pv3 metallurgical testing of future ores from€¦ · pv2 metallurgical program. testing was...

15
BL0005 20 January 2015 PV3 Metallurgical Testing of Future Ores from --------------

Upload: others

Post on 18-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

BL0005 20 January 2015

PV3 Metallurgical Testing of Future Ores from --------------

Page 2: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

PV3 METALLURGICAL TESTING OF FUTURE ORES FROM

PINTO VALLEY

BL0005

Contents 1.0 INTRODUCTION ................................................................................................... 1

2.0 COMPOSITE CONSTRUCTION ............................................................................... 1

3.0 CHEMICAL CONTENT ........................................................................................... 3

4.0 COMMINUTION TESTING ...................................................................................... 4

5.0 SPECIFIC GRAVITY ............................................................................................. 5

6.0 FLOTATION TESTING ........................................................................................... 7

6.1 ROUGHER FLOTATION TESTING .............................................................................. 7

6.2 CLEANER FLOTATION TESTING .............................................................................. 10

6.3 LOCKED CYCLE FLOTATION TESTS .......................................................................... 12

7.0 CONCLUSIONS AND RECOMMENDATIONS.............................................................. 15

Appendices: APPENDIX A ............................................................................................ CHAIN OF CUSTODY

APPENDIX B ...................................................................................... METALLURGICAL TESTING

APPENDIX C ............................................................................................................ ASSAYS

APPENDIX D ....................................................................................... COMMINUTION TESTING

APPENDIX E ............................................................................................................. SIZINGS

APPENDIX F ........................................................................ MINERALOGY - PHOTOMICROGRAPHS

HELEN JOHNSTON ................................................................... BRADLEY ANGOVE

P. ENG., MAUSIMM(CP) .................................................. P. ENG., MAUSIMM(CP)

Page 3: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

1

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

1.0 Introduction

The objective of this Pinto Valley program was to determine the expected metallurgical

performance of potential future ores from the Pinto Valley deposit in comparison to the

mineralization currently processed by the concentrator. Michael Oxciano, Project Engineer for

Capstone Mining, and Ken Major, Consultant to Capstone Mining, together provided the scope

of work and direction for the testing.

About 300 kilograms of drill core and Run-Of-Mine (ROM) ore was received at Base

Metallurgical Laboratories in late November 2014 for testing. Testing included specific gravity

determinations, comminution testing, head assays, batch rougher and cleaner flotation testing

and locked cycle testing. Flotation testing was conducted using a flowsheet developed in the

PV2 metallurgical program. Testing was concluded early January, after which this report was

prepared.

This report summarizes key results from the test program, using data summaries and graphical

displays. Detailed results, such as condition sheets and full sizing distributions, can be found in

the Appendices as follows:

- Appendix A: Chain of Custody

- Appendix B: Metallurgical Testing

- Appendix C: Assays

- Appendix D: Comminution Testing

- Appendix E: Sizings

- Appendix F: Mineralogy - Photomicrographs

2.0 Composite Construction

Appendix A describes the process of sample preparation, whereby 7 composites were

constructed for metallurgical testing according to client instructions. Prior to crushing of the

samples, apparent density was determined using two methods. Specific gravity of the 7

composites was also determined after preparation using a third method.

Table 1 shows the drill core lengths that were combined to construct the composites. Three

composites were constructed for the Eastern Pushback, two for the Northern Pushback, an

Aplite Composite and a ROM Composite. The Run of Mine (ROM) composite was understood

to represent current ore feeding the Pinto Valley concentrator.

Page 4: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

2

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

TABLE 1: COMPOSITES

ZONE / Composite Drill Hole ID From - ft To - ft Sample Form Mass - kg

Run of Mine (ROM Composite) Bucket 1 Bulk Rock 25.6

Bucket 2 Bulk Rock 26.8

Eastern Pushback Low-level Length

DDH-12-91 580 590 1/2 HQ Core 11.8 DDH-12-62 310 320 1/2 HQ Core 11.8 DDH-12-175 1330 1340 1/2 HQ Core 12.2 DDH-12-176 1210 1220 1/2 HQ Core 9.4

Eastern Pushback Mid-level

Length

DDH-12-161 630 640 1/2 HQ Core 10.4 DDH-12-156 510 520 1/2 HQ Core 10.4

GTH-12-3 950 960 1/2 HQ Core 9.4 DDH-12-156 25 35 1/2 HQ Core 11.6

Eastern Pushback Upper-level

Length

DDH-11-33 420 430 1/2 HQ Core 11.9 DDH-11-33 390 400 1/2 HQ Core 13.1 DDH-12-156 240 250 1/2 HQ Core 12.3 DDH-12-154 80 90 1/2 HQ Core 11.3

Northern Pushback Low-level

Length

DDH-11-20 440 450 1/2 HQ Core 10.5 GTH-12-8 500 510 1/2 HQ Core 8.4

DDH-12-55 410 420 1/2 HQ Core 11.2 DDH-12-90 640 650 1/2 HQ Core 12.3

Northern Pushback Mid-level

Length

DDH-12-79 50 60 1/2 HQ Core 6.1 DDH-11-15 820 830 1/2 HQ Core 5.2 DDH-11-14 1280 1290 1/2 HQ Core 9.1 DDH-11-15 860 870 1/4 HQ Core 10.1 DDH-12-177 1150 1160 1/2 HQ Core 10.4

Aplite Composite

DDH-13-195 579 584 1/2 HQ Core 5.2 DDH-13-194 382 394 1/2 HQ Core 13.7 DDH-13-194 465 479 1/2 HQ Core 14.8 DDH-13-194 577 583 1/2 HQ Core 7.3

Detailed sample preparation details are located in Appendix A, along with photos and the memorandum from AJAX Limited

regarding sample collection.

Page 5: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

3

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

3.0 Chemical Content

Duplicate, representative head cuts were removed from each composite and assayed via a

multi-element ICP scan. Full results are provided in Appendix C. A summary of average results

for key elements are shown in Table 2.

TABLE 2: HEAD ASSAYS

Composite Assay - percent or g/tonne

Cu Mo Fe S

ROM Composite 0.38 42 1.17 0.66

Eastern Pushback Low-level Length 0.29 66 1.46 0.59

Eastern Pushback Mid-level Length 0.30 57 1.24 0.95

Eastern Pushback Upper-level Length 0.32 39 6.13 2.71

Northern Pushback Low-level Length 0.29 54 1.13 0.51

Northern Pushback Mid-level Length 0.26 83 1.56 1.23

Aplite Composite 0.22 154 0.51 0.35

Mo is in g/tonne, all other assays are in percent.

All the future mineralization samples were lower in copper than the ROM composite.

Molybdenum, however, was similar, or in the case of the Aplite Composite, substantially higher

than the ROM composite.

Sulphur contents were higher than that of copper suggesting the presence of pyrite in the

samples. The variable content of sulphur suggests variation in the content of pyrite with the

Eastern Pushback Upper-level Length containing the most, measuring a relatively high ratio of

sulphur to copper at over 8 to 1. At this ratio, aggressive flotation conditions that reject pyrite

will be necessary for production of high grade copper concentrates. Mineralogical assessment

would be required to confirm the presence of pyrite.

Page 6: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

4

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

4.0 Comminution Testing

A sub-sample of each composite was removed after crushing each composite to 12.7mm (1/2

inch) for Bond Rod and Bond Ball Mill Work Index Tests. The tests were conducted by ALS

Metallurgy Kamloops. Their full report is provided in Appendix D. A summary of the results is

provided in Table 4.

TABLE 4: BOND ROD AND BALL MILL TEST RESULTS

Sample ID Rod Ball

kWh/tonne kWh/tonne

ROM Composite 12.5 13.6

Eastern Pushback Low-level Length 13.0 14.1

Eastern Pushback Mid-level Length 11.1 13.2

Eastern Pushback Upper-level Length 14.8 17.1

Northern Pushback Low-level Length 13.1 14.5

Northern Pushback Mid-level Length 12.2 13.2

Aplite Composite 12.5 13.1

The Bond Ball Mill Work Index Test was conducted using a closing screen sizing of 300µm,

resulting in a product sizing averaging 241µm K80. At this closing screen sizing, the 7

composites recorded work indices averaging 14.1 kWh/tonne. The Bond Rod Mill Work Index

averaged 12.7 kWh/tonne.

The Bond Ball Mill Work Index results were similar to those in PV2 testing, which measured

14.7 kWh/tonne at the same closing screen size. Notably, the Eastern Pushback Upper-level

Length measured higher indices, both Rod and Ball, than the other composites. Lower

concentrator throughput would be expected for this mineralization if the same primary grind

sizing is required.

Page 7: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

5

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

5.0 Specific Gravity

Apparent density and specific gravity measurements were performed on the samples using a

total of three different methods. Apparent density was measured on pieces of drill core or large

rock pieces using a wet-dry and wax dip method. After preparation of the composites, specific

gravity was determined on a pulverized sub-sample of each composite using a methyl hydrate

method. Detailed data for these measurements is located in Appendix B.

Since the wet-dry and wax dip method use a randomly selected piece of drill core, they may be

less representative of the overall composite than the methyl hydrate specific gravity

measurement. Also, density would be expected to be slightly lower than the methyl hydrate

method due to pores in the rock pieces. Photos showing the apparatus for the wet-dry apparent

density measurements, and the pieces selected for apparent density measurements are shown

in Photos 1 to 3.

PHOTOS 1 TO 3: APPARENT DENSITY MEASUREMENTS

The left photo shows the set-up for the wet-dry method. The sample is weighed on the scale then placed into the sieve in the water

which is attached to the base of the scale and weighed again. The middle and right photos show the drill core pieces selected for

apparent density measurements.

Page 8: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

6

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

A summary of average results is provided in Table 3.

TABLE 3: DENSITY

Composite Apparent Density SG

Wet-dry Wax Dip Methyl Hydrate

ROM Composite 2.59 N/A 2.59

Eastern Pushback Low-level Length 2.58 2.46 2.63

Eastern Pushback Mid-level Length 2.48 2.53 2.64

Eastern Pushback Upper-level Length 2.75 2.85 2.80

Northern Pushback Low-level Length 2.57 2.61 2.61

Northern Pushback Mid-level Length 2.64 2.57 2.66

Aplite Composite 2.56 N/A 2.63

For all measurements, density measured between 2.39 and 2.89. The differential between the

apparent density and SG measurement was generally low, indicating that the rock has relatively

low porosity.

Page 9: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

7

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

6.0 Flotation Testing

For each of the seven composites, a single batch rougher and cleaner flotation test was

conducted using flotation conditions developed in a previous metallurgical testing program.

Following these tests, two blend composites were constructed, one for each the Eastern and

Northern Pushbacks. Locked cycle tests, to determine closed circuit flotation response, were

conducted on these two blend composites. An additional two batch tests were conducted to

evaluate the effect of primary grind sizing.

6.1 Rougher Flotation Testing

A single rougher flotation test was conducted on each of the seven composites at

primary grind sizing of 300µm K80 using the flowsheet developed previously. In addition,

a second test, at a finer primary grind sizing of 250µm K80 was conducted on the ROM

Composite. A summary of the test schematic, conditions and results is provided as

Figure 1.

For all samples, natural hydrophobicity was observed, with significant copper recoveries

from the first roughing stage despite no addition of collector. Sodium Isobutyl Xanthate

(SIBX) and a sodium dialkyl dithiophosphate (Aero 3477 Promoter, understood to be

equivalent to Flottec 2044) collectors were used, similarly to the current Pinto Valley

concentrator. Although collector dosages were reduced compared to that recorded in

the PV2 program, further reductions may still be possible and perhaps necessary to

avoid excessive pyrite flotation.

Compared to the ROM Composite, the composites representing potential future

mineralization recorded lower copper recoveries. This is likely related to the lower head

grade of these composites1.

The finer primary grind sizing of 250µm K80 for the ROM Composite showed a slight

improvement in copper recovery of around 1 to 2 percent at comparable mass recovery.

A more significant improvement in molybdenum recovery of about 7 percent, was

recorded. Slightly faster flotation kinetics were also observed at the finer sizing.

Duplicate tests would be required to confirm the differential in performance, particularly

for molybdenum.

1 This could be due to lower liberation or grain size of the copper sulphides that is often observed for lower grade ores.

Page 10: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

FIGURE 1

ROUGHER RESULTS

Flowsheet Schematic

ROM Composite – Copper Performance

ROM Composite – Molybdenum Performance

Rougher Recoveries at 300µm K80

Bulk Rougher

Concentrates

250-300 µm K80

Conditions Summary

Feed

Notes: Aero 3477 is considered to be equivalent to Flottec 2044. They are sodium dialkyl dithiophosphate collectors.

SIBX: Sodium Isobutyl Xanthate

Note: Detailed test results are provided in Appendix B.

Lime Fuel Oil SIBX 3477*

Primary Grind 8.8-9.5 100-400 10 - -

Roughers 9.5-9.9 0-125 - 2 4

StageTotal Addition - g/tonne

pHTail

8

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

50

55

60

65

70

75

80

85

90

95

100

0 1 2 3 4 5 6

Co

ppe

r R

eco

ve

ry -

pe

rce

nt

Mass Recovery - percent

T1 250µm K80

T2 300µm K80

50

55

60

65

70

75

80

85

90

95

100

0 1 2 3 4 5 6

Moly

bde

nu

m R

eco

ve

ry -

perc

ent

Mass Recovery - percent

T1 250µm K80

T2 300µm K80

0

10

20

30

40

50

60

70

80

90

100

T2 ROMComposite

T3 Low-levelLength

T4 Mid-levelLength

T5 High-levelLength

T6 Low-levelLength

T7 Mid-levelLength

T8Composite

Re

co

ve

ry -

pe

rce

nt

Cu Recovery

Mo Recovery

Page 11: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

9

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

6.2 Cleaner Flotation Testing

Like for the rougher tests, a single batch cleaner test was conducted on each of the

seven composites. For the Eastern Pushback (EP) Upper-level Length composite, a

second test was conducted at a finer primary grind sizing and coarser regrind sizing.

Figure 2 shows the test schematic, conditions and a summary of the results from the

batch cleaner tests.

The target regrind sizing was 43µm K80 based on the program conducted in PV2.

However, achieving this target proved challenging due to the range of rougher masses

and low power requirement to achieve this relatively coarse sizing. For all the initial

cleaning tests, a 5 minute regrind time was used. For the ROM, Eastern Pushback (EP)

Low and Mid and Northern Pushback (NP) Mid composites, the regrind sizings were

close to target. But for the EP Upper, NP Low and Aplite composites, the sizings were

finer than target at around 20µm K80.

Despite the regrind sizing being the coarsest for the ROM composite, this composite still

exhibited superior copper performance to all the other samples. For the ROM

Composite, about 88 percent of the copper was recovered to the second cleaner

concentrate which graded about 28 percent copper. This was reportedly in line with that

commonly obtained at the Pinto Valley Concentrator. Higher sulphur to copper ratios in

the feed tended to result in poorer concentrate copper grades; presumably due to pyrite

dilution.

Despite finer regrind sizings, copper recovery for all the other composites averaged 80

percent into the second cleaner concentrates at an average grade of 26 percent copper.

Molybdenum performance was, however, similar to that of the ROM composite. It

appears that concentrate molybdenum grade is somewhat predictable using

molybdenum head grade.

A second test was conducted on the EP Upper composite at a finer primary grind sizing.

In this test, a shorter regrind time of 2 minutes was used but the regrind sizing was too

coarse from this test at 95µm K80. As a result, copper performance of the cleaning

circuit was poor. It is also notable that significantly different rougher performance for

iron and sulphur was observed in the second test, suggesting that the collector dosage

may be too high in the rougher; activating the pyrite.

Page 12: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

FIGURE 2

CLEANER RESULTS

Flowsheet Schematic

Eastern Pushback Upper-level Length – Copper Performance Copper Performance – 300µm K80

Cleaner Performance – 300µm K80

250-300 µm K80

Conditions Summary

Feed

Note: Detailed test conditions and results are provided in Appendix B.

50

55

60

65

70

75

80

85

90

95

100

0 5 10 15 20 25 30

Cop

pe

r R

eco

ve

ry -

pe

rce

nt

Copper Grade - percent

300µm K80 PG,19µm K80 RG

250µm K80 PG,95µm K80 RG

Bulk Con

Rougher

Tailing

Cleaner

Tailings

Lime Fuel Oil SIBX 3477*

Primary Grind 8.4-9.2 100-400 10 - -

Roughers 9.4-9.5 0-125 - 2 4

Regrind 9.0-10.0 50 10 - -

Cleaners 11.0-11.1 - - 1

Stage pHTotal Addition - g/tonne

50

55

60

65

70

75

80

85

90

95

100

0 5 10 15 20 25 30 35

Co

pp

er

Re

co

ve

ry -

pe

rce

nt

2nd Clnr Con Cu Grade - percent

Other Comps

T9 ROM

Effect of S:Cu Ratio

Regrind

K80 - µm 47 36 36 19 24 40 18

10

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

18-95µm

K80

0

5

10

15

20

25

30

35

0 1 2 3 4 5 6 7 8 9

2n

d C

lnr

Con

c C

u G

rad

e -

pe

rce

nt

Feed S:Cu Ratio

0

10

20

30

40

50

60

70

80

90

100

T9ROM

T10Low

T11Mid

T12Upper

T13Low

T14Mid

T15

Re

co

ve

ry -

pe

rce

nt

Cu RecoveryMo Recovery2nd Clnr Con Cu Grade - percent

Page 13: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

11

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

6.3 Locked Cycle Flotation Tests

Two blends were constructed, according to client instructions, in preparation for locked

cycle tests. For each the Eastern and Northern Pushbacks, a 50:50 ratio of Low and

Mid-level Lengths were combined to construct two blends. Tailings and water collected

from these tests were submitted to ACZ Laboratories for further testing.

At client request, a slightly finer primary grind sizing was used for the locked cycle tests.

For the Eastern Pushback blend, the primary grind sizing was 255µm K80, while the

Northern Pushback sizing was coarser at 281µm K80. Since the same primary grind time

was used, the coarser sizing would be considered to be a result of harder mineralization.

A regrind time of 3 minutes was used, resulting in sizings of 39 and 48µm K80 for the

Eastern and Northern Pushback blends, respectively. This was in line with the target.

Under these conditions, about 85 percent of the copper was recovered in both tests.

However, the concentrates were relatively low grade, at about 20 to 23 percent copper,

despite the inclusion of three dilution cleaning stages. Visual observation indicated

relatively high levels of pyrite in the cleaners that appeared to be activated.

Subsamples of the concentrate from the test on the Eastern Pushback blend, as well as

the first cleaner tailings from both tests were mounted onto slides for inspection under an

optical microscope. It was apparent that most particles of concern (copper sulphides

and pyrite) were liberated, in both the concentrate and the tailing. This suggests that

improved selectivity may be possible by changes to chemical conditions. Options to

reduce pyrite activation may include lower collector dosages or removal of the stronger

collector, SIBX, from the rougher stage, the addition of pyrite depressants, or higher pH

levels. The presence of some binaries suggests further regrinding would also provide

some benefit.

Molybdenum recovery measured about 48 and 62 percent for the Eastern and Northern

Pushback blends, respectively. The concentrates graded about 0.2 and 0.3 percent

molybdenum; which may be sufficient for economic separation of a molybdenum

concentrate.

The finer primary grind sizings for the two tests did appear to slightly improve rougher

recovery for both copper and molybdenum when compared to the rougher tests at

300µm K80.

Page 14: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

FIGURE 3

LOCKED CYCLE TESTS

Flowsheet Schematic

Locked Cycle Test Results – Cycle IV+V Summary

255-281 µm K80

Conditions SummaryFeed

Bulk Con

Rougher

Tailing

Cleaner

Tailings

12

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

39-48µm

K80

Lime Fuel Oil SIBX 3477*

Primary Grind 9.5 250-300 10 - -

Roughers 9.5 - 2 4

Regrind 11.0 100 10 - -

Cleaners 11.0 - - 0-1

Stage pHTotal Addition - g/tonne

T17 Bulk Concentrate Cycle V

Note: Detailed test conditions and results are provided in Appendix B.

All full size photomicrographs are located in Appendix F.

T18 1st Cleaner Tailing Cycle V

Product Weight Assay - percent or g/t Distribution - percent

% Cu Mo Fe S Cu Mo Fe S

T17 50:50 Blend of Eastern Pushback Low and Mid-level Lengths

Feed 100.0 0.30 55 1.44 0.85 100 100 100 100

Concentrate 1.3 20.1 2008 34.7 42.6 85.8 47.6 31.4 64.8

Cleaner Tail 6.3 0.25 133 4.74 3.99 5.1 15.2 20.7 29.3

Rougher Tail 92.4 0.030 22 0.74 0.055 9.1 37.1 47.9 6.0

T18 50:50 Blend of Northern Pushback Low and Mid-level Lengths

Feed 100.0 0.30 64 1.40 1.01 100 100 100 100

Concentrate 1.1 22.9 3484 33.7 42.8 85.2 61.9 27.1 47.6

Cleaner Tail 5.9 0.44 189 7.26 8.32 8.6 17.6 30.7 48.7

Rougher Tail 92.9 0.020 14 0.63 0.040 6.1 20.5 42.1 3.7

Page 15: PV3 Metallurgical Testing of Future Ores from€¦ · PV2 metallurgical program. Testing was concluded early January, after which this report was prepared. This report summarizes

13

Ba

se

Me

tallu

rgic

al La

bo

rato

rie

s L

td.

7.0 Conclusions and Recommendations

Six samples of potential future mineralization for the Pinto Valley operation were

evaluated in comparison to a ROM composite understood to represent current feed ore

to the Pinto Valley concentrator. The grade of copper in these future ores was lower,

averaging about 0.3 percent copper, compared to the ROM composite. Likely as a

result, copper performance was generally poorer when compared to the ROM

composite.

In a batch cleaner test on the ROM composite, about 88 percent of the copper was

recovered into a copper concentrate grading about 28 percent copper. In comparison,

the samples of potential future mineralization recorded an average copper recovery of

80 percent to a concentrate grading about 26 percent copper under similar conditions.

In locked cycle tests conducted on blend samples from the Eastern and Northern

Pushbacks, copper was about 85 percent recovered to concentrates grading 20 to 23

percent copper. Visual observations during the test and inspection of slides under an

optical microscope indicate that pyrite was diluting the concentrates. Most of this pyrite

appeared to be liberated. Conversely, most of the copper sulphides observed under the

microscope in the first cleaner tailing appeared to be liberated. Further optimization of

collector type and dosage may allow higher grade concentrates to be produced. Other

alternatives to improve selectivity against pyrite might include the addition of pyrite

depressants or further elevation of pH. Further testing would be required for

confirmation. Notably, the presence of some unliberated particles would suggest further

regrinding would assist with performance to a lesser degree.

Molybdenum grades tended be related to molybdenum grades of the feed which varied

from about 40 to 150 g/tonne for the seven composites. Concentrates from the higher

grade mineralization, particularly the

Aplite composite, would be considered sufficiently high in molybdenum to allow for

economic separation of a separate molybdenum concentrate.