  • Quarterly Review Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 2

    Table of Contents Executive Summary........................................................................................................................................................................ 3 

    Status of ESA Budget and Schedule............................................................................................................................................. 3 Budget and Schedule Review....................................................................................................................................................... 4 American Recovery and Reinvestment Act (ARRA) ..................................................................................................................... 4 Highlights .................................................................................................................................................................................... 4 Project Construction Critical Tasks (Page 1 of 2)........................................................................ Error! Bookmark not defined. Project Construction Critical Tasks (Page 2 of 2)....................................................................................................................... 7 Active Construction Contracts Summary..................................................................................................................................... 8 

    Active Projects – Manhattan........................................................................................................................................................ 10 CM009 – Manhattan Tunnels Excavation ................................................................................................................................. 10 CM019 – Manhattan Structures Part 1 ..................................................................................................................................... 12 CM008A – Madison Yard Site Clearance.................................................................................................................................. 14 CM004 – 44th St. Demolition & Construct Fan Plant Structure & 245 Park Ave. Entrance ..................................................... 16 FM216 – MNR Traction Power MODs & 13.2 kV Loop ........................................................................................................... 17 CS790 – GCT Protection Works................................................................................................................................................ 19 

    Active Projects – Queens.............................................................................................................................................................. 20 CQE28-01 – Emergency Work Civil/Structural......................................................................................................................... 20 CQE28-02 – Emergency Work – Environmental ....................................................................................................................... 21 CS810 – Queens Instrumentation .............................................................................................................................................. 22 CQ031 – Queens Bored Tunnels and Structures ....................................................................................................................... 23 CH053 – Harold Structure Part 1 and GO2 Substation ............................................................................................................ 24 CH054A – Harold Structures – Part 2A.................................................................................................................................... 26 FHA01 – Harold Stage 1 – Amtrak Direct Force Account ........................................................................................................ 27 FHA02 – Harold Early Stage 2 – Amtrak Direct F / A.............................................................................................................. 29 FHL01 – Harold Stage 1 – LIRR Direct Force Account............................................................................................................ 31 FHL02 – Harold Early Stage 2 LIRR Direct F/A ...................................................................................................................... 33 FHA62 – F Interlocking CIH..................................................................................................................................................... 35 VHA/L02 – Procure Harold Materials – Stage 2 ...................................................................................................................... 37 VH051 (Part 1) – Harold and Point CILs ................................................................................................................................. 38 VH051 (Part 2) – Harold Tower Supervisory Control System .................................................................................................. 40 

    Summary of Completed Contracts .............................................................................................................................................. 42 Summary Program Schedule ..................................................................................................................................................... 43 Contract Packaging Plan – Rev. 8.0.......................................................................................................................................... 45 

    Funding and Budget ..................................................................................................................................................................... 46 Project Budget Summary (As of Sep 30, 2009) ($ in thousands) ............................................................................................... 46 Pending Federal Funding from the American Recovery and Reinvestment Act ........................................................................ 46 Project Funding Status (As of Sep 30, 2009) ............................................................................................................................. 47 Risk Management and Project Execution Strategy – FFGA Budget.......................................................................................... 48 Force Account Construction Budget (As of Sep 30, 2009) ........................................................................................................ 49 Force Account 2009 Commitment Summary (As of Sep 30, 2009) ............................................................................................ 49 Changes from Last Quarter ....................................................................................................................................................... 49 

    Construction Safety, Security and Quality ................................................................................................................................. 50 

    Fourth Quarter ‘09 – Look Ahead .............................................................................................................................................. 50 Design ....................................................................................................................................................................................... 50 Grand Central Terminal............................................................................................................................................................ 50 Railroad Systems ....................................................................................................................................................................... 50 Operational Readiness/LIRR Start Up ...................................................................................................................................... 50 Construction .............................................................................................................................................................................. 51 Budget and Finance................................................................................................................................................................... 52 Quality....................................................................................................................................................................................... 52 Methods and Procedures ........................................................................................................................................................... 52 Safety ......................................................................................................................................................................................... 52 Site and Systems Security .......................................................................................................................................................... 52 Real Estate................................................................................................................................................................................. 53 Public Outreach ........................................................................................................................................................................ 53 

  • Quarterly Review Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 3

    Executive Summary Status of ESA Budget and Schedule

    BUDGET TOTAL (millions) Budget Awards Invoiced $ 7,328.0 $ 3,464.5 $ 1,775.3

    % Budget 47% 24% % Awards 51%

    Note: The budget and schedule reflect the September 2009 rebaseline as approved by the MTA Board

    CONSTRUCTION ONLY Budget Awards* Invoiced

    (millions) $ 5,590.5 $ 2,437.9 $ 894.6

    % Budget 44% 16%

    % Awards 37%

    *Awards reflect current contract values.

    CONTINGENCY (millions) Contingency

    FFGA Baseline $ 855 $ 424 Sept ’09 Baseline

    Current Contingency $ 424

    Fifteen contracts valued at $348.0 million COMPLETED CONTRACTS Contracts Completed This Quarter

    Procure Harold Material Stage 1 – Amtrak (VHA01) Procure Harold Material Stage 1 – LIRR (VHL01)

    Note: As a result of the budget rebaseline, General Conditions contracts are now included in Construction which adds previously completed contracts to the completed contract count. ACTIVE CONTRACTS Twenty eight contracts valued $ 2.329 billion

    Contracts Awarded This Quarter 44th St and 245 Park Ave Entrance (CM004) Queens Bored Tunnels and Structures (CQ031) Harold Structures Part 2A (CH054A) Harold Stage 2 – LIRR (FHL02)

    Note: As a result of the budget rebaseline, General Conditions contracts are now included in Construction which adds previously active contracts to the active contracts count. Value includes unexecuted options for CQ031 and CM019.

    2009 PLANNED AWARDS (Budget) Three contracts valued at $0.215 billion (includes force account)

    50th St Vent Plant (CM013) 115.83rd Party Stimulus Materials (CS099) 37.9Northern Boulevard Crossing (CQ039) 61.5DESIGN 87% complete as of 9/30/09

    4th Qtr ‘09 work plan includes: 1 contracts achieving 60% submittal 1 contracts achieving 90% submittal

    Note Above budget values for 2009 Planned Awards may change as project scopes are further developed

  • Quarterly Review Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 4

    Budget and Schedule Review In September, the MTA Board approved the 2010-14 Capital Program which included a

    revised Budget and Schedule for East Side Access. The Budget was raised to $7.328 billion and the Revenues Service date is September 2016, as presented to the MTACC Committee in July 2009.

    East Side Access – Budget & Schedule

    Note: July 2009 values exclude $463M in rolling stock costs, now budgeted elsewhere.

    7.244 7.220 7.3288.013

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    Budget Low Budget HighMTA

    Mar-08Estimate

    MTAJul-09

    Estimates

    $ Billions

    w/o risk reserve

    Com

    plet

    ion

    Dec-

    2013

    Com

    plet

    ion

    Feb-

    2015

    Com

    plet

    ion

    Mar-2

    016

    Com

    plet

    ion

    Sep-

    2016

    Com

    plet

    ion

    Jan-

    2017

    Com

    plet

    ion

    Apr-2

    017

    Com

    plet

    ion

    Apr-2

    017

    +The MTA Capital Program Review Board approved a Capital Plan Amendment

    authorizing an additional $1.5 billion in funding for the 2005-2009 Capital Program

    A series of working sessions were held between MTACC, FTA and the PMOC on developing an Enterprise Level Project Execution Plan that will be used as a tool for managing risks for both the East Side Access and the Second Avenue Subway projects

    American Recovery and Reinvestment Act (ARRA) MTA has submitted a grant to the FTA for use of $195.4 million in funds made available

    through the ARRA. See page 52 for a list of the projects identified for ARRA funds

    Highlights Excavation started in the Manhattan East Bound Main Cavern and continues in the West

    Bound Main Cavern

    Drill and blast excavation at Grand Central Terminal (GCT) started in September 2009. Reframing steel has arrived which will take the load of existing columns surrounding escalator #4 Wellway in the lower level

  • Quarterly Review Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 5

    All the Amtrak signal enclosures (case/hut) required for the F Interlocking Central Instrumentation Houses (FHA62) arrived at Amtrak’s Lancaster, PA facility

    Achieved substantial completion for contracts Madison Yard Preparation (CS780), Grand Central Terminal Instrumentation (CS800), Procure Harold Material Stage 1 Amtrak (VHA01), and Procure Harold Material Stage 1 LIRR (VHL01)

    Awarded the 44th St. Demolition & Construct Fan Plant Structure & 245 Park Ave. Entrance (CM004). The work includes construction of building structure and exterior architectural finishes at 44th St., entrance infrastructure, and fit-out mechanical, electrical, and architectural finishes at 245 Park Ave.

    Awarded the last tunneling contract Queens Bored Tunnels and Structures (CQ031) for construction of three revenue tunnels and one non-revenue tunnel beneath Sunnyside Yard and Harold Interlocking

    Awarded contract Harold Structures Part 2A (CH054A) for construction of various civil infrastructure elements at Harold Interlocking. This contract expands the existing LIRR and Amtrak Right of Way to make room for the future tunnels and track diversions

    LIRR began early work on Harold Stage 2 (FHL02) which includes cable trough, conduit and pull box installations located in Point Interlocking and the west end of Harold Interlocking

    Completed the Concept of Operations (Rev A), Asset Management Plan (Rev 0), and Operational Readiness Program Management Plan (Rev 0)

    Reviewing bids for Northern Boulevard Crossing (CQ039) and 50th St. Ventilation Facility (CM013). Awards are scheduled for the fourth quarter 2009.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 6

    Project Construction Critical Tasks (Page 1 of 2)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 7

    Project Construction Critical Tasks (Page 2 of 2)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 8

    Active Construction Contracts Summary

    Substantial Completion Cost Expenditure

    % Complete Plan

    NTP Orig Revised Forecast Plan* Actual

    Current Budget

    ($M)

    Original Contract Award ($M)

    Current Approved Contract

    ($M)

    Estimate at Completion

    ($M) Remarks

    MANHATTAN / BRONX CM009 – Manhattan Tunnels Excavations Dragados-Judlau 7/10/06 07/10 03/12 8/12 57.5/61.5% 58.7 449.3 427.9 438.0 449.3 Project team is working with contractor to mitigate delays and recover schedule.

    CM019 – Manhattan Structures 1 Dragados-Judlau

    04/01/08 03/12 03/12 8/12 14.9/15.2% 15.0 760.1 734.0 740.3 760.1 Project team is working with contractor to mitigate delays and recover schedule.

    CM008A – Madison Yard Site Clearance Gramercy Group, Inc.

    03/09/09 06/10 06/10 06/10 57.1/71.8% 47.4 40.9 39.0 39.0 40.9 Progress was limited due to two incidents this period. Contractor is now in full production and is preparing a plan to recover schedule.

    CM004 – 44th St. Demolition & Construct Fan Plan Structure & 245 Park Ave. Entrance Yonkers Contracting Company, Inc. 09/16/09 08/11 08/11 08/11 0.0% 0.0% 44.3 40.8 40.8 44.3 Contract awarded September ‘09.

    FM216 – MNR Traction Power MODs & 13.2 kV Loop TC Electric

    09/25/08 03/10 03/10 07/10 53.9/59.8% 41.1% 14.8 13.8 14.1 14.8 Slightly behind schedule. Project team is working with MNR to improve access to the requested tracks.

    CS790 – GCT Protection Works Ad Tech Enterprises 10/23/08 10/09 06/10 06/10 61.0% 41.0% 12.8 10.3 12.0 12.8 Contract Amendment #4 revised contract value and completion date. *Late/ Early Plan

    QUEENS CQE28-01 – Emergency Work Civil/Structural Railroad Construction Company , Inc.

    06/11/08 11/08 010/09 11/09 99.5% 96.7% 9.1 5.5 8.7 9.1 Contract winding down with award of CQ031.

    CQE28-02 – Emergency Work Environmental Impact Environmental 07/14/08 08/09 009/09 10/09 99.0% 66.9% 8.4 8.0 3.0 3.0 Remaining work scope transferred to CQ031.

    CS810 – Queens Instrumentation Wang Technology 05/06/09 05/09 05/10 05/10 25.8% 21.8% 7.0 2.7 2.7 7.0 Slightly behind schedule due to delay in awarding CQ031.

    CQ031 – Queens Bored Tunnels and Structures Granite-Traylor-Frontier Joint Venture 09/28/09 09/12 09/12 09/12 0.0% 0.0% 694.1 659.2 659.2 694.1 Contract awarded September 09.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 9

    Substantial Completion

    Cost Expenditure % Complete

    Plan NTP Orig Revised Forecast Plan* Actual

    Current Budget

    ($M)

    Original Contract

    Award ($M)

    Current Approved Contract

    ($M)

    Estimate at Completion

    ($M) Remarks

    HAROLD INTERLOCKING CH053 – Harold Structures Part 1 and GO2 Substation Perini Corp.

    01/02/08 05/10 05/10 05/11 66.5/87.5% 30.1 152.7 137.3 142.0 152.7 A revised schedule is being prepared by Perini as a result of electrical traction (ET) work. CH054A – Harold Structures Part 2A Perini Corp. 08/09 12/10 12/10 12/10 0% 0% 39.2 21.8 21.8 39.2 Contract awarded in August 09. FHA01 – Harold Stage 1 – Amtrak Amtrak Direct Force Account

    06/1/07 09//09 09/10 07/11 81.3% 47.9% 16.8 12.4 13.9 16.8 Behind schedule due to the issues of catenary staging plan and redesign (CH053). FHA02 – Harold Early Stage 2 – Amtrak Amtrak Direct Force Account 12/09 08/10 08/10 04/10 35.1% 69.3% 4.1 4.1 4.1 3.6 Progressing ahead of schedule.

    FHL01 – Harold Stage 1 – LIRR LIRR Direct Force Account

    6/29/07 01/10 10/10 05/11 64.4% 47.4% 20.8 28.9 20.8 20.8 Behind schedule due to the issues of catenary staging plan and redesign (CH053).

    FHL02 – Harold Early Stage 2 – LIRR LIRR Direct Force Account 08/09 04/10 04/10 04/10 10.6% 13.5% 2.4 2.4 2.4 2.4 Progressing ahead of schedule.

    FHA62 – F Interlocking CIH Amtrak Direct Force Account

    10/08 0/10 08/10 11/10 43.5/782.2% 49.0% 8.2 6.9 6.9 8.2 Schedules have been revised to reflect delivery schedule changes. No impact to follow-on contracts.

    VHA02 – Procure Harold Material Stage 2 – Amtrak Amtrak Direct Force Account 01/09 08/13 08/13 08/13 9.0% 9.0% 13.2 13.2 13.2 13.2 Progressing on schedule.

    VHL02 – Procure Harold Material Stage 2 – LIRR LIRR Direct Force Account 01/09 08/13 08/13 08/13 7.0% 7.0% 26.2 26.2 26.2 26.2 Progressing on schedule.

    VH051 (Part 1) – Harold and Point CILs Ansaldo STS USA, Inc 05/11/09 06/12 06/12 06/12 2.1/4.0% 3.5 30.8 25.8 25.8 30.8 Progressing on schedule.

    VH051 (Part 2) – Harold Tower Supervisory Control System ARINC, Inc. 02/03/09 05/12 05/12 05/12 24.0/24.0% 24.0% 7.1 5.4 5.4 7.1 Progressing on schedule.

    *Late/ Early Plan

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 10

    Active Projects – Manhattan CM009 – Manhattan Tunnels Excavation Jul, Aug, Sep ‘09 Contractor: Dragados/Judlau Construction Manager: Mike Pujdak

    LONP#:: 8 FTA Grant: NY-03-0344

    Description: The Manhattan tunnels excavation contract includes procurement of two 22 foot diameter rock tunnel boring machines, installation of temporary utilities, excavation of chambers and wyes, TBM (4 drives) excavation of approximately 25,000 linear feet of tunnels and final concrete lining of 11,600 lf of the running tunnels.

    Construction

    Concrete Plug Removal at WB GCT 5. Robbins TBM in Anticipated Bad Ground at Lower Level.

    Schedule and Cost

    TBM Mining Data Length (lf) Start Date 3rd Qtr. (lf) Cum lf % Complete

    EAST 3,108* 05/26/09 A 471 3,108 100 WEST 5747 07/06/09 A 1,300 1,300 22.6

    * Length adjusted to account for additional footage mined w/ Roadheader (~ 5 ft)

    Progress: 1. SELI TBM backed up 2,764 of 6,036 feet and will

    resume backing up after rib removal at GCT 5 East Bound

    2. Robbins TBM mining is ongoing at lower level 1,300 of 5,747 LF (22.6 % Completed)

    3. Concrete plug removal completed at GCT 5 West Wye 4. Begin excavation at GCT 1 and 2 West Wye, top

    heading by drill and blast 5. Blasting operation is ongoing at Shaft 5 which is a

    temporary access entrance (blasted 990 of 1,357 cubic yard)

    Schedule: MTA conditionally approved a recovery schedule. Current schedule is showing delay of 4.5 months. Project team is working with contractor to mitigate schedule impact and finding new opportunities to recover delays. Cost: The project is within budget.

    Contract Modifications: As of 09/30/09, twenty modifications, for a total of $10,074,942 have been executed.

    Critical Issues: Robbins TBM is currently in bad ground which was anticipated but is impacting the schedule to a greater extent than planned.

    Milestones CM009*

    Milestones Description Current

    Approved Plan Actual

    /Forecast Advertise (RFP) 01/06 01/06 (A) NTP 07/06 07/06 (A) Start Tunnel Mining 09/07 09/07 (A) Substantial Completion 03/12 8/12 (F) Close-Out 08/12 10/12 (F)

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan** Actual Plan** Actual Percent Complete 5.1/9.2 6.9 57.5/61.5 58.7 * Milestones reflects combine CM009/CM019 Rebaseline schedule * * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 CM009 F/A Support Total Budget at Award 449,351 4,041 453,393 Current Budget 449,351 4,120 453,471

    Original Award 427,954 3,924 431,878 Approved Changes 10,074 0 10,074 Current Contract Value 438,028 3,924 441,952 Invoiced Amount 257,282 1,321 258,603

    Estimate at Completion 449,351 4,120 453,471

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 11

    Coordination Required Real Estate: All properties and easements are secured for tunnel construction. MTA sent mailings to owners regarding contract NTP, zones of influence, pre-construction survey, instrumentation, and monitoring.

    Railroad Agencies: Flagging and access protection are being provided by MNR and NYCT.

    MOU: N/A

    Permits: The contractor is responsible for securing the following:

    Blasting Permit – FDNY: Permit received Water Discharge Permit – NYCDEP: Permit received

    but contractor is seeking a variance Lane Closure Permits – NYCDOT: Permit received for

    2nd Ave. and Northern Blvd

    Progress (CM009)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12

    % C

    ompl

    ete

    Early Plan % CompleteLate Plan % CompleteActual

    NOTE: 1) The Progress curve is Rebaselined to incorporate Recovery (UD9 Rev 3)

    Safety

    Project Contract BLS**(’07)

    Lost Time Accidents 2.10 3.00 2.60

    Zero Lost Time Accidents this month

    Updated safety training, and reinforced best practices

    Continued ongoing safety walk-thru of sites *The project performance statistics are based on construction hours only**Bureau of Labor Statistics/National Industry Average

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 12

    CM019 – Manhattan Structures Part 1 Jul, Aug, Sep ‘09 Contractor: Dragados-Judlau Construction Manager: Mike Pujdak

    FTA Grant: NY-03-0344

    Description: Excavation and lining of four tunnel drives, shafts, escalator well-ways, air plenums, cross-passages, and caverns mainly under Grand Central Terminal (GCT).

    Construction

    Installing Rock Bolts at WB Cavern. Collar Concrete Pour at Shaft 4.

    Schedule and Cost

    WB GCT Main Cavern Excavation Segment Cut # Total (CY) 3rd Qtr. (CY) Cum (CY) % Complete Total 95,842 2,686 2,686 2.8

    1 & 1A 9,872 2,278 2,278 23.0 2 & 2A 9,872 408 408 4.1 Top Heading

    3 11,864 0 0 0.0 Bench I 4 & 4A 11,525 0 2,204 19.1

    5 16,058 0 0 0.0 Bench II 6 16,058 0 0 0.0 Bench III 7 20,592 0 0 0.0

    EB GCT Main Cavern Excavation Segment Cut # Total (CY) 3rd Qtr. (CY) Cum (CY) % Complete Total 95,842 158 158 0.0

    1 & 1A 9,872 0 0 0.0 2 & 2A 9,872 0 0 0.0

    Top Heading

    3 11,864 0 0 0.0 Bench I 4 & 4A 11,525 158 158 1.3

    5 16,058 0 0 0.0 Bench II 6 16,058 0 0 0.0 Bench III 7 20,592 0 0 0.0 CY - Cubic Yard;

    Progress: 1. Shaft 5 – Completed mechanical excavation, drill and blast

    excavation on-going (785 CY out of 1695 CY) 2. Shaft 4 – Ongoing mechanical excavation (547 CY of 4117.2

    CY), concrete collar walls were poured 3. Shaft 3 – Ongoing mechanical excavation (337 CY out of

    3533 CY), poured concrete work slab surrounding the shaft and drilled holes for expansion grout

    4. Continued pile load test for escalator well ways. Steel fabrication is underway

    5. Began excavation with Roadheader in West Bound Cavern

    Schedule: MTA conditionally approved a recovery schedule. Current schedule is showing delay of 4.5 months. Project team is working with contractor to mitigate schedule impact and finding new opportunities to recover delays. Cost: The contract was awarded for $499 million. An option exists that if exercised will increase the value to $734 million.

    Milestones CM019*

    Milestones Description Current Approved Plan Actual/Forecast

    Advertise (RFP) 02/07 02/07 (A) NTP 04/08 04/08 (A) Substantial Completion 03/12 8/12 (F) Close-Out 08/12 10/12 (F)

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan** Actual Plan** Actual Percent Complete 4.4/4.7 4.5 14.9/15.2 15.0 * Milestones reflects combine CM009/CM019 Rebaseline schedule **Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 CM019 F/A Support* Total

    Budget at Award 756,020 28,712 784,732 Current Budget 760,125 33,449 793,574

    Original Award 734,000 13,893 747,893 Approved Changes 6,326 0 6,326

    Current Contract Value 506,313 13,893 520,206

    Invoiced Amount 111,320 5,488 116,808

    Estimate at Completion 760,125 33,449 793,574 * Includes F/A for all existing GCT contracts. Original Award value of the Force Account Support was reduced by $15.4 million. The MTA has uncommitted these funds for use on other packages.

    Contract Modifications: As of 09/30/09, six modifications, for a total of $6,326,622 have been executed.

    Critical Issues: ESA and Dragados-Judlau continue to develop strategies to ensure no impact to MNR operations from blasting.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 13

    Coordination Required Real Estate: All properties and easements are secured.

    Railroad Agencies: Flagging and access protection are being provided by MNR and NYCT.

    MOU: N/A

    Permits: The contractor is responsible for securing the following:

    Blasting Permit – FDNY: Permit received. Lane Closure Permits – NYCDOT: Permit received for

    Park Ave utility work.

    Progress (CM019)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-08Jun-08Aug-08Oct-08Dec-08Feb-09Apr-09Jun-09Aug-09Oct-09Dec-09Feb-10Apr-10Jun-10Aug-10Oct-10Dec-10Feb-11Apr-11Jun-11Aug-11Oct-11Dec-11Feb-12Apr-12Jun-12Aug-12

    % C

    ompl

    ete

    Early - Plan % Complete

    Late - Plan % Complete

    Actual

    NOTE: 1) The Progress curve is Rebaselined to incorporate Recovery (UD9 Rev 3)

    Safety Safety Statistics*

    (Cumulative Incidents per 200,000 work-hours) Project Contract BLS**(’07)

    Lost Time Accidents 2.10 0.52 2.60

    Zero Lost Time Accidents this month

    Continue ongoing safety walk-thru of sites continues

    The contractor continues to maintain appropriate ventilation and housekeeping *The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

    Cut1

    Cut2

    Cut3

    Cut

    Cut5

    Cut6

    Cut7

    Top Heading-Cut 1

    Bench I-Cut 4

    Bench II –Cut 5 & 6

    Bench III –Cut 7

    Cheeks

    Cut 1 Cut 2

    Cut3

    Cut4

    Cut 5

    Cut6

    Cut7

    EB Cavern WB Cavern

    T304T303

    T404T403

    T302T301

    T401 T402

    TBM Mined

    TBM Future

    Haircut1A

    1

    2A

    3

    4

    6

    7

    Legend

    2

    4A

    Cavern Excavation

    Haircut

    Top Heading-Cut 2

    Top Heading-Cut 3

    1A 2A

    5

    4A

    4A

    Looking South

    4A 4A

    BCY/FT(14 bcy/ft)

    Varies

    (8.6 bcy/ft)

    Varies

    (14 bcy/ft)

    (8.6 bcy/ft)

    (10.4 bcy/ft)

    (8.1 bcy/ft)

    (1.0 bcy/ft)

    (14 bcy/ft)

    18 bcy/ft)

    GCT Main Cavern Excavation

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 14

    CM008A – Madison Yard Site Clearance Jul, Aug, Sep ‘09Contractor: Gramercy Group, Inc. Construction Manager: Daniel Connor

    FTA Grant: ARRA Stimulus Fund

    Description: Dismantle rail, ballast, concrete slab, crash walls, two platforms, and miscellaneous buildings; Demolish elevators and remove accompanying mechanical/electrical equipment; Remove 45th St. cross passage walls and floor for Shaft 2; Relocate 46th St. out of well way 2 excavation footprint; Plumbing: Above and below slab pipe removals and relocations and new pipe installations, HVAC: Duct removal and installation and fan work, and all other mechanical/electrical systems. Construct new MNR Commissary

    Construction

    Installation of Ventilation System.

    Schedule and Cost Progress: 1. Continued saw cutting and removal of crashwalls

    (99% completed) 2. Continued ballast removal (98% completed) 3. Removal and relocation of utilities in Wellway 4 4. Continued asbestos abatement work 5. Completed removal of track slab concrete south of

    Gridline 2 6. Completed temporary electric lighting installation 7. Completed installation of Temporary Ventilation

    system 8. Started excavation of Track 115 demising wall

    footing

    Schedule: As a result of two safety incidents (dust and equipment fire), production work was limited this period. All work necessary for the Manhattan Structures (CM019) contract has been completed and will not impact their schedule. Interim schedule milestones for the Madison Yard Clearance (CM008A) contract are impacted but there is no impact to substantial completion.

    The contractor is in full production and is preparing a plan to recover schedule.

    Cost: Project is within budget.

    Safety: No recorded lost time incidents. Dust incident and equipment fire during the quarter impacted progress.

    Critical Issues: Construction of concrete masonry unit (CMU) demising wall may not be completed during the 4 month track outage agreement with MNR. This may extend the track outage requirement.

    Milestones CM008A

    Milestones Description Current

    Approved Plan

    Actual/ Forecast

    Advertise (IFB) 08/08 08/08 (A) NTP 03/09 03//09 (A) Complete All Work (Excluding Perimeter Wall) North of Gridline 10.5 09/09 10/09

    Complete All Work (Excluding Perimeter Wall and MNR Commissary Work) South of Gridline 10.5

    11/09 12/09

    Substantial Completion 06/10 06/10 Close-Out 08/10 08/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan* Actual Plan* Actual Percent Complete 35.4/49.1 30.0 57.1/71.8 47.4

    *Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 CM008A F/A Support* Total Budget at Award 40,932 40,932 Current Budget 40,932 40,932

    Original Award 38,983 38,983 Approved Changes Current Contract Value 38,983 38,983 Invoiced Amount 18,496 18,496

    Estimate at Completion 40,932 40,932 * Force Account costs are reported with CM019.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 15

    Coordination Issues Real Estate: N/A Railroad Agencies: MNR

    MOU: Permits: Demolition permit received. Construction permit received

    Progress (CM008A)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    Com

    plet

    e

    Early Plan

    Late Plan

    Actual

    Safety Safety Statistics*

    (Cumulative Incidents per 200,000 work-hours) Project Contract BLS**(’07)

    Lost Time Accidents 2.10 0.00 2.60

    Zero Lost Time Accidents

    Continued ongoing safety walk-thru of sites

    The contractor continues to maintain appropriate ventilation and housekeeping during demolition *The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 16

    CM004 – 44th St. Demolition & Construct Fan Plant Structure & 245 Park Ave. Entrance Jul, Aug, Sep ‘09

    Contractor: Yonkers Contracting Company, Inc. Construction Manager: Daniel Connor FTA Grant: ARRA Stimulus Funds

    Construction

    Description: 47 E. 44th Street: Remove hazardous material, demolish existing building, perform soil and rock excavation. Construct shell of new building. Frame and partially fit out new building 245 Park Avenue Entrance: Conduct environmental abatement and demolition; construct new foundations, walls and supports, Furnish and install escalator; Install architectural finishes, plumbing, fire protection, HVAC, lighting, power, fire alarm, and communication systems.

    Schedule and Cost Progress:

    1. Contract awarded September ‘09

    2. Receipt and review of submittals are ongoing

    3. Weekly meetings with the contractor are being held

    4. Coordination of all MNR related work with the railroad has commenced

    5. Contractor is acquiring all required permits for all demolition and construction work

    Schedule: Preliminary schedule has been received and is under review Cost: Budget reflects the award amount. Critical Issues: None.

    Milestones CM004

    Milestones Description Current Approved Plan Actual/

    Forecast Advertise (IFB) 12/08 12/08 (A) NTP 09/09 9/09 (A) Substantial Completion 08/11 08/11 Close-Out 12/11 12/11

    Schedule Progress 3nd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09 CM004 F/A Support Total Budget at Award 44,259 44,259

    Current Budget 44,259 44,259

    Original Award 40,765 40,765 Approved Changes Current Contract Value 40,765 40,765 Invoiced Amount

    Estimate at Completion 44,259 44,259 Note: Force Account costs are reported with CM019.

    Coordination Required Real Estate: 47 E 44th St. acquired and vacated; NYC Planning Commission approved 245 Park Ave. place change of use in Plaza area. Agreement was signed on April 14, 2009.

    Railroad Agencies: MNR and LIRR.

    Permits: Acquiring demolition, sidewalk and lane closing permits. MOU: MOU with MNR executed.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 17

    FM216 – MNR Traction Power MODs & 13.2 kV Loop Jul, Aug, Sep ‘09 Contractor: TC Electric Construction Manager: James Murray

    FTA Grant: NY-03-0344

    Description: Furnish, deliver and install automated system for motor-operated disconnect switches (MODs). Scope of work also includes reconfiguration of 13.2kV Traction Power feeder cables.

    Construction

    New Elevator Distribution Board in Switchboard Room. Core Drilling for Negative Feeder Conduit at Track 38.

    Schedule and Cost Progress 1. Continued installation of conduit runs for power and control

    feeder for transformer houses (98% completed) 2. Continued the installation of conduit runs for low voltage

    power feeders in the upper level (95% completed) 3. Continued the installation of conduit runs for negative

    feeders (75% completed) and positive feeders (25% complete) in the upper level

    4. Continued pulling cables for power feeder Q94 and Q47A (98% completed)

    5. Continued pulling cables for negatives feeder 703A & B (95% completed)

    6. Started the replacement of existing switchboards in Switchboard Room D (55% completed)

    7. The new Elevator Distribution Board was energized and cut-over for power super feeder were completed on September

    Schedule: Contract is running behind schedule due to difficulty getting track outage but no impact to follow-on contracts is anticipated. Cost: Project is within budget. Current budget includes scope transfer from Manhattan Structures MNR (FMM19)

    Contract Modifications: As of 09/30/09, three modifications, for a total of $343,930.04 have been executed.

    Safety: No recorded lost time incidents. Madison Yard shutdown during the period of 8/24/09 to 9/21/2009 was due to contract Madison Yard Site Clearance (CM008A) construction equipment fire. Impact is being evaluated.

    Critical Issues: Coordinating with MNR on outages due to operational needs and other ESA contracts needed to keep performance on schedule going forward.

    Milestones FM216

    Milestone Description Current Approved Plan Actual/

    Forecast Advertise (IFB) 05/08 05/08(A) NTP 09/08 09/08 (A) Compl. Work - 100’ of Shaft #5 01/09 10/09 Complete Switchboard “D” 03/09 11/09 Complete Work N of 46th St. 12/08 11/09 Complete Madison Yd. Work 04/09 02/10 Substantial Completion 03/10 07/10 Close-Out 06/10 10/10 Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan* Actual Plan* Actual Percent Complete 22.0/23.8 12.7 53.9/59.8 41.1

    *Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 FM216 MNR Share Total Budget at Award 14,479 4,348 18,827 Current Budget 14,765 4,348 19,113

    Original Award 13,790 4,140 17,930 Approved Changes 344 0 344 Current Contract Value 14,134 4,140 18,274 Invoiced Amount 7,347 167 7,514

    Estimate at Completion 14,751 4,348 19,099 * Force Account costs are reported with CM019.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 18

    Coordination Issues Real Estate: N/A Railroad Agencies: MNR

    MOU: Permits: N/A

    Progress (FM216)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    % C

    ompl

    ete

    Early

    Late

    Actual

    Safety Safety Statistics*

    (Cumulative Incidents per 200,000 work-hours) Project Contract BLS**(’07)

    Lost Time Accidents 2.10 8.36 2.60

    Zero Lost Time Accidents

    Continued ongoing safety walk-thru of sites

    The contractor continues to maintain appropriate ventilation and housekeeping during activity *The project performance statistics are based on construction hours only

    **Bureau of Labor Statistics/National Industry Average

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 19

    CS790 – GCT Protection Works Jul, Aug, Sep ‘09 Contractor: Ad-Tech Enterprises Construction Manager: Larry Nigro

    FTA Grant: N/A

    Description: Make all necessary concrete repairs to slabs, columns and beams and install protective mesh in GCT as needed.

    Construction

    Netting Installation at Track 34. Asbestos Abated Pipes at Platform S.

    Schedule and Cost Progress: 1. Completed 75% of netting system installation north of gridline

    15 in the Upper Level of Grand Central Terminal 2. Completed 55% of Asbestos Containing Materials (ACM) pipe

    insulation abatement in the Upper Level 3. Completed 30% of beam clamp/cable for netting system above

    platform U and adjacent tracks 41 & 42 4. Completed 40% of beam clamp/cable for netting system above

    platform T and adjacent track 39 & 40 5. Completed netting for switches 507, 511, 529, 531 and 547

    North of Gridline 15 in the Upper Level

    Schedule: Contractors schedule has been adjusted to support blasting operations. Contract completion date modified to 6-30-10

    Cost: Contract costs are within budget

    Contract Modifications: As of 9/30/09, four modifications for a total of $ 1,630,948 have been executed.

    Safety: No recorded lost time incidents.

    Critical Issues: Coordination with MNR on outages for North of Gridline 15 (Upper Level) for netting system installation in support of Manhattan Tunnels Excavation and Structures (CM009/19) blasting at shafts 4 & 5.

    Milestones CS790 Milestones Description

    Current Approved Plan

    Actual/ Forecast

    Advertise (RFP) 06/08 08/08 (A) NTP 10/08 10/08 (A) Substantial Completion 6/10 6/10 Close-Out 7/10 7/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 6.0 12.0 61.0 41.0

    Contract Costs ($000) as of 09/30/09

    CS790 F/A Support* Total

    Budget at Award 12,841 N/A 12,841 Current Budget 12,841 N/A 12,841

    Original Award 10,329 N/A 10,329 Approved Changes 1,631 N/A 1,631 Current Contract Value 11,960 N/A 11,960

    Invoiced Amount 4,912 N/A 4,912

    Estimate at Completion 12,841 N/A 12,841

    *Force Account costs are included in FMM19.

    Coordination Required Real Estate: N/A Railroad Agencies: MNR

    Permits: Issued MOU: This contract is covered by existing MNR MOU.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 20

    Active Projects – Queens CQE28-01 – Emergency Work Civil/Structural Jul, Aug, Sep ‘09 Contractor: Railroad Construction Co., Inc. Construction Manager: John Annoni

    FTA Grant: N/A

    Description: Perform work at open-cut excavation south of Northern Blvd. under the civil and structural emergency work contract. The scope of work includes, resolving site safety/security issues, completing in-progress struts, completing Amtrak deck and track work, investigating and repairing defective slurry wall panels, and completing slurry wall interface grouting (This scope was previously part of CQ028).

    Construction

    Asbestos Abatement. Coring Slurry Wall Panels.

    Schedule and Cost Progress:

    1. Completed asbestos abatement at Amtrak Buildings 1 and 5. The asbestos abatement will continue at Amtrak’s building 2.

    2. Continue investigation of open-cut slurry wall repairs. The investigation includes pump test and coring the slurry wall panels. Information is being given to the Queens Bored Tunnels and Structures (CQ031) contractor who will complete the investigation and do the repairs.

    Schedule:

    1. Delay in asbestos abatement work due to finalizing the easement agreement of Amtrak’s building 1, 2 and 5 and because additional asbestos was found in Buildings 2 and 5.

    2. Time extension to be granted for additional work from the original survey discovered during the abatement.

    Cost: Budget for additional work was funded from General Conditions.

    Contract Modifications: As of 09/30/09, thirteen modifications to the original scope for a total of $3,222,980 were executed.

    Safety: No recorded lost time incidents.

    Critical Issues: None.

    *Substantial Completion extended for additional work from the original scope.

    Milestones CQE28-01

    Milestones Description Current

    Approved Plan Actual/

    Forecast NTP 06/08 06/08(A) Safety & Security Issues 07/08 07/08 (A)

    Complete Amtrak Deck 08/08 08/08(A) Complete in-Progress Struts 09/08 09/08 (A) Substantial Completion* 10/09 11/09

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 2.6 17.3 99.5 96.7

    Contract Costs ($000) as of 09/30/09 CQE28-01 F/A Support** Total Budget at Award 6,827 N/A 6,827 Current Budget 9,087 N/A 9,087

    Original Award 5,548 N/A 5,548 Approved Changes 3,223 N/A 3,223 Current Contract Value 8,771 N/A 8,771 Invoiced Amount 8,483 N/A 8,483

    Estimate at Completion 9,087 N/A 9,087 ** F/A Access and Protection is currently being managed thru other contracts (FQA28 and FQL28)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 21

    CQE28-02 – Emergency Work – Environmental Jul, Aug, Sep ‘09 Contractor: Impact Environmental Consulting, Inc. Construction Manager: John Annoni

    FTA Grant: N/A

    Description: The scope of work includes disposing of current stockpiles on site and excavated materials by other contractors, monitoring groundwater, sampling water quality, environmental reporting and obtaining renewal of discharge permits (This scope was previously part of CQ028).

    Construction

    Collecting Water Sample for Quality. Water Elevation Reading.

    Schedule and Cost Progress:

    1. Continued water quality and elevation readings

    2. Completed amendment to Long Island Well and Discharge Permit

    Schedule:

    1. Substantial completion is delayed pending the transfer of the Long Island Well Permit monitoring to Queens Bored Tunnels and Structures (CQ031) contract

    Cost: The contract value is reduced because the remaining scope for disposal of excavated materials in this contract was transferred to Queens Bored Tunnels and Structures (CQ031).

    Contract Modifications: As of 09/30/09, five modifications to the original scope for the total of ($4,958,079) were executed.

    Safety: No recorded lost time incidents. Critical Issues: None.

    Milestones CQE28-02

    Milestones Description Current

    Approved Plan Actual/

    Forecast NTP 07/08 07/08 (A) Renewal of Discharge Permit 07/08 08/08 (A) Disposal of current stockpile 10/08 10/08 (A) Substantial Completion 10/09 10/09

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 22.3 4.3 99.0 66.9

    Contract Costs ($000) as of 09/30/09

    CQE28-02 F/A

    Support** Total Budget at Award 8,388 N/A 8,388 Current Budget 8,388 N/A 8,388

    Original Award 7,989 N/A 7,989 Approved Changes -4,958 N/A -4,958 Current Contract Value 3,031 N/A 3,031 Invoiced Amount 2,027 N/A 2,027

    Estimate at Completion 3,031 N/A 3,031 ** F/A Access and Protection is currently being managed thru other contracts (FQA28 and FQL28)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 22

    CS810 – Queens Instrumentation Jul, Aug, Sep ‘09 Contractor: Wang Technology, LLC Construction Manager: John Annoni

    FTA Grant: N/A

    Description: Procurement, installation and establishment of initial readings for structural instrumentation, geotechnical instrumentation, and data acquisition systems in Sunnyside Yard and Harold Interlocking to support Queens tunnel excavation.

    Construction

    Installing Surface Monitoring Points. Drilling Deep Bench Mark.

    Schedule and Cost Progress: 1. Installed track dynamic profile monitoring points at

    Sunnyside Yard, Loop tracks and LIRR tracks (90% installation completed)

    2. Installed two deep bench marks and two inclinometers 3. Tested prisms on LIRR tracks have been installed for

    testing interference with train operation. No issue reported.

    4. Began installation of surface and structural monitoring points

    Schedule: Contractor’s baseline schedule is accepted. The first update was submitted.

    The contractor was issued a modification to adjust interim milestone. The installation schedule is being adjusted to correspond to the Queens Bored Tunnels and Structures (CQ031) schedule. Some work activities will begin later than the original schedule. As contract Queens Bored Tunnels and Structures (CQ031) was not awarded until September 2009 items behind schedule are no longer critical.

    Cost: The Estimate at Completion is within budget.

    Contract Modifications: As of 9/30/09, one modification has been executed with no dollar value.

    Critical Issues: None.

    Milestones CS810

    Milestones Description Current

    Approved PlanActual/

    Forecast Notice to Proceed 05/09 05/09 (A) Complete prisms at 43rd St Bridge 09/09 10/09

    Instrumentation at Yard lead area 12/09 12/09

    Instrumentation near three tunnel exit 02/10 01/10 Final acceptance 05/10 05/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 24.4 20.4 25.8 21.8

    Contract Costs ($000) as of 09/30/09 CS810 F/A Support* Total Budget at Award 3,007 - 3,007 Current Budget 3,007 - 3,007

    Original Award 2,737 - 2,737 Approved Changes - - - Current Contract Value 2,737 - 2,737 Invoiced Amount 597 - 597

    Estimate at Completion 3,007 - 3,007 * Force Account Access and protection costs are reported with CH053.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 23

    CQ031 – Queens Bored Tunnels and Structures Jul, Aug, Sep ‘09 Contractor: Granite-Traylor-Frontier Joint Venture Construction Manager: Robert Magnifico

    FTA Grant: NY-03-0344/ARRA Stimulus Funds

    Construction

    Description: Construct three revenue tunnels and one non-revenue tunnel beneath Sunnyside Yard and Harold Interlocking. Construction includes the following; complete main open-cut excavation (from CQ028), procurement and assembly of two pressurized face tunnel-boring machines and ancillary equipment, tunnel excavation, installation of a one-pass pre-cast concrete tunnel liner segments, installation of ground treatment along the alignment to support tunnel construction, underpinning bridge piers and LIRR mainline structures, construction of an Amtrak access road, and construction of exit/ventilation structures (below-ground) and TBM reception pit.

    Track ATrack ATrack B/CTrack B/C

    LIRR LeadLIRR Lead

    Track DTrack D

    Honeywell St

    Honeywell St

    3939 thth StSt

    Mid

    Mid

    --Day

    Sto

    rage

    Yar

    d

    Day

    Sto

    rage

    Yar

    d

    Sunn

    ysid

    e Su

    nnys

    ide

    Yar

    dY

    ard

    TBM Launch WallTBM Launch Wall

    TBMTBMOpenOpen--Cut Cut

    ExcavationExcavation

    Site Map.

    Schedule and Cost Progress:

    1. The award letter and notice to proceed were issued to GTF JV on September 28, 2009

    2. The kick-off meeting will be held early October 2009

    3. Obtained Amtrak Project Initiative on September 19, 2009 Schedule: Contractor’s preliminary schedule was submitted for review. Cost: Contract value is $659,200,700 with one option, $58,400,000, to be executed at a future date. Final budget number will include the option once the option is awarded. Critical Issues: None

    Milestones CQ031

    Milestone Description Current Approved Plan Actual/

    Forecast Advertise N/A 03/08 (A) NTP 09/09 09/09 (A) Temporary Substation for TBM 09/10 09/10

    Complete Tunnels 03/12 03/12 Substantial Completion 09/12 09/12 Close-Out 01/13 01/13

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09 CQ031 F/A Support Total Budget at Award 756,763 22,677 779,440 Current Budget 756,763 22,677 779,440

    Original Award 659,201 0 659,201 Approved Changes 0 0 0 Current Contract Value 659,201 0 659,201 Invoiced Amount 0 0 0

    Estimate at Completion 756,763 22,677 779,440

    Coordination Required Real Estate: All Real Estate has been acquired and tenants are being relocated. Railroad Agencies: Amtrak, LIRR, NYAR.

    Permits: A FDNY blasting permit and a water discharge permit are required. Long Island well permit has been obtained (from CQ028). MOU: Amtrak Project Initiative obtained and Permit to Enter application submitted

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 24

    CH053 – Harold Structure Part 1 and GO2 Substation Jul, Aug, Sep ‘09 Contractor: Perini Corp. Construction Manager: Ray Busch

    FTA Grant: NY-03-0344

    Description: Construct various civil infrastructure elements at Harold Interlocking and expand the existing LIRR Amtrak Right of Way for the future TBM tunnels and Mainline track diversions including the design, and installation of a pre-fabricated substation.

    Construction

    Driving Micro Boring Machine for Tunnel Run 9. Installing Pre-Cast Panels at Retaining Wall 39-S1.

    Schedule and Cost Progress:

    1. Completed installation of Harold Access Bridge North and South abutment

    2. Continued drilling shaft posts for Retaining wall 39-S3 and installation of pre-cast panel at Retaining Wall 39-S1

    3. Completed microtunneling Run 9 4. Installed test piles at 43rd St bridge ML4 and successfully

    completed load test 5. Continued excavation, rebar and concrete for catenary pole

    foundations at various locations 6. Continued liner plates for Jacking pit #1 and receiving pit #2

    for microtunneling Run 6-7, west of 39th St. 7. Continued sheeting at G02 substation and jacking pit 4 8. Continued fabrication of 27 catenary structures, 31 additional

    structures are in fabrication 9. Installed temporary relocation of 26.5KVfeeder along 39 St

    bridge

    Schedule: 1. An initial delay was experienced due to late issuance of the

    Amtrak Project Initiative and Amtrak entry permit. Impact of this delay on contractor is in negotiation.

    2. An additional delay was experienced for design of catenary and signal tower foundations and structures. General Engineering Consultant (GEC) to issue 100% design drawings by end of the year.

    3. Continued developing a revised CPM schedule taking into account design related issues.

    4. Contractor hit static catenary line with no equipment or personal injuries causing a week plus shutdown. Impact to schedule is being evaluated.

    Cost: Delay to schedule, scope transfers and changes to design are impacting cost. Full impact is being evaluated. The option work of $2 million for the Thompson Ave. Microtunnel was exercised.

    ** Additional $2 million option from LIRR is not included in the Current Contract Value

    Contract Modifications: As of 9/30/09, nineteen modifications for a total of $4,750,139 have been executed.

    Critical Issues: Resolve Amtrak ET (electrical traction) and 12KV ductbank design issues so this activity can resume. Complete catenary and signal tower design packages. A re-baseline schedule is being developed so as to not impact critical path work.

    Milestones CH053

    Milestones Description Current Approved Plan Actual/

    Forecast NTP 01/08 01/08 (A) Substantial Completion 05/10 07/11 (F) Close-Out 09/10 11/11 (F)

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan* Actual Plan* Actual Percent Complete 10.3/12.3 6.1 66.5/87.5 30.1 *Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    CH053 F/A

    Support Total Budget at Award 144,144 18,212 162,356 Current Budget 152,708 20,560 173,268

    Original Award 137,280 18,212 155,492 Approved Changes 4,750 0 4,750 Current Contract Value** 142,030 18,212 160,242 Invoiced Amount 42,341 8,859 51,200

    Estimate at Completion 152,708 20,560 173,268

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 25

    Coordination Required Real Estate: All easements have been secured. Railroad Agencies: LIRR and Amtrak will provide flagging protection and perform required support work.

    Permits: Pre-award reviews and approvals have been obtained from NYCDOT and NYCDEP. Relevant permit have been obtained by the contractor. Amtrak Entry Permit approved.

    MOU: Amtrak labor clearance was obtained. LIRR and Amtrak force account agreements were signed. Project Initiative (PI) with Amtrak signed.

    Progress Curve (CH053)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jan-08 Mar-08 May-08 Jul-08 Sep-08 Nov-08 Jan-09 Mar-09 May-09 Jul-09 Sep-09 Nov-09 Jan-10 Mar-10 May-10 Jul-10 Sep-10 Nov-10 Jan-11 Mar-11

    % Co

    mplet

    e

    Early

    Late

    Actual

    Safety

    Safety Statistics* (Cumulative Incidents per 200,000 work-hours)

    Project Contract BLS**(‘07)

    Lost Time Accidents 2.10 1.42 2.60

    Contractor hit static catenary line with no equipment or personal injuries

    Perini and ESA have worked with the railroads to establish and implement a Truck Access Management Protocol to define truck routes, staging areas and minimize hazards associated with truck movements

    Train additional 3rd party safety representatives and continued to advise contractor management

    Continue ongoing safety walk-thru of sites. The contractor continues to implement improvements in training while maintaining area vigilance and housekeeping

    *The project performance statistics are based on construction hours only **Bureau of Labor Statistics/National Industry Average

    Site Map

    G02 Substa

    tion

    Retaining

    Wall (RW)

    HON-N1

    “A” Pit & A

    pproach S

    tructure

    43rd Stree

    t Bridge (W

    BY)

    43rd Stree

    t Bridge (W

    BY)

    48th Stree

    t Bridge (W

    BY)

    RW 39-N2

    RW 43-N2

    RW 43-N1

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 26

    CH054A – Harold Structures – Part 2A Jul, Aug, Sep ‘09 Contractor: Perini Corp. Construction Manager: Ray Busch

    FTA Grant: NY-03-0344/ARRA Stimulus Funds

    Description: Construct various civil infrastructure elements at Harold Interlocking and expand the existing LIRR and Amtrak Right of Way for the future TBM tunnels and Main-line track diversions including: 1) the construction of retaining walls, 2) Track D TBM Reception Pit, 3) AC Traction Power Duct Bank, 4) access road work, 5) demolition of existing Catenary Foundations, 6) procurement of 2 Signal Bridges, and 7) other utility relocations and adjustments.

    Construction

    CHO054A Overview Map at Harold Interlocking.

    Schedule and Cost Progress: 1. Awarded to Perini Corp. August 19, 2009 2. Contractor transmitted required submittals and work plans

    for reviews prior to field activities 3. Contractor will submit the Permit to Enter application to

    Amtrak in Oct ‘09 Schedule: The contractor submitted the baseline schedule which is under review. Cost: The budget includes changes to the 12KV ductbank work which has not yet been awarded. Critical Issues: Resolve Amtrak ET 12KV ductbank design issues to commence work on this activity.

    Milestones CH054A

    Milestones Description Current Approved Plan Actual/

    Forecast Advertise 12/08 12/08(A) NTP 08/09 08/09 (A) Substantial Completion 12/10 12/10 Closeout 02/11 02/11

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete TBD TBD TBD TBD

    Contract Costs ($000) as of 09/30/09 CH054A F/A Support Total Budget at Award 39,225 3,199 42,424 Current Budget 39,225 3,199 42,424

    Original Award 21,778 0 21,778 Approved Changes Current Contract Value 21,778 0 21,778 Invoiced Amount

    Estimate at Completion 39,225 3,199 42,424

    Coordination Required Real Estate: All work on railroad property or in city streets. Railroad Agencies: Amtrak and LIRR.

    Permits: NYCDOT permits needed. Water discharge permit (DEP) needed.

    MOU: Amtrak Project Initiative needed. Permit to Enter application to be submitted.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 27

    FHA01 – Harold Stage 1 – Amtrak Direct Force Account Jul, Aug, Sep ‘09 Contractor: Amtrak Construction Manager: Peter Malvese

    FTA Grant: N/A

    Description: Install one track crossover (723); Relocate catenary and signal power at several locations, perform modifications and removal of poles; Third-rail installation; Signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of the 723 crossover incorporating changes to “F” Interlocking and software and hardware modification for the Penn Station Central Control (PSCC) ; Clear debris, materials and other incidentals from the Amtrak Maintenance-of-Way Yard; electrical traction relocations in support of the CH053 civil work.

    Construction

    Connecting Spur Track at North of Harold Interlocking.

    Schedule and Cost Progress:

    1. Completed removal of Long Island connector track

    2. Provided protection for catenary and signal gang Project Initiative (P.I.) status: P.I. for C&S, O1-O2 Switch and #51 switch – Completed P.I. for 68 Spur track - Completed P.I. for Stage 1 ET Catenary– In Progress

    Schedule: The schedule variance is the result of the delayed start of Harold Structures Part 1 (CH053) and Harold Stage 1 catenary work. The catenary work drives the substantial completion date.

    Cost: The increase in budget and forecast is due to the scope transfer of the signal trough installation from Harold Stage 2 to Harold Stage 1 plus the addition of the 68 spur track and 51 switch installations.

    Critical Issues: Completion of final design for electric traction and subsequent Amtrak approval.

    Milestones FHA01

    Milestones Description Current Approved Plan Actual/

    Forecast 100% Design 11/07 11/07 (A) Commence Stage 1 06/07 06//07 (A) Cutover Switch O1/O2 08/08 10/08 (A) Compl. 68 Spur Track 11/09 11/09 Compl. Signal Power Cable 12/09 01/10 Substantial Completion 09/10 07/11

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 6.3 2.8 81.3 47.9

    Contract Costs ($000) as of 09/30/09

    Stage 1 F/A

    Support Total Budget at Award 12,100 N/A 12,100 Current Budget 16,825 N/A 16,825

    Original Award 12,448 N/A 12,448 Approved Changes 1,500 N/A 1,500 Current Contract Value 13,948 N/A 13,948 Invoiced Amount 10,209 N/A 10,209

    Estimate at Completion 16,825 N/A 16,825

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 28

    Progress Curve (FHA01)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-08 Jun-08 Aug-08 Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10

    % C

    ompl

    ete

    Plan

    Actual

    Coordination Required Real Estate: None required. Railroad Agencies: LIRR and Amtrak.

    Permits: None required.

    MOU: Amtrak Force Account Agreement has been signed.

    Site Map

    Subset J

    Amtrak Signal Tower

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 29

    FHA02 – Harold Early Stage 2 – Amtrak Direct F / A Jul, Aug, Sep ‘09 Contractor: Amtrak Construction Manager: Peter Malvese

    FTA Grant: N/A

    Description: Convert air switches 735, 737, 741, and 743 from air to electric; Install new electric switch machines; Install temporary signal case, cable pulls, tie-ins, testing and cut-over switches; Install signal troughs, pull boxes, 9-ways/conduits, and case foundations for F1 and F2 Central Instrument Houses;

    Construction

    Retaining Wall for Future Signal Case Queens Blvd. Pull Box Installation at Thomson Ave.

    Schedule and Cost Progress: 1. Continued installing pull boxes, troughs, conduits and 9-

    way ducts for F1 / F2 Central Instrument House (CIH) 2. Completed installation of case foundation for signal case

    West of Queens Blvd 3. Completed surveying trough lines and case foundations

    for new F1 Central Instrument House 4. Continued to develop Stage 2 estimate and schedule

    based on the 90% design Project Initiative (P.I.) status: P.I for Early Stage 2 Signal Work – Completed P.I for the remaining Stage 2 Work – In progress

    Schedule: Progress ahead of schedule, work started early.

    Cost: The current budget will be finalized once the PI for remaining Stage 2 is approved. Critical Issues: None

    Milestones Early FHA02

    Milestones Description Current Approved Plan Actual/

    Forecast Commence Early Stage 2 12/08 12/08 (A) Cutover Switch Machine-741 06/09 06/09 (A) Cutover Switch Machine-743 06/09 06/09 (A) Cutover Switch Machine-735 07/09 05/09 (A) Cutover Switch Machine-737 07/09 06/09 (A) Complete Early Stage 2 08/10 04/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 10.1 21.0 35.1 69.3

    Contract Costs ($000) as of 09/30/09

    Early Stage 2 F/A

    Support Total Budget at Award** 4,161 N/A 4,161 Current Budget** 4,161 N/A 4,161

    Original Award 4,161 N/A 4,161 Approved Changes - N/A - Current Contract Value 4,161 N/A 4,161 Invoiced Amount 2,056 N/A 2,056

    Estimate at Completion 4,161 N/A 4,161 **Note: Stage 2 partial budget (early work only)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 30

    Progress Curve (FHA02)

    Coordination Required Real Estate: None required. Railroad Agencies: LIRR and Amtrak.

    Permits: None required.

    MOU: Amtrak Force Account Agreement has been signed.

    Site Map

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10

    % C

    ompl

    ete Plan

    Actual

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 31

    FHL01 – Harold Stage 1 – LIRR Direct Force Account Jul, Aug, Sep ‘09 Contractor: LIRR Construction Manager: Peter Malvese

    FTA Grant: NY-03-0344

    Description: Install eight track switches into the existing signal system; remove two switches; Install signal infrastructure in preparation of Stage 2 (Harold and Point CILs); Reroute signal power cables: Install third rail for new switches & track. Pull traction power cables from G02 Substation final manholes to Harold Main Line tracks; Energize and commission the relocated G02 Substation installed by CH053. Install and relocate signal and communications cables. Cut and throw Main Line 4 and relocated Main Line 2 upon CH053 expanding the South ROW East of 43rd Street.

    Construction

    Installation of Snowmelter at 863 Switch. Repairing Communication Duct at 39th St. Bridge.

    Schedule and Cost Progress: 1. Completed 3rd rail ductbank work for 863 switches 2. Completed switch point and insulated joints for 863

    Switch 3. Completed point installation and insulated joints for

    821 switch 4. Continued testing of hut and Harold control panels and

    circuit revision 5. Continued installation of conduit, trough and pull box Schedule: The schedule variance is the result of the delay to Harold Structures Part 1 (CH053) work. LIRR has increased their signal force to two gangs to expedite the work for the planned switch installations and cutovers. Cost: Approved changes reflect the scope transfer of the M2 switch installation from Stage 1 to Stage 3. Critical Issues: Schedule being impacted by delays to Harold Structures Part 1 (CH053).

    Milestones FHL01

    Milestones Description Current

    Approved Plan

    Actual/ Forecast

    100% Design 07/07 07/07 (A) Commence Stage 1 06/07 06/07 (A) Install 823 Switch 09/09 03/10 Compl. Signal power Cable 01/10 01/10 Cutover 821 & 823 Switch 06/10 06/10 Substantial Completion 10/10 05/11

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual

    Percent Complete 9.2 7.4 64.4 47.4

    Contract Costs ($000) as of 09/30/09

    Stage 1 F/A

    Support Total Budget at Award 28,781 N/A 28,781 Current Budget 20,782 N/A 20,782

    Original Award 28,781 N/A 28,781 Approved Changes (7,999) N/A (7,999) Current Contract Value 20,782 N/A 20,782 Invoiced Amount 7,536 N/A 7,536

    Estimate at Completion 20,782 N/A 20,782

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 32

    Progress Curve (FHL01)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-08 Jun-08 Aug-08 Oct-08 Dec-08 Feb-09 Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10

    % C

    ompl

    ete

    Plan

    Actual

    Coordination Issues Real Estate: None required. Railroad Agencies: LIRR and Amtrak.

    MOU: Amtrak Force Account Agreement signed. LIRR Force Account Agreement signed.

    Permits: None required.

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 33

    FHL02 – Harold Early Stage 2 LIRR Direct F/A Jul, Aug, Sep ‘09 Contractor: LIRR Construction Manager: Peter Malvese

    FTA Grant: NY-03-0344

    Description: Advanced signal work for Stage 2 including cable trough, conduit and pull box installations, located in Point Interlocking and the West End of Harold Interlocking.

    Construction

    Trough Installation at Hunters Point.

    Schedule and Cost Progress: 1. Started installation of trough and pull boxes at H

    signal case location and Hunters Point

    2. Continued developing the Stage 2 estimate and schedule based on 90% design

    Schedule: Progress on schedule. Cost: The current budget will be revised once the MOU for remaining Stage 2 is approved. Critical Issues: None

    Milestones FHL02

    Milestones Description Current

    Approved Plan

    Actual/ Forecast

    Commence Stage 2 08/09 08/09 (A) Compl. Trough - Point CIL 10/09 10/09 Compl. Trough - H4 CIL 03/10 03/10 Complete. Early Stage 2 04/10 04/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 10.6 13.5 10.6 13.5

    Contract Costs ($000) as of 09/30/09

    Early Stage 2 F/A

    Support Total Budget at Award** 2,417 N/A 2,417 Current Budget** 2,417 N/A 2,417

    Original Award 2,417 N/A 2,417 Approved Changes Current Contract Value 2,417 N/A 2,417 Invoiced Amount 132 132

    Estimate at Completion 2,417 N/A 2,417 **Note: Stage 2 partial budget (early work only)

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 34

    Progress Curve (FHL02)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10

    % C

    ompl

    ete

    Plan

    Actual

    Coordination Issues Real Estate: None required. Railroad Agencies: LIRR and Amtrak.

    MOU: Amtrak Force Account Agreement signed. LIRR Force Account Agreement signed.

    Permits: None required.

    Site Map

    Early Stage 2 Trough Line

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 35

    FHA62 – F Interlocking CIH Jul, Aug, Sep ‘09 Contractor: Amtrak Construction Manager: Chuck Miller

    FTA Grant: N/A

    Description: Amtrak manufacture and delivery of Central Instrumentation Houses (CIHs) and cases for the F2 and F1 Interlockings.

    Construction

    Main Terminal and Supplemental Boards. Wire Distribution Between Relay Racks.

    Schedule and Cost Progress: 1. Continued wiring on the nine huts and six cases

    2. Changes to control line due to agreement between Amtrak and LIRR resolving operating issues in Harold F and Point Interlockings

    3. Modifications have begun on the cases and huts. Hut and case deliveries will continue through the 4th quarter, with completion targeted for the 1st quarter of 2010.

    4. Due to control line changes and reassessment of the level of effort required by Amtrak to complete associated revisions, delivery of the Central Instrumentation Houses (CIH) is anticipated in July and October of 2010 for F2 and F1, respectively.

    Schedule: Substantial completion and close-out schedules have been revised to reflect delivery schedule changes. No impact on critical path is anticipated. Cost: Project is within budget.

    Critical Issues: None. Note: All work will be performed by Amtrak.

    Milestones FHA62

    Milestones Description Current Approved Plan Actual/

    Forecast 100% Design 08/08 08/08 (A) NTP 09/08 09/08 (A) Delivery of F2 CIL 12/09 07/10 Delivery of F1 CIL 03/10 10/10 Substantial Completion 08/10 11/10 Close-Out 10/10 12/10

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan* Actual Plan* Actual Percent Complete 14.3/32.5 19.0 43.5/78.2 49.0

    * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 FHA62 F/A Support Total Budget at Award 8,894 8,894 Current Budget 8,178 8,178

    Original Award 6,954 6,954 Approved Changes Current Contract Value 6,954 6,954 Invoiced Amount 2,477 2,477

    Estimate at Completion 8,178 8,178 * F/A support costs are not applicable as there are no 3rd party contractors

    working as part of FHA/L01.

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 36

    Progress Curve (FHA62)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10

    % C

    ompl

    ete

    Early

    Actual

    Late

    Coordination Issues Real Estate: N/A Railroad Agencies: Amtrak

    MOU: Amtrak Force Account Agreement signed. Amtrak Project Initiative required signed. Permits: N/A

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 37

    VHA/L02 – Procure Harold Materials – Stage 2 Jul, Aug, Sep ‘09 Contractor: Various Construction Manager: Mark Denise

    FTA Grant: NY-03-0344/Stimulus Funds (Only VHL02)

    Description: Procure LIRR and Amtrak Force Account material in support of Stage 2 construction. LIRR will manage and operate the project warehouse with ESA oversight. Example of materials include: Track - switches, rail, concrete ties and ballast; Third-Rail & Power – rail, cables, boards, brackets, wire, power connectors, bus bar; Signal Equipment – switch machines, cables, signals, relays, heaters, troughs, impedance bonds; and Structures – signal bridges, retaining walls etc.; Communications – equipment, wire, cables, and poles.

    Procurement

    Force Account Materials at Warehouse Storage Area.

    Schedule and Cost

    Status: Awarded purchase orders for materials and proceeding with bids for material

    Cost: Table shows awards to date. Various purchase orders for are expected in the coming months. Half of Procure Material Stage 2 LIRR (VHL02) procurements are ready to be initiated in November 2009 in concurrence with the American Recovery and Reinvestment Act. Critical Issues: Alternate materials are being submitted by the vendors with bids which hamper an effective bid award process. Working with Amtrak to ensure timely reviews going forward.

    Amtrak – VHA02 – Budget Summary (09/30/09)

    Material Budget

    Harold Stage 2 Awarded PO Value to Date

    Percent Procurement Completed

    Estimate at Completion

    Signals 6,074,955 846,422 14% 6,074,955 Track 3,434,215 0 TBD TBD Third Rail 491,632 7170 2% 622,689 DC Traction 431,615 0 TBD TBD Communication 126,716 0 TBD TBD Catenary 553,007 0 TBD TBD Elec. Traction 2,106,948 283,200 13% 2,106,948

    Totals 13,219,087 1,136,792 9% TBD

    LIRR – VHL02 – Bid Value Summary (09/30/09)

    Material Budget

    Harold Stage 2 Bid Values to

    Date

    Percent Procurement Completed

    Estimate at Completion

    Signals 10,444,523 1,815,790 17% 10,444,523 Track 13,264,679 0 TBD TBD Third Rail / ET 1,944,087 0 TBD TBD DC Traction 0 0 TBD TBD Communication 510,111 0 TBD TBD Totals 26,163,400 1,815,790 7% TBD

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 38

    VH051 (Part 1) – Harold and Point CILs Jul, Aug, Sep ‘09 Contractor: Ansaldo STS USA, Inc Construction Manager: Chuck Miller

    FTA Grant: NY-03-0344

    Description: This is the procurement of six Harold Interlocking Central Instrument Locations (CILs) and one Point Interlocking Central Instrument Location and the purchase of a fully operational Vital Microprocessor-Based Interlocking Control System for the referenced interlockings.

    Construction

    Schedule and Cost Progress: 1. Conduct weekly technical meetings with contractor to

    assist with staging, interface and other technical issues 2. Finalize review of submittal #1 (of six submittals) and

    elements of subsequent submittals as completed by the contractor

    3. Reviewed Point Central Instrument Location and forward comments to the vendor

    4. Reviewing H3 Central Instrument Location foundation to confirm for build by construction contractor

    5. Reviewing detailed schedule update. Follow-on discussions with the vendor will take place in October 2009

    Schedule: The detailed schedule update has been submitted and is under review. Follow-on discussions with the vendor will take place in October to finalize. Cost: See contract costs. Critical Issues: None.

    Milestones VH051 (Part 1)

    Milestones Description Current Approved Plan Actual/

    Forecast Advertise 04/08 03/08 (A) NTP 05/09 05/09 (A) Compl. Point Huts & Cases 07/10 07/10 Compl. H4-H6 Huts & Cases 12/10 12/10 Compl. H1-H3 Huts & Cases 01/11 01/11 Compl. H4 CIL 04/11 04/11 Compl. H5 CIL 05/11 05/11 Compl. H6 CIL 07/11 07/11 Compl. H1, H2, H3 CILs 08/11 08/11 Substantial Completion 06/12 06/12 Final Completion 07/12 07/12

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan* Actual Plan* Actual Percent Complete 1.1/3.0 2.5 2.1/4.0 3.5

    * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09 VH051-1 F/A Support Total Budget at Award 30,891 N/A 30,891 Current Budget 30,753 N/A 30,753

    Original Award 25,840 N/A 25,840 Approved Changes N/A Current Contract Value 25,840 N/A 25,840 Invoiced Amount N/A

    Estimate at Completion 30,753 N/A 30,753

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 39

    Coordination Required Real Estate: N/A Railroad Agencies: LIRR/ Amtrak

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Progress Curve (VH051 Part 1)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10 Dec-10 Feb-11 Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12

    % C

    ompl

    ete

    Month/Year

    Early

    Late

    Actual

    Coordination Issues Real Estate: N/A

    Railroad Agencies: LIRR/ Amtrak

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 40

    VH051 (Part 2) – Harold Tower Supervisory Control System Jul, Aug, Sep ‘09 Contractor: ARINC, Inc. Construction Manager: Chuck Miller

    FTA Grant: NY-03-0344

    Description: This procurement contract requires purchase of a fully operational Supervisory Control System for control of signal at Harold and Point Interlocks.

    Construction

    Supervisory Control System (Sample). Harold Tower Supervisory Control System - Existing Tower.

    Schedule and Cost Progress: 1. Reviewing final elements of submittal #3 and elements

    of submittal #4 for final design

    2. Vendor procurement of Harold Tower hardware is underway

    3. Final General Engineering Consultant (GEC) checks of the alternate control system specifications and drawings modification to include Amtrak requirements was completed. Information was submitted to Amtrak and LIRR for review.

    4. Vendor is working with Central Instrument Location (CIL) contractor on the interface design

    Schedule: Updates to the detailed schedule from ARINC have been received and are under review. However, final assessment will be made upon the addition of Amtrak’s alternate control system. Cost: See contract costs. Critical Issues: None.

    Milestones VH051 (Part 2)

    Milestones Description Current Approved Plan Actual/

    Forecast Advertise 04/08 03/08 (A) NTP 02/09 02/09 (A) Delivery of Control Systems 03/10 03/10 Substantial Completion 08/10 08/10 Final Completion 05/12 05/12

    Schedule Progress 3rd Qtr Cumulative Cost Expenditure Plan Actual Plan Actual Percent Complete 12.0/12.0 12.0 24/24.0 24.0

    * Late/ Early Plan

    Contract Costs ($000) as of 09/30/09

    VH051-2 F/A

    Support Total Budget at Award 7,061 N/A 7,061 Current Budget 7,061 N/A 7,061

    Original Award 5,354 N/A 5,354 Approved Changes N/A Current Contract Value 5,354 N/A 5,354 Invoiced Amount 1,266 N/A 1,266

    Estimate at Completion 7,061 N/A 7,061

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 41

    Progress Curve (VH051 Part 2)

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Apr-09 Jun-09 Aug-09 Oct-09 Dec-09 Feb-10 Apr-10 Jun-10 Aug-10 Oct-10 Dec-10 Feb-11 Apr-11 Jun-11 Aug-11 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12

    % C

    ompl

    ete

    Early

    Late

    Actual

    Coordination Issues Real Estate: N/A

    Railroad Agencies: LIRR.

    Permits: N/A

    MOU: LIRR Force Account MOU signed.

    Site Map

  • Quarterly Report – 3rd Quarter ‘09

    Quarterly Report (Jul, Aug, Sep ‘09) - East Side Access (PM 3.2.62240) 42

    Summary of Completed Contracts Substantial Completion % Complete Plan

    NTP Orig Revised Forecast Plan Actual Original Budget

    ($M) Final ($M)

    QUEENS CQ025 – Demolition of Superior Reed Bldg and Preparation of Yard A Tully Environmental, Inc.

    11/5/02 7/2/03 9/15/03 9/15/03 (A) 100.0% 100.0% 5.3 5.6

    CQ026 – Open Cut Excavation at Bellmouth Kiewit Construction, Inc.

    10/7/02 9/7/03 11/25/03 11/25/03 (A) 100.0% 100.0% 16.8 18.7

    CQ027 – Arch St Yard and Shop Facility Slattery Skanska/Edwards & Kelcey

    7/9/02 6/28/04 11/30/04 12/31/04 (A) 100.0% 100.0% 77.1 77.1

    CQ028 –Queens Open-Cut Excavation Pile Foundation Construction Co., Inc.

    04/27/06 04/15/08 10/22/08 06/08 (A) 100.0% 100.0% 62.8 62.8

    FQA/L36 – Arch Street Yard Access – Amtrak/LIRR Amtrak/LIRR F/A

    11/14/04 09/01/05 06/23/06 06/23/06 (A) 100.0% 100.0% 12.1 8.3

    FQL35 – Wood Interlocking – LIRR LIRR F/A

    07/05 10/08 10/08 11/08 (A) 100.0% 100.0% 23.8 27.4

    VH055 – Switch Exchange System (Procurement) Plasser American Corp.

    12/20/02 06/27/04 05/29/05 09/30/05 (A) 100.0% 100.0% 17.7 17.2

    VHA01 – Procure Harold materials – Stage 1 Amtrak Various

    06/06/06 07/08 29/09/10 09/09 (A) 100.0% 100.0% 5.1 5.6

    VHL01 – Procure Harold materials – Stage 1 LIRR Various

    626/07 01/09 03/10 09/09 (A) 100.0% 100.0% 8.3 6.0

    MANHATTAN / BRONX CM001 – Highbridge Yard Highbridge Yard Contractors

    9/5/01 4/15/03 4/15/03 12/4/03 (A) 100.0% 100.0% 79.4 75.