Proton Plan PMG 7/26/07 E Prebys 1
Proton Plan StatusProton Plan Status June June
Eric Prebys
![Page 2: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/2.jpg)
Proton Plan PMG 7/26/07 E Prebys 2
• Shutdown Schedule – Mau• Operations - Prebys• Technical Progress – Prebys
Focus on shutdown preparation
• Cost/Schedule Report – Baller
AgendaAgenda
![Page 3: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/3.jpg)
Proton Plan PMG 7/26/07 E Prebys 3
Operations
![Page 4: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/4.jpg)
Proton Plan PMG 7/26/07 E Prebys 4
Operational HighlightsOperational Highlights
• NuMI Great until 2nd horn problem knocked them off the
air
• MiniBooNE/SciBooNE Will ~hit design goal for the fiscal year in spite of
three month down time!
![Page 5: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/5.jpg)
Proton Plan PMG 7/26/07 E Prebys 5
NuMINuMI
Dotted lines are 2.4 second rep rate
Now this is a coincidence
Oops!
![Page 6: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/6.jpg)
Proton Plan PMG 7/26/07 E Prebys 6
MiniBooNE/SciBooNEMiniBooNE/SciBooNE
• Good running plus delayed shutdown => both beamlines ~hit their design goals for the fiscal year in spite of mistakes, unforeseen problems, etc.
No sense letting all the NuMI protons just sit there
![Page 7: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/7.jpg)
Proton Plan PMG 7/26/07 E Prebys 7
Total Booster Output Total Booster Output
Operations smoothly switches NuMI’s protons to BNB
![Page 8: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/8.jpg)
Proton Plan PMG 7/26/07 E Prebys 8
Technical Status
![Page 9: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/9.jpg)
Proton Plan PMG 7/26/07 E Prebys 9
Significant Activity Since Last PMGSignificant Activity Since Last PMG
• (1.1) Linac (1.2.2) Quad Power Supply Upgrade
• Continues adiabatically
(1.2.4) Linac LLRF Upgrade• Prototype FPGA board working and being used for tests• Unlikely to finish job during shutdown
– Goal: Complete at least station 5 and all prep work (VXI crates, etc) for other stations.
– Adiabatically upgrade remaining stations as hardware appears.
• (1.2) Booster Magnets, magnets, magnets
![Page 10: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/10.jpg)
Proton Plan PMG 7/26/07 E Prebys 10
Magnet Production (as of yesterday)Magnet Production (as of yesterday)
completebottleneck
![Page 11: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/11.jpg)
Proton Plan PMG 7/26/07 E Prebys 11
Latest Delivery ScheduleLatest Delivery Schedule
• Will not delay installation• Does not free up technicians until well into the shutdown
Date Magnets Available
August 3 10
August 10 11
August 17 13
August 24 15
August 31 19
September 7 23
September 14 26
![Page 12: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/12.jpg)
Proton Plan PMG 7/26/07 E Prebys 12
Prototype InstallationPrototype Installation
• All power supplies and water connected• Pulsing (hard) on beam off cycles• Proceeding with beam tests
![Page 13: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/13.jpg)
Proton Plan PMG 7/26/07 E Prebys 13
Main Injector ActivityMain Injector Activity
• (1.3) Main Injector (1.3.2) MI Collimation Systems
• Ring:– All collimators assembled in MI-65– Motion control tested– Ready for shutdown
![Page 14: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/14.jpg)
Proton Plan PMG 7/26/07 E Prebys 14
Assembled CollimatorAssembled Collimator
![Page 15: Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys](https://reader036.vdocuments.net/reader036/viewer/2022062421/56649cce5503460f94999b21/html5/thumbnails/15.jpg)
Proton Plan PMG 7/26/07 E Prebys 15
Cooldown?Cooldown?
• Current Estimate: 530 mRem/person!• Propose turning MiniBooNE/SciBooNE off one week
before shutdown
Average Normalized Dose vs Cool Down
0.0
0.2
0.4
0.6
0.8
1.0
1.2
0 10 20 30 40 50 60
Days since Beam
Data Single Exponential Double Exponential
One week