Public Private Partnerships

Dr Kevin Doherty Director, Public Private Partnerships

Page 2: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP Definition in New Zealand

• “A long term contract for the delivery of a service, where the provision of the service requires the construction of a new asset, or the enhancement of an existing asset, that is privately financed on a non-recourse basis, and for which full legal ownership is retained by the Crown”

Page 3: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPPs in New Zealand to Date

Wiri Prison

• 25 year contract

• Cost: $110-120 million

• Open 2014

• 25 year contract

• Cost: $840 million

• Opening 2015

Hobsonville Schools

Page 4: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP Patronage Risk Transfer Models

• Private partner revenue based on patronage

• E.g. Toll road

Page 5: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP Availability Based Model (Response to previous PPP failures)

Page 6: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Outcome Based Performance Regime

Performance Regime used to complement the Availability Model

• Incentivises the desired OUTCOMES by putting equity and debt at risk if they are not achieved

Travel Time

Page 7: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

The Public Private Partnerships Value Proposition

Page 8: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP – Part of the Procurement Portfolio Where it delivers best value…

Conventional

Design &

construct

Alliancing

DCM (+ 0)

DBFM

(PPP)

BOOT

Integrator

or

strategic

partner /

JV model

Vector

Arena

Wiri Prison

Pa

rtne

rin

g

Tra

ditio

nal

HIG

HE

R

LO

WE

R

HIG

HE

R

LO

WE

R

Private sector risk

Project

complexity

Scale

Vic Park Tunnel

SH20-1

Transmission Gully

Waterview

Connectio

n

HIGHER LOWER

Page 9: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Why the Transport Agency has included PPP within its procurement model portfolio

Procure with PPP where it provides

Better Value to do so:

• The achievement of the same or better

OUTCOMES at the same or lower cost than can be achieved by the Public Sector using any other procurement model.

Page 10: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP – Don’t judge too soon……..

Page 11: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Why does PPP provide Value for Money on some projects?

To provide a “better than government procurement” value proposition the private sector must:

• achieve construction, operating and risk management cost savings to offset their additional costs; and

• provide outcomes that meet the same level (or better) than government procurement would have achieved.

Page 12: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Public Sector Comparator (PSC)

• A Public Sector Comparator is calculated as a benchmark to compare private sector offers

• The PSC is an estimate of the hypothetical risk adjusted cost if the project were to be designed, built, “financed”, maintained and operated by the government

Page 13: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Using the Proxy Bid Model to test if PPP can deliver best value

$750 $750

$660

$50 $50

$35

$150 $150

$120

$50 $30

$25

$170

$160

$0

$200

$400

$600

$800

$1,000

$1,200

Public Sector Comparitor Proxy Bid Model Potential Value Bid

Net

Pre

sent

Cos

t ($M

illio

ns)

Financing

SPV management and bid costs

Competitive neutrality

Transferred Risk

Operating

Construction

Total = $1b

Total = $ 1.15b

Total = <$1b

12% saving in construction cost

20% better risk management

30% saving in O&M

Page 14: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Payment profile: PPP vs Conventional Procurement

(250)

(200)

(150)

(100)

(50)

-

50

100

An

nu

al N

et P

rese

nt

Co

sts

$mil

lio

ns

Operations & maintenance phase Construction phase

Conventional procurement: Total NPC = $1 billion

PPP procurement: Total NPC = $1 billion

The net present cost of the cash flows are the same but the timing and profile of the cash flows are different

Page 15: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Nominal versus NPC

• Some commentators point out that the nominal cost of a PPP can be 3 times higher than the construction cost alone.

• Not comparable as doesn’t include :

• O&M costs; or

• Time value of money (different cash flow timing)

Page 16: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Traditional Procurement

Page 17: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

PPP Procurement

Page 18: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Transmission Gully NZs First Roading Public Private Partnership

Page 19: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Consented Design Outcomes

• Improved safety - 40% mid-block crash reduction

• Reduction in travel time

– 10 mins from Kapiti to/from Wgtn

– 15 mins Kapiti to Hutt Valley

– 5-7 mins Porirua to Hutt Valley

• Reduced average travel time variability from 5-10 mins to less than 1 minute

• Improved seismic and storm resilience

Transmission Gully Project

Page 20: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New
Page 21: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Detailed Business Case

• Likely that private sector will through innovation and better risk management offset higher cost of capital and SPV costs

• PPP likely to provide best value procurement

Page 22: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Programme to Complete

• Issue EOI – February 2013

• Shortlist and Issue RFP – May 2013

• Preferred Identified – November 2013

• Financial Close – July 2014

• Start Digging – late 2014

• Road open – approx. 2020

• Concession end – approx. 2045

Page 23: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

What to invest in - OUTCOMES

• Safer journeys

• Reduced travel time;

• Improved travel time reliability;

• Satisfied Customers; and

• Resilience

Page 24: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Commercial incentives for OUTCOME performance

Travel Time

Safety

Direct KPI Deductions •Minimum travel time

•Non-serious injury crashes •Customer surveys

Customer Satisfaction

Charges

Safety: • Fatalities

• Serious injuries

Indirect KPI Deductions Asset condition, reporting

Project Outcomes

Unavailability

Page 25: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Payment Regime Callibration

108,000

108,200

108,400

108,600

108,800

109,000

109,200

109,400

109,600

109,800

110,000

Best Good Average Avg-poor Poor

$000

s

UP Pavement / other Unavailability / travel time Safety (incl f low on) Operator margin ($200-300k)

Performance Scenario

Page 26: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Public Private Partnerships New Zealand Pipeline

Page 27: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Puhoi to Warkworth (Potential RFP 2015)

Preferred route identified

Currently concluding land acquisition and designation

Board of Inquiry expected to conclude in August 2014

Approx. $1b

Expected RFP 2015

Page 28: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Ara Tuhona Puhoi to Warkworth Indicative Terrain

Page 29: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New
Page 30: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

City Rail Link

Key facts •3.4km twin 7m diameter tunnels

•Linking Britomart to the existing rail line near Eden Terrace

•Three new stations – Aotea, Karangahape Rd, Newton (these may

be staged)

•Cost $2.2b to $2.8b

•Potential Start 2016 – 2020

Page 31: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Proposed city rail link route and station locations

Albert Street

Page 32: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Waitemata Harbour

Page 33: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Additional WHX Timing Requirement

Page 34: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Additional Waitemata Harbour Crossing

Key facts

•Twin Tunnels future-proofed for rail below

•Cost > $3b

•Potential start 2020 - 2025

Page 35: Public Private Partnerships - Constructing Excellence Doherty, NZTA... · Public Private Partnerships Dr Kevin Doherty Director, Public Private Partnerships . PPP Definition in New

Questions