3rd PSS Meeting held on 28.06.2016
SOUTHERN REGIONAL POWER COMMITTEE BENGALURU
Record Notes of Deliberations of the 3
rd Meeting on PSS Tuning of Generators held
on 28th
June 2016
The 3rd
Meeting on PSS related issues was held at SRPC, Bengaluru on 28th June 2016. The List of
participants is furnished at Annexure-I.
Shri. S.R.Bhat, Member Secretary, SRPC welcomed the participants to the Meeting. He said that
the 2nd
Meeting on PSS tuning was held in the month of October 2015, in which, schedules and modalities
for PSS tuning for all generators of installed capacity of more than 50 MW had been finalized. He stated
that some noticeable progress had been observed from the utilities since PSS tuning for a few generators
had been completed while process had been initiated for most of the units. Step Response Test reports
received from the generators which had completed PSS tuning needed to be analyzed by PSS Study
Committee.
It was again noted that provision for PSS tuning was mandated in accordance with IEGC & CEA
(Technical Standards for Connectivity to the Grid) Amendment Regulations, 2013. The Enquiry Committee
for Grid Disturbances constituted by GoI had also emphasized on tuning of PSS (Recommendation 9.9.2).
This was also subsequently deliberated in the Meeting held in MoP (Para 1.4) to discuss the Task Force
Report.
Status of PSS:
APGENCO
Station Name Status of PSS tuning Comments/SRT report
submitted or not
Rayalaseema TPS Units 1
to U5
PSS tuning has been carried out on
13.1.2016 for U1 to U5
SRT report submitted.
Vijayawada TPS (NTTPS)
U1 to U7
PSS tuning had been carried out on
01.04.2016 for U1 to U4 & U7.
For U5 & U6, PO has been placed for
replacement of AVR with DAVR and
would be completed by December 2016.
SRT Report submitted for U1
to U4 and U7.
PSS tuning /SRT reports to be
submitted by December 2016
for Units-5 & 6.
SDSPP (Krishnapatnam
JV) U1 & U2
PSS tuning has been carried out on
07.10.2015 for U1 & 29.10.2015 for U2.
SRT Report submitted
Lower Sileru HEP U1 to
U4
Unit-1: Work order had been placed with
M/s BHEL on 4.6.2016 & PSS tuning
could be completed within a month.
Unit-2, 3 & 4 : DVR under tendering &
PSS tuning/SRT report to be
submitted by August 2016 for
Unit-1.
APGENCO was
3rd PSS Meeting held on 28.06.2016
would be completed within 6-8 months recommended to complete
the DVR replacement /PSS
tuning and submit the SRT
reports by March 2017.
Upper Sileru HEP U1 to
U4
Unit-1 & 2: Excitation systems were of
convention type and to be replaced for
making PSS provision. OERLIKON is
the OEM & not responding. Hence,
DVRs would be procured through
tenders.
Unit-3 & 4: Work order has been placed
with M/s. BHEL on 21.3.2016 & the PSS
tuning would be completed by August
2016.
APGENCO was suggested to
complete DVR replacement
/PSS tuning by Dec-2016.
SRT report to be submitted
by September 2016.
Srisailam RB HEP U1 to
U7
Work order had been placed with M/s
BHEL on 4.6.2016 for PSS tuning &
would be taken up soon after the
availability of water.
APGENCO was
recommended to ensure that
PSS tuning is completed
during water availability
(generation)
Andhra Pradesh IPPs
It was noted with concern that there was no representation from HNPCL.
Station Name Status of PSS tuning Comments/SRT graphs
submitted or not
HNPCL, Vizag PSS tuning and details as per
format not furnished. HNPCL to
furnish the details & PSS tuning
details before September 2016
GVK, Jegurupadu St–I, St
–II, Spectrum PGL, Lanco,
Kondapalli, Reliance
BSES, GMR Vemagiri,
Gowtami & Konaseema
APSLDC was requested to take
up for PSS tuning with the IPPs
of capacity above 50 MW.
TSGENCO
It was noted with concern that there was no representation from TSGENCO.
Station Name Status of PSS tuning Comments/SRT graphs
submitted or not
Kakatiya TPP U1 & 2 PSS tuning for the Unit-1 had been carried out
on 24.01.2016.
Unit-1 SRT submitted.
TSGENCO to furnish
PSS/SRT details for Unit-2.
Kothagudem TPS U5 to Unit-5 to 8: TSGENCO had informed that the TSGENCO to complete PSS
3rd PSS Meeting held on 28.06.2016
U11 units are 50 years old and already planned for
phasing out before December 2019 in the
phased manner as per the GOI No.J-
13012/24/2012-IA.II(T), Dt.16.07.2015.
Unit-9 to 11: PSS tuning had been carried out
on 22.12.2015.
tuning else approach Hon’ble
CERC for exemption.
SRT submitted for Unit-9 to
11.
Nagarjunasagar HEP U1
to U8
PSS not available for U1.
PSS tuning had been carried out for Unit-2 to
6 & 8 on 26.05.2015 & Unit-7 on 19.07.2015.
PSS details for Unit-1 were
yet to be submitted.
SRT submitted for Unit-2 to
8.
Srisailam LB HEP U1 to
U6
- TSGENCO was
recommended to complete
PSS tuning in
August/September 2016 (as
water / generation would be
available) and submit SRT
reports.
KPCL
It was noted with concern that there was no tangible progress by KPCL. KPCL representative was
suggested to appraise the Management and ensure timely compliance. KPCL to revert back with
unit/station-wise action plan within a month.
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
Raichur TPS U1 to U4 KPCL informed that Unit-4 was
equipped with AVR and to be replaced
with DVR.
KPCL was recommended to
complete PSS tuning and submit
SRT reports by September 2016 for
Unit-1 to 3.
Replacement with DVR / PSS tuning
/SRT reports to be completed by
March 2017 for Unit-4.
Raichur TPS U5 to U8 AVR to be replaced with DVR for Unit 6 KPCL was recommended to
complete PSS tuning and submit
SRT reports by September 2016 for
Unit-5, 7 & 8.
Replacement with DVR / PSS tuning
/SRT reports to be completed by
March 2017 for Unit-7.
BTPS U1 & U2 KPCL had informed that Step
Response Test for Unit 1 was
completed on 15.10.2015 and Unit 2
was done on 17.07.2012. KPCL had
agreed to conduct Step Response Test
for U2 during Overhaul period before
March 2016.
It was noted that the reports
furnished were PID test (at no load)
for AVR and not PSS tuning reports.
KPCL was recommended to
complete PSS tuning and submit the
SRT reports by September 2016 for
Unit-1 & 2.
3rd PSS Meeting held on 28.06.2016
KPCL was suggested to complete
the PSS tuning and submit the SRT
reports before COD for Unit-3.
Yeramarus TPP In the meeting, KPCL informed that
PSS tuning and SRT would be taken
up before COD.
KPCL was suggested to complete
the PSS tuning and submit the SRT
report before COD.
Almathy HEP U2 to U6 In the meeting, KPCL informed that
discussion with M/s BHEL was
scheduled for discussion in August
2016.
KPCL was suggested to complete
the PSS tuning and submit the SRT
reports by September 2016.
Sharavati Tail Race U1
to U4
In the meeting, KPCL informed that
static AVRs were to be replaced with
DVRs.
KPCL was recommended to replace
with DVRs and complete PSS tuning
and submit SRT reports by March
2017.
Varahi UGPH HEP U1
to U4
In the meeting, KPCL informed that M/s
BHEL had not come up for discussion
for Unit-1 & 2.
For Unit-3 & 4, they received the offer
and the quotes were on the higher side.
KPCL was suggested to complete
the PSS tuning and submit the SRT
reports by September 2016.
Nagjheri HEP U1 to U6 In the meeting, KPCL informed that the
OEMs were not responding.
KPCL was suggested to complete
the PSS tuning and submit the SRT
reports by September 2016.
Sharavathy HEP U1 to
U10
In the meeting, KPCL informed that the
discussions with M/s BHEL were
underway.
In view of revival of the units after
fire accident, KPCL was
recommended to complete the PSS
tuning and submit the SRT reports
by March 2017.
Karnataka IPPs
It was noted with concern that there was no representation from JSWEL.
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
UPCL U1 & U2 Step Response Test was carried out for
Unit-1 & 2 on 04.10.2015.
SRT reports were submitted for Unit-
1 & 2.
UPCL was suggested to submit that
PSS details in the format.
JSWEL U1 to U4 In the meeting, it was noted that PSS
details were not received from JSWEL.
JSWEL was recommended to
carryout PSS tuning and submit the
SRT reports by August 2016.
JSWEL was suggested to submit that
PSS details in the format.
KSEBL
3rd PSS Meeting held on 28.06.2016
KSEBL stated that since cost for ensuring PSS (since units were very old and complete replacement of the
excitation system was required) was quite high, the expenditure could be met through PSDF as it was for
reliable grid operation.
It was noted that PSDF funding proposal needed to be submitted to NLDC and the Appraisal Committee
would take a call on it.
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
Idukki HEP U1 to U3 In the meeting, KSEBL informed that
the RMU had been tendered and
awarded to M/s Alstom. Engineering
works were expected to be completed
in one year and another six months for
the commissioning activities. PSS have
been included in the tender document.
KSEBL was recommended to ensure
that PSS tuning is completed by
December 2017.
Idukki HEP U4 to U6 In the meeting, KSEBL informed that
the existing cards were checked and
PSS was enabled. Heavy oscillations
were observed and PSS was disabled.
As OEM assistance was not available,
they would once again attempt PSS
tuning through internal resources during
AMC & after gaining experience of PSS
at other stations.
KSEBL was recommended to ensure
PSS tuning else approach Hon’ble
CERC for exemption.
Lower Periyar HEP
U1
In the meeting, KSEBL informed that
tendering was underway and pre-bid
was under discussion for replacement
of exciter. It would take three months
after PO is placed.
KSEBL was recommended to ensure
that the replacements and PSS tuning
is completed before December 2016.
Lower Periyar HEP
U2 & U3
In the meeting, KSEBL informed that
both M/s BHEL/Andritz had been
referred. M/s BHEL had come forward
but the offer was not conclusive. M/s
BHEL had informed that they would
assess the healthiness of the cards and
try for PSS tuning, if possible in the
available cards.
KSEBL to complete PSS tuning else
approach Hon’ble CERC for
exemption.
Sabarigiri HEPU1 to
U6
In the meeting, KSEBL informed that
the PSS would be completed by within
three months for five units (except Unit-
4).
KSEBL to complete PSS tuning and
submit SRT reports by October 2016.
TANGEDCO
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
3rd PSS Meeting held on 28.06.2016
NCTPS St-1 U1 to U3 PSS tuning was carried out on
14.7.2013 (U-1), 07.01.2016 (U-2) and
26.10.2015 (U-3)
TANGEDCO to take action as per the
recommendations of the Study
Committee.
NCTPS St-II U1 & U2 In the meeting, TANGEDCO informed
that PSS tuning for U-1 & 2 was
scheduled for August 2016 &
September 2016 respectively through
M/s BHEL.
TANGEDCO was suggested to submit
the SRT reports by October 2016.
Tuticorin TPS U1 to
U5
PSS tuning was completed for U-1
(28.11.2008), U-2 (20.08.2012), U-3
(10.1.2013), U-4 (03.07.2014) & U-5
(30.09.2015).
TANGEDCO was suggested to go for
PSS tuning for the units which was
taken up before August 2013 or within
three years of last PSS tuning.
Mettur St-I TPS U1 to
U4
PSS tuning was completed for U-1
(26.7.2013), U-2 (08.12. 2015),
U-3 (30.09.2012) & U-4 (09.10.2015).
TANGEDCO was suggested to go for
PSS tuning for the units which was
taken up before August 2013 or within
three years of last PSS tuning.
Mettur St-II TPS U1 In the meeting, TANGEDCO informed
that PSS tuning would be taken up
through M/s ABB.
TANGEDCO was suggested to submit
the SRT reports by October 2016.
Kundah III HEP U1 to
U3
In the meeting, TANGEDCO informed
that DAVR was not available and
requested for exemption since units
capacity was less than 100 MW.
TANGEDCO to complete PSS tuning
else approach Hon’ble CERC for
exemption.
Aliyar HEP U1
Kodayar I U1
Kadamparai HEP U1
to U4
In the meeting, TANGEDCO informed
that DAVR was available and PSS
tuning was to be taken up by OEM.
TANGEDCO was recommended to
ensure that PSS tuning is completed
before September 2016.
Kovil Kalappal (Gas) TANGEDCO informed that SRT would
be carried out after consultation with
OEM during next possible major shut
down opportunity.
TANGEDCO was suggested to
complete the SRT before September
2016.
TN IPPs
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
STCMS TNSLDC was suggested to follow up
the PSS tuning and ensure SRT test
before September 2016. Gas IPP Stations
CGS/ISGS
It was noted with concern that there was no representation from NTPL, KGS, MAPS & KKNPP.
3rd PSS Meeting held on 28.06.2016
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
NTPC, Ramagundam
STPS U1 to U7
In the meeting, NTPC informed that
SRT would be taken up for U1 (Dec -
16), U2 (Dec-16), U3 (Dec-16), U4
(Sep-16), U5 (Oct-16) & U6 (Aug-16) &
PO has been placed on M/s Siemens.
For U6, PO had been placed with M/s
Siemens for DAVR replacement. For
U7, PO had been placed with M/s
BHEL for SRT & PSS tuning.
NTPC, Ramagundam was suggested
to complete the works and submit the
SRT reports before December 2016.
PSS details as per format to be
furnished.
NTPC, Simhadri St-I &
II U1 to U4
In the meeting, NTPC informed that the
SRT had been taken up for
U1(14.03.2016) and for U2, U3 & U4
on 18.03.2016
NTPC, Simhadri to take up action as
per Study Committee
Recommendations.
PSS details as per format to be
furnished.
NTPC, Talcher STPS
St-II U 3 to U6
In the meeting, NTPC informed that
SRT for U3 & 6 was completed
between 04.06.2016 to 07.06.2016.
For U4 & U5 was not completed due to
port problem. The issue would be
rectified during the annual
maintenance.
NTPC, Talcher to take up action as per
Study Committee Recommendations
for U3 & U6.
SRT for U4 & U5 to be submitted
before December 2016.
PSS details as per format to be
furnished.
NTPC, Kudgi NTPC, Kudgi to ensure PSS tuning
before COD.
NTPC, RGCCP,
Kayamkulam 2 GTs &
1 ST
In the meeting, NTPC informed that
they were ready to conduct the SRT
test at 80% load.
NTPC was suggested to carry out SRT
whenever the unit(s) are scheduled
above 80%.
NTECL, Vallur TPS U1
– U3
In the meeting, NTECL informed that
SRT of U1 (09.03.2012), U2
(09.08.2015) & U3 (28.02.2014) had
been carried out.
It was noted that the reports furnished
were PID test (at no load) for AVR
and not PSS tuning reports.
NTECL agreed to complete the PSS
tuning by July 2016 for all the three
units and submit the SRT.
NLC, Neyveli TPS I U7
to U9
In the meeting, NLC informed that M/s
BHEL would be visiting NLC next week
for discussions.
NLC TS-1, was suggested to submit
the SRT before December 2016.
PSS details as per format to be
furnished.
NLC, Neyveli TPS I
Exp U1 & U2
In the meeting, NLC informed that SRT
had been carried out on U-1
(12.10.2015) and U-2 (05.11.2015).
NLC TPS-1 Exp was suggested to
submit the SRT.
NLC, Neyveli TPS II
U1 to U7
In the meeting, NLC informed that the
contract for SRT was in advance stage
and SRT would be completed by
December 2016.
NLC TS-1, was suggested to submit
the SRT by December 2016.
NLC, Neyveli TPS II
Exp U1 & U2
In the meeting, NLC informed that SRT
would be completed by 15.07.2016.
NLC TS-II Exp was suggested to
submit the SRT before July 2016.
3rd PSS Meeting held on 28.06.2016
PSS details as per format to be
furnished.
(NLC & TN JV)NTPL
U1 & U2
In the meeting, NLC informed that as
per feedback, PSS was on. SRT
would be taken up shortly.
NTPL was suggested to complete the
SRT and submit the report before Sep
2016.
PSS details as per format to be
furnished.
NPCIL, KGS U1 to U4 PSS not in service for U-1 & U-2.
PSS tuning was carried out for U-3
(19.04.2007) & U-4 (17.01.2011).
KGS was suggested to enable the PSS
and complete the SRT for U-1 & U-2
and submit the report by Sep 2016.
For U-3 & U-4 complete the SRT and
submit the report by Sep 2016.
NPCIL, MAPS U1 &
U2
PSS tuning was carried out for U-1
(11.01.2006) & U-2 (03.08.2003).
MAPS to complete the SRT and submit
the report by Sep 2016.
NPCIL, KKNPP KKNPP had informed that SRT was
done on 07.06.2014.
KKNPP to take action as per Study
Committee recommendation.
KKNPP to ensure PSS tuning before
COD of U-2.
ISTS connected IPPs
It was noted with concern that there was no representation from SEL, CEPL, IL&FS and SGPL.
Station Name Status of PSS tuning Comments/SRT graphs submitted
or not
Simhapuri Energy Ltd
(SEL) U 1 to U4
PSS not available. SEL to ensure PSS availability by
December 2016.
MEPL U1 & U2 In the meeting, MEPL informed that
PSS was not available and they were
in discussion with their OEM.
MEPL to ensure PSS availability by
December 2016.
TPCIL (Thermo Power
Tech) U1 & U2
In the meeting, TPCIL informed that
PSS was carried out on U-1
(22.12.2014) & U-2 (11.08.2015). SRT
was planned to be taken up on
20.08.2016 for U-1 and SRT for U-2
would be taken up during shut down.
It was noted that earlier reports were
PID test reports (at no load) for AVR.
SRT to be taken up by TPCIL and
complete for both the units before
December 2016.
Coastal Energen CEPL was suggested to complete the
SRT and submit the report before Sep
2016.
PSS details as per format to be
furnished.
IL & FS SRT for U-1 was carried out on
12.04.2015.
IL&FS to take up action as per Study
Committee Recommendation for U-1.
SRT for U-2 to be carried out before
Sep 2016.
PSS details as per format to be
furnished.
3rd PSS Meeting held on 28.06.2016
Lanco Stage II & III LKPPL was suggested to complete the
SRT and submit the report before Sep
2016.
PSS details as per format to be
furnished.
SGPL, Nellore SGPL to ensure PSS tuning and SRT
before COD.
Other issues:
KSEBL /TANGEDCO pointed out that many Hydro units were very old and needed exorbitant cost
to enable them with PSS. IEGC /CEA Connectivity Regulations had come up subsequently. CEA
Regulation mandates PSS only for Units above 100 MW.
CEA Connectivity Regulations stipulates:
Part II
Connectivity Standards applicable to the generating stations
A. Connectivity Standards applicable to the Generating Stations other than wind and
generating stations using inverters
……………..
A1.For Generating stations which are connected on or after the date on which CEA
(Technical Standards for Connectivity of the Grid) Regulation, 2007 became effective
( 1 ) The excitation system for every generating unit:-
…………………..
( c ) The Automatic Voltage Regulator of generator of 100 MW and above shall include
Power System Stabilizer (PSS)
……………………
A2. For Generating stations which were already connected to the grid on the date on
which CEA (Technical Standards for Connectivity of the Grid) Regulation, 2007 became
effective
For all thermal generating unit having rated capacity of 200 MW and above and hydro units
of having rated capacity of 100 MW and above, the following facilities would be provided at
the time of renovation and modernization.
…………………..
( 2 ) Every generating unit of capacity having rated capacity of higher than 100 MW shall
have Power System Stabilizer.
……………………
IEGC Regulations 5.2(k) stipulates
“All generating stations shall normally have their automatic voltage regulators (AVRs) in
operation. In particular, if a generating unit of over fifty (50) MW size is required to be operated
without its AVR in service, the RLDC shall be immediately intimated about the reason and
duration, and its permission obtained. Power System Stabilizers (PSS) in AVRs of generating
units (wherever provided), shall be got properly tuned by the respective generating owner as per
a plan prepared for the purpose by the CTU/RPC from time to time. CTU/RPC will be allowed to
carry out checking of PSS and further tuning it, wherever considered necessary.”
In view of the above provisions, it was suggested that respective entities could suitably take up for
exemption with Hon’ble CERC for the applicable units.
3rd PSS Meeting held on 28.06.2016
Generators was suggested to go for PSS tuning/SRT for the units for which SRT was taken up
before August 2013 or within three years of last SRT.
It was agreed to form a PSS web group in which all the SRT/PSS details would be posted.
The following to be taken care during SRT/Report preparation :
Damping Torque to be calculated for every SRT test with and without PSS.
Power System Stabilizer Models to be given along with the implemented settings (Final).
SRT to be carried out at >80% Load and at 50% loading.
Both Step Up and Step Down tests needs to be carried out.
Real (Active) Power Scale to be within 10 % of operating point in the graphs. Proper Graphs
(soft copy) with visible scale to be provided.
Make, Type & Model of Excitation System to be provided.
Step up to be followed by Step down with a time gap of 20 sec, if taken up, simultaneously.
Station personnel to co-ordinate and be associated with the OEM/Testing Agency during the
SRT test to ensure the requirements as envisaged.
It was observed that PSS performance of brushless exciters was not evident when compared
to the PSS performance of static exciters. There was no discernible improvement observed
with PSS On with respect to PSS Off for the units equipped with brushless exciters. It was
opined that the brushless excitation system were improved version and M/s BHEL / OEM
require to be address the issue for making PSS performance more effective.
It was also noted with concern that many of the submitted graphs/reports were not legible. Hence it
was agreed that Step Response Test Reports would be furnished in the specified format /Graph as
given in Annexure- II. Active Power, Reactive Power, Terminal Voltage, Field Current and PSS
contribution in different colours would be ensured. Soft copy of the graphs/report needed to be sent
to web group and SRLDC ([email protected]) / SRPC ([email protected] )/ CTU
It was agreed that the exact schedule of testing would be communicated to SLDC/SRLDC/SRPC.
There could be representation from SRLDC, SRPC Secretariat & State during PSS tuning/ Step
Response Test being conducted by OEM.
All the utilities would take up with their OEMs/Testing Agency at the earliest to conduct Step
Response Test as per the schedule.
All new units with capacity over 50 MW must carry out PSS tuning before declaration of Date of
Commercial Operation (COD). A report in the specified format along with model parameters shall
be submitted to SRLDC/SRPC/CTU.
PSS shall be kept in service (“On” or energized and performing as designed by the manufacturer).
PSS could be taken out only under intimation to SLDC/SRLDC along with technical justification i.e.
for short duration of one week.
Analysis of SRT reports submitted:
PSS study committee analyzed the PSS Tuning/SRT reports/graphs submitted and the
recommendations had been finalized (Analysis & recommendations are available at Annexure-III). The
SRT of following unit(s) were analyzed:
3rd PSS Meeting held on 28.06.2016
APGENCO
NTTPS (VTPS) Units – 1,2,3,4,&7 Krishnapatnam(SDSPP) U
– 1 & 2
Rayalasema TPP Units 1-
5
TSGENCO Kakatiya TPS Unit 1 Kothagudem TPS UNIT-9,
10 & 11
Nagarjunasagar PH Units
2-8
KPCL Bellary TPS Units 1 &2
TANGEDCO
Tuticorin TPS Units 1-5 NCTPS Stage- I Units 1 -3 Mettur TPS Stage I Units
1-4 NTPC
Talcher Stage II Units 3 & 6
Simhadri TPS Units 1-4
NTECL Vallur TPS Unit-2
NPCIL Kaiga GS Units 3 & 4 KKNPP Unit-1
IPPS/MPPS IL&FS Unit-1
UPCL Units 1 &2
TPCIL Units 1 &2
Vote of Thanks
Member Secretary, SRPC thanked the participants for their active deliberations. He again
suggested that all generators complete the PSS tuning/Step Response Test for the units as per
schedule finalized.
*****************************
Response of Unit # 1
Step input on # 1, PSS-1 & PSS-2 OFF
Active Power
Reactive Power Output
Field Current
PSS contribution
Terminal Voltage
3rd PSS Meeting held on 28.06.2016
Annexure- III
PSS STEP RESPONSE TEST ANALYSIS & RECOMMENDATIONS
Brief Background
PSS is a device that enhances the damping of low frequency oscillations at the synchronous
machine by controlling excitation. As a benefit of the action of several PSSs at several synchronous
machines, the stability of the whole power system increases.
The low frequency oscillations that can be damped by the PSS are divided into following modes
Local Mode – 1.0 to 2.0 Hz ( One generator swings against rest of the system)
Inter Area Mode – Around 0.3 Hz. ( Two Area’s swinging against each other)
Torsional Mode – 10 – 40 Hz. ( Generator Geometry )
Damping Torque
3rd PSS Meeting held on 28.06.2016
SR PSS MEETING- MINUTES
o The 2nd Meeting on PSS related issues was held at SRPC, Bengaluru on 30th October
2015.
o It was decided that all generating units to set PSS in such a way that it should
come into service when the unit loading is above 50 % of installed capacity
o It was agreed that step in the range of 2- 5 % could be taken at full load and at 50 % (or
at a value as suggested by OEM) load for Step Up and Step Down with PSS On & Off for
Step Response Test of each unit. PSS for the other units (of the station/stage)
would be kept Off during the test
o All generating units with a capacity over 50 MW, for which PSS have not been tuned or
Step Response Test has not been carried out during last 24 months (after August 2013),
should do so by August 2016 and submit result of Step Response Test to SRLDC/
SRPC/ CTU
SRT of 210 MW machine - PSS OFF
3rd PSS Meeting held on 28.06.2016
SRT of 210 MW machine - PSS ON
PSS Tuning/SRT analysis and recommendations:
APGENCO
NTTPS (VTPS) UNITS – 1,2,3,4,&7
For Unit 1
Step response was done with ± 3% step change in Vref.
Without PSS in-service and step change in Vref the oscillations took 4.5 second to die
down.
With PSS in-service and final Gain settings of K1 = 7.5pu & K2 = 0.5pu, the oscillation were
dying down in 1.5 secs.
For Unit – 2
Step response was done with ± 3% step change in Vref.
Without PSS, the oscillation Pout were taking almost around 4sec to settle down.
With PSS in-service, the oscillations were settling down in almost 1.5 sec.
For Unit 3
Step response test of ± 3 % were conducted.
It was observed that there were oscillations observed in Real Power. The scale is not clear.
VTPS to to discuss the results with the SRT agency /OEM. Accordingly, PSS Tuning may
be taken up again.
3rd PSS Meeting held on 28.06.2016
For Unit 4
Step response of ±3 % was conducted.
Small oscillations were observed in Pout of the Machine with and without PSS.
The same was being reflected in the PSS Output which was trying to damp down the
oscillation.
Was this a measurement error? or were there such oscillations at NTPPS Unit 4 terminal
needs to be verified.
The PSS may not be tuned properly, the Gains and Phase needs to be tuned as this is
evident as PSS is unable to damp the oscillations. VTPS to discuss the results with the
SRT agency /OEM.
For Unit 7
Step response test was conducted with different Gains with PSS in-service and without
PSS.
From the plots it was seen that the PSS was causing more sustained oscillations as evident
from the Pout and Vfield plots.
The PSS may not be tuned properly, the Gains and Phase needs to be tuned as this is
evident as PSS is unable to damp the oscillations. VTPS to discuss the results with the
SRT agency /OEM.
KRISHNAPATNAM U – 1 & 2
Unit – 1
Step response of +3 % was done at 80 % Loading of the machine.
The Oscillations in Pout were well damped with PSS in-service. Damping torque
computations were showing improvement with PSS On.
Step up response was done for Unit -1 without PSS, step down is done with PSS On.
The PSS was well tuned.
Unit – 2
Step response of ±3 % was conducted at 80 % loading.
The Oscillations in Pout took almost 3.5 sec to settle down without PSS. Damping torque
computations were showing improvement with PSS On.
With PSS the oscillation settled down in 1.5 secs.
The PSS was well tuned.
RAYALASEMA TPP
Unit – 1 & 2
The PSS was not damping out the oscillations and Damping Torque was the same with and
without PSS.
In respect of Unit-2, it was noted that PSS contributions and Pout were in the same phase
and were to be ascertained. It was noted that there could be chances of reverse polarity.
APGENCO clarified that PSS contribution was in opposite phase though graphically it was
3rd PSS Meeting held on 28.06.2016
showing in the same phase (after ascertaining from M/s BHEL telephonically). APGENCO
to revert back after ascertaining the facts.
PSS needs to be tuned properly to increase the damping torque to damp out the
oscillations more quickly. RYTPP to discuss the results with the SRT agency /OEM and
SRT may be carried out again.
Unit – 3 , 4 & 5
It was observed that with the step response change in Vref , there was no change in
Electrical Output of the Machine
The reactive power of the machine may also be plotted to see whether the Machine is
responding to such Vref changes.
The PSS had no significant effect during the step response test.
RYTPP to discuss the results with the SRT agency /OEM and SRT may be carried out
again.
TSGENCO
KAKATIYA TPS
Unit – 1
A step of ±4 % in Vref was conducted
The Power Oscillations were well damped with and without PSS.
During step down in Vref there was no change in Field current , the excitation system
parameters needed to checked, had the under excitation limiter hit?
KOTHAGUDEM TPS UNIT-9, 10 & 11
Unit – 9
SRT of ±4.5 % was done with & without PSS
As observed from the SRT , there was not much significant reduction in damping, for with
and without PSS
KTPS to discuss the results with the SRT agency /OEM and SRT may be carried out again.
Unit – 10
SRT of ±5 % was done with & without PSS
The oscillations in Electrical Power Output were less without PSS
The oscillations were minimal with PSS Gain Settings of K1 = 3sec & K2 = 0
PSS Tuning needed to be carried out again as it was inducing oscillation
KTPS to discuss the results with the SRT agency /OEM and SRT may be carried out again.
Unit – 11
SRT of ±4 % was done with & without PSS
The test was done at full Load
The Machine Real Power was sufficiently well-Damped in both the scenarios.
NAGARJUNASAGAR PH
3rd PSS Meeting held on 28.06.2016
Unit – 2, 3, 5 , 6, 7 & 8
Step Up in Vref test was conducted.
The Power Oscillations were damped better with PSS in-service.
Step Down in Vref also needed to be conducted.
The Damping Torque to be calculated.
PSS response for Units 2, 3, 5 & 8 was good. One PSS response was most likely for U7
(though not mentioned in the report) was also good.
Unit – 4
PSS in-service with step up in Vref is plotted and PSS Out-off service with step down in Vref
is provided.
For Step Up in Vref both PSS in-service and Out of-service to be plotted.
For Step Down in Vref both PSS in-service and Out of-service to be plotted.
The Damping Torque to be calculated.
NSR/TSGENCO to discuss the results with the SRT agency /OEM and SRT may be carried
out again.
KPCL
Bellary TPS
Unit – 1 & 2
The plots/graphs were not clear
Time scale may be clearly mentioned.
It was noted that the test reports were not clear. Bellary TPS to discuss the results with
the SRT agency /OEM and SRT may be carried out again.
TANGEDCO
TUTICORIN TPS
Unit – 1
Date of Test : 29-11-2008
No Graphs Attached.
Unit – 2
Date of Test : 21-06-2012
SRT ±3 % & ±5 % was done.
Only with PSS in-service graphs were attached.
Unit – 3
Date of Test : 09-01-2013
4% PSS ON 180MW LOAD
3% PSS ON 120MW LOAD.
Unit – 4
2 % SRT was done
Unit – 5
2 % SRT was done
3rd PSS Meeting held on 28.06.2016
As Tuticorin TPS had not furnished the graphs of PSS Off, the effect of PSS was not able to be
assessed. TTPS to discuss the results with the SRT agency /OEM and furnish the clarification. If
required, SRT to be taken up again.
NCTPS Stage- I:
Unit– 1
SRT of ±3 % was done at 70 % & 40 % loading, but with and without PSS is not being
mentioned.
Since the test was carried out in July 2013, SRT to be carried out again.
Unit -2
The SRT was carried out, but the % step was not mentioned.
The damping seems slightly better with PSS out of service.
Small oscillations were observed in the Electrical Output of the Machine always.
NCTPS Stage I to discuss the results with the SRT agency /OEM and furnish the
clarification. If required, SRT to be taken up again.
Unit -3
The SRT was out, but the % step is not mentioned.
Small oscillations were observed in the Electrical Output of the Machine always
No change in Electrical Output Damping, with and without PSS
NCTPS Stage I to discuss the results with the SRT agency /OEM and furnish the
clarification. If required, SRT to be taken up again.
Mettur TPS Stage I
Unit - 1
The % Step Change in Vref was not mentioned.
SRT with PSS & without PSS was done
Oscillation in Electrical Output were well damped with PSS in-service.
Unit – 2
Step Up and Step down Tests were done, but with and without PSS was not done.
MTPS to discuss the results with the SRT agency /OEM and SRT may be carried out
again.
Unit – 3
The Electrical Output was not being visualized.
The SRT with proper scales may be re-submitted.
MTPS to discuss the results with the SRT agency /OEM and SRT may be carried out
again.
Unit – 4
The % step change in Vref was not mentioned
There were sustained oscillations observed in Electrical Output of the Machine.
3rd PSS Meeting held on 28.06.2016
MTPS to discuss the results with the SRT agency /OEM and SRT may be carried out
again.
NTPC
Talcher Stage II
Unit – 3
Step Response of ±3% was done.
There was no much change in Electrical Output Oscillations of the Machine for PSS – OFF
& PSS – In-service. Noted as brushless exciter.
It was observed that the PSS Output in complete Phase opposition to the Electrical Output
of the Machine.
Unit – 6
Step Response of ±3% is done.
It is observed that the PSS Output in complete Phase opposition to the Electrical Output of
the Machine.
Simhadri TPS
Unit – 1, 2, 3 & 4
Step Response of ±2% was done
There was no change in Electrical Output of the Machine when there was change in Vref.
Hence, a higher step change may be done to compare the Damping for both PSS IN & Out
Plots may be given with Proper Scale.
Simhadri TPS to discuss the results with the SRT agency /OEM and SRT may be carried
out again.
NTECL
VALLUR TPS
Unit – 2
No Load SRT of ±5 % & ±10 % was conducted.
Field Current , Vref , Vactual were plotted
Machine Real & Reactive power to be plotted.
The Damping Torque to be calculated.
It was noted that the test report submitted was for PID for AVR (at no load). NTECL to
discuss the results with the SRT agency /OEM and SRT may be carried out again.
NPCIL
KAIGA GS
Unit – 3 & 4
The test report is dated 19th April 2007
The graphs corresponds to which unit was not mentioned.
In one unit, Electrical Output was well damped without PSS, but has large settling time,
whereas with PSS there were oscillations observed.
Are these correct legends?? The PSS SRT needs to be done every 3 years.
For other Unit, after the SRT, the oscillations were well damped with PSS.
Time reduced from 2.5 secs to around 1.5 secs.
3rd PSS Meeting held on 28.06.2016
The Magnitude of the oscillation is also reduced.
Since the tests were conducted in 2007, KGS to take up the SRT/PSS tuning again.
KKNPP Unit-1
Step Response of 1% step was carried out with PSS On and Off
Step Response of 3% step was also carried out but with PSS On only, PSS Off was not
done
PSS output graphs were not plotted.
KKNPP may kindly provide the graphs/plots consisting the parameters Field current,
Filed Voltage, P, Q and PSS output.
IPPS/MPPs
IL&FS
Unit – 1
SRT of ±3 % AT 50% loading and 90% loading was conducted.
The Oscillations in Pout were well damped with PSS in-service.
SRT of Higher % change also to be done.
The Damping Torque to be calculated.
IL&FS has submitted the photographs of the SRT. IL&FS was suggested to furnish the
test report (preferably the soft copy of the downloadable version).
Udupi Power Corporation Limited
Unit – 1
SRT ±3 % & ±4 % was done with PSS and without PSS
It was observed that Machine Real Power output was sufficiently damped.
PSS Activation test was done
PSS was taken into service , and no change observed in Pout of the Machine
Also the Channel Changeover test was also conducted at full load.
Unit – 2
SRT ±2 % , ±3 % & ±4 % was done with PSS and without PSS
It was observed that Machine Real Power output was sufficiently damped for all the SRT.
The damping torque to be calculated.
The above test were done at 290 MW loading, the same may be carried out full Load
during the next SRT.
TPCIL
Unit – 1 & 2
No Load SRT ±5 % was done with PSS and without PSS
The Legend of the signals plotted was not clear. ( Field Current, Vref )
With and without PSS, the SRT were not conducted.
It was noted that the test report submitted was for PID for AVR at no load. TPCIL to
discuss the results with the SRT agency /OEM and SRT may be carried out again.