summary of implementation status of the environmental mitigation measures
are provided in Appendix F. In particular, the following mitigation measures were brought to attention
during the site audits during the reporting period:
Air Quality
• All stockpiles should be covered by tarpaulin or kept wet by water spraying;
• All vehicles should be washed to remove any dusty materials before leaving the construction sites;
• the portion of road leading the construction site that is within 30m of a designated vehicle entrance
or exit should be kept clear of dusty materials;
• Sufficient water spraying should be provided at haul road to reduce dust emission; and
• Ensure proper functioning of the wheel wash facility.
![Page 9: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/9.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
3
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Noise
• Mobile plant should be sited as far away from NSRs as possible;
• Plant known to emit noise strongly in one direction should be orientated to direct noise away from
the NSRs; and
• The construction activities should be better scheduled to reduce noise nuisance.
Water Quality
• Water accumulated in the site (including water inside drip trays) should be cleared frequently;
• Ensure proper functioning of the wastewater treatment facility;
• Silt and debris should be removed from the temporary drainage channel regularly; and
• Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be
filled with suitable materials.
Waste management
• Reuse the excavated materials as far as practical to reduce the amount of waste disposal;
• Ensure drip trays are provided for chemical containers to prevent leakage or soil contamination;
• All plants and vehicles should be properly maintained to prevent oil leakage;
• Oil stains on soil should be cleared by disposal of contaminated soil; and
![Page 10: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/10.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
4
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
2.1 Air Quality Monitoring
Results and graphical plots of 1-hour TSP and 24-hr TSP at the four monitoring locations are summarised
in are shown in Appendix D. The Action levels of 1-hr TSP were exceeded for all the monitoring events on
7 December 2010 at the 4 air quality monitoring stations.
The weather conditions in the reporting period were generally fine and sunny with relatively lower humidity
and occasional strong wind. For details of wind speed and direction during the monitoring period, please
refer to the Monthly EM&A reports.
2.2 Construction Noise Monitoring
The construction noise monitoring results and graphical plots are shown in Appendix D. No exceedance
(Action/Limit Level) of construction noise was recorded in the reporting period.
2.3 Water Quality Monitoring
The water quality monitoring results and the graphical plots of the monitoring data are shown in Appendix
D.
Exceedances of pH, DO, turbidity and SS were observed. For MP1 to MP3, there were frequent
exceedances of action and limit levels for pH. There were a few occasions of exceedance of action and
limit levels of SS and turbidity at MP2 while two exceedances of limit levels of DO were found at MP3 in
December 2010. On the other hand, exceedances of pH were observed at MP4 to MP6 representing the
ditch at the north of the site from early December 2010 onward. For MP5, there was one occasion of
exceedance of action level of turbidity on 24 November 2010.
2.4 Ecological Monitoring
2.4.1 Monitoring of Birds
Monitoring was undertaken following the survey methodology in the EM&A Manual. The Wetland
Restoration Area (hereafter WRA) was also surveyed during the reporting period as the area became
accessible and site formation works for WRA has been completed. Low intensity monitoring of the WRA
was undertaken (on a monthly basis) to monitor faunal usage of the newly formed cells; monitoring
intensity will follow that outlined in the EM&A Manual at the completion of the WRA. A transect was
followed in the bird surveys (see Figure 2.1).
All bird species of conservation importance and/or wetland dependent were identified and enumerated.
Flying birds were not recorded unless they were foraging and associated with the habitat (such as swifts).
Further, notable bird observations during other surveys were also recorded. A summary of survey data is
provided in Appendix E.
A total of 42, 52 and 39 bird species (30, 34 and 21 in WRA) were recorded in the survey area in
November, December 2010 and January 2011 respectively. Among the birds surveyed in the WRA, 17, 27
2. Summary of Monitoring Results
![Page 11: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/11.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
5
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
and 18 bird species of conservation importance and/or wetland-dependence were recorded in November,
December 2010 and January 2011 respectively.
In January 2011, species prone to disturbance were also recorded regularly on-site; these include three
duck species and five ardeid species. It is also of note that high numbers of ardeids (comprising mainly
Little Egret and one Black-faced Spoonbill) were recorded roosting in one of the adjacent fish ponds (Pond
52), indicating that disturbance from the construction site was not an issue.
Species and numbers recorded in this survey period are typical of fish pond area during the winter months
indicating that birds in the area are not presently being adversely affected by the construction of the
Wetland Restoration Area.
2.4.2 Monitoring of Herpetofauna
One day-time herpetofauna survey was conducted in November 2010. No amphibian species or reptile
species were recorded in the survey period.
One Red-eared Slider Trachemys scripta was found in the ponds within the survey area during the bird
survey conducted on the 20 November. This species is widely disturbed in Hong Kong and is exotic to
Hong Kong.
A summary of the survey findings are provided in Appendix E.
2.4.3 Monitoring of Dragonfly and Butterfly
Monitoring of dragonflies and butterflies was conducted once in November 2010. A total of nine dragonfly
species and ten butterfly species were recorded, and eight dragonfly species and four butterfly species
were recorded in the WRA. All species recorded were common and widespread and recorded in low to very
low numbers.
No dragonfly and butterfly surveys were scheduled in the December 2010 and January 2011. A summary
of the survey findings are provided in Appendix E.
2.4.4 Monitoring of Mammal
Monitoring of mammal was conducted concurrently with other surveys. No mammals were recorded in the
survey period.
2.5 Landscape and Visual Monitoring
The audit was undertaken with references to the specific mitigation measures recommended in Section
10.2 of the EM&A Manual and the audit results are summarized as below:
Table 2.1: Construction Audit Summary on Landscape and Visual
Area of Works Items to be Monitored
![Page 12: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/12.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
6
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Works Area The boundaries of the works area have been established on site in accordance
with the contract documents and approved plans (EP), and the limit of current
heavy construction activity is now confined to within the site hoardings (North
side of the site / access road) and the noise barriers (other sides of the site).
Minor works such as horticultural maintenance of the planting and transplanted
trees, and boundary fence repair was proceeding along the Royal Palms - Palm
Springs boundary.
No construction works were observed to have exceeded the site boundaries.
Moreover, no construction was carried out at the wetland restoration area after
15 November 2010.
Protection of all trees and woodland blocks to be retained
Trees to be retained within the site, located northeast boundary alongside
wetland restoration area, have been identified and protected by temporary
protective fencing.
Streams The works site is encircled by a berm to intercept surface water and prevent it
from washing off into any of the neighboring sites. Surface water is collected
within the site in a temporary drainage channel. Gravels beds and barriers have
been installed to filter site runoff, sedimentation tanks provided to enable
primary treatment before discharge to mains drains.
Clearance of existing vegetation
Site clearance was completed prior to the commencement of construction. A
bed of existing Phragmites reeds which have been retained within a fenced off
area at the centre of the site and some reed clumps have been reused in the
vegetation of the wetland restoration area.
Transplanting of trees
Tree transplanting has been completed, with the trees relocated to various
points within the planting strip along the southern boundary of the site, outside
the noise barrier. The trees continue to re-establish well.
Topsoil stripping Suitable pond bund and pond bottom material excavated and stockpiled from
the original site has now been re-used in the formation of the wetland areas.
Active dust suppression measures are still being adopted along internal site
access tracks.
New buildings No new permanent buildings have yet been constructed on site.
Boundaries Hoardings have been erected along most of the boundaries of the site.
Installation of new fence between the future residential sites and the constructed
wetland area is complete. Fence has been being painted green to match with
the surrounding vegetated environment.
Noise Barrier Noise barriers have been installed along the southern and western boundaries
of the site in accordance with the contract requirements.
The noise barrier design complies with the mitigation requirements, with upper 6
to 7m portion of the barrier being made from a translucent material with green
tinted (to match with the environment). Supporting GMS structure, likewise, has
been painted green.
Night-time lighting No night-time works were reported to have been carried out during the
monitoring period.
![Page 13: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/13.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
7
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Landscape and wetland treatments
Continuous belt of screen planting along the southern and western boundaries
of the site has been completed. The formation, soiling and water control
structures for all cells of the wetland restoration area has been completed. Rain
water has partially filled some wetland cells. The clumps of Phragmites australis
reeds from the original site have been successively translocated to the edge of
the ponds in wetland restoration area.
No construction was carried out at the wetland restoration area after 15
November 2010.
Soiling The soiling for the advance planting strip has been completed. Some bricks
have been installed to create a stronger edge of planting bed and to prevent soil
erosion. The soil placement and grading for the wetland restoration area is
complete.
Plant supply The plant material used for the Advance Planting Strip along the southern and
western boundaries of the site are all common species and came from
commercial sources.
Details of the procurement of special plant material for the wetland areas are to
be provided in Spring 2011, when nursery supplies become available.
Planting The total number of trees that will reach a minimum of 10m in the advance
planting strip meet the contract requirements. The tree species are all from the
approved list. This planting should achieve the required screening effect.
Health condition of recently transplanted trees (Eucalyptus) should be monitored
closely and identified die-back trees may need to be replanted.
Overhanging trees from adjacent properties had been cut back to allow more
light to the shrubs within the Advance Planting Strip. The overhanging trees will
need to be pruned regularly if situation is allowed. Replacement or repairing
works should be carried for those shrubs of poor health.
Establishment Works
The advance planting, the compensatory planting and the transplanted trees
have not yet been hand over for maintenance, the planting works are under
supervision onsite to ensure that the requirements of the approved planting
proposal are met. The advance planting is currently being maintained by the
landscape sub-contractor.
![Page 14: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/14.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
8
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
3.1 Site Inspection
The ET had carried out construction phase weekly site inspections on 3, 10, 19 and 26 November 2010; 1,
10, 15, 21 and 30 December 2010; and 5, 12, 19, 26 and 31 January 2011. All observations have been
recorded in the site inspection checklist and passed to the Contractor together with the appropriate
recommended mitigation measures where necessary.
3.2 Solid and Liquid Waste Management Status
The Contractor has been registered as a chemical waste producer for the Project. Construction and
demolition (C&D) material sorting was carried out on site. A sufficient number of receptacles were available
for general refuse collection.
As advised by the Contractor, 0 tonnes C&D material were generated on site and disposed off at Public Fill
Reception Facilities at Tuen Mun Area 38 during the period. No metals was generated and collected by
registered recycling collector. No paper cardboard packing and plastic were generated on site and
collected by registered recycling collector. No chemical waste was generated and collected by licensed
chemical waste collector. 22.3 tonnes of other types of wastes (e.g. general refuse) was generated on site
and disposed of at North East New Territories (NENT) Landfill.
The Contractor is advised to maintain on site waste sorting and recording system and maximize
reuse/recycling of C&D wastes.
3. Environmental Site Inspection and Audit
![Page 15: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/15.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
9
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
4.1 Record on Non-compliance of Action and Limit Levels
4.1.1 Record of Non-compliance
The Action levels of 1-hr TSP were exceeded for all the monitoring events on 7 December 2010 at the 4 air
quality monitoring stations.
There is no breach of Action or Limit Levels for Noise monitoring in the reporting period.
Exceedances of Action and Limit Levels were recorded for Water Quality at MP1, MP2, MP3, MP4, MP5
and MP6 on different monitoring dates.
Exceedances of pH, DO, turbidity and SS were observed. For MP1 to MP3, there were frequent
exceedances of action and limit levels for pH. There were a few occasions of exceedance of action and
limit levels of SS and turbidity at MP2 while two exceedances of limit levels of DO were found at MP3 in
December 2010. On the other hand, exceedances of pH were observed at MP4 to MP6 representing the
ditch at the north of the site from early December 2010 onward. For MP5, there was one occasion of
exceedance of action level of turbidity on 24 November 2010.
4.1.2 Constructional Impacts on Water Quality
In order to determine the constructional impacts on water quality, the suspended solids level, which is a
good indicator of the quality of effluent from construction site, is selected for assessment. The average
value of suspended solids (SS) for water quality monitoring stations (MP1 – MP6) during baseline
monitoring and construction phase monitoring for the reporting period are listed in Table 4.1 below.
Table 4.1: Comparison of monitoring data of Suspended Solids
Average levels of Suspended Solids (mg/L)
Monitoring Stations During Baseline Monitoring
During Construction Phase Monitoring for the reporting period
Within 130% of mean value of Baseline data?
MP1 103.5 45.9 Yes
MP2 60.1 53.5 Yes
MP3 49.5 20.5 Yes
MP4 36.9 24.1 Yes
MP5 47.7 28.8 Yes
MP6 54.1 29.3 Yes
The average levels of suspended solids during the reporting period were within 130% of the baseline
values. Although there were exceedances of water quality parameters, the above statistics show that the
water quality during the reporting period has not significantly worsen when compared with the baseline
condition.
It was noted that during the reporting period, all the water quality parameters monitored have been
influenced by the natural environment and other external factors and exceedances of criteria were resulted.
The exceedances have been investigated and are described in below section.
4. Report on Non-compliance and Complaints
![Page 16: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/16.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
10
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
4.1.3 Exceedance Investigations
Air Quality
From investigation, the Contractor implemented air quality mitigation measures as recommended in EIA
report which include paving the vehicle washing area and site entrance, and keeping clear of the portion of
road leading the construction site from dusty materials, limiting vehicle speed to below 10 kph except on
completed access roads, and washing every vehicle to remove any dusty materials from its body and
wheels before leaving the construction sites. During the dry season, the Contractor has also made use of
the excavated fish pond clay to mix with the other imported soil materials to form the top layer of the works
area. The mixed soil layer was able to maintain higher moisture content and it generated less fugitive dust
from observations of the site inspection. In addition, water spraying has been provided by the Contractor at
various locations in the site on 7 Dec 2010 from photo record, including works area and haul road, to
further suppress dust.
The possible causes of exceedances have been investigated and reported to the IEC during construction
phase monitoring. From the record of the Hong Kong Observatory, there was moderate to strong wind on 7
Dec 2010. The prevailing wind direction became north to northeast starting from 6 Dec 2010 and the
direction was unchanged at the time of monitoring. Due to the close proximity of the site to the border with
mainland China and the unfavourable wind direction, it was believed that the wind blowing from north has
carried suspended particulates from Shenzhen and caused a short term deterioration of air quality. Record
of 24-hr TSP on 7 Dec 2010 showed that the average daily dust level remained at normal level (the 24-hr
TSP ranged from 79 to 93 µg/m3 for the 4 stations).
Consider the mitigation measures undertaken and the adverse wind condition, the exceedances were
considered not due to construction works.
Water Quality
From investigation, the Contractor has implemented water quality mitigation measures as recommended in
the EIA report, including the provision of temporary drainage facility and associated treatment facility. Sand
bags are in place in the temporary drainage channel to enhance the desilting efficiency. The Contractor
further enhanced the water quality mitigation measures by erecting several segments of rock bunds at the
discharge outlet to avoid site runoff draining directly to the northern ditches.
The possible causes of exceedances have been investigated and reported to the IEC during construction
phase monitoring. The exceedance investigations have also been included in the monthly EM&A report and
some of them are extracted and summarised in Table 4.1. The causes of some of the exceedances were
unknown but all of them were considered not related to the project. For detail, please refer to the previous
monthly EM&A reports.
Table 4.2: Summary of exceedance investigations
Descriptions of exceedances
Possible causes Exceedance related to project?
Exceedance of pH at MP1, MP2
The exceedance may have been caused by natural variations or other unknown factors.
No, as there was no direct discharge from the site to the ditch where MP1 and MP2 are located.
Exceedance of turbidity and SS on 6 and 15 Dec 2010 and turbidity on 22
The exceedance may have been caused by natural variations or other unknown factors such as high fish activities.
Ditto.
![Page 17: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/17.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
11
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Descriptions of exceedances
Possible causes Exceedance related to project?
Dec 2010 at MP2
Exceedances of pH and DO at MP3 in Dec 2010
The exceedance maybe due to natural variation or other unknown factors such as pond fish culture activities.
No, noting that the fish pond (MP3) was being separated from the construction site by the WRA since November 2010.
Exceedance pH at MP4, MP5 and MP6
The exceedance may have been caused by natural variations or other unknown factors.
No, as there was also only small amount of site runoff generated and discharged in the dry season and considered the similar or lower pH compared with other monitoring stations.
Exceedance of turbidity at MP5 on 24 Nov 2010
The increase in turbidity at MP5 was due to some unknown factors.
No, since SS was not exceeded.
Conclusively, all of the exceedances were caused by external factors including natural variation and other
unknown factors such as pond fish culture activities. Moreover, as noted by monitoring team during on-site
sampling, no direct muddy water discharge was observed from the site. The exceedances were considered
not due to construction works.
4.2 Record on Environmental Complaints received
No environmental complaint was received this month.
4.3 Follow-up actions taken
Although it is considered that the exceedances were not related to the Project, the Contractor was
reminded to implement the air and water quality mitigation measures in accordance with the
recommendation stated in Section 3.6.1 and 5.6.1 – 5.6.4 of the EIA Report respectively as far as
practicable and regular spot check would be conducted on the nearby discharge by Contractor and inform
ET for investigation.
During the dry season, the Contractor has made use of the excavated fish pond clay to mix with the other
imported soil materials to form the top layer of the works area. The mixed soil layer was able to maintain
higher moisture content and it generated less fugitive dust from observations of the site inspection.
To cater for the site runoff in the previous months, the Contractor has further enhanced the water quality
mitigation measures by erecting several segments of rock bunds at the discharge outlet to avoid site runoff
draining directly to the northern ditches.
It was also advised that the operation condition of the Wastewater Treatment Facilities should be checked
regularly to ensure proper functioning of the plant and good quality of effluent discharge.
![Page 18: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/18.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
12
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
5.1 Construction Works for the Coming Months
The major site works to be commissioned in the coming three months include:
� Installation of band drain;
� Trial embankment for ground improvement; and
� Site formation (Filling)
5.2 Key Issues for the Coming Months
Key issues to be considered in the coming three months include:
� Generation of dust from activities on-site (esp. stockpiling for Trial Embankment);
� Noise impact from operating equipment and machinery on-site;
� Generation of site surface runoffs and wastewater from activities on-site;
� Sorting, recycling, storage and disposal of general refuse and construction waste from activities on-
site; and
� Management of chemicals and avoidance of oil spillage on-site.
5.3 Conclusions and Recommendations
5.3.1 Conclusions
The EM&A programme as recommended in the EM&A manual has been undertaken in the reporting
period.
Monitoring of Air Quality, Noise, Water Quality, Ecology and Landscape and Visual impacts due to the
Project was under way. In particular, the 1-hr TSP, 24-hr TSP, noise level (as Leq) and water quality
parameters (such as pH, DO and SS) under monitoring have been checked against established Action and
Limit levels.
The Action levels of Air Quality (1-hr TSP) were exceeded on 7 Dec 2010 at the four monitoring stations.
Investigations on the exceedance showed that the unfavourable wind direction on the date of exceedance
may have carried pollutants from Shenzhen and caused short term deterioration of air quality in the project
area. The exceedance was not considered to be related to the project.
There was no breach of Action or Limit levels for Noise (as Leq) in the reporting month.
Action and Limit Level exceedances of pH, DO, turbidity and SS were recorded at water quality monitoring
stations. However, Investigations on the exceedance showed that the exceedances were not related to the
Project and may have been due to external factors including natural variations and other unknown factors
such as pond fish culture activities and high fish activities in the ditch.
5. Future Key Issues
![Page 19: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/19.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
13
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
5.3.2 Recommendations
With considerations on the construction activities and environment, the following recommendations were
provided:
Air Quality
• All stockpiles should be covered by tarpaulin or kept wet by water spraying;
• All vehicles should be washed to remove any dusty materials before leaving the construction sites;
• the portion of road leading the construction site that is within 30m of a designated vehicle entrance or exit
should be kept clear of dusty materials;
• Sufficient water spraying should be provided at haul road to reduce dust emission; and
• Ensure proper functioning of the wheel wash facility.
Noise
• Mobile plant should be sited as far away from NSRs as possible;
• Plant known to emit noise strongly in one direction should be orientated to direct noise away from the NSRs;
and
• The construction activities should be better scheduled to reduce noise nuisance.
Water Quality
• Water accumulated in the site (including water inside drip trays) should be cleared frequently;
• Ensure proper functioning of the wastewater treatment facility; and
• Silt and debris should be removed from the temporary drainage channel regularly.
Waste management
• Reuse the excavated materials as far as practical to reduce the amount of waste disposal;
• Ensure drip trays are provided for chemical containers to prevent leakage or soil contamination;
• All plants and vehicles should be properly maintained to prevent oil leakage; and
• Oil stains on soil should be cleared by disposal of contaminated soil.
![Page 20: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/20.jpg)
![Page 21: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/21.jpg)
Legends:
Air Quality Monitoring
Stations
Noise Monitoring Stations
Water Quality Monitoring
Stations
Site Boundary
HENG SHUNG CONSTRUCTION CO. LTD
PROPOSED COMPREHENSIVE DEVELOPMENT
AT WO SHANG WAI, YUEN LONG
General Site Layout and
Locations of Monitoring
Stations
Figure 1.1
NSR1 (Construction Phase)
NSR3
NSR5 NSR7
NSR1 ASR1
ASR4
ASR3
ASR2A
![Page 22: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/22.jpg)
Figure 2.1
![Page 23: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/23.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Contact information:
Company Position Name Telephone / Mobile
Profit Point Enterprises
Limited
Project Manager Mr Kelvin Lau 2908 8114
Heng Shung Construction
Co. Ltd. (The Contractor)
Assistant Construction Manager Ms Lynne Hung 2908 2391
Heng Shung Construction
Co. Ltd. (The Contractor)
Site Agent Mr Poon Man Ho 9426 3533
Heng Shung Construction
Co. Ltd. (The Contractor)
Environmental Officer Mr. Lun Ho Yin 9866 7497
ENVIRON Hong Kong Ltd
(IEC)
Independent Environmental
Checker
Mr David Yeung 3743 0788
Mott MacDonald Hong Kong
Ltd. (ET)
ET Team Leader Ms Florence Yuen 2828 5768
Appendix A. Project Organization Chart
Line of Reporting
Line of Communication
Project Proponent
Profit Point Enterprises Limited
The Contractor
Heng Shung Construction Co. Ltd.
ET Leader
Mott MacDonald Hong Kong Limited
IEC
ENVIRON Hong Kong Limited
Environmental Protection Department
![Page 24: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/24.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
![Page 25: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/25.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Appendix B. Tentative Construction Programme
![Page 26: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/26.jpg)
ID Task Name Working Start Finish
0 Wo Shang Wai Construction Phase 1205days
Tue 01/06/10 Fri 30/05/14
1
2 Install Band Drain 317 days Tue 01/06/10 Thu 30/06/11
3 Trial Embankment 300 days Thu 17/06/10 Sat 25/06/11
4 Site Formation 1029 days Mon 03/01/11 Fri 30/05/14
5 Filling 899 days Mon 03/01/11 Mon 30/12/13
6 Excavations for construction of footing 833 days Mon 05/09/11 Fri 30/05/14
Install Band Drain
Trial Embankment
Filling
Excavations for construction of footing
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q22011 2012 2013 20
Task Milestone Summary
Wo Shang Wai Construction Works Programme
Page 1
Project : Wo Shang WaiRevision : EPrint Date : Mon 14/02/11
![Page 27: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/27.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Air Quality
Action and Limit Levels for 24-hour TSP
Monitoring Station Action Level (µµµµg/m3) Limit Level (µµµµg/m3)
ASR1 226 260
ASR2A 213 260
ASR3 205 260
ASR4 237 260
Action and Limit Levels for 1-hour TSP
Monitoring Station Action Level (µµµµg/m3) Limit Level (µµµµg/m3)
ASR1 378 500
ASR2A 357 500
ASR3 358 500
ASR4 372 500
Noise
Action and Limit Levels for Construction Noise
Time Period Action Level Limit Level
NSR1, NSR3, NSR5, NSR7
0700 – 1900 hours on normal weekdays
When one documented complaint is received from any one of the sensitive receivers
75 dB(A)
Water Quality
Action and Limit Levels for Water Quality
Parameters DO in mg/L Turbidity in NTU SS in mg/L pH
Action Level
Limit Level
Action Level
Action Level
Action Level
Limit Level
Action Level
Limit Level
MP1 1.23 1.17 173 177 231 299
MP2 1.04 0.89 132 163 170 209
MP3 6.85 6.65 64 67 65 66
MP4 3.91 3.82 60 64 50 53
MP5 4.13 3.87 81 84 66 69
MP6 4.61 4.52 94 96 75 75
< 5.5 or > 7.5
< 4.0 or > 8.0
Appendix C. Action and Limit Levels for Construction Phase
![Page 28: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/28.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
![Page 29: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/29.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Appendix D. Summary and Graphical plots of the monitoring results
![Page 30: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/30.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
![Page 31: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/31.jpg)
Page 1 of 28
Air Quality (1-hr TSP)
Station ASR1
Start Finish TSP
Concentration Weather Action Level Limit Level
Date Time Time (µg/m3) Condition (µg/m
3) (µg/m
3)
3-Nov-10 8:52 9:52 320 Sunny 378 500 3-Nov-10 9:52 10:52 305 Sunny 378 500
3-Nov-10 10:52 11:52 288 Sunny 378 500
9-Nov-10 9:12 10:12 180 Sunny 378 500
9-Nov-10 10:12 11:12 183 Sunny 378 500
9-Nov-10 11:12 12:12 182 Sunny 378 500
15-Nov-10 9:06 10:06 224 Sunny 378 500
15-Nov-10 10:06 11:06 204 Sunny 378 500
15-Nov-10 11:06 12:06 219 Sunny 378 500
19-Nov-10 9:11 10:11 269 Sunny 378 500
19-Nov-10 10:11 11:11 258 Sunny 378 500
19-Nov-10 11:11 12:11 268 Sunny 378 500
25-Nov-10 9:13 10:13 210 Sunny 378 500
25-Nov-10 10:13 11:13 215 Sunny 378 500
25-Nov-10 11:13 12:13 199 Sunny 378 500
1-Dec-10 9:06 10:06 197 Sunny 378 500
1-Dec-10 10:06 11:06 211 Sunny 378 500
1-Dec-10 11:06 12:06 235 Sunny 378 500
7-Dec-10 9:04 10:04 454 Sunny 378 500
7-Dec-10 10:04 11:04 422 Sunny 378 500
7-Dec-10 11:04 12:04 456 Sunny 378 500
13-Dec-10 9:17 10:17 115 Fine 378 500
13-Dec-10 10:17 11:17 104 Fine 378 500
13-Dec-10 11:17 12:17 108 Fine 378 500
17-Dec-10 9:19 10:19 128 Sunny 378 500
17-Dec-10 10:19 11:19 120 Sunny 378 500
17-Dec-10 11:19 12:19 121 Sunny 378 500
23-Dec-10 9:11 10:11 248 Sunny 378 500
23-Dec-10 10:11 11:11 325 Sunny 378 500
23-Dec-10 11:11 12:11 318 Sunny 378 500
29-Dec-10 9:14 10:14 166 Sunny 378 500
29-Dec-10 10:14 11:14 158 Sunny 378 500
29-Dec-10 11:14 12:14 150 Sunny 378 500
4-Jan-11 9:14 10:14 190 Cloudy 378 500
4-Jan-11 10:14 11:14 182 Cloudy 378 500
4-Jan-11 11:14 12:14 177 Cloudy 378 500
10-Jan-11 9:03 10:03 315 Sunny 378 500
10-Jan-11 10:03 11:03 327 Sunny 378 500
10-Jan-11 11:03 12:03 313 Sunny 378 500
14-Jan-11 9:13 10:13 359 Sunny 378 500
14-Jan-11 10:13 11:13 344 Sunny 378 500
14-Jan-11 11:13 12:13 356 Sunny 378 500
20-Jan-11 9:12 10:12 332 Sunny 378 500
20-Jan-11 10:12 11:12 345 Sunny 378 500
20-Jan-11 11:12 12:12 337 Sunny 378 500
26-Jan-11 9:06 10:06 283 Sunny 378 500
26-Jan-11 10:06 11:06 264 Sunny 378 500
26-Jan-11 11:06 12:06 266 Sunny 378 500
Min. 41 Max. 327
Average 116
Values Bold indicate Action Level exceedance.
![Page 32: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/32.jpg)
Page 2 of 28
Air Quality (1-hr TSP)
Station ASR2A
Start Finish TSP
Concentration Weather Action Level Limit Level
Date Time Time (µg/m3) Condition (µg/m
3) (µg/m
3)
3-Nov-10 13:24 14:24 188 Sunny 378 500 3-Nov-10 14:24 15:24 194 Sunny 378 500
3-Nov-10 15:24 16:24 181 Sunny 378 500
9-Nov-10 13:32 14:32 133 Sunny 378 500
9-Nov-10 14:32 15:32 137 Sunny 378 500
9-Nov-10 15:32 16:32 126 Sunny 378 500
15-Nov-10 13:20 14:20 155 Sunny 378 500
15-Nov-10 14:20 15:20 147 Sunny 378 500
15-Nov-10 15:20 16:20 144 Sunny 378 500
19-Nov-10 13:27 14:27 206 Sunny 378 500
19-Nov-10 14:27 15:27 202 Sunny 378 500
19-Nov-10 15:27 16:27 211 Sunny 378 500
25-Nov-10 13:30 14:30 154 Sunny 378 500
25-Nov-10 14:30 15:30 151 Sunny 378 500
25-Nov-10 15:30 16:30 146 Sunny 378 500
1-Dec-10 13:19 14:19 159 Sunny 378 500
1-Dec-10 14:19 15:19 165 Sunny 378 500
1-Dec-10 15:19 16:19 169 Sunny 378 500
7-Dec-10 13:10 14:10 376 Sunny 378 500
7-Dec-10 14:10 15:10 391 Sunny 378 500
7-Dec-10 15:10 16:10 405 Sunny 378 500
13-Dec-10 13:26 14:26 79 Fine 378 500
13-Dec-10 14:26 15:26 86 Fine 378 500
13-Dec-10 15:26 16:26 83 Fine 378 500
17-Dec-10 13:25 14:25 105 Sunny 378 500
17-Dec-10 14:25 15:25 112 Sunny 378 500
17-Dec-10 15:25 16:25 117 Sunny 378 500
23-Dec-10 13:25 14:25 252 Sunny 378 500
23-Dec-10 14:25 15:25 241 Sunny 378 500
23-Dec-10 15:25 16:25 227 Sunny 378 500
29-Dec-10 13:19 14:19 67 Sunny 378 500
29-Dec-10 14:19 15:19 84 Sunny 378 500
29-Dec-10 15:19 16:19 97 Sunny 378 500
4-Jan-11 13:05 14:05 174 Cloudy 357 500
4-Jan-11 14:05 15:05 162 Cloudy 357 500
4-Jan-11 15:05 16:05 158 Cloudy 357 500
10-Jan-11 13:10 14:10 275 Sunny 357 500
10-Jan-11 14:10 15:10 287 Sunny 357 500
10-Jan-11 15:10 16:10 299 Sunny 357 500
14-Jan-11 13:22 14:22 307 Sunny 357 500
14-Jan-11 14:22 15:22 315 Sunny 357 500
14-Jan-11 15:22 16:22 319 Sunny 357 500
20-Jan-11 13:13 14:13 297 Sunny 357 500
20-Jan-11 14:13 15:13 301 Sunny 357 500
20-Jan-11 15:13 16:13 313 Sunny 357 500
26-Jan-11 13:17 14:17 261 Sunny 357 500
26-Jan-11 14:17 15:17 245 Sunny 357 500
26-Jan-11 15:17 16:17 242 Sunny 357 500
Min. 67 Max. 405
Average 201
Values Bold indicate Action Level exceedance.
![Page 33: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/33.jpg)
Page 3 of 28
Air Quality (1-hr TSP)
Station ASR3
Start Finish TSP
Concentration Weather Action Level Limit Level
Date Time Time (µg/m3) Condition (µg/m
3) (µg/m
3)
3-Nov-10 13:08 14:08 225 Sunny 358 500 3-Nov-10 14:08 15:08 198 Sunny 358 500
3-Nov-10 15:08 16:08 208 Sunny 358 500
9-Nov-10 13:17 14:17 128 Sunny 358 500
9-Nov-10 14:17 15:17 150 Sunny 358 500
9-Nov-10 15:17 16:17 139 Sunny 358 500
15-Nov-10 13:05 14:05 165 Sunny 358 500
15-Nov-10 14:05 15:05 175 Sunny 358 500
15-Nov-10 15:05 16:05 168 Sunny 358 500
19-Nov-10 13:13 14:13 238 Sunny 358 500
19-Nov-10 14:13 15:13 227 Sunny 358 500
19-Nov-10 15:13 16:13 221 Sunny 358 500
25-Nov-10 13:16 14:16 146 Sunny 358 500
25-Nov-10 14:16 15:16 132 Sunny 358 500
25-Nov-10 15:16 16:16 166 Sunny 358 500
1-Dec-10 13:05 14:05 181 Sunny 358 500
1-Dec-10 14:05 15:05 179 Sunny 358 500
1-Dec-10 15:05 16:05 175 Sunny 358 500
7-Dec-10 12:56 13:56 405 Sunny 358 500
7-Dec-10 13:56 14:56 403 Sunny 358 500
7-Dec-10 14:56 15:56 386 Sunny 358 500
13-Dec-10 13:10 14:10 84 Fine 358 500
13-Dec-10 14:10 15:10 85 Fine 358 500
13-Dec-10 15:10 16:10 90 Fine 358 500
17-Dec-10 13:11 14:11 117 Sunny 358 500
17-Dec-10 14:11 15:11 115 Sunny 358 500
17-Dec-10 15:11 16:11 110 Sunny 358 500
23-Dec-10 13:12 14:12 233 Sunny 358 500
23-Dec-10 14:12 15:12 241 Sunny 358 500
23-Dec-10 15:12 16:12 219 Sunny 358 500
29-Dec-10 13:03 14:03 90 Sunny 358 500
29-Dec-10 14:03 15:03 96 Sunny 358 500
29-Dec-10 15:03 16:03 104 Sunny 358 500
4-Jan-11 12:55 13:55 177 Cloudy 358 500
4-Jan-11 13:55 14:55 167 Cloudy 358 500
4-Jan-11 14:55 15:55 183 Cloudy 358 500
10-Jan-11 12:54 13:54 288 Sunny 358 500
10-Jan-11 13:54 14:54 298 Sunny 358 500
10-Jan-11 14:54 15:54 292 Sunny 358 500
14-Jan-11 13:03 14:03 315 Sunny 358 500
14-Jan-11 14:03 15:03 318 Sunny 358 500
14-Jan-11 15:03 16:03 327 Sunny 358 500
20-Jan-11 12:58 13:58 311 Sunny 358 500
20-Jan-11 13:58 14:58 313 Sunny 358 500
20-Jan-11 14:58 15:58 319 Sunny 358 500
26-Jan-11 13:02 14:02 262 Sunny 358 500
26-Jan-11 14:02 15:02 266 Sunny 358 500
26-Jan-11 15:02 16:02 270 Sunny 358 500
Min. 84 Max. 405
Average 211
Values Bold indicate Action Level exceedance.
![Page 34: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/34.jpg)
Page 4 of 28
Air Quality (1-hr TSP)
Station ASR4
Start Finish TSP
Concentration Weather Action Level Limit Level
Date Time Time (µg/m3) Condition (µg/m
3) (µg/m
3)
3-Nov-10 8:58 9:58 277 Sunny 372 500 3-Nov-10 9:58 10:58 319 Sunny 372 500
3-Nov-10 10:58 11:58 299 Sunny 372 500
9-Nov-10 9:21 10:21 185 Sunny 372 500
9-Nov-10 10:21 11:21 174 Sunny 372 500
9-Nov-10 11:21 12:21 177 Sunny 372 500
15-Nov-10 9:21 10:21 248 Sunny 372 500
15-Nov-10 10:21 11:21 259 Sunny 372 500
15-Nov-10 11:21 12:21 242 Sunny 372 500
19-Nov-10 9:18 10:18 223 Sunny 372 500
19-Nov-10 10:18 11:18 222 Sunny 372 500
19-Nov-10 11:18 12:18 214 Sunny 372 500
25-Nov-10 9:18 10:18 190 Sunny 372 500
25-Nov-10 10:18 11:18 172 Sunny 372 500
25-Nov-10 11:18 12:18 169 Sunny 372 500
1-Dec-10 9:10 10:10 145 Sunny 372 500
1-Dec-10 10:10 11:10 155 Sunny 372 500
1-Dec-10 11:10 12:10 174 Sunny 372 500
7-Dec-10 9:10 10:10 413 Sunny 372 500
7-Dec-10 10:10 11:10 422 Sunny 372 500
7-Dec-10 11:10 12:10 417 Sunny 372 500
13-Dec-10 9:22 10:22 96 Fine 372 500
13-Dec-10 10:22 11:22 84 Fine 372 500
13-Dec-10 11:22 12:22 98 Fine 372 500
17-Dec-10 9:28 10:28 116 Sunny 372 500
17-Dec-10 10:28 11:28 110 Sunny 372 500
17-Dec-10 11:28 12:28 114 Sunny 372 500
23-Dec-10 9:16 10:16 305 Sunny 372 500
23-Dec-10 10:16 11:16 297 Sunny 372 500
23-Dec-10 11:16 12:16 290 Sunny 372 500
29-Dec-10 9:18 10:18 136 Sunny 372 500
29-Dec-10 10:18 11:18 142 Sunny 372 500
29-Dec-10 11:18 12:18 105 Sunny 372 500
4-Jan-11 9:19 10:19 135 Cloudy 372 500
4-Jan-11 10:19 11:19 141 Cloudy 372 500
4-Jan-11 11:19 12:19 149 Cloudy 372 500
10-Jan-11 9:09 10:09 284 Sunny 372 500
10-Jan-11 10:09 11:09 302 Sunny 372 500
10-Jan-11 11:09 12:09 298 Sunny 372 500
14-Jan-11 9:21 10:21 348 Sunny 372 500
14-Jan-11 10:21 11:21 345 Sunny 372 500
14-Jan-11 11:21 12:21 351 Sunny 372 500
20-Jan-11 9:16 10:16 346 Sunny 372 500
20-Jan-11 10:16 11:16 337 Sunny 372 500
20-Jan-11 11:16 12:16 334 Sunny 372 500
26-Jan-11 9:10 10:10 245 Sunny 372 500
26-Jan-11 10:10 11:10 251 Sunny 372 500
26-Jan-11 11:10 12:10 242 Sunny 372 500
Min. 84 Max. 422
Average 231
Values Bold indicate Action Level exceedance.
![Page 35: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/35.jpg)
Page 5 of 28
Air Quality (1-hr TSP)
![Page 36: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/36.jpg)
Page 6 of 28
Air Quality (1-hr TSP)
![Page 37: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/37.jpg)
Page 7 of 28
Air Quality (24-hr TSP)
Station ASR1
Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)
Date Time Date Time Initial Final Initial Final
Sampling Time (hrs) Initial Final Average
Conc. (µg/m
3)
Weather Condition
Action Level
Limit Level
3-Nov-10 9:42 4-Nov-10 9:42 2.8259 2.9767 10478.68 10502.68 24.00 1.2000 1.2000 1.2000 87 Sunny 226 260
9-Nov-10 9:54 10-Nov-10 9:54 2.7946 2.9414 10502.68 10526.68 24.00 1.2000 1.2000 1.2000 85 Sunny 226 260
15-Nov-10 9:49 16-Nov-10 9:49 2.8535 2.9975 10526.68 10550.68 24.00 1.2000 1.2000 1.2000 83 Sunny 226 260
19-Nov-10 9:19 20-Nov-10 9:19 2.8574 3.0114 10550.68 10574.68 24.00 1.2600 1.2600 1.2600 85 Sunny 226 260
25-Nov-10 9:57 26-Nov-10 9:57 2.8110 3.0411 10574.68 10598.68 24.00 1.2600 1.2600 1.2600 127 Sunny 226 260
1-Dec-10 9:50 2-Dec-10 9:50 2.8613 3.0226 10598.68 10622.68 24.00 1.2600 1.2600 1.2600 89 Sunny 226 260
7-Dec-10 9:53 8-Dec-10 9:53 2.8641 3.0277 10622.68 10646.68 24.00 1.2600 1.2600 1.2600 90 Sunny 226 260
13-Dec-10 10:03 14-Dec-10 10:03 2.8473 3.0017 10646.68 10670.68 24.00 1.2600 1.2600 1.2600 85 Sunny 226 260
17-Dec-10 9:27 18-Dec-10 9:27 2.8351 3.0077 10670.68 10694.68 24.00 1.2600 1.2600 1.2600 95 Sunny 226 260
23-Dec-10 9:56 24-Dec-10 9:56 2.8459 2.9967 10694.68 10718.68 24.00 1.2600 1.2600 1.2600 83 Sunny 226 260
29-Dec-10 9:59 30-Dec-10 9:59 2.8490 3.0067 10718.68 10742.68 24.00 1.2600 1.2600 1.2600 87 Sunny 226 260
4-Jan-11 9:59 5-Jan-11 9:59 2.8355 2.9969 10742.68 10766.68 24.00 1.2600 1.2600 1.2600 89 Cloudy 226 260
10-Jan-11 9:51 11-Jan-11 9:51 2.8709 3.0227 10766.68 10790.68 24.00 1.2400 1.2400 1.2400 85 Sunny 226 260
14-Jan-11 9:20 15-Jan-11 9:20 2.8055 2.9827 10790.68 10814.68 24.00 1.2400 1.2400 1.2400 99 Sunny 226 260
20-Jan-11 9:55 21-Jan-11 9:55 2.8701 3.0369 10814.68 10838.68 24.00 1.2400 1.2400 1.2400 93 Sunny 226 260
26-Jan-11 9:52 27-Jan-11 9:52 2.8114 2.9874 10838.68 10862.68 24.00 1.2400 1.2400 1.2400 99 Sunny 226 260
Min 83
Max 127
Average 91
![Page 38: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/38.jpg)
Page 8 of 28
Air Quality (24-hr TSP)
Station ASR2A
Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)
Date Time Date Time Initial Final Initial Final
Sampling Time (hrs) Initial Final Average
Conc. (µg/m
3)
Weather Condition
Action Level
Limit Level
3-Nov-10 13:24 4-Nov-10 13:24 2.8449 2.9769 13918.45 13942.45 24.00 1.2500 1.2500 1.2500 73 Sunny 213 260
9-Nov-10 13:32 10-Nov-10 13:32 2.8325 2.9709 13942.45 13966.45 24.00 1.2500 1.2500 1.2500 77 Sunny 213 260
15-Nov-10 13:20 16-Nov-10 13:20 2.8669 2.9981 13966.45 13990.45 24.00 1.2500 1.2500 1.2500 73 Sunny 213 260
19-Nov-10 13:26 20-Nov-10 13:26 2.8844 3.0014 13990.45 14014.45 24.00 1.2500 1.2500 1.2500 65 Sunny 213 260
25-Nov-10 13:30 26-Nov-10 13:30 2.8614 3.0119 14014.45 14038.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260
1-Dec-10 13:19 2-Dec-10 13:19 2.8411 3.0097 14038.45 14062.45 24.00 1.2500 1.2500 1.2500 94 Sunny 213 260
7-Dec-10 13:19 8-Dec-10 13:19 2.8350 2.9968 14062.45 14086.45 24.00 1.2500 1.2500 1.2500 90 Sunny 213 260
13-Dec-10 13:26 14-Dec-10 13:26 2.8047 2.9566 14086.45 14110.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260
17-Dec-10 13:24 18-Dec-10 13:24 2.8570 3.0117 14110.45 14134.45 24.00 1.2500 1.2500 1.2500 86 Sunny 213 260
23-Dec-10 13:25 24-Dec-10 13:25 2.8903 3.0511 14134.45 14158.45 24.00 1.2500 1.2500 1.2500 89 Sunny 213 260
29-Dec-10 13:19 30-Dec-10 13:19 2.8460 2.9967 14158.45 14182.45 24.00 1.2500 1.2500 1.2500 84 Sunny 213 260
4-Jan-11 13:05 5-Jan-11 13:05 2.8490 3.0152 14182.45 14206.45 24.00 1.2500 1.2500 1.2500 92 Cloudy 213 260
10-Jan-11 13:10 11-Jan-11 13:10 2.8473 3.0071 14206.45 14230.45 24.00 1.2800 1.2800 1.2800 87 Sunny 213 260
14-Jan-11 13:21 15-Jan-11 13:21 2.8409 3.0121 14230.45 14254.45 24.00 1.2800 1.2800 1.2800 93 Sunny 213 260
20-Jan-11 13:13 21-Jan-11 13:13 2.8339 2.9925 14254.45 14278.45 24.00 1.2800 1.2800 1.2800 86 Sunny 213 260
26-Jan-11 13:16 27-Jan-11 13:16 2.8527 3.0127 14278.45 14302.45 24.00 1.2400 1.2800 1.2400 90 Sunny 213 260
Min 65
Max 94
Average 84
![Page 39: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/39.jpg)
Page 9 of 28
Air Quality (24-hr TSP)
Station ASR3
Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)
Date Time Date Time Initial Final Initial Final
Sampling Time (hrs) Initial Final Average
Conc. (µg/m
3)
Weather Condition
Action Level
Limit Level
3-Nov-10 13:08 4-Nov-10 13:08 2.8634 3.0061 4140.69 4164.69 24.00 1.2700 1.2700 1.2700 78 Sunny 205 260
9-Nov-10 13:17 10-Nov-10 13:17 2.7997 2.9333 4164.69 4188.69 24.00 1.2700 1.2700 1.2700 73 Sunny 205 260
15-Nov-10 13:05 16-Nov-10 13:05 2.8627 3.0112 4188.69 4212.69 24.00 1.2700 1.2700 1.2700 81 Sunny 205 260
19-Nov-10 13:12 20-Nov-10 13:12 2.8713 3.0047 4212.69 4236.69 24.00 1.2800 1.2800 1.2800 72 Sunny 205 260
25-Nov-10 13:15 26-Nov-10 13:15 2.8336 2.9828 4236.69 4260.69 24.00 1.2800 1.2800 1.2800 81 Sunny 205 260
1-Dec-10 13:04 2-Dec-10 13:04 2.8767 3.0319 4260.69 4284.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260
7-Dec-10 12:55 8-Dec-10 12:55 2.8746 3.0195 4284.69 4308.69 24.00 1.2800 1.2800 1.2800 79 Sunny 205 260
13-Dec-10 13:09 14-Dec-10 13:09 2.8996 3.0290 4308.69 4332.69 24.00 1.2800 1.2800 1.2800 70 Sunny 205 260
17-Dec-10 13:11 18-Dec-10 13:11 2.8814 3.0400 4332.69 4356.69 24.00 1.2800 1.2800 1.2800 86 Sunny 205 260
23-Dec-10 13:12 24-Dec-10 13:12 2.8667 3.0211 4356.69 4380.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260
29-Dec-10 13:02 30-Dec-10 13:02 2.8334 2.9886 4380.69 4404.69 24.00 1.2800 1.2800 1.2800 84 Sunny 205 260
4-Jan-11 12:54 5-Jan-11 12:54 2.8521 3.0117 4404.69 4428.69 24.00 1.2800 1.2800 1.2800 87 Cloudy 205 260
10-Jan-11 12:54 11-Jan-11 12:54 2.8864 3.0396 4428.69 4452.69 24.00 1.2000 1.2000 1.2000 89 Sunny 205 260
14-Jan-11 13:03 15-Jan-11 13:03 2.8229 2.9960 4452.69 4476.69 24.00 1.2000 1.2000 1.2000 100 Sunny 205 260
20-Jan-11 12:57 21-Jan-11 12:57 2.8525 3.0072 4476.69 4500.69 24.00 1.2000 1.2000 1.2000 90 Sunny 205 260
26-Jan-11 13:01 27-Jan-11 13:01 2.8339 2.9966 4500.69 4524.69 24.00 1.2000 1.2000 1.2000 94 Sunny 205 260
Min 70
Max 100
Average 83
![Page 40: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/40.jpg)
Page 10 of 28
Air Quality (24-hr TSP)
Station ASR4
Start Finish Filter Weight (g) Elapsed Time Reading Flow Rate (m3/min)
Date Time Date Time Initial Final Initial Final
Sampling Time (hrs) Initial Final Average
Conc. (µg/m
3)
Weather Condition
Action Level
Limit Level
3-Nov-10 8:51 4-Nov-10 8:51 2.8371 2.9921 11339.86 11363.86 24.00 1.1500 1.1500 1.1500 94 Sunny 237 260
9-Nov-10 9:12 10-Nov-10 9:12 2.8063 2.9577 11363.86 11387.86 24.00 1.1500 1.1500 1.1500 91 Sunny 237 260
15-Nov-10 9:06 16-Nov-10 9:06 2.8808 3.0191 11387.86 11411.86 24.00 1.1500 1.1500 1.1500 84 Sunny 237 260
19-Nov-10 9:12 20-Nov-10 9:12 2.8309 2.9912 11411.86 11435.86 24.00 1.1800 1.1800 1.1800 94 Sunny 237 260
25-Nov-10 9:12 26-Nov-10 9:12 2.8624 3.0059 11435.86 11459.86 24.00 1.1800 1.1800 1.1800 84 Sunny 237 260
1-Dec-10 9:05 2-Dec-10 9:05 2.8234 2.9716 11459.86 11483.86 24.00 1.1800 1.1800 1.1800 87 Sunny 237 260
7-Dec-10 9:03 8-Dec-10 9:03 2.8914 3.0494 11483.86 11507.86 24.00 1.1800 1.1800 1.1800 93 Sunny 237 260
13-Dec-10 9:16 14-Dec-10 9:16 2.8671 3.0011 11507.86 11531.86 24.00 1.1800 1.1800 1.1800 79 Sunny 237 260
17-Dec-10 9:18 18-Dec-10 9:18 2.8214 2.9901 11531.86 11555.86 24.00 1.1800 1.1800 1.1800 99 Sunny 237 260
23-Dec-10 9:11 24-Dec-10 9:11 2.8735 3.0346 11555.86 11579.86 24.00 1.1800 1.1800 1.1800 95 Sunny 237 260
29-Dec-10 9:14 30-Dec-10 9:14 2.8751 3.0306 11579.86 11603.86 24.00 1.1800 1.1800 1.1800 92 Sunny 237 260
4-Jan-11 9:13 5-Jan-11 9:13 2.8241 2.9962 11603.86 11627.86 24.00 1.1800 1.1800 1.1800 101 Cloudy 237 260
10-Jan-11 9:03 11-Jan-11 9:03 2.8221 2.9759 11627.86 11651.86 24.00 1.2300 1.2300 1.2300 87 Sunny 237 260
14-Jan-11 9:12 15-Jan-11 9:12 2.8513 3.0201 11651.86 11675.86 24.00 1.2300 1.2300 1.2300 95 Sunny 237 260
20-Jan-11 9:11 21-Jan-11 9:11 2.8762 3.0127 11675.86 11699.86 24.00 1.2300 1.2300 1.2300 77 Sunny 237 260
26-Jan-11 9:06 27-Jan-11 9:06 2.8227 2.9861 11699.86 11723.86 24.00 1.2300 1.2300 1.2300 92 Sunny 237 260
Min 77
Max 101
Average 90
![Page 41: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/41.jpg)
Page 11 of 28
Air Quality (24-hr TSP)
![Page 42: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/42.jpg)
Page 12 of 28
Air Quality
![Page 43: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/43.jpg)
Page 13 of 28
Noise
Station NSR1
Noise Level for 30 min, dB(A)
Date Start Time End Time
Leq L10 L90
Wind Speed (m/s)
Weather Condition
Limit Level
3-Nov-10 13:29 13:59 50 52 47 0.4 Sunny 75
9-Nov-10 13:37 14:07 50 50 45 0.2 Sunny 75
15-Nov-10 13:27 13:57 50 51 48 0.2 Sunny 75
25-Nov-10 13:36 14:06 50 52 45 0.2 Sunny 75
1-Dec-10 13:24 13:54 50 51 41 0.2 Sunny 75
7-Dec-10 13:16 13:46 49 51 44 0.4 Sunny 75
13-Dec-10 13:31 14:01 49 50 42 0.2 Fine 75
23-Dec-10 13:31 14:01 47 48 44 0.2 Sunny 75
29-Dec-10 13:23 13:53 49 51 43 0.3 Sunny 75
4-Jan-11 13:11 13:41 50 52 45 0.3 Cloudy 75
10-Jan-11 13:17 13:47 63 66 50 0.2 Sunny 75
20-Jan-11 13:18 13:48 54 56 49 0.2 Sunny 75
26-Jan-11 13:21 13:51 51 52 44 0.2 Sunny 75
Station NSR3
Noise Level for 30 min, dB(A)
Date Start Time End Time
Leq L10 L90
Wind Speed (m/s)
Weather Condition
Limit Level
3-Nov-10 14:31 15:01 52 53 50 0.2 Sunny 75
9-Nov-10 14:39 15:09 50 51 47 0.2 Sunny 75
15-Nov-10 14:29 14:59 51 52 47 0.2 Sunny 75
25-Nov-10 14:38 15:08 50 52 46 0.3 Sunny 75
1-Dec-10 14:28 14:58 50 51 50 0.2 Sunny 75
7-Dec-10 14:18 14:48 54 55 47 0.4 Sunny 75
13-Dec-10 14:33 15:03 49 51 46 0.3 Fine 75
23-Dec-10 14:33 15:03 50 52 47 0.2 Sunny 75
29-Dec-10 14:29 14:59 48 50 46 0.2 Sunny 75
4-Jan-11 14:16 14:46 49 51 47 0.2 Cloudy 75
10-Jan-11 14:18 14:48 50 52 47 0.2 Sunny 75
20-Jan-11 14:20 14:50 50 51 48 0.2 Sunny 75
26-Jan-11 14:25 14:55 46 48 41 0.3 Sunny 75
![Page 44: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/44.jpg)
Page 14 of 28
Noise
Station NSR5
Noise Level for 30 min, dB(A)
Date Start Time End Time
Leq L10 L90
Wind Speed (m/s)
Weather Condition
Limit Level
3-Nov-10 9:03 9:33 57 60 54 0.4 Sunny 75
9-Nov-10 9:22 9:52 56 58 51 0.3 Sunny 75
15-Nov-10 9:13 9:43 57 58 53 0.4 Sunny 75
25-Nov-10 9:20 9:50 55 57 52 0.4 Sunny 75
1-Dec-10 9:13 9:43 52 54 49 0.3 Sunny 75
7-Dec-10 9:15 9:45 57 58 54 0.5 Sunny 75
13-Dec-10 9:25 9:55 52 54 48 0.4 Fine 75
23-Dec-10 9:18 9:48 55 57 52 0.3 Sunny 75
29-Dec-10 9:21 9:51 55 57 53 0.4 Sunny 75
4-Jan-11 9:22 9:52 62 64 57 0.4 Cloudy 75
10-Jan-11 9:13 9:43 54 57 53 0.2 Sunny 75
20-Jan-11 9:19 9:49 55 58 52 0.3 Sunny 75
26-Jan-11 9:14 9:44 57 60 53 0.2 Sunny 75
Station NSR7
Noise Level for 30 min, dB(A)
Date Start Time End Time
Leq L10 L90
Wind Speed (m/s)
Weather Condition
Limit Level
3-Nov-10 10:17 10:47 65 68 63 0.7 Sunny 75
9-Nov-10 10:34 11:04 64 66 61 0.3 Sunny 75
15-Nov-10 10:30 11:00 64 66 61 0.5 Sunny 75
25-Nov-10 10:26 10:56 64 66 61 0.8 Sunny 75
1-Dec-10 10:17 10:47 64 66 61 0.4 Sunny 75
7-Dec-10 10:17 10:47 64 66 60 0.9 Sunny 75
13-Dec-10 10:30 11:00 64 66 60 0.6 Fine 75
23-Dec-10 10:33 11:03 64 66 60 0.6 Sunny 75
29-Dec-10 10:25 10:55 64 66 61 0.5 Sunny 75
4-Jan-11 10:37 11:07 65 67 62 0.6 Cloudy 75
10-Jan-11 10:22 10:52 63 65 60 0.5 Sunny 75
20-Jan-11 10:28 10:58 65 67 61 0.5 Sunny 75
26-Jan-11 10:23 10:53 64 66 61 0.5 Sunny 75
![Page 45: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/45.jpg)
Page 15 of 28
Noise
![Page 46: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/46.jpg)
Page 16 of 28
Noise
![Page 47: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/47.jpg)
Page 17 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP1
1/11/2010 23.9 7.6 5.2 63.2 16.3 2 10.5
3/11/2010 23.1 7.7 5.0 59.3 15.0 2.5 11.5
5/11/2010 20.8 7.8 5.5 62.7 29.6 2.5 24
8/11/2010 23.7 7.7 4.8 56.8 95.9 3 103.5
10/11/2010 24.4 7.8 6.7 80.9 45.8 3 36.5
12/11/2010 23.1 7.8 7.6 88.3 84.9 6 93
15/11/2010 23.8 7.9 7.2 84.6 80.0 6.5 80
17/11/2010 23.8 8.0 6.3 74.1 15.9 2 10
19/11/2010 24.4 7.8 5.8 70.2 40.3 2 33.5
22/11/2010 23.4 7.5 6.1 73.5 94.4 4.5 113.5
24/11/2010 22.7 7.9 5.9 67.7 63.7 4 75
26/11/2010 21.6 7.5 4.7 53.8 21.1 2.5 20
29/11/2010 22.5 7.6 4.7 54.8 21.9 2 17.5
1/12/2010 23.1 7.9 6.85 80.2 37.45 2.5 42.5
3/12/2010 23.2 8.3 6.3 74 31.2 2.5 35
6/12/2010 23.2 8.5 7.25 84.85 100.5 6 140
8/12/2010 21.1 8.1 7.15 80.75 55.9 4 51
10/12/2010 21.7 8.7 7.195 81.9 71.6 5.5 45.5
13/12/2010 23 8.1 7.5 87.75 67.75 5 65
15/12/2010 21.9 8.2 5.55 63.35 74.05 3 69.5
17/12/2010 17.3 8.3 6.115 64.05 27.2 3 23
20/12/2010 21.1 8 4.1 46.95 47.75 2.5 39.5
22/12/2010 20.4 8.6 7.15 79.55 79.45 5.5 82.5
24/12/2010 20.5 8.1 7.15 79.05 70.6 5.5 64.5
28/12/2010 19 8.3 7.1 76.65 81.7 3.5 91
30/12/2010 17.8 8.4 5.95 62.3 87.9 3.5 87
3/1/2011 17.2 8.6 6.9 71.1 66.6 5 63
5/1/2011 16.9 8.4 7.6 78.2 27.2 4 29
7/1/2011 11.8 8.4 10.0 92.4 32.9 10.5 24.5
10/1/2011 12.6 8.3 10.0 94.9 7.2 2 4.5
12/1/2011 11.1 8.7 9.4 85.9 11.4 2 5
14/1/2011 12.7 8.7 11.1 105.3 9.1 2 6
17/1/2011 12.4 7.9 7.1 69.2 28.3 5 34.5
19/1/2011 14.8 8.4 10.3 102.3 20.1 5.5 29
21/1/2011 15.4 6.8 10.1 102.4 7.6 4.5 2
24/1/2011 13.9 7.0 9.6 92.9 14.2 2.5 8
26/1/2011 13.9 7.3 9.1 88.5 13.9 2 13
28/1/2011 15.3 7.9 8.1 81.3 32.6 5.5 38
31/1/2011 14.6 7.8 5.1 49.8 64.6 6 68
Average 19.4 8.0 7.0 76.0 46.0 3.9 45.9
Action Level - <5.5 or >7.5 <1.23 - >173 - >231
Limit Level - <4.0 or >8.0 <1.17 - >177 - >299
![Page 48: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/48.jpg)
Page 18 of 28
Water Quality
Temperature at MP1
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP1
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP1
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
y
Turbidity at MP1
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP1
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP1
0
20
40
60
80
100
120
140
160
180
200
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, m
g/L
![Page 49: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/49.jpg)
Page 19 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP2
1/11/2010 23.2 7.6 5.6 66.7 7.3 2 5.5
3/11/2010 23.4 7.5 5.7 67.9 14.3 2 10.5
5/11/2010 21.5 7.5 5.5 63.6 35.1 2 33
8/11/2010 23.9 7.6 5.9 69.9 80.8 3.5 87
10/11/2010 24.2 7.8 6.8 80.2 82.1 3.5 69.5
12/11/2010 23.0 7.7 7.5 86.5 72.0 5 83
15/11/2010 24.1 7.7 7.2 84.9 75.8 6 57
17/11/2010 23.1 7.9 6.6 76.9 29.0 2 23.5
19/11/2010 23.6 7.7 6.2 73.2 65.4 4 63.5
22/11/2010 23.3 7.4 6.6 77.6 71.6 4 78
24/11/2010 23.0 7.7 6.5 75.0 61.2 3 64.5
26/11/2010 21.7 7.5 4.8 55.4 32.3 2.5 29
29/11/2010 22.6 7.6 5.9 69.0 16.3 2 15.5
1/12/2010 23.3 7.8 6.85 81.05 33.55 2 41.5
3/12/2010 22.7 7.9 6.45 75 57.9 3 66.5
6/12/2010 23.3 8 7.4 86.9 207.5 8 247.5
8/12/2010 21.3 8 7.5 84.75 42.25 4 39.5
10/12/2010 22 8.2 7.19 82.4 70.25 5 65
13/12/2010 22.7 8.2 7.15 82.75 64.75 5 60
15/12/2010 22.2 8.1 6.35 72.75 206.5 6 226
17/12/2010 18.9 8.4 6.75 72.75 67.3 6.5 81
20/12/2010 20.9 8.3 5.35 59.95 50.95 3.5 39.5
22/12/2010 20.5 8.3 7.65 84.85 135 7 143
24/12/2010 20.7 8 7.43 83.05 48.4 5.5 48.5
28/12/2010 18.7 8.2 7.45 80 92.75 4 115.5
30/12/2010 18.1 8 6.25 66.35 52.55 2 56
3/1/2011 17.0 8.3 7.4 76.9 33.5 4 28.5
5/1/2011 16.7 8.2 7.9 81.2 27.5 4.5 27
7/1/2011 12.3 8.2 9.8 92.3 10.6 2 10
10/1/2011 12.5 8.1 10.1 95.8 10.6 2 8
12/1/2011 11.5 8.3 9.0 83.0 8.4 2 7
14/1/2011 12.6 8.3 10.6 101.1 8.4 2 6
17/1/2011 12.5 7.8 5.3 52.1 31.7 5.5 35
19/1/2011 15.0 8.3 10.1 100.9 5.8 2 4.5
21/1/2011 15.8 7.0 9.6 96.3 9.5 2 8.5
24/1/2011 14.1 7.1 9.4 91.4 11.6 2 8.5
26/1/2011 14.4 7.5 9.2 90.2 11.7 2 12
28/1/2011 16.5 7.8 8.2 83.0 31.9 5.5 30.5
31/1/2011 14.2 7.5 4.5 44.0 49.0 5 53.5
Average 19.5 7.9 7.2 78.1 51.9 3.7 53.5
Action Level - <5.5 or >7.5 <1.04 - >132 - >170
Limit Level - <4.0 or >8.0 <0.89 - >163 - >209
![Page 50: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/50.jpg)
Page 20 of 28
Water Quality
Temperature at MP2
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP2
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP2
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
Turbidity at MP2
0.0
50.0
100.0
150.0
200.0
250.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP2
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP2
0
50
100
150
200
250
300
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, m
g/L
![Page 51: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/51.jpg)
Page 21 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP3
1/11/2010 19.9 7.8 8.1 89.3 13.0 4 12
3/11/2010 20.9 7.8 8.2 91.4 16.2 5 14
5/11/2010 20.0 7.7 7.1 79.0 19.0 6 13.5
8/11/2010 21.4 7.4 7.8 87.8 25.8 5.5 16
10/11/2010 22.9 7.5 8.4 98.0 22.3 5 12.5
12/11/2010 22.7 7.4 8.0 93.1 29.7 6 25
15/11/2010 23.9 7.4 8.2 97.1 30.3 6 25.5
17/11/2010 22.9 7.7 9.1 106.2 30.9 6 23
19/11/2010 23.7 7.6 8.3 98.1 34.8 8 33
22/11/2010 22.4 7.6 8.4 98.6 33.6 7.5 35.5
24/11/2010 22.0 7.5 7.5 86.2 39.0 10 37
26/11/2010 20.7 7.6 8.1 90.0 38.5 10 33
29/11/2010 22.5 8.6 10.7 126.7 41.5 7.5 42
1/12/2010 22.6 7.5 8.75 101.2 35.85 10 30.5
3/12/2010 22.6 8.2 9.35 109.2 38 11.5 33.5
6/12/2010 21.9 7.7 7.55 86.7 41 11.5 43.5
8/12/2010 18.7 7.9 8 86.75 37.3 3.5 39
10/12/2010 18.6 7.8 8.46 91.05 35.95 10 35.5
13/12/2010 21.1 7.8 8.55 96.85 31.7 7.5 22
15/12/2010 19.7 8.1 6.55 72.55 42.15 10 24.5
17/12/2010 14 8 10.85 106 38.05 9 26
20/12/2010 18.3 7.8 10.65 113.8 28.35 7 15
22/12/2010 17.6 7.8 8.5 89.8 27.35 7 12
24/12/2010 18.1 7.7 7.55 80.6 29.85 6 18
28/12/2010 14.1 8.2 6.25 61.25 30.25 3 7.5
30/12/2010 15.7 7.6 7.15 72.45 33.45 3 11.5
3/1/2011 13.5 7.9 8.7 84.2 37.8 3 15.5
5/1/2011 12.3 7.9 9.3 87.5 39.6 4 14.5
7/1/2011 11.8 8.6 9.3 86.3 34.4 3 11
10/1/2011 12.2 8.1 9.8 92.0 29.1 2.5 12
12/1/2011 10.7 8.2 9.4 85.2 25.8 2 9.5
14/1/2011 12.5 8.2 9.7 91.8 23.1 2 7.5
17/1/2011 11.6 8.3 10.5 96.9 22.7 3 15.5
19/1/2011 14.8 8.1 8.1 80.2 16.0 2.5 7
21/1/2011 15.2 7.1 9.6 95.6 15.9 2.5 6.5
24/1/2011 13.8 7.2 8.2 79.2 14.3 2 9.5
26/1/2011 13.8 7.4 8.0 77.3 14.4 2 10.5
28/1/2011 15.5 7.6 7.9 79.8 22.5 3 17.5
31/1/2011 13.7 7.6 10.3 99.5 23.9 5 22
Average 18.0 7.8 8.6 90.9 29.3 5.7 20.5
Action Level - <5.5 or >7.5 <6.85 - >64 - >65
Limit Level - <4.0 or >8.0 <6.65 - >67 - >66
![Page 52: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/52.jpg)
Page 22 of 28
Water Quality
Temperature at MP3
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP3
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP3
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
Turbidity at MP3
0.0
20.0
40.0
60.0
80.0
100.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP3
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP3
0
20
40
60
80
100
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, mg
/L
![Page 53: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/53.jpg)
Page 23 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP4
1/11/2010 22.4 7.5 7.0 80.0 40.4 2 29.5
3/11/2010 21.7 7.4 5.1 58.0 53.9 2.5 39
5/11/2010 20.1 7.5 5.8 63.7 28.2 3 15
8/11/2010 23.6 7.3 5.6 65.2 38.1 2 22.5
10/11/2010 24.3 7.4 6.6 78.8 29.2 2 15.5
12/11/2010 24.4 7.5 7.3 87.2 30.8 3 18.5
15/11/2010 25.1 7.2 6.4 77.0 34.9 4 23
17/11/2010 22.9 7.4 5.5 63.8 42.5 2 26
19/11/2010 24.6 7.4 6.4 75.9 46.8 3.5 34
22/11/2010 22.6 7.5 5.2 62.3 32.7 2 24
24/11/2010 22.5 7.4 6.4 73.7 42.9 4 30.5
26/11/2010 20.5 7.5 6.6 72.9 35.6 3 23.5
29/11/2010 22.8 7.9 7.4 85.5 32.7 2 23
1/12/2010 23.3 7.3 6.25 73.2 26.2 2.5 20
3/12/2010 23.8 7.7 6.15 73.55 26.75 2 19
6/12/2010 21.8 7.6 5.35 60.75 26.85 5 16
8/12/2010 19 7.8 6.95 75.85 36.05 4 23
10/12/2010 18.4 7.5 5.03 54 29.95 3 22.5
13/12/2010 21.9 7.9 7.8 89.4 40.75 9 33
15/12/2010 20.2 7.8 5.15 57.6 58.4 3 29
17/12/2010 12.3 8.1 10.245 96.35 22.8 3 9.5
20/12/2010 20.8 7.8 6.05 68.1 25.15 2 15.5
22/12/2010 19.8 7.7 6.35 69.8 44.35 2 31.5
24/12/2010 18.4 7.5 4.25 46.1 36.7 2 25.5
28/12/2010 11.7 8.1 5.5 50.8 23.65 2.5 17
30/12/2010 15.3 7.5 5.65 57.05 34.85 2 24.5
3/1/2011 12.0 7.8 8.6 80.3 36.8 2 29
5/1/2011 12.2 7.9 10.0 94.1 22.1 5 17
7/1/2011 11.2 7.9 8.4 77.3 28.8 2 18.5
10/1/2011 12.8 7.9 6.8 64.3 33.7 5.5 24.5
12/1/2011 8.1 8.2 11.0 93.4 22.7 5 17
14/1/2011 15.0 8.1 11.5 114.6 32.6 8.5 27
17/1/2011 11.9 8.0 11.8 110.6 30.6 15.5 31
19/1/2011 17.6 7.9 8.4 89.3 59.5 4 50
21/1/2011 15.3 6.9 8.7 88.0 44.4 2 32.5
24/1/2011 15.1 7.1 6.0 59.3 20.8 3 18
26/1/2011 13.1 7.4 6.5 62.2 37.8 2 30
28/1/2011 15.8 7.3 6.2 63.0 27.5 3 19.5
31/1/2011 13.1 7.3 8.8 84.8 17.3 3 14
Average 18.4 7.6 7.0 74.3 34.2 3.5 24.1
Action Level - <5.5 or >7.5 <3.91 - >60 - >50
Limit Level - <4.0 or >8.0 <3.82 - >64 - >53
![Page 54: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/54.jpg)
Page 24 of 28
Water Quality
Temperature at MP4
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP4
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP4
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
Turbidity at MP4
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP4
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP4
0
20
40
60
80
100
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, m
g/L
![Page 55: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/55.jpg)
Page 25 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP5
1/11/2010 21.8 7.2 7.4 84.3 43.3 2 30.5
3/11/2010 21.4 7.3 7.0 80.0 32.5 3.5 22.5
5/11/2010 19.8 7.2 6.6 72.1 31.9 6 19.5
8/11/2010 23.5 7.3 5.9 69.6 40.4 2 20
10/11/2010 23.8 7.3 7.0 83.7 27.3 2 15
12/11/2010 23.5 7.4 8.0 95.1 32.1 2 21.5
15/11/2010 24.9 7.5 8.8 106.1 35.5 2 20.5
17/11/2010 22.9 7.4 7.3 84.8 30.8 2 16.5
19/11/2010 24.9 7.2 6.6 79.8 31.6 2 20.5
22/11/2010 22.4 7.4 7.2 83.7 48.9 5 38.5
24/11/2010 22.1 7.4 6.2 71.1 83.4 4 50
26/11/2010 20.2 7.3 7.1 78.3 55.8 2 35.5
29/11/2010 22.9 7.4 5.3 61.7 33.9 3.5 25
1/12/2010 22.5 7.2 6.5 75.8 34.4 4 21
3/12/2010 22.9 7.4 6.95 81.45 33.8 3.5 24
6/12/2010 21.7 7.7 6.55 75.55 30.7 7 30
8/12/2010 18.1 7.7 7.75 83.5 39.95 6 26.5
10/12/2010 18 7.6 7.26 77.95 46.5 8.5 31.5
13/12/2010 21.8 7.7 6.35 72.95 36.8 2.5 21.5
15/12/2010 20.1 7.8 6.05 67.55 65.55 2 42.5
17/12/2010 12.4 8.2 10.35 97 26.45 3 13.5
20/12/2010 20.9 7.6 6.25 70.35 35 2 23
22/12/2010 19.7 7.8 6.55 72.75 63.6 4 52
24/12/2010 18.6 7.6 5.05 54.9 49.25 2 39
28/12/2010 10.8 7.7 7.15 64.95 26.5 2 15
30/12/2010 15.8 7.5 6.35 64.5 69.7 2.5 54.5
3/1/2011 12.3 7.8 8.2 77.0 39.1 2 25.5
5/1/2011 12.6 8.0 9.1 86.5 33.2 5 27
7/1/2011 11.1 7.9 8.6 79.1 29.0 2 19
10/1/2011 12.4 7.7 9.5 89.7 41.5 8.5 33
12/1/2011 7.8 8.3 13.4 113.0 42.9 11 33.5
14/1/2011 15.7 8.6 11.5 116.9 65.1 10 53.5
17/1/2011 11.8 8.1 12.3 115.4 28.5 12.5 34
19/1/2011 17.8 7.9 8.4 89.4 67.9 4 66
21/1/2011 15.5 7.1 9.1 92.3 37.0 2 22.5
24/1/2011 15.3 7.0 6.8 68.7 34.8 2 27.5
26/1/2011 12.9 7.9 7.1 67.5 28.7 2 19.5
28/1/2011 16.0 7.3 6.3 65.0 26.8 2 21
31/1/2011 13.3 7.2 8.3 80.3 16.9 2 11.5
Average 18.3 7.6 7.6 80.8 40.4 3.9 28.8
Action Level - <5.5 or >7.5 <4.13 - >81 - >66
Limit Level - <4.0 or >8.0 <3.87 - >84 - >69
![Page 56: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/56.jpg)
Page 26 of 28
Water Quality
Temperature at MP5
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP5
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP5
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
Turbidity at MP5
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP5
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP5
0
20
40
60
80
100
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, mg
/L
![Page 57: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/57.jpg)
Page 27 of 28
Water Quality
Notes:
Values Bold indicate Action Level exceedance. Values Underlined and Bold indicate Limit Level exceedance.
Monitoring Date
Temp (oC)
pH Dissolved Oxygen (mg/L)
DOS (%)
Turbidity (NT)
BOD (mg/L)
Suspended Solids (mg/L)
MP6
1/11/2010 21.6 7.3 7.3 83.9 35.9 2 25.5
3/11/2010 21.1 7.4 7.4 83.7 40.5 3 29
5/11/2010 19.5 7.3 6.5 71.8 38.8 6 27.5
8/11/2010 23.4 7.4 6.3 73.5 59.4 2 34.5
10/11/2010 23.9 7.4 6.9 82.2 37.2 3 21.5
12/11/2010 22.8 7.5 8.7 101.7 60.0 2 39.5
15/11/2010 24.3 7.7 10.1 122.8 42.0 3 27.5
17/11/2010 22.6 7.3 7.1 82.9 41.3 2 23.5
19/11/2010 24.5 7.3 7.5 90.8 42.6 2 28.5
22/11/2010 22.8 7.5 7.3 83.8 55.9 6.5 43.5
24/11/2010 22.0 7.5 6.5 75.0 78.6 7 49
26/11/2010 20.0 7.3 6.4 70.1 63.6 2 40
29/11/2010 21.3 7.5 5.7 65.1 42.6 2 30.5
1/12/2010 22.2 7.3 6.25 73.1 30.95 3 20.5
3/12/2010 23.1 7.5 8.05 94.95 45.7 10 30
6/12/2010 21.9 7.8 6.15 73.7 33.15 4.5 25
8/12/2010 17.9 7.7 8 86.05 40.85 5.5 26
10/12/2010 18.2 7.9 6.815 73.45 46.9 2 31.5
13/12/2010 21.7 7.7 6.2 70.95 38.1 2 23
15/12/2010 19.9 7.9 5.85 65 90.25 2 57
17/12/2010 10.6 8.2 10.5 95 23.4 3 13
20/12/2010 21 7.7 6.75 76.65 38.25 2 24
22/12/2010 19.3 7.9 6.25 68.7 85.1 3.5 58
24/12/2010 18.9 7.6 5.25 57.05 39.25 2 28
28/12/2010 11.8 7.7 7.85 74 18.2 2 15.5
30/12/2010 15.4 7.6 6.45 65.55 64.15 2 48
3/1/2011 13.1 7.6 7.4 71.4 39.7 2 26.5
5/1/2011 13.2 8.5 8.0 77.0 39.5 2 22.5
7/1/2011 11.5 8.0 8.2 75.7 50.8 2 33.5
10/1/2011 12.8 7.8 7.9 75.7 28.7 2 20.5
12/1/2011 9.3 8.1 9.4 83.1 26.7 3.5 15
14/1/2011 15.4 8.7 11.2 113.5 25.0 7.5 19.5
17/1/2011 12.5 8.0 10.1 95.1 50.9 5 45
19/1/2011 17.2 7.8 8.3 87.1 34.8 3 24
21/1/2011 15.4 7.2 9.2 93.7 37.6 2 21
24/1/2011 15.4 7.4 7.0 70.4 54.2 2 43
26/1/2011 13.2 8.0 6.7 64.0 23.2 2 16.5
28/1/2011 16.3 7.4 5.9 60.8 30.6 2 23.5
31/1/2011 13.5 7.2 8.4 82.8 19.4 2 14
Average 18.2 7.7 7.5 79.8 43.4 3.2 29.3
Action Level - <5.5 or >7.5 <4.61 - >94 - >75
Limit Level - <4.0 or >8.0 <4.52 - >96 - >75
![Page 58: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/58.jpg)
Page 28 of 28
Water Quality
Temperature at MP6
7.0
12.0
17.0
22.0
27.0
32.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Te
mp
era
ture
, d
eg
. C
pH at MP6
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
pH
Dissolved Oxygen (DO) at MP6
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Dis
so
lve
d O
xy
ge
n (
DO
), m
g/L
Turbidity at MP6
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
Tu
rbid
ity
, N
TU
BOD at MP6
0
2
4
6
8
10
12
14
16
18
20
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
BO
D
Suspended Solids (SS) at MP6
0
20
40
60
80
100
1/10/2010 26/10/2010 20/11/2010 15/12/2010 9/1/2011 3/2/2011
Date
SS
, m
g/L
![Page 59: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/59.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Table E1. Summary of bird monitoring in the Survey Area
Nov 2010
Species Name Scientific Name
Conservation Status
(2) Survey
(3) Mean
(4)
Little Grebe Tachybaptus ruficollis LC, (1) 4 43.3
Great Cormorant Phalacrocorax carbo PRC, (1) 4 10.0
Grey Heron Ardea cinerea PRC, (1) 4 18.0
Great Egret Egretta alba PRC, (1) 4 10.0
Intermediate Egret Egretta intermedia RC, (1) 3 1.3
Little Egret Egretta garzetta PRC, (1) 4 41.3
Chinese Pond Heron Ardeola bacchus PRC, (1) 4 36.3
Black-crowned Night Heron Nycticorax nycticorax LC, (1) 1 0.3
Black-faced Spoonbill Platalea minor PGC, (1) 3 5.3
Northern Shoveler Anas clypeata RC, (1) 4 1.5
Besra Accipiter virgatus - 1 0.3
Common Buzzard Buteo buteo - 1 0.3
White-breasted Waterhen Amaurornis phoenicurus (1) 4 2.5
Common Moorhen Gallinula chloropus (1) 4 19.0
Pheasant-tailed Jacana Hydrophasianus chirurgus LC, (1) 1 0.3
Greater Painted-Snipe Rostratula benghalensis LC, (1) 1 0.3
Black-winged Stilt Himantopus himantopus RC, (1) 4 5.8
Little Ringed Plover Charadrius dubius LC, (1) 4 9.8
Kentish Plover Charadrius alexandrinus RC, (1) 1 0.3
Spotted Redshank Tringa erythropus RC, (1) 1 0.3
Common Redshank Tringa totanus RC, (1) 1 0.3
Marsh Sandpiper Tringa stagnatilis RC, (1) 3 2.5
Common Greenshank Tringa nebularia RC, (1) 4 3.5
Green Sandpiper Tringa ochropus (1) 4 7.3
Wood Sandpiper Tringa glareola LC, (1) 4 8.3
Common Sandpiper Actitis hypoleucos (1) 4 20.5
Common Snipe Gallinago gallinago (1) 2 1.0
Temminck’s Stint Calidris temminckii LC, (1) 3 3.3
Pied Kingfisher Ceryle rudis (LC), (1) 1 0.3
Common Kingfisher Alcedo atthis (1) 4 7.8
White-throated Kingfisher Halcyon smyrnensis (LC) 4 2.0
Pale Martin Riparia diluta - 1 0.5
Yellow Wagtail Motacilla flava (1) 4 23.5
Grey Wagtail Motacilla cinerea (1) 1 0.5
Richard's Pipit Anthus richardi - 4 8.0
Red-throated Pipit Anthus cervinus LC 3 1.3
Black-browed Reed Warbler Acrocephalus bistrigiceps - 1 0.8
Oriental Reed Warbler Acrocephalus orientalis - 1 0.3
Zitting Cisticola Cisticola juncidis LC 4 2.8
Red-billed Starling Sturnus sericeus GC 4 46.8
White-cheeked Starling Sturnus cineraceus PRC 2 2.8
Appendix E. Summary of Ecological Monitoring results
![Page 60: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/60.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Collared Crow Corvus torquatus LC, NT 3 1.5
Total no. of species 42
Dec 2010
Species Name Scientific Name
Conservation Status
(2) Survey
(3) Mean
(4)
Little Grebe Tachybaptus ruficollis LC, (1) 5 30.6
Great Cormorant Phalacrocorax carbo PRC, (1) 5 15.4
Grey Heron Ardea cinerea PRC, (1) 5 15.4
Great Egret Egretta alba PRC, (1) 5 8.2
Intermediate Egret Egretta intermedia RC, (1) 2 0.4
Little Egret Egretta garzetta PRC, (1) 5 23.6
Cattle Egret Bubulcus ibis (LC), (1) 1 0.6
Chinese Pond Heron Ardeola bacchus PRC, (1) 5 15.2
Black-faced Spoonbill Platalea minor PGC, (1) 2 1.4
Northern Shoveler Anas clypeata RC, (1) 1 0.2
Osprey Pandion haliaetus RC 3 0.6
Black Kite Milvus migrans (RC) 2 0.6
Water Rail Rallus aquaticus LC, (1) 2 0.4
White-breasted Waterhen Amaurornis phoenicurus (1) 3 0.8
Common Moorhen Gallinula chloropus (1) 5 16.6
Black-winged Stilt Himantopus himantopus RC, (1) 2 2.0
Pied Avocet Recurvirostra avosetta RC,(1) 3 1.2
Little Ringed Plover Charadrius dubius LC, (1) 5 17.4
Spotted Redshank Tringa erythropus RC, (1) 1 0.2
Common Greenshank Tringa nebularia RC, (1) 5 3.0
Green Sandpiper Tringa ochropus (1) 5 7.2
Wood Sandpiper Tringa glareola LC, (1) 5 8.4
Common Sandpiper Actitis hypoleucos (1) 5 14.8
Pintail/Swinhoe's Snipe Gallinago stenura/megala (1) 1 0.6
Common Snipe Gallinago gallinago (1) 1 0.2
Temminck's Stint Calidris temminckii LC, (1) 3 3.6
Pied Kingfisher Ceryle rudis (LC), (1) 1 0.2
Common Kingfisher Alcedo atthis (1) 5 6.0
White-throated Kingfisher Halcyon smyrnensis (LC) 2 1.0
Yellow Wagtail Motacilla flava (1) 5 25.8
Grey Wagtail Motacilla cinerea (1) 2 0.6
Richard's Pipit Anthus richardi - 5 10.0
Red-throated Pipit Anthus cervinus LC 3 2.8
Buff-bellied Pipit Anthus rubescens LC 2 1.0
Daurian Redstart Phoenicurus auroreus - 1 0.2
Common Stonechat Saxicola torquata - 3 1.6
Zitting Cisticola Cisticola juncidis LC 4 3.2
Red-billed Starling Sturnus sericeus GC 5 153.2
White-cheeked Starling Sturnus cineraceus PRC 3 5.0
Collared Crow Corvus torquatus LC, NT 4 1.8
Total no. of species 41
Jan 2011
Species Name Scientific Name
Conservation Status
(2) Survey
(3) Mean
(4)
![Page 61: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/61.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Little Grebe Tachybaptus ruficollis LC, (1) 4 18.0
Great Cormorant Phalacrocorax carbo PRC, (1) 4 12.5
Grey Heron Ardea cinerea PRC, (1) 4 9.3
Great Egret Egretta alba PRC, (1) 4 11.3
Intermediate Egret Egretta intermedia RC, (1) 2 1.5
Little Egret Egretta garzetta PRC, (1) 4 75.0
Chinese Pond Heron Ardeola bacchus PRC, (1) 4 22.3
Black-faced Spoonbill Platalea minor PGC, (1) 2 13.3
Osprey Pandion haliaetus RC 1 0.3
Common Buzzard Buteo buteo - 1 0.3
Eastern Water Rail Rallus indicus LC,(1) 1 0.3
White-breasted Waterhen Amaurornis phoenicurus (1) 4 2.5
Common Moorhen Gallinula chloropus (1) 4 18.3
Black-winged Stilt Himantopus himantopus RC, (1) 1 0.3
Little Ringed Plover Charadrius dubius LC, (1) 4 9.0
Common Greenshank Tringa nebularia RC, (1) 4 3.3
Green Sandpiper Tringa ochropus (1) 4 4.0
Wood Sandpiper Tringa glareola LC, (1) 3 3.3
Common Sandpiper Actitis hypoleucos (1) 4 9.8
Pintail/Swinhoe's Snipe Gallinago stenura/ Gallinago megala
(1) 1 0.3
Common Snipe Gallinago gallinago (1) 1 0.3
Temminck's Stint Calidris temminckii LC, (1) 4 3.8
Black-headed Gull Larus ridibundus PRC, (1) 1 0.3
Common Kingfisher Alcedo atthis (1) 3 3.0
White-throated Kingfisher Halcyon smyrnensis (LC) 1 0.3
Yellow Wagtail Motacilla flava (1) 4 14.8
Red-throated Pipit Anthus cervinus LC 1 0.3
Zitting Cisticola Cisticola juncidis LC 2 0.8
Red-billed Starling Sturnus sericeus GC 4 277.5
White-cheeked Starling Sturnus cineraceus PRC 2 5.8
Collared Crow Corvus torquatus LC, NT 3 1.3
Total no. of species 31
(1) indicates wetland-dependant or -associated species. (2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2010). (3) indicates number of surveys recorded within the survey period. (4) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys.
Table E2. Summary of bird monitoring in the WRA
Nov 2010
Species Name Scientific Name Conservation
Status (2)
Survey(3)
Total(4)
Records outside survey
(5)
Grey Heron Ardea cinerea PRC, (1) 2 1.0
Great Egret Egretta alba PRC, (1) - - � Intermediate Egret Egretta intermedia RC, (1) - - � Little Egret Egretta garzetta PRC, (1) - - � Chinese Pond Heron Ardeola bacchus PRC, (1) 1 1.0 � Black Kite Milvus migrans (RC) - - �
![Page 62: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/62.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Common Kestrel Falco tinnunculus - 2 1.0
Black-winged Stilt Himantopus himantopus
RC, (1) - - �
Little Ringed Plover Charadrius dubius LC, (1) 2 24.5 �
Common Greenshank Tringa nebularia RC, (1) 1 0.5 �
Green Sandpiper Tringa ochropus (1) 1 1.0
Wood Sandpiper Tringa glareola LC, (1) - - �
Common Sandpiper Actitis hypoleucos (1) 1 0.5
Pintail/Swinhoe's Snipe Gallinago stenura/ Gallinago megala
(1) 1 0.5
Common Snipe Gallinago gallinago (1) - - �
Temminck’s Stint Calidris temminckii LC, (1) 1 0.5 �
Pied Kingfisher Ceryle rudis (LC), (1) - - � White-throated Kingfisher Halcyon smyrnensis (LC) - - � Yellow Wagtail Motacilla flava (1) 2 14.5 � White Wagtail Motacilla alba - 0 0.0 � Richard's Pipit Anthus richardi - 2 1.5 � Olive-backed Pipit Anthus hodgsoni - 1 0.5
Red-throated Pipit Anthus cervinus LC 2 2.5
Buff-bellied Pipit Anthus rubescens LC 2 1.5
Common Stonechat Saxicola torquata - 1 0.5 � Plain Prinia Prinia inornata - - - �
Dusky Warbler Phylloscopus fuscatus
- - - �
Little Bunting Emberiza pusilla - 1 0.5
Scaly-breasted Munia Lonchura punctulata - - - � Eurasian Tree Sparrow Passer montanus - - - �
No. of Species Recorded 30
Dec 2010
Species Name Scientific Name Conservation
Status (2)
Survey(3)
Total(4)
Records outside survey
(5)
Grey Heron Ardea cinerea PRC, (1) 3 1.6 �
Great Egret Egretta alba PRC, (1) 1 0.4 �
Intermediate Egret Egretta intermedia RC, (1) - - �
Little Egret Egretta garzetta PRC, (1) 2 1.8 �
Chinese Pond Heron Ardeola bacchus PRC, (1) 1 0.2
Eurasian Wigeon Anas penelope RC, (1) 1 1.6
Common Teal Anas crecca RC, (1) - - �
Northern Pintail Anas acuta RC,(1) 1 0.2
Osprey Pandion haliaetus RC 1 0.2
Black Kite Milvus migrans (RC) - - �
Common Kestrel Falco tinnunculus - 2 0.4 �
Black-winged Stilt Himantopus himantopus RC, (1) - - �
Pied Avocet Recurvirostra avosetta RC, (1) 1 0.2
Little Ringed Plover Charadrius dubius LC, (1) 4 7.4 �
Kentish Plover Charadrius alexandrinus RC, (1) - - �
Marsh Sandpiper Tringa stagnatilis RC, (1) - - �
![Page 63: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/63.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Common Greenshank Tringa nebularia RC, (1) - - �
Green Sandpiper Tringa ochropus (1) 2 0.4
Wood Sandpiper Tringa glareola LC, (1) 0 0.0 �
Common Sandpiper Actitis hypoleucos (1) 3 1.0
Temminck's Stint Calidris temminckii LC, (1) - - �
Spotted Dove Steptopelia chinensis - - - �
Pied Kingfisher Ceryle rudis (LC), (1) 1 0.2
Common Kingfisher Alcedo atthis (1) 2 0.4
Yellow Wagtail Motacilla flava (1) 5 10.2 �
Grey Wagtail Motacilla cinerea (1) 1 0.2
White Wagtail Motacilla alba (1) 2 1.8 �
Richard's Pipit Anthus richardi - 3 0.8 �
Red-throated Pipit Anthus cervinus LC 2 1.2 �
Common Stonechat Saxicola torquata - 3 1.0 �
Plain Prinia Prinia inornata - - - �
Eurasian Tree Sparrow Passer montanus - - - �
Large-billed Crow Corvus macrorhynchos - 1 0.4
Collared Crow Corvus torquatus LC, NT 1 0.2
No. of Species Recorded 34
Jan 2011
Species Name Scientific Name Conservation
Status (2)
Survey(3)
Total(4)
Records outside survey
(5)
Little Grebe Tachybaptus ruficollis LC, (1) 1 0.5
Great Cormorant Phalacrocorax carbo PRC, (1) 3 0.8
Grey Heron Ardea cinerea PRC, (1) 4 2.0
Great Egret Egretta alba PRC, (1) 4 14.0
Intermediate Egret Egretta intermedia RC, (1) 3 1.7
Little Egret Egretta garzetta PRC, (1) 4 8.0
Black-faced Spoonbill Platalea minor PGC, (1) 1 0.3
Eurasian Wigeon Anas penelope RC, (1) 1 2.5
Common Teal Anas crecca RC, (1) 1 1.0
Northern Pintail Anas acuta RC, (1) 1 7.0
Black Kite Milvus migrans (RC) 2 0.8
Common Kestrel Falco tinnunculus - 3 1.0
Little Ringed Plover Charadrius dubius LC, (1) 2 3.8
Green Sandpiper Tringa ochropus (1) 1 0.5
Pied Kingfisher Ceryle rudis (LC), (1) 1 0.3
Common Kingfisher Alcedo atthis (1) 2 0.5
Yellow Wagtail Motacilla flava (1) 4 15.0
Richard's Pipit Anthus richardi - 2 0.5
Red-throated Pipit Anthus cervinus LC 1 0.5
Common Stonechat Saxicola torquata - 3 1.0
Collared Crow Corvus torquatus LC, NT 1 0.3
N/A
No. of Species Recorded 21
(1) indicates wetland-dependant or -associated species. (2) Conservation status follows that of Fellowes et al. (2002) and BirdLife International listing (2010). (3) indicates number of surveys recorded within the survey period.
![Page 64: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/64.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
(4) refers to the total number of individuals recorded in the survey (5) includes observations during other surveys and/or site visits.
Summary of herpetofauna surveys: Species Name Scientific Name Nov 2010 – Jan 2011
Conservation Status(1)
Survey
(2) Mean
(3)
Amphibians
(No Records)
Survey(2)
Mean(3)
Reptiles
(No Records)
(1) Conservation status follows that of Fellowes et al. (2002), Chan et al. (2005) and Karsen et al. (1998). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)
Summary of mammals:
Common Name Scientific Name
Conservation Status
(1) Nov 2010 – Jan 2011
No Records)
Summary of insect surveys conducted in the nearby fish ponds:
Common Name Scientific Name Nov 2010
Conservation Status
(1)
Survey(2)
Mean(3)
Odonate 5
Common Bluetail Aschnura senegalensis - 1 1
Crimson Darter Crocothemis servilia - 1 1
Green Skimmer Orthetrum sabina - 1 4
Wandering Glider Pantala flavescens - 1 6
Saddlebag Glider Tramea virginia - 1 3
Butterfly 8
Unidentified Swift Pelopidas sp. - 1 1
Red-base Jezebel Delias pasithoe - 1 1
Indian Cabbage White Pieris canidia - 1 17
Common Grass Yellow Eurema hecabe - 1 6
Unidentified Cerulean Jamides sp. - 1 2
Pale Grass Blue Zizeeria maha - 1 7
Common Tiger Danaus genutia - 1 1
Blue-Spotted Crow Euploea midamus - 1 1 (1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Wilson (2004) and Young & Yiu (2002). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)
![Page 65: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/65.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Summary of insect surveys conducted in the WRA
Common Name Scientific Name Nov 2010
Conservation Status
(1)
Survey(2)
Mean(3)
Odonate 8
Common Bluetail Aschnura senegalensis - 1 8
Pale-spotted Emperor Anax guttatus - 1 1
Lesser Emperor Anax parthenope - 1 1
Crimson Darter Crocothemis servilia - 1 3
Blue Percher Diplacodes trivialis - 1 2
Common Red Skimmer Orthetrum pruinosum - 1 1
Green Skimmer Orthetrum sabina - 1 30
Wandering Glider Pantala flavescens - 1 25
Butterfly 4
Common Straight Swift Parnara guttatus - 1 1
Lemon Emigrant Catopsilia pomona - 1 1
Common Grass Yellow Eurema hecabe - 1 4
Blue-Spotted Crow Euploea midamus - 1 2 (1) Conservation status follows that of Fellowes et al. (2002), Lo & Hui (2004), Wilson (2004) and Young & Yiu (2002). (2) indicates number of surveys recorded within the survey period. (3) equals the average number of individual species surveyed in each survey (i.e. total counts in all surveys divided by number of surveys)
![Page 66: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/66.jpg)
![Page 67: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/67.jpg)
266567/TNI/ENL/16/A Jan 2011 P:\Hong Kong\ENL\PROJECTS\266567 Wo Shang Wai ET\Deliverable\Quarterly EM&A\3. Nov 2010 - Jan 2011\Quarterly EM&A Summary Report Nov 2010 - Jan 2011 Rev A.doc
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 - Jan 2011
Appendix F. Environmental Mitigation Measures - Implementation Status
![Page 68: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/68.jpg)
![Page 69: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/69.jpg)
- 1 -
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status
Air Quality – Recommended Mitigation Measures Air Quality Mitigation Measures during construction Implementation Status
• use of effective dust screens, sheeting or netting to be provided to enclose dry scaffolding which may be provided from the ground floor level of the building or if a canopy is provided at the first floor level, from the first floor level, up to the highest level (maximum four floors for this Project) of the scaffolding where scaffolding is erected around the perimeter of a building under construction;
N/A
• dump trucks for material transport should be totally enclosed using impervious sheeting; �
• any excavated dusty materials or stockpile of dusty materials should be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;
P
• dusty materials remaining after a stockpile is removed should be wetted with water; �
• the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with e.g. concrete, bituminous materials or hardcore or similar;
�
• the portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;
P
• stockpile of dusty materials to be either covered entirely by impervious sheeting, placed in an area sheltered on the top and the 3 sides; or sprayed with water so as to maintain the entire surface wet;
N/A
• all dusty materials to be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;
�
• vehicle speed to be limited to 10 kph except on completed access roads; �
• every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites;
�
• the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;
�
• the working area of excavation should be sprayed with water immediately before, during and immediately after (as necessary) the operations so as to maintain the entire surface wet;
�
Odour mitigation measures
• all malodorous excavated material should be placed as far as possible from any ASRs; N/A
• the stockpiled malodorous material should be removed from site as soon as possible; and N/A
• the stockpiled malodorous material should be covered entirely by plastic tarpaulin sheets. N/A
Noise – Recommended Mitigation Measures Noise Mitigation Measures during construction Implementation Status
• only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction works;
�
• machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;
�
• plant known to emit noise strongly in one direction should, where possible, be orientated to direct noise away from the NSRs;
�
• silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction period;
�
• mobile plant should be sited as far away from NSRs as possible; �
![Page 70: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/70.jpg)
- 2 -
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status
• material stockpiles and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities; and
�
• The Contractor shall at all times comply with all current statutory environmental legislation.
�
Selection of quieter plant and working methods The Contractor shall obtain particular models of plant that are quieter than standards given in GW-TM. The list of assumed quieter plants can be found in the Table 4–14 of the EIA report. The Contractor shall select from the available models achieving the assumed sound levels while making reference to the GW-TM and BS5228: Part 1: 1997
N/A
Use of Noise Barriers Noise barriers are proposed along the site boundary to block the direct line of sight from the most affected NSRs to the major noise contribution construction phases. The height of the noise barriers ranged from 9-10m. The noise barriers shall be built before the commencement of construction works in order to ensure protection to nearby NSRs. The noise barrier should have a surface density of at least 10kg/m
2 or material providing
equivalent transmission loss. The noise barriers and hoardings should have no gaps and openings to avoid noise leakage.
P
Water Quality – Recommended Mitigation Measures Water Quality Mitigation Measures during construction Implementation Status
• The site should be confined to avoid silt runoff to the site. �
• No discharge of silty water into the storm drain and drainage channel within and the vicinity of the site.
�
• Any soil contaminated with chemicals/oils shall be removed from site and the void created shall be filled with suitable materials.
�
• Stockpiles to be covered by tarpaulin to avoid spreading of materials during rainstorms; N/A
• Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport;
�
• Chemical waste containers shall be labelled with appropriate warning signs in English and Chinese to avoid accidents. there shall also be clear instructions showing what action to take in the event of an accidental;
�
• Storage areas shall be selected at safe locations on site and adequate space shall be allocated to the storage area;
�
• Any construction plant which causes pollution to the water system due to leakage of oil or fuel shall be removed off-site immediately;
�
• Spillage or leakage of chemical waste to be controlled by using suitable absorbent materials;
�
• Chemicals will always be stored on drip trays or in bunded areas where the volume is 110% of the stored volume;
P
• Regular clearance of domestic waste generated in the temporary sanitary facilities to avoid waste water spillage.
�
• Temporary sanitary facilities to be provided for on-site workers during construction. �
• Temporary drainage channel and associated facilities will be provided to collect the surface runoff generated within the Project Area during the construction phase.
�
• Sandbags or silt traps will need to be placed to avoid silt runoff to the drainage channel draining the water in the northern ditch. Draining of the ditches should avoid rainy weather.
�
• Excavated soil which needs to be temporarily stockpiled should be stored in a specially designated area and provided with a tarpaulin cover to avoid runoff into the drainage channels.
�
![Page 71: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/71.jpg)
- 3 -
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status
Waste Management – Recommended Mitigation Measures Waste Management Mitigation Measures during construction Implementation Status
Site Clearance Waste
• The major construction works of Wo Shang Wai is in the development of residential buildings and other associated facilities (club house, tennis courts, etc). The amount of site clearance works will be limited with the exception of the excavated materials. The thin layer of vegetation removed can be stored and reused for landscaping.
�
Excavated Materials The intention is to maximize the reuse of the excavated materials on-site as fill materials.
�
Imported Filling Material The excavated/imported filling material may have to be temporarily stockpiled on-site for the construction of road embankment and foundation of viaduct substructure. Control measures should be taken at the stockpiling area to prevent the generation of dust and pollution of stormwater channels. However, to eliminate the risk of blocking drains in the wet season, it is recommended that stockpiling of excavated materials at during wet season should be avoided as far as practicable.
N/A
Construction and Demolition Materials Careful design, planning and good site management can minimise over-ordering and generation of waste materials such as concrete, mortars and cement grouts. The design of formwork should maximise the use of standard wooden panels so that high reuse levels can be achieved. Alternatives such as steel formwork of plastic facing should be considered to increase the potential for reuse.
�
The Contractor should reuse any C&D material on-site. C&D waste should be segregated and stored in different containers to other wastes to encourage the re-use or recycling of materials and their proper disposal.
�
Chemical Waste For those processes which generate chemical waste, it may be possible to find alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical waste.
N/A
Containers used for the storage of chemical wastes should:
• be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed:
�
• have a capacity of less than 450 litres unless the specification have been approved by the EPD; and
�
• display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations,
�
The storage area for chemical wastes should:
• be clearly labelled and used solely for the storage of chemical waste; �
• be enclosed on at least 3 sides; �
• have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area whichever is the greatest;
�
• have adequate ventilation; �
• be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and
�
• be arranged so that incompatible materials are adequately separated. �
Disposal of chemical waste should:
• be via a licensed waste collector; and �
• be to a facility licensed to receive chemical waste, such as the Chemical Waste Treatment Facility which also offers a chemical waste collection service and can supply the necessary storage containers, or
N/A
• to be reuser of the waste, under approval from the EPD. N/A
![Page 72: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/72.jpg)
- 4 -
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status
General Refuse Should be stored in enclosed bins or compaction units separate from C&D and chemical wastes. The Contractor should employ a reputable waste collector to remove general refuse from the site, separate from C&D and chemical wastes, on a regular basis to minimise odour, pest and litter impacts. Burning of refuse on construction sites is prohibited by law.
P
Disposal of Excavated Sediment at Sea
The requirements and procedures for excavated sediment disposal are specified under the ETWB TCW No. 34/2002 and PNAP 252. The management of the excavation, use and disposal of sediment is monitored by Fill Management Committee, whilst the licensing of marine dumping is the responsibility of the Director of Environmental Protection (DEP).
N/A
The excavated sediment would be loaded onto barges or other appropriate vessel and transported to the designated marine disposal site. Category L sediment and Category M sediment passing the biological test would be suitable for disposal at a gazetted open sea disposal ground. Category M sediment failing the biological test and Category H sediment passing the biological test would require confined marine disposal.
N/A
During transportation and disposal of the dredged sediment, the following measures should be taken to minimize potential impacts on water quality: -
N/A
• Bottom opening transport vessels should be fitted with tight fitting seals to prevent leakage of material. Excess material should be cleaned from the decks and exposed fittings of vessels before the vessel is moved.
N/A
• Monitoring of the barge loading should be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels should be equipped with automatic self-monitoring devices as specified by the DEP.
N/A
Ecology – Recommended Mitigation Measures Ecology Mitigation Measures during construction Implementation Status
Clear Definition of Site Limit
Clear definition of the site limit should be provided in order to minimize and confine the disturbance during the construction period, especially the northern limit of the Site which is adjacent to fishponds within the Conservation Area (CA) zone and are considered to be ecological sensitive receivers.
During wetland construction stage the WRA boundary will be delineated using a temporary hoarding in order to reduce disturbance to off-site habitats and wildlife. During the establishment phase this hoarding will be replaced with a 1 m high chain-link fence in order to reduce disturbance to the WRA through access by humans and dogs, and a hoarding will be established around the residential construction site.
�
Dust and Noise Suppression and Avoidance of Water Pollution
Good site practices of dust and noise suppression should be strictly implemented to ensure that disturbance is minimized to acceptable levels. Mitigation measures for the off-site disturbance impacts on the fishponds in the CA include hoarding at the northern site boundary during construction of the WRA to reduce noise and dust impacts to the adjacent habitats. Through the use of quieter plant and temporary/movable noise barriers, the noise level would be reduced significantly to an acceptable level. Hoarding at the northern boundary should be replaced with a 1 m high chain-link fence following construction and the WRA will then act as a buffer between the existing wetland areas and the residential part of the site until construction is completed. Hoarding will be retained between the WRA and ongoing construction work to avoid visual disturbance and reduce noise and dust emissions. Pollution of watercourses and sedimentary runoff will be minimized by good site practice, especially the containment of water and sediment within the site for removal.
These standard noise and air and water quality site practices are considered to be effective measures for minimizing the disturbance impact during the construction period.
�
Planning of Construction Schedule
![Page 73: Proposed Comprehensive Development at Wo …...On 12 November 2010, the Contractor issued a letter on completion of construction of WRA with reference to the EP Condition 3.3 to 3.5](https://reader036.vdocuments.net/reader036/viewer/2022070910/5f9d75b70f83203fa265bd23/html5/thumbnails/73.jpg)
- 5 -
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long Quarterly EM&A Summary Report for Nov 2010 – Jan 2011 Environmental Mitigation Measures - Implementation Status
The construction of the proposed project should be scheduled in phases. Because mitigation is preferably carried out in advance of the main works rather than after the completion of works, the construction of the WRA will commence at the start of the project. Construction work within the WRA is scheduled to take place in a single wet season, followed by 1.5 years of wetland establishment. During the wetland establishment period no noisy work will be undertaken within the WRA to minimize the disturbance to off-site habitats and wildlife.
�
Reusing Onsite Materials
Soil and plants on-site should be reused (e.g. used as fill material) as far as practical. Stock piles of these reusable materials should be stored in an appropriate area on-site. In particular, the re-use of the wetland soils and topsoil should be considered.
�
Construction of the Wetland Restoration Area The WRA will be operational within 2.5 yrs from the commencement of construction (1 year for site formation and 1.5 years for establishment) and will compensate for the predicted ecological impacts of the proposed development.
�
Landscape and Visual – Recommended Mitigation Measures Landscape and Visual Mitigation Measures during construction Implementation Status
CM1- The construction area and contractor’s temporary works areas should be minimised to avoid impacts on adjacent landscape.
�
CM2 - Screening of construction works by hoarding / noise barriers. �
CM3 - Reduction of construction period to practical minimum. �
CM4 - Topsoil, where identified, should be stripped and stored for re-use in the construction of the soft landscape works, where the soil material meets acceptable criteria and where practical. The Contract Specification shall include storage and reuse of topsoil as appropriate.
�
CM5 - Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone).
�
CM6 – Advance screen planting of noise barriers �
CM7 - Control night-time lighting and glare by hooding all lights. �
CM8 - Ensure no run-off into streams adjacent to the Project Area. �
CM9 - Protection of existing trees on boundary of site shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at S16 and Tree Removal Application stage).
�
CM10 - Trees unavoidably affected by the works shall be transplanted where practical. Trees should be transplanted straight to their destinations and not held in a nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, if applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme.
�
Legend:
� Implemented × Not implemented P Partially implemented N/A Not applicable