PSMSpecialtyGroup

Page 2: PSM Specialty Group

Training Process Safety Management AUDITING

Ujwal Ritwik CRSP, QEP, REM, LA ISO 45001/14001/9001/22000/50001

PSM Expert

KuwaitChapter

Page 3: PSM Specialty Group

Objectives

Participants will - § Get an overview of Compliance Audit element of OSHA

standard 29 CFR 1910.119 § Get a snapshot Audit element of CCPS RBPS § Get a view of current state of practice of Auditing for Process

Safety Management

Page 4: PSM Specialty Group

Agenda Overview Session - 1

§ Audit definition § Quick recap of OSHA Process Safety Management Standard 29

CFR 1910.119 § Requirements of Compliance Audit in OSHA PSM § Success factors for auditing § Requirements of PS Audit in CCPS RBPS § Question - answer

Page 5: PSM Specialty Group

Why I am interested –  I remain deeply interested in Process Safety

–  Background of Nuclear Industry where public risk perception is critical

–  Began career in high hazard chemical industry, encountered several situations and major accident

– Worked at ICI, originator of HAZOP, and met Trevor Kletz

–  Part of team to survey Major Hazard Control program in India; experienced several catastrophic accidents closely

–  Became passionate about PS and risk management; self appointed ambassador

–  Implemented Process Safety Management at KPC and KNPC TrainingonPSMAuditing:UjwalRitwik

Page 6: PSM Specialty Group

Quick Revisit of Process Safety Management

Page 7: PSM Specialty Group

Opening question

Wouldyouliketohavebenefitsofcheaperenergy,plastic,fuel,transport,technology,conveniencesoflife?

TrainingonPSMAuditing:UjwalRitwik

Areyoureadytopaytheprice-hurtandkillpeople,poisontheenvironment,losemoneyand

destroyproperty?

Page 8: PSM Specialty Group

The History of Major Chemical Accidents

•  Flixborough,UnitedKingdom,1974•  Seveso,Italy,1976•  Bhopal,India,1984•  PemexLPGTerminal,MéxicoCity,México,1984•  PiperAlphaPlatform(Offshore),UKContinentalShelf,1988•  TexasCity,Texas,BP2005•  BuncefieldOilDepotFire,HertfordshireUK,2005•  GulfofMexico,BPMacondo,2010

WhendidPSMstart?

TrainingonPSMAuditing:UjwalRitwik

Page 9: PSM Specialty Group

OnthenightofDecember2-3,1984,asuddenreleaseofabout30metrictonsofmethyliso-cyanate(MIC)occurredattheUnionCarbidepesticideplantatBhopal,India.Theaccidentwasaresultofpoorsafetymanagementpractices,poorearlywarningsystems,andthelackofcommunitypreparedness.Theaccidentledtothedeathofover3,500peoplelivinginthevicinityandcausedrespiratorydamageandeyedamagetoover20,000others.Atleast200,000peoplefledduringtheweekEstimateddamage$350millionto$3billion

Methyl Isocyanate Tank Rupture and Release Bhopal, India – Dec. 2-3, 1984

TrainingonPSMAuditing:UjwalRitwik

Page 10: PSM Specialty Group

Phillips 66 Houston Chemical Complex Pasadena, Texas – Oct. 23, 1989

OnOctober23,1989,anexplosionandfirerippedthroughthePhillips66CompanyHoustonChemicalComplexinPasadena,Texas.Twenty-threeworkerswerekilledandmorethan130wereinjured.Propertydamagewasnearlythree-quartersofabilliondollars.Morethan85,000poundsofhighlyflammablegaseswerereleasedthroughanopenvalve,duringregularmaintenanceoperationsononeoftheplant'spolyethylenereactors.Avaporcloudformedandtraveledrapidlythroughthepolyethyleneplant.Within90to120seconds,thevaporcloudcameintocontactwithanignitionsourceandexplodedwiththeforceof2.4tonsofTNTTrainingonPSMAuditing:UjwalRitwik

Page 11: PSM Specialty Group

Regulatory Responses – Clean Air Act Amendments of 1990

1.  OSHAProcessSafetyManagementregulations–(29CFR1910.119)concernedwithaccidentpreventionintheworkplace(1992)

2.  EPARiskManagementProgramRegulations(40CFRPart68)-concernedwithaccidentpreventiontoprotectthepublicandenvironment(1996)

3.  TheAmendmentsalsoestablishedtheindependentU.S.ChemicalSafetyandHazardInvestigationBoard(42U.S.C.7412)(CSB,1998)

TrainingonPSMAuditing:UjwalRitwik

Page 12: PSM Specialty Group

29 CFR 1910.119

OSHA’sProcessSafetyManagementStandard

TrainingonPSMAuditing:UjwalRitwik

Page 13: PSM Specialty Group

Elements of PSM Standard

1.  EmployeeParticipation2.  ProcessSafetyInformation3.  ProcessHazardAnalysis4.  OperatingProcedures5.  Training6.  Contractors7.  Pre-startupSafetyReview

TrainingonPSMAuditing:UjwalRitwik

8.  MechanicalIntegrity9.  Hot-workPermits10.  ManagementofChange11.  IncidentInvestigations12.  EmergencyPlanning&Response13.  ComplianceAudits14.  TradeSecrets

Page 14: PSM Specialty Group

Quiz

1.  Whatpricedowepayforcheaperenergy,chemicalsandplastics?2.  WhatpromptedCleanAirActAmendmentBill(USA,1990)?3.  WhatyearOSHAPSMstandardregulationwasbroughtinforce?4.  WhatisthecompanionregulationbyEPAtoprotectpublicand

environment?5.  HowmanyelementsdowehaveinOSHAPSMstandard?

TrainingonPSMAuditing:UjwalRitwik

Page 15: PSM Specialty Group
Page 16: PSM Specialty Group

Components of OSHA - PSM Compliance Audit Element

Page 17: PSM Specialty Group

Audit is a feedback mechanism that provides management with the status and measurement of effectiveness of the various efforts and leads to the appropriate control over these efforts A site audit program consists of

- separating the PSM program into its component parts - auditing each part to determine actual versus intended effectiveness - formulating corrective action to improve performance - reporting / documenting findings - follow up controls

In addition to PSM improvement often audits point to improvements in operations, maintenance, and engineering aspects Compliance Audit: Evaluation of compliance with the provisions of law

What is Process Safety Management Audit

Page 18: PSM Specialty Group

29 CFR 1910.119, OSHA Process Safety Management of Highly Hazardous Chemicals (o) Compliance Audits

(1) Employers shall certify that they have evaluated compliance with the provisions of this section at least every three years to verify that the procedures and practices developed under the standard are adequate and are being followed

(2) The compliance audit shall be conducted by at least one person knowledgeable in the process

(3) A report of the findings of the audit shall be developed

(4) The employer shall promptly determine and document an appropriate response to each of the findings of the compliance audit, and document that deficiencies have been corrected

(5) Employers shall retain the two (2) most recent compliance audit reports

OSHA PSM Compliance Audit Text

Page 19: PSM Specialty Group

Compliance Audits - Requirements

• ComplianceauditsofPSMProgramevery3years• Auditsconductedbyperson(s)knowledgeableintheprocess• Auditteamsizewillvary•  Trainedauditteamleader• Writtenreportofcorrectiveactionandfollow-up•  Last2complianceauditreportsonfile• Createdocumentationofsafeandunsafepractices

TrainingonPSMAuditing:UjwalRitwik

Page 20: PSM Specialty Group

Compliance Audits – Recommendations

•  TrainedauditteamsortrainedsingleauditorsshouldconductPSMaudits

• PSMauditsshouldconsistofPSMprocessdocumentreviews,recordsreviews,employeeinterviewsandonsiteobservations

•  Trackingsystemsshouldbeusedtomanageauditrecommendations/correctiveactions

TrainingonPSMAuditing:UjwalRitwik

Page 21: PSM Specialty Group

Compliance Audits – Recommendations

•  Thirdparty(outside)auditorswhileimpartialarenotmandated• However,U.S.OSHAsays,"Theauditshouldbeconductedorledbyapersonknowledgeableinaudittechniqueswhoisimpartialtowardsthefacilityorareabeingaudited."(emphasisadded)

• Certificationofauditrequiredbyresponsibleperson-shouldincludesignatureanddate

TrainingonPSMAuditing:UjwalRitwik

Page 22: PSM Specialty Group

Compliance Audits – Recommendations

• PSM“StatusAssessments”,“ReadinessReviews”,etc.canbecountedasauditsiftheyweredonetocomplywithAuditProtocols

• Recommendationsdonothavetobedevelopedaspartoftheaudititselfbutcanbeaddedlater

• ResolvingAuditRecommendations:•  notexpectingeverythingtobecompletedin2-3months•  everythingshouldbecompletedin6months,unlessjustificationiswarrantedforlongerperiod(e.g..leadtimeonmaterial)

•  keywillbewhatinterimstepshavebeentakentoassureemployeesafetyNote:Thesecommentsmayapplytootherelements

TrainingonPSMAuditing:UjwalRitwik

Page 23: PSM Specialty Group

Compliance Audits – Recommendations

• ResolvingAuditRecommendations:•  Facilitiescannottakethe3yearsuntilthenextaudittocorrectfindings-correctiveactionsshouldstartimmediately

•  Standardauditprotocol/checklistorreportformatisrecommended•  Thetriennialrequirementforthenextauditshouldbemeasuredfromthecertificationdateofthepreviousaudit

TrainingonPSMAuditing:UjwalRitwik

Page 24: PSM Specialty Group

Compliance Audits – Best Practices • Useauditteammembersfromotheroperatingdepartmentsatsite• Useauditteammembersfromothersites• Conductauditsonasmallerscopebutmorefrequentbasis

TrainingonPSMAuditing:UjwalRitwik

Page 25: PSM Specialty Group

Auditing Audit Program • Haveyouestablishedaformalauditprogramtoreviewtheprocesssafetyofyourfacility?

• Doestheprogramcallforre-evaluationauditsatleasteverythreeyears?

• Doyouhavearecommendationstrackingsysteminplacethatassuresthatdeficienciesaredocumented,assignedtoaresponsiblepartyforcorrectiveaction,anddocumentedwhencomplete?

• AreyourauditsconductedbyanindividualorteamthatisknowledgeableofthePSMprogramandrequirements?

TrainingonPSMAuditing:UjwalRitwik

Page 26: PSM Specialty Group

Compliance Audit Checklist

TrainingonPSMAuditing:UjwalRitwik

Page 27: PSM Specialty Group

Quiz

1.  WhatisthenameofthePSMelementonaudit?2.  Whoissupposedtodotheaudit?3.  Howoftentheauditisrequired?4.  Whomustbepartofauditteam?5.  Whatmustbedocumentedbytheemployerafterreceivingan

auditreport?6.  Howmanycomplianceauditreportstheemployerisrequiredto

retain?

TrainingonPSMAuditing:UjwalRitwik

Page 28: PSM Specialty Group

Auditing Success Factors

Page 29: PSM Specialty Group

Effectiveness of PSM Audits

TrainingonPSMAuditing:UjwalRitwik

D.JonesSurvey(2000)figuresuggestedthat•  ProcessSafetyManagement(PSM)complianceauditsarespecificand

comprehensive,focusingon14elementsofOSHA’sPSMStandards•  Awell-plannedandorganizedauditprocess—includingcross-trainedpersonnel,

auditchecklistsandself-audits—canhelpensureasuccessfuloutcome•  ThePSMauditshavebroughtthenumberofaccidentsdownverysharply•  PSMsystemsauditsaskedthetopcorporatemanagementtounderstandits

importanceandallocatesufficientresourcesforitsongoingsuccess

Page 30: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

Page 31: PSM Specialty Group

Top 7 PSM Audit Violations and How to Avoid Them - 1

TrainingonPSMAuditing:UjwalRitwik

1.OutdatedProcessSafetyInformation

e.g.Safetyreliefsystem,inventory,ventilationcalculations,“Fieldverified”pipingandinstrumentationdrawings(P&IDs);Manytimes,facilitieshavemadechangestotheprocesssystemwithoutupdatingthisdocumentation.

2.PreviousProcessHazardAnalysis(PHA)Issues

OutstandingPHArecommendationsthathavenotbeenaddressedorproperlyclosedout.

3.VagueStandardOperatingProcedures(SOPs)

Thosethataregenericinnature,notequipmentspecificandhavenotbeenreviewed/certifiedannuallyasrequiredbytheOSHAStandard.

Page 32: PSM Specialty Group

Top 7 PSM Audit Violations and How to Avoid Them - 2

TrainingonPSMAuditing:UjwalRitwik

4.ImproperManagementofChange(MOC)Documentation

Toooften,aMOCiscompletedaftertheequipmenthasbeeninstalledandisoperational.EnsurethatMOCsarefullycompletedandsignedoffbytheauthorizingpersonnelbeforestartupoftheequipment.Similarly,MOCsaremanytimesforgottenwhencompletingchangestooperatingprocedures,Elements,etc.MOCsarerequiredforanychangeaffectinghowyoudosomething(i.e.,addingstepstothestart-upprocessofapieceofequipment).

5.LackofProperPSMTraining

PSMrequiresthatpersonnelinvolvedwiththeoperationandmaintenanceoftheammoniasystemreceiveinitialtrainingandrefreshertrainingeverythreeyears.

Page 33: PSM Specialty Group

Top 7 PSM Audit Violations and How to Avoid Them - 3

TrainingonPSMAuditing:UjwalRitwik

6.GapsinAuditFrequency

ThisreferstoauditsthathavenotbeenconductedeverythreeyearsasrequiredbythePSMStandardortheactionitemsthatweregeneratedfromthepreviousauditthathavenotbeenclosedoutintimeforthenextauditcycle.

7.ImproperorUnorganizedDocumentation

Inpreparationfortheaudit,ensureallofyourwrittendocumentationisuptodateandfiledinaformatthatiseasilyaccessibletotheauditor.Theauditorwillneedtoreadandreviewalargeamountofwrittenproceduresandguidelines.It’sbesttoplacethesedocumentsinanofficeorconferenceroomfortheauditortoworkfrom.Thiswillalsoprovideanareawheretheauditorcanworkprivatelyandconductemployeeinterviews.

Page 34: PSM Specialty Group

Incidents that underline Ineffective Auditing

TrainingonPSMAuditing:UjwalRitwik

§  Reviewofseveralcatastrophicaccidentshaverevealedineffectiveandinappropriateauditingpracticesprevalentpriortotheincidents

§  PiperAlphaoilrigfire1988–auditingdonebutnomanagementoversight,recommendationsnotactedupon

§  TexasCityRefineryexplosion2005–PSMauditsdonejustforcompletingtheritual,tofulfillpaperwork

Page 35: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

Page 36: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

6 July 1988: A series of explosions destroyed the Piper Alpha oil platform in the North Sea. One hundred and sixty seven men died in the world's worst offshore oil disaster.

Page 37: PSM Specialty Group

PSM Systems Audit

Page 38: PSM Specialty Group

Management System

§ OSHA29CFR1910.119isaregulatorystandard,1992§ Itisanobjectivestandardformanagingprocesssafety(PSM),andnotadetailedprescriptivestandard

§ Itisnotamanagementsystem§ Center for Chemical Safety (CCPS) in 2007 cameoutwith a ProcessSafetyManagementSystem–RiskBasedProcessSafetyManagementSystem(RBPS)

§ RBPShasfourfoundationalblocks,20elements

TrainingonPSMAuditing:UjwalRitwik

Page 39: PSM Specialty Group

PSM System Audit Vs. PS Audit

§ Process Safety ManagementSystemsAuditinclude

•  Policiesandprocedures•  Managementorganization•  Planningprocess•  R i s k a s s e s s m e n t a n dmanagement

TrainingonPSMAuditing:UjwalRitwik

§ ProcessSafetyAudit•  Moredetailedandspecific•  Provide increased assurance thatu n i t s a r e o p e r a t e d a n dmaintained people, plant andenvironmentareprotected

•  Sometime combine hazardevaluations

Page 40: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

CCPS - RBPS 3Pillar(FoundationalBlock)–ManageRisk3.1Element–OperatingProcedures3.2Element–SafeWorkPractices3.3Element–AssetIntegrityandReliability3.4Element–ContractorManagement3.5Element–TrainingandPerformanceAssurance3.6Element–ManagementofChange3.7Element–OperationalReadiness3.8Element–ConductofOperations3.9Element–EmergencyManagement4Pillar(FoundationalBlock)–LearnfromExperience4.1Element–IncidentInvestigation4.2Element–MeasurementsandMetrics4.3Element–Auditing4.4Element–ManagementReviewandContinuousImprovement

1Pillar(FoundationalBlock)-CommitmenttoProcessSafety1.1Element–ProcessSafetyCulture1.2Element–CompliancewithStandards1.3Element–ProcessSafetyCompetency1.4Element–WorkforceInvolvement1.5Element–StakeholdersOutreach2Pillar(FoundationalBlock)–UnderstandingHazardsandRisks2.1Element–ProcessKnowledgeManagement2.2Element–HazardIdentificationandRiskAnalysis

Page 41: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

CCPS - RBPS

Page 42: PSM Specialty Group

RBPS Audit Element - Overview

TrainingonPSMAuditing:UjwalRitwik

§  CriticalevaluationoftheRBPSmanagementsystemisoneoffourelementsintheLearningfromExperiencePillar(FoundationalBlock).

§  Theauditselementisintendedtoevaluatewhethermanagementsystemsareperformingasintended.

§  ItcomplementsotherRBPScontrolandmonitoringactivitiesinelementssuchasmanagementreview,metrics,andinspectionworkactivitiesthatarepartoftheassetintegrityandconductofoperationselements.

§  Theauditselementcomprisesasystemforscheduling,staffing,effectivelyperforming,anddocumentingperiodicevaluationsofallRBPSelements,aswellasprovidingsystemsformanagingtheresolutionoffindingsandcorrectiveactionsgeneratedbytheaudits.

Page 43: PSM Specialty Group

RBPS Audit Element – Key Principles 1

TrainingonPSMAuditing:UjwalRitwik

Thefollowingkeyprinciplesshouldbeaddressedwhendeveloping,evaluating,orimprovinganymanagementsystemfortheauditselement:§  MaintainaDependablePractice

•  Whenacompanyidentifiesordefinesanactivitytobeundertaken,thatcompanylikelywantstheactivitytobeperformedcorrectlyandconsistentlyoverthelifeofthefacility.

•  Theauditselementshouldbedocumentedtoanappropriatelevelofdetailinaprocedureorawrittenprogramaddressingthegeneralmanagementsystemaspectspreviously.

oEnsureconsistentimplementation.oIdentifywhenauditsareneeded.

Page 44: PSM Specialty Group

RBPS Audit Element – Key Principles 2

TrainingonPSMAuditing:UjwalRitwik

§  ConductElementWorkActivitiesNote:Thisnarrativeassumesthata2ndor3rdpartyauditteamisconductinganauditofthefullRBPSmanagementsystem.Manyofthesesameactivitieswouldberequiredfora1stpartyaudit;however,someofthelogisticalissuesandpreparatorytaskswouldbesimpler,ornonexistent,forateamself-auditingitsownfacility.

oPreparefortheaudit.oDeterminetheauditscopeandschedule.oAssembletheteam.oAssignresponsibilities.oGatheradvancedinformation.oPlanonsiteactivities.oConducttheaudit.oDocumenttheaudit.oAddressauditfindingsandrecommendations.

Page 45: PSM Specialty Group

RBPS Audit Element– Key Principles 3

TrainingonPSMAuditing:UjwalRitwik

§  UseAuditstoEnhanceRBPSEffectiveness

oMonitorRBPSmaturationovertimeforeachfacility.oSharebestpractices.

Page 46: PSM Specialty Group

Quiz

1.  WhatisthedifferencebetweenPSMSystemsauditandProcessSafetyaudit?

2.  IsCCPSRiskBasedProcessSafetyManagementSystemaregulation?

3.  HowmanyfoundingpillarsandelementsRBPShas?4.  HowmanykeyAuditingprinciplesRBPShas?5.  Whataretheprinciples?

TrainingonPSMAuditing:UjwalRitwik

Page 47: PSM Specialty Group

What did we do?

TrainingonPSMAuditing:UjwalRitwik

1.  OSHA PSM 2.  Compliance audit – a vital element of PSM standard 3.  Minimum requirements of the Compliance Audit program 4.  Audit checklist 5.  PSM System Audit Vs. PS Audit 6.  CCPS RBPS Auditing

Post session exercise – review the OSHA PSM Audit Checklist https://www.osha.gov/sites/default/files/2019-03/08_PSM_Auditing_Checklist.pdf

Page 48: PSM Specialty Group

Next session

TrainingonPSMAuditing:UjwalRitwik

1.  Current status of PSM auditing 2.  Best practices 3.  How to improve auditing 4.  Revision 5.  Question answer 6.  Conclusion

Page 49: PSM Specialty Group

TrainingonPSMAuditing:UjwalRitwik

Page 50: PSM Specialty Group

Thank you for being with us

Stay Home stay Safe