pw/engineering june 20, 2013 - vbgov.com · 6/18/2013  · microsoft powerpoint - eastern shore dr...

36
June 20, 2013 1 PW/Engineering

Upload: others

Post on 17-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

June 20, 2013

1

PW/Engineering

Page 2: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

2

Three Questions

• Why is the Eastern Shore Drive Drainage Area Experiencing Recurrent Flooding?

• What can be done about it?

• What is being done?– Comprehensively– On an Interim basis

Page 3: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

3

Why is the Eastern Shore Drive Drainage Area Experiencing

Recurrent Flooding?

Page 4: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

4

Recurrent Flooding & Sea Level Rise

• Storm water & flooding: A major citizen concern

• Flooding is increasing• Sea level is rising

Page 5: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

5

Sea Level RiseInformation

• Sewell’s Point: + 0.18 in/yr • CBBT: + 0.24 in/yr • Rise last 50 years: ~ 1 ft • Projected rise next 50 years: 1 – 3 ft• Result:

Sea Level Rise

CoastalStorms+ =

Increased and Recurrent Flooding

in Many Areas

Page 6: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

6

Ocean Park

Cape Henry Shores

Lynnhaven Colony

Back Bay

Eastern ParkKings Grant

Cape Story

Windsor Woods

Princess Anne Plaza

Thalia

Glenwood

Old Beach

Oceanfront

Sandbridge

Green RunOcean Lakes

Page 7: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

730th Street

Page 8: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

8Goodspeed Road

Page 9: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

9Dockside Vicinity

Page 10: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

10Bubba’s

Page 11: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

11Eastern Shore Drive Neighborhoods

Page 12: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

12

A Particularly Vulnerable Area

-High Tides -Storm Surge -Rainfall

Eastern Shore Drive Area

Page 13: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

13

Close-up of Eastern Shore Drive Area

Flooding & Sea Level Rise

Page 14: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

What can be done about it?

14

Page 15: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

15

Recurrent Flooding Adaptation Strategies

• Management/Retreat– Prevent development in high risk areas– Discourage rebuilding in high risk areas

• Accommodation– Elevating buildings/Flood proofing homes– Evacuation routes/warning systems

• Protection Measures– Focus of Today’s Discussion

Page 16: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

16

Recurrent Flooding & Sea Level RiseAdaptation Strategy: Protection Measures

• Engineering Flood Control Measures:– Complex– Costly– O&M Intensive– Limit to Effectiveness (LOS)

• LOS Exceedence = Major Flooding

Page 17: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

What is being done?

17

Page 18: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

18

Comprehensive Flood Control Measures

Page 19: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

19

Comprehensive Flood Control Measures

Major CIP: 7-151 Eastern Shore Drive Drainage ImprovementProgrammed Funding: $53.13 MFinal Cost: TBDProject Development Study Underway

• Identify Improvements: Pump Stations, Outfalls, Flood Control Gates, Flood Walls

• Lowest Lying Areas May Be Problematic• Develop Implementation Plan (Phasing)• Results By End of This Year

Page 20: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

20

• Some have suggested installing backflow preventers to keep tides out

Interim Flood Control Measures

Page 21: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

Lynnhaven Colony – Cape Henry Ditch

21

Interim Flood Control Measures

Page 22: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

22

Detailed analysis:• Determine where backflow prevention devices

will help reduce flooding from high tides• Determine where backflow prevention devices

will not increase flooding from rainfall• Determine type of backflow prevention device

appropriate for location (flexible check valve or automated sluice gate)

Interim Flood Control Measures

Page 23: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

23

Interim Flood Control Measures

For Each Location Evaluated:• Determined tidal elevation at which flooding will

occur, even with backflow preventer in place• Determined elevations of streets and homes• Calculated available storage for rainfall in each

drainage basin• Hydraulically modeled numerous rainfall / tidal

elevation combinations to determine benefits and impacts of installing backflow prevention devices

Page 24: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

24

Interim Flood Control Measures39 Locations Considered

Page 25: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

25

Lynnhaven Colony - Tidally Adjacent Area

Interim Flood Control Measures

Page 26: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

• Range of Effectiveness– Up to overtopping elevations of 3.3 to 4.7 Feet (NAVD88)

depending on location– Up to 4 to 6 inches of rainfall depending on location

• Cost: $244,000 (5 Locations- 4, 5, 8, 10, 11)• Houses Protected: 0• Garages Protected: 4• Linear Feet of Lynnhaven Drive Protected: 320 L.F.

26

Lynnhaven Colony - Tidally Adjacent AreaResults

Interim Flood Control Measures

Page 27: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

Lynnhaven Colony Cape Henry Ditch

27

Interim Flood Control Measures

Page 28: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

Lynnhaven Colony Cape Henry Ditch

28

• Range of effectiveness:– Up to Overtopping Elevation: 5.4 Feet (NAVD88)– Up to 1 inch of rainfall with tide gates closed

• Total Cost: $672,000 (2 Locations- 18 & 26)• Houses protected: 4• Garages protected: 9• Length of Cape Henry Drive protected: 150 L.F.

Results

Interim Flood Control Measures

Page 29: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

Cape Henry Area

29

Interim Flood Control Measures

Page 30: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

Cape Henry Area

30

Results• Range of Effectiveness

– Up to Overtopping Elevation: 5.2 Feet (NAVD88)– Up to 1 inch of rainfall with tide gate closed

• Cost: $290,000 (Location 39)• Houses Protected: 1• Garages Protected: 2• Linear Feet of Street Protected: 0 L.F.

Interim Flood Control Measures

Page 31: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

31

• In eight locations backflow prevention devices can provide limited benefit by reducing the frequency of flooding from certain moderately high tides

• Backflow prevention devices cannot eliminate all flooding

• There has been at least three storm since 2009 for which the backflow preventers would have had absolutely no benefit:– Nor’Ida (November 2009) Elev. 6.9’– Irene (August 2011) Elev. 5.5’– Sandy (October 2013) Elev. 5.7’

Summary of Findings

All elevations are in NAVD 88 datum.

Page 32: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

32

Sewell’s Point Tidal Surge InfoBenchmarks and Events MLLW  (FT)

Category 4 ‐ (13‐19 Feet Surge at High Tide) 21.56Category 3 ‐ (9‐12 Feet Surge at High Tide) 14.56Category 2 ‐ (6‐8 Feet Surge at High Tide) 10.56

1933 Hurricane 8.02' Above MLLW 8.028.0 FT OCCURS ONCE EVERY 80 YEARS (EXTREME) 8.00Hurricane Isabel 9/18/2003 7.89' Above MLLW 7.89

November Nor'easter 11/12/2009 7.75' Above MLLW 7.75Category 1 ‐ (3‐5 Feet Surge at High Tide) 7.56

Hurricane Irene 8/27/2011  7.55 Above MLLW 7.55Ash Wednesday Storm 3/7/1962 7.22 ' Above MLLW 7.227.0 FT OCCURS ONCE EVERY 20 YEARS (SEVERE) 7.00Hurricane Sandy 10/29/2012 6.81' Above  MLLW 6.81

Hurricane 1936 6.2' Above MLLW 6.72Thanksgiving Nor'easter 2006 6.63' Above MLLW 6.63

Twin Nor'easter #2 1998 6.58' Above MLLW 6.58Columbus Day Nor'easter 6.52' Above MLLW 6.52

Nor'easter 1956 6.12' Above MLLW 6.126.0 FT OCCURS ONCE EVERY 7 YEARS (MODERATE) 5.00

Twin Nor'easter 1998 6.04' Above MLLW 6.04Hurricane Floyd 1999 5.97' Above MLLW 5.97Hurricane Flossy 1956 5.92' Above MLLW 5.92Hurricane Donna 1960 5.92' Above MLLS 5.92

4.5 FT OCCURS 3 TIMES PER YEAR (MINOR) 4.502.56 OCCURS 3 TIMES PER YEAR 2.56

MEAN HIGH HIGH WATER‐MHW (Average all High Tides) 2.56MEAN SEA LEVEL 1.35

MEAN LOWER LOW WATER‐MLLW (Average all Low Tides) 0.00

Lowest Tide of Record 1/31/1996 ‐3.58

Page 33: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

33

• Total Cost of Interim Improvements: $1.2 M• Benefit is some reduction in flooding frequency for:

– 5 house– 15 Garages– 570 L.F. of Street

• Comprehensive improvements are budgeted and initial phases could begin in 2016

• A decision on whether to fund the Interim Improvements is needed

Return On Investment

Page 34: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

If Authorized

• Procure / Install Check Valves at 5 locations in the Lynnhaven Colony Tidally Adjacent Area (Fall 2013, $244,000)

• Detailed Engineering / Permitting / Construction for 1 Check Valve and 2 Sluice Gates in Cape Henry Ditch (1 gate at West Great Neck and 1 gate at First Landing Lane, Check Valve at Sunstates Court; Construct Fall 2014, $962,000)

34

Two Step Process

Page 35: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

35

• Brief the City Management Leadership Team √• Brief the Bayfront Advisory Committee √ • Brief the District Council Member• Brief the City Council

Decision Process

Page 36: PW/Engineering June 20, 2013 - VBgov.com · 6/18/2013  · Microsoft PowerPoint - Eastern Shore Dr Backflow Prevention for 20 June BAC Mtg.pptx Author: mbumbaco Created Date: 6/18/2013

QUESTIONS

36

FOLLOW UP NEXT DOOR

Report Located on VBGOV.COM under Public Works Stormwater http://www.vbgov.com/government/departments/public-works/storm-water/Pages/east-shore-dr-drainage-impvts.aspx