PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan Atomic Energy Commission INPRO Dialogue Forum on Global Nuclear Energy Sustainability Long-Term Prospects for Nuclear Energy in the Post Fukushima Era 27-31 August, 2012, Seoul, Republic of Korea.

Upload: others

Post on 21-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

PROSPECTS OF NUCLEAR POWER IN PAKISTAN

Ghulam Mustafa

Principal Engineer Applied Systems Analysis Division

Pakistan Atomic Energy Commission

INPRO Dialogue Forum on Global Nuclear Energy Sustainability Long-Term Prospects for Nuclear Energy in the Post Fukushima Era

27-31 August, 2012, Seoul, Republic of Korea.

Page 2: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

OUTLINE

2

Current Status of Power Sector in

Pakistan

Electricity demand projections and

prospective supply options

Current status of nuclear power and

expansion plans

Policy and Initiatives after Fukushima

Summary

Page 3: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Installed Capacity* : 22,477 MW (Gross)

Oil & gas : 67.0%

Coal : 0.7%

Hydro : 28.8%

Nuclear : 3.5%

Peak Demand : 21,063 MW (Last summer)

Shortages of electricity supply primarily due to:

Capacity shortfall

De-rated capacity of some plants,

Shortage of fuel (natural gas due to other uses and

furnace oil due to circular debt),

Seasonality of hydro (Capacity factor ~50%).

The above resulted in load shedding. On June 16, 2012,

load shedding was ~ 8500 MW

CURRENT STATUS OF POWER SECTOR IN PAKISTAN

* July 2011, Pakistan Energy Yearbook 2011

Fossil Fuels 67.7 %

3

1/2

Page 4: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Electricity Generation (2010-11): 95.6 TWh

Hydro: 33.6%

Oil: 35.1%

Gas: 27.3%

Coal: 0.1%

Nuclear: 3.6%

Imported: 0.3%

Access to Electricity: ~ 80% of households

Per Capita Electricity Consumption: 435 kWh

(Around one-sixth of the world average of 2,730 kWh)

Sources: Pakistan Energy Yearbook 2011, and Key World Energy Statistics 2011

CURRENT STATUS OF POWER SECTOR IN PAKISTAN

Fossil Fuels 62.5%

Heavy Dependence

on Oil/gas Mix Not Sustainable

4

2/2

Page 5: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Source: National Transmission and Dispatch Company (NTDC), 2010

-

50

100

150

200

250

300

350

400

2010 2015 2020 2025 2030 2035 2040 2045 2050

Peak D

em

and (

000 M

W)

High Scenario (GDP Growth Rate 6.5% p.a.)

Normal Scenario (GDP Growth Rate 5.9% p.a.)

Low Scenario (GDP Growth Rate 4.8% p.a.)

Estimated by Curve Fitting

2010 2020 2030 2035 2040 2050

High Scenario 20.2 50.4 117.1 169.4 226.0 373.7

Normal Scenario 20.2 45.4 97.5 134.8 177.1 283.4

Low Scenario 20.2 38.7 74.5 100.5 129.2 201.7

ELECTRICITY DEAMAND PROJECTIONS

5

1/2

Peak electricity demand projections

Page 6: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Source: National Transmission and Dispatch Company (NTDC)

2,909

5,389

4,087

-

1,000

2,000

3,000

4,000

5,000

6,000

2010 2015 2020 2025 2030 2035 2040 2045 2050

KW

h/Capita

High Scenario

Normal Scenario

Low Scenario

Estimated by Curve Fitting

ELECTRICITY DEAMAND PROJECTIONS

6

2/2

Per capita electricity demand

Page 7: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

7

Hydro (with storage/run-of-river plants)

Simple and Combined Cycle plants on indigenous

gas

Oil-fired Steam/Diesel engine (expensive option)

Nuclear

Wind

Combined Cycle plants based on imported gas.

Steam plants on domestic coal and imported coal

Solar Energy

SUPPLY OPTIONS FOR ELECTRICITY 1/5

Page 8: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Prospects of hydro power development

Potential : 55,000 MW

Already exploited : 6,634 MW (12% of the

potential)

High investment cost of major hydro-power

projects

Socio-political issues i.e., water allocation among

provinces, and resettlement of people.

Total hydro built – last 15 years: 1808 MW

SUPPLY OPTIONS FOR ELECTRICITY

8

2/5

Page 9: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Oil

Small Reserves

Pakistan meets its more than 80% oil

requirements through import

Gas

Production is already insufficient to

meet the current requirement

Demand/supply gap could be 17 billion

cubic feet per day by 2030 (Medium

Term Development Framework)

SUPPLY OPTIONS FOR ELECTRICITY

9

3/5

Page 10: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Fuel Unit

Proven reserves

Quantity For 1000 MW size plants of 30-year life

Oil Million Barrels 307 1

Gas Trillion Cubic Feet 27.6 15

Coal Billion Tonnes 3.5* 33

* Total resource potential is around 186 billion tonnes

(~ 1746 plants of 1000 MW of 30 year life)

If whole Indigenous fossil fuel reserves are used for power generation:

SUPPLY OPTIONS FOR ELECTRICITY

10

4/5

Page 11: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Wind

Potential

– Theoretical = ~ 55,000 MW

– Exploitable = ~ 11,000 MW

(considering availability of land and

assuming 23 -28% capacity factors)

Upfront Tariff for wind generation

projects is 14.7 cent/kWh

Solar

Potential is high. But have techno-

economic issues.

SUPPLY OPTIONS FOR ELECTRICITY

11

5/5

Prospects of renewable development

Page 12: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

KANUPP

Capacity : 137/90 MW

Commercial Operation : Dec 1972

Lifetime availability Factor : 55.51%

Life time capacity factor : 28.51%

CHASNUPP-2

Capacity : 325 MW

Commercial Operation : May 2011

Lifetime availability factor : 86.50%

Life time capacity factor : 84.87%

CHASNUPP-1

Capacity : 325 MW

Commercial Operation : Sep 2000

Lifetime availability factor : 76.60%

Life time capacity factor : 72.84%

12

CURRENT STATUS OF NUCLEAR POWER & EXPANSION PLANS 1/3

Nuclear Power Plants in Operation

Page 13: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Nuclear Power Plants Under Construction in the Country

CHASNUPP-4

Capacity : 340 MW

First Concrete Pour : Dec 18, 2011

Commercial Operation : Oct 31, 2017

CHASNUPP-3

Capacity : 340 MW

First Concrete Pour : Mar 4, 2011

Commercial Operation : Dec 31, 2016

13

CURRENT STATUS OF NUCLEAR POWER & EXPANSION PLANS 2/3

Page 14: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Current

20121

Projections

20222

Projections

20303

Installed Capacity (MW) 22,477 55,000 162,590

Economic Growth 3.7% 5%

Average for 13 year

7% - 8% Average for

25 year

Nuclear Capacity (MW) 787 4,345 8,800

% of installed capacity 3.5% 7.9% 5.4%

1. Economic Survey 2011-12, Finance Division, Govt. of Pakistan 2. Integrated Energy Plan (IEP) 2009-2022, Economic Advisory

Council, Ministry of Finance, March 2009 3. Medium Term Development Framework 2005-10, developed in 2005.

14

CURRENT STATUS OF NUCLEAR POWER & EXPANSION PLANS 3/3

Nuclear power deployment plans

Page 15: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

15

Continuation of operations of existing NPPs and

expansion plans

Fukushima Response Action Plan (FRAP) was

formulated for all nuclear power plants. Under

the Plan

– Internal safety reviews have been carried out,

– Safety features of the existing plants are being

further upgraded,

– Emergency response programs are being

strengthened,

– Design safety of future plants is being revisited.

POLICY AND INITIATIVES AFTER FUKUSHIMA ACCIDENT 1/3

Page 16: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Major items under FRAP

Reassess external natural hazards and

incorporate greater safety margins for

events such as earthquakes, tsunamis,

and floods

Add more sources of emergency power

supply for greater protection against

prolonged station blackout

Add diverse means of emergency

cooling

16

POLICY AND INITIATIVES AFTER FUKUSHIMA ACCIDENT 2/3

Continued

Page 17: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Ensure that spent fuel can also be

cooled under all conditions

Add means to maintain containment

integrity at all times

Emphasize Emergency Operating

Procedures (EOP’s) and Severe

Accident Management Guidelines

(SAMG’s)

Increase off-site emergency

preparedness

17

POLICY AND INITIATIVES AFTER FUKUSHIMA ACCIDENT 3/3

Page 18: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

Growing energy needs and inadequate

indigenous energy resources dictate large scale

use of nuclear power in Pakistan

Safety remains top priority in nuclear power

program of Pakistan. Fukushima accident

provides an even bigger drive to enhance safety

and develop emergency response program

Post Fukushima Policy:

• No change in nuclear power deployment plans up to 2030

18

SUMMARY

Page 19: PROSPECTS OF NUCLEAR POWER IN PAKISTAN 2-B/Countries with … · PROSPECTS OF NUCLEAR POWER IN PAKISTAN Ghulam Mustafa Principal Engineer Applied Systems Analysis Division Pakistan

19

THANK YOU.......