puntledge river capital projects and hydroelectric...
TRANSCRIPT
Puntledge River Capital Projects And
Hydroelectric Operations
Comox Valley Regional District:
Board Of Directors
May 30, 2017
Stephen Watson
The Puntledge River Hydroelectric System
Overview of five capital projects:
• Comox Puntledge Flow Control Improvement Project;
• Puntledge River Water Level Gauge System and Public Safety Warning System
Project;
• Puntledge Old Penstock and 25 Cycle Building Retirement Project;
• Puntledge Penstock Re-Coating Project; and
• Buckley Bay Substation Project.
Discussion on the 2016/2017 water supply forecast.
Comox Puntledge Flow Control Improvement Project
• There are existing facility challenges in controlling water flows in the upper
Puntledge River hydroelectric system – the specific concern is unplanned
flow events that can release water flows below the diversion dam that can
pose a significant public safety risk.
• Barber’s Hole area is the highest public safety risk on the river system for
water flow changes.
• Unplanned flow events happen about once every year or two. Drivers
• This project is seeking to improve on the ability to manage water flows in a
more controlled and safe manner: to reduce the risk of unplanned flow
events.
3
Comox Puntledge Flow Control Improvement Project
4
Comox Puntledge Flow Control Improvement Project
Conceptual Design Stage (Complete in 2016)
We completed a system overview:
• Narrowed scope from 11 to eight concept groups for further consideration
(removing long term dam upgrades, penstock strengthening or replacement,
system reconfiguration/modification).
• We then further narrowed down the concept groups down to five for further
consideration.
• The leading alternative at the end of conceptual design included five
concept groups that were recommended for advancement to Feasibility
Design
5
6
Comox Puntledge Flow Control Improvement
Project – Leading Alternative
Upgrade Generation Conveyance
Control System
Provide Water Storage Buffer
(Height) at Puntledge Diversion Dam
Upgrade Comox Dam Right
Abutment
Improve Comox Dam Spillway Gate
Reliability
Improve Support for
Operational Decisions
Puntledge Diversion Dam
Comox Dam With Two
Spillway Gates
Puntledge Powerhouse
Puntledge Water Intake
To Powerhouse
Comox Puntledge Flow Control Improvement Project
Right Abutment Geotechnical Investigation – Drilling In May/June 2017
7
Comox Puntledge Flow Control Improvement Project
Next Steps - Schedule
• Start preliminary design in 2018;
• Seek construction funding at the end of 2019; and
• Project could be in-service by early 2022.
• Cost TBD. In terms of cost magnitude, potentially in the lower tens of
millions of dollars.
8
9
Puntledge River Water Level Gauge System and
Public Safety Warning System Project
• This project will improve public safety and provide more reliable watershed flow information with which to make operational decisions, including during flood risk management situations.
• Siren warning system; and
• Water gauges
• The total project cost is about $8 million. The system improvements are happening and hope to be in operation this summer.
• Watershed flows and levels on web site: https://www.bchydro.com/energy-in-bc/our_system/transmission_reservoir_data/hydrometric_data/vancouver_island.html
10
Puntledge River Water Level Gauge System and
Public Safety Warning System Project
11
Puntledge River Water Level Gauge System and
Public Safety Warning System Project
There are seven main improvements or differences:
• Siren sound change to a whooping sound;
• Moved to be better heard in the river where the risk resides and at the same time lessen the nuisance they may create to nearby residents. They will be more directional and effective;
• The higher river flow thresholds for siren blocking. Flood risk management operations –the river is already high and the public would not be in the river;
• Seasonal siren activation has been modified. Operate during daylight hours. From December 1 to April 30 the sirens will be operating from 8 am to 6 pm, then March 1 to May 14 from 7 am to 10 pm, then May 15 to September 30 from 6 am to 11 pm, and finally October 1 to November 30 from 7 am to 8 pm;
• We have added strobe lights, angled down or up the river corridor, to initiate during the daytime together with the sirens, and during the night when the sirens are not engaged;
• Public warning signage along the river will be updated; and
• The public warning system has been made more sensitive to flow changes near Puntledge Park for improved public safety.
The new system is intended for follow the Canadian Dam Association guidelines.
Puntledge Old Penstock and 25 Cycle Building
Retirement Project
Public safety driven project
• The BC Power Commission undertook significant upgrades to the system in the
1950s. When those upgrades took place some of the older facility works were
abandoned.
• The original powerhouse building, sometimes referred to as the 25 Cycle
Building, and some elements of the old penstock corridor such as the concrete
anchor blocks, remain today. Those works will be removed.
• We have begun to remove these old and abandoned works this summer. Work
is being carried out through an FMI/K’omoks First Nation joint venture.
• Letter sent to the Regional District on March 30. Also been communicating with
the CVRD’s Water Services staff.
• Large sections of the penstock corridor will be closed off for public safety given
the deconstruction work involves the use of heavy equipment. Warning signage
will be placed around the site.
• About a $7 million project cost.
12
Puntledge Old Penstock and 25 Cycle Building
Retirement Project – Work Zones
13
Puntledge 25 Cycle Building
14
Puntledge Old Penstock and 25 Cycle Building
Retirement Project
15
Puntledge Old Penstock and 25 Cycle Building
Retirement Project
16
Puntledge Old Penstock and 25 Cycle Building
Retirement Project
17
Puntledge Penstock Re-Coating Project
• Work includes recoating the interior and exterior of the steel penstock.
• Request for proposals for painting to be issued in one-two months.
• Exterior work on penstock planned for completion between July 2018 and
end of 2020.
• Work on inside of the penstock (interior recoating and addition of new
access openings) has been deferred to 2021 given the CVRD’s water
project – CVRD will be off the BC Hydro penstock by then.
18
Buckley Bay Substation Project – Completed
19
20
2016/2017 Water Supply Year – To Date
Record Rain And Water Inflows – Oct/Nov
2016. Comox Lake Water Inflows Vs
Discharges
21
Snowmelt: End Of May Cruikshank River
Flow Rates Into Comox Lake
22
23
2017 Water Supply Year – To Date