quarterly progress report:4th quarter of 2011-12 · 46scrap&ld slag handling at ......
TRANSCRIPT
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
46 Scrap&LD Slag handling at VSP for the Period 2008‐2011
5389.12 5389.12 0.00 VSP/WC/SSD/58315‐0/N/2009‐2010/8090000272 18‐MAY‐09
FERRO SCRAP NIGAM LTD
01‐07‐08 30‐06‐11 95.03 AGM(SSD), SSD
Job Completed
50 STEEL / IRON SCRAP PROCESSING AND EMERGENCY CONTAINER MANAGEMENT.
1214.55 2623.43 116.00 VSP/WC/SSD/58388‐0/OT/2009‐2010/8090000274 18‐MAY‐09
NEHA CONSTRN (P) LTD
16‐05‐09 15‐05‐12 53.16 AGM (SSD), SSD
Work in Progress
49 Recovery of steel scrap, iron scrap, iron / steel muck and fines and used/ rejected refractories from the Central dump &Processing Yard, transportation of Slag & debris.
981.02 2217.11 126.00 VSP/WC/SSD/58387‐0/OT/2009‐2010/8090000273 18‐MAY‐09
NEHA CONSTRN (P) LTD
16‐05‐09 15‐05‐12 56.80 AGM (SSD), SSD
Work in Progress
12 RUNNING AND PLANNED REPAIR JOBS (REFRACTORY AND MECHANICAL) IN COCCP BATTERIES FOR THE YEAR 2008‐2011
1597.72 1700.00 6.40 VSP/WC/CRG/58058 ‐ 0/OT/2008‐2009/8080000166 19‐NOV‐08
ROSY ENTERPRISES
01‐10‐08 30‐09‐11 24.64 DGM CRG, COCCP
Extended up to 30/09/12
55 STRAPPING OF MILL PRODUCT IN WIRE ROD MILL
1091.95 1275.00 16.76 VSP/WC/WRM/58495‐0/OT/2009‐10/8090000359 12‐SEP‐09
MIDFIELD INDUSTRIES LTD
16‐08‐09 15‐08‐11 95.59 AGM(O)/WRM, WRM
Job Completed
6
Technological Assistance in Batteries of CO&CCP which involves cleaning of Standpipes, Valve boxes, Oven doors, Oven door windows, Hatches etc in A,B,C &G shifts in smoky, dusty & hot environment.
388.79 379.90 ‐2.29 VSP/WC/CO&CCP/71407‐0/OT/2011‐12/8110000940 03‐DEC‐11
MULTI‐TECH CONSTRUCTIONS
01‐12‐11 30‐11‐12 ‐ DGM(O)‐CO, COCCP
Work in Progress
16
Strapping of steel products (LMMM and MMSM) for Unitization purpose of open end wagons.
320.95 337.58 5.18 VSP/WC/LMMM/71220‐0/OT/2011‐2012/8120000983 10‐JAN‐12
MIDFIELD INDUSTRIES LTD
25‐12‐11 24‐12‐13 ‐ AGM (O), LMMM, LMMM
Work in Progress
Compiled from WCMS data given by IT departmemt Page 1 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
51 Lifting, Shifting,Transportation and dumping of slag boulders,muck and debris from DF Bay of SMS and collection,Transportation and Delivery of Bloom End Cutting Scrap to SMS Scrap Pit
320.06 320.06 0.00 VSP/WC/SSD/58510‐0/N/2009‐2010/8090000395 05‐NOV‐09
HINDUSTAN STEELWORKS CONSTRUCTIONS LTD
01‐08‐09 31‐07‐12 33.60 MGR(SSD), SSD
Work in Progress
8
Cold Vulcanising Of Conveyor Belts and Conveyor Belts Changing
280.15 280.15 0.00 VSP/WC/CMM/71460‐0/OT/2011‐12/8120001002. 08‐FEB‐12
THEJO ENGINEERING LTD
01‐02‐12 31‐01‐15 ‐ AGM(M)/CMM, CMM
2
SHIFTING OF EXCESS BF GRANULATED SLAG
243.81 228.58 ‐6.25 VSP/WC/BF/71206‐ 0/OT/2011‐2012/8110000803 07‐JUL‐11
SAI LAKSHMI ENTERPRISES
08‐07‐11 07‐07‐12 ‐ AGM(O), BF Work in Progress
62
Periodic Overhauling (POH) of Two nos. of VSP Locomotives. consisting of the following jobs , a) Complete dismantling of all sub‐assemblies., b) Overhauling/ Reconditioning/ replacement as necessary, c) Reassembly of the same, d) Modifications/ Upgradations/ as desired by VSP, e)Special repairs
220.00 220.00 0.00 VSP/WC/TRAFFIC/71590‐0/N/2011‐12/8120001004 11‐FEB‐12
SOUTHERN RAILWAY‐ CENTRAL WORKSHOP
29‐02‐12 28‐02‐13 ‐ AGM(MAINT.), TRAFFIC
Work in Progress
Compiled from WCMS data given by IT departmemt Page 2 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
57
Capital Repairs,Tube leakage Repairs, HP Welding in CDCP1,2,3&4 Boilers,Replacement of Economiser & Evaporator Tube bundles in CDCP Boilers, and Misc jobs in Auxilliary units of Thermal Power Plant
186.24 204.83 9.98 VSP/WC/TPP/71319‐0/OT/2011‐12/8110000921 24‐NOV‐11
V&S CONSTRUCTIONS
01‐01‐12 31‐12‐13 ‐ DGM(O)/TPP, TPP
Work in Progress
59
CAPITAL REPAIR OF BOILER PRESSURE PARTS
155.64 195.00 25.29 WC/VSP/70509‐O/O/2011‐12/8110000799 01‐JUL‐11
V&S CONSTRUCTIONS
16‐07‐11 15‐07‐13 ‐ DGM(M), TPP
Work in Progress
65
Evacuation & transportation of metallurgical waste and opr & Maint of Metallurgicl pond pump house
159.74 167.32 4.75 VSP/WC/WMD/71279‐0/OT/2011‐12/8110000949 14‐DEC‐11
SAI LAKSHMI ENTERPRISES
15‐12‐11 14‐12‐12 ‐ AGM (T)//WMD, WMD
Work in Progress
47 Digging, loosening, Removal and Shifting of old and accumulated metallic jam, muck & debris up to `zero' meter level (as defined in para 2 & 3 of clause 2 of Scope of Work) from area below CCM‐2, CCM‐3, CCM‐4, CCM‐5 & CCM‐6 in DF Bay of SMS at the specified place of work.
115.75 158.76 37.16 VSP/WC/SSD/70367‐0/OT/2011‐12/8110000760 04‐MAY‐11
METAL TRADERS & PROCESSING CO.
11‐05‐11 10‐03‐12 93.32 MANAGER (SSD), SSD
Work in Progress
20
STRAPPING OF MILL PRODUCTS IN MMSM.
110.59 158.00 42.86 VSP/WC/MMSM/71219‐0/OT/2011‐2012/8120000982 10‐JAN‐12
MIDFIELD INDUSTRIES LTD
01‐01‐12 31‐12‐13 ‐ AGM (O), MMSM
Work in Progress
Compiled from WCMS data given by IT departmemt Page 3 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
10 Cold Vulcanising Of Conveyor Belts and Conveyor Belts Changing
144.90 153.00 5.59 VSP/WCD/CMM/57418‐0/O/2007‐08/13059 24‐MAR‐08
THEJO ENGG SERVICES PVT LTD
01‐04‐08 31‐03‐11 94.25 AGM(M)/CMM, CMM
Job Completed
45 HANDLING AND PROCESSING OF NON‐ROLLABLE BLOOMS IN BSY OF SMS AREA
144.36 144.36 0.00 VSP/WC/SMS/58496‐0/N/2008‐09/8090000269 11‐MAY‐09
HINDUSTAN STEELWORKS CONSTRUCTIONS LTD
01‐06‐09 31‐05‐12 57.57 AGM ‐ BSY/ SMS, SMS
Work in Progress
63 Periodic Overhauling (POH) of VSP Locomotive Nos. VSP‐03 & VSP‐04. consisting of the following jobs , a) Complete dismantling of all sub‐assemblies., b) Overhauling/ Reconditioning/ replacement as necessary, c) Reassembly of the same, d) Modifications/ Upgradations/ as desired by VSP, e)Special
140.00 140.00 0.00 VSP/WC/TRAFFIC/70285‐0/N/2010‐11/8110000695 24‐FEB‐11
SOUTHERN RAILWAY‐ CENTRAL WORKSHOP
01‐03‐11 29‐02‐12 64.35 AGM(MAINT.), TRAFFIC
Work in Progress
26 MAINTENANCE & UPKEEP OF 42 NOS. LIFTS IN VSP FOR 3 YEARS PERIOD
128.23 135.00 5.28 VSP/WC/LUB&HYD/70319‐0/OT/2010‐11/8100000638 11‐NOV‐10
BECO ELEVATOR ENGINEERING
01‐11‐10 31‐10‐13 9.07 AGM(MECH), Lub & Hyd
Work in Progress
25
Refractory lining jobs of SMS ‐I & II, Rolling Mills and allied units.
116.87 128.22 9.72 VSP/WC/RED/70638‐0/OT/2011‐2012/8110000841 23‐AUG‐11
KRISHNA CONSTRUCTIONS
06‐08‐11 05‐08‐13 ‐ AGM, RED Work in Progress
18
Repair of DE Systems 2011‐12
128.28 125.00 ‐2.55 VSP/WC/ENMD/71300‐0/OT/2011‐12/8110000891 29‐OCT‐11
DURGA SRI RAGHAVENDRA ENGG SERVICES
01‐11‐11 31‐10‐12 ‐ MANAGER(ENMD), EnMD
Work in Progress
Compiled from WCMS data given by IT departmemt Page 4 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
3 Maintenance Contract of On‐Line Stack Monitoring Systems and their associated equipment installed in VSP
123.00 123.00 0.00 VSP/WC/INSTN/70425‐0/N/2010‐11/8100000123 27‐OCT‐10
NEVCO ENGINEERS PVT LTD
21‐12‐10 20‐12‐13 4.46 J.N. MURTHY, AGM (INST), INSTMN
Work in Progress
48 SUPERVISION OF THE WORK OF " STEEL AND IRON SCRAP PROCESSING INCLUDING EMERGENCY CONTAINER MANAGEMENT IN VSP(INSIDE PLANT)" FOR THE PERIOD 2009‐12
118.05 118.05 0.00 VSP/WC/SSD/58509‐0/N/2009‐2010/8090000392 02‐NOV‐09
HINDUSTAN STEELWORKS CONSTRUCTIONS LTD
16‐05‐09 15‐05‐12 57.37 MGR (SSD), SSD
Work in Progress
26
Up keep of Wagon Tipplers and conveyor galleries of stacking streamin RMHP ( Ore & Flux ) Part ‐I
114.12 117.54 3.00 VSP/WC/RMHP/71417‐0/OT/2011‐2012/8110000947 13‐DEC‐11
CLT ENGINEERING ENTERPRISES (Partnership)
01‐01‐12 31‐12‐12 ‐ S.GOPALA KRISHNA, DGM(O)I/C, RMHP
Work in Progress
11 Mechanised Handling , Stacking and Loading of Ammonium Sulphate bags and HP Naphthalene at Coal Chemicals Plant at CO&CCP.
108.09 117.28 8.50 VSP/WC/CO&CCP/58483‐0/OT/2009‐10/8090000320 05‐AUG‐09
MANASA ENTERPRISES
01‐09‐09 31‐08‐12 40.39 AGM(O)/CCP, COCCP
Work in Progress
11 Rubber Lagging Of Conveyor Pulleys (For the Years 2008‐11)
105.09 111.40 6.00 VSP/WC/CMM/58011‐0/OT/2008‐09/8080000062 18‐AUG‐08
THEJO ENGG SERVICES PVT LTD
18‐08‐08 17‐08‐11 75.71 AGM(M)/CMM, CMM
Job Completed
1
OPERATION AND MAINTENANCE OF ADMINISTRATION BUILDING & OUTSIDE PERIPHERY AC PLANTS
103.16 102.49 ‐0.65 VSP/WC/ACS/71492‐0/OT/2011‐12/8120001018 23‐FEB‐12
VIJAYA ENGG WORKS
01‐03‐12 28‐02‐13 ‐ AGM(ACS), ACS
Work yet to be started
40 Technological assistance in Bloom storage yard‐1
95.97 99.81 4.00 VSP/WC/SMS/70456‐0/OT/2010‐11/8110000736 06‐APR‐11
SRI LAKSHMI ENGG WORKS
01‐05‐11 01‐04‐13 ‐ AGM‐ELECT, SMS
Work in Progress
Compiled from WCMS data given by IT departmemt Page 5 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
64
Comprehensive operation, housekeeping and mechanical maintenance jobs in treatment plants of BF Pump houses of Water Management Department on 24 hrs. x 365 days basis.
101.25 96.03 ‐5.15 VSP/WC/WMD/70592‐0/OT/2011‐12/8110000961 22‐DEC‐11
SKI Engineering 09‐01‐12 08‐01‐13 ‐ AGM(T)/WMD, WMD
Work in Progress
3
OPERATION AND MAINTENANCE OF UKKU HOUSE AND VSGH AC PLANTS
92.91 90.00 ‐3.13 VSP/WC/ACS/71507‐0/OT/2011‐12/8120000995 30‐JAN‐12
SIRI CONSTRUCTIONS ‐CHAITANYA NAGAR GAJUWAKA
01‐02‐12 31‐01‐15 ‐ AGM (ACS), ACS
Work in Progress
17
Technological Assistance for operational works in finishing and shipping areas fo LMMM, Part‐3
82.86 84.00 1.37 VSP/WC/LMMM/71277‐0/OT/2011‐2012/8110000933 28‐NOV‐11
RISHITA ASSOCIATES
16‐12‐11 15‐11‐13 ‐ AGM(O), LMMM
Work in Progress
1 MISCELLANEOUS CIVIL JOBS IN SMS AND ES&F ZONE/AREAS(Part‐1)
119.76 80.21 ‐33.03 VSP/WC/CED/71526‐1/OT/2011‐12/8120001027 03‐MAR‐12
CH BANGARAIAH & CO
09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
4
Repair of 7.5 MW Generator Rotor
76.13 76.13 0.00 VSP/WC/71593‐N/NOM/8120001001. 08‐FEB‐12
BHEL ‐ VISAKHAPATNAM SITE OFFICE
13‐02‐12 12‐05‐12 ‐ AGM(E), TPP
Work in Progress
60
CAPITAL REPAIR OF BOWL MILLS OF TPP BOILERS
58.76 74.76 27.24 VSP/WC/TPP/70495‐O/O/2011‐12/8110000801 07‐JUL‐11
HI‐TECH SERVICES
08‐07‐11 07‐07‐13 ‐ DGM(M), TPP
Work in Progress
9 REFRACTORY MAINTENANCE OF CDCP , CCP OF CCCD
74.11 73.90 ‐0.29 VSP/WC/CRG/58438‐0/OT/2009‐2010/8090000264 28‐APR‐09
MULTI‐TECH CONSTRUCTIONS
01‐06‐09 31‐05‐11 92.92 AGM(CRG), COCCP
Job Completed
Compiled from WCMS data given by IT departmemt Page 6 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
36
Technological assistance in Bloom storage yard‐2
71.48 73.73 3.15 VSP/WC/SMS/71374‐0/OT/2011‐12/8110000942 08‐DEC‐11
SRI VENKATA RAMA ENTERPRISES
01‐01‐12 31‐12‐14 ‐ AGM(O)/BSY, SMS
Work in Progress
25 Hiring of Mini trucks of 2.5/3t capacity.
48.25 69.97 45.02 VSP/WC/FMD/59050‐0/1/OT/2010‐11/ 21‐APR‐10
MAJJI GOWRI MINI TRANSPORT
01‐05‐10 30‐04‐13 25.43 AGM(FMD), FMD
Work in Progress
2 MAINTENANCE OF PERSONAL COMPUTERS AND ITS RELATED EQUIPMENT IN VSP
99.59 68.70 ‐31.02 VSP/WC/IT/70385‐0/O/2011‐12/8110000751 26‐APR‐11
ACS TECHNOLOGIES LTD
01‐05‐11 30‐04‐13 ‐ AGM(IT), I T
Work in Progress
22 Cleaning Works in MMSM 73.45 68.61 ‐6.60 VSP/WC/MMSM/70484‐0/OT/2010‐2011/8110000686 07‐FEB‐11
SWATHI ENGG WORKS
20‐02‐11 19‐02‐13 ‐ AGM(O)/MMSM, MMSM
Work in Progress
22 RETREADING / REPAIRS OF HEAVY DUTY TYRES (OTR) OF EARTH MOVING EQUIPMENTS OF FMD
47.61 66.38 39.43 VSP/WC/FMD/59019‐0/OT/2009‐10/ 10OCT‐09
SURYA TYRE TECH
12‐12‐09 11‐12‐11 45.36 AGM(FMD), FMD
Extended up to 11/04/12
29
CLEANING OF RECLAIMING CONVEYOR & ROTARY DRYER STREAM IN RMHP (PART II B)
65.78 65.78 0.00 VSP/WC/RMHP/71383‐0/OT/2011‐2012/8110000881 20‐OCT‐11
P APPALA NAIDU 21‐10‐11 20‐10‐12 ‐ MSV KRISHNAIAH, DGM (O), RMHP
Work in Progress
5 OPERATION AND MAINTENANCE OF ADMINISTRATION BUILDING & OUTSIDE PERIPHERY AC PLANTS
64.37 65.66 2.00 VSP/WC/ACS/58237‐0/OT/2008‐09/ 29‐OCT‐08
VIJAYA ENGG WORKS
01‐11‐08 31‐10‐11 97.83 SR. MANAGER(ACS), ACS
Job Completed
6 OPERATION AND MAINTENANCE OF UKKU HOUSE AND VSGH AC PLANTS
68.36 64.20 ‐6.08 VSP/WC/ACS/58267‐0/OT/2008‐09/ 14‐NOV‐08
SIRI CONSTRUCTIONS ‐CHAITANYA NAGAR GAJUWAKA
01‐12‐08 30‐11‐11 97.52 SR. MANAGER (ACS), ACS
Job Completed
Compiled from WCMS data given by IT departmemt Page 7 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
23 Hiring of Mini trucks of 2.5/3t capacity.
42.89 62.19 45.02 VSP/WC/FMD/59050‐0/2/OT/2010‐11/ 21‐APR‐10
K VASANTA RAO 01‐05‐10 30‐04‐13 27.27 AGM(FMD), FMD
Work in Progress
24 Hiring of Mini trucks of 2.5/3t capacity.
42.89 62.19 45.02 VSP/WC/FMD/59050‐0/3/OT/2010‐11/ 21‐APR‐10
A V LAKSHMANA RAO
01‐05‐10 30‐04‐13 26.98 AGM(FMD), FMD
Work in Progress
33
Repainting of various structures including EMD pipelines in TPP zone, ASP zone& PCM in BF zone
65.96 62.13 ‐5.82 VSP/WC/STED/70608‐0/OT/2011‐12/8110000789 02‐JUN‐11
COROMONDAL PAINTS LTD
02‐06‐11 01‐06‐12 ‐ MANAGER, StED
Work in Progress
54 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of Converter shop, Slag Yard, LP Bay, Mixer and other Auxiliary Units in SMS Area (Part‐2)(Group‐B)
59.38 59.38 0.00 VSP/WC/StED/59375‐2/OT/2010‐11/8100000567 15‐JUL‐10
JYOTHI ERECTORS
23‐07‐10 22‐07‐11 85.58 AGM, StED Job Completed
52 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of Blast Furnace (Part‐3)
58.95 58.95 0.00 VSP/WC/StED/59375‐3/OT/2010‐11/8100000568 15‐JUL‐10
FRANCO INDIA 23‐07‐10 22‐07‐11 86.47 AGM, StED Job Completed
34
Repainting of Various structures including ODPL structures and pipelines in BF area
56.94 58.05 1.95 VSP/WC/STED/70622‐0/OT/2011‐12/8110000790 02‐JUN‐11
COROMONDAL PAINTS LTD
02‐06‐11 01‐06‐12 ‐ SR MANAGER, StED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 8 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
27 DEVELOPMENT OF MANUFACTURING DRAWINGS FOR SPARE PARTS USING LDS MACHINE AND CAD WORK STATION AND SUPPLY OF CAD BACK UP FILES IN CD'S.
53.45 56.66 6.00 VSP/WC/PD/58219‐0/OT/2008‐09/8080000184 22‐DEC‐08
ESQUIRE ENGINEERING SOLUTIONS LTD,
29‐12‐08 28‐12‐11 57.38 AGM(MECH), PD DEPT
Extended up to 28/04/12
35
Repainting of Various structures including ODPL structures in Battery side & FLTs at COCCP area and FLTs & WTs along boundary wall.
66.27 56.27 ‐15.09 VSP/WC/STED/70561‐0/OT/2011‐12/8110000788 02‐JUN‐11
SHIVA CHEMICALS
02‐06‐11 01‐06‐12 ‐ MANAGER, StED
Work in Progress
10 Technological Assistance & Upkeep of Coal Chemical Plant (Part‐2)
55.69 55.68 ‐0.02 VSP/WC/CO&CCP/70491‐0/OT/2010‐2011/810000710 09‐MAR‐11
REDDY ENTERPRISES (LRK)
01‐04‐11 31‐03‐12 46.73 AGM(O)CCP, COCCP
Work in Progress
24
Refractory works of Blast Furnaces, CRMP, Sinter Plant and T.P.P
52.35 55.65 6.30 VSP/WC/RED/71282‐0/OT/2011‐2012/8110000871 29‐SEP‐11
MULTI‐TECH CONSTRUCTIONS
05‐10‐11 04‐10‐13 ‐ AGM(RED), RED
Work in Progress
51 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of Sinter Plant area (Part‐4)
55.40 55.40 0.00 VSP/WC/StED/59375‐4/OT/2010‐11/8100000569 15‐JUL‐10
ANIL ENGINEERING WORKS
23‐07‐10 22‐07‐11 88.10 AGM, StED Job Completed
8
Peripheral Cleaning works of CO&CCP Batteries
58.29 55.26 ‐5.20 VSP/WC/CO&CCP/71243‐0/OT/2011‐12/8110000839 19‐AUG‐11
R KONDAYYA 01‐09‐11 31‐08‐12 ‐ DGM(O), COCCP
Work in Progress
Compiled from WCMS data given by IT departmemt Page 9 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
14 HANDLING AND POISITIONING OF RAW MATERIALS, HOUSE KEEPING AND MACHINE CLEANING AT FOUNDRY FOR THE YEAR 2010 ‐ 12
58.72 55.13 ‐6.11 VSP/WC/ES&F/70411‐0/OT/2010‐11/8100000667 16‐DEC‐10
BABA ENGG WORKS
16‐01‐11 15‐01‐13 9.60 S.K.PANDEY, AGM(FOUNDRY), ES&F
Work in Progress
53 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of WRM, LMMM, MMSM & other units of Mills including lighting towers and watch towers along Boundary wall (Part‐5)
54.53 54.53 0.00 VSP/WC/StED/59375‐5/OT/2010‐11/8100000570 15‐JUL‐10
RK CONSTRUCTION
23‐07‐10 22‐07‐11 85.95 AGM, StED Job Completed
32 Technological upkeep of Converter shop floors and equipments in SMS.
61.35 53.62 ‐12.60 VSP/WC/SMS/71568‐0/OT/2011‐12/8120001042 10‐MAR‐12
PAHAL SWAYAM SEVI SANSTHA
01‐04‐12 31‐03‐13 ‐ AGM(O), SMS
Work yet to be started
18 CLEANING WORKS IN BAR MILL AREAS OF LMMM.
51.51 52.90 2.69 VSP/WC/LMMM/70397‐0/OT/2010‐11/8110000733 04‐APR‐11
M SOMULU 08‐04‐11 07‐04‐13 ‐ AGM(O), LMMM
Work in Progress
36
Repainting of various units in Rolling Mills area and Conveyor galleries in C& CCD area
59.28 52.75 ‐11.01 VP/WC/STED/70447‐0/OT/2011‐12/8110000787 02‐JUN‐11
MK GOLD PAINTS PVT LTD
02‐06‐11 01‐06‐12 ‐ MANAGER, StED
Work in Progress
28
TECHNOLOGICAL ASSISTANCE IN LOSP & LOCP IN RMHP ZONE
52.46 52.46 0.00 VSP/WC/RMHP/71384‐0/OT/2011‐2012/8110000886 25‐OCT‐11
K CHINNA RAO 01‐11‐11 31‐10‐12 ‐ AK DHAWAN, AGM (O), RMHP
Work in Progress
Compiled from WCMS data given by IT departmemt Page 10 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
39 Repainting of Various structures in CO&CCP area including EMD Pipelines
49.24 52.19 6.00 VSP/WC/STED/70602‐0/OT/2011‐12/8110000778 24‐MAY‐11
TRITON PAINTS 24‐05‐11 23‐05‐12 ‐ SR MANAGER, StED
Work in Progress
21 Technologial Assistance in CMS of Engg. Shops & Fdy.
53.73 50.34 ‐6.30 VSP/WC/ES&F/70445‐0/OT/2010‐11/8100000668 16‐DEC‐10
SREE SAI RAMA CONSTRUCTIONS
15‐01‐11 14‐01‐13 8.05 SENIOR MANAGER(CMS)/ES&F, ES&F
Work in Progress
2 MISCELLANEOUS CIVIL JOBS IN ROLLING MILLS ZONE/AREAS(Part‐2).
75.15 50.33 ‐33.03 VSP/WC/CED/71526‐2/OT/2011‐12/8120001028 03‐MAR‐12
S SATISHKUMAR & CO
09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
1
REPAIR OF 220KV TRANSMISSION LINES AND SWITCH YARD EQUIPMENTS FOR DNW DEPT.
45.26 48.40 6.93 VSP/WC/DNW/71353‐0/OT/2011‐12/8120000994 27‐JAN‐12
PG POWER SYSTEMS PVT LTD
30‐01‐12 29‐01‐15 ‐ DCM/DNW, DNW
Work in Progress
17 THERMAL INSULATION AND CLADDING WORKS IN VISAKHAPATNAM STEEL PLANT
48.36 48.30 ‐0.13 VSP/WC/EMD/70328‐1/OT/2010‐2011/8100000608 30‐SEP‐10
SWAMY CONSTRUCTIONS
08‐10‐10 07‐10‐11 7.23 AGM ‐ EMD ( ODPL), EMD
Extended up to 07/04/12
40 Repainting of Various structures at COCCP area
47.97 48.25 0.58 VSP/WC/STED/70562‐0/OT/2011‐12/8110000776 24‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
24‐05‐11 23‐05‐12 ‐ MANAGER, StED
Work in Progress
43 Technological upkeep of Converter shop floors and equipments in SMS.
49.59 48.00 ‐3.21 VSP/WC/SMS/70522‐0/OT/2010‐11/8110000728 23‐MAR‐11
SREE NOOKAMBIKA BUILDERS
01‐04‐11 31‐03‐12 87.92 AGM(O), SMS
Work in Progress
27
CLEANING OF STOCKYARD BEDS, YARD CONVEYORS & EQUIPMENT STREAM IN RMHP (PART II A)
47.78 47.78 0.00 VSP/WC/RMHP/71385‐0/OT/2011‐2012/8110000883 24‐OCT‐11
K GANGA RAJU 12‐11‐11 11‐11‐12 ‐ PK CHARI, AGM (O), RMHP
Work in Progress
Compiled from WCMS data given by IT departmemt Page 11 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
37 Repainting of various units of SMS area
52.61 47.20 ‐10.29 VSP/WC/STED/70429‐0/OT/2011‐12/8110000785 31‐MAY‐11
MK GOLD PAINTS PVT LTD
31‐05‐11 30‐05‐12 ‐ MANAGER, StED
Work in Progress
13 Pipe line replacement in Coal Chemicals Plant
53.97 46.80 ‐13.29 VSP/WC/CO&CCP/59339‐0/OT/2010‐11/8100000493 05‐APR‐10
SWAMY CONSTRUCTIONS
12‐04‐10 11‐04‐11 36.99 AGM(M)/CO&CCP, COCCP
Extended up to 11/04/12
7
CUTTING , BAGGING & LOADING OF SOLID PITCH IN COAL CHEMICAL PLANT
45.98 46.74 1.65 VSP/WC/CO&CCP/71213‐0/OT/2011‐12/8110000875 04‐OCT‐11
P DHANUNJAYA REDDY
01‐11‐11 31‐10‐12 ‐ AGM(O), COCCP
Work in Progress
41 Repainting of various structures in SMS including ODPL structures.
53.24 46.58 ‐12.50 VSP/WC/STED/70607‐0/OT/2011‐12/8110000777 24‐MAY‐11
AMBUJA PAINTS LTD.
24‐05‐11 23‐05‐12 ‐ MANAGER / STED, StED
Work in Progress
9
Technological repairs and structural modifications in various units of the plant under CMM
60.28 46.50 ‐22.86 VSP/WC/CMM/71209‐0/O/2011‐12/8110000826 06‐AUG‐11
MANI ENGG. WORKS
11‐08‐11 10‐08‐12 ‐ AGM(M)/CMM), CMM
Work in Progress
52 Cleaning works in TPP and its auxiliaries.
51.57 46.41 ‐10.00 VSP/WC/TPP/70485‐0/OT/2010‐11/ 07FEB‐11
A SURYANARAYANA VARMA
01‐03‐11 29‐02‐12 85.91 DGM(O)/TPP(W), TPP
Extended up to 30/06/12
53 Cleaning works in TPP and its auxiliaries.
51.57 46.41 ‐10.00 VSP/WC/TPP/70485‐0/OT/2010‐11/ 07FEB‐11
A SURYANARAYANA VARMA
01‐03‐11 29‐02‐12 4.74 DGM(O)/TPP(W), TPP
Extended up to 30/06/12
41 Technological assistance for online jam lancing of blowing lance, misc. lancing jobs, bagging for special steels and purging while tapping in SMS.
45.41 45.90 1.08 VSP/WC/SMS70515‐0/OT/2010‐11/8110000722 18‐MAR‐11
SURYA TEJ ENGG WORKS
01‐04‐11 31‐03‐12 ‐ AGM(O)‐LD, SMS
Extended up to 31/05/12
Compiled from WCMS data given by IT departmemt Page 12 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
44 Technological assistance for online jam lancing of blowing lance, misc. lancing jobs, bagging for special steels and purging while tapping in SMS.
45.41 45.90 1.08 VSP/WC/SMS70515‐0/OT/2010‐11/8110000722 18‐MAR‐11
SURYA TEJ ENGG WORKS
01‐04‐11 31‐03‐12 78.36 AGM(O)‐LD, SMS
Extended up to 31/05/12
3 MISCELLANEOUS CIVIL JOBS IN BF & ASP ZONE/AREAS(Part‐3).
68.26 45.71 ‐33.03 VSP/WC/CED/71526‐3/OT/2011‐12/8120001029 03‐MAR‐12
M SOMULU 09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
38 Repainting of various structures including conveyor deck plates & stringer posts in SMS area
54.05 45.12 ‐16.52 VSP/WC/STED/70428‐0/OT/2011‐12/8110000786 31‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
31‐05‐11 30‐05‐12 ‐ MANAGER, StED
Work in Progress
7 Repair of critical AC units inside the plant
43.90 45.00 2.50 VSP/WC/ACS/70469‐0/OT/2010‐11/8110000704 25‐FEB‐11
SIRI CONSTRUCTIONS ‐CHAITANYA NAGAR GAJUWAKA
01‐03‐11 29‐02‐12 71.67 AGM(E)/ACS, ACS
Job Completed
15 ONLINE JACKETING OF DAMAGED GAS PIPE LINE
48.22 43.90 ‐8.97 VSP/WC/EMD/70313‐0/OT/2010‐2011/8100000618 14‐OCT‐10
RAO WELDING WORKS
20‐10‐10 19‐10‐11 46.67 AGM (MECH), EMD
Extended up to 18/04/12
43 Repainting of Various structures and conveyor Galleries including Flood light towers in Sinter Plant area
44.59 43.68 ‐2.04 VSP/WC/STED/70443‐0/OT/2011‐12/8110000766 12‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
12‐05‐11 11‐05‐12 ‐ MANAGER, StED
Work in Progress
44 Repainting of Various structures and chimney shells in ESF, Stores and Traffic areas.
44.87 43.50 ‐3.04 VSP/WC/STED/70541‐0/OT/2011‐12/8110000767 12‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
12‐05‐11 11‐05‐12 ‐ SR MANAGER, StED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 13 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
45 Repainting of Various structures and conveyor Galleries including ODPL structures in Sinter Plant area
44.82 42.56 ‐5.04 VSP/WC/STED/70442‐0/OT/2011‐12/8110000765 12‐MAY‐11
MK GOLD PAINTS PVT LTD
12‐05‐11 11‐05‐12 ‐ MANAGER, StED
Work in Progress
58
REPLACEMENT OF TUBULAR AIR PRE‐HEATER IN BOILER
41.13 42.45 3.20 VSP/WC/TPP/71208‐0/OT/2011‐12/8110000834 12‐AUG‐11
V&S CONSTRUCTIONS
20‐08‐11 19‐08‐12 ‐ AGM(M), TPP
Work in Progress
46 Re‐Painting of various Structures including conveyor deck plates and Flood Light Towers in BF Zone
48.17 42.38 ‐12.02 VSP/WC/STED/70430‐0/OT/2011‐12/8110000762 12‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
12‐05‐11 11‐05‐12 ‐ MANAGER, StED
Work in Progress
55 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of TPP & ASP including PCM‐1 to 4 Area (Part‐6)
42.22 42.22 0.00 VSP/WC/StED/59375‐6/OT/2010‐11/8100000571 15‐JUL‐10
JS ENGG. WORKS 23‐07‐10 22‐07‐11 82.42 AGM, StED Job Completed
13 FETTLING OF CASTINGS PRODUCED IN FOUNDRY
40.83 42.17 3.28 VSP/WC/ES&F/59031‐0/OT/2009‐10/ 08‐SEP‐09
LAXMI & COMPANY
13‐10‐09 12‐10‐11 84.01 DCM(FOUNDRY), ES&F
Job Completed
28
Assistance for shift Mechanical Maintenance of RMHP (2011‐12)
54.99 42.00 ‐23.62 VSP/WC/RMHP/71398‐0/OT/2011‐2012/8110000900 09‐NOV‐11
SRI RAJ MOHAN ENTERPRISES
11‐11‐11 10‐11‐12 ‐ AJEET KUMAR ‐ AGM(M), RMHP
Work in Progress
61
CAPITAL REPAIR OF ESPs OF TPP BOILERS
40.61 42.00 3.42 VSP/WC/TPP/70600‐0/OT/2011‐12/ 24MAY‐11
FRIENDS ENTERPRISES
11‐06‐11 10‐06‐13 ‐ DGM(M), TPP
Work in Progress
Compiled from WCMS data given by IT departmemt Page 14 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
2
Maintenance of Air‐conditioning equipments in SMS‐II ,ASU‐IV & WMD building for SMS‐II of expansion area
40.85 41.77 2.25 VSP/WC/ACS/70640‐0/OT/2011‐12/8120000992 23‐JAN‐12
BHARATH REFREGERATION COMPANY
01‐02‐12 31‐01‐13 ‐ AGM, ACS Work in Progress
56 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of Battery No‐01 to 04 and other Aux. Units in C & CCD Area (Group‐A) (Part‐7)
41.75 41.75 0.00 VSP/WC/StED/59375‐7/OT/2010‐11/8100000572 15‐JUL‐10
MAHALAXMI CONSTRUCTIONS
23‐07‐10 22‐07‐11 74.22 AGM, StED Job Completed
1
CLEANING WORKS IN PCM,PSY & SSY AREAS OF BF
41.02 40.87 ‐0.36 VSP/WC/BF/71430‐0/OT/2011‐12/8110000932 28‐NOV‐11
CHAKRADHARA ENTERPRISES
19‐01‐12 18‐01‐13 ‐ AGM(O), BF Work in Progress
4
REPAIR OF AIR CONDITIONERS, WATER COOLERS ETC.
40.08 40.08 0.00 VSP/WC/ACS/71244‐0/OT/2011‐12/8110000843 25‐AUG‐11
BHARATHI REFRIGERATIONS
01‐09‐11 31‐08‐13 ‐ AGM / ACS, ACS
Work in Progress
4 MISCELLANEOUS CIVIL JOBS IN C&CCD ZONE/AREAS(Part‐4).
57.78 38.69 ‐33.03 VSP/WC/CED/71526‐4/OT/2011‐12/8120001030 03‐MAR‐12
BABA ENGG WORKS
09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
19
"Assistance in Preparatory Jobs for Rolling and Assembly,Repair & Revisioning of Operational Spares for MMSM"
37.94 38.44 1.32 VSP/WC/MMSM/71217‐0/OT/2011‐2012/8120000976 02‐JAN‐12
ROSHNI TECHNOLOGIES
22‐01‐12 21‐01‐13 ‐ AGM(OPRN)/MMSM, MMSM
Work in Progress
42 Re‐Painting of various Structures including conveyor deck plates and tensioning devices in BF Zone
48.00 38.40 ‐20.00 VSP/WC/STED/70441‐0/OT/2011‐12/8110000775 24‐MAY‐11
SHIVA CHEMICALS
24‐05‐11 23‐05‐12 ‐ MANAGER, StED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 15 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
50 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of Engineering Shops, Foundry, FMD, Traffic, Stores and Miscellaneous Buildings/Units (Part‐8)
38.02 38.02 0.00 VSP/WC/StED/59375‐8/OT/2010‐11/8100000573 15‐JUL‐10
TIJO CONSTRUCTIONS
23‐07‐10 22‐07‐11 88.36 AGM, StED Job Completed
19
TECHNOLOGICAL ASSISTANCE & REPAIR OF SLUDGE TREATMENT PLANT/CCCD:2011‐12
39.65 38.01 ‐4.13 VSP/WC/EnMD/71363‐0/OT/2011‐12/8110000890 29‐OCT‐11
CHANDAN ENTERPRISES
01‐11‐11 31‐10‐12 ‐ MANAGER(ENMD), EnMD
Work in Progress
47 Repainting of Various structures including Flood light towers and steel chimneys in RMHP (Coal) area
39.97 37.90 ‐5.18 VSP/WC/STED/70440‐0/OT/2011‐12/8110000764 12‐MAY‐11
MK GOLD PAINTS PVT LTD
12‐05‐11 11‐05‐12 ‐ MANAGER, StED
Work in Progress
30 Up Keep and on line mechanical repair works and cleaning of Wagon Tippler and conveyor gallaries of stacking stream in RMHP(CHP) ‐ PART‐I
28.63 37.80 32.03 VSP/WC/RMHP/OT/70337/8110000715 11‐MAR‐11
CLT ENGINEERING ENTERPRISES (Partnership)
12‐03‐11 11‐03‐12 ‐ DGM(O), RMHP
Extended up to 11/06/12
31 Up Keep and on line mechanical repair works and cleaning of Wagon Tippler and conveyor gallaries of stacking stream in RMHP(CHP) ‐ PART‐I
28.63 37.80 32.03 VSP/WC/RMHP/OT/70337/8110000715 11‐MAR‐11
CLT ENGINEERING ENTERPRISES (Partnership)
12‐03‐11 11‐03‐12 76.22 DGM(O), RMHP
Extended up to 11/06/12
Compiled from WCMS data given by IT departmemt Page 16 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
37
TECHONOLOGICAL ASSISTANCE FOR SHIFTING AND ADDING OF LADLE COVERING COMPOUND(GRANULES/POWDER/FLAKES), PETROCOKE, FERROALLOYS ETC. INTO STEEL LADLES AT ARS‐1, IRUT, ARS‐3 & LF.
29.93 37.25 24.45 VSP/WC/SMS/71337‐0/OT/2011‐12/8110000939 02‐DEC‐11
KUSHEL ENTERPRISES
10‐12‐11 09‐12‐12 ‐ AGM(O)/CCD, SMS
Work in Progress
29
Servicing of CNC Roll Turning Lathes at RS&RS
37.00 37.00 VSP/WC/RS&RS/71388‐0/N/2011‐12/8110000850 31‐AUG‐11
DEUSCHE MASCHINEN INDIA PVT. LTD
01‐10‐11 30‐09‐12 ‐ SR.MANAGER(MECH), RSRS
Work in Progress
5 MISCELLANEOUS CIVIL JOBS IN SP&TPP ZONE/AREAS.(Part‐5)
55.00 36.83 ‐33.03 VSP/WC/CED/71526‐5/OT/2011‐12/8120001031 03‐MAR‐12
VA NAIDU 09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
30
Repair and maintenance of DF cranes etc. in SMS
36.21 36.51 0.83 VSP/WC/SMS/71311‐0/OT/2011‐12/8110000956 21‐DEC‐11
BHAVANI INDUSTRIAL ENGG SERVICES
01‐03‐12 28‐02‐13 ‐ AGM(M), SMS
Work yet to be started
49 Structural repair work for buildings and technological structures including Roof Sheeting and side cladding works in various units of RMHP & CRMP Area (Part‐9)
36.32 36.32 0.00 VSP/WC/StED/59375‐9/OT/2010‐11/8100000574 15‐JUL‐10
SURYA TEJ ENGG WORKS
23‐07‐10 22‐07‐11 89.13 AGM, StED Job Completed
48 Repainting of Various structures including Flood light towers in RMHP (ore area)
40.61 35.70 ‐12.10 VSP/WC/STED/70434‐0/OT/2011‐12/8110000763 12‐MAY‐11
COLOUR INDIA PAINTS INDUSTRIES
12‐05‐11 11‐05‐12 ‐ MANAGER, StED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 17 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
3 TECHNOLOGICAL ASSISTANCE FOR TLC JAM UP‐KEEPING, BC,TC, CHANGING, BLOW PIPES AND ELBOWS CHANGING, LOADING AND UNLOADING OF BOULDERS, JAM REMOVAL FROM CAST HOUSE AND OTHER AREAS OF BF
36.04 35.50 ‐1.50 VSP/WC/BF/70526‐0/OT/2010‐ 2011/8110000745 11‐APR‐11
GOPI CONSTRUCTIONS
01‐05‐11 30‐04‐12 ‐ AGM(O), BF Work in Progress
5
CLEANING WORKS OF CSP UNITS IN CO&CCP
36.81 35.10 ‐4.65 VSP/WC/CO&CCP/71420‐0/OT/2011‐12/8110000925 26‐NOV‐11
M. RAMA RAJU & CO.
13‐01‐12 12‐01‐13 ‐ AGM(O), COCCP
Work in Progress
4 CLEANING WORKS IN PCM,PSY & SSY AREAS OF BF
33.93 34.73 2.36 VSP/WC/BF/70403‐0/OT/2010‐11/8100000679 03‐JAN‐11
CHAKRADHARA ENTERPRISES
19‐01‐11 18‐01‐12 99.30 AGM(O), BF
14
Rejuvenation of Structure & Pipelines of EMD, Capital Repair of BFGCP etc. for the year 2011‐2012
34.11 34.00 ‐0.33 VSP/WC/EMD/71203‐0/OT/2011‐12/8110000820 01‐AUG‐11
SANTHI FABRICATORS
08‐08‐11 07‐08‐12 ‐ AGM (MECH), EMD
Work in Progress
33 Collection and disposal of sludge and scale in GCM of SMS
35.37 34.00 ‐3.89 VSP/WC/SMS/71528‐0/OT/2011‐12/8120000989 19‐JAN‐12
SVL ENTERPRISES
08‐03‐12 07‐03‐13 ‐ AGM(O), SMS
Work yet to be started
34
Technological assistance by deployement of helpers and semi‐skilled manpower in CCD of SMS
32.97 33.92 2.88 VAP/WC/SMS/71274‐0/OT/2011‐12/8110000878 13‐OCT‐11
CHAKRADHARA ENTERPRISES
18‐02‐12 17‐02‐13 ‐ AGM (O) CCD, SMS
Work in Progress
66 Common Shutdown Capital Repair Jobs in SMS Pipeline Tunnel/Pump House Area.
32.75 33.50 2.28 VSP/WC/WMD/70594‐0/OT/2011‐12/8110000753 27‐APR‐11
RESHMA ENTERPRISES
02‐05‐11 01‐05‐12 ‐ AGM(T)/WMD, WMD
Work in Progress
Compiled from WCMS data given by IT departmemt Page 18 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
23 "Assistance in Preparatory Jobs for Rolling and Assembly,Repair & Revisioning of Operational Spares for MMSM"
33.10 33.39 0.87 VSP/WC/MMSM/70271‐0/OT/2010‐2011/8100000554 03‐JUL‐10
MECH‐WELD ENGG WORKS
22‐09‐10 21‐09‐11 98.25 AGM(OPRN)/MMSM, MMSM
Job Completed
6 MISCELLANEOUS CIVIL JOBS IN RMHP ZONE/AREAS.(Part‐6)
49.85 33.39 ‐33.03 VSP/WC/CED/71526‐6/OT/2011‐12/8120001032 03‐MAR‐12
VISAKHA CONSTRUCTIONS
09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
15
Cleaning works in Billet Mill & Shipping areas of LMMM.
34.70 32.70 ‐5.76 VSP/WC/LMMM/71456‐0/OT/2011‐2012/8110000955 19‐DEC‐11
SRI RAJ MOHAN ENTERPRISES
28‐12‐11 27‐12‐12 ‐ AGM(O), LMMM
Work in Progress
20
Repair/Fabrication of 'RECUPERATORS'
34.34 32.63 ‐4.99 VSP/WC/ES&F/71256‐0/O/2011‐12/8110000845 26‐AUG‐11
DYNAMIC CONSTRUCTIONS
01‐09‐11 31‐08‐12 ‐ AGM (ESF), ES&F
Work in Progress
16 THERMAL INSULATION AND CLADDING WORKS IN VISAKHAPATNAM STEEL PLANT
32.24 32.20 ‐0.13 VSP/WC/EMD/70328‐2/OT/2010‐2011/8100000609 30‐SEP‐10
BEARDSELL LIMITED
08‐10‐10 07‐10‐11 43.42 AGM ‐ EMD ( ODPL), EMD
Job Completed
21 On Line Gas Cutting of MMSM Products
34.79 32.00 ‐8.01 VSP/WC/MMSM/70523‐0/OT/2010‐2011/8110000714 10‐MAR‐11
UNITED FREIGHT CARRYING CORPORATION
08‐04‐11 07‐04‐12 ‐ AGM (O) ‐ MMSM, MMSM
Work in Progress
35
TECHNOGICAL ASSISTANCE IN TUNDISH NOZZLE FIXING, MONOBLOCK STOPPERS SETTING, ETC. IN TPBAY OF SMS
29.74 31.83 7.00 VSP/WC/SMS/71336‐0/OT/2011‐12/8120000980 05‐JAN‐12
MGM ENTERPRISES
07‐01‐12 06‐01‐13 ‐ AGM(O)/TP BAY, SMS
Work in Progress
38
Technological assistance for shroud fixing in CCD of SMS
33.03 31.77 ‐3.81 VSP/WC/SMS/71211‐0/OT/2011‐12/8110000798 01‐JUL‐11
HARSHA ENTERPRISES
01‐08‐11 31‐07‐12 ‐ AGM (O) CCD, SMS
Work in Progress
Compiled from WCMS data given by IT departmemt Page 19 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
31
Repair/replacement of hood,stack and skirt tubes of GCP in SMS.
31.61 31.40 ‐0.66 VSP/WC/SMS/71483‐0/OT/2011‐12/8110000963 26‐DEC‐11
P NARASIMHA RAO & CO
01‐01‐12 31‐12‐12 ‐ AGM(MECH), SMS
Work in Progress
54 Replacement of unserviceable damaged wooden/steel sleepers with PSC sleepers, through packing, spreading of slag etc., in various yards of Traffic department (part‐1)
30.19 31.27 3.58 VSP/WC/TRAFFIC/70512‐1/OT/2010‐11/8110000724 21‐MAR‐11
PARAMESWARI ENGG WORKS
01‐04‐11 31‐01‐12 90.49 AGM (M)‐ P.WAY& F/S, TRAFFIC
Job Completed
32 Repair and maintenance of DF cranes etc. in SMS
31.83 31.19 ‐2.00 VSP/WC/SMS/70297‐0/OT/2010‐11/8100000611 04‐OCT‐10
BHAVANI INDUSTRIAL ENGG SERVICES
01‐11‐10 31‐10‐11 85.27 AGM(M), SMS
Job Completed
12
Repair & Replacement Jobs of CCP Equipments at CO&CCP (Part‐II)
31.48 31.17 ‐1.00 VSP/WC/CO&CCP/70571‐0/OT/2011‐2012/8110000748 18‐APR‐11
JOY MA KALI CONSTRUCTION CO.
02‐09‐11 01‐09‐12 ‐ AGM(M)/CO&CCP, COCCP
Work in Progress
39
Cleaning works in CCD area of SMS
34.70 30.78 ‐11.29 VSP/WC/SMS/71201‐0/OT/2011/12/8110000802 07‐JUL‐11
HARSHA ENTERPRISES
16‐07‐11 15‐07‐12 ‐ AGM (O) CCD, SMS
Work in Progress
42 Collection and disposal of sludge and scale in GCM of SMS
30.35 30.00 ‐1.15 VSP/WC/SMS/70521‐0/OT/2010‐11/8100000707 03‐MAR‐11
MGM ENTERPRISES
08‐03‐11 07‐03‐12 98.00 AGM(O), SMS
Work in Progress
7 MISCELLANEOUS CIVIL JOBS IN CRMP,FMD & TRAFFIC ZONE/AREAS.(Part‐7)
43.48 29.12 ‐33.03 VSP/WC/CED/71526‐7/OT/2011‐12/8120001033 03‐MAR‐12
VENU CONSTRUCTIONS
09‐03‐12 08‐03‐13 ‐ MANAGER(C)‐CED, CED
Work yet to be started
Compiled from WCMS data given by IT departmemt Page 20 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
8
CLEANING JOBS IN CED AND ED(W) Bldg. AREAS(PART‐1)
29.79 27.74 ‐6.90 VSP/WC/CED/71447‐1/OT/2011‐12/8110000965 30‐DEC‐11
SRI SAI RAGHAVENDRA ENGINEERS & CONTRACTORS
15‐01‐12 14‐01‐13 ‐ MANAGER(C)‐CED, CED
Work in Progress
9
CLEANING JOBS IN RMHP AREAS(PART‐2)
28.75 26.77 ‐6.90 VSP/WC/CED/71447‐2/OT/2011‐12/8110000966 30‐DEC‐11
SENSIITIVE iNSTRUMENTATION & ELECTRICAL WORKS
15‐01‐12 14‐01‐13 ‐ MANAGER(C)‐CED, CED
Work in Progress
10
CLEANING JOBS IN C&CCD,CRG,ETL,QATD,INSTRUMENTATION & TELECOM AREAS.(PART‐4)
28.75 26.77 ‐6.90 VSP/WC/CED/71447‐4/OT/2011‐12/8110000968 30‐DEC‐11
KEERTHI CONSTRUCATIONS
15‐01‐12 14‐01‐13 ‐ MANAGER(C)‐CED, CED
Work in Progress
11 CLEANING JOBS IN BF & SP AREAS(PART‐3).
28.75 26.77 ‐6.90 VSP/WC/CED/71447‐3/OT/2011‐12/8110000967 30‐DEC‐11
RKV ENGG WORKS
15‐01‐12 14‐01‐13 10.24 MANAGER(C)‐CED, CED
Work in Progress
12 CLEANING JOBS IN SMS,CRMP,RED & SSD AREAS(PART‐5)
27.71 25.79 ‐6.90 VSP/WC/CED/71447‐5/OT/2011‐12/8110000969 30‐DEC‐11
S.R.INDUSTRIES 15‐01‐12 14‐01‐13 9.85 MANAGER(C)‐CED, CED
Work in Progress
16 CLEANING JOBS IN ESF,SPC,ERS,WCC,StED,CMM&CME AREAS(PART‐6).
27.71 25.79 ‐6.90 VSP/WC/CED/71447‐6/OT/2011‐12/970 30‐DEC‐11
SUNITHA PADMASRI ENTERPRISES
15‐01‐12 14‐01‐13 7.75 MANAGER(C)‐CED, CED
Work in Progress
2 ENVIRONMENTAL PROTECTION WORKS,BEAUTIFICATION AND HORTICULTURE DEVELOPMENT INSIDE THE PLANT OF VSP PACKAGE‐1
19.60 24.89 27.00 VSP/WC/CED/71370‐1/OT/2011‐12/8110000907 17‐NOV‐11
P DHANUNJAYA REDDY
17‐11‐11 16‐11‐12 28.72 MANAGER(C)‐CED, CED
Work in Progress
15 CLEANING JOBS IN LMMM,WRM,MMSM AND RS&RS AREAS(PART‐7)
26.66 24.82 ‐6.90 VSP/WC/CED/71447‐7/OT/2011‐12/8110000971 30‐DEC‐11
SURYA TEJ ENGG WORKS
15‐01‐12 14‐01‐13 7.78 MANAGER(C)‐CED, CED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 21 of 22
Quarterly Progress Report:4th Quarter of 2011-12(MONEYTORY LIMIT: MECH./ OPR./ELEC.- Rs.30Lakhs above, CIVIL- Rs.1.00 Cr.above/ 2 Largest Value, HORTICULTURE-Rs.2Lakhs above)
SLN Name of work and Location
Estimated Cost (`Lakhs)
Tendered Cost
(`Lakhs)
%age above/ below Est.
Agreement No. & Date / Order No.&
Date
Agency Date of start
Time of completio
n
Physical progress (%)
Engineer Incharge, Department
Remarks
3 ENVIRONMENTAL PROTECTION WORKS,BEAUTIFICATION AND HORTICULTURE DEVELOPMENT INSIDE THE PLANT OF VSP PACKAGE‐2
17.89 22.73 27.00 VSP/WC/CED/71370‐2/OT/2011‐12/8110000908 17‐NOV‐11
SURYA TEJ ENGG WORKS
17‐11‐11 16‐11‐12 22.35 MANAGER(C)‐CED, CED
Work in Progress
1 ENVIRONMENTAL PROTECTION WORKS, BEAUTIFICATION AND HORTICULTURE DEVELOPMENT INSIDE THE PLANT OF VSP PACKAGE‐3
17.83 22.65 27.00 VSP/WC/CED/71370‐3/OT/2011‐12/8110000909 17‐NOV‐11
MD JAHANGEER 17‐11‐11 16‐11‐12 34.53 MANAGER(C)‐CED, CED
Work in Progress
13 CLEANING JOBS IN TRAFFIC AREAS(PART‐8)
24.29 22.61 ‐6.90 VSP/WC/CED/71447‐8/OT/2011‐12/8110000972 30‐DEC‐11
PRAGADA PAPAYYA
15‐01‐12 14‐01‐13 9.55 MANAGER(C)‐CED, CED
Work in Progress
4 ENVIRONMENTAL PROTECTION WORKS, BEAUTIFICATION AND HORTICULTURE DEVELOPMENT INSIDE THE PLANT OF VSP PACKAGE‐4
17.76 22.55 27.00 VSP/WC/CED/71370‐4/OT/2011‐12/8110000910 17‐NOV‐11
K POTTENNA 17‐11‐11 16‐11‐12 20.35 MANAGER(C)‐CED, CED
Work in Progress
14 CLEANING JOBS IN WMD,UTILITIES,EMD,EnMD,ACVS,MMS & TS AREAS(PART‐9)
22.49 20.94 ‐6.90 VSP/WC/CED/71447‐9/OT/2011‐12/8110000972 30‐DEC‐11
G MOHAN RAO 15‐01‐12 14‐01‐13 8.12 MANAGER(C)‐CED, CED
Work in Progress
Compiled from WCMS data given by IT departmemt Page 22 of 22