PUBLIC PARTICIPATION REPORT
PPP SUMMARY
PUBLIC PARTICIPATION SUMMARY
This serves as a summary of the Public Participation Process (PPP) followed for the Proposed eGoli
Water Supply Project, Ugu District Municipality, KwaZulu-Natal.
The PPP commenced in September 2012 where site notices were erected along the route in eGoli
Area. During this time comment forms & BID flyers were distributed to the councillor and at tribal
council as well as to other interested and affected parties (I&APs). An advert was placed in the
Isolezwe newspaper on the 17th October 2012 followed by a comment period which was open for the
I&APs to raise their issues and concerns regarding the proposed activity. A draft Basic Assessment
Report and Environmental Management Programme was compiled, and was distributed to the
relevant authorities and to the public for review, for a 40 day comment period in which I&AP’s were
afforded the opportunity to raise any further issues and concerns, until the finalisation of the document
for submission to the KwaZulu-Natal Department of Agriculture and Environmental Affairs (KZN
DAEA).
PUBLIC PARTICIPATION AS PART OF THE SCOPING PP PROCESS
Public Notices/Site Notices
Public notices and site notes were displayed at the entrance of the site and at areas frequently
used by the public: Refer to copy of:
Site notice, providing the displayed detail in Appendix E - Site Notice;
Photographs as proof of site notices displayed.
Written Notices and Background Information Document (BID)
A background information document and notification letter with an invitation register to I&APs, to
submit comments as per attached comment sheet was distributed as follows:
Posted to I&AP database (which included neighbouring properties);
Placed at locations frequently used by the public.
Refer to Background Information Document provided in the PPP section (Appendix E) for the
detail regarding individuals contacted as per above-mentioned list as well as content of BID and
comment form.
Advertisements
Advertisements regarding inter alia the proposed project scope of works, location, details of public
meeting and details of locations and date for draft Basic Assessment Report review as well as
details of EAP were placed in the Isolezwe Newspaper (16.10.2012).
Refer to proof of placement of advert in the PPP section (Appendix E) – Adverts.
Public Meeting
No public meeting was held but stakeholders were engaged with.
I&AP Communication
Refer to Issues trail within PPP section (Appendix E) for further detail.
I&APs Comments
As a result of the advertisement, BID’s and public meeting, correspondence was received from
I&APs.
Refer to attached comments: Appendix E – I&AP Correspondence, public meeting minutes and
issues trail for comments and responses.
Draft Basic Assessment Report Review
The draft Basic Assessment Report has been made available for review for a period of 40 days
and hard copies were placed at the following venues, as advertised:
Ugu District Municipality Offices;
Tribal Council; and
RHDHV Website: www.rhdhv.com
Comments will be received and compiled into an Issues Trail.
Issues Trail
An Issues Trial, summarizing the objections and comments from the PPP has been provided in
the PPP section (Appendix E) – Issues Trial.
Ongoing I&AP / Stakeholder communication
The project Team has ongoing communication with I&AP’s to ensure the continued involvement of
all stakeholders and I&AP throughout the EIA process and beyond.
PUBLIC PARTICIPATION REPORT
SITE NOTICE
PUBLIC PARTICIPATION REPORT
PROOF OF SITE NOTICE
PUBLIC PARTICIPATION REPORT
ADVERTISMENT
PUBLIC PARTICIPATION REPORT
PROOF OF ADVERTISMENT
PUBLIC PARTICIPATION REPORT
BID & COMMENT FORM
PUBLIC PARTICIPATION REPORT
I&AP DATABASE
First Name
Last Name Company/Organisation Postal Address Telephone Fax Cell No. E-mail
Kushela Naidoo RHDHV [email protected]
Manisha Maharaj DWA [email protected]
Thembile Dlungwana DAFF [email protected]
Dominic Wieners KZN Wildlife [email protected]
Weziwe Tshabalala Amafa [email protected]
Sello Mokhaya Amafa [email protected]
Carolyn Schwegmann WESSA [email protected]
Nonhlanhla Mnyeni Department of Agriculture
Melissa Packree Ugu DM [email protected]
Cllr TE Sibisi Ward Councillor [email protected]
Inkosi Hlengwa Chief
729 373 028
PUBLIC PARTICIPATION REPORT
ISSUES TRAIL
Royal HaskoningDHV October, 2012
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
ISSUES TRAIL
eGoli Water Supply Project
Ugu District Municipality
SUMMARY OF ISSUES/CONCERNS AND SUGGESTIONS RAISED BY INTERESTED AND/OR AFFECTED PARTIES
October 2012
This Issues Trail provides a summary of concerns raised by Interested and/or Affected Parties
(I&APs). A full record of the public participation process and stakeholder / I&AP correspondence is
available at Royal HaskoningDHV offices. The issues have been arranged into groups of similar
issues, and are listed within each group in the date order in which they were received. The name,
affiliation and date of the commentator are also indicated.
The Proposed eGoli Water Supply Project, Ugu District Municipality
Royal HaskoningDHV October, 2012
NO COMMENTS HAVE BEEN RECEIVED TO DATE
Issue / Comment Raised By Response