provision of project management consultancy (pmc) … · 2018. 3. 17. · authorisation letter ref...
TRANSCRIPT
TENDER DOCUMENT
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
CHIEF CONSTRUCTION ENGINEER (R&D) DELHI,
MINISTRY OF DEFENCE, DRDO
P-1 BUILDING
METCALFE HOUSE COMPLEX
DELHI – 110 054
AUTHORISATION LETTER
Ref No. CCE(R&D)D/PILKHUWA/ Chief Construction Engineer(R&D)Delhi
ENQ-III/17-18/0001 Ministry of Defence, D.R.D.O.
P-1 Building,
Metcalfe House Complex,
Delhi – 110 054
Dated : 16 Mar 2018
TENDER AND CONTRACT FOR WORKS REQUIRED
In the execution of "Provision of Project Management Consultancy (PMC) Services for DRDO Skill
Development Centre for Integrated Safety Management in Fire, Disaster and CBRN Site, Pilkhuwa".
Complete bid consisting of BOQ and other required documents should be submitted online at
CPP Portal (www.eprocure.gov.in) in Cover-1 (Eligibility & Tender Documents) & Cover-2
(Financial Bid). The Critical dates are given in NIT.
The original copy of EMD and tender cost should be submitted to this office before the date
of opening. Tender without EMD & Tender Cost is liable for rejection.
The President of India does not bind himself to accept the Lowest or any tender.
_____________________________________________
Signature of Officer
issuing the documents ___________________
Appointment : CHIEF CONSTRUCTION ENGINEER (R&D) DELHI
GOVERNMENT OF INDIA – MINISTRY OF DEFENCE
DEFENCE RESEARCH & DEVELOPMENT ORGANIZATION
TENDER DOCUMENTS
ANNEXURE – I
INVITATION OF TENDER
ANNEXURE – II
GENERAL CONDITIONS OF CONTRACTS WITH AMENDMENTS
ANNEXURE – III
SCOPE OF WORK AND COMPLETION MILES STONES
ANNEXURE – IV
SCOPE OF PROJECT MANAGEMENT CONSULTANCY (PMC)
ANNEXURE – V
LIST OF MANPOWER TO BE EMPLOYED
ANNEXURE – VI
BILL OF QUANTITIES
CHIEF CONSTRUCTION ENGINEER (R&D) DELHI,
MINISTRY OF DEFENCE, DRDO
P-1 BUILDING
METCALFE HOUSE COMPLEX
DELHI – 110 054
ANNEXURE – I
INVITATION OF TENDER
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
INVITATION OF TENDER
PROVISION OF PROJECT MANAGEMENT CONSULTANCY (PMC) SERVICES
FOR DRDO SKILL DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE, PILKHUWA.
1. RECEIPT OF TENDERS :-
Tender shall be received latest by
Dated : 05 Apr 2018 Time : 1100 Hours.
2. REFERENCE CODE FOR TENDER :
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
3. TENDER DOCUMENTS :
Tender Documents shall comprise of the following :-
Cover - I
(i) Invitation of tender - (Annexure-I)
(ii) General Conditions of Contracts with Amendments - (Annexure-II)
(iii) Scope of work and Completion Milestones - (Annexure-III)
(iv) Scope of Project Management Consultancy (PMC) - (Annexure-IV)
(v) List of Manpower - (Annexure-V)
Cover - II
(i) BOQ - (Annexure-VI)
4. SUBMISSION OF TENDER
Complete bid consisting of BOQ and other required documents should be submitted online at
CPP Portal (www.eprocure.gov.in) in Cover-1 (Eligibility & Tender Documents) and
Cover-2 (Financial Bid). The Critical dated are given in NIT.
The original copy of EMD and tender cost should be submitted to this office before the date
of opening. Tender without EMD & tender cost is liable for rejection.
Terms and conditions as stipulated in the draft contract agreement are NOT NEGOTIABLE.
Conditional offer shall be liable for rejection.
5. CLARIFICATION AND TENDER DOCUMENTS
For any clarifications in connection with these tender documents and drawings, tenderer
may contact the following addressee :-
Chief Construction Engineer(R&D)Delhi
Ministry of Defense, D.R.D.O.
P-1 Building,
Metcalfe House Complex,
Delhi – 110 054
6. INSPECTION OF SITE
Tenderer is advised to inspect site of work and acquaint himself with working conditions
including constraints and collect all necessary information for carrying out the work.
7. LANGUAGE
Tender documents including tender drawings, if any, and other information shall be
prepared and submitted in English language only.
8. VALIDITY OF TENDER
Tender and the price/rates quoted shall remain valid for acceptance for a period of
90 (Ninety) Days from the date of receipt of tender.
9. EARNEST MONEY
Tender shall be accompanied by Earnest money as stated below :-
Amount of Earnest Money : Rs.1,28,360/-
Form of Earnest Money
- Demand Draft / Fixed Deposit Receipt (FDR) /Bank Guarantee / Bankers Cheque issued
by a Nationalized Bank / Scheduled Bank.
- A part of earnest money is acceptable in the form of bank guarantee also. In such
cases 50% of earnest money or Rs. 20.00 lakhs whichever is less, will have to be deposited
in shape of prescribed above and balance can be accepted in form of bank guarantee issued
by a Nationalized/scheduled bank.
- FDR is pledged in favour of the tender inviting authority. It is in the tenderer’s own
interest to keep the FDR valid as long as it is required. There is no need for the department
to insist upon the tenderer keeping the FDR valid, since he can encash the FDR only when
it is assigned back to him by the tender inviting authority.
- The bank guarantee submitted as a part of Earnest Money shall be valid for a period of six
(06) months or more from the date of submission of the tender.
Refund of Earnest Money
- The earnest money given by all the tenderers except the lowest tenderer should be
refunded immediately after the opening of the tenders, or latest within a week from the
date of receipt of tenders.
Forfeiture of Earnest money
- If the tenderer withdraws his tender before the expiry of the validity period, or before the
issue of letter of acceptance, whichever is earlier, or makes any modification in the terms
and conditions of the tender which are not acceptable to the department, then the
Government shall, without prejudice to any other right or remedy, be at liberty to forfeit
50% of the earnest money absolutely. This provision would naturally apply only to the
lowest tenderer once the earnest money of all the tenderers except those of the lowest is
refunded.
- If contractor fails to furnish the prescribed performance guarantee within the prescribed
period, the earnest money is absolutely forfeited to the President automatically without any
notice.
- In case the contractor fails to commence the work specified in the tender documents on the
15th day of such time period as mentioned in letter of award, after the date on which the
Engineer-in-Charge issues written orders to commence the work, or from the date of
handing over of the site, whichever is later, the Government shall, without prejudice to any
other right or remedy, be at liberty to forfeit whole of the earnest money absolutely.
- If only a part of the work as shown in the tender is awarded, and the contractor does not
commence the work, the amount of the earnest money to be forfeited to the Government
should be worked out with reference to the estimated cost of the work so awarded.
- In case of forfeiture of earnest money as prescribed above paras, the tenderer shall not be
allowed to participating in the retendering process of the work.
10. COMPLETENESS OF TENDER
The scope of work, terms and conditions and other details have been specified in the tender
document. Tenderer shall prepare and submit his tender keeping in mind the requirements of
tender documents.
11. AMENDMENTS TO TENDER DOCUMENTS
OWNER shall have the right to amend delete/add to the various provisions in the
tender documents or withdraw/cancel the invitation to tender without assigning any reason
whatsoever. The amendments/errata issued by the owner shall be read carefully in
conjunction with the tender documents. The contract price/rate/amount shall be deemed to
have been worked out taking into account amendment/errata also.
12. ACCEPTANCE OF TENDER
OWNER shall not be bound to accept the lowest or any tender or to assign reasons for
non acceptance of any Tender. OWNER also reserves the right to accept a tender either
in whole or in part. Breakup of prices/items rates shall be binding on the tenderer even
in the case of acceptance of a tender in part.
13. TENDER NOT TO RESILE
The tender for the work shall remain open for acceptance for a period of Ninety (90) days
from the date of opening of tenders/ Ninety (90) days from the date of opening of financial
bid in-case tenders are invited on 2/3 bid system. If any tenderer withdraws his tender before
the said period or issue of letter of acceptance, whichever is earlier, or makes any
modifications in the terms and conditions of the tender which are not acceptable to the
department, then the government shall, without prejudice to any other right or remedy, be at
liberty to forfeit 50% of the Earnest Money. Further the tenderer shall not be allowed to
participate in the retendering process of the work.
However, tenderer shall be allowed to revise his offer only if required by tender appraisal
committee / tender standing committee based on the negotiations in order to give rebate on
overall tender or on specific items(s).
14. REGULATIONS, TAXES AND DUTIES
(a) GST as applicable shall be levied on the contract as per extant Govt. Orders.
(b) The bidder shall comply with all statutory obligations like, Registration with Labour
Deptt, Payment of ESI, EPF, Bonus and Welfare issues alongwith Proof of Payment of
taxes i.e. GST levies etc. as applicable with respect to the stated work. If found at any
stage, non-compliance of the same, the bidder will be debarred from enlistment and no
further tenders will be issued duly foreclosing the awarded work, if any.
15. PERFORMANCE GUARANTEE
The Consultant shall submit an Initial security deposit at 2.5% (Two and a half percent) of
the total consultancy fees in the form of Bank Guarantee Bond from a scheduled Bank within
15 (.Fifteen) days of award of work. The Bank Guarantee should be valid for two months
plus the consultancy period including extensions if any. In the event of failure to submit the
Bank Guarantee no payment shall be made to the consultant. The Bank guarantee shall be
released after satisfactory completion the consultancy services.
16. RETENTION MONEY
Retention money @ 5% (Five percent) of consultancy fee will be deducted from each running
bill. This Retention Money deducted from each running bill amount will be released after
consultancy work is over and completion certificate is issued by the OWNER.
17. LIQUIDATED DAMAGES FOR DELAY
(a) In case of delay in completion of services, liquidation damages at the rate of 1% (one
percent) subject to a maximum of a 10% (Ten percent) of the total contract price for delay of
every week or part thereof will be deducted from the running bill of the consultant.
(b) However, liquidated damages will not be recovered in the event of delay not
attributable to the consultant and the consultant is entitled for extension of completion time.
18. PROFESSIONAL LIABILITY INSURANCE
(a). Consultant will maintain Professional Liability Insurance including coverage for
errors and Omissions caused by Consultants negligence, breach in the performance of its
duties under this contract from an Insurance Company permitted to offer such policies in
India. Consultant will bear all expenses to maintain this insurance cover. The Insurance
coverage will be for 5 years effective from completion of consultancy services and will be
for minimum of the following amount:
i) Total Professional Fees including reimbursable expenditure made or expected to
be made to the consultants.
ii) Proceeds, the Consultants may be entitled to receive from any Insurance
Maintained by the Consultants to cover such a liability.
(b). The indemnity limit in terms of "Any One Accident" (AOA) and "Aggregate limit on
the policy period" (AOP) should not be less than the amount stated in the contract. In case of
joint venture or in association', the policy should be in the name of joint venture / in
association entity and not by the individual partners of the joint venture/association.
(c). In the event of failure to comply the above clause by the consultant no further tender
enquiry will be issued to the consultant in future.
19. TERMS OF PAYMENT:
The payment will be made on monthly basis as per BOQ and other terms and conditions.
20. General Conditions of Contracts and all amendments as applicable to the Project
Management Consultancy will be enforced.
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY
This deed of guarantee made on _____ day _____________ Two Thousand Eighteen between
_________________________ (Name of Banker) having its Registered office at ________________
(hereinafter referred to as the Surety) and President of India acting by and through
Chief Construction Engineer(R&D)Delhi, P-1 Building, Metcalfe House Complex, Delhi –
110 054 (herein after referred to as the "OWNER").
WHERE AS _____________________________________________ (Contractor's name) hereinafter
referred to as "CONTRACTOR" having their registered office at
_______________________________________ is bound to deposit with the owner by way of
Earnest money Rs.___________________________ (Rupees
__________________________________________ Only) in connection with their tender for
_______________________________ (name of work) with reference to "OWNER" tender enquiry
No. ____________________________ dated ___________________ as per specifications and
terms and conditions enclosed therein. Whereas the contractor as per clause No. 09 of invitation to
tender has agreed to furnish a Bank Guarantee valid upto ________________ (date) instead of
deposit of earnest money.
NOW THIS WITNESSETH
That the surety in consideration of the above Tender made by the CONTRACTOR to the OWNER
hereby undertakes to guarantee payment on demand to the owner of the said amount of
Rs.1,28,360/- which the contractor is bound to deposit with the OWNER by way of earnest money
in connection with his tender.
Not withstanding anything contained in the foregoing, the surety's liability under the guarantee
is restricted to Rs.1,28,360/- (Rupees One Lakh Twenty Eight Thousand Three Hundred Sixty
only). The guarantee shall remain in force and affective upto and shall expire and become
ineffective on intimation there-of being given to the surety by the owner in which event this
guarantee shall stand discharged.
This guarantee shall not be affected by any change in the constitution of the OWNER,
CONTRACTOR or the surety.
The OWNER shall be eligible to make any claim under this guarantee only if the contractor
submitting the tender resiles from the offer or modify the terms and conditions thereof in a manner
not acceptable to the OWNER or fail to sign the contract and deposit initial security deposit within
10 (Ten) days after the OWNER has advised the contractor the acceptance for (name of work) on
mutually agreed terms and conditions. The OWNER's decision in this regard shall be firm and
binding.
The surety cannot revoke this guarantee during its currency except by the previous consent of the
OWNER in writing.
Not with standing anything contained hereinabove unless a demand or claim under this guarantee is
made on the surety in writing on or before the surety shall be discharged from all liabilities under
this guarantee thereafter.
for and on behalf of
(Banker's Name)
AGREEMENT
This AGREEMENT made and entered into this ____ day of __________ Two Thousand Eighteen
between the President of India acting by and through Chief Construction Engineer (R&D) Delhi,
P-1 Building, Metcalfe House Complex, Delhi – 110054 hereinafter referred to as the
"OWNER" (which expression shall, unless excluded by or repugnant to the context or the meaning
thereof, be deemed to include its successors and assigns) of ONE PART.
AND
M/s._____________________________________ having their registered office and principal
place of business at __________________________________________________________
hereinafter referred to as the "CONTRACTOR" (which expression shall unless excluded by or
repugnant to the context or the meaning thereof, be deemed to include its successors and assigns) of
the OTHER PART.
WITNESSETH THAT
WHEREAS, the OWNER invited the CONTRACTOR to submit tender for
_________________________________________________________________________________
_________________________________________________________________________________
AND
WHEREAS, the CONTRACTORS submitted their tenders to the OWNER for execution of the
work in accordance with the tender documents including technical specifications, schedule of
items and tender drawings vide his letters
AND
WHEREAS, the OWNER has accepted the tender submitted by the CONTRACTOR for the
execution of the aforesaid work with reference to letter No.
_________________________________________________________________________________
_________________________________________________________________________________
AND WHEREAS, the CONTRACTOR has agreed to execute the aforesaid work on the terms and
conditions as stated in tender documents & general conditions of contract and has also agreed to
submit to the OWNER initial security deposit required to be paid on the date of signing of the
agreement, in accordance with the Tender.
NOW , THEREFORE, in consideration of the foregoing promises and mutual covenants herein
contained, the parties hereby agree to fulfill the obligations stated in the tender documents
alongwith contractors offer.
IN WITNESS
WHEREOF THE Chief Construction Engineer (R&D) Delhi, P-1 Building, Metcalfe House
Complex, Delhi - 110054 has set his hand for & on behalf of PRESIDENT OF INDIA.
AND
Sh. duly authorized representative of the CONTRACTOR for and on behalf of
M/s. ____________________ has affixed his signature and the seal of the said company in
accordance with Articles of Association.
Signed and delivered by Signed and delivered by
( ) ( )
For and on behalf of CHIEF CONSTRUCTION ENGINEER (R&D) DELHI
M/s.
Accepting Officer
For and on behalf of PRESIDENT OF INDIA
WITNESSES
1. 1.
2. 2.
PROFORMA FOR INTEGRITY PACT
This Integrity Agreement is made at ……................... on this ….......... day of ……………2018. BETWEEN
President of India represented through Chief Construction Engineer(R&D)Delhi Ministry of Defence, DRDO
P-1 Building, Metcalfe House Complex, Delhi – 110 054 , (Hereinafter referred as the (CCED) ‘OWNER’,
which expressi on shall unless repugnant to the meaning or context hereof include its Successors and permitted assigns)
AND ………………….. through ……. (Hereinafter referred to as ……… in M/s. …………………… “Bidder/CONTRACTOR” and which expression shall unless repugnant to the meaning or context hereof include its successors and permitted assigns) Preamble WHEREAS the OWNER has floated the e-Tender …… (hereinafter referred to as “Tender.........”) and intends to award, under laid down organizational procedure, contract for “Provision of Project Management
Consultancy (PMC) Services for DRDO Skill Development Centre for Integrated Safety Management
in Fire, Disaster and CBRN Site, Pilkhuwa” hereinafter referred to as the “Contract”.
AND WHEREAS the OWNER values full compliance with all relevant laws of the land, rules, regulations, economic use of resources and of fairness/transparency in its relation with its Bidder(s) and CONTRACTOR(s). AND WHEREAS to meet the purpose aforesaid both the parties have agreed to enter into this Integrity Agreement (hereinafter referred to as “Integrity Pact” or “Pact”), the terms and conditions of which shall also be read as integral part and parcel of the Tender/Bid documents and Contract between the parties. NOW, THEREFORE, in consideration of mutual covenants contained in this Pact, the parties hereby agree as follows and this Pact witnesses as under: Clause 1: Commitment of the OWNER 1) The OWNER commits itself to take all measures necessary to prevent corruption and to observe the following principles:
(a) No employee of the OWNER, personally or through any of his/her family members, will in connection with the Tender, or the execution of the Contract, demand, take a promise for or accept, for self or third person, any material or immaterial benefit which the person is not legally entitled to.
(b) The OWNER will, during the Tender process, treat all Bidder(s) with equity and reason. The OWNER will, in particular, before and during the Tender process, provide to all Bidder(s) the same information and will not provide to any Bidder(s) confidential / additional information through which the Bidder(s) could obtain an advantage in relation to the Tender process or the Contract execution.
(c) The OWNER shall endeavour to exclude from the Tender process any person, whose conduct in the past has been of biased nature.
2) If the OWNER obtains information on the conduct of any of its employees which is a criminal offence under the Indian Penal code (IPC)/Prevention of Corruption Act, 1988 (PC Act) or is in violation of the principles herein mentioned or if there be a substantive suspicion in this regard, the OWNER will inform the Chief Vigilance Officer an d in addition can also initiate disciplinary actions as per its internal laid down policies and procedures.
Clause 2: Commitment of the Bidder(s)/CONTRACTOR(s)
1) It is required that each Bidder/CONTRACTOR (including their respective officers, employees & agents) adhere to the highest ethical standards, & report to the Government /Department all suspected acts of fraud or corruption or Coercion or Collusion of which it has knowledge or becomes aware, during the tendering process & throughout the negotiation or award of a contract.
2) The Bidder(s)/CONTRACTOR(s) commits himself to take all measures necessary to prevent corruption.
He commits himself to observe the following principles during his participation in the Tender process and
during the Contract execution:-
a) The Bidder(s)/CONTRACTOR(s) will not, directly or through any other person or firm, offer, promise or give to any of the OWNER’s employees involved in the Tender process or execution of the Contract or to any third person any material or other benefit which he/she is not legally entitled to, in order to obtain in exchange any advantage of any kind whatsoever during the Tender process or during the execution of the Contract.
b) The Bidder(s)/CONTRACTOR(s) will not enter with other Bidder(s) into any undisclosed agreement or understanding, whether formal or informal. This applies in particular to prices, specifications, certifications, subsidiary contracts, submission or non-submission of bids or any other actions to restrict competitiveness or to cartelize in the bidding process.
c) The Bidder(s)/CONTRACTOR(s) will not commit any offence under the relevant IPC/PC Act. Further the Bidder(s)/CONTRACTOR(s) will not use improperly, (for the purpose of competition or personal gain), or pass on to others, any information or documents provided by the OWNER as part of the business relationship, regarding plans, technical proposals & business details, including information contained or transmitted electronically.
d) The Bidder(s)/CONTRACTOR(s) will, when presenting his bid, disclose (with each tender as per proforma enclosed) any & all payments he has made, is committed to or intends to make to agents, brokers or any other intermediaries in connection with the award of the Contract.
3) The Bidder(s)/CONTRACTOR(s) will not instigate third persons to commit offences outlined above or be an accessory to such offences. 4) The Bidder(s)/CONTRACTOR(s) will not, directly or through any other person or firm indulge in fraudulent practice means a willful misrepresentation or omission of facts or submission of fake/forged documents in order to induce public official to act in reliance thereof, with the purpose of obtaining unjust advantage by or causing damage to justified interest of others and/or to influence the procurement process to the detriment of the Government interests. 5) The Bidder(s)/CONTRACTOR(s) will not, directly or through any other person or firm use Coercive Practices (means the act of obtaining something, compelling an action or influencing a decision through intimidation, threat or the use of force directly or indirectly, where potential or actual injury Jun befall upon a person, his/her reputation or property to influence their participation in the tendering process). Clause 3: Consequences of Breach
Without prejudice to any rights that Jun be available to the OWNER under law or the Contract or its established policies & laid down procedures, the OWNER shall have the following rights in case of breach of this Integrity Pact by the Bidder(s)/CONTRACTOR(s) & the Bidder/ CONTRACTOR accepts & undertakes to respect & uphold the Principal/OWNER’s absolute right:
1) If the Bidder(s)/CONTRACTOR(s), either before award or during execution of Contract has committed a
transgression through a violation of Clause 2 above or in any other form, such as to put his reliability or credibility in question, the OWNER after giving 14 days notice to the CONTRACTOR shall have powers to disqualify the Bidder(s)/CONTRACTOR(s) from the Tender process or terminate/determine the Contract, if already executed or exclude the Bidder/ CONTRACTOR from future contract award processes. The imposition & duration of the exclusion will be determined by the severity of transgression
& determined by the Principal/OWNER. Such exclusion Jun be forever or for a limited period as decided by the Principal/OWNER.
2) Forfeiture of EMD/Performance Guarantee/Security Deposit: If the OWNER has disqualified the
Bidder(s) from the Tender process prior to the award of the Contract or terminated/ determined the Contract or has accrued the right to terminate/determine the Contract according to Clause 3(1), the OWNER apart from exercising any legal rights that Jun have accrued to the Principal/OWNER, Jun in its considered opinion forfeit the entire amount of Earnest Money Deposit, Performance Guarantee & Security Deposit of the Bidder/ Contractor.
3) Criminal Liability: If the OWNER obtains knowledge of conduct of a Bidder or Contractor, or of an employee or a representative or an associate of a Bidder or Contractor which constitutes corruption within the meaning of Indian Penal code (IPC)/Prevention of Corruption Act, or if the OWNER has substantive suspicion in this regard, the OWNER will inform the same to law enforcing agencies for further investigation.
Clause 4: Previous Transgression
1) The Bidder declares that no previous transgressions occurred in the last 5 years with any other Company* in any country confirming to the anticorruption approach or with Central Government or State Government or any other Central/State Public Sector Enterprises in India that could justify his exclusion from the Tender process.
2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the Tender process or action can be taken for banning of business dealings/holiday listing of the Bidder/Contractor as deemed fit by the OWNER.
3) If the Bidder/CONTRACTOR can prove that he has resorted/recouped the damage caused by him and has installed a suitable corruption prevention system, the OWNER Jun, at its own discretion, revoke the exclusion prematurely. Clause 5: Equal Treatment of all Bidders/CONTRACTOR(s)/Sub CONTRACTOR(s)
1) The Bidder(s)/CONTRACTOR(s) undertake(s) to demand from all subcontractors a commitment in conformity with this Integrity Pact. The Bidder/CONTRACTOR shall be responsible for any violation(s) of the principles laid down in this agreement/Pact by any of its Sub-contractors/sub-vendors. 2) The OWNER will enter into Pacts on identical terms as this one with all Bidders and Contractors .
3) The OWNER will disqualify Bidders, who do not submit, the duly signed Pact between the OWNER and the bidder, along with the Tender or violate its provisions at any stage of the Tender process, from the Tender process. Clause 6- Duration of the Pact This Pact begins when both the parties have legally signed it. It expires for the Contractor/Vendor 24 months after the completion of work under the contract or till the continuation of defect liability period, whichever is more and for all other bidders, till the Contract has been awarded. If any claim is made/lodged during the time, the same shall be binding and continue to be valid despite the lapse of this Pacts as specified above, unless it is discharged/determined by the Competent Authority, DRDO.
Clause 7- Other Provisions
1) This Pact is subject to Indian Law, place of performance & jurisdiction is the Headquarters of the Division of the OWNER, who has floated the Tender. 2) Changes and supplements need to be made in writing. Side agreements have not been made. 3) If the Contractor is a partnership or a consortium, this Pact must be signed by all the partners or by one or more partner holding power of attorney signed by all partners & consortium members. In case of a Company, the Pact must be signed by a representative duly authorized by board resolution.
4) Should one or several provisions of this Pact turn out to be invalid; the remainder of this Pact remains valid. In this case, the parties will strive to come to an agreement to their original intensions. 5) It is agreed term & condition that any dispute or difference arising between the parties with regard to the terms of this Integrity Agreement/Pact, any action taken by the OWNER in accordance with this Integrity Agreement/Pact or interpretation thereof shall not be subject to arbitration. Clause 8 - Legal and Prior Rights All rights and remedies of the parties hereto shall be in addition to all the other legal rights & remedies belonging to such parties under the Contract and/or law & the same shall be deemed to be cumulative & not alternative to such legal rights & remedies aforesaid. For the sake of brevity, both the parties agree that this Integrity Pact will have precedence over the tender documents with regard any of the provisions covered under this Integrity Pact.
IN WITNESS WHEREOF the parties have signed and executed this Integrity Pact at the place and date first above mentioned in the presence of following witnesses: ................................................................
(For and on behalf of OWNER) ........................................................................
(For and on behalf of Bidder/CONTRACTOR)
ANNEXURE – II
GENERAL CONDITIONS OF CONTRACTS WITH
AMENDMENTS
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
RESTRICTED
RDCE WP – 1999
APPENDIX ‘E’
GENERAL CONDITIONS OF CONTRACTS
AS APPLICABLE
TO
R & D CONSTRUCTION ESTABLISHMENTS
DEFENCE RESEARCH & DEVELOPMENT ORGANIZATION
MINISTRY OF DEFENCE
NEW DELHI
RESTRICTED
CONTENTS
Article No. Description
1. Definitions 2. Scope of Work
3. Completion time
4. Contract Price 5. Terms of Payment
6. Taxes and Dues
7. Responsibility of the Owner
8. Obligations of the Contractor 9. Standard of Work
10. Responsibility for Completion
11. Exclusions 12. Rates for Extra Items
13. Measurement of Works
14. Engineer’s Authority 15. Changes
16. Working Hours
17. Drawings, Specification and Schedule of Items
18. Contractor’s Representative at Site 19. Rejection
20. Co-ordinations with other contractors
21. Liquidated Damages for Delay 22. Completion Certificate
23. Maintenance Guarantee
24. Materials
25. Other Persons engaged by Owner 26. Misuse of Works
27. Refund/Forfeiture of Security Deposit
28. Inspection and Test 29. Access to Work
30. No Interest Payable
31. Materials not incorporated in Works 32. Site Conditions
33. Owner’s Claim
34. Sub –Contracting
35. Passage of Property and Risk 36. Safety and Security
37. Accident or Injury to Workmen
38. Deductions from Contract Price 39. Compliance with Statutory & other regulations
40. Indemnity
41. Patent 42. Preservation of Peace
43. Operation
44. Secrecy
45. Suspension and Termination 46. Force Majeure
47. Arbitration
48. Liquidation/Termination 49. Effective date of Agreement
50. Annexures to Agreement
51. Entire Agreement
52. Amendment to Agreement 53. Waiver 54. Assignment
55. Copies 56. Stamp Duty
57. Notices 58. Amendments 01 to 06
ARTICLE – 1 : DEFINITIONS
In this document as hereinafter defined, the following words and expressions shall have the meanings assigned to them except where the agreement explicitly provides :-
1.01 “AGREEMENT” shall mean contract agreement together with tender documents and acceptance
thereof including annexures, drawings, correspondence, if any, referred to in the Agreement.
1.02 “OWNER” shall mean the President of India, acting by and through Chief Construction Engineer
(R&D) Delhi, D.R.D.O. Ministry of Defence, P-1 Building, Metcalfe House Complex, Delhi – 110
054.
1.03 “CONTRACTOR” shall mean M/s.____________________________________________________
having their registered office and principal place of business at
__________________________________________________________________________________
______________________________________________
1.04 “ENGINEER” shall mean ENGINEER nominated by Chief Construction Engineer (R&D) Delhi,
D.R.D.O. Ministry of Defence, P-1 Building, Metcalfe House Complex, Delhi – 110 054.
1.05 “SITE ENGINEER” shall mean the Engineer nominated by Chief Construction Engineer (R&D) at
site, responsible for day to day supervision of the work.
1.06 “WORK” shall mean all work, supplies and services to be executed / made / performed by the
CONTRACTOR under the Agreement.
1.07 “SITE” shall mean the area identified by CCE (R&D) for the scope of work indicated in Article – 2 of
general conditions of Contract.
1.08 “SPECIFICATIONS” shall mean all technical specifications, statements of technical data, schedule of
items / quantities / rates, drawings, sketches, Indian and / or British standards, instructions etc.
according to which the work shall be executed by the CONTRACTOR.
1.09 “DRAWINGS” shall mean any and all drawings including working drawings and sketches or any
modifications enclosed with the tender documents of such drawings, working drawings and sketches
as may be issued from time to time by the ENGINEER to the CONTRACTOR for execution of the
work.
1.10 (a) “Contract Price” shall mean the price for which the Contract is accepted as per the Letter of
Intent.
(b) “Final Contract Sum”: shall mean the sum to be paid by the OWNER to the CONTRACTOR
for executing the work and shall be computed on the basis of actual net quantities of various items of
work executed at the applicable rates as per the schedule of items/quantities/rates forming part of the
Agreement.
1.11 “CONSTRUCTION PLANT AND EQUIPMENT” shall mean all equipment, machinery, appliances,
tools, tackles etc. of whatever nature required in or about the execution, completion and maintenance
of the works or temporary works.
1.12 “TEMPORARY WORKS” shall mean all temporary / enabling works of every kind required in or
about the execution, completion and maintenance of the works.
1.13 “APPROVAL” shall mean approval in writing by the ENGINEER or any authorised representative of
the OWNER.
1.14 “MONTH” shall mean calendar month as per the Gregorian Calendar.
ARTICLE – 2 : SCOPE OF WORK
2.01 The scope of work to be executed by the Contractor under this Agreement shall include all work,
supplies and services for construction, completion and maintenance as specified in the tender
documents (or as finalised) and stated below :-
2.02 The work shall be executed strictly in accordance with the working drawings, specifications, schedule
of items, quantities / rates, sketches and written and oral instructions (to be subsequently confirmed in
writing) of the ENGINEER or any representative of Chief Construction Engineer (R&D). The
working drawings marked “good for construction” shall be issued progressively to suit the
construction schedule.
2.03 In the case of item rate contracts tender drawings issued at the time of Invitation to Tenders are for
guidance only. The actual work shall be carried out as per the working drawings stated under Article
2.02 above.
2.04 In case of any discrepancy in the drawings or between the drawings, technical specifications, and / or
schedule of items / quantities, the CONTRACTOR shall seek clarifications from the ENGINEER and
shall carry out the work in accordance with the clarifications furnished by the ENGINEER. In
absence of specifications for any particular item of work, the CONTRACTOR shall also carry out the
work as per the instructions given by the ENGINEER. Several documents forming the contract
agreement are to be taken as complimentary to one another.
The following order of preference shall be observed for interpretation of the contract :-
1. Description in schedule ‘A’ / Bill of quantities.
2. Technical specifications.
3. Drawings.
4. General conditions of contract.
Any error in description, quantity or rate in schedule ‘A’ / Bill of quantities or any omission
thereof shall not initiate the contract or release the CONTRACTOR from execution of whole or any
part of the works comprised therein according to drawings and specifications or from any of his
obligations under the contract.
2.05 The scope of work to be carried out by the CONTRACTOR shall also include the following :-
i. Setting out of the works in respect of position, level, dimensions, alignments, etc. including
establishment of bench marks, survey reference points, etc.
ii. Clearance of the site.
iii. Site levelling / terracing within the limits as shown in the drawings or as directed by the
ENGINEER.
iv. Disposal of debris, excavated materials, etc. as per the instructions of the ENGINEER.
v. Testing of water, soil and concrete.
vi. Pumping out rain water / underground water from foundations, excavations and drainage of
surface water from work site.
vii. All scaffolding, shorting, centering, shuttering works, etc.
viii. Running and maintenance of all construction plants and equipments, tools and tackles, etc.
a) All temporary / enabling works such as approach road to the site, water supply, drainage and
sewerage, power supply including diesel generator set, temporary offices, stores, construction
yard, canteens, toilet blocks, labour camp, fencing, etc.
b) Protection and maintenance of trees, shrubs, green and other surfaces as instructed by the
ENGINEER.
c) Any other work required in connection with the execution of the contract work.
The cost of all the above mentioned works shall be deemed to be included in the rates for various
items of work although such inclusion may not be specifically spelt out.
2.06 Whether specified elsewhere in the Agreement or not, the CONTRACTOR shall provide all materials
(including steel and cement unless specifically spelt out in the agreement otherwise), labours of every
description, energy and water and all tools, tackles, plant and transport necessary for proper execution
of the work to the entire satisfaction of the OWNER.
2.07 Where specified, the construction power and construction water will be provided free of cost by the
OWNER at a point. However, CONTRACTOR has to make his own tapping arrangements for
drawing the construction power and construction water from these points upto the works spot at his
own cost.
ARTICLE – 3 : COMPLETION TIME
3.01 The works shall be completed in all respects and handed over by the CONTRACTOR to the OWNER as described in Article – 2 and within the time stipulated in the Agreement.
3.02 In order to achieve the completion time as stated above, the CONTRACTOR shall submit to the OWNER with 2 (two) weeks from the effective date of Agreement a detailed Bar chart/ PERT
Network showing all the activities including mobilisation, site clearance, procurement of major
construction materials like steel and cement, excavation, foundation work, sanitary and water supply
work, etc. The list of activities for which the Bar chart / PERT network has been worked out and their commencement, duration and completion shall be subject to the approval of the OWNER.
3.03 Detailed Bar chart/PERT Network as specified above and approved by the OWNER shall form part of the Agreement.
3.04 The CONTRACTOR shall not be allowed any extension of completion time except in the following cases :-
(i) Force Majeure. The extension of completion time shall be as per Article-46.
(ii) Major changes or substantial addition to the work ordered by the OWNER adversely affecting the completion time. Extension of time shall be as per decision of the OWNER.
(iii) Delay in handing over site etc.
3.05 The works shall be deemed to be completed when upon notice by the CONTRACTOR the
ENGINEER has inspected the works and satisfied himself that the works have been fully completed
strictly in accordance with the Agreement and necessary completion certificate issued to the CONTRACTOR by the OWNER.
3.06 The OWNER shall have the right to take possession of or use any completed part of the work at any
time. Such possession or use shall not be deemed to be completion and acceptance of any work done not in accordance with the Agreement.
3.07 The CONTRACTOR shall submit to the ENGINEER monthly / fortnightly Progress Reports in
prescribed proforma listing progress achieved during the reporting period on activities as per Article
3.02.
ARTICLE – 4 : CONTRACT PRICE
4.01 In consideration of the work, supplies and services to be executed / made / performed by the
CONTRACTOR as per Article-2 above and for any other obligation to be met by the CONTRACTOR
under the Agreement, the OWNER shall pay to the CONTRACTOR, a Contract price Rs………………………………………………………………………………………………………
………………………..…………………………………………………………………………………
…………………………………...
4.02 The Contract Price as stated in Article 4.01 has been arrived at based on the quantities and the actual
rates as finalised and stated in the agreement. The contract sum to be paid to the CONTRACTOR
shall be arrived based on the actual net quantity executed under various items of work as per the schedule of items.
4.03 Items rates as stated under the schedule of items / rates shall be firm and fixed and binding on the CONTRACTOR during the period of this Agreement irrespective of any variations of quantities
stated therein upto +/- 20% variations of Contract price. For variations beyond 20% (Twenty percent)
of Contract price, applicable item rates shall be mutually discussed and agreed. The item rates on
above shall not be subjected to any variations on account whatsoever, whether statutory or otherwise.
4.04 Where the agreement provides for issue of cement & steel by the OWNER to the CONTRACTOR,
the base rates for the purpose of arriving of contract sum shall be based on the price of cement and steel as stipulated in the tender documents.
4.05 Item rates of various items of work shall be deemed to include cost of all materials, labour, tools,
plants, usage of equipments, templates, scaffoldings, supports approaches etc., security & safety measures, power, fuel, lubricants, consumables, transport, handling, storage, approval, checking,
testing, insurance, taxes, royalties, other revenue expenses, temporary facilities like roads, drains etc.,
facilities for testing/checking temporary accommodation, services, pumping out water, disposal of rubbish/surplus earth, supervision, overheads, profits etc. and such other items as may be required for
executing in full, the particular item of work.
4.06 Contract price / item rates shall include all taxes, fees and dues as per Article-6.
4.07 No reimbursement shall be made for escalation in price of materials, labour and / or fuel during the
contract period on any account statutory or otherwise.
4.08 In case the CONTRACTOR is allowed to use any material other than the ones specifically provided
for the difference in cost shall be deducted as per the prevailing market rate and in no case a higher rate shall be allowed.
4.09 Item rates payable to the CONTRACTOR for such items, for which no provision has been made in the schedule of items / rates, shall be determined as per Article – 12.
4.10 For payment of Contract sum, measurement of works under various items of work shall be made as
per the provision under Article – 13.
4.11 The CONTRACTOR shall submit an initial Security Deposit of 2.5% (Two and a half percent) of the
initial contract price in the form of a Bank Guarantee Bond or FDR of any scheduled Bank within 10 (Ten) days of acceptance of tender. The security deposit shall be released on expiry of maintenance
guarantee period and satisfactory completion of rectification of defects and on issuance of “Final
Acceptance Certificate” by the OWNER and submission of “No Claim Certificate” by the
CONTRACTOR (In case of increase in final contract sum the additional 2.5% {Two and a half percent} security deposit shall be deposited in the form of Bank Guarantee Bond / FDR before release
of final payment).
4.12 The rates quoted by the CONTRACTOR deemed to include all preparatory works required for
satisfactory completion of work and any rectification / replacement of works carried out as part of
defect liability.
ARTICLE – 5 : TERMS OF PAYMENT
5.01 In respect of Civil Works subject to any deduction which the OWNER may be authorised to make
under the Agreement, the CONTRACTOR shall receive payment from the OWNER as follows :
i) 10% (Ten percent) of the Contract price as interest free mobilisation advance within 02 (Two)
weeks after the effective date of Agreement, or date of deposit of initial security, whichever
is later against a Bank Guarantee for an equal amount in the format prescribed by the
OWNER, valid upto issue of “Completion Certificate” by the OWNER. The value of Bank
Guarantee shall be progressively reduced to the extent of outstanding Mobilisation Advance
to be adjusted / recovered. Any outstanding Bank Guarantee Bond shall be released when the
entire work is completed as per the Agreement and on issuance of “Completion Certificate”
by the ENGINEER.
ii) (a) 75% (Seventy five percent) of the value of imperishable materials such as aggregate, electrical, sanitary fittings, etc. brought to site which will be incorporated in the
works excluding cement and steel. This shall be recovered from running bills on pro-rata
according to the quantity of work billed for. This will be paid on sufficient documentary proof and on certification by the ENGINEER and acceptance by the OWNER.
(b) 85% (Eighty five percent) of the cost of cement and steel procured by the CONTRACTOR
and brought to site for incorporation into the works. This shall be recovered from running bills on pro-rata according to the quantity of work billed for. This will be paid on sufficient
documentary proof and on certification by the ENGINEER and acceptance by the OWNER.
iii) 80% (Eighty percent) of the value of the work done less recoveries in running bill payments
according to the progress of works performed as measured as per Article -13.
iv) Balance 10% (Ten percent) of the value of work done but not paid in running bills shall be
held as retention money. It shall be released in stages, when the retention money accumulated
exceeds Rs.2 (Two) lakhs on production of Bank Guarantee Bond of an equivalent amount so
released and valid upto the date of expiry of maintenance period. Alternatively, the
CONTRACTOR may produce a Bank Guarantee Bond for an equal value valid upto the date
of expiry of maintenance period, the retention money recovered in each running bill can be
released to the extent of the value of such Ban Guarantee Bond. On completion of entire
work as per the Agreement and on issuance of completion certificate by OWNER, the value
of Bank Guarantee submitted for release of retention money of 10% held in running bills
payment shall be reduced 2.5% (Two and a half percent) on final contract sum shall be
released on completion of all works and on issuance of completion certificate by the OWNER.
v) The Bank Guarantee totalling to 5% (Five percent) of the final contract sum {inclusive of
initial Security Deposit of 2.5% (Two and a half percent)} shall be released on expiry of the
maintenance period and satisfactory completion of rectification of defects and on issuance of
“Final Acceptance Certificate” by the OWNER and submission of “No Claim Certificate” by
the CONTRACTOR.
5.02 Adjustment of final contract sum shall be made in the last 3 (three) consecutive running bill payment
based on the final quantities against various items of work. Adjustment shall also be made in the
contract sum due to extra work executed, if any, as per requirement of ENGINEER/OWNER in those 3 (three) last running bill payments.
5.03 In respect of E&M Works subject to any deduction which the OWNER may be authorised to make
under the agreement, the CONTRACTOR shall receive payment from the OWNER as follows :-
(i) 10% (Ten percent) of the contract price as down payment against submission of Bank Guarantee
Bond for an equal amount valid till the date of completion. Bank Guarantee Bond submitted
against down payment shall be released when the entire work is completed and on issuance of Completion Certificate.
(ii) 10% (Ten percent) of the Contract Price against submission and approval of Engineering drawings & details.
(iii) 50% (Fifty percent) of the Contract Price against delivery of all materials and equipments at site.
(iv) 15% (Fifteen percent) of the Contract Price against erection and commissioning on pro-rata basis.
(v) Balance 15% (Fifteen percent) of the Contract Price on completion of the entire work and testing and handling over to the OWNER against submission of performance Bank Guarantee Bond for
5% of the completion cost, valid for a period of 12 months from the date of completion of work.
The performance Bank Guarantee Bond held for 5% of the completion cost shall be in addition to the
initial security deposit of 2.5% (Two and a half percent) and shall be released on expiry of
maintenance period after satisfactory conduct of performances test and completion of rectifications if
any and issuance of “Final Acceptance Certificate” by the OWNER and submission of “No Claim Certificate” by the CONTRACTOR.
5.04 All running payments shall be regarded as payment by way of advance against final payment only and not as payment for the work completed till the date of final payment. The running payment made
shall not preclude the liability of the CONTRACTOR to finally complete the work strictly in
accordance with the specifications and drawings, if required by re-constructing faulty work.
5.05 All invoices for running payments as well as for final payments shall be submitted in prescribed forms
(cost of forms to be borne by the CONTRACTOR) duly recommended by the ENGINEER and supported by detailed measurement of items of work in accordance with Article 13.
5.06 The final bill shall be submitted by the CONTRACTOR within 2 (Two) months from the date of
completion of the works accompanied by :
(a) Completion certificate issued by the OWNER.
(b) No claim Certificate by the CONTRACTOR. (c) Consumption Statement of steel and cement certified by the ENGINEER.
(d) Consumption Statement for all other imperishable materials like bricks, electrical and sanitary
fittings etc. for which advance has been given by the OWNER as mentioned above in Article – 5.01 (ii).
(e) Original guarantee furnished by CONTRACTOR’s Suppliers for applicable items.
(f) Maintenance guarantee by the CONTRACTOR.
(g) Test Certificate for items and materials. (h) Completion drawings showing the layout, invert levels, locations, sizes of pipelines and all
fittings and fixtures in respect of internal water supply and sanitary fittings.
(j) Completion drawings showing layout of all electrical fittings and fixtures, circuit diagram and sizes and capacities of all cables and other installations in respect of internal electrification.
(k) Completion drawings showing the layout of pipelines, electrical cables, sewer lines,
manholes, septic tank, soak pit, drains, street lighting etc. indicating actual invert levels of critical
points in respect of all external services. (l) Completion drawings showing the layout and cross section details of road/pavements with
specifications alongwith location and other details of culverts/bridges and other pipe crossings
etc. (m) Periodical Services Measurement Books.
5.07 Payments dues and payable by the OWNER shall be made within 15 (fifteen) days from the date of
receipt of invoices supported by requisite details of measurements certified by the ENGINEER.
5.08 All payments to the CONTRACTOR shall be made by Account Payee Cheque or Demand Draft. All
Bank charges in connection with payment to the CONTRACTOR shall be to the account of the
CONTRACTOR.
5.09 Bank Guarantee Bonds only from Nationalised Banks or Scheduled Banks shall be accepted by the
OWNER.
ARTICLE – 6 : TAXES AND DUES
6.01 All taxes including sales tax on works contract if any, dues, fees, levies, octroi, excise or other charges levied on the CONTRACTOR in connection with the contract work shall be borne and paid
by the CONTRACTOR. No increase / decrease in taxes / duties, statutory or otherwise, after
submission of tenders and during the execution of the works, shall be adjusted.
6.02 All Bank Charges, taxes, dues and all other charges in connection with payment to be made to the
CONTRACTOR and in connection with Bank Guarantee Bond shall be borne and paid by the CONTRACTOR.
6.03 Income Tax at the rate of 02 (Two) percent of the gross value of the contract and surcharge there on
as applicable, shall be progressively deducted from the CONTRACTOR’s bills by the OWNER for depositing the same with the Income Tax Authorities.
6.04 Wherever required by the State Government(s), Sales Tax on works contract shall be recovered at the prescribed rates from the CONTRACTOR’s running bills by the OWNER for depositing the same
with the State Government.
ARTICLE – 7 : RESPONSIBILITY OF THE OWNER
7.01 The OWNER shall provide at no cost to the CONTRACTOR the following :-
i) Hand over the site to the CONTRACTOR including the site for labour camp, if any, within seven
days from the effective date of agreement.
ii) Furnish to the CONTRACTOR working drawings, sketches, instructions for execution of the
works.
iii) Arrange to inspect the works and witness the tests where conducted.
7.02 The OWNER shall not be responsible to fulfil his obligations as per Article 7.01 in time if such obligations are dependent on CONTRACTOR’s furnishing information in time and where the
CONTRACTOR has failed to do so.
7.03 The OWNER shall be responsible to get the entry passes issued to the CONTRACTOR and his
Employees to work within any restricted area.
7.04 Where specified in the contract, arrange to supply water and electricity at locations marked in site
plan.
ARTICLE – 8 : OBLIGATIONS OF THE CONTRACTOR
8.01 In order to ensure that the contract work is executed strictly in accordance with the Agreement and in
time, the CONTRACTOR shall have the following obligations at no extra cost to the OWNER in addition to such other obligations and responsibilities as have been specified elsewhere in the
Agreement:
i) Make arrangements to bring water and power from points indicated by the OWNER in the tender
documents to the site of Construction.
ii) Arrange for testing of water, soil, concrete etc. as directed by the ENGINEER.
iii) Provision of adequate numbers of construction plants and machinery including mechanised
system of construction, handling and transportation as directed by ENGINEER.
iv) Provide special magazine at site for storage of explosive for which requisite licence shall be
obtained from the concerned authorities.
v) Provide adequate safety and obligatory provisions for work and workmen.
8.02 All fossils, gold, silver, oil and other minerals, precious stones, coins, article of value of antiquity and
structures and other remains and things of geological or archaeological interest discovered at site of
works shall be notified by the CONTRACTOR immediately to the OWNER for onward intimation to
the concerned authorities.
8.03 The CONTRACTOR shall take reasonable precautions to prevent his workmen or any other person
from removing or damaging any such articles or things and protect the same till removal as per the instructions of the OWNER.
8.04 Clearance of the site of all rubbish, debris, vats, tanks, materials, labour huts, temporary structures, plant and machinery, scaffolding and filling of all pits, excavation and hand over the site in a tidy and
clean condition to the OWNER.
8.05 Opening up of covered work if instructed by the ENGINEER, if such covering was done before inspection by the ENGINEER or without permission from the ENGINEER.
ARTICLE – 9 : STANDARD OF WORK
9.01 All material and workmanship shall be of best quality available in the country and shall be in
accordance with the technical specification, drawings and other instructions issued to the
CONTRACTOR.
9.02 If for any material or workmanship appropriate Indian Standards or codes are not available or have
not been adequately specified in the technical specifications, such materials and workmanship shall confirm to other suitable standards and codes as may be approved by the ENGINEER.
9.03 The CONTRACTOR shall take due care in achieving and maintaining tolerances specified for various works.
9.04 The surface finishes shall be free of all defects under critical lighting conditions.
9.05 The CONTRACTOR shall ensure provision of anti-termite and water proofing treatment for the
foundations / basements / roof work and other specified work, as detailed in BOQ through specialised
agencies with a warranty period of 05 (Five) years. Certificate to this effect shall be submitted to the OWNER to the CONTRACTOR.
ARTICLE – 10 : RESPONSIBILITY FOR COMPLETION
10.01 Subject to provision under Article – 11 : Exclusions, any work, supplies or services which might have
not been specifically mentioned in the specifications, schedule of items or drawings but are necessary for entire completion of the contract work shall be executed / provided / rendered by the
CONTRACTOR without any extra cost and within the time schedule specified. Rates quoted shall be
deemed to include such elements of labour and materials necessary to complete the items of work in all respects.
10.02 Any work or item not envisaged but necessary to execute the contract work in completeness shall be
carried out by the CONTRACTOR under instruction of the ENGINEER. The rates for such work / items of work shall be determined in accordance with Article – 12.
ARTICLE – 11 : EXCLUSIONS
11.01 Unless otherwise specifically provided elsewhere in the Agreement including technical specifications,
drawings and schedule of items, the works / items of work to be excluded from the scope of the CONTRACT shall be clearly and specifically indicated in Schedule ‘A’.
ARTICLE – 12 : RATES FOR EXTRA ITEMS
12.01 Should it be found necessary to execute any item(s) of work which is not included in the schedule of
items and as such no contract rate is available, the rate for such items of work shall be arrived at as per the following procedure :-
i) Where the extra item(s) of work is similar in character and / or executed under similar conditions
as to any item of work appearing in the Contract Agreement, then the rates for such extra items
shall be derived from contract rates of similar / closest item of work.
ii) Where the nature of item is such that the rate for the same cannot be derived as per ARTICLE –
12.01(i), then the rate shall be established based on the market rates and taking into account 20%
(Twenty percent) over cost of labour and materials to cover supervision, overheads and profits.
The norms followed by CPWD or MES, as may be approved by the ENGINEER with the
concurrence of the OWNER regarding labour and material content, shall be adopted for this
purpose.
iii) Where rates of extra item / work can neither be established by derivation from the existing rates
as per Article – 12.01 (i) above or by rate analysis as per Article-12.01 (ii), then the rate for such
item / work shall be estimated and fixed by the ENGINEER, which shall be binding on the
CONTRACTOR.
iv) Where the nature of extra item / work is such that, it has to be got executed through a specialised
Agency, the Agency shall be got approved from the OWNER on recommendation of
ENGINEER and decision of the OWNER regarding appointment of the Agency and the rates
shall be final and binding. In such cases, the CONTRACTOR shall be paid at rate(s) approved
for the agency plus 15% (Fifteen percent) to cover supervision, overhead and profits.
v) The price for cement and steel for arriving the rates of extra item shall be as given below :-
a. Cement – Rs…………………………………
b. R/F Steel – Rs……………………………….
c. Structural Steel – Rs…………………………
The above prices are inclusive of taxes, duties etc., and nothing extra shall be payable towards
the taxes and duties.
ARTICLE – 13 : MEASUREMENT OF WORK
13.01 Unless otherwise specified, measurement of work shall be carried from the works actually executed.
13.02 The measurements for the purpose of preparing Bills will be taken jointly by the CONTRACTOR’s
representative and the SITE ENGINEER.
13.03 In measurement of work as stated under Article 13.01 and 13.02, the CONTRACTOR shall certify
that the work has been carried out strictly as per the drawings, specifications and item of work in
terms of the AGREEMENT. Such certificate shall require SITE ENGINEER’s endorsement for the purpose of payment.
13.04 In the event of any dispute with regard to the measurement of the work executed, the decision of the OWNER shall be final and binding on the CONTRACTOR.
13.05 In the case of site measurements as per Article 13.02 above, should the CONTRACTOR not attend or neglect or fail to send his representative for taking joint measurements, the measurements taken by the
SITE ENGINEER shall be deemed to be the correct measurement of work and shall be binding on the
CONTRACTOR.
ARTICLE – 14 : ENGINEERS AUTHORITY
14.01 ENGINEER shall be the sole communicating Authority and all correspondence under this Agreement to the OWNER shall be addressed to the ENGINEER by the CONTRACTOR.
14.02 ENGINEER shall issue necessary drawings, sketches, specifications, instructions, clarifications, etc. to the CONTRACTOR required for the execution of work and also record instructions in site order
book where called for compliance by the CONTRACTOR.
14.03 ENGINEER shall have the authority to :-
i) Make modifications, alterations to the drawings / sketches etc. already supplied to the
CONTRACTOR.
ii) Increase / decrease the quantum of work specified in the schedule of items or to omit item(s) of
works and / or to order substitutions. iii) Inspect, test and examine all the materials and workmanship employed in construction.
iv) Reject materials / workmanship not conforming to instructions / specifications / drawings and to
order for removal of rejected materials or pull down / dismantle defective work (s). v) Enforce the provision of various statutory laws and regulations in vogue pertaining to labour and
construction work and ensure their strict compliance by the CONTRACTOR.
vi) Give notice to the CONTRACTOR if any deficiency is found with regard to adherence to accepted programme or sequence of work or delay in procurement of material and labour or
negligence on the part of the CONTRACTOR or his authorized agent.
vii) Alter already agreed programme or sequence of work if found necessary at a later date.
viii) Instruct the CONTRACTOR to expel from site any of his employee (s) / workmen who in his opinion is incompetent or otherwise whose presence is undesirable at site.
ix) Enforce any or all provisions in the Agreement to ensure that the work is carried out by the
CONTRACTOR strictly in accordance with the Agreement.
However these do not absolve the CONTRACTOR from his responsibilities to carry out all the works
as per terms and conditions of the agreement.
ARTICLE – 15 : CHANGES
15.01 The OWNER / ENGINEER shall have the right, during the performance of the Agreement, to make any addition to, alterations in and omission from the works or any alterations in the kind or quality of
the materials to be used therein and shall give notice thereof in writing to the CONTRACTOR.
15.02 The CONTRACTOR shall, in accordance with such notice as per Article 15.01, alter, add to or omit
from the works as the case may require.
15.03 The CONTRACTOR shall not carry out any work extra to or make any alterations or additions to or
omission from the works or any deviation from any of the provision of the Agreement, stipulation,
specification or contract drawings without the prior consent in writing from the ENGINEER.
15.04 If any changes or missing items of work are required for completion of the work as per Article 10.01,
the CONTRACTOR shall not be entitled to extra price or time.
15.05 The CONTRACTOR shall proceed with the changes as instructed as per Article 15.01 pending
settlement of rates for extra items.
ARTICLE – 16 : WORKING HOURS
16.01 Unless otherwise directed or permitted by the ENGINEER, no work shall be carried between Sun-set
and 8.00 AM or on Sundays or OWNER’s Holidays.
16.02 Where instructed by the ENGINEER the CONTRACTOR shall get the works executed in 2/3 shifts and on Sundays and Holidays if so deemed necessary by the ENGINEER for completion of the work
as per the time schedule. No claim for any compensation or extra payment on this account shall be
admissible by the OWNER.
16.03 In the case of working at night, the CONTRACTOR shall arrange additional workmen and provide
adequate lighting and make other arrangements necessary to carry out the work properly.
16.04 Should it be necessary, the CONTRACTOR shall obtain necessary permission from the authorities for
night work.
ARTICLE – 17 : DRAWINGS, SPECIFICATIONS, SCHEDULE OF ITEMS
17.01 Drawings, specifications and schedule of quantities / items shall be treated as supplementary to each other and should anything appear in the one that is not described in the other, no advantage shall be
taken by the CONTRACTOR for any such omission. For such discrepancy / inconsistency the
CONTRACTOR shall seek instructions from the ENGINEER before proceeding with work and the
clarification / decisions given by the ENGINEER shall be treated as final and binding on the CONTRACTOR.
17.02 All drawings, specifications, sketches, schedule of items, etc. furnished by the OWNER shall be treated strictly confidential property of the OWNER. All such drawings, specifications, sketches,
schedule of quantities / items etc., shall be returned to the OWNER upon the completion of the
contract work. No copies, duplications or photostat shall be retained by the CONTRACTOR without
the written consent of the OWNER.
17.03 CONTRACTOR shall furnish to the OWNER with 3 (three) sets of all catalogues, literature, manuals,
etc., in respect of applicable brought-out items incorporated in the works.
17.04 The CONTRACTOR shall not himself make any changes in the drawings / sketches,
specifications and schedule of items issued by the ENGINEER for executing the contract work. If any error or omission is detected he shall promptly bring the same to the notice of the ENGINEER for
clarification / decision / rectification.
17.05 One (1) set of working drawings, specifications and schedule of quantities / items shall be available at the CONTRACTOR’s site office for reference by the ENGINEER.
17.06 The CONTRACTOR shall be supplied with 03 (three) sets of working drawings for Construction purposes.
ARTICLE – 18 : CONTRACTOR’S REPRESENTATIVE AT SITE
18.01 The CONTRACTOR shall, during progress of the works, employ a full time qualified, experienced
and competent representative at the site for executing the works.
18.02 Any decision, instruction, authorisation or approval given by the ENGINEER to such
CONTRACTOR’s representative shall be deemed to have been given to the CONTRACTOR.
18.03 The CONTRACTOR shall provide necessary competent and experienced personnel to assist his
representative at site for superintendence during the execution of the works and / or as long thereafter,
as the ENGINEER may consider necessary till the expiration of maintenance guarantee period.
18.04 If, in the opinion of the ENGINEER, due progress is not achieved in the contract and / or execution
thereof becomes contrary to the specification and / or substandard work is executed and / or
substandard materials are used or supplied by the CONTRACTOR and / or any direction given by the
ENGINEER is not properly complied with or attended to, the ENGINEER may direct the
CONTRACTOR to employ extra supervisory staff to supervise the work and the CONTRACTOR
shall do so within seven days from the date of such direction and the cost of employment of such
additional supervisors shall be to the account of the CONTRACTOR.
18.05 The CONTRACTOR shall maintain at his site office a site order book for the ENGINEER to give in
writing any instructions, decision, etc. to the CONTRACTOR in connection with execution of the
contract work. The CONTRACTOR shall acknowledge receipt of such instructions, direction,
decision by signing on the order book and ensure its compliance.
18.06 Positioning of CONTRACTOR’s representative as per Article 18.01 shall be subject to the approval
of the OWNER.
ARTICLE – 19 : REJECTION
19.01 If the Contract work or any portion thereof, at any time, is found to be defective or fails to fulfil the requirements of the agreement, the ENGINEER shall give the CONTRACTOR notice in writing
setting-forth particulars of such defects or failure and the CONTRACTOR shall forthwith make good
the defects or replace or alter the same to make it comply with the requirements of the agreement.
19.02 Any materials, equipment, etc. brought to the site and found to be not in accordance with the
agreement, shall be rejected by the ENGINEER and the CONTRACTOR shall remove the materials from the site within the period specified by the ENGINEER.
19.03 The CONTRACTOR shall not be entitled to any extension of time or extra cost for rejection as per
Article 19.01 and 19.02.
ARTICLE –20 : COORDINATION WITH OTHER CONTRACTORS
20.01 The CONTRACTOR shall co-ordinate with other Contractors / agencies working in or about the site
or at the adjoining areas on works having direct or indirect connection with the contract work being
executed by the CONTRACTOR under this Agreement.
20.02 The CONTRACTOR shall interact with other contractors and agencies stated under Article 20.01 and
sequence various activities with the activities of other contractors in a manner required for timely and
sequential completion of the contract work.
20.03 Should there be any disagreement between the CONTRACTOR and other contractors and agencies in
respect of any activity or sequencing of activities, the same should be referred to the ENGINEER whose decision shall be final and binding on the CONTRACTOR.
20.04 Co-ordination with other contractors / agencies or any dis-agreement or delay in co-ordination or
interruption in work shall not entitle the CONTRACTOR to any extra time or cost.
ARTICLE – 21 : LIQUIDATED DAMAGES FOR DELAY
21.01 If the CONTRACTOR fails to complete the work / item(s) of work in all respects and hand over the
same to the OWNER within the time stipulated the CONTRACTOR, without prejudice to any other
right or remedy of the OWNER on account of such breach, be liable to pay the OWNER liquidated
damages at the rate of 1% (one percent) of the total contract price for delay of every week or part
thereof.
21.02 The total amount of liquidated damages shall be limited to 10% (Ten percent) of the total contract
price.
21.03 The provision under Article 21.01 and 21.02 shall not apply in cases of delay for which the
CONTRACTOR is entitled to extension of completion time as per Article 3.04.
ARTICLE – 22 : COMPLETION CERTIFICATE
22.01 Within 10 days of completion of the work, the CONTRACTOR shall give notice of such completion
to the ENGINEER and within 30 (Thirty) days of the receipt of such notice, the ENGINEER shall
inspect the work and if there is no defect, imperfection or shortfall in the work, shall recommend to the OWNER for issue of completion certificate. The OWNER will issue the completion certificate.
22.02 At the option of the OWNER a provisional completion certificate may be issued indicating defects (a) to be rectified or re-constructed by the CONTRACTOR and / or (b) for which payment shall be made
at reduced rate.
22.03 No completion certificate or provisional completion certificate shall be issued nor shall the work be
considered to be complete until the CONTRACTOR shall have removed from the site all scaffolding,
surplus materials, rubbish, etc. and all the temporary works, labour camps and clean off the dirt from
wood work, doors, windows, walls, floors or other parts of the works.
ARTICLE – 23 : MAINTENANCE GUARANTEE
23.01 Maintenance Guarantee period will be 12 months from the actual date of completion and handling
over to the OWNER.
23.02 The CONTRACTOR guarantees that within the maintenance guarantee period, the contract work shall not show any signs of defects, cracks, settlements, disfigurations, shrinkage, leakage, dampness or any
other defects.
23.03 The CONTRACTOR shall maintain and satisfactorily execute, at his own cost, all such works of
repair, amendment, re-construction, rectification, replacement and any other work to make good the
faulty work as stated in Article 23.01 during the maintenance guarantee period.
23.04 The CONTRACTOR shall, if required by the ENGINEER, search for the causes of any defects,
imperfection or fault under the direction of the ENGINEER. The cost of such search shall be borne
by the CONTRACTOR.
23.05 At intervals specified by the ENGINEER the CONTRACTOR, along with the ENGINEER, shall
inspect the contract work to satisfy himself that no defects have cropped up in the contract work. Should there be any signs of defects, the CONTRACTOR shall take immediate steps to rectify the
same, failing which, the ENGINEER may get the defects rectified at the risk and cost of the
CONTRACTOR.
23.06 At the end of the maintenance guarantee period, the CONTRACTOR, along with the ENGINEER,
shall carry out final inspection of the contract work to prove that no defects had appeared in the
contract work or that all defects which appeared in the contract work have been rectified to the entire satisfaction of the ENGINEER. If during the final inspection it is found that the defects still remain in
the contract work, the period of maintenance guarantee shall be extended at the discretion of the
ENGINEER and the CONTRACTOR shall be liable to make good the defects and be responsible for the maintenance of the work till the defects have been fully rectified.
23.07 Upon successful completion of the maintenance guarantee period the OWNER shall issue final
acceptance certificate to the CONTRACTOR.
ARTICLE – 24 : MATERIALS
24.01 The CONTRACTOR shall arrange all the materials required for the work including cement and steel.
24.01.01 Steel shall be procured from main producer of steel viz. SAIL, TISCO, RINL IISCO. Name of the supplier shall be approved by the OWNER.
24.01.02 Type of cement to be incorporated in the work shall be ordinary Portland cement of grade 43 and
above as per relevant IS Code. The cement shall be procured from main producers of cement and
name of supplier shall be approved by the OWNER.
24.02 The CONTRACTOR shall have full knowledge of all the materials required to be procured and
incorporated in the works by him regarding source of supply, technical characteristics and conformation to technical specifications.
24.03 All the materials procured and incorporated in the works shall comply with technical specifications / Indian Standards including latest amendments / revisions. The BIS codes wherever mentioned in
tender documents shall be deemed to be changed / modified / revised as per the latest BIS published.
24.04 Cement and steel where so stipulated in the agreement as to be supplied by the OWNER, the rate of supply and recovery thereof shall be as indicated in the tender documents.
However Steel will not be issued for door / window frames, window grills, railings, gates, chainlink fencing, security / architectural grill for compound wall, MS door / rolling shutters, foundation bolts
and insert plates. Cement required for manufactured items like solid concrete blocks for masonry,
floor tiles etc. will not be issued by the department.
24.04.01 The CONTRACTOR shall lift the steel at his cost and transport the same to the site from local
stock-yards / sidings as the case may be.
24.04.02 The CONTRACTOR shall not use cement and steel issued by the OWNER for any work other than
the contract work without the prior permission of the OWNER.
24.04.03 Any excess quantity of cement and steel procured with the assistance of the OWNER / issued by the
OWNER over and above the quantities consumed in the works including wastages as may be
computed and certified by the ENGINEER, if not returned on completion of the work, shall be treated as misuse of cement and steel by the CONTRACTOR.
24.04.04 In case the CONTRACTOR is asked to transport the cement / steel from outstation stockyard /
sidings, he will be reimbursed the transportation charges at actuals on production of documentary evidence and on certification by the ENGINEER. However, the local handling charges that would
have been incurred by the CONTRACTOR for transportation from local stockyards / sidings shall be
recovered for the quality of steel consumed in the work.
24.04.05 In the event of mis-use of cement or steel as defined under Article 24.04.03, the CONTRACTOR
shall, in addition to making himself liable for action for contravention of the terms of the permit and / or for criminal breach of trust, be liable to the OWNER for payment of penalty at double the base rate
per tonne of cement and steel.
24.04.06 The CONTRACTOR shall make necessary storage facilities at his own cost at the site to prevent
damage / deterioration of cement or steel.
24.04.07 Steel sections required in quantities less than 500 Kgs for the whole work will not be issued by the OWNER and it will be procured by the CONTRACTOR at his own cost.
24.05 Where the Agreement stipulates that cement and steel will be supplied by the OWNER and the OWNER is unable to supply cement and steel under Article 24.04 above for reasons beyond their
control to the CONTRACTOR, the OWNER will permit either of the following :-
a) On the request from the CONTRACTOR, depending upon the circumstances in case, the OWNER at his discretion may permit the CONTRACTOR to procure from the open market cement and
steel keeping in view the overall Time Schedule. The quantities of Cement and Steel to be
procured from the open market will be decided by the OWNER at his sole discretion. Any difference in cost shall be adjusted at actuals against documentary proof.
b) Contractor will not be given or accomodated in another form / mode of compensation / benefit due
to non-availability of cement or steel. However, the OWNER may consider giving a suitable
extension of time in case of any undue delay in availability of cement / steel on production of documentary evidence by the CONTRACTOR.
24.06 The CONTRACTOR shall provide samples, technical brochures, details, etc. to ENGINEER/OWNER for approval of make, brand, colour, shade, etc., at his own cost before placing orders.
24.07 Materials brought at site of work shall be in-sealed containers or original packing and CONTRACTOR shall submit vouchers / challans and test certificate to ENGINEER on demand.
ARTICLE – 25 : OTHER PERSONS ENGAGED BY OWNER
25.01 The OWNER reserves the right to use the premises or any portion of the site for the execution of any
work not included in the Agreement, which he may desire to be carried out by other persons, and the CONTRACTOR shall allow all reasonable facilities for the execution of such work but shall not be
required to provide any plant or materials for the execution of such work except by special
arrangement with the OWNER.
ARTICLE – 26 : MISUSE OF WORKS
26.01 The CONTRACTOR shall ensure that the works or any portion of the work completed or partially completed are not mis-used by him or his sub-contractors or their employees, workmen, agents,
servants etc. leading to deterioration / temporary deterioration of the work.
26.02 The CONTRACTOR may however be permitted by the ENGINEER to use the work or a portion of
the work completed or partially completed for such purposes as may be approved by the ENGINEER.
ARTICLE- 27 : REFUND/FORFEITURE OF SECURITY DEPOSIT
27.01 If the CONTRACTOR shall duly and faithfully carry out the provisions of the Agreement and shall
duly satisfy all claims properly chargeable against him hereunder, the security deposit made by him in terms of the Agreement shall be refunded to him upon issuance of the “Final Acceptance Certificate”
on expiry of the successful maintenance guarantee period.
27.02 Should the CONTRACTOR fail to perform the contract work in terms of the Agreement or fail to
maintain the contract work during the maintenance guarantee period and if the OWNER incurs any
expenditure or is likely to incur any expenditure for completion of the work or rectification of defects,
then the OWNER shall be entitled to deduct such sum or sums as may be necessary for such completion or rectification from the security deposit made by the CONTRACTOR under this
Agreement. The decision of the OWNER in determining such sums to be deducted from the
CONTRACTOR’s security deposit shall be final and binding on the CONTRACTOR and shall not be subject to arbitration.
ARTICLE – 28 : INSPECTION AND TEST
28.01 The CONTRACTOR shall ensure inspection and test of all materials and work at his cost through his
ENGINEER and other technical staff either at site or through any approved laboratory.
28.02 The CONTRACTOR shall ensure proper supervision and inspection during the progress of work at
site.
28.03 All materials and work, whether at the site or in the CONTRACTOR’s / Sub-Contractor’s premises
shall be subject to inspection and test by the ENGINEER. The CONTRACTOR / his Sub-Contractor
shall provide all facilities free of cost to the ENGINEER including all labour, materials, tools, tackles,
instruments, appliances, etc. to enable the ENGINEER to carry out inspection and / or test.
28.04 All test certificates shall be subject to certification by the ENGINEER.
28.05 The CONTRACTOR shall submit to the ENGINEER three copies of all inspection / test certificates.
28.06 The CONTRACTOR shall not be entitled to any claim for extra time or cost due to any delay in carrying outinspection and testing or re-inspection and re-testing if so decided by the ENGINEER.
28.07 The CONTRACTOR shall take adequate steps to rectify the defects or to replace such materials and work which have failed during inspection / testing.
ARTICLE – 29 : ACCESS TO WORK
29.02 The OWNER, ENGINEER and / or any person authorised by them shall at all times have free access
to the work site and / or to the workshops, factories or other places where materials are being prepared or constructed for the contract work and also to any place where materials are lying from where they
are being taken out, and the CONTRACTOR shall give every facility to them for inspection,
examination and testing of the materials and workmanship.
ARTICLE – 30 : NO INTEREST PAYABLE
30.01 The CONTRACTOR shall not be entitled to any interest with respect to security deposit or any
money which may be due to him from the OWNER or for any delay on the part of the OWNER to
make any running or other payments.
ARTICLE – 31 : MATERIALS NOT INCORPORATED IN WORKS
31.01 Any material for which the CONTRACTOR has received payment or the ENGINEER has included
for payment the value of any un-fixed material intended for incorporation in the works, such materials
shall become the property of the OWNER and shall not be removed except for the use upon the works
without the written authority of the OWNER / ENGINEER. The CONTRACTOR shall keep in safe custody of the same and be liable for any loss or damage to such materials till issue of completion of
maintenance guarantee period.
ARTICLE – 32 : SITE CONDITION
32.01 Before submitting the tender the CONTRACTOR shall inspect the site of work and acquaint himself
with and collect all necessary information regarding site conditions and working conditions including
constraints for carrying out the work. No claim of the CONTRACTOR due to ignorance of site
condition / working condition for any increase of completion time and / or cost shall be entertained by the OWNER.
ARTICLE – 33 : OWNER’S CLAIM
33.01 The OWNER shall have a lien on and over all materials of every description, tools, tackles, plant, equipment or any money due and / or that may become due and payable to the CONTRACTOR either
under the Agreement or any other contract and / or also on and over deposits including the security
amount or amounts made under the Agreement and / or any other contract and which may become
repayable to the CONTRACTOR under the conditions or that behalf herein or therein contained, for or in respect of any debt or sum that may become due and payable to the OWNER by the
CONTRACTOR either alone or jointly with another and either under the Agreement or under any
other contract / s or transactions / s of any nature and whatsoever between the OWNER and the CONTRACTOR.
ARTICLE – 34 : SUB-CONTRACTING
34.01 The CONTRACTOR shall not sub-contract the contract work as a whole or a part to a third party for
the performance of the Agreement.
34.02 The CONTRACTOR may sub-contract a portion of the contract work to third parties with the written
approval of the OWNER. The CONTRACTOR shall furnish to the OWNER full particulars about the
proposed sub-contractors and the details of the portion to be sub-contracted while seeking such approval.
34.03 The OWNER shall give approval or shall refuse approval in writing within 30 (thirty) days of request
of such approval along with all supporting details as per Article 34.02.
34.04 Bought-out items including fittings & fixtures, appliances, proprietary items etc. which are to be
procured from specialised manufactures / supplier and which the CONTRACTOR intends to
incorporate in the contract work shall also come within the purview of the provisions under Article 34.02. Specifications, makes, models etc., if not already specified in the technical specifications shall
be subject to approval of the ENGINEER / OWNER.
34.05 The approval extended by the OWNER to sub-contractors recommended by the CONTRACTOR
shall not discharge the latter from his obligations. The CONTRACTOR shall remain solely liable for
any action, deficiency, and / or negligence on the part of his sub-contractors, including the
specifications not being met with and the quality of work not being maintained by the sub-contractors.
34.06 The OWNER may request the CONTRACTOR to submit unpriced copies of relevant specifications
included in all orders placed on sub-contractors.
34.07 In the event certain obligations extended by a sub-contractor to the CONTRACTOR should extend
beyond the maintenance guarantee period specified in the Agreement, the OWNER shall
automatically be entitled to benefit thereof.
34.08 In no event shall the OWNER be deemed to have contract obligation whatsoever in respect of
CONTRACTOR’s, sub-contractors and / or Title Holders of any sub-holders placed by him.
ARTICLE – 35 : PASSAGE OF PROPERTY AND RISK
35.01 Subject to provisions under Articles 3, 23 and 36, the property and risk of the contract work shall pass
on to the OWNER upon issuance of the completion certificate.
35.02 This Article shall not in any way adversely affect or derogate against the CONTRACTOR’s
obligations to provide to the OWNER contract work completed in all respects.
ARTICLE – 36 : SAFETY AND SECURITY
36.01 The CONTRACTOR shall adopt adequate safety measure and use protective clothing for all workmen at site whether or not engaged in actual execution of work or supervision thereof. The
CONTRACTOR shall ensure that the workmen on site use safety belts, gloves, helmets, masks etc. as
necessary for their safety.
36.02 The CONTRACTOR shall be responsible for safety arrangements of all equipment used in connection
with the execution of the work and shall ensure employment of only trained operators to man the
equipment. Only tested equipment, tools, wires, ropes etc. shall be used and shall periodically be tested to the satisfaction of the OWNER. All test certificates shall be made available to the OWNER
at site as and when required by him.
36.03 The CONTRACTOR shall, in connection with the execution of the work, ensure provision and maintenance of lights, guards, fencing with gates, watch & ward when and where necessary or
required by the OWNER or by any duly constituted authority for the protection of the work and / or
for the safety and convenience of the public or others.
36.04 The CONTRACTOR shall take adequate safety precautions for prevention of accidents at site.
The CONTRACTOR shall also ensure that their employees / workmen observe the statutory safety rules and regulations as also those laid down by the OWNER from time to time.
36.05 The CONTRACTOR shall provide at his cost necessary watch and ward force as may be required by
the OWNER to ensure security and safety of all buildings, structures, equipment and materials under
their custody at the site of work.
36.06 The CONTRACTOR shall abide by all security regulations at site promulgated by the OWNER from
time to time. The CONTRACTOR shall provide identity badges to their personnel and workmen
which must be properly displayed by them on their person.
36.07 In order to facilitate issue of gate passes by the OWNER for materials and equipment either during
execution or the maintenance period, the CONTRACTOR shall submit to the OWNER list of construction / erection equipment, etc., and / or other materials that shall be taken by them inside the
site from time to time. Such movement of materials, equipment, tools, tackles etc., shall be subject to
certification by the OWNER / ENGINEER.
36.08 The CONTRACTOR and his personnel / workmen shall be subjected to security check by OWNER’s
own security force for the overall protection of the Project.
36.09 The CONTRACTOR shall not allow any visitor on the works except with the written permission of
the OWNER.
36.10 From commencement to completion of work, the CONTRACTOR shall take full responsibility for the
care of the work, construction plant and equipment and all temporary works and in case of any
damage or loss to the work, construction plant and equipment or to any temporary work from any
cause whatsoever the CONTRACTOR shall, at his own cost replace or repair and make good the same.
ARTICLE – 37 : ACCIDENT OR INJURY TO WORKMEN
37.01 The CONTRACTOR shall be solely liable for any accident or injury to any of the personnel engaged
by him or by his sub-contractors in connection with the Contract work.
37.02 The OWNER shall not be liable for any damage or compensations payable by law in respect of or in
consequence of any accident or injury to any personnel in the employment of the CONTRACTOR or
his sub-contractor and the CONTRACTOR shall indemnify and hold harmless the OWNER against all such claims, damages, compensations and proceedings.
37.03 The CONTRACTOR or his sub-contractor shall forthwith report to the OWNER all cases of accidents to any of their personnel / workmen and shall make every arrangement to render all possible
assistance and aid to the victim of the accident.
ARTICLE – 38 : DEDUCTIONS FROM CONTRACT PRICE
38.01 The CONTRACTOR shall reimburse to the OWNER all costs, charges, damages or expenses which
the OWNER may have paid or to which the OWNER may be entitled and to the extent to which the CONTRACTOR is obliged under the Agreement to do so within 30 (thirty) days upon written request
of the OWNER, failing which such costs, charges, damages or expenses shall be deducted by the
OWNER from any money due or becoming due by him to the CONTRACTOR under this Agreement.
38.02 Whenever any claim(s) for payment of sum of money arise(s) out of or under this Contract against the
CONTRACTOR, the CONTRACTOR shall, on written demand make the payment of the same or
agree for effecting adjustment from any amounts due to him by the OWNER. If, however, he refuses or neglects to make the payment on written demand, or does not agree for effecting adjustment from
any amounts due to him, OWNER shall be entitled to withhold an amount not exceeding the amount
of the claim(s), from any sum when due or which at any time thereafter may become due to the
CONTRACTOR, under this or any other contract with the OWNER or from any other sum due to the
CONTRACTOR from the OWNER (which may be available with the OWNER) or from the
CONTRACTOR’s security deposit or security bond amount, and retain the same by way of lien till such time payment is made by the CONTRACTOR or till the claim(s) is / are settled or adjudicated
upon, or till the CONTRACTOR, at his expense furnishes “Fixed Deposit Receipt(s)” duly endorsed
as directed by the Accepting Officer, or a Guarantee Bond from a scheduled bank for an amount equal to the amount of the claim(s), in the form as directed by the Accepting Officer.
38.03 OWNER reserve the right to carry out post payment audit and technical examination of the works and Final Bill, including all supporting vouchers, abstracts etc. OWNER further reserve the right to carry
out the aforesaid examinations and enforced recovery when detected, notwithstanding the fact that the
amount of the final bill may have been included by one of the parties as an item of dispute before an
arbitrator appointed under the arbitration clause of the contract and notwithstanding the fact that the amount of the final bill figures in the arbitrator’s award.
38.04 If, as a result of such audit and technical examination, any over payment is discovered in respect of the work done under this contract, the CONTRACTOR shall, on written demand make payment of a
sum equal to the amount of over payment or agree for effecting necessary adjustment from any
amount(s) due to him by OWNER. If however, he refuses or neglects to make the payment on demand(s) or does not agree for effecting adjustment from any amount(s) due to him, OWNER shall
be entitled to take action as per Article 38.02.
38.05 All notices under these conditions shall be given by the Accepting Officer.
ARTICLE – 39 : COMPLIANCE WITH STATUTORY AND OTHER REGULATIONS
39.01 The CONTRACTOR shall, throughout the performance of the Agreement comply with all Central or
State Statutes, Ordinance or Laws and the Rules, Regulations, or Bye-Laws of any local or other duly
constituted authority having jurisdictions over the contract work or any part of the site.
39.02 The CONTRACTOR shall give all notices and pay all fees and taxes required to be given or paid
under any Central or State Statues Ordinance or other Laws or any Regulations or Bye-Laws of any
local or other constituted authority in relation to the contract work.
39.03 The CONTRACTOR shall get himself registered with the concerned authorities as provided under
various applicable Acts and shall be directly responsible to such authorities for compliance with the provision thereof.
39.04 By way of illustration of various Acts as stated under Article 40.01, the following Acts as amended
from time to time shall be complied with by the CONTRACTOR :-
(i) Employee’s Provident Fund Act 1952
(ii) Contract Labour Act (Regulations and Abolition 1970) (iii) Minimum Wages Act 1948
(iv) Payment of Wages Act 1936
(v) Workmen Compensation Act 1923 (vi) Factories Act 1948
(vii) Apprenticeship Act 1961
39.05 The CONTRACTOR shall ensure that no child labour is employed or permitted to work in any activity covered under the Agreement.
39.06 The CONTRACTOR shall submit periodical (daily/weekly/monthly/quarterly) statements of labour employed by him in the proforma prescribed by the OWNER.
39.07 The CONTRACTOR’s establishment shall be subjected to inspection, investigation etc., by the
OWNER / ENGINEER for ensuring proper and faithful compliance of the provisions of the Agreement by the CONTRACTOR with regard to the implementation of labour laws and matters
stated in this Article.
39.08 The CONTRACTOR shall provide, at his cost, to all staff and workmen directly or indirectly
employed on the works all amenities for securing proper working and living conditions at the site and
at the labour camp. The CONTRACTOR shall also provide medical facilities at the site as per rules in force in relation to the strength of their staff and workmen deployed at site.
ARTICLE - 40 : INDEMNITY
40.01 Notwithstanding all reasonable and proper precautions being taken by the CONTRACTOR at all
items during the performance of the contract work, the CONTRACTOR shall remain wholly
responsible for all damages, whether to the contract work executed by him or to any other
OWNRER’s property or to the lives, persons or property of others during progress of the contract
work and the period of maintenance thereof and shall indemnify, defend and hold harmless the
OWNER, ENGINEER or their employees against all claims, loss, demands, proceedings, charges and
expenses, liability for personal injury (including death), and / or damage to property incurred by
reasons of any act or omission or default by the CONTRACTOR, his sub-contractors, agents, servants
or employees and arising out of or connected with the performance of this Agreement.
40.02 The CONTRACTOR shall also indemnify and hold harmless the OWNER, ENGINEER or their
employees from all liability, claims, costs, expenses, taxes and assessments, including penalties,
punitive damages, attorney’s fees and court costs which are or may be required with respect to any
beach of the CONTRACTOR’s obligations or for which the CONTRACTOR has assumed
responsibility including those imposed by Statutes, Ordinances, Laws, Rules, Regulations or Bye-laws
or in respect of salaries, wages or other compensations of all persons employed by the
CONTRACTOR or his sub-contractors or suppliers in connection with the performance of any work
covered by the Contract.
40.03 The CONTRACTOR shall execute and deliver and shall cause his subcontractors and suppliers to
execute and deliver such other further instruments and to comply with such requirements of such
Statutes, Ordinances, Laws, Rules, Regulations or Bye-laws as may be necessary thereunder to
confirm and effectuate the Agreement and to protect the OWNER, the ENGINEER or their
employees.
40.04 Notwithstanding anything hereinbefore contained, the OWNER shall not accept any liability for the
CONTRACTOR, his sub-contractors, agents, servants or employees or any of them or for their / his
property while on the premises or in service of, or used for / on behalf of the OWNER by any person.
ARTICLE – 41 : PATENT
41.01 The CONTRACTOR shall indemnify and hold harmless the OWNER and ENGINEER against all
actions, claims, demands, costs, charges and expenses arising from or incurred by reason of any
infringement of patent, trade mark, registered design, copy rights and / or other protected rights in
respect of any construction plant, machinery, work or material used for or in connection with the
contract work or temporary work or any of them whether or not the OWNER is held liable for by any
court judgment.
ARTICLE - 42 : PRESERVATION OF PEACE
42.01 The CONTRACTOR shall take adequate precautions and use his best endeavours to prevent any
riotous of any unlawful behaviour by or amongst his workmen and / or others employed by him and
for the preservation of peace and protection of the inhabitants and security of property at or in the
neighbourhood of the site.
42.02 In the event of the OWNER requiring the maintenance of a special Police force at or in the vicinity of
site during the tenure of the contact in consequence of the riotous or unlawful behaviour by or
amongst the CONTRACTOR’s workmen and / or others employed by him, all expenses thereof, and costs of all damages due to such riotous or unlawful behaviour shall be borne by the CONTRACTOR
and if paid by the OWNER, shall be recovered by the OWNER from him from any money due or that
may become due to him.
ARTICLE - 43 : OPERATION
43.01 The Agreement shall be operated on behalf of the OWNER by such agency as may be determined by
the OWNER and the CONTRACTOR shall deal with such agency directly.
43.02 The OWNER reserves the right to call for clarifications and interact with the CONTRACTOR on technical and functional aspects of any part of the work at his discretion.
ARTICLE – 44 : SECRECY
44.01 All maps, plans, drawings, specifications, schemes and the subject matter contained therein and all other information given to the CONTRACTOR by the OWNER / ENGINEER in connection with the
performance of the contract work shall be held confidential by the CONTRACTOR and shall remain
the property of the OWNER and shall not be used or disclosed to third parties by the CONTRACTOR
for any purpose other than for which they have been supplied or prepared. The CONTRACTOR may disclose to third parties, upon execution of secrecy agreements, such part of the drawings,
specifications or information if such disclosure is necessary for the performance of the contract work
after the approval of the OWNER.
44.02 On completion of the work or upon termination of the Agreement, the CONTRACTOR shall return to
the OWNER all drawings and documents received by him from the OWNER / ENGINEER. The CONTRACTOR shall ensure that neither the CONTRACTOR nor any of his officials and employees
or any other persons shall have possession or access to ay copy thereof.
44.03 The CONTRACTOR shall ensure that all persons employed on any work connected with this Agreement have notice that the Indian Official Secret Act 1923 (XIX of 1923) applies to them and
continue to apply even after the termination or expiry of the Agreement. This condition shall also
apply to his sub-contractors. An undertaking to this effect is to be submitted by the CONTRACTOR to the OWNER before commencement of the Contract.
ARTICLE - 45 : SUSPENSION & TERMINATION
45.01 The OWNER may suspend the work in whole or in part at any time by giving the CONTRACTOR
notice in writing to such effect stating the nature, the effective date and duration of such suspension.
45.02 On receiving the notice of suspension, the CONTRACTOR shall stop all such work which the
OWNER has directed to be suspended with immediate effect. The CONTRACTOR shall continue to
perform other works in terms of the Agreement which the OWNER has not suspended.
45.03 The OWNER, may at any time, cancel the suspension notice for all or any part of suspended work by
giving written notice to the CONTRACOTOR specifying the part of work to be resumed and the
effective date of withdrawal of suspension. The CONTRACTOR shall resume the suspended work as expeditiously as possible after receipt of such withdrawal of suspension notice.
45.04 In the event, such suspension exceeds a period of three months the OWNER and the CONTRACTOR shall consult each other to determine the extent of claims or compensation due each other on account
of such suspension provided however that if the suspension has been due to inclement weather, unsafe
working condition and non-conformance to specifications, continued violations by the CONTRACTOR of ENGINEER’s/OWNER’s instructions and such other causes for which the
CONTRACTOR is responsible, then no compensation shall be payable by the OWNER.
45.05 If the CONTRACTOR violates the Agreement or shall neglect to execute the work with due diligence
or expedition or shall refuse or neglect to comply with any reasonable directions, instructions or
orders given to him in writing by the OWNER / ENGINEER in connection with the work or shall contravence or breach any provisions of the Agreement, the OWNER may give notice in writing to
the CONTRACTOR to make good the failure, neglect or contravention complained of or cure that
breach within a period of 30 (thirty) days of receiving such notice and in default of the compliance with the said notice, the OWNER without prejudice to his rights as below may rescind or terminate
the Agreement stating therein the effective date of termination, holding the CONTRACTOR liable for
the damages that the OWNER may sustain in this behalf.
45.06 Should the CONTRACTOR fail to comply with such notice within the period stipulated in Article -
45.05 in the case of failure, neglect or contravention capable of being made good within that time or
otherwise within such time as may be reasonably necessary for making good, the same then and in such case without prejudice to the OWNER’s right under Article – 45.05 here to, the OWNER shall
have the option and be at liberty to take the work wholly or in part out of the CONTRACTOR’s hands
and may complete the work envisaged in the agreement either directly or may recontract with any other person / persons to execute the same or any part thereof and provide other materials, tools,
tackle or labour for the purpose of completing the work or any part thereof.
45.07 In such event the OWNER shall, without being responsible to the CONTRACTOR for fair, wear and
tear of the same, be entitled to seize and take possession and have free use of all materials, tools,
tackle or other things which may be on the site for use at any time in connection with the work to the
exclusion of any right of the CONTRACTOR over the same, and the OWNER shall be entitled to retain and apply any balance sum which may otherwise be then due on the Agreement by him to the
CONTRACTOR on such part thereof as may be necessary, to the payment of the cost of execution of
such work as aforesaid.
45.08 If the cost of executing the work as aforesaid shall exceed due to the CONTRACTOR and the
CONTRACTOR fails to make good the deficit, the said materials, tools, tackle, construction plant or
other things, the property of the CONTRACTOR as may not have been used up in the completion of the works, may be sold by the OWNER and the proceeds applied towards the payment of such
difference and the cost of and incidental to such sale. Any outstanding balance existing after
crediting the proceeds of such sale shall be paid by the CONTRACTOR on the certificate of the OWNER, but when all expenses, costs and charges incurred in the completion of the work are paid for
by the CONTRACTOR, all such materials, tools, tackle, construction, plant or other things not used in
the completion of the works and remaining unsold shall be removed by the CONTRACTOR.
45.09 The OWNER, without prejudice to his rights as stipulated under Article 45.06 to 45.08, shall also
have the option to consult with the CONTRACTOR to arrive at a fair solution in determining the
claims and payments due to the OWNER arising out of such termination. If no fair solution is reached within 3 (three) months from the effective date of termination then the matter may be referred
to arbitration in terms of Article 47.
ARTICLE - 46 : FORCE MAJEURE
46.01 If either party shall be delayed or impeded in the fulfilment of its obligations under the agreement by reasons of force majeure, such as, act of God, operation of force of nature, act of state, war, civil war,
revolution, rebellion, military or unsurped power, explosion, fire, epidemic, quarantine, floods,
earthquake or other physical disaster, freight embargo, confiscation, expropriation, governmental
orders or restrictions or the like or similar events due to any cause beyond the reasonable control of the party affected and which such party could not have reasonably foreseen and guarded against and
which by exercise of reasonable care and diligence, such party is unable to prevent, then any delay
directly arising therefrom shall constitute an excusable delay provided :-
i) It is established that any of such event has occurred adversely affecting the party concerned and
the continued performance of this Agreement without any contributory negligence or default on
their part.
ii) It is proved that as a result thereof, further performance of the Agreement by such party is
inevitably delayed or impeded.
iii) Such party gives notice to the other party within 10 (ten) days from the occurrence of such event
giving sufficient details of such event and proof of its effect on the performance of the Agreement on the part of such party, and time for the performance of that part of the obligation
of the party concerned which so delayed or impeded shall be extended by a period or periods
equal to the durations of such delay provided that the other party shall not be required to perform the corresponding part of its obligations under this Agreement.
46.02 If the duration of the delays or impediments due to such continuing force majeure events exceeds a period of 6 (six) months, the party shall consult each other to find an amicable solution to problems
created by such delays or impediments.
46.03 In the event that parties are unable to resolve such problems to their mutual satisfaction within 3 (three) months of the first consultation under Article 46.02 either party shall have the right exercisable
of such 30 (thirty) days after the expiration of such 3 (three) months by serving on the other 30 (thirty)
days written notice to terminate the Agreement wholly or partly. Depending upon the nature and consequence of the force majeure. Article 46 shall take effect to the extent applicable, provided that
neither party shall have any claim for damages or compensation against the other in respect of any
such delay or impediment or as a result of any acts or action taken by any of the parties.
46.04 This article shall not effect or alter the rights and liabilities of the parties which have already accrued
by virtue of or in consequence to the obligations already performed.
ARTICLE – 47 : ARBITRATION
47.01 Any dispute, disagreement or question arising out of or relating to or in consequence of the Agreement or relating to its construction or performance which cannot be settled amicably shall, from
the date either party informs the other in writing that such dispute or disagreement existing and
requests in such notice to refer the matter to arbitration, shall be submitted to arbitration for final
settlement.
47.02 Within 30 days of the said notice, Director (Civil Works & Estates), DRDO shall nominate a panel of
3 names from among the serving officers of the Ministry of Defence. The CONTRACTOR shall choose any one of the three persons to Act as the Sole Arbitrator.
47.03 The award of the arbitrator shall be final binding on both the parties.
47.04 The arbitration award shall, in addition to dealing with the merits of the case, decide which of the
parties shall bear the cost of arbitration or in what proportion the cost shall be borne by the parties.
47.05 The parties shall continue to perform their obligations under the Agreement during the arbitration
proceedings and no payment due to or payable by the OWNER subject to provision of Article - 38
shall be withheld or delayed except as regards any particular obligation or any particular payment which itself is or forms a direct part of the subject matter of the arbitration proceedings.
47.06 In the event of the arbitrator resigning or becoming incapable or unable to act, the Authority appointing him shall appoint another in place of the outgoing arbitrator and arbitrator proceedings
shall continue as if such arbitrator had been originally nominated.
47.07 The arbitrator shall be deemed to have entered on the reference made on the date he issues notices to both the parties asking them to submit to him their statement of the case and pleading on defence.
47.08 The arbitrator may, from time to time, with the consent of the parties enlarge the time upto but not exceeding one year from the date of entering on reference for making the award.
47.09 The arbitrator may proceed with the arbitration exparte if either party, inspite of notice from the
arbitrator, fails to take part in the proceedings.
47.10 The venue (s) of arbitration shall be fixed by the arbitrator at his sole discretion.
47.11 Subject to aforesaid, the provision of the Arbitration Act, 1940, or any statutory amendment,
modification, or re-enactment thereof and the rules made thereunder and for the time being in force
shall apply to the arbitration proceedings.
ARTICLE - 48 : LIQUIDATION/TERMINATION
48.01 If the CONTRACTOR commences to be wound up, not being a member’s voluntary winding up for
the purpose of amalgamation or reconstruction, or carries on his business under a receiver for the
benefits of his creditor the OWNER shall be at liberty to :
i) Give such receiver the liquidator or other person the option of carryout the performance under the
Agreement, subject to the receiver, liquidator or other person providing a guarantee up to an
amount to be agreed upon by the OWNER and such receiver liquidator or other person for the due and faithful performance of the CONTRACOTOR’s obligations under this agreement, or
ii) If the receiver, liquidator or other person fails within 30 (thirty) days to exercise one option to carry out performance of the Agreement then the OWNER may terminate the Agreement and
give notice in writing to the CONTRACTOR or to the receiver, liquidator or to any person in
whom the Agreement may have become vested.
48.02 Termination of contract : Without prejudice to any of the rights or remedies under this contract, if the
contractor dies, the Accepting Officer shall have the option of terminating the contract without
compensation to the CONTRACTOR.
ARTICLE - 49 : EFFECTIVE DATE OF AGREEMENT
49.01 The agreement shall become effective from the date of issue of letter of intent by the OWNER.
ARTICLE - 50 : ANNEXURES TO THE AGREEMENT
50.01 Following Annexures shall constitute an integral part of the Agreement :
Annexure – I : Invitation to Tender, Draft Agreement, General Conditions & Special Conditions of
Contract as well as correspondence, if any.
Annexure – II : Scope of works, completion milestones, construction programme, manpower and
equipment mobilisation.
Annexure – III : Schedule of items, Bill of Quantities and List of Drawings.
Annexure – IV : Tender drawings.
Annexure – V : Technical Specifications.
50.02 If annexure other than as specified under Article 50.01 above as referred to elsewhere in the
Agreement, such Annexures shall also form integral part of the Agreement.
ARTICLE - 51 : ENTIRE AGREEMENT
51.01 The terms & conditions herein contained including tender documents, shall constitute the entire
agreement and understanding between the parties hereto and shall supersede all other communications
which were made prior to the signature of the Agreement, whether written or oral, between parties hereto with respect to the subject matter hereof.
ARTICLE - 52 : AMENDMENT TO AGREEMENT
52.01 Any amendment to the terms of the Agreement shall be made in writing by both parties hereto and
shall specially state it is an amendment to the agreement.
ARTICLE - 53 : WAIVER
53.01 Non-enforcement by either party of any of the provisions on the Agreement shall not operate or constitute as a waiver of the provision itself or any subsequent breach thereof.
53.02 The validity of the agreement shall not be affected should one or more of its stipulations to be or become legally invalid and such stipulation is severable from and not fundamental to the obligations
of either party to the Agreement. In such a case, the party shall negotiate in good faith to replace the
invalid clause by an agreed stipulation which is in accordance with the applicable law and which shall
be as close as possible to the parties original intent.
ARTICLE - 54 : ASSIGNMENT
54.01 The CONTRACTOR shall not assign his rights and obligations under the terms to the Agreement to
any party other than its legal successor without the written consent of the OWNER.
ARTICLE - 55 : COPIES
55.01 The Agreement shall be executed in triplicate. The original and triplicate shall be retained by the
OWNER and duplicate, by the CONTRACTOR.
ARTICLE - 56 : STAMP DUTY
56.01 Stamp duty payable in respect of this agreement shall be borne and paid by the CONTRACTOR.
ARTICLE - 57 : NOTICES
57.01 All notices under this Agreement shall be given in writing and shall be deemed sufficiently given
when delivered either manually or by telegraph, telex or by registered mail addressed to the other
party. Communication shall be made to the OWNER with a copy to the ENGINEER. The communication shall be made to the CONTRACTOR at his registered office with a copy to the
ENGINEER.
57.02 If any notice is delivered by hand, it shall be duly acknowledge and if given by telegram, telex or
verbally, it shall be confirmed by letter within 7 (seven) days of the date of such notice. Either party
shall by notice in writing inform the other party of any change of address as stated under Article – 57.01 for receiving such notices.
57.03 The date of communication and notices under Article – 57.01 shall be the date of receipt of such
original communication and notice by the receiving party.
AMENDMENT NO. 1
GENERAL CONDITIONS OF CONTRACTS
1. Reference No. Admin/87116/DWP/RD-28/1957/D(R&D) dated 28 May 1999 (Appendix ‘E’ to RDCE –
WP – 1999).
(a) Article 9.05 :-
For : The CONTRACTOR shall ensure provision of Anti-termite and Water Proofing treatment
for the foundations/basement/roof work and other Specified works, as detailed in BOQ through
specialized agencies with a Warranty period of 05 (Five) years. Certificate to this effect shall be
submitted to the OWNER by the CONTRACTOR.
Read : The contractor shall ensure provision of antitermite and water proofing treatment for
foundations/basement/sunken portion/roof work and other specified work as detailed in BOQ through specialized agencies as approved by the OWNER. These work shall carry a warranty of 05
(Five) years from completion of contract and issue of completion certificate in this regard. Final
payment against antitermite and water proofing work shall be released on production of Bank Guarantee Bond for equal value of final payment due against these works valid for a period of 05
(Five) years from issue of completion. Alternatively agency may choose to submit Standing
Bank Guarantee Bond valid for 5 (Five) years for Rs.100.00 lakhs against these works. Any
defect noticed during this period shall be rectified within 30 days of written intimation by the OWNER failing which the rectification shall be carried out by the OWNER out of the Bank
Guarantee amount. The Bank Guarantee Bonds shall be released on expiry of warrant period and
satisfactory completion of rectification of defects and on issuance of final “Acceptance Certificate” for these items by the OWNER.
(b) Article 23.01 :-
For :Maintenance Guarantee period will be 12 months from the actual date of
Completion and handing over to the OWNER.
Read : Maintenance Guarantee period will be 24 (Twenty Four) months from the actual date of
completion and handing over to the OWNER.
Signature of Contractor
Date :
AMENDMENT NO. 2
GENERAL CONDITIONS OF CONTRACTS AS APPLICABLE TO R&D CONSTRUCTION
ESTABLISHMENT ( Appendix- ‘E’ to Govt. of India MOD Letter No. Admin/87116/DWP/28-
28/1957/D (R&D) dated 28 May 1999
1. Delete Clause 5.01 (i) of General Conditions of Contracts and substitute
(i) (a) 10% (ten percent) of contract price as Mobilization Advance within 2 (two) weeks after the
effective date of Agreement or the date of deposit of Initial Security, whichever is later against a
Bank Guarantee from schedule bank for 110% amount of advance in the format prescribed by
OWNER, valid up to issue of “Completion Certificate” by the OWNER. The value of Bank
Guarantee shall be progressively reduced to the extent of outstanding Mobilization to be
adjusted/recovered. Any outstanding Bank Guarantee Bond shall be released when the entire work
is completed as per the agreement and on issuance of “Completion Certificate by the Engineer”.
(b) Mobilization Advance shall be paid in 2 (two) or more instalments to be decided by the
OWNER, each instalment will not be more than 50% of the total admissible Mobilization Advance.
Subsequently instalments of advance shall be released by the OWNER only after satisfying himself
for appropriate utilization of previous advances.
(c) Mobilization Advance will bear simple interest of 10% (ten percent) per annum and shall
be calculated on the outstanding amount of advance from the date of advance to the date of recovery
both date inclusive.
Signature of Contractor
Date :
AMENDMENT NO. 3
GENERAL CONDITIONS OF CONTRACT
1. Reference Amendment No. 1 issued to General Conditions of Contract vide this office letter no.
DCWE/11/C-32997/133 dated 12 Oct 2010.
2. The following amendments are further issued to the amendment no. 1 to General Conditions of
Contract :-
(a) Article 9.05 :-
For : The CONTRACTOR shall ensure provision of Anti-termite and Water Proofing treatment
for the foundations/basement/sunken portion/roof work and other Specified works, as detailed in
BOQ through specialized agencies as approved by the OWNER. These work shall carry warranty period of 05 (Five) years from completion of contract and issue of completion Certificate in this regard.
Final payment against antitermite and water proofing work shall be released on production of Bank
Guarantee Bond for equal value of final payment due against these works valid for a period of 05 (Five) years form issue of completion. Alternatively agency may choose to submit standing Bank Guarantee
Bond valid for 05 (Five) years for 100.00 lakhs against these works. Any defect noticed during this
period shall be rectified within 30 days of written intimation by the OWNER failing which the
rectification shall be carried out by the OWNER out of the Bank Guarantee amount. The Bank Guarantee Bonds shall be released on expiry of warranty period and satisfactory completion of
rectification of defects and on issuance of final “Acceptance Certificate” for these items by the owner.
Read : The contractor shall ensure provision of antitermite and water proofing treatment for
foundations/basement/sunken portion/roof work and other specified work as detailed in BOQ
through specialized agencies as approved by the OWNER. These work shall carry a warranty of 05
(Five) years from completion of contract and issue of completion certificate in this regard. Final payment against antitermite and water proofing work shall be released on production of Bank
Guarantee Bond/FDR for equal value of final payment due against these works valid for a period of
05 (Five) years from issue of completion. Alternatively agency may choose to submit Standing Bank Guarantee Bond/FDR for the following values.
Agencies prequalified for work Value of Bank Guarantee
Bond / FDR
(i) Upto Rs. 50.00 lakhs Rs. 10.00 lakhs
(ii) Rs. 50.00 to Rs. 120.00 lakhs Rs. 20.00 lakhs
(iii) Rs. 120.00 lakhs to Rs. 500.00 lakhs Rs. 50.00 lakhs
(iv) Rs. 500.00 lakhs Rs. 100.00 lakhs
Any defect noticed during this period shall be rectified within 30 days of written intimation by the
OWNER failing which the rectification shall be carried out by the OWNER out of Bank Guarantee/FDR
amount. The Bank Guarantee Bonds/FDR shall be released on expiry of warranty period and satisfactory completion of rectification of defects and on issuance of final “Acceptance Certificate” for
these items by the owner.
Signature of Contractor
Date :
AMENDMENT NO. 4
GENERAL CONDITIONS OF CONTRACT
1. Refer Amendment No.4 issued to General Conditions of Contract vide DCWE letter
No. DCWE/11/C-32997/133 dated 17 May 2012.
2. The following amendments are further issued to the General Conditions of Contract :-
(a) Article 12.01 (ii) :-
For : Where the nature of item is such that the rate for the same cannot be derived as per ARTICLE-
12.01(i), then the rate shall be established based on the market rates and taking into account 20% (Twenty percent) over cost of labour and materials to cover supervision, overheads and profits. The
norms followed by CPWD or MES, as may be approved by the ENGINEER with the concurrence of
the OWNER regarding labour and material content, shall be adopted for this purpose.
Read : Where the nature of item is such that the rate for the same cannot be derived as per
ARTICLE-12.01(i), then the rate shall be established based on the market rates and taking into account 15% (Fifteen percent) over cost of labour and materials to cover supervision, overheads and
profits. The norms followed by CPWD or MES, as may be approved by the ENGINEER with the
concurrence of the OWNER regarding labour and material content, shall be adopted for this purpose.
Signature of Contractor
Date :
AMENDMENT NO. 5
GENERAL CONDITIONS OF CONTRACT
1. Refer Amendment No.5 issued to General Conditions of Contract vide DCWE letter
No. DCWE/04/C-32997/133 dated 14 Aug 2013.
2. The following amendments are further issued to the General Conditions of Contract :-
(a) Article 3.04 :-
For : The CONTRACTOR shall not be allowed any extension of completion time except in the
following cases :
(i) Force Majeure : The extension of completion time shall be as per Article-46.
(ii) Major changes or substantial addition to the work ordered by the OWNER adversely affecting the completion time.
(iii) Delay in handing over the site, etc.
Read: The CONTRACTOR shall not be allowed any extension of completion time except in the
following cases :
(i) Force Majeure : The extension of completion time shall be as per Article-46, or
(ii) Major changes or substantial addition to the work ordered by the OWNER adversely affecting the completion time, or
(iii) Delay in handing over the site, etc, or
(iv) Abnormally bad weather, or
(v) Civil commotion, local commotion of workmen, strike or lockout, affecting any of the trade employed on the work, or
(vi) Delay on part of other contractor or tradesmen engaged by engineer in charge in
executing works not forming part of the contract, or
(vii) Non availability of stores, which are the responsibility of Government to Supply, or
(viii) Non availability of stores, which are the responsibility of Government to Supply, or
(ix) Any other cause which, in the absolute discretion of the Engineer in Charge is Beyond the contractor’s control.
In case of conditions from (ii) to (ix) Extension of time shall be as per decision of
the OWNER.
(a) Article 4.03 :-
For : Item rates as stated under schedule of items / rates shall be firm and fixed and
binding on the CONTRACTOR during the period of this Agreement irrespective of
any variations of quantities stated therein up to +/- 20% variations of contract price. For variations beyond 20% (twenty percent) of contract price, applicable items rates
shall be mutually discussed and agreed. The item rates on above shall not be subject
to any variations on any account whatsoever, whether statutory or otherwise.
Read : Item rates as stated under schedule of items / rates shall be firm and fixed
and binding on the CONTRACTOR during the period of this Agreement irrespective
or any variations of quantities stated therein up to +/- 20% variations of contract price. For variations beyond 20% (twenty percent) of contract price, applicable items
rates shall be derived based on prevailing market rates and taking into account 15%
(Fifteen percent) over cost of labour and materials to cover supervision, over-heads and profits. The norms followed by CPWD, may be approved by the ENGINEER
with the concurrence of the OWNER regarding labour and material content, shall be
adopted for this purpose. The item rates on above shall not be subject to any variations on any account whatsoever, whether statutory or otherwise. However,
under no circumstances the rate of deviated quantity will exceed the rate give in
agreements.
(b) ARTICLE 50 – ANNEXURE 1
For : “Tenderer shall not resile from his technical, commercial and price offer. Should the tenderer resile from his tender in any manner whatsoever the tender
submitted by him shall be liable to rejection. Tenderer shall be allowed to revise his
offer only if specifically so requested by the owner”
Read : “The tender for the work shall remain open for acceptance for a period of
Ninety (90) days from the date of opening of tenders/Ninety (90) days from the date
of opening of financial bid in case tenders are invited on 2/3 bid system. If any tenderer withdraws his tender before the said period or issue of letter of acceptance,
whichever is earlier, or makes any modifications in the terms and conditions of the
tender which are not acceptable to the department, then the Government shall, without prejudice to any other right or remedy, be at liberty to forfeit 50% of the
Earnest Money. Further the tenderer shall not be allowed to participate in the
retendering process of the work.
However, the tenderer shall be allowed to revise his offer only if required by tender
appraisal committee / tender standing committee based on the negotiations in order to give
rebate on overall tender or on specific items (s)”.
Signature of Contractor
Date :
AMENDMENT NO. 6
AMENDMENT TO APPENDIX – ‘E’ TO RDCE-WP-1999 GENERAL CONDITION OF CONTRACT
(ARTICLE 5.01 & 5.03) VIDE GOVT. OF INDIA, MINISTRY OF DEFENCE LETTER NO.
ADMIN/87116/DWP/RD-28/2032/D(R&D) DATED 17 OCTOBER 2017.
1. The following amendments are further issued to the General Conditions of Contract :-
(a) Article 5.01 (i) :-
For : In respect of Civil Works subject to any deduction which the OWNER may be
authorized to make under the Agreement, the CONTRACTOR shall receive payment from the
OWNER as follows :
i) 10% (Ten percent) of the Contract price as Interest free mobilization advance within
02 (Two) weeks after the effective date of Agreement, or date of deposit of initial security,
whichever is later against a Bank Guarantee for an equal amount in the format prescribed by
the OWNER, valid upto issue of “Completion Certificate” by the OWNER. The value of
Bank Guarantee shall be progressively reduced to the extent of outstanding Mobilization
Advance to be adjusted / recovered. Any outstanding Bank Guarantee Bond shall be released
when the entire work is completed as per the Agreement and on issuance of “Completion
Certificate” by the ENGINEER.
Read : In respect of Civil Works subject to any deduction which the OWNER may be authorized to make under the agreement, the CONTRACTOR shall receive payment from the
OWNER as follows :
i) (a) 10% (ten percent) of the contract price as Mobilization Advance within 2 (two)
weeks after the effective date of Agreement, or the date of deposit of initial security,
whichever is later against a Bank Guarantee from scheduled bank for 110% amount of
advance in the format prescribed by the OWNER, valid up to issue of “Completion
Certificate” by the OWNER. The value of Bank Guarantee shall be progressively reduced to
the extent of outstanding Mobilization to be adjusted / recovered. Any outstanding Bank
Guarantee Bond shall be released when the entire work is completed as per the Agreement
and on issuance of “Completion Certificate” by the ENGINEER.
(b) Mobilization advance shall be paid in 2 (Two) or more installments to be decided by
the OWNER. Each installment will not be more than 50% of the total admissible Mobilization Advance. Subsequent installments of advance shall be released by the OWNER
only after satisfying himself for appropriate utilization of previous advances, if necessary /
feasible, based on indicative documentary proof of expenditure incurred on material /
equipment and / or on quantum of work initiated on ground
(c) Mobilization Advance will bear simple interest of 10% (Ten percent) per annum and shall be calculated on the outstanding amount of advance from the date of advance to the date
of recovery, both days inclusive.
(b) Article 5.03 :-
For : In respect of E&M Works subject to any deduction which the OWNER may be
authorised to make under the agreement, the CONTRACTOR shall receive payment from the OWNER as follows :-
(i) 10% (Ten percent) of the contract price as down payment against submission of Bank
Guarantee Bond for an equal amount valid till the date of completion. Bank Guarantee Bond submitted against down payment shall be released when the entire work is completed and on
issuance of Completion Certificate.
(ii) 10% (Ten percent) of the Contract Price against submission and approval of
Engineering drawings & details.
(iii) 50% (Fifty percent) of the Contract Price against delivery of all materials and
equipments at site.
(iv) 15% (Fifteen percent) of the Contract Price against erection and commissioning on
pro-rata basis.
(v) Balance 15% (Fifteen percent) of the Contract Price on completion of the entire work
and testing and handling over to the OWNER against submission of performance Bank
Guarantee Bond for 5% of the completion cost, valid for a period of 12 months from the date
of completion of work.
The performance Bank Guarantee Bond held for 5% of the completion cost shall be in
addition to the initial security deposit of 2.5% (Two and a half percent) and shall be released on expiry of maintenance period after satisfactory conduct of performances test and
completion of rectifications if any and issuance of “Final Acceptance Certificate” by the
OWNER and submission of “No Claim Certificate” by the CONTRACTOR.
Read : In respect of E&M Works subject to any deduction which the OWNER may be
authorized to make under the agreement, the CONTRACTOR shall receive payment from the
OWNER as follows :-
(i) (a) 10% (Ten Percent) of the Contract price as mobilization advance with 2 (Two)
weeks after the effective date of agreement or date of deposit of initial security, whichever is later against a Bank Guarantee from scheduled bank for 110% amount of advance in format
prescribed by the owner, valid upto issue of “Completion Certificate” by the OWNER. Any
outstanding Bank Guarantee Bond shall be released when the entire work is completed as per
the Agreement and on issuance of “Completion Certificate” by the ENGINEER.
(b) Mobilization advance shall be paid in 2 (Two) or more installments to be decided by
the OWNER. Each installment will not be more than 50% of the total admissible Mobilization Advance. Subsequent installments of advance shall be released by the OWNER only after
satisfying himself for appropriate utilization of previous advances, if necessary / feasible,
based on indicative documentary proof of expenditure incurred on material / equipment
and / or on quantum of work initiated on ground
(c) Mobilization Advance will bear simple interest of 10% (Ten Percent) per annum and
shall be calculated on the outstanding amount of advance from the date of recovery, both days inclusive.
(ii) 60% (Sixty percent) of the Contract price or value of material (as per paid voucher) whichever is less, against delivery of all materials and equipments at site on sufficient
documentary proof and on certification by the Engineer and acceptance by the OWNER.
(iii) 15% (Fifteen percent) of the Contract Price against erection and commissioning on
pro-rata basis.
(iv) Balance 15% (Fifteen percent) of the Contract Price on completion of the entire work and testing and handing over to the OWNER against submission of performance Bank
Guarantee Bond for 5% of the completion cost, valid for a period of 24 months from the date
of completion of work.
The performance Bank Guarantee Bond held for 5% of the completion cost shall be in
addition to the initial security deposit of 2.5% (Two and a half percent) and shall be released
on expiry of maintenance period after satisfactory conduct of performances test and completion of rectifications if any and issuance of “Final Acceptance Certificate” by the
owner and submission of “No Claim Certificate” by the CONTRACTOR.
ANNEXURE – III
SCOPE OF WORK AND COMPLETION MILES STONES
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
NAME OF WORK: PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR
DRDO SKILL DEVELOPMENT CENTRE
FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER
AND CBRN SITE, PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
SCOPE OF WORK AND COMPLETION MILES STONES
_______________
Sl. No Scope of Work Period of Completion from
Effective date of L. O. I.
_______________
Provision of Project Management Consultancy (PMC) 23 (Twenty Three) Months
Services for DRDO Skill Development Centre for
Integrated Safety Management in Fire, Disaster and CBRN Site, Pilkhuwa
____________
ANNEXURE – IV
SCOPE OF PROJECT MANAGEMENT CONSULTANCY (PMC)
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
SCOPE OF PROJECT MANAGEMENT CONSULTANCY (PMC)
PROVISION OF PROJECT MANAGEMENT CONSULTANCY (PMC) SERVICES FOR
DRDO SKILL DEVELOPMENT CENTRE FOR INTEGRATED SAFETY MANAGEMENT
IN FIRE, DISASTER AND CBRN SITE, PILKHUWA.
1. Planning, scheduling for site preparation & enabling activities including site supervision of
all project sites to include civil, structural and E/M works. The work sites are located in the
following areas of project site:-
(a) CBRN Site, Pilkhuwa
2. Project Planning:
a) Planning and scheduling
i) Planning and co-ordination of all activities including those connected with the
implementation of temporary and permanent works of the project.
ii) Preparation of project schedule in the form of a Master PERT/CPM network, bar
charts, S-curve etc., with the help of computer. Preparation of monthly work schedule
in advance for all works. Forecasting the anticipated delays and suggesting the
corrective measures to prevent slippage of overall / part of the project schedules.
Computer & supplementary accessories/consumable items such as cartridge, paper
will be provided by PMC agency.
iii) Monthly updating of the schedule based on feed back on progress of work.
iv) Preparation of monthly progress reports, identifying the areas where progress of
work is not as per time schedule and suggesting corrective measures for timely
completion of work including preparation of contingent plans.
v) Progress monitoring and quality assurance for all works with feed back and
interaction systems for corrective measures.
vi) Planning, co-ordination, monitoring, supervision and quality assurance connected with
execution of the works.
vii) Planning of complete construction/ erection work including construction materials and
construction equipment.
viii)Issue of monthly construction progress reports and forecasting monthly site work
plan.
b) Budget & cost control
a) Firming up of detailed cost estimates for the purpose of budgetary and cost control.
3. Site activities:
a) Supervision of all site activities viz, civil and structural works as well as E/M to ensure
that work is being executed as per contract, BOQ, drawings and specifications.
b) Inspection and checking of works at various stages and maintaining the records e.g.,
checklists, cards, inspection reports etc., Inspection and checking shall be done as per
BOQ, approved drawings relevant specifications and instructions of Engineer-in-Charge.
c) Suggesting corrective measures for rectification of workmanship and quality of materials
before actual use in construction.
d) Checking out design & arrangement of shuttering, specially for high rise, long span
buildings/ strucatures.
e) Quantity estimation / deviations of various activities for planning purpose.
f) Checking levels and layout of various facilities and keeping records of all levels.
g) Supervision, inspection of structural fabrication works at workshop / yard.
h) System of interaction / meeting among consultant and suppliers / contractors / erectors
including meeting for progress review and monitoring with owner.
i) System of preparation of contingent site work plan, to maintain project completion and
commissioning schedule.
j) Quantity surveying, measurement and recording of measurements.
k) Quality control & certification of work for payment of bills.
l) Recommending for issue of certificates on completion of contractor’s work.
m) Suggesting & monitoring site safety measures.
n) Maintaining records of all quality related tests.
4. Quality Control Measures:
a) Preparation of quality assurance plan, monitoring and supervision for conducting field
and lab test of materials and works.
b) Maintaining records of all quality related tests.
c) Monitoring and supervision for conducting sample test at site lab and other approved lab
for approval of sample of various construction materials.
d) Monitoring and supervision for conducting testing & commissioning of various
equipments at site.
e) Physical inspection of all construction materials before use in terms of quality and
quantity. Monitoring and supervision carrying out necessary tests for acceptance.
5. PSMB, RPMBs, Road Register, PRBs, & Fan & Meter Register and As Built
Drawings:
Assisting in preparation of completion / as Built Drawings, reproducible, RPMBs,
PSMBs and Road Register, Circuit and layout of water supply lines, power lines, fire fighting,
lightening protection, earthing and earth pits, AC plan layout and road layout, inventory of
building fittings & fixtures, Inventory of electrical fittings & fixtures, Record of E/M
installation (Water supply, Electric supply & Air-conditioning Plants, Motors & Pumps etc).
E/M Plant Record Book, Electric fan and meter Register. Electrical wiring test sheet, Record
of earthing test. Testing of lightening conductors, Electric Bulb & Tube Account, Street light
record etc. as applicable.
ANNEXURE – V
LIST OF MANPOWER TO BE EMPLOYED
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018
LIST OF MANPOWER TO BE EMPLOYED
1. Providing of following technical persons :-
S. No. Designation of manpower Education Qualification / Experience No.
of
person
(a) Asstt Engineer (Civil) - B.E (Civil) Minimum 05 (Five) years
Or
Diploma (Civil) 15 years experience
1
(b) Junior Engineer (Civil) - Diploma (Civil) Minimum 04 (Four) years
experience
2
(c) Junior Engineer (E & M) - Diploma (Electrical/Mechanical) Minimum 05
(Five) years experience
1
Note - The AE Civil, JE (Civil) and JE (E/M) who have obtained degree/diploma from a
recognised Central Govt. / State Govt. and AICTE approved Pvt. Engineering Colleges / State
Govt. Certified Institutions for 3 years Diploma will only be eligible for PMC.
1. Employment of Engineers (Manpower) will be with prior approval of Engineer-in-Charge
and Verification of Essential Qualification and Experience of work with Central Govt. / State Govt. /
PSU to be done before engaging manpower at site.
2. Engineers to be employed / engaged with approval of Engineer-in-Charge during the duration
of Project Management Consultancy.
3. Agency to provide reliever / replacement in case of absence of engineer at site.
Cover - II
ANNEXURE – VI
BILL OF QUANTITIES
FOR
PROVISION OF PROJECT MANAGEMENT
CONSULTANCY (PMC) SERVICES FOR DRDO SKILL
DEVELOPMENT CENTRE FOR INTEGRATED SAFETY
MANAGEMENT IN FIRE, DISASTER AND CBRN SITE,
PILKHUWA.
TENDER ENQUIRY NO. : CCE(R&D)D/PILKHUWA/ENQ-III/17-18/0001
DATED 16 Mar 2018