quelles leçons de management de projet peut-on tirer de ces ......flamanville, taishan, olkiluoto...

35
Flamanville, Taishan, Olkiluoto et Hinkley Point : quelles leçons de management de projet peut-on tirer de ces quatre EPR ? Club Grands Projets 10 juin 2020 Thierry ROLLAND

Upload: others

Post on 30-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • Flamanville, Taishan, Olkiluoto et Hinkley Point :

    quelles leçons de management de projet

    peut-on tirer de ces quatre EPR ?

    ClubGrandsProjets10juin2020

    ThierryROLLAND

  • Club Grands Projets - 10 juin 2020 – p.2

    4 EPR™ Units Under Execution

    Olkiluoto 3 Flamanville 3

    Taishan 1&2

    The World’s First Gen III+ Fleet to be

    deployed

  • Club Grands Projets - 10 juin 2020 – p.3

    The largest contract ever signed in the civil nuclear industry : 8G€

    Taishan 1&2

  • Club Grands Projets - 10 juin 2020 – p.4

    Site location

    TAISHAN

    Hong Kong

  • Club Grands Projets - 10 juin 2020 – p.5 Project Management – January 18th 2013 - p.5

    November 2007… TAISHAN

    Daya Bay

    TAISHAN

    Daya Bay

  • Club Grands Projets - 10 juin 2020 – p.6

    $13Bn*

    The Chinese contract A long-term vision of nuclear supply

    *8Bn€ Discussions on cooperation in treatment and

    recycling

    Uranium supply until 2026

    Conversion + enrichment services

    until 2026

    Construction of 2 EPR

    Fuel assemblies for

    15 years + JV zirconium tubing

    JV Engineering

    This contract illustrates the value of AREVA’s model

  • Club Grands Projets - 10 juin 2020 – p.7

    Project overview Customer CGNPC

    CGNPC – China Guangdong Nuclear Power Holding Corp. Ltd.

    One of the 3 Chinese Nuclear Electrical Companies

    Developing a nuclear program historically in the Guangdong province (Daya Bay, Ling Ao I&II…) and now in other provinces

    Capital: CNNC (45%), Guangdong Province (45%) & China Power Investment (10%)

    Today, CGNPC wants to create its own nuclear industry to position as the major actor of the electronuclear development in China

    CGNPC involves many of its own subsidiaries into the Taishan Project, among them China Nuclear Power Engineering Company (CNPEC) and China Nuclear Power Design Company (CNPDC)

  • Club Grands Projets - 10 juin 2020 – p.8

    November 26, 2007 (Beijing) - signature of Global Agreement and its 4 contracts:

    u Nuclear Island Engineering & Procurement, incl. Full-Scope Simulator

    u Fuel Cores Supply

    u 2 related Technological Transfers

    Contractual situation

    AREVA is responsible for the Nuclear Island (NI)

    design and procurement, and is leader

    of a consortium involving 2 subsidiaries

    of CGNPC for procurement (CNPEC)

    and design (CNPDC)

  • Club Grands Projets - 10 juin 2020 – p.9

    Two EPR units, French EPR (FA3) as the reference power station

    Client: JV between CGNPC (70%) with EDF (30%)

    EP Contract (not EPC) for whole Nuclear Island

    Construction managed by the Client

    Technical Assistance for Installation & Commissioning (Client scope)

    Three party Consortium with AREVA leadership

    Other: Enriched Uranium and Fuel assemblies, Technological transfer

    8 B€

    Taishan Project integrated contract over 20 years

  • Club Grands Projets - 10 juin 2020 – p.10

    Taishan scope of work

    Primary Loop:

    - Engineering

    - Procurement

    I&C, Electrical:

    - Engineering

    - Procurement

    Bulk & HVAC:

    - Engineering

    - Procurement

    Auxiliary Equipment:

    - Engineering

    - Procurement

    Civil:

    - Basic design

    - Detailed design

    In addition, in Shenzhen, a Joint Design Team is led by IOSIS/ COB and includes CNPDC as its partner for the execution of the reinforcement shop drawings of most of the NI buildings.

    Execution Detail Design:

    - Detailed design

    Systems & Layout:

    - Basic design

    The Joint Design Organization led by ANP mobilizes CNPDC (Self Reliance Program) for the piping and electrical detail design.

    Site support:

    - Site Representative - Civil design Liaison team - Technical Support

  • Club Grands Projets - 10 juin 2020 – p.11

    Nuclear Steam Supply System

  • Club Grands Projets - 10 juin 2020 – p.12 Project Management – January 18th 2013 - p.12

    Steam Supply / Balance of NI / CI (Turbine) — 170 systems: Cooling chain, (P155b,t°330, chemical, HVAC) control – Fuel – Waste

  • Club Grands Projets - 10 juin 2020 – p.13

    Taishan 1&2 Industrial Scheme

    Engineering Manufacturing Construction Commissioning Operation Management Civil Work Erection

    Overall Design CNPDC

    TNPJVC/ CNPEC TNPJVC/ CNPEC TNPJVC/ CNPEC

    NI PLP

    ANP+CNPDC ANP+DEC+SEC

    (Localization ratio 50%) HXCC CNI23

    BNI CNPEC is in charge of the procurement which is mainly in domestic market

    CI TG ALSTOM+DEC ALSTOM+DEC (the share of Chinese party accounts for

    2/3) SBC

    Guangdong Coal-Fired

    Power Engineering Co,

    Ltd BCI CNPDC+ALSTOM +GEDI CNPEC is in charge of the procurement which is mainly in domestic market

    BOP CNPDC CNPEC is in charge of the procurement which is mainly in domestic market Domestic contractors

    Note: joint cooperation between China & France under the charge of domestic company under the charge of CGNPC

  • Club Grands Projets - 10 juin 2020 – p.14

    Consortium Organization & Scope

    Scope of supply

    112 packages 206 packages IOSIS COB (*)

    TNPJVC

    SOFINEL(*)

    (*) subcontracts

  • Club Grands Projets - 10 juin 2020 – p.15

    Great amount of resource is mobilized More than 1,500 people working for the NI EP Consortium

    1,000 AREVA and more than 500 CNPDC/CNPEC

    Data 01.12.2010

    On site, TNPJVC responsibility: 12,000 people

  • Club Grands Projets - 10 juin 2020 – p.16

    6 site locations in China

    Beijing

    CTEC

    Taishan

    Dong Fang

    Daya Bay

    Shenzhen

    ALO Procurement

    DFHM RPV+SG

    TSN site Technical assistance

    SENPEC SG

    JDO

    Design

    CORYS Beijing

  • Club Grands Projets - 10 juin 2020 – p.17

    Initial time schedule

    Self reliance starts

    (May 2008)

    LOI JV WECAN (Oct. 2008)

    FCD TSN2

    (April 2010)

    RPV intro-duction TSN1

    (Dec. 2011)

    Circuit Cleaning TSN1

    (Dec. 2012)

    End of Performance tests TSN1 (Dec. 2013)

    ContractsignatureTSN1-2

    (Nov.2007)

    Excavationceremony(Aug.2008)

    FCDTSN1

    (Oct.2009)

    Dome lifting TSN1

    (July 2011)

    Simulator ready

    (June 2012)

    Fuel loading TSN1

    (July 2013)

    2008 2009 2010 2011 2012 2013

  • Club Grands Projets - 10 juin 2020 – p.18

  • Club Grands Projets - 10 juin 2020 – p.19

    Consortium Organization & Scope for NI EP Contract

    AREVA Project Management

    CNPEC Project Management

    CNPEC

    TNPJVC

    CGNPC : 70% EDF : 30%

    NIEP Consortium Led by AREVA

    AREVA CNPDC SOFINEL

    IOSIS COB

    Nuclear Island Engineering

    AREVA

    Supply for Nuclear Island

    JDO

    JDT

    125,000 documents More than 336 contracts

    PLP + I&C

    BNI

    Full scope Simulator

    System and layout …

    Detailed design …

    Civil work design …

    Civil work detailed design …

  • Club Grands Projets - 10 juin 2020 – p.20

    BD in Europe, DD in China Lump-sum + cap for LDs (€ + RMB) LDs for Equipment; EXW / FOB 50/50 risk sharing in Consortium Completeness Performance guaranty No Consortium team 2 units / 10 months between Unit 2 localized Milestones SOC, FCD, FL, EPT Never achieved schedule

  • Club Grands Projets - 10 juin 2020 – p.21 Project Management – January 18th 2013 - p.21

    Taishan NI EP Project

  • Club Grands Projets - 10 juin 2020 – p.22

  • Club Grands Projets - 10 juin 2020 – p.23

    Contract

    Project Management Office

    Project Control

    Quality & Environment

    Procurement

    Support functions -  Secretary

    -  Liaison officer

    TAISHAN NI EP Project GmbH Deputy

    Execution Detail Design

    CW B & D Design

    Lay-out 3D Model

    Configuration Interface Methods & Tools

    Erection Commissioning

    Primary Loop Package

    Engineering Manager Primary Loop Package

    Bulk Material & HVAC (supplied by CNPEC)

    Auxiliary Equipment (supplied by CNPEC)

    I&C (partly supplied by CNPEC)

    Site Activities (Field Design / Technical Assistance

    on Construction, Erection, Commissioning)

    Schedule

    IMS

    Self Reliance

    (*)

    NSSS Equipment BNI(*)

    NSSS Systems BNI(*)

    I&C Electrical

    Process

    Safety &

    Functional Supports Legal : S. Santos Tax : G. Cintura Insurance : M. Guillon Export Finance : I; Logeais Export Control : J.M. Leudet IT : W. Ambrose Human Resources : J. Rebut

    AREVA Liaison Office

    2010 2011

  • Club Grands Projets - 10 juin 2020 – p.24

    (2) – Have a specific process to enable anticipation

    Calendar

    Objectives Actions

    Vision / Key words Visibility on critical paths & action Analysis, cross analysis Discriminating amongst criticality Collaborative work for efficiency Facilitation with method or tools Process strength versus people strength Quick access to updated information Risk Mgt, a practice for any team member Decision Making with figures and Euro Align energy sharing the vision Alignment on vision/action/method Synchronization Team Work

    The roadmap, the “GPS” built together with the Team to provide anticipation

  • Roadmap LegendTop-level NIEP

    Objectives 2010 as set-up

    by Patrick ANIERE

    Top-level NIEP Objectives

    2010 as set-up by Patrick ANIERE

    iiExpected achievement, KPI's level, maturity on

    transverse NIEP performance drivers

    Expected achievement, KPI's level, maturity on

    transverse NIEP performance drivers

    Scope Management

    TimeManagement

    Cost, MarginManagement

    "Set-up" action

    Analyze issues or problems and root causes,

    Define solution (process, meth., tools, practices, orga..)

    and Plan implementation

    "Run & Operate" action

    Implement and execute and define process, practice, tool…Monitor and control execution,

    KPI's and run, improve

    "Achieve & Close"action

    Ensure completeness of the execution of a running process,

    achievement of deliverables, termination of activities and

    resources removal

    TSN Seminar(Feb. 2010)SpecificLegend

    Action or topicsintroduced / staged in a

    "Booth" (Day 1 AM)

    Action or topicsaddressed in a WorkShopwith specific preparation

    (Feb 18-19th Seminar)

    WS WS

    Set of Action or topicsadressed in a WorkShop

    (Feb 18-19th Seminar)

    S1

    S2

    S2

    Q2

    Q1

    Q2

    Q1

    D

    S1

    Q4

    Q3

    Q2

    Q1

    N

    O

    S

    A

    J

    J

    M

    A

    M

    F

    J

    20122011

    2010

    2012Q1 Q2 Q3 Q4 S1 S2

    J F M A M J J A S O N D Q1 Q2

    2010 2011Q3 Q4 S1 S2

    1st I&C LotSite

    Delivery

    Start of I&C SW – V2

    (TXS, TXP…)

    Start ofCable trays

    install. in HL

    Functions, System

    I&C

    NSSS

    BNI

    BULK

    LAYOUT

    CW

    (Civil work)

    ELECTRIC

    AL

    PIPING

    HVAC

    .

    ENG-D

    ATA-INT

    EGRA

    TION

    + KPI'S

    VPRM

    -DATA

    -

    INTEG

    RATIO

    N

    + KPI'S

    CNPE

    C-

    SUPP

    ORT

    PROC

    ESS

    & DEL

    IVERY

    (Sele

    ction

    ,

    Orde

    r plac

    emen

    t,

    Mana

    geme

    nt,

    Expe

    diting

    )

    CONS

    TRUC

    TION

    INST

    ALLA

    TION

    I&C

    NSSS

    BNI

    SYST

    EM,

    NISU

    PPO

    RT T

    OCL

    IENT

    TNPJ

    VC

    RO

    LE &

    R

    ESPO

    NSA

    BILI

    TY

    / OR

    GA

    CO

    MPE

    TEN

    CY

    REP

    OR

    TIN

    G

    MO

    NIT

    OR

    ING

    &

    CO

    NTR

    OL

    PM

    O

    PR

    OJE

    CT

    DA

    TAIN

    TEG

    RA

    TIO

    N+

    KP

    I'S

    MANA

    GING &

    SECU

    RING

    CRITIC

    AL PA

    THS

    TO CO

    MPLET

    ION

    MANA

    GING

    SCO

    PE

    AT C

    OMPL

    ETIO

    N

    (Con

    tract,

    Con

    figur

    ation

    , Cha

    nge)

    MAN

    AGIN

    G A

    ND

    SECU

    RING

    CO

    ST &

    MAR

    GIN

    AT

    COM

    PLET

    ION

    Schedule first, with project and contract in harmony

    Schedule first, with project and contract in harmony

    33

    Completeness for TFR (Rev ITT incl., also

    spares, consumables, enabling systems, …

    Completeness for TFR (Rev ITT incl., also

    spares, consumables, enabling systems, …

    I&C, TXS V2 or V3, Electrical…

    I&C, TXS V2 or V3, Electrical…

    Priority and counter measures for D2-D2' modification or hold

    on, CWD, JDO Prod, BNI delivery…

    Priority and counter measures for D2-D2' modification or hold

    on, CWD, JDO Prod, BNI delivery…

    PEC procurement and expediting, ANP

    associated engineering

    PEC procurement and expediting, ANP

    associated engineering

    Mitigate (performance) risk for erection / commissioning

    Mitigate (performance) risk for erection / commissioning

    Fine tuning Project Orga., PE role,

    Expediting, ALO role…

    Fine tuning Project Orga., PE role,

    Expediting, ALO role…

    Quali or Quanti KPI'sor objectives to be refined

    Quali or Quanti KPI'sor objectives to be refined

    Dry Run to test capability

    and usage "Test Case"

    Dry Run to test capability

    and usage "Test Case"

    Operational Capability to

    perform trade ff construction x

    erection

    Operational Capability to

    perform trade ff construction x

    erection

    Operational Capability to

    perform trade ff construction x

    erection x commissioning

    Operational Capability to

    perform trade ff construction x

    erection x commissioning

    Freeze of Schedule

    Baseline to completion

    (2010)

    Freeze of Schedule

    Baseline to completion

    (2010)

    1 2Monitor risk of CW DD

    Drawings delays => impacts on construction

    Manage Changes on CW Detail

    Design

    Ensure convergence of decoupling values for

    CW interference

    4.1 4.2Issue Safety I&C (TXS)

    V2 Development Schedule

    Issue I&CLicensing roadmap

    22

    Implement I&C Interfaces synchronizat°management

    5Clarify Electrical Basic and Detail Design process,

    schedule & organization

    6Tune handover

    process from Piping BD to DD at JDO

    7

    Define pre-requisite for site piping prefabrication

    activities

    8.c

    Review and perform sanity check of Tech. Req in

    Tendering Package – Present conclusion to Proj. Direct°

    (Re)EnforceConfig/Change Mgt practices on TSN

    10

    Define and monitor mitigation measures on construct°/erect°

    for all late civil dependent equip'ts

    11(Re)inforce procedure for CNPEC order placement (incL

    STC/GTC)

    Fix Bottleneck issue on Supplier Tech. Document.

    14.1

    14.2

    Share vision and target on VPRM use (vs EPP) and define process to enrich

    accuracy and completeness

    Migrate data and implement new practices with VPRM as back-

    bone of source data and updates (follow-up and reporting) /

    "Endoctrination"

    16

    Define Schedule for Bulk Team expatriation to

    China

    17

    Increase commercial capabilities of PE (Change proposal,

    pricing template & tool..)

    18.1

    20.1

    18.1…

    20.2…

    Improve Project Reporting Cycle /

    and Communication

    Set-up Project Data Integration and KPI's plan

    Implement Project Data Integration and KPI'smgt along with Project Monitoring & Control

    19

    Refine PMO Contribut° and role

    – TSN Orga and support

    21

    Identify Top-Level Construction / Erection / Commissioning risks on which to develop

    mitigation tactics (based on GEN3 List of Witness Points asset)

    24Optimize Resources / schedule trade-off of JDO DD "production"

    23.1

    23.2

    23.3

    23.4

    28Refer only to

    TSN Catalog(s) in TSN model

    29Manage impacts of

    feed-back from Valves suppliers

    4.3Stabilize impacts of

    Licensing issues on I&C Architecture

    3.2Monitor effectively D2 and D2' open points

    3.1

    3.3

    Material Management using

    VPRM in place

    14.3

    Polar Crane FOB

    RB Level +19,5waterproofed

    Dome Lifting

    Start Elec.Tests

    SimulatorReady

    Schedule first will make our TaishanProject a success and the

    reference EPRTM project.

    It will trigger our Client's support as well.

    Anticipation and teamwork must pave

    the way.

    Last I&C LotSite Delivery

    SimulatorFAT

    Close any remaining Basic Design pending

    issue

    Close any remaining Basic Design pending

    issue

    44

    Achieve the complete

    specification of NI Equipment

    Achieve the complete

    specification of NI Equipment

    55

    Analyze Critical Paths for

    optimizing our Project

    Management and focusing our efforts

    Analyze Critical Paths for

    optimizing our Project

    Management and focusing our efforts

    11

    Make BNI procurement by

    CNPEC a success for ANP

    Make BNI procurement by

    CNPEC a success for ANP

    77

    Bridge our supplier responsibility

    between equipment delivery and plant

    operation

    Bridge our supplier responsibility

    between equipment delivery and plant

    operation

    88

    Adjust internal organization for a

    smooth and optimized NI Consortium operation

    Adjust internal organization for a

    smooth and optimized NI Consortium operation

    66

    Proactive and representative KPI on each EDL, SFL layout and systems, Mfg ANP, Proc

    ANP and BNI with VPRM implementat°

    Proactive and representative KPI on each EDL, SFL layout and systems, Mfg ANP, Proc

    ANP and BNI with VPRM implementat°

    The best (and the less) KPIs for right analyses and our

    (re)actiondevelopment

    The best (and the less) KPIs for right analyses and our

    (re)actiondevelopment

    22

    Refine set-up and ensure implementation of Equip. Suppliers Doc. Related to

    Erect°& Installation:- Documentum (LDRF, LPD)

    - For both ANP and PEC!

    8.b

    8.a

    8.e

    Ensure good understanding by JDO of TSN Contractual "Typical" Work Product

    - Expected as Transition (I/F) from DD (Piping, Electrical) to Erection- Matching LINGAO framework /

    template (acc. Contract)

    Start ofPiping Install.

    Start ofPiping Prefab

    32

    PCPA Tool & Process Dvlpt

    Phase 1

    PCPA Tool & Process

    Refinement Ph.2

    PCPA Tool & Process Run

    Ph. 3

    PCPA Tool & Process Run -

    Ph. 4

    (Re)inforceprocedure for

    NAR and expediting

    12

    EQUI

    PMEN

    T

    MANA

    GEME

    NT

    27

    Tune Detail Design Content

    30Set-up ramp-up of

    Licensing Deliverables issuance

    Initiate I&C Early Validation on

    Models / Simulat°

    33 Initiate Commissioning Proc. production

    34 Set-up tracking of Equipts perfo. discrepancies on Licensing / I&C

    35 Set-up TSN operational DEN procedure on SDM

    and Test Proc

    36.1Tune process to gather set of spares, consumables, special tools on NI scope

    36.2Gather set of spares, consumables, special

    tools on NI scope

    36.3Freeze a baseline of set of spares, consumables, special tools on NI scope

    13

    37Set-up / Initiate TSN operational

    procedure for Equipt Delivery

    38

    (Re)inforce Quality Assurance / Qua. Inspect°/Control

    Procedures?

    8.f

    Set-up and tune operational way to manage "Appel en Garantie"

    (lost items, broken items, re-supply…): from Client Proc down to

    Consortium, Internal, Project proc….

    39

    9.1

    (Re)EnforceContract Mgt

    practices on TSN

    40

    26.1

    Set-up TSN Project Roadmap

    (rolling)

    26.2

    Manage & Update TSN Project

    Roadmap – "alive"

    25

    Confirm "Value Chain", Com. channel and R&R from Eng to Site (and Vice-Versa) on issues,

    optimization, trade-off (EDL, PEs, Proc., JDO, Site…)

    41

    Enhance easiness to know and access to

    applicable procedures and their status

    42.1

    Implement a PEC Team for Mfg follow-

    up in Europe

    42.2

    Assess PEC expediting

    capabilities in Europe / China

    44

    Select Logistic Supplier for ANP Scope (and set-

    up implementation operational process)

    In 2009, all of you have achieved a lot. You all fed the Project with a lot of energy to stick to the NI EP Contract commitments. So far, you managed to cope with numerous difficulties. You have been continuously creative and we have reinforced our organization. To date FCD pouring is a reality. You have recovered most of our engineering delays. The PSAR and the FSAR process are well on track. All the PLP equipment are now being manufactured just like the localized equipment for unit 2. 50% of packages are now placed and the first equipment are already delivered on site.

    Today, new challenges appear for 2010 & 2011. The synchronization of our teamwork will be the key success factor. The Roadmap, “Scheduled First” oriented, will be the tool for this. In a snapshot, it will provide you with a clear and consistent view on our objectives and the key actions we are undertaking. This dynamic Roadmap will be updated continuously to monitor and to enhance our performance.

    “Schedule First" is also our Client’s primary goal: this is the reason why we have translated our big picture in a global and paced approach. We must have in mind the overall Project progress, atop the NI EP Contract. As we are closely linked to the Client through the now driving site activities, “Schedule First” will also trigger Client’s support for the global efficiency of our vision and for a common success.

    Have in mind the next major Project Milestones upcoming with the Polar Crane FOB delivery in October 2010, the start of pipes erection in November 2010 and of course with the Dome Lifting in May 2011. Furthermore, unit 2 FCD is now scheduled in April 2010: it is tomorrow!

    Today, our Client renewed its satisfaction to work with a team dedicated to the success of Taishan Project. Tomorrow, paving the way for the future EPR projects, you will be a decisive contribution to Taishan success.

    George Tsang

    Patrick Aniéré

    Denis Mosser

    Thierry Rolland

    Stefan GossensGeorge Tsang

    Patrick Aniéré

    Denis Mosser

    Thierry Rolland

    Stefan Gossens

    Taishan NIEP Roadmap

    WS

    WS

    WS

    WS WS

    WS

    Set-up and implement reporting process expediter

    towards PE's on all equipments (ANP and PEC)

    46

    45

    47.1

    47.2

    Establish and share "Target" Baseline(s)

    trajectory for NI Systems (Conf)

    Manage realization of targeted

    Baseline(s), PCR, waivers..

    48.1Set-up dedicated Integrat° & Plant

    Operat° System Team 48.2 Initiate System Tests Procedures def (for Test PF)

    9.2

    Ensure implementation of Change & Conf Mgt practices on Handover

    BD to DD

    49Check Completeness of NI "Basic Scope"

    Taishan Project commitment 2010-2011

    Taishan NIEP Process Big Picture… within the Contract

    Quali or Quanti KPI'sor objectives to be refined

    Quali or Quanti KPI'sor objectives to be refined

    Quali or QuantiKPI's or

    objectives to be

    refined

    Quali or QuantiKPI's or

    objectives to be

    refined

    Monito

    r suppl

    y

    of Anch

    ors

    Quali or QuantiKPI's or objectives

    to be refined

    Quali or QuantiKPI's or objectives

    to be refined

    Set-up PE, EDL (incl. SFL), Procurement , ALO way to operate (BNI, Proc Meeting)

    31Org. Operating Proc. Product°(also with Client)

    Set-up and implement TSN

    operational C.I.N. procedure

    Show pressure from Proj. Dir. on JEUMONT

    Define a tactic to enter in short to

    mid-term into Local Client Organization

    "on site"

    8.d

    Integrate in JDO an "Erection Eye" to ensure

    proper compliance of JDO DD to erection end-user needs and contract (similar to LINGAO Typical)

    15

    with 15

    with 8.b

    with 25

    51

    Propose a way to "facilitate" and

    "run" the cost and margin axis in the roadmap

    52

    Set-up / Refine Suppliers Claim

    management process with CNPEC

    NEW!

    NEW!

  • Club Grands Projets - 10 juin 2020 – p.26 Project Management – January 18th 2013 - p.61

    Roadmap

    Beginning 2010End 2010Beginning 2011

  • Club Grands Projets - 10 juin 2020 – p.27

    And in 2017, less than 10 years later….

  • Club Grands Projets - 10 juin 2020 – p.28

    Stratégie Globale Chinoise

    Planification systématique

    Toute l’organisation se tient et se parle

    Tout se décide à Pékin

    Recherche de la localisation à outrance

    Recherche systématique de transfert de technologie

    Difficultés pour monter des JV et durée courte en général

    Nombreuses lois repoussent l’action étrangère : HAF 604…

    Forte aspiration à devenir le N°1 mondial dans tous les domaines

  • Club Grands Projets - 10 juin 2020 – p.29

    Attention aux différences culturelles

    Eviter de faire perdre la face à un chinois devant son équipe

    Ne comprend pas la vision occidentale de gestion de projet

    En Chine on fait et on négocie après

    L’engagement des chefs est un axe majeur

    Excellents négociateurs sur les coûts et les montages contractuels

    Importance des minutes of meeting qui valent contrat

    Sont fiers de leur réalisation mais grand respect du fournisseur européen

    Importance du discours, de la synthèse en fin de réunion

    Importance des cérémonies pour tous les événements du projet, remise de cadeaux

    Une réponse mineure à une question peut bloquer un projet

  • Club Grands Projets - 10 juin 2020 – p.30

    Différences d’organisation Chine vs. Europe

    Séparent volontairement les fonctions projet / commercial / technique

    Connaissent et jouent les contrats à fond (taxes, pénalités…)

    Evitent les avenants par principe par peur de devoir rendre compte

    N’arrivent pas toujours à décider même quand le sujet est important si des coûts sont à engager

    Recherchent toujours l’engagement des patrons plus que des directeurs de projet

    En Chine le chef ne connait pas bien les détails et délègue plus qu’en Europe

    Management très directif, peu de place à la liberté d’action contrairement au système D en France

    Excellence du reporting projet

  • Club Grands Projets - 10 juin 2020 – p.31

    Raisons du succès de Taishan EPR comparé à FA3 (Flamanville) et OL3 (Olkiluoto)

    Prise en compte du Retour d’Expérience OL3 et FA3

    Meilleur schéma industriel EPCC

    Organisation Équipe de projet plus adaptée au périmètre du projet

    Prise en compte du process projet

    Profil de l’équipe de projet avec plus d’expérience de terrain

    Anticipation des risques mieux maîtrisée

    Le client très impliqué et moteur avec une grosse expérience de CPR1000

    Provision pour risques mieux calculée que sur les précédents projets

    Meilleure communication

    Spirale du succès

    Respect du client chinois

    Nombreuses interventions de la direction de projet sur des sujets à risques

    Recherche de standardisation à outrance

    Adaptation successive du projet au cours des étapes

  • Club Grands Projets - 10 juin 2020 – p.32

    Raisons de l’échec d’OL3

    Premier de série car FA3 (Flamanville) devait commencer avant OL3

    AREVA a vu trop large et aurait dû se contenter du Nuclear Island

    Client incompétent en PWR et pas motivé n’attendant que le turnkey

    AREVA s’est séparé en 2009 d’EDF, le seul sachant du Nuclear Island

    Refus de réalité planning et coûts

    Trop focalisé sur les KPI et jalons court terme pour tenir le planning

    L’éloignement de la base France n’a pas permis d’avoir les meilleurs éléments

  • Club Grands Projets - 10 juin 2020 – p.33

    Ma vision de FA3

    Attention, je n’y ai jamais été directement impliqué

    Structure projet pour moi lourde

    Cela faisait 20 ans qu’EDF n’avait pas fait de réacteurs

    De fait, direction de projet loin du terrain

    Beaucoup trop de turn-over

  • Club Grands Projets - 10 juin 2020 – p.34

    Ma vision de HPC (Hinkley Point)

    Pas de standardisation suffisante par rapport à FA3

    Structure projet encore plus lourde que FA3

    Des hiatus culturels entre Anglais et Français ?

    Beaucoup trop de « contractés » qui n’ont pas la motivation des « payroll »

    Des exigences différentes en terme d’Autorité de Sûreté qui changent la définition

    Recherche de fournisseurs différents qui vont faire prendre plus de temps et de risques au projet

    Trop de gestion contractuelle au détriment de la gestion technique

    Trop grand éloignement du site par rapport aux voies d’accès

  • Questions -réponses

    ClubGrandsProjets10juin2020

    ThierryROLLAND